Maintenance support device, and maintenance support method
The maintenance support device optimizes nuclear power plant maintenance by classifying equipment and prioritizing tasks based on safety, quality, and cost, addressing the reliability gap in existing technologies.
Patent Information
- Application Number
- JP2023043511
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-17
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing maintenance technologies for nuclear power plants focus on cost reduction but lack sufficient consideration for ensuring reliability, which is crucial for safety and operational efficiency.
A maintenance support device that classifies equipment into multiple classes based on the importance of elemental functions and necessity, using a scoring system to prioritize maintenance tasks, optimizing inspection cycles and activities to ensure safety, quality, and cost-effectiveness.
Enhances maintenance operations by extending inspection cycles and reducing unnecessary tasks, thereby improving reliability and reducing maintenance costs while maintaining safety and quality standards.
Smart Images

Figure 2024132657000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a maintenance support device and the like. [Background technology]
[0002] A known technology for supporting plant maintenance work is described in, for example, Patent Document 1. That is, Patent Document 1 describes that "the processing unit compares a total reduced cost obtained by adding up the reduced costs of each construction / inspection item candidate included in each group with a maximum increased cost, which is the maximum value of the increased costs of the construction / inspection item candidates included in each group." [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2004-355206 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the technology described in Patent Document 1, the possibility of extending the construction and inspection cycle is judged from the viewpoint of cost reduction, but there is room for improvement in terms of ensuring reliability. For example, when the target of maintenance work is a nuclear power plant, there is a tendency to place special emphasis on ensuring reliability.
[0005] Therefore, an object of the present disclosure is to provide a maintenance support device or the like that appropriately supports maintenance work in a nuclear power plant. [Means for solving the problem]
[0006] In order to solve the above-mentioned problems, the maintenance support device according to the present disclosure classifies equipment of the nuclear plant into a number of classes based on the importance of element functions in the nuclear plant system and the necessity of equipment to realize the element functions, and further includes a processing unit that displays candidates for changing the maintenance work of the nuclear plant on a display device based on the results of subdividing the classes from the viewpoint of S (safety)>Q (quality)>D (delivery time)>C (cost). Effect of the Invention
[0007] According to the present disclosure, it is possible to provide a maintenance support device etc. that appropriately supports maintenance work of a nuclear power plant. [Brief description of the drawings]
[0008] [Figure 1] 1 is a configuration diagram of a maintenance support system including a maintenance support device according to an embodiment. [Diagram 2] FIG. 2 is an explanatory diagram illustrating an example of a configuration management DB used in the maintenance support device according to the embodiment. [Diagram 3] FIG. 2 is an explanatory diagram showing an example of a maintenance activity / monitoring item DB used in the maintenance support device according to the embodiment. [Figure 4] FIG. 2 is an explanatory diagram illustrating an example of a sensing DB used in the maintenance support device according to the embodiment. [Diagram 5] FIG. 2 is an explanatory diagram showing an example of an FMEA DB used in the maintenance support device according to the embodiment; [Figure 6] 1 is an explanatory diagram showing an example of a field data DB used in the maintenance support device according to the embodiment; [Figure 7] FIG. 2 is an explanatory diagram showing an example of a material ordering DB used in the maintenance support device according to the embodiment. [Figure 8] 4 is a flowchart showing a process of the maintenance support device according to the embodiment. [Figure 9] 1 is an explanatory diagram illustrating an example of a correspondence table between systems, functions, and components of the maintenance support device according to the embodiment; [Figure 10]4 is an explanatory diagram of a class classification determination table used in the maintenance support device according to the embodiment. FIG. [Figure 11] 11 is an explanatory diagram showing an example of scoring by an evaluation unit of the maintenance support device according to the embodiment; FIG. [Figure 12] 5 is a flowchart showing details of processing by the maintenance support device according to the embodiment. [Figure 13] 1 is an explanatory diagram showing an example of a candidate list for class A in the maintenance support system according to the embodiment; [Figure 14] 1 is an explanatory diagram showing an example of a candidate list for class B in the maintenance support system according to the embodiment; [Figure 15] 1 is an explanatory diagram showing an example of a candidate list for class C in the maintenance support system according to the embodiment; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] <Embodiment> <Maintenance support system configuration> FIG. 1 is a configuration diagram of a maintenance support system 300 including a maintenance support device 100 according to an embodiment. The maintenance support system 300 is a system for supporting maintenance work (inspection, monitoring, and maintenance) of a specified facility. In the following, as an example, a case where the facility to be subjected to the maintenance work is a nuclear power plant will be described, but the present invention is not limited to this. That is, the facility to be subjected to the maintenance work may be, for example, a chemical plant, a manufacturing plant, or a water treatment plant, or may be a power transmission and distribution facility, a communication facility, a medical facility, or a railway facility. As shown in FIG. 1, the maintenance support system 300 is configured to include a maintenance support device 100 and a database device 200.
[0010] The maintenance support device 100 is a device that supports maintenance work of a nuclear power plant or the like. Examples of such nuclear plants include nuclear power generation facilities and nuclear research facilities. The maintenance support device 100 has a function of selecting equipment to be the target of maintenance work and proposing to a user a change in the inspection period of the equipment. Such a maintenance support device 100 may be configured as one computer, or may be configured as a plurality of computers (e.g., servers) that can communicate with each other. As shown in FIG. 1, the maintenance support device 100 is connected to a database device 200 via a network N1.
[0011] 1, the maintenance support device 100 includes a storage unit 10, a processing unit 20, an input unit 30, an output unit 40 (display device), and a communication unit 50. The storage unit 10 includes a non-volatile memory such as a read only memory (ROM) and a hard disk drive (HDD), and a volatile memory such as a random access memory (RAM) and a register. The storage unit 10 stores in advance a program to be executed by the processing unit 20, and also stores predetermined data to be used by the processing unit 20.
