Maintenance support device, maintenance support method, and maintenance support program
The maintenance support device optimizes maintenance plans for nuclear power plants by integrating work management, safety, and hazard information to manage temporary changes, ensuring safety and resource allocation, addressing the challenges of maintaining plant integrity during maintenance.
Patent Information
- Application Number
- JP2023043606
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-17
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-03-17
AI Technical Summary
Existing maintenance support devices for nuclear power plants struggle to manage and optimize maintenance processes during temporary changes in physical configuration, which can impact safety and hazard management, especially during parallel tasks and external/internal events, making it difficult to ensure the health and safety of the plant.
A maintenance support device that integrates work management units, safety and hazard management information, system operation information, and legal regulations to create and optimize maintenance plans, using process optimization units to prioritize constraint conditions and resource allocation, ensuring the integrity of nuclear power plants during maintenance.
The device provides a clear maintenance plan that ensures the health and safety of nuclear power plants by managing temporary changes in physical configuration, optimizing processes to meet safety and hazard management constraints, and efficiently allocating resources.
Smart Images

Figure 2024132714000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a maintenance support device, a maintenance support method, and a maintenance support program for supporting a long-term inspection plan in a nuclear power plant. [Background technology]
[0002] In nuclear power plants, the reactor is shut down for periodic inspections (routine inspections) to inspect each piece of equipment at the nuclear power plant, replace parts / repair them (collectively referred to as "maintenance" in this specification), and carry out modification work. These routine inspections are carried out based on a routine inspection schedule in order to be completed within a specified period.
[0003] For example, Patent Document 1 discloses a support device for creating regular inspection processes that enables even non-expert engineers to create regular inspection process plans that take the safety of a power plant into consideration. The support device includes a database that stores information on work performed during regular inspection periods input from an input unit, inspection equipment data, safety regulation data, and past regular inspection process performance data, and an inspection process creation procedure creation function unit that automatically generates a main process schedule consisting of main processes related to critical processes by referring to the past regular inspection process performance data from basic information related to critical processes among the information on work performed during regular inspection periods stored in the database, and determines an order for determining the timing of inspection processes for multiple inspection equipment other than the critical processes from information on work performed on the equipment, and a schedule creation function unit that displays times that can be assigned to the main process schedule when determining the timing of inspection processes for the inspection equipment according to the order.
[0004] In recent years, at nuclear power plants, operators are being required to implement a configuration management (CM) initiative to constantly verify and guarantee that each facility and equipment is manufactured, installed, and operated and maintained (maintained) in accordance with the design requirements. CM involves maintaining and managing the consistency of the three elements of design requirements, design configuration information, and physical configuration. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2021-135144 A Summary of the Invention [Problem to be solved by the invention]
[0006] In nuclear power plants, the physical configuration of the actual structures, facilities, systems, and equipment may be temporarily changed due to maintenance work. During such temporary changes to the physical configuration of the nuclear power plant, in order to ensure safety, it is desirable to perform CM, including how each maintenance work affects the parameters (constraint conditions) that ensure the soundness of the nuclear power plant.
[0007] However, during regular inspections when various tasks are performed in parallel, it is difficult to manually collect and manage this information, and it is difficult to grasp the impact on the soundness of the nuclear power plant. The support device for creating regular inspection schedules in Patent Document 1 does not take this information into consideration either.
[0008] Even during plant shutdowns, external events such as earthquakes, tsunamis, tornadoes, and eruptions, as well as internal events such as flooding and fires, are anticipated. In order to minimize the ripple effects of these hazard events, ensure the safety of the plant, and protect the equipment, it is necessary to constantly grasp the hazard boundary status of the functional maintenance range as well as the hazard boundary information of the functional loss range, and take appropriate measures according to the situation. During regular inspections, many tasks are carried out simultaneously in many areas, which creates a problem in that the manager cannot comprehensively grasp the operational status of the hazard barriers.
