Yield rate calculation device, yield rate calculation method, and yield rate calculation program

The yield rate calculation device accurately accounts for discarded parts in resin molding, enhancing yield analysis precision and cost management by calculating total resin consumption, including runner and purge amounts.

JP2024141754AInactive Publication Date: 2024-10-10OBIC CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023053569
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-10
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing yield rate calculation methods for resin molding do not accurately account for the consumption of discarded parts such as runners and defective materials, leading to inaccurate yield analysis and inadequate cost management.

Method used

A yield rate calculation device and method that considers the consumption of discarded parts by calculating the total resin amount including product weight, runner weight, and purge amount, using a master database to determine standard resin amounts and yield rates.

Benefits of technology

Enables precise yield rate calculation by accounting for discarded parts, improving material consumption accuracy and enabling better cost control and equipment maintenance decisions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

To highly accurately calculate a yield rate by taking into account a consumption amount of a portion that is discarded other than finished products when performing product molding from resin using a molding machine.SOLUTION: A yield rate calculation device comprises: a master in which a master item as product, one or more resins as materials forming the master item, and the constitution number of each resin are registered in association with one another; and manufacturing result input means for, according to operations of an operator on a manufacturing result input screen, when manufacturing result number, manufacturing date, reception item as product, received order quantity, defective number, product weight per piece, runner weight per piece, and purge quantity are specified, calculating a total resin amount by (reception quantity + defective number)×(product weight per piece + runner weight per piece) + purge quantity, calculating reference resin amount for each resin obtained from the master using a reception item as a key, as a total of reference use quantity calculated by (reception quantity + defective number)×constitution number of the resin in the master, and calculating a yield rate by reference resin amount / total resin amount.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a yield calculation device, a yield calculation method, and a yield calculation program. [Background technology]

[0002] For example, in a manufacturing industry where products are molded from resin using a molding machine, there are parts that are discarded in addition to the finished product (runners, defective materials due to purging work). Conventionally, there is a device for calculating the yield rate, for example, as disclosed in Patent Document 1. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2005-277290 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, the above Patent Document 1 does not state anything about calculating the yield rate with high accuracy by taking into account the consumption amount of parts that will be discarded other than the finished product when molding products from resin using a molding machine.

[0005] The present invention has been made in consideration of the above, and aims to provide a yield rate calculation device, a yield rate calculation method, and a yield rate calculation program that are capable of calculating the yield rate with high accuracy by taking into account the consumption amount of parts that will be discarded other than the finished product when products are molded from resin using a molding machine. [Means for solving the problem]

[0006] In order to solve the above-mentioned problems and achieve the object, the present invention provides a yield rate calculation device that includes a control unit and calculates a yield rate when a product is molded from resin using a molding machine, the control unit being configured to be able to access a master in which a parent item, which is a product, one or more resins that are materials for molding the parent item, and the constituent number of each resin are registered in association with each other, and the control unit is ...

[0007] According to another aspect of the present invention, the production performance input means may register production performance data including a production performance number, a production date, an accepted item, a total quantity, an accepted number, a defective number, equipment, a product weight per unit, a runner weight per unit, a number of restarts, a purged amount, a total resin amount, and a reference resin amount in a storage area.

[0008] According to another aspect of the present invention, the control unit may further include a yield analysis means for creating a product-by-product yield statement that aggregates the manufacturing performance data for each product for the current month.

[0009] According to another aspect of the present invention, the control unit may further include a yield analysis means for creating a yield statement by facility and product by aggregating the manufacturing performance data for the current month by facility and product.

[0010] In addition, in order to solve the above-mentioned problems and achieve the object, the present invention provides a yield rate calculation method executed by an information processing device equipped with a control unit, the control unit being configured to be able to access a master in which a parent item which is a product, one or more resins which are materials for molding the parent item, and the constituent number of each resin are registered in association with each other, and the control unit includes a manufacturing history input process in which, when the manufacturing history number, manufacturing date, accepted item which is the product, order number, number of defects, product weight per piece, runner weight per piece, and purge amount are specified in response to an operator's operation on the manufacturing history input screen executed by the control unit, the total resin amount is calculated as (accepted number + number of defects) x (product weight per piece + runner weight per piece) + purge amount, the standard resin amount is calculated as the sum of the standard usage amounts calculated for each resin obtained from the master using the accepted item as a key, by (accepted number + number of defects) x the constituent number of the resin in the master, and the yield rate is calculated as the standard resin amount / the total resin amount.

[0011] In addition, in order to solve the above-mentioned problems and achieve the object, the present invention provides a yield rate calculation program to be executed by an information processing device having a control unit, the control unit being configured to be able to access a master in which a parent item which is a product, one or more resins which are materials for molding the parent item, and the constituent number of each resin are registered in association with each other, and the control unit is configured to execute a manufacturing performance input process in which, when a manufacturing performance number, manufacturing date, accepted item which is a product, order number, number of defects, product weight per piece, runner weight per piece, and purge amount are specified in response to an operator's operation on the manufacturing performance input screen, the control unit calculates a total resin amount as (accepted number + number of defects) x (product weight per piece + runner weight per piece) + purge amount, calculates a standard resin amount as the sum of standard usage amounts calculated for each resin obtained from the master using the accepted item as a key, by (accepted number + number of defects) x the constituent number of the resin in the master, and calculates a yield rate as standard resin amount / total resin amount. Effect of the Invention

[0012] According to the present invention, when a product is molded from resin using a molding machine, it is possible to calculate the yield rate with high accuracy by taking into account the consumption amount of parts that will be discarded other than the finished product. [Brief description of the drawings]

[0013] [Figure 1] FIG. 1 is a block diagram showing an example of the configuration of a yield calculation device according to the present embodiment. [Diagram 2] FIG. 2 is a diagram illustrating an example of the configuration of the manufacturing configuration master (parent). [Diagram 3] FIG. 3 is a diagram illustrating an example of the configuration of the manufacturing configuration master (child). [Figure 4] FIG. 4 is a diagram illustrating an example of the configuration of the item master. [Diagram 5] FIG. 5 is a diagram illustrating an example of the configuration of the facility master. [Figure 6] FIG. 6 is a flowchart for explaining an outline of the overall process of the control unit of the yield calculation device in this embodiment. [Figure 7] FIG. 7 is a diagram for explaining a specific example of the process of the control unit of the yield calculation device in the present embodiment. [Figure 8] FIG. 8 is a diagram for explaining a specific example of the process of the control unit of the yield calculation device in this embodiment. [Figure 9] FIG. 9 is a diagram for explaining a specific example of the process of the control unit of the yield calculation device in the present embodiment. [Figure 10] FIG. 10 is a diagram for explaining a specific example of the process of the control unit of the yield calculation device in this embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] Hereinafter, preferred embodiments of a yield calculation device, a yield calculation method, and a yield calculation program according to the present invention will be described in detail with reference to the accompanying drawings. Note that the present invention is not limited to the preferred embodiments.

[0015] [1. Overview] For example, in the manufacturing industry where products are made from resin using molding machines, there are parts that are discarded in addition to the finished product (runners, defective materials from the purging process). "Runners" are unnecessary materials that are generated in the path of the resin during multi-cavity molding. "Purging" refers to the process of removing unnecessary materials remaining in the heater barrel when the equipment is restarted (initial operation, restarting after a brief stop).

[0016] Previously, when calculating yield rates, waste materials (runners, defective materials from purging) other than