[0012] The processing unit 20 is, for example, a CPU (Central Processing Unit), which reads out programs and data stored in the storage unit 10 and executes predetermined processing. The input unit 30 inputs predetermined data based on a user's operation. A keyboard or a mouse is used as this type of input unit 30. The output unit 40 outputs the results of processing by the processing unit 20. A display is used as this type of output unit 40. The communication unit 50 communicates with the database device 200 in a predetermined manner via the network N1.
[0013] 1, the storage unit 10 stores a system / function / component correspondence table 11, a class classification judgment table 12, maintenance activity extraction information 13, sensing extraction information 14, FMEA extraction information 15, field data extraction information 16, evaluation information 17, and a candidate list 18. Each piece of information in the storage unit 10 will be described later.
[0014] 1, the processing unit 20 includes a device relationship extraction unit 21, a class classification unit 22, an evaluation unit 23, an extraction / comparison unit 24, and a candidate output unit 25. Each component of the processing unit 20 will be described later.
[0015] The database device 200 is an external storage device in which a plurality of databases used for processing by the maintenance support device 100 are stored. For example, an HDD (Hard Disk Drive) is used as such a database device 200. As shown in Fig. 1, the database device 200 stores a configuration management DB 210, a maintenance activity / monitoring item DB 220, a sensing DB 230, an FMEA DB 240, a field data DB 250, and a material ordering DB 260.
[0016] It should be noted that "DB" is an abbreviation for database. Also, "FMEA" in the FMEA DB 240 is an abbreviation for Failure Mode and Effect Analysis. "FMEA" is a systematic analysis method for potential failures, and is used to prevent the occurrence of failures and malfunctions. In the following, first, each database stored in the database device 200 will be explained in order.
[0017] FIG. 2 is an explanatory diagram showing an example of the configuration management DB 210. As shown in FIG. The configuration management DB 210 is a database in which design information of the nuclear plant and data indicating the configuration of each device are stored in advance. In the example of Fig. 2, the configuration management DB 210 is configured to include items of "category" and "configuration data". As "categories", design requirements, facility configuration information, and physical configuration are provided. For example, design requirements, which is one of the "categories", includes "configuration data" such as laws and regulations, design criteria documents, and calculation and analysis results.
[0018] FIG. 3 is an explanatory diagram showing an example of the maintenance activity / monitoring item DB 220. As shown in FIG. The maintenance activity / monitoring item DB 220 is a database that stores data related to the maintenance work of a nuclear power plant. In the example of FIG. 3, "maintenance activities" and "monitoring items" are provided as maintenance work. Note that "maintenance activities" are inspections that involve a relatively large workload, such as non-destructive testing and overhaul inspection. Also, "monitoring items" are monitoring items that involve a relatively small workload, such as visual inspection and analysis based on sensor data.
[0019] 3, for "maintenance activities" and "monitoring items," information indicating the contents and frequency of the "maintenance activities" and "monitoring items," as well as the target deterioration events, is stored in the maintenance activity / monitoring item DB 220. For example, the frequency at which workers perform non-destructive testing of a given device, and deterioration events such as corrosion that may be found in the non-destructive testing are stored in advance in the maintenance activity / monitoring item DB 220.
[0020] FIG. 4 is an explanatory diagram illustrating an example of the sensing DB 230. As shown in FIG. The sensing DB 230 is a database in which data such as failure locations, deterioration mechanisms, causes of deterioration, measurement targets, measurement methods, and sensor installation locations for nuclear power plant equipment are associated with equipment names. In the example of Figure 4, packing deterioration is listed as the deterioration mechanism for the sealing part of the "XX valve."
[0021] FIG. 5 is an explanatory diagram showing an example of the FMEA DB 240. FMEA DB240 is a database in which data such as the deterioration modes of nuclear plant equipment, as well as effective maintenance activities and monitoring items to prevent malfunctions, are associated with the equipment. The deterioration modes include information such as the failure location and deterioration mechanism, as well as the effects of the deterioration, the severity of the deterioration, and the frequency of deterioration. In the example of Figure 5, when the shaft of the "◇◇ Pump" breaks down due to corrosion, it is shown that the effects of the deterioration include increased vibration, the severity of the deterioration is high, and the frequency of deterioration is low. Vibration measurement and overhaul inspection are listed as effective maintenance activities and monitoring items to prevent the occurrence of such deterioration modes.
[0022] FIG. 6 is an explanatory diagram showing an example of the field data DB 250. As shown in FIG. The field data DB250 is a database in which the history of actual maintenance work (inspection, monitoring, maintenance, etc.) in the nuclear plant is recorded. In other words, data indicating the results of the specific maintenance activities and monitoring items specified in the maintenance activity / monitoring item DB220 (see FIG. 3) when they are actually performed is stored in the field data DB250. In the example of FIG. 6, the frequency and results of maintenance activities, such as non-destructive testing and overhaul inspection, are stored in association with the maintenance activities. Also, the frequency and results of monitoring are stored in association with the monitoring items, such as lubricant analysis and visual inspection. The field data DB250 also includes the failure and defect records of facilities, equipment, and parts.
[0023] FIG. 7 is an explanatory diagram showing an example of the material order DB 260. As shown in FIG. The material ordering DB 260 is a database that stores data on the equipment and parts of the nuclear plant, such as the stock quantity and unit price for replacement, the next scheduled delivery date, and the stock quantity of other plants. In the example of Fig. 7, data such as the stock quantity and unit price for each equipment is shown, but data may be created for each part (e.g., packing or bearing) that constitutes the equipment. Such material ordering DB 260 is used for inventory management and ordering of equipment and parts, and is also used when the maintenance support device 100 (see Fig. 1) proposes changes to maintenance work to the user.