[0009] An object of the present invention is to provide a maintenance support device, a maintenance support method, and a maintenance support program for ensuring the soundness of a nuclear plant, such as a nuclear power plant, during temporary changes to the physical configuration that occur due to maintenance work on the nuclear plant, and for planning a process that satisfies constraints such as safety and hazard management when carrying out the work. [Means for solving the problem]
[0010] In order to solve the above problems, the maintenance support device of the present invention is provided with a process optimization unit that creates and / or optimizes a process using as input at least one of work management units that constitute a maintenance plan for a nuclear power plant and safety / hazard management information, system operation information, and legal / regulatory information assigned to the work management units. Effect of the Invention
[0011] According to the present invention, it is possible to provide a maintenance plan that ensures the soundness of a nuclear power plant during a temporary change in the physical configuration that occurs due to maintenance work of the nuclear power plant. [Brief description of the drawings]
[0012] [Figure 1] FIG. 2 is a functional block diagram of the maintenance support device according to the embodiment. [Diagram 2] FIG. 2 is a diagram illustrating a physical configuration of the maintenance support device. [Diagram 3] FIG. 13 is a diagram illustrating a method for calculating a parallel work constraint. [Figure 4] FIG. 13 illustrates a method for resolving parallel work constraints. [Diagram 5] 13 is a flowchart of a maintenance support process. [Figure 6] 13 is a flowchart of a process optimization process. [Figure 7] FIG. 13 is a diagram showing an example of a display of work steps and resource information. [Figure 8] This is a table that patterns work management units. [Figure 9] FIG. 13 is a diagram showing a screen displaying Pareto solutions that are process analysis results. [Figure 10] 13 is a flowchart of a process progress management support process. [Figure 11] FIG. 13 is a diagram showing a screen showing a critical work management unit, constraints, and affected destinations. [Figure 12]FIG. 13 is a diagram showing a screen showing sub-critical task management units, constraints, and affected destinations. [Figure 13] FIG. 13 is a diagram illustrating another physical configuration of the maintenance support device. [Figure 14] 13 is a flowchart of an improvement item review support process. [Figure 15] FIG. 13 is a diagram showing an output screen displaying a process after optimization. [Figure 16] FIG. 13 is a diagram showing an output screen for displaying a simulation result. [Figure 17] FIG. 13 is a diagram illustrating resource load leveling. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. The maintenance support device, the maintenance support method, and the maintenance support program according to the embodiment manage the work management unit of a nuclear power plant by linking it with the safety and hazard management information, the system operation information, and the legal and regulatory information of the nuclear power plant. Then, by adding the temporary change information of the physical configuration that occurs during the implementation of the work management unit to the work management unit, the creation and implementation of a work plan that ensures the soundness of the nuclear power plant during the work is supported.
[0014] FIG. 1 is a functional block diagram of a maintenance support device 1 according to an embodiment. The maintenance support device 1 includes a processing unit 11 including a process optimization unit 111 and a parallel work constraint calculation unit 112, a constraint condition storage unit 121, and an optimization calculation result storage unit 122, and performs management including the effect of each maintenance work on parameters (constraint conditions) for ensuring the soundness of the nuclear power plant.
[0015] The maintenance support device 1 receives information from the safety / hazard management information database 22, the system operation database 25, the laws and regulations database 26, and the work management unit database 21, calculates work progress management information 32 and an optimization work plan 33, and outputs them to the user's process management system 61 or process management database 62. In addition, the optimization work plan 33 is stored in the optimization calculation result storage unit 122.
[0016] The safety and hazard management information database 22 is a database in which safety management and hazard management information for the nuclear power plant is stored. The safety and hazard management information database 22 stores safety management and hazard management information assigned to each work management unit.
[0017] In detail, the information stored in the safety and hazard management information database 22 is information on the isolation range of each system, information on the isolation step of the system, location information of the function maintenance equipment based on the isolation information, hazard area information, each hazard boundary configuration information of the function maintenance equipment, allowable fire load information of the fire area area, allowable floor area (volume) information of the overflow area area, fire load information of brought-in goods, floor occupation area (volume) information of brought-in goods, function information to be maintained related to the safety of the power plant including hazard boundary collapse information and said function management information, hazard barrier and hazard boundary information to be maintained and hazard barrier and hazard boundary management information.
[0018] Furthermore, the safety / hazard management information database 22 stores information on temporary changes to the physical configuration of the equipment that accompany the execution of work, or configuration information or design requirement information of the equipment that is the subject of temporary changes.
