Maintenance management support apparatus and maintenance management support system
The maintenance management support system enhances building maintenance by using mobile terminals and remote monitoring to facilitate efficient and high-quality maintenance across multiple buildings, addressing the challenges of information sharing and quality control.
Patent Information
- Application Number
- JP2023043366
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-17
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-03-17
AI Technical Summary
Conventional building maintenance systems face challenges in sharing information and maintaining quality across multiple buildings due to the assignment of staff to individual buildings, making it difficult to manage and perform maintenance efficiently.
A maintenance management support system and device that utilizes a mobile information terminal for dispatch, implementation, and reporting, integrated with remote monitoring, to facilitate efficient maintenance across multiple buildings by traveling equipment workers.
Enables quick dispatch, high-quality repair responses, and streamlined reporting across multiple buildings, reducing the risk of deterioration in maintenance quality and improving operational efficiency.
Smart Images

Figure 2024132554000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a maintenance management support device and a maintenance management support system. [Background technology]
[0002] In conventional building maintenance work, personnel are always present in the building to carry out the work. Various types of facilities installed in the building, such as air conditioning equipment, lighting equipment, and electrical substation equipment, are known to be the objects of maintenance work. Maintenance work includes work that is planned in advance, work to respond to problems such as equipment failures, and liaison work to respond to inquiries from building owners or tenants.
[0003] Various technologies have been proposed as systems for supporting the above-mentioned maintenance and management work (for example, see Patent Document 1). Patent Document 1 discloses a technology that prevents the labor required for equipment inspection from becoming too large. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2006-048584 A Summary of the Invention [Problem to be solved by the invention]
[0005] As mentioned above, when maintenance work is performed by personnel stationed in buildings, personnel are assigned to each building where the maintenance work is performed. Also, maintenance work is completed for each building. In this way, when personnel are assigned to each building and maintenance work is completed, it becomes difficult to share information such as maintenance.
[0006] This has led to problems such as the difficulty of having personnel perform maintenance work on multiple buildings, and the difficulty of performing maintenance work on multiple buildings while maintaining the quality of the work.
[0007] The present invention has been made to solve the above-mentioned problems, and aims to provide a maintenance management support device and a maintenance management support system that can perform maintenance management work for multiple buildings while maintaining the quality of the maintenance management work. [Means for solving the problem]
[0008] In order to achieve the above object, the present invention provides the following means. A maintenance support device according to a first aspect of the present invention is a maintenance support device that supports the maintenance of a plurality of buildings by a traveling equipment worker, and is characterized in that it is provided with a control unit that outputs information regarding a dispatch to a building to a portable information terminal carried by the traveling equipment worker based on repair response information, which is information on repair responses related to the building, an implementation unit that outputs implementation information regarding repair responses based on the repair response information to the portable information terminal, and a reporting unit that acquires result information regarding the results of the repair responses input to the portable information terminal and creates report information.
[0009] A maintenance support system according to a second aspect of the present invention is a maintenance support system having a maintenance support device that supports the maintenance of multiple buildings by a traveling equipment worker, and a portable information terminal connected to the maintenance support device so as to be able to communicate with the maintenance support device, wherein the maintenance support device is characterized in that it is provided with a control unit that outputs information regarding a dispatch to a building to the portable information terminal carried by the traveling equipment worker based on repair response information, which is information on repair responses related to the building, an implementation unit that outputs implementation information regarding repair responses based on the repair response information to the portable information terminal, and a reporting unit that acquires result information regarding the results of the repair responses input to the portable information terminal and creates report information.
[0010] According to the maintenance support device according to the first aspect of the present invention and the maintenance support system according to the second aspect, by outputting information regarding dispatch to a mobile information terminal, a patrol equipment worker can be dispatched to a building where repair work is to be performed, making it easy to perform maintenance of multiple buildings. By outputting implementation information regarding the repair work to a mobile information terminal, the patrol equipment worker can perform repair work based on the implementation information regarding the repair work, making it easy to prevent a decrease in the quality of the repair work by the patrol equipment worker. By obtaining result information and creating report information, it is easy to prevent a decrease in the quality of the report information.
[0011] In the first aspect of the present invention, it is preferable that the control unit has a reception unit that receives the repair response information, a dispatch determination unit that determines whether a response by the patrol equipment worker is necessary based on the repair response information, and an output unit that outputs information regarding the dispatch to a mobile information terminal carried by the patrol equipment worker.
[0012] In this way, by providing the control unit with a reception unit, a dispatch determination unit, and an output unit, it becomes easier to dispatch patrol equipment technicians to buildings requiring repairs, making it easier to maintain and manage multiple buildings.
[0013] In the first aspect of the present invention, it is preferable that the reception unit at least receives the repair response information via a remote monitoring device arranged at a location different from the building, and the remote monitoring device has an acquisition unit that acquires alarm information output from a building management unit that detects the occurrence of a repair response in the building, an alarm issuing unit that, upon acquiring the alarm information, issues an alarm in a manner that allows the building that output the alarm information to be identified, and an operation unit that operates the building management unit.
[0014] By receiving at least defect information via a remote monitoring device in this manner, repair response information can be received without the intervention of an operator, making it easier to maintain and manage multiple buildings.