[0024] Let us return to FIG. 1 again to continue the explanation. The equipment relationship extraction unit 21 included in the processing unit 20 extracts the systems of the nuclear power plant, as well as the elemental functions of the systems and the relationships between the equipment that composes the systems. Here, a "system" refers to a group of equipment or components extracted based on a specific viewpoint, such as cooling water, electricity, or mechanical connections. Examples of such a "system" include a cooling system, an electrical system, a mechanical system, and a control system.
[0025] The device relationship extraction unit 21 has a function of extracting "element functions" of a specific system. Here, "element functions" refer to individual functions among a plurality of functions in a specific system. For example, a cooling system has a plurality of "element functions" such as a pressure resistance function and a flow control function in addition to a cooling function. In this way, one system often has a plurality of element functions.
[0026] The equipment relationship extraction unit 21 reads out information on the equipment constituting the nuclear plant from the configuration management DB 210 (see also FIG. 2 ), extracts the systems as well as the element functions of the systems and the relationships between the equipment constituting the systems, and generates a system-function-component correspondence table 11. The system-function-component correspondence table 11 generated by the equipment relationship extraction unit 21 is stored in the storage unit 10.
[0027] The classifying unit 22 has a function of classifying the equipment of the nuclear plant into a plurality of classes. In this embodiment, the equipment is classified into three classes, Class A, Class B, and Class C, in order of increasing importance of maintenance work, based on the importance of each "elementary function" of the system and the necessity of the equipment to realize the "elementary function". The details will be described later, but the classifying unit 22 classifies each equipment of the nuclear plant into one of Class A, Class B, and Class C based on the information of the class classification determination table 12 (see FIG. 10).
[0028] The evaluation unit 23 assigns scores to devices (or parts thereof) that are classified into class B or class C from the classification results of the classifying unit 22, in the order of S (Safety)>Q (Quality)>D (Deadline)>C (Cost). In other words, the evaluation unit 23 assigns scores to devices and parts based on the idea that safety (S) is most important, followed by quality (Q), delivery date (D), and cost (C) in that order. The scores are used as an index showing the importance of the maintenance work. The results of the scoring by the evaluation unit 23 are stored in the memory unit 10 as evaluation information 17.
[0029] The classification unit 22 classifies, for example, devices belonging to class B that have the above-mentioned score equal to or greater than a predetermined value as class B. + Those with scores below a certain value are classified as Class B. - In the same manner, the classifying unit 22 classifies devices in class C that have the above-mentioned score equal to or greater than a predetermined value. + Those with scores below a certain value are classified as Class C. - Classify into:
[0030] The extraction and comparison unit 24 is Class A, Class B + , Class B - , Class C + , Class C - Each of the items is compared with information in a prescribed database, and candidates for optimization of maintenance activities and monitoring items are extracted as a candidate list 18. As for class A equipment, since it is important equipment for ensuring the reliability of the nuclear power plant, the evaluation places great importance on S (safety) among S (Safety) > Q (Quality) > D (Deadline) > C (Cost). In addition, "optimization" of maintenance activities and monitoring items means lengthening the inspection cycle or changing the contents of maintenance activities and monitoring items so as to reduce waste in maintenance activities and monitoring items while ensuring the reliability of the nuclear power plant. The candidate list 18 extracted by the extraction and comparison unit 24 is stored in the storage unit 10. The candidate output unit 25 causes the output unit 40 to display candidates for the maintenance activities and monitoring items to be changed as a candidate list 18.
[0031] The system / function / component correspondence table 11 stored in the storage unit 10 is a data table that indicates systems, as well as element functions of the systems and relationships between devices that make up the systems, as described above. The classification determination table 12 is a data table used when the classifying unit 22 classifies the equipment of the nuclear power plant into a plurality of classes. The maintenance activity extraction information 13 is information extracted in a predetermined manner by the processing unit 20 from the maintenance activity / monitoring item DB 220. The sensing extraction information 14 is information extracted in a predetermined manner from the sensing DB 230. The FMEA extraction information 15 is information extracted in a predetermined manner from the FMEA DB 240. The field data extraction information 16 is information extracted in a predetermined manner from the field data DB 250. Details of each of these extracted information will be described later.
[0032] The evaluation information 17 stored in the memory unit 10 is information indicating the results of the scoring by the evaluation unit 23. The candidate list 18 is a list (data table) indicating candidates for maintenance activities and monitoring items to be changed.
[0033] <Processing of maintenance support devices> FIG. 8 is a flowchart showing the processing of the maintenance support device (also see FIG. 1 as appropriate). 8, the processing unit 20 extracts element functions of the system and relationships between the equipment constituting the system by the equipment relationship extraction unit 21. That is, the processing unit 20 reads information on the equipment included in the nuclear plant from the configuration management DB 210 (see FIG. 2), extracts element functions of the system and relationships between the equipment constituting the system, and generates a correspondence table 11 of systems, functions, and components.
[0034] FIG. 9 is an explanatory diagram showing an example of the system / function / component correspondence table 11. As shown in FIG. The system-function-component correspondence table 11 is a data table in which a plurality of element functions in a given system, the importance of each element function, and the necessity of a component (a component device of the system) for the element function are associated with each other.
[0035] In the example of Fig. 9, a cooling function, an isolation function, and a flow control function are listed as a number of element functions in a given system. The importance of each element function is associated with one of H (High), M (Middle), and L (Low) in ascending order. The necessity of a component (a component device of the system) for a given element function is associated with one of H (High), M (Middle), L (Low), and no contribution (-) in descending order.