[0019] The work management unit database 21 is a database in which information on work management units of a nuclear power plant is stored. The information stored in the work management unit database 21 is information related to the identification and management of work, including the work management unit ID, the work execution period or execution trigger, work area information, target equipment information, information on conditions under which work can be started, information on conditions for completing work, resources required for the work, work step information that uses shared equipment in the work area such as an overhead crane, work step information that uses shared facilities such as a large item entrance, and information on items brought in.
[0020] More specifically, the work area information includes the work loading / unloading area and area constraints. The target equipment information includes the equipment name, equipment control number, inspection cycle, required functions of the equipment, equipment status, and change information of the physical configuration. The context of the work includes the network path or ancillary work. The resources required for work include the number of personnel, skills, work support machines, and materials. Standard processes include standard work time, work location, and work content.
[0021] The information stored in the system operation database 25 includes information on operating / standby systems during regular inspections and information on system target equipment, and is information for enabling automatic selection of which system or category the equipment to be worked on belongs to and its system operation.
[0022] The information stored in the statutes and regulations database 26 is information including safety regulations and the like that are constraints on work imposed by statutes and regulations.
[0023] The plant health database 24 is a database that stores information on functions, operating equipment, and standby equipment that are required when the plant is operating and when it is stopped.
[0024] The user input information 31 is information that the user instructs the maintenance support device, and includes operation cycle period information, mobilizable resource information, resource cost information, target values of the plan, fine adjustments of the plan, work progress information, and the like.
[0025] The processing unit 11 is composed of, for example, a CPU (Central Processing Unit) and executes various types of arithmetic processing. The processing unit 11 executes a maintenance support program 123 shown in FIG. 2 to embody a process optimization unit 111 and a parallel operation constraint calculation unit 112.
[0026] When information from the safety / hazard management information database 22, system operation database 25, statutes / regulations database 26, and work management unit database 21 is input, the process optimization unit 111 cooperates with the parallel work constraint calculation unit 112 to calculate work progress management information 32 and an optimized work plan 33. In other words, the process optimization unit 111 optimizes the process using as input the work management units constituting the maintenance plan for the nuclear power plant equipment and the information assigned to the work management units.
[0027] The parallel work constraint calculation unit 112 calculates constraint conditions for parallel work. The process optimization unit 111 optimizes the process under the work constraints calculated by the parallel work constraint calculation unit 112, using the work management unit and the configuration management information assigned to the work management unit.
[0028] FIG. 2 is a diagram showing a physical configuration of the maintenance support device 1. As shown in FIG. The maintenance support device 1 is a computer including a processing unit 11, a storage unit 12, an input unit 13, a communication unit 14, and an output unit 15, and is installed in an on-premise environment or a cloud environment.
[0029] When the processing unit 11 executes the maintenance support program, a process optimization unit 111 and a parallel operation constraint calculation unit 112 are realized. The storage unit 12 is configured with a large capacity storage device such as an SSD (Solid State Drive) or a hard disk drive, and stores a constraint condition storage unit 121, an optimization calculation result storage unit 122, and a maintenance support program 123.
[0030] The communication unit 14 is, for example, a network interface. The input unit 13 is, for example, a mouse, keyboard, touch panel, etc., and the output unit 15 is, for example, a display device such as a liquid crystal display, which displays characters, figures, images, etc. The output unit 15 and the input unit 13 may be configured as a touch panel display.
[0031] The data center 2 is a facility in which a large number of server groups are installed. In the servers installed in this data center 2, a work management unit database 21, a safety and hazard management information database 22, an inspection record database 23, a plant health database 24, a system operation database 25, and a laws and regulations database 26 are constructed.
[0032] The maintenance support device 1 is capable of communicating with the work management unit database 21, safety and hazard management information database 22, inspection record database 23, plant health database 24, system operation database 25, and laws and regulations database 26 of the data center 2 via the network NW via the communication unit 14.
[0033] Past regular inspection results are stored in the inspection result database 23. The contents of the other databases are the same as those in FIG.