[0015] The alarm issuing unit of the remote monitoring device can issue an alarm in a manner that enables identification of the building that output the alarm information, making it easier to maintain and manage multiple buildings. The operation unit of the remote monitoring device can operate the building management unit, making it easier to maintain and manage multiple buildings.
[0016] In the first aspect of the present invention, it is preferable that the implementation unit creates the implementation information including repair response items and information regarding the results of the repair response based on the repair response information, and outputs the implementation information to the mobile information terminal.
[0017] In this way, the implementation department creates implementation information based on the repair response information and outputs the implementation information to the mobile information terminal, making it easier for the traveling facility staff to carry out repair responses based on the implementation information regarding the repair responses, and making it easier to prevent a decline in the quality of the repair responses by the traveling facility staff.
[0018] In the first aspect of the present invention, it is preferable that the reporting unit has a completion determination unit which determines whether repair response regarding the building has been completed based on the result information, and a creation unit which creates the report information after it is determined that repair response regarding the building has been completed.
[0019] In this way, by providing the report section with a completion determination section and a creation section, it becomes easier to prevent deterioration in the quality of the report information.
[0020] In the first aspect of the present invention, it is preferable that the repair response information, the emergency response information, the implementation information, the result information, and the report information include identification information that individually identifies the target of the repair response.
[0021] In this way, by including common identification information in the repair response information, emergency response information, implementation information, result information, and report information, a series of processes in the control department, implementation department, and reporting department can be carried out more smoothly.
[0022] In the first aspect of the present invention, it is preferable that the identification information has first information based on laws and regulations related to the object, second information based on the type of the object, third information based on the type of the object, and fourth information based on the model of the object.
[0023] In this way, the identification information has the first information, the second information, the third information, and the fourth information, which makes it easier for the control unit, the implementation unit, and the reporting unit to perform their respective processes. [Brief description of the drawings]
[0024] [Figure 1] 1 is a diagram illustrating a configuration of a maintenance management support system according to an embodiment of the present invention. [Diagram 2] 2 is a block diagram illustrating the configuration of the maintenance support device of FIG. 1. [Diagram 3] 2 is a block diagram illustrating the configuration of the remote monitoring device of FIG. 1. [Figure 4] 11 is a flowchart illustrating a calculation process when performing a dispatch response. [Diagram 5] 13 is a flowchart illustrating a calculation process of reception. [Figure 6] 13 is a flowchart illustrating a calculation process for dispatching a vehicle. [Figure 7] 11 is a flowchart illustrating a calculation process for responding to a dispatch. [Figure 8] 13 is a flowchart illustrating a calculation process of a post-correspondence process. [Figure 9] 11 is a flowchart illustrating a calculation process when performing a routine task. [Figure 10] 11 is a flowchart illustrating a process for creating a material. [Figure 11] FIG. 2 is a schematic diagram illustrating remote monitoring by a remote monitoring device. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0025] A maintenance management support device 10 and a maintenance management support system 1 according to an embodiment of the present invention will be described with reference to Fig. 1 to Fig. 11. The maintenance management support device 10 and the maintenance management support system 1 according to the present embodiment are a device and a system that support building maintenance work, and are a device and a system that support maintenance work performed by facility personnel who patrol multiple buildings. Hereinafter, a facility personnel who patrols multiple buildings will also be referred to as a patrol facility personnel.
[0026] As shown in Fig. 1, the maintenance management support system 1 is provided with a maintenance management support device 10 that supports maintenance management work, one or more remote monitoring devices 40 that monitor the condition of buildings that are the subject of maintenance management, and one or more mobile information terminals 50 carried by patrol personnel. Fig. 1 shows an example in which one maintenance management support device 10, one remote monitoring device 40, and three mobile information terminals 50 are provided in the maintenance management support system 1.
[0027] The number of maintenance management support devices 10 provided may be one, or multiple maintenance management support devices 10 may be provided and the multiple maintenance management support devices 10 may work together to perform the calculation processing described below.
[0028] The number of remote monitoring devices 40 provided may be changed according to the number of buildings to be managed and may be more than 1. The number of mobile information terminals 50 provided may be changed according to the number of patrol personnel or the number of groups, and may be less than 3 or more than 3.
[0029] In addition, while FIG. 1 shows an example in which the maintenance management support device 10 and the remote monitoring device 40 in the maintenance management support system 1 are separate devices, the maintenance management support device 10 and the remote monitoring device 40 may also be an integrated device.
[0030] The maintenance support device 10 is, for example, a device disposed in a support center that supports the work of a patrol facility worker. The support center may be provided in a building different from the multiple buildings that are the targets of maintenance, or may be provided in the building that is the target of maintenance.
[0031] The maintenance management support device 10 is communicably connected to the remote monitoring device 40 and the mobile information terminal 50 via a known wired or wireless information communication network. The maintenance management support device 10 is an information processing device such as a server or a personal computer having a CPU (Central Processing Unit), ROM, RAM, an input / output interface, etc.