[0036] The necessity of a component for an element function is an index showing the degree to which a specific device (component) is required to perform a specific element function (for example, a cooling function). As shown in FIG. 9, the importance of the element functions of a system and the necessity of the component for the element function are stored as a system-function-component correspondence table 11 in a state where they are associated with each device. In the example of FIG. 9, the importance of the cooling function is "M", and the necessity of the component for the cooling function is "H" for "◇◇Pump", while "◇Motor" is "L". In addition, the importance of each element function and the necessity of the component for the element function, such as an isolation function and a flow control function, are also shown.
[0037] Returning to FIG. 8 again, the explanation will be continued. After extracting the element functions of the system and the relationships between the devices that make up the system in step S1, the processing unit 20 proceeds to step S2. In step S2, the processing unit 20 classifies the devices of the nuclear plant into any of classes A, B, and C by the classifying unit 22 (see FIG. 1). When classifying the devices into classes in this manner, the class classification determination table 12 (see FIG. 1) is used.
[0038] FIG. 10 is an explanatory diagram of the class classification determination table 12. As shown in FIG. The vertical axis in Fig. 10 indicates the importance of element functions, and is divided into three categories: H (High), M (Middle), and L (Low). These three categories correspond to the categories of importance of element functions in the system / function / component correspondence table 11 (see Fig. 9). The horizontal axis in Fig. 10 indicates the necessity of equipment for element functions, and is divided into four categories: H (High), M (Middle), L (Low), and "no contribution." These four categories correspond to the categories of necessity of components in the system / function / component correspondence table 11 (see Fig. 9).
[0039] Then, the classifying unit 22 (see FIG. 1) classifies the equipment into any of classes A, B, or C based on a combination of the importance of the element function and the necessity of the component equipment for the element function. For example, if the importance of the element function is "H" and the necessity of the equipment for the element function is "H", the equipment is classified into class A. Class A is the class with the highest importance when performing maintenance work.
[0040] Additionally, if the importance of the element function is "H" and the necessity of equipment for the element function is "M" or "L", the equipment is classified as Class B. Additionally, if the importance of the element function is "M" and the necessity of equipment for the element function is "H" or "M", the equipment is also classified as Class B. Additionally, if the importance of the element function is "L" and the necessity of equipment for the element function is "H", the equipment is also classified as Class B. Class B is a class of medium importance when performing maintenance work.
[0041] Moreover, if the importance of the element function is "H" and the necessity of the equipment for the element function is "no contribution", the equipment is classified as class C. Moreover, if the importance of the element function is "M" and the necessity of the equipment for the element function is "L" or "no contribution", the equipment is also classified as class C. Moreover, if the importance of the element function is "L" and the necessity of the equipment for the element function is either "M", "L", or "no contribution", the equipment is also classified as class C. Class C is the lowest class of importance when performing maintenance work.
[0042] 10, the processing unit 20 classifies the equipment of the nuclear plant into a plurality of classes A, B, and C based on the importance of element functions in the nuclear plant system and the necessity of equipment to realize the element functions. In other words, after dividing the functions of the system into a plurality of element functions, the processing unit 20 classifies each piece of equipment into one of classes A, B, and C using these element functions as a medium. This makes it possible to appropriately classify the enormous number of pieces of equipment in the nuclear plant based on the importance of maintenance work.
[0043] When classifying each piece of equipment in a nuclear plant into class A, B, or C, the information in the system / function / component correspondence table 11 (see Fig. 9) is referenced in addition to the class classification judgment table 12 (see Fig. 10). For example, for the "XX valve" shown in Fig. 9, the importance of the isolation function is "H," and furthermore, the necessity of the "XX valve" for the isolation function is also "H."
[0044] Here, for the "XX valve," there are combinations related to cooling functions and flow control functions, but when classifying into classes, the combination that has the highest rank based on the class classification judgment table 12 (see FIG. 10) is used. Therefore, the "XX valve" is classified into class A. The same can be said for classifying into classes related to other devices. Next, in step S3 of FIG. 8, the processing unit 20 assigns scores to the devices (or parts) of classes B and C by the evaluation unit 23 (see FIG. 1).
[0045] FIG. 11 is an explanatory diagram showing an example of scoring by the evaluation unit. The horizontal axis of Fig. 11 indicates multiple viewpoints for scoring. Such viewpoints are S (safety), Q (quality), D (delivery time), and C (cost). The vertical axis of Fig. 11 indicates the score for each viewpoint of equipment (or parts) classified as class B or class C.
[0046] The evaluation unit 23 (see FIG. 1) assigns scores to a given piece of equipment from the standpoints of S (safety), Q (quality), D (delivery time), and C (cost). Here, S (safety) refers to ensuring the safety of the nuclear plant, and is the most important. The higher the likelihood that a safety concern will occur if a malfunction occurs in the given piece of equipment, the higher the S (safety) score. Q (quality) shown in FIG. 11 refers to ensuring that the performance of the equipment in the nuclear plant is fully exhibited. The higher the likelihood that the performance of the equipment will not be fully exhibited if a malfunction occurs, the higher the Q (quality) score.
[0047] D (Delivery time) is the perspective of ensuring that parts used in nuclear plant maintenance work are procured appropriately and that maintenance work proceeds as planned. The higher the likelihood that maintenance work will take longer than planned if a malfunction occurs in a specified piece of equipment, the higher the score for D (Delivery time). C (Cost) shown in Figure 11 is the perspective of reducing the costs required for nuclear plant maintenance work. The higher the cost of maintenance work if a malfunction occurs in a specified piece of equipment, the higher the score for C (Cost).
[0048] The scores for S (safety), Q (quality), and D (delivery date) are calculated based on information from the field data DB 250 (see FIG. 6), as well as the sensing DB 230 (see FIG. 4) and the FMEA DB 240 (see FIG. 5). The score for C (cost) is calculated based on information from the material ordering DB 260 (see FIG. 7). The evaluation unit 23 (see FIG. 1) scores a given device by calculating the total score for S (safety), Q (quality), D (delivery date), and C (cost). This score (total score) indicates the importance of performing maintenance work on the given device.