[0034] Next, the processing of the parallel operation constraint calculation unit 112 and the process optimization unit 111 (see Fig. 1 and Fig. 2) which perform process optimization will be explained with reference to Fig. 3 and Fig. 4. First, with reference to Fig. 3, a state in which the constraint conditions are not satisfied by operations A and B which are performed in parallel and processed by the parallel operation constraint calculation unit 112 will be explained.
[0035] Work A is composed of process A-1 to A-3, which are work management units. The fire load indicates the amount of combustible material in area X that occurs in work A during each period. The combustible material in area X that occurs in work A corresponds to a temporary change in the physical configuration that occurs due to maintenance work on the nuclear power plant.
[0036] Work B is composed of process B-1 to B-3, which are work management units. The fire load indicates the amount of combustible material in area X that occurs in work B during each period. The combustible material in area X that occurs in work B corresponds to a temporary change in the physical configuration caused by maintenance work on the nuclear power plant.
[0037] The total fire load indicates the total amount of combustibles in area X. The allowable fire load indicates the amount of combustibles that can be tolerated in area X. In Figure 3, the total fire load exceeds the allowable fire load in the fourth and fifth periods, and the constraints are not met.
[0038] For this reason, the process optimization unit 111 prioritizes the constraint conditions of parallel work over the progress of the process when optimizing individual work management units (processes) in each regular inspection. Figure 4 shows the state in which the parallel work constraints are eliminated.
[0039] In Figure 4, process A-2 of work A is modified so that it is not carried out in periods 4 and 5. This makes the total fire load lower than the allowable fire load in all periods from 1 to 15, and satisfies the constraints.
[0040] FIG. 5 is a flowchart of the maintenance support process. This flowchart uses the user-entered planning period, the timing and duration of regular inspections, and the relative cost coefficient for constraint conditions to create a regular inspection process that maintains the integrity of the nuclear power plant and supports the optimization of that process, using work management units between parallel tasks and the safety and hazard management information assigned to them, system operation information, and legal and regulatory information.
[0041] First, the user inputs a planning period (step S10). The process optimization unit 111 extracts information on task management units to be executed during a period from the task management unit database 21 (step S11). Then, the process optimization unit 111 extracts at least any of the information corresponding to these work management units from the safety / hazard management information database 22, the system operation database 25, and the laws and regulations database 26 (step S12).
[0042] The process optimization unit 111 classifies the constraint conditions related to the information extracted in step S12 (step S13), and displays a list of the classifications of these constraint conditions (step S14). Next, the process optimization unit 111 accepts user condition input via the input unit 13 (step S15). Information of the user condition input includes, for example, a relative cost coefficient, the implementation timing and duration of each regular inspection, a preferred solution for optimization, a desired level, and the like.
[0043] The process optimization unit 111 executes the process optimization process based on this information (step S16), and displays the Pareto solutions and the like, which are the optimization calculation results (step S17).
[0044] Next, when the input unit 13 accepts a process adjustment input from the user in step S18, the process optimization unit 111 determines whether or not there is a new adjustment input (step S19). If there is a new adjustment input (Yes in S19), the process optimization unit 111 returns to step S16 and repeats optimization based on the new adjustment input. If there is no new adjustment input (No in S19), the process optimization unit 111 ends the process.
[0045] FIG. 6 is a flowchart showing details of the process optimization process in step S16 of FIG.
[0046] First, in step S71, the process optimization unit 111 selects a critical WO as a critical WO based on the information assigned to the work order (WO) and the constraints entered by the process planner. Based on the WO information and constraints such as the context of the work, the device selects a series of WOs with the longest duration for each regular inspection. Then, in step S72, a process optimization calculation is performed for the critical WO based on various constraint conditions.
[0047] Next, in step S73, when the period information of the critical process created by the optimization calculation is used as a constraint condition, it is determined whether a WO that was not selected as a critical WO in step S71 will become a new critical WO. If a critical WO is to be added (Yes in S73), the process is executed again from step S71. At this time, it is determined whether a WO that has a risk of becoming a critical WO due to an arbitrary time delay, etc., is to be treated as a critical WO.