[0032] The program stored in the storage device such as the ROM described above causes the CPU, ROM, RAM, and input / output interface to cooperate with each other to function as a control unit 11, an implementation unit 21, and a reporting unit 31, as shown in FIG. 2.
[0033] The control unit 11 has a configuration for creating information related to emergency dispatch, and a configuration for outputting the created information related to emergency dispatch to the mobile information terminal 50. The information related to emergency dispatch includes information instructing a patrol facility staff member to dispatch to a building where a malfunction has occurred, information instructing a patrol facility staff member to dispatch to a building where routine work is performed, information specifying the building to dispatch to, information indicating the content of the malfunction, information indicating the content of the routine work, etc. The information related to emergency dispatch is information created based on repair response information.
[0034] The repair response information is information on repair responses related to buildings, and the targets of the repair responses include not only buildings but also facilities related to the buildings. The repair responses include at least one of repair responses for defects and work in routine tasks. The repair response information includes at least one of defect information, which is information on defects related to buildings, and routine task information, which is information on the work content in routine tasks.
[0035] The control unit 11 includes a receiving unit 12, a rush determination unit 13, and an output unit . The reception unit 12 has a configuration for receiving repair response information. The defect information included in the repair response information may be received by the reception unit 12 via the remote monitoring device 40, or may be received by the reception unit 12 upon notification from the owner of the building, a management company that manages the building, or a tenant residing in the building. The routine task information included in the repair response information may be received by the reception unit 12 from a storage unit (not shown) in which routine regular task information of the maintenance management support device 10 is stored, or may be received by the reception unit 12 from an information processing terminal other than the maintenance management support device 10.
[0036] The dispatch determination unit 13 has a configuration for determining whether or not a mobile facility staff member is required to respond on the basis of the defect information included in the repair response information. The contents of the calculation process for determining whether or not a mobile facility staff member is required to respond on the basis of the defect information included in the repair response information will be described later.
[0037] The output unit 14 has a configuration for outputting information relating to the dispatch to a mobile information terminal 50 carried by the patrol facility staff member.
[0038] The implementation unit 21 has a configuration for creating implementation information related to repair responses, and a configuration for outputting the created implementation information to the mobile information terminal 50. The implementation information related to repair responses includes at least one of implementation information related to malfunction responses and implementation information related to routine work responses. The implementation information includes items of work to respond to malfunctions, and information related to malfunction resolution, which is the content of the work to resolve the malfunctions. The implementation information also includes items of work corresponding to routine work.
[0039] The reporting unit 31 has a configuration for creating report information in a creation unit 33 described later, and a configuration for reporting the created report information. Examples of destinations to which the report information is reported include the owner of the building, a company that manages the building, tenants who reside in the building, and administrative personnel.
[0040] The reporting unit 31 includes a completion determination unit 32 and a creation unit 33 . The completion determination unit 32 has a configuration for determining whether the building repair response is completed. The calculation process for making the determination may use result information and implementation information regarding the results of the repair response input to the mobile information terminal 50. The building repair response includes at least one of response to defects related to the building and response to routine work related to the building.
[0041] The creation unit 33 has a configuration for creating the above-mentioned report information. The report information is created after it is determined that the building repair work is completed. The report information is created based on the result information input to the mobile information terminal 50.
[0042] The above-mentioned malfunction information, dispatch information, implementation information, result information, and report information all contain identification information that individually identifies the object in which the malfunction occurred. The object includes equipment installed in a building. The identification information is information that combines the first information, second information, third information, and fourth information described below.
[0043] The first information is information based on laws and regulations related to the target, and is also referred to as a law name code. The first information is, for example, information that identifies the name of a law and regulations related to the target. The second information is information based on the type of target, and is also referred to as an equipment code. The second information is, for example, information that identifies the type of target. The combination of the first information and the second information is also referred to as an equipment code.
[0044] The third information is information based on the type of the object and is also referred to as a type code. The third information is, for example, information that identifies the type of the object. The fourth information is information based on the object model and is also referred to as a model code. The fourth information is, for example, information that identifies the model. The combination of the third information and the fourth information is also referred to as an attribute code.
[0045] The identification information may be expressed as an eight-digit number. In this case, the first information may be expressed as a two-digit number, the second information may be expressed as a two-digit number, the third information may be expressed as a two-digit number, and the fourth information may be expressed as a two-digit number.
[0046] The number of digits expressing the identification information may be eight digits, or may be greater than eight digits, or may be less than eight digits. The number of digits expressing the first information, the second information, the third information, and the fourth information may be two digits, or may be greater than two digits, or may be less than two digits. The first information, the second information, the third information, and the fourth information may all be expressed with the same number of digits, or at least some of them may be expressed with different numbers of digits. The identification information, the first information, the second information, the third information, and the fourth information may be expressed with numbers, or may be expressed with alphabets or symbols other than numbers.
[0047] For example, when the target is an emergency power supply facility, in other words, a storage battery facility, the identification information can be expressed as "17100300." This identification information is information in which the first information "17," the second information "10," the third information "03," and the fourth information "00" are combined.
[0048] The remote monitoring device 40 is, for example, a device that is arranged in the same support center as the maintenance management support device 10. Note that the remote monitoring device 40 may be arranged in a place different from the maintenance management support device 10.