[0049] In this embodiment, the evaluation unit 23 scores devices (or parts) based on the idea of placing the most importance on S (safety), followed by Q (quality), D (delivery date), and C (cost) in that order. In this way, the evaluation unit 23 scores devices based on the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost), thereby making it possible to reduce the cost required for maintenance work while ensuring the reliability of the nuclear plant.
[0050] When reflecting the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost), as shown in FIG. 11, S (safety) may have the highest score, followed by Q (quality), D (delivery date), and C (cost). The evaluation unit 23 may multiply the score of each viewpoint by a predetermined coefficient (positive value) and calculate the sum of (coefficient x score). In this case, the coefficient of S (safety) may be the highest, followed by Q (quality), D (delivery date), and C (cost). This process can also reflect the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost). The results of the scoring by the evaluation unit 23 are stored in the storage unit 10 as evaluation information 17 (see FIG. 1) in association with the equipment or parts.
[0051] Next, in step S4 of Fig. 8, the processing unit 20 subdivides classes B and C by the class classification unit 22 (see Fig. 1). That is, the processing unit 20 subjects classes B and C, which have relatively low importance among the multiple classes A, B, and C, to subdivision. For example, the class classification unit 22 classifies devices belonging to class B that have a score (the sum of the scores S, Q, D, and C) that is a result of processing by the evaluation unit 23 that is equal to or greater than a predetermined value as class B. + Those with points below the specified value are classified as Class B. - The above-mentioned predetermined value classifies devices belonging to Class B as Class B. + and Class B - Class B is a threshold that is a criterion for classifying a product into one of the following two categories: + The importance of maintenance work in this area is Class B. - shall be higher than
[0052] In addition, the classification unit 22 classifies devices belonging to class C that have a score equal to or greater than a predetermined value, which is the processing result of the evaluation unit 23. + Those with points below the specified value are classified as Class C. - Class C + The importance of maintenance work in this area is Class C. - The order of importance of maintenance work is as follows: Class A, Class B + , Class B - , Class C + , Class C - The order is as follows.
[0053] In this way, when the processing unit 20 subdivides a predetermined class (e.g., class B) among multiple classes A, B, and C, it assigns scores to the equipment or parts belonging to the predetermined class in terms of S (safety) > Q (quality) > D (delivery time) > C (cost), and subdivides the predetermined class based on the scores.
[0054] In this way, the results of subdivision of classes B and C, which have a relatively low level of importance, are used when optimizing maintenance work. Note that class A, which has the highest level of importance, is not subject to subdivision because there is no particular need to examine whether to reduce the frequency of future maintenance work. In other words, the processing unit 20 excludes class A, which has a relatively high level of importance among the multiple classes A, B, and C, from the subdivision target.
[0055] Next, in step S5 of FIG. 8, the processing unit 20 compares each class with information in a predetermined database by the extraction / comparison unit 24 (see FIG. 1). In step S6, the processing unit 20 extracts candidates for the maintenance activities and monitoring items to be changed by the extraction and comparison unit 24 (see FIG. 1), and further outputs the candidate list 18 to the output unit 40 by the candidate output unit 25 (see FIG. 1). After performing the process of step S6, the processing unit 20 ends the series of processes (END).
[0056] In this way, the processing unit 20 performs processing to display candidates for changing the maintenance work of the nuclear plant on the output unit 40 (display device) based on the result of subdividing the multiple classes B and C from the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost). This makes it possible to present candidates for the maintenance work to be changed to the user while ensuring the reliability of the nuclear plant.
[0057] FIG. 12 is a flowchart showing details of the processing of the maintenance support device (also see FIG. 1 as appropriate). In step S101, the processing unit 20 outputs the system / function / component correspondence table 11 (see FIG. 9) by the device relationship extraction unit 21. The process of step S101 corresponds to step S1 in FIG.
[0058] Next, in step S102, the processing unit 20 classifies the equipment into a plurality of classes by the classifying unit 22. That is, the processing unit 20 classifies the equipment into any of classes A, B, and C based on the system / function / component correspondence table 11 (see FIG. 9) and the class classification judgment table 12 (see FIG. 10). This makes it possible to identify whether a given equipment in the nuclear plant is an equipment necessary for maintaining important element functions (class A: S103), an equipment that is not important for maintaining element functions (class C: S104), or another equipment (class B: S105). The processing in steps S102 to S105 corresponds to step S2 in FIG. 8.
[0059] In step S106, the processing unit 20 classifies the devices included in class B as class B + and Class B - That is, the processing unit 20 classifies devices included in class B into those in class B based on the viewpoint of S (safety) > Q (quality) > D (delivery date) > C (cost). + and Class B - The process in step S106 corresponds to steps S3 and S4 in FIG. 8 (the same applies to S107).
[0060] In step S107, the processing unit 20 classifies the devices included in class C as class C + and Class C - That is, the processing unit 20 classifies the devices included in class C into those in class C based on the viewpoint of S (safety) > Q (quality) > D (delivery date) > C (cost). + and Class C - It is classified into one of the following categories.
[0061] In step S108, the processing unit 20 compares the deterioration mode and the maintenance activity for class A. Specifically, the processing unit 20 determines the suitability of the maintenance activity and the monitoring items corresponding to the deterioration mode of the equipment based on the data of the FMEA DB 240 (see also FIG. 5). In step S109, the processing unit 20 outputs monitoring items to be added. For example, when a maintenance activity corresponding to a predetermined deterioration mode is not set for a device necessary for maintaining an important element function, the processing unit 20 outputs monitoring items to be added based on information of the sensing DB 230 (see also FIG. 4).