[0048] If there is no new critical WO (No in S73), the process proceeds to step S74, where the Pareto solutions of the process optimization calculation and the points of the creation process are calculated and displayed. A display example of the Pareto solutions and the points of the creation process created here will be described later in FIG.
[0049] Next, in step S75, it is determined whether the regular inspection period and cost coefficient have been adjusted by the user based on the display results of step S74, and if adjustments have been made (Yes in S75), the process is repeated from step S72. If no adjustment is required (No in S75), the process proceeds to step S76 to determine the critical process.
[0050] Then, in step S77, the critical process is added to the constraints, and optimization calculations for the non-critical WO are performed. Finally, in step S78, the plant health database 24 is referenced to confirm the feasibility of the overall process, and the overall process is determined.
[0051] The idea behind resource loading is to adjust the timing of WO and optimize work costs during the scheduled inspection period. Based on the mobilization capacity during the scheduled inspection period, the necessary resource information such as the personnel and capabilities / work equipment required to carry out the work, cost information, and operation cycle information, the necessary resources are appropriately allocated for the work management unit and the work step unit in the figure, and an optimization plan for work is made for the entire mobilization resources during the scheduled inspection period. Details will be described later.
[0052] If necessary, information such as work qualifications and skill training history can be set as resource allocation constraints for inter-task units or work steps, as shown in Figure 7. In addition, if there are legal constraints, deviation content constraints can be set.
[0053] FIG. 8 is a table that patterns work management units. This table is for drawing up maintenance plans related to life cycle management. For physical equipment, inspection work management units are patterned according to material quantity, cost, resources, and required period. Then, the process optimization unit 111 creates patterns of work management units that constitute the maintenance plan for equipment in the plant life cycle so as to satisfy the inspection implementation conditions for the physical equipment (maintenance cycle of the physical equipment), and selects the optimal pattern.
[0054] Specifically, in the table of Figure 8, when 20 bottles are inspected, the cost is 25 million yen and the time is 3 days. When 30 bottles are inspected, the cost is 35 million yen and the time is 4 days. When 40 bottles are inspected, the cost is 45 million yen and the time is 5 days. When 60 bottles are inspected, the cost is 60 million yen and the time is 7 days. When 80 bottles are inspected, the cost is 75 million yen and the time is 9 days. When 100 bottles are inspected, the cost is 90 million yen and the time is 11 days.
[0055] FIG. 9 shows a screen 53 that displays the Pareto solutions that are the results of the process analysis. In a multi-objective optimization problem where multiple characteristics need to be improved, there is not a single optimal solution when there are multiple optimization targets. When there are two optimization targets, the solution is an optimal trade-off curve, and when there are three or more optimization targets, the solution is a trade-off surface. These multiple optimal solutions are called Pareto solutions.
[0056] Screen 53 displays a Pareto front 531, which is a curve obtained when the Pareto solutions are plotted in the evaluation function space, and creation process points 532. The optimization targets in the evaluation function space are cost and power generation suspension period. This screen 53 makes it possible to intuitively confirm the variable range of period and cost under the current constraint conditions, and to revise the plan to make it more economical in response to changes in power demand.
[0057] FIG. 10 is a flowchart of the process progress management support process. During regular inspection, it is ideal for all work management units to proceed as scheduled, but there are cases where they are completed earlier than scheduled or delayed. In such cases, it is necessary to quickly consider whether or not to start the work management units to be performed in the subsequent process and to develop a recovery plan. The maintenance support device 1 of the embodiment supports appropriate management of configuration management conditions and real-time process progress management using the process progress during regular inspection as an input through the processing of the flowchart in FIG. 10.
[0058] In step S30, when the input unit 13 of the maintenance support device 1 accepts input of process progress and adjustments by the user, the parallel operation constraint calculation unit 112 calculates constraint conditions for parallel operations (step S31) and displays the calculation results (step S32).
[0059] Then, in step S33, the maintenance support device 1 determines whether or not process review is necessary, and if process review is not necessary (No in S33), ends the processing, and if process review is necessary (Yes in S33), proceeds to step S34.
[0060] In step S34, it is determined whether or not the work management unit needs to be changed, and if it needs to be changed (Yes in S34), process change information is input (step S35), and the process proceeds to step S36. If it is not necessary to change the work management unit (No in S34), the process proceeds to step S36.