[0049] The remote monitoring device 40 is communicably connected to the maintenance management support device 10 via a known wired or wireless information communication network. It is also communicably connected to a building management unit 60 (described later) via a known wired or wireless information communication network. The remote monitoring device 40 is an information processing device such as a server or personal computer having a CPU, ROM, RAM, input / output interface, etc.
[0050] The program stored in the storage device such as the ROM described above causes the CPU, ROM, RAM, and input / output interface to function in cooperation with each other as an acquisition unit 41, an alarm unit 42, and an operation unit 43, as shown in FIG. 3.
[0051] The acquisition unit 41 has a configuration for acquiring alarm information output from the building management unit 60. The building management unit 60 has a configuration for detecting the occurrence of a malfunction in a building. An example of the building management unit 60 is a system or device used for managing a building, such as a building automation system (hereinafter also referred to as BAS). Examples of malfunctions in a building detected by the building management unit 60 include failures of electrical equipment, air conditioning equipment, sanitary equipment, lighting equipment, disaster prevention equipment, and elevator equipment installed in the building.
[0052] The alarm issuing unit 42 is configured to notify that the alarm information has been acquired. For example, the alarm issuing unit 42 is configured to issue an alarm in a manner that allows the building that has output the alarm information to be identified. Identifiable manners include a manner in which the building that has output the alarm information is identified visually and a manner in which the building that has output the alarm information is identified audibly.
[0053] The manner in which the building that has output the alarm information can be visually identified includes a manner in which an image identifying the building that has output the alarm information is displayed on a display unit such as a liquid crystal display provided on the remote monitoring device 40.
[0054] The operation unit 43 has a configuration for remotely operating the building management unit 60. Examples of devices into which operation contents are input in the operation unit 43 include a keyboard and a mouse provided in the remote monitoring device 40.
[0055] The operation content input to the operation unit 43 is input to a building management unit 60 selected from the multiple building management units 60. An example of the selected building management unit 60 is the building management unit 60 that output the alarm information.
[0056] The mobile information terminal 50 is a terminal carried by a visiting facility staff member. For example, the mobile information terminal 50 is a terminal that travels with the facility staff member along a patrol route visiting a plurality of buildings, or is brought to a site where maintenance work is performed.
[0057] The mobile information terminal 50 is connected to the maintenance support device 10 via a known wired or wireless information communication network so as to be capable of communicating information. The mobile information terminal 50 is a portable information processing device such as a notebook computer, a tablet computer, or a smartphone having a CPU, a ROM, a RAM, an input / output interface, etc.
[0058] Next, the contents of the calculation process when a dispatch response is performed by the maintenance management support device 10 and the maintenance management support system 1 configured as described above will be described with reference to Figs.
[0059] Emergency response is a non-routine task that differs from routine tasks, which are planned repairs, and is an emergency task that occurs on an ad hoc basis. Emergency response includes repair tasks performed in response to an alarm output from the remote monitoring device 40, repair tasks at night, during accidents, or during disasters, etc.
[0060] When power is supplied to the maintenance management support device 10, reception processing is started (S10), as shown in Fig. 4. When reception processing is started, processing is performed to determine whether defect information, which is a request for temporary repair, has been input to the reception unit 12 of the control unit 11, as shown in Fig. 5 (S11).
[0061] The defect information may be input directly to the reception unit 12 from the remote monitoring device 40, or may be input directly to the reception unit 12 from an information processing terminal operated by the building owner, the management company that manages the building, or the tenants occupying the building.
[0062] The malfunction information input from the remote monitoring device 40 may be an alarm. The malfunction information input from the building owner, the management company that manages the building, or the tenants occupying the building may be request information.
[0063] In addition, the operator may input defect information into the reception unit 12 based on information received via telephone or the like from the building owner, the management company that manages the building, or the tenants occupying the building.
[0064] It is preferable that the defect information includes information such as who or what, who or what, where, by when, what is desired, etc. For example, defect information may be "ABC Building, XX floor, XYZ Company, Patent Taro, inquiring about a burned-out light bulb in the office on the XX floor. Please replace the bulb by tomorrow."
[0065] If it is determined that a request for emergency repair has not been input (No in S11), the determination process of S11 is repeated again. If it is determined that a request for emergency repair has been input (Yes in S11), the control unit 11 performs a process of determining whether the emergency repair is within a range of predetermined specifications (S12).
[0066] The specification range is a range of specifications that can be responded to by an emergency response, and is a range that has been determined in advance. The determination process is a process of determining by comparing the identification information and the contents of the repair included in the defect information with the predetermined specification range. For example, the process is a process of determining whether or not a repair is to be performed based on the identification information, or a process of determining whether or not the type of repair requires an emergency response.
[0067] If it is determined that the temporary repair is not within the range of the predetermined specifications (No in S12), a process corresponding to small-scale repair (S13) is performed. An example of the process corresponding to small-scale repair is a process of making a repair request to a contractor who undertakes repairs outside the range of the predetermined specifications. The contractor to which the repair request is made may be selected from contractors registered in advance.