[0062] In step S110, the processing unit 20 + or Class B - The processing unit 20 compares the performance data with the maintenance activities for the above items. That is, the processing unit 20 judges whether the inspection period of a given device (or part) is appropriate or not based on information (performance data) of the field data DB 250 (see also FIG. 6) or the like.
[0063] Next, in step S111, the processing unit 20 outputs the extension of the inspection cycle of the predetermined device or the alternative monitoring items. + If the equipment belongs to Class B, the processor 20 may extend the inspection period of the equipment to two years to ensure a sufficient margin. - If the inspection is in Class B, the processor 20 may reduce the margin and extend the inspection period to four years. + and Class B - By making the degree to which the inspection cycle of the equipment is lengthened (how the margin is taken) different for each of the above, the inspection cycle of the equipment can be changed in a finer manner. That is, based on the idea of S (safety) > Q (quality) > D (delivery date) > C (cost), the processing unit 20 reduces the margin of the inspection cycle within a range in which the safety and quality of the equipment are sufficiently guaranteed even if the margin is reduced. In other words, the inspection cycle is lengthened from the current state by optimizing the excess margin based on the idea of S (safety) > Q (quality) > D (delivery date) > C (cost).
[0064] In this way, when the processing unit 20 lengthens the inspection period of a candidate device as a change in the maintenance work, it reduces the margin of the inspection period after the change against the predetermined standard within a range in which the safety and quality of the device are ensured from the viewpoint of S (safety) > Q (quality) > D (delivery date) > C (cost). As a result, as described above, the excessive margin can be optimized and the inspection period can be lengthened from the current state.
[0065] In addition, candidates for alternative monitoring items may be output as the process of step S111. As mentioned above, "monitoring items" such as fault detection based on sensor data and visual inspection (see FIG. 3) are less burdensome for workers and less expensive than "maintenance activities" such as disassembly inspection and non-destructive testing (see FIG. 3). Therefore, Class B + or Class B - For devices belonging to the above category, candidates for alternative monitoring items may be output, for example, by switching from overhaul inspection (maintenance activity) to visual inspection (monitoring item). For example, the processing unit 20 changes the content of the maintenance work of the candidate device from current inspection to monitoring based on predetermined sensor data as a change in the maintenance work. This can reduce the burden and cost of workers in the maintenance work.
[0066] In step S112, the processing unit 20 + or Class C - The processing unit 20 compares the current maintenance activities with the elemental functions of the system for the above items. That is, the processing unit 20 judges whether the inspection period and the inspection contents of a given device (or part) are appropriate based on information of the field data DB 250 (see FIG. 6) or the like.
[0067] In step S113, the processing unit 20 outputs candidates for extending the inspection period or optimizing the maintenance activity. + If the equipment belongs to class C, the processing unit 20 may extend the inspection period of the equipment to a predetermined period. -If the maintenance activity belongs to the category of the defective part, the processing unit 20 may select the defective part as a candidate for switching the maintenance activity to corrective maintenance. This can reduce the burden on workers and costs involved in maintenance work.
[0068] After performing the processes of steps S109, S111, and S113, in step S114, the processing unit 20 causes the candidate output unit 25 to display on the output unit 40 the candidate list 18 (see FIG. 1) of maintenance activities and monitoring items that are candidates for change.
[0069] The processes of steps S108, S110, and S112 in Fig. 12 correspond to step S5 in Fig. 8. The processes of steps S109, S111, S113, and S114 in Fig. 12 correspond to step S6 in Fig. 8.
[0070] In step S115 of FIG. 12, it is determined whether the contents of the candidate list 18 are reflected in the actual maintenance work. For example, the contents of the candidate list 18 to be reflected in the change of the maintenance work may be selected based on the user's operation of the input unit 30 (see FIG. 1). In step S115, if the contents of a predetermined candidate list 18 are reflected in the actual maintenance work (S115: Yes), the contents of the candidate list 18 are reflected in the maintenance activity / monitoring item DB 220 (see also FIG. 3). In addition, if the contents of the predetermined candidate list 18 are not reflected in the actual maintenance activity (S115: No), there is a possibility that the information used for the current decision-making may have room for improvement, so for example, a process of adding information on the deterioration mode to the FMEA DB 240 is performed.
[0071] FIG. 13 is an explanatory diagram showing an example of a candidate list for class A. In FIG. The system / function / component correspondence table 11 included in Fig. 13 is the same as that shown in Fig. 9. In the example shown in the bold frame in Fig. 13, the importance of the isolation function is "H", and the necessity of the "XX valve" for the isolation function is also "H". Note that there are also cooling functions and flow control functions as combinations of the importance of element functions and the necessity of equipment, but as mentioned above, the combination with the highest rank is used when classifying classes. Therefore, the "XX valve" is classified into class A (see Fig. 10).
[0072] The maintenance activity extraction information 13 shown in Fig. 13 is information extracted from the maintenance activity and monitoring item DB 220 (see Fig. 3). For example, it is shown that a visual inspection is to be performed every three years to check whether or not the packing of the sealing portion has deteriorated with age. FMEA extracted information 15 shown in Fig. 13 is information extracted from the FMEA DB 240 (see Fig. 5). From the "Severity of Deterioration" included in the FMEA extracted information 15, it can be seen that the deterioration of the packing of the sealing portion is a serious defect.
[0073] In the example of Fig. 13, a new monitoring item is added to the candidate list 18 as the additional monitoring item (S109: see Fig. 12) described above. That is, a monitoring item of monitoring the fluid temperature near the seal portion is added to the candidate list 18. By monitoring the fluid temperature near the seal portion while the nuclear plant is in operation, aging deterioration of the seal portion due to heat can be detected at an early stage. This improves the reliability of the nuclear plant.