[0061] In step S36, the process optimization unit 111 optimizes the process, and the process of FIG. 10 ends.
[0062] FIG. 11 is an output screen (screen 51) of the output section 15 of the maintenance support device 1, which shows critical work management units, constraints, and affected destinations. Screen 51 displays a table consisting of a critical work management unit column, a critical constraint column, and an affected work management unit column, and shows which constraint conditions make a series of work management units critical processes, and which work management units are affected by them.
[0063] FIG. 12 is an output screen (screen 52) of the output section 15 of the maintenance support device 1, which shows sub-critical task management units, constraints, and affected destinations. A table consisting of a sub-critical task management unit column, a critical constraint column, and an affected task management unit column is displayed on screen 52. Screen 52 displays which constraint conditions have made the task management units operating in parallel critical processes, and which task management units are affected by them.
[0064] Using these screens 51 and 52, the user can pick out constraint conditions that are effective for process improvement.
[0065] Next, a maintenance support device 1 that supports the study of improvement items for further optimizing the process will be described. Fig. 13 is a diagram showing a physical configuration of the maintenance support device 1 of this embodiment. This differs from the maintenance support device 1 of Fig. 1 in that the processing unit 11 includes a process improvement support unit 113 that supports the consideration of improvement items for further optimizing the process based on the optimization calculation result.
[0066] FIG. 14 is a flowchart of the improvement item review support process in the process improvement support unit 113 (see FIG. 13).
[0067] First, in step S50, the process improvement support unit 113 inputs a process selected by the user. Then, in step S51, the process improvement support unit 113 refers to the optimization calculation result storage unit 122 and analyzes the optimization calculation result related to the selected process. Next, the process improvement support unit 113 displays the trade-off relationship of the optimization items and the rate of change due to the constraint conditions.
[0068] As described above, the process improvement support unit 113 picks out constraint condition items with a high rate of change that have a large impact on the process through sensitivity analysis of the process optimization results as improvement items or risk information. Here, risk information refers to information on a process in which a delay occurs in a certain process and the subsequent process is significantly delayed.
[0069] Next, in step S53, in order to simulate the effect on the entire process when the constraint conditions of the work are changed by inputting the changed constraint conditions, the constraint conditions are input as simulation information.
[0070] In step S54, the process improvement support unit 113 uses the constraint trade-off information to analyze the impact on the process when the constraint of the work management unit is changed, and calculates a simulation process. For example, it is possible to confirm effects such as extending the inspection cycle to reduce the frequency of the work management unit and reduce the number of days for regular inspection in the long term.
[0071] Finally, in step S55, the process improvement support unit 113 displays the simulation results and ends the process.
[0072] As an example of long-term schedule creation, the optimization of inspection of multiple objects will be explained. Here, we consider a case where 180 control rod drive mechanisms (FMCRD: Fine Motion Control Rod Drive) are all inspected every six years. In such a case, it is effective for optimization to pattern the work management unit and select the appropriate number of control rod drive mechanisms for each regular inspection. The inspection implementation condition is that 180 control rod drive mechanisms are inspected within six years, and the inspection timing is planned so that the second and subsequent inspections, i.e., the (n+1)th and subsequent inspections, can also be performed within six years. In this case, it is assumed that inspections can be performed under the conditions (patterning of work management units) shown in Figure 8.
[0073] FIG. 15 is an output screen (screen 54) that displays the steps after optimization in the processing unit 11. Here, the work management units, processes A-1 to A-3 and processes B-1 to B-3, are displayed. Processes B-1 and B-2, and processes A-2 and A-3 use specific resources, which is shown by hatching.
[0074] When process A-1 is completed, processes A-2 and A-3 can start. However, when process A-1 is completed, the specific resource is being used by process B-2, so process A-2 cannot start until process B-2 is completed. Therefore, it is possible to reconsider the method of process A-2 so that it does not use the specific resource.
[0075] FIG. 16 is an output screen (screen 55) that displays the simulation results in the processing unit 11. Here, because process A-2 does not use any specific resources, it can start when process A-1 is finished. Also, process A-3 can start when process B-2 is finished. If this improvement is implemented, the construction period from process A-1 to A-3 can be shortened. And processes B-1 to B-3 will also become critical processes.