[0068] If it is determined that the request is within the range of the predetermined specifications (Yes in S12), the control unit 11 performs a process of determining whether the request is a request for an emergency response (S14). An example of the process of determining whether the request is a request for an emergency response is a process of determining whether the malfunction information includes information requesting an emergency response. Another example is a process of determining whether the type of malfunction that requires an emergency response or the target where the malfunction occurs matches the type of malfunction or the target included in the malfunction information, which is determined in advance.
[0069] If it is determined that the request is not for an emergency response (No in S14), the control unit 11 performs a trouble response process (S15). An example of the trouble response process is a process of making a repair request to a preregistered contractor who undertakes repairs on a larger scale than small scale repairs.
[0070] If it is determined that the request is for an emergency response (Yes in S14), the process returns to FIG. 4 and the dispatch unit 11 performs processing for dispatching a response (S20). When the dispatch dispatch process is started, the dispatch determination unit 13 of the dispatch unit 11 performs a process of determining whether a dispatch response is necessary (S21), as shown in Fig. 6. The determination process is performed based on the defect information.
[0071] For example, a process for determining whether the defect information includes information requesting a response can be exemplified. In addition, a process for determining whether the defect type and target that require a response are predetermined and the defect type and target included in the defect information match the predetermined defect type and target can be exemplified.
[0072] If it is determined that no emergency response is required (No in S21), a process for carrying out measures (S22) is carried out. An example of the process for carrying out measures is a process for requesting a pre-registered contractor to carry out periodic repairs.
[0073] When it is determined that a dispatch response is necessary (Yes in S21), a process of determining a dispatcher (S23) is performed by the control unit 11. In the process of determining a dispatcher, the dispatcher is actively selected and determined from a plurality of predetermined patrol facility personnel.
[0074] For example, among a plurality of predetermined patrol personnel, the person who rushes to the scene may be selected from the remaining patrol personnel, excluding the patrol personnel scheduled to handle the routine work described below. In other words, the person who rushes to the scene may be selected from the patrol personnel who are not scheduled to handle the routine work described below.
[0075] Also, from among the predetermined patrol personnel, a patrol personnel who is patrolling during the time period when the processing is being performed may be selected. Furthermore, from among the patrol personnel who are patrolling, a patrol personnel who is patrolling a location close to the emergency destination may be selected. Furthermore, a patrol personnel who can handle the repair may be selected based on the content of the repair included in the defect information.
[0076] When the dispatcher is determined, a process (S24) is performed in which the output unit 14 of the control unit 11 issues a dispatch instruction to the determined dispatcher. The output unit 14 outputs information related to the dispatch to the mobile information terminal 50 carried by the determined dispatcher.
[0077] The information on the dispatch includes identification information and information on the location of the building to which the dispatch is to be made. The information on the dispatch may also include information on the target time of arrival, and may further include information on the malfunction target, the details of the repair, and the tools and equipment required for the repair, which are included in the malfunction information.
[0078] When the process of issuing the dispatch instruction has been performed, the process returns to FIG. 4 and the implementation unit 21 performs a dispatch response process (S30). When the dispatch response process is started, the implementation unit 21 performs a process of determining whether or not a treatment such as repair is possible (S31), as shown in Fig. 7. The process of determining whether or not a treatment is possible includes a process of outputting implementation information to the mobile information terminal 50 carried by the dispatcher.
[0079] The implementation information in the emergency response is information related to the response to the malfunction, and includes the items of work to be done to resolve the malfunction, and information on resolving the malfunction, which is the content of the work to resolve the malfunction, etc. The implementation unit 21 collects the items of work to be done to resolve the malfunction linked to the identification information, and information on resolving the malfunction, which is the content of the work to resolve the malfunction, to create the implementation information.
[0080] The process of determining whether treatment is possible includes obtaining information entered by the responder into the mobile information terminal 50 as to whether treatment such as repair is possible, and performing a calculation to determine whether treatment is possible based on the obtained information.
[0081] If it is determined that the treatment is not possible (No in S31), the implementation unit 21 performs a process of dealing with the trouble (S32). An example of the trouble-response process is a process of making a repair request to a company that is different from the person who rushed to the scene and that is registered in advance.
[0082] If it is determined that the treatment is possible (Yes in S31), the implementation unit 21 performs a process of implementing the treatment (S33). The process of implementing the treatment includes a process of outputting information instructing the implementation of the treatment, such as repair, to the mobile information terminal 50 carried by the person who rushes to the scene. It may also include a process of outputting more detailed information used in the implementation of the treatment.
[0083] Once the process for implementing the measures has been carried out, the process returns to FIG. 4, and the reporting unit 31 carries out post-measurement processing (S40). When the post-response process is started, as shown in Fig. 8, the report unit 31 performs a process of reporting to the informant (S41). The contents of the report include the target where the problem occurred, the completion of the process carried out in S33, the result of the repair, etc. The contents of the completion of the process carried out in S33, the result of the repair, etc. are linked to the identification information.
[0084] The reporter to whom the report is made is the reporter regarding the defect information input in the process of S11. When the defect information is input from the remote monitoring device 40, the report is made to the manager of the building in which the remote monitoring device 40 is installed, etc. When the defect information is information input by the owner of the building, a management company that manages the building, or a tenant residing in the building, the report is made to the owner of the building, the management company that manages the building, or the tenant residing in the building.