[0074] FIG. 14 is an explanatory diagram showing an example of a candidate list for class B. In FIG. The system / function / component correspondence table 11 included in FIG. 14 is the same as that shown in FIG. 9. In the example shown by the bold frame in FIG. 14, the importance of the cooling function is "M," and the necessity of the "◇◇ pump" for the cooling function is "H." Therefore, the "◇◇ pump" is classified as Class B (see FIG. 10). This "◇◇ pump" is further classified as Class B based on the scoring by the evaluation unit 23 (see FIG. 1). + ,B- It is classified into one of the following.
[0075] The maintenance activity extraction information 13 indicates that a visual inspection of the packing of the seal is performed every three years, and the field data extraction information 16 indicates that the results of this visual inspection are sound (no abnormalities). For example, if the "◇◇ pump" is Class B, + If the equipment belongs to class B, a material analysis of the seal packing may be added as a maintenance activity, as shown in candidate list 18 in FIG. 14. By carrying out additional maintenance activities in this way, the deterioration of the packing can be detected early. + The inspection period of the devices belonging to may be set to be longer than the current period.
[0076] Also, Class B - For devices that belong to Class B + In comparison with the case of (1), the margin for extending the inspection period (for example, the margin based on the FMEA analysis results) may be made smaller. This makes it possible to reduce the cost required for maintenance work while ensuring reliability.
[0077] FIG. 15 is an explanatory diagram showing an example of a candidate list for class C. In FIG. The system / function / component correspondence table 11 included in FIG. 15 is the same as that shown in FIG. 9. In the example shown in the bold frame in FIG. 15, for example, the importance of the cooling function is "M" and the necessity of a specific valve for the cooling function is "L." In addition, taking into consideration the importance of the isolation function and the flow control function and the necessity of valves for these element functions, the specific valve shown in the bold frame is classified as Class C (see FIG. 10). This valve is further classified as Class C based on the scoring by the evaluation unit 23 (see FIG. 1). + ,C - It is classified into one of the following.
[0078] In the candidate list 18 of FIG. 15, it is proposed to switch the visual inspection of the valve seat to corrective maintenance for the above valve. In addition, fault detection in the valve opening and closing test is proposed as an additional monitoring item. In other words, it is proposed to perform corrective maintenance based on the results of fault detection in the valve opening and closing test. In this way, by reviewing unnecessary inspections, it is possible to reduce the cost of maintenance work while ensuring reliability and quality. Although not shown in Figure 15, Class C + The inspection period for equipment belonging to Class C may be set longer than the current period. - For devices belonging to the above category, corrective maintenance as shown in the candidate list 18 may be performed.
[0079] <Effects> According to this embodiment, equipment belonging to class B is scored based on the viewpoints of S (safety)>Q (quality)>D (delivery time)>C (cost), and further, the equipment belonging to class B is classified based on the scores. + and Class B - Class B is relatively less important. - For Class B + In comparison, the margin for extending the inspection period is made smaller. Based on the idea of S (safety) > Q (quality) > D (delivery) > C (cost), the margin for the inspection period for a given standard is made smaller within a range where the safety and quality of the equipment are adequately guaranteed. In this way, by optimizing the excess margin based on the idea of S (safety) > Q (quality) > D (delivery) > C (cost), the inspection period for the equipment can be made longer than it is now. The same can be said about the subdivision of class C. This allows the optimization of maintenance work to be carried out in a finer manner. As a result, it is possible to ensure the reliability of the nuclear plant while reducing the amount of maintenance work (the effort and cost required for maintenance work).
[0080] <<Variations>> Although the maintenance support device 100 according to the present disclosure has been described in the above embodiments, the present disclosure is not limited to these descriptions and various modifications can be made. For example, in the embodiment, the case where the inspection period of the equipment is changed based on the inspection history, failure history, malfunction history, etc. of the equipment of the nuclear plant has been described, but the present invention is not limited to this. For example, when the same type of equipment or parts as the candidate for changing the maintenance work is used under common conditions in another nuclear plant, the processing unit 20 may acquire information on the inspection history, failure history, and malfunction history of the same type of equipment from the other nuclear plant. Note that a "failure" of an equipment means that the normal operation of the equipment is impaired due to an abnormality in the equipment. The above-mentioned "failure history" is a history related to the "failure" of the equipment. Also, a "malfunction" of the equipment means that the performance of the equipment is not fully exhibited. The above-mentioned "malfunction history" is a history related to the "malfunction" of the equipment. When the inspection period of a candidate device is lengthened as a change in the maintenance work, the processing unit 20 may set a smaller margin of the inspection period after the change with respect to the predetermined standard as the importance of the class to which the device belongs is lower. The processing unit 20 may also set a smaller margin of the inspection period after the change with respect to the predetermined standard within a range in which the safety and quality of the device are ensured from the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost). The above-mentioned predetermined standard is set based on information on the inspection history, failure history, and malfunction history acquired from other nuclear plants. In this way, the inspection period of the device, etc. can be appropriately changed by using the information on the inspection history, failure history, and malfunction history of other nuclear plants. In other words, the excessively secured inspection period margin can be optimized based on the idea of S (safety)>Q (quality)>D (delivery date)>C (cost).
[0081] Furthermore, when changing the maintenance work to lengthen the inspection cycle of a candidate device from the current cycle, the processing unit 20 may set the changed inspection cycle based on the information on the inspection history, failure history, and defect history of a specific critical part. The critical part is a part with the shortest current inspection cycle among multiple parts included in the candidate device. By using the inspection history of such a critical part, the inspection cycle of the device, etc. can be appropriately changed.
[0082] In addition, when the inspection cycle of a candidate device is to be made longer than the current cycle, the revised inspection cycle may be set based on the lifespan and inventory information of the parts contained in the device, as well as the results of a specified EQ (Environmental Qualification) test.
[0083] In the embodiment, the number of subdivisions of class B is two (class B + and Class B - ), but the present invention is not limited to this. That is, class B may be subdivided into three or more classes based on the scores calculated by the evaluation unit 23. The same can be said about the subdivision of class C.
[0084] In the embodiment, among devices belonging to class B, devices with a score equal to or greater than a predetermined value are classified as class B. + Those with scores below the specified value are classified as Class B. - However, this is not limited to the above. For example, among the devices belonging to class B, a certain number of devices may be classified into class B in descending order of the score. + The remaining devices are classified as Class B. - The same can be said about the subdivision of class C.
[0085] In the embodiment, the case where class B and class C are subdivided based on the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost) has been described, but S (safety) may be given much more importance than the others. In other words, the scoring may be performed based on the viewpoint of S (safety)>>Q (quality)>D (delivery date)>C (cost). In addition, in the embodiment, the processing unit 20 is described as assigning scores to class B and class C devices, but the scores may also be assigned by a human by operating the input unit 30 (or the scores assigned by the processing unit 20 may be corrected by a human). Further, subdivision of classes based on the viewpoint of S (safety)>Q (quality)>D (delivery date)>C (cost) may be performed for class A in addition to class B and class C.
[0086] In the embodiment, the maintenance support device 100 (see FIG. 1) includes the input unit 30 and the output unit 40, but the present invention is not limited to this. That is, the input unit 30 and the output unit 40 may be provided outside the maintenance support device 100. In this case, a mobile terminal such as a smartphone or a tablet having the functions of the input unit 30 and the output unit 40 may be used.
[0087] Furthermore, the present disclosure is not limited to the above-described embodiment, and includes various modified examples. For example, the embodiment has been described in detail to clearly explain the present disclosure, and is not necessarily limited to those having all of the configurations described. Furthermore, it is possible to add, delete, or replace part of the configuration of the embodiment with other configurations.
[0088] Furthermore, the above-mentioned configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware, for example, by designing them as integrated circuits. The above-mentioned configurations, functions, etc. may be realized in software by a processor interpreting and executing a program that realizes a predetermined function (for example, a maintenance support method). Information such as programs, tables, files, etc. that realize each function can be stored in a memory, a recording device such as a hard disk or SSD (Solid State Drive), or a recording medium such as an IC card, SD card, or DVD.
[0089] In addition, the control lines and information lines shown are those that are considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it can be considered that almost all components are connected to each other. [Explanation of symbols]
[0090] 10 Storage section 11 System / Function / Component Correspondence Table 12 Classification decision table 13 Conservation activity extraction information 14. Sensing Extraction Information 15 FMEA Extraction Information 16 Field Data Extraction Information 17 Evaluation Information 18 Shortlist 20 Processing section 21 Device Relationship Extraction Unit 22 Classification section 23 Evaluation Department 24 Extraction and comparison section 25 Candidate output section 30 Input section 40 Output section (display device) 50 Communications Department 100 Maintenance support equipment 200 Database device 210 Configuration management DB 220 Maintenance activities / monitoring item DB 230 Sensing DB 240 FMEA DB 250 Field Data DB 260 Material Order DB 300 Maintenance Support System N1 Network
Claims
1. 1. A maintenance support device comprising: a processing unit that classifies equipment of a nuclear plant into a plurality of classes based on the importance of element functions in a nuclear plant system and the necessity of equipment for realizing the element functions, and further displays on a display device candidates for changing maintenance work of the nuclear plant based on a result of subdividing the plurality of classes from the viewpoint of S (safety) > Q (quality) > D (delivery time) > C (cost).
2. When subdividing a predetermined class among the plurality of classes, the processing unit assigns scores to devices or parts belonging to the predetermined class from the viewpoints of S (safety)>Q (quality)>D (delivery time)>C (cost), and subdivides the predetermined class based on the scores.
2. The maintenance support device according to claim 1,
3. The processing unit selects a class having a relatively low importance among the plurality of classes as a target for subdivision.
2. The maintenance support device according to claim 1,
4. The processing unit excludes a class having a relatively high importance from among the plurality of classes from a target for subdivision.
2. The maintenance support device according to claim 1,
5. When the processing section extends the inspection period of the candidate equipment as a change in the maintenance work, the processing section reduces a margin of the inspection period after the change with respect to a predetermined standard within a range in which the safety and quality of the equipment are ensured from the viewpoint of S (safety) > Q (quality) > D (delivery date) > C (cost).
2. The maintenance support device according to claim 1,
6. The processing unit includes: When the same type of equipment or part as the candidate equipment or part is used under common conditions in another nuclear power plant, information on the inspection history, failure history, and malfunction history of the same type of equipment or part is obtained from the other nuclear power plant; When lengthening the inspection period of the candidate equipment as the change in the maintenance work, the lower the importance of the class to which the equipment belongs, the smaller the margin of the inspection period after the change with respect to a predetermined standard becomes; The predetermined criteria are set based on the information.
2. The maintenance support device according to claim 1,
7. The processing unit changes, as the change in the maintenance work, the content of the maintenance work of the candidate device from a current inspection to monitoring based on predetermined sensor data.
2. The maintenance support device according to claim 1,
8. When changing the maintenance work to lengthen the inspection cycle of the candidate equipment from the current state, set the changed inspection cycle based on information on the inspection history, failure history, and defect history of a predetermined critical part; The critical part is the part with the shortest current inspection cycle among the multiple parts contained in the equipment.
2. The maintenance support device according to claim 1,
9. 1. A maintenance support method comprising: classifying equipment of a nuclear plant into a plurality of classes based on the importance of element functions in a nuclear plant system and the necessity of equipment to realize the element functions; and displaying on a display device candidates for changing maintenance work of the nuclear plant based on the results of further subdividing the plurality of classes from the standpoint of S (safety) > Q (quality) > D (delivery time) > C (cost).