[0076] Next, a function of the maintenance support device 1 of the embodiment that supports the optimization of the implementation period of regular inspections by using mobilizable resources as a constraint will be described. The maintenance support device 1 manages mobilizable resources to optimize inspection costs and improve the feasibility of process implementation. Specifically, resource loading across power plants can ensure mobilization capacity during regular inspections and level out resource loads.
[0077] In the maintenance support device 1 of the embodiment, the planning period input in step S10 of FIG. 5 is determined by the work to be performed during regular inspection in accordance with regulations, laws, and the maintenance cycle of the equipment, and the period required for that work, but in order to execute the plan within the determined period, it is also necessary to take into account the resources that can be mobilized for the work.
[0078] Therefore, in the case of regular inspections in which work is determined to require prior resource adjustment based on the work management unit information, the process optimization unit 111 optimizes the timing of the regular inspection by using the mobilizable resources as a constraint. In addition, for resources that are limited in number, the system identifies the mobilizable resources required for work during a set period, and secures resources according to the plan and levels out the resource load (resource loading function).
[0079] More specifically, a case in which the resource utilization periods of other power plants during the same period are grasped as a constraint condition and the planned period is optimized will be described using the resource load leveling in FIG. 17 as an example. Specifically, Fig. 17 shows a case where a resource usage plan for power plant C is made when the resource usage schedules for power plants A and B have already been decided. As a constraint, there are two sets of resources that can be mobilized at the same time.
[0080] The process optimization unit 111 stores the resource utilization period (resource mobilization information) shown in FIG. 17 as a resource constraint condition, and displays the target WO executable period in the C power plant based on the resource constraint condition.
[0081] Furthermore, the process optimization unit 111 avoids periods when resource utilization rates are high, and displays periods with low risk of fluctuations in available resources. Also, when there is information that mobilization costs vary depending on the time of year, it displays periods with cost advantages. In addition, if there are multiple types of resources to be considered, the overlapping parts of the possible implementation periods of the target WOs are displayed.
[0082] When there are multiple plants (regular inspections) to manage work, the process optimization unit 111 sets the necessary resource conditions for each plant and displays the target WO executable period as a constraint condition. At this time, if there is cost information, etc., optimization is performed and the cost-effective period is displayed.
[0083] (Modification) The present invention is not limited to the above-described embodiment, and includes various modified examples. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and is not necessarily limited to those having all of the configurations described. It is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is also possible to add, delete, or replace a part of the configuration of each embodiment with another configuration.
[0084] The above configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware such as an integrated circuit. The above configurations, functions, etc. may be realized by software by a processor interpreting and executing a program that realizes each function. Information such as the program, table, file, etc. that realizes each function can be stored in a recording device such as a memory, a hard disk, or an SSD (Solid State Drive), or a recording medium such as a flash memory card or a DVD (Digital Versatile Disk).
[0085] In each embodiment, the control lines and information lines are those that are considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it may be considered that almost all components are connected to each other.
[0086] In the above embodiment, the maintenance support device 1 supports the creation and implementation of a work plan that ensures the soundness of a nuclear power plant. However, the present invention can be applied not only to nuclear power plants but also to nuclear plants such as fuel reprocessing facilities and decommissioning facilities. [Explanation of symbols]
[0087] 1 Maintenance support equipment 11 Processing section 111 Process Optimization Department 112 Parallel Work Constraint Calculation Unit 113 Process Improvement Support Department 12 Storage section 121 Constraint storage section 122 Optimization calculation result storage unit 13 Input section 14 Communications Department 15 Output section 2. Data Center 21 Work Management Unit Database 22 Safety and Hazard Management Information Database 23 Inspection record database 24 Plant Health Database 25 Power System Operation Database 26 Laws and Regulations Database 31 User-entered information 32 Work progress management information 33 Optimization Work Plan 51~55 screens 61 Process Control System 62 Process Control Database
Claims
1. a process optimization unit that creates and / or optimizes a process using as input at least one of a work management unit constituting a maintenance plan for the nuclear plant and safety / hazard management information, system operation information, and legal / regulatory information assigned to the work management unit; A maintenance support device comprising:
2. A parallel operation constraint calculation unit is further provided for calculating a constraint on a parallel operation, The process optimization unit creates and / or optimizes a process by using the work management unit and at least any of safety / hazard management information, system operation information, and legal / regulatory information assigned to the work management unit under the work constraints calculated by the parallel work constraint calculation unit.