[0085] When the reporting process to the informant is performed, the reporting unit 31 performs a process of reporting a malfunction that requires urgent reporting (S42). The malfunction that requires urgent reporting may be a predetermined malfunction, or may be a malfunction that is determined based on information input to the mobile information terminal 50 carried by the dispatcher. It may also be a malfunction caused by a predetermined target. The content of the malfunction that requires urgent reporting is linked to the identification information.
[0086] A process for proposing repairs may be performed simultaneously with or after at least one of the processes of reporting in S41 and reporting the defect in S42. Furthermore, if the repair proposal is adopted, the repair may be carried out. The proposed repairs may be small-scale repairs. For example, the repairs are performed on deteriorated equipment such as equipment with reduced performance, and include repairs that restore at least a part of the performance or repairs that return the equipment to the performance at the time of new installation.
[0087] When the defect report is processed, the completion determination unit 32 of the reporting unit 31 performs a process of checking the defect items (S43). The completion determination unit 32 collects the defect items linked to the identification information, checks the defect items, and determines whether the response to the defect related to the building has been completed.
[0088] Examples of the items to be checked include result information and implementation information regarding the results of the troubleshooting that were input to the mobile information terminal 50. The items of the problem to be checked may be items that are predetermined in correspondence with the identification information, or items of all the measures taken for the target where the problem occurred.
[0089] When the process of checking the defective item is completed, the report unit 31 performs a registration process (S44). The registration destination may be a storage device of the maintenance management support device 10, or may be an information processing device other than the maintenance management support device 10. The contents of the registered report are linked to the identification information.
[0090] Once the registration process has been completed, the process returns to the reception process of S10 as shown in FIG. 4, and the calculation process for carrying out the above-mentioned emergency response is repeated.
[0091] Next, the contents of the calculation process when performing routine tasks by the maintenance management support device 10 and the maintenance management support system 1 will be described with reference to Fig. 9. The routine tasks include, for example, tasks such as patrols and meter readings, and attendance for administrative inspections and regular inspections. Below, the attendance routine task will be mainly described.
[0092] When power is supplied to the maintenance management support device 10, as shown in Fig. 9, the maintenance management support device 10 performs a process of determining whether a routine task is scheduled (S51). In the determination process, the reception unit 12 performs a process of acquiring repair response information including routine task information. Based on the acquired routine task information, a determination process is performed by comparing the date and time of the determination with the stored date and time when the routine task is to be performed.
[0093] If it is determined that no routine work is scheduled (No in S51), the process returns to S51 and another determination is made. If it is determined that a routine task is scheduled (Yes in S51), a preparation process is performed by the maintenance management support device 10 (S52). The preparation process includes a process of outputting information on the work plan from the maintenance management support device 10 to the mobile information terminal 50.
[0094] When the routine task is a periodic inspection, the information on the work plan is information that is used before the inspection. The information on the work plan includes, for example, an inspection work plan, an inspection cycle, inspection check items, equipment to be inspected, and information on the inspection company. The maintenance management support device 10 obtains information on the inspection work plan, the inspection cycle, the inspection check items, equipment to be inspected, and the inspection company that are linked to the identification information, and creates the information on the work plan.
[0095] In addition, the preparation processing may include processing to output information regarding the procedures for entering a building where a patrol facility staff member performs routine work, and may also include processing to output information regarding the preparation of a key to be used for entry.
[0096] After the preparation process, the maintenance management assistance device 10 performs an implementation process (S53). The implementation process includes a process in which the maintenance management assistance device 10 acquires information on the inspection result from the mobile information terminal 50.
[0097] The information on the inspection results is information that the visiting facility staff inputs into the mobile information terminal 50 after the inspection. The information on the inspection results includes, for example, the inspection record, the inspection cycle, the inspection check result, the equipment to be inspected, and the inspection company. The information on the inspection record, the inspection cycle, the inspection check result, the equipment to be inspected, and the inspection company is linked to the identification information.
[0098] The process of implementation may include a process of outputting information regarding witnessing the inspection or checkup, or may include a process of outputting information regarding repairs performed in parallel with the inspection or checkup. The information regarding witnessing the inspection or checkup, or the information regarding repairs performed in parallel with the inspection or checkup, may be linked to the identification information.
[0099] When the implementation process is performed, the maintenance management support device 10 performs a process of determining whether or not there is a problem (S54). In the determination process, the determination is made based on the information of the inspection result acquired in the process of S53, for example. If the inspection result includes information that there is a problem, it is determined that there is a problem. If the inspection result does not include information that there is a problem, it is determined that there is no problem.
[0100] If it is determined that there is a malfunction (Yes in S54), a status confirmation process is performed (S55). The status confirmation process includes a process of confirming the status of the equipment with the malfunction and outputting information instructing a report of the confirmation result to the mobile information terminal 50.
[0101] If it is determined that there is no defect (No in S54), a completion confirmation process is performed (S56). The completion confirmation process includes a process of confirming whether all of the inspection check items have been checked.