2. The maintenance support device according to claim 1.
3. The safety and hazard management information assigned to the work management unit includes information on the isolation range of each system, information on the isolation steps of each system, information on the location of the functional maintenance equipment based on the isolation information, hazard area information, information on the configuration of each hazard boundary of the functional maintenance equipment, information on the allowable fire load of the fire area, information on the allowable floor area (volume) of the overflow area, information on the fire load of brought-in items, information on the floor occupation area (volume) of brought-in items, information on the collapse of the hazard boundary, information on the functions to be maintained related to the safety of the power plant and management information on the above-mentioned functions, information on the hazard barriers and hazard boundaries to be maintained, and information on the management of the hazard barriers and hazard boundaries.
3. The maintenance support device according to claim 2.
4. The safety and hazard management information assigned to the work management unit stores information on temporary changes to the physical configuration of the equipment involved in the work, or information on the configuration or design requirements of the equipment that is subject to the temporary changes.
3. The maintenance support device according to claim 2.
5. The process optimization unit assigns safety and hazard management information, system operation information, or legal and regulatory information to each of the work management units in each periodic inspection and the work management units in the maintenance plan related to the life cycle management, 2. The maintenance support device according to claim 1.
6. the process optimization unit optimizes the process by using the work management units and safety / hazard management information, system operation information, or legal / regulatory information assigned to the work management units, under constraints that ensure the reliability of the nuclear power plant, taking into consideration the duration of the process for each task, the cost of each task, and the resources required for each task; 6. The maintenance support device according to claim 5.
7. The process optimization unit performs a process optimization calculation for the critical operation management unit, and performs an optimization calculation for the non-critical operation management unit using the obtained critical operation management unit as a constraint condition, thereby confirming the feasibility of the entire process.
2. The maintenance support device according to claim 1.
8. The process optimization unit determines the critical work management unit when no new critical work management unit is generated using the period information of the critical process created by the optimization calculation as a constraint condition and when there is no adjustment of the outage period and the cost coefficient.
8. The maintenance support device according to claim 7.
9. The system further includes a process improvement support unit that supports the consideration of improvement items for further optimizing the process based on the optimization calculation results.
2. The maintenance support device according to claim 1.
10. The process improvement support department includes: By performing sensitivity analysis on the process optimization results of the selected process, constraint items with high rates of change that have a large impact on the process are picked up as improvement items or risk information. Using trade-off information on constraints, analyze the impact on the process when constraints for work management units are changed 10. The maintenance support device according to claim 9.
11. The process optimization unit has a function of leveling resource loads based on the resource mobilization capacity and period information for each regular inspection or regular inspection process.
2. The maintenance support device according to claim 1.
12. a step of assigning at least one of safety / hazard management information, system operation information, and legal / regulatory information corresponding to a work management unit constituting a maintenance plan for the nuclear plant; optimizing a process by inputting the work management unit and at least one of safety / hazard management information, system operation information, and legal / regulatory information assigned to the work management unit; A maintenance support method comprising:
13. On the computer, a step of assigning at least one of safety / hazard management information, system operation information, and legal / regulatory information corresponding to a work management unit constituting a maintenance plan for the nuclear plant; a step of optimizing a process by inputting at least one of the work management unit and safety / hazard management information, system operation information, and legal / regulatory information assigned to the work management unit; A conservation support program to implement this.
Citation Information
Patent Citations
Method and device for forming long-term inspection plan for control rod drive mechanism
JP1995280978A
Management device for plant maintenance work
JP1996129414A
Method and device for preparing periodic inspection process of nuclear plant
JP1999242092A
Process control system, method, and program
JP2014203359A
Periodical inspection process creation support device and periodical inspection process creation support method
JP2021135144A