[0102] When the status confirmation process or the completion confirmation process is performed, the maintenance management support device 10 performs an emergency malfunction report process (S57). In the emergency malfunction report process in S57, the same process as the emergency malfunction report process in S42 is performed.
[0103] A process for proposing repairs may be performed simultaneously with or after the process for reporting the defect in S57. Furthermore, if the proposed repairs are adopted, the repairs may be carried out. The proposed repairs may be small-scale repairs. For example, the repairs are performed on deteriorated equipment, such as equipment whose performance has decreased, and include repairs that restore at least a part of the performance or repairs that return the equipment to the performance at the time of new installation.
[0104] When the emergency malfunction report is processed, the maintenance management support device 10 performs a process of confirming the malfunction item (S58). In the process of confirming the malfunction item in S58, the same process as the process of confirming the malfunction item in S43 is performed.
[0105] After the process of checking the defective item is completed, the maintenance management support device 10 performs a registration process (S59). In the registration process in S59, the same process as the registration process in S44 is performed.
[0106] Once the registration process has been completed, the process returns to step S51 for determining whether or not a routine task is scheduled, and the above-described calculation process for performing a routine task is repeated.
[0107] Next, the process of creating materials will be described with reference to FIG. The process of creating materials is carried out after the calculation process for responding to an emergency has been completed and after the calculation process for performing routine tasks has been completed.
[0108] In the document creation process, first, a report creation process is performed by the mobile information terminal 50 (S71). In the report creation process, a process is performed to collect information linked to the identification information of the target for which the report is to be created. Then, a process is performed to create the report based on the collected information. The collected information includes information stored or registered in the calculation process when responding to an emergency or in the calculation process when performing routine tasks.
[0109] If the repair is a patrol or meter reading, an inspection report is prepared. If the repair is an administrative inspection or regular inspection, an administrative report is prepared.
[0110] When the report is created, the maintenance management support device 10 performs a process of checking the report (S72). The checking process includes a process of acquiring electronic data of the report created by the mobile information terminal 50 based on the identification information. The checking process may include, for example, a process of checking whether the report format matches a predetermined format, whether all items required to be recorded in the report are included, etc. The report format and the items required to be recorded in the report may be a format and items linked to the identification information.
[0111] Once the report has been confirmed, the maintenance management support device 10 performs inspection of the report (S73). If the repair is work performed by patrol or meter reading, the inspection process includes a process to confirm the quantity. The quantity is, for example, the number of materials used during the repair. If the repair is work performed by an administrative inspection or regular inspection, the inspection process includes a process of stamping and reporting to the administration.
[0112] Next, remote monitoring by the remote monitoring device 40 will be described with reference to FIGS. As shown in Figures 3 and 11, the remote monitoring device 40 is connected to a building management unit 60, which is the BAS for building A, a building management unit 60, which is the BAS for building B, and a building management unit 60, which is the BAS for building C, so as to be able to communicate information.
[0113] The display unit of the remote monitoring device 40 displays the management status of the building management unit 60. For example, the display surface of the display unit may be divided to display the management status of a plurality of building management units 60. For example, as shown in Fig. 11, the display surface may be divided into four to display the management status of three building management units 60.
[0114] When the building management unit 60 outputs the alarm information, the acquisition unit 41 acquires the output alarm information, as shown in Fig. 3. When the alarm information is acquired, the alarm issuing unit 42 performs a process of notifying that the alarm information has been acquired.
[0115] 11, for example, a display notifying that the building management unit 60, which is the BAS of Building B, has output alarm information is performed by the alarm issuing unit 42. The alarm issuing unit 42 may also output an alarm sound.
[0116] Furthermore, the operation contents input to the operation unit 43 of the remote monitoring device 40 are input to a selected building management unit 60 from among the multiple building management units 60. Fig. 11 shows a state in which the building management unit 60, which is the BAS of building A, is selected by using a mouse to move the cursor displayed on the display unit over the display area of building A. Note that the method of selecting the building management unit 60 may be a method using a mouse or a method using a keyboard.
[0117] Furthermore, the figure shows a state in which an input operation has been performed to turn on the monitoring function of the building management unit 60 by placing the cursor over the display area of building A and clicking. Note that the method of controlling the functions of the building management unit 60 may be a method using a mouse or a method using a keyboard.
[0118] A signal to turn on the monitoring function is input from the remote monitoring device 40 to the building management unit 60, which is the BAS of the A building, and the operation of monitoring the A building is started.
[0119] According to the maintenance support device 10 and the maintenance support system 1 configured as above, by outputting information regarding dispatch to the mobile information terminal 50, it is possible to dispatch a patrol equipment worker to a building where repairs are to be performed, making it easy to perform maintenance of multiple buildings. By outputting implementation information regarding repairs to the mobile information terminal 50, the patrol equipment worker can perform repairs based on the implementation information regarding repairs, making it easy to prevent a decrease in the quality of repairs by the patrol equipment worker. By obtaining result information and creating report information, it is easy to prevent a decrease in the quality of report information.
[0120] By providing the control unit 11 with the reception unit 12, the dispatch determination unit 13, and the output unit 14, it becomes easier to dispatch patrol equipment personnel to buildings requiring repairs, making it easier to perform maintenance on multiple buildings.
[0121] By receiving at least the repair response information via the remote monitoring device 40, the repair response information can be received without the intervention of an operator, making it easier to perform maintenance management of multiple buildings.
[0122] The alarm issuing unit 42 of the remote monitoring device 40 can issue an alarm in a manner that allows the building that output the alarm information to be identified, making it easier to maintain and manage multiple buildings. The operation unit 43 of the remote monitoring device 40 can operate the building management unit 60, making it easier to maintain and manage multiple buildings.
[0123] The implementation unit 21 creates implementation information based on the repair response information and outputs the implementation information to the mobile information terminal 50, making it easier for the visiting facility staff to carry out repair responses based on the implementation information regarding the repair responses, and making it easier to prevent a decline in the quality of the repair responses by the visiting facility staff.
[0124] Providing the completion determination unit 32 and the creation unit 33 in the reporting unit 31 makes it easier to prevent the quality of the report information from deteriorating.
[0125] By including common identification information in the repair response information, emergency response information, implementation information, result information, and report information, a series of processes in the control unit 11, implementation unit 21, and report unit 31 can be carried out more smoothly.
[0126] For example, the efficiency of report creation processing in the reporting unit 31 can be improved. Since repair results such as inspection results are linked to identification information, by using identification information corresponding to a report, it becomes easier to collect the inspection results to be described in the report, and the report can be created more easily.
[0127] By the identification information having the first information, the second information, the third information, and the fourth information, it becomes easier to perform processing in each of the control unit 11, the implementation unit 21, and the reporting unit 31. For example, among the first information, the second information, the third information, and the fourth information included in the identification information, it becomes easier to collect information such as inspection results using the first information etc. related to processing as a key, and it becomes easier to perform processing such as reporting and analysis. [Explanation of symbols]
[0128] 1...maintenance management support system, 10...maintenance management support device, 11...control section, 12...reception section, 13...dispatch determination section, 14...output section, 21...implementation section, 31...report section, 32...completion determination section, 33...creation section, 40...remote monitoring device, 41...acquisition section, 42...alarm section, 43...operation section, 50...portable information terminal, 60...building management section
Claims
1. A maintenance management support device that supports the maintenance management of a plurality of buildings by a traveling facility worker, A control unit that outputs information regarding dispatch to the building to a mobile information terminal carried by the patrol facility staff based on repair response information, which is information regarding repair responses to the building; an implementation unit that outputs implementation information regarding repair response based on the repair response information to the mobile information terminal; a report unit that acquires result information regarding the results of the repairs input to the mobile information terminal and creates report information; A maintenance management support device comprising:
2. The control unit is A reception unit that receives the repair response information; A dispatch determination unit that determines whether or not a dispatch response by the patrol facility staff is necessary based on the repair response information; an output unit that outputs information regarding the dispatch to a mobile information terminal carried by the patrol facility staff; 2. The maintenance management support device according to claim 1, further comprising:
3. The reception unit receives at least the repair response information via a remote monitoring device that is disposed in a location different from the building, The remote monitoring device includes: An acquisition unit that acquires alarm information output from a building management unit that detects the occurrence of repair work in the building; an alarm issuing unit that issues an alarm in a manner that enables identification of the building that has output the alarm information when the alarm information is acquired; An operation unit for operating the building management unit; 3. The maintenance management support device according to claim 2, further comprising:
4. The maintenance support device described in claim 1, characterized in that the implementation unit creates the implementation information including repair response items and information regarding the results of the repair response based on the repair response information, and outputs the implementation information to the mobile information terminal.
5. The reporting unit: a completion determination unit that determines whether the repair work for the building has been completed based on the result information; a creation unit that creates the report information after it is determined that the repair work for the building has been completed; 2. The maintenance management support device according to claim 1, further comprising:
6. A maintenance support device as described in any one of claims 1 to 5, characterized in that the repair response information, the emergency response information, the implementation information, the result information, and the report information include identification information that individually identifies the target of the repair response.
7. The maintenance support device described in claim 6, characterized in that the identification information includes first information based on laws and regulations related to the object, second information based on the type of the object, third information based on the type of the object, and fourth information based on the model of the object.
8. A maintenance management support system having a maintenance management support device that supports the maintenance management of a plurality of buildings by a traveling facility worker, and a mobile information terminal connected to the maintenance management support device so as to be capable of communicating information therewith, The maintenance management support device includes: A control unit that outputs information regarding dispatch to the building to the mobile information terminal carried by the patrol facility staff based on repair response information, which is information regarding repair responses to the building; an implementation unit that outputs implementation information regarding repair response based on the repair response information to the mobile information terminal; a report unit that acquires result information regarding the results of the repairs input to the mobile information terminal and creates report information; A maintenance management support system comprising:
Citation Information
Patent Citations
Emergency dispatch support system
JP2000348277A
Work management system and work management method
JP2003122889A
Method of requesting special dispatch on occurrence of malfunction
JP2006146759A
Elevator inspection report system, and its control method
JP2006199469A
Method and system for diagnosing abnormality of apparatus
JP2010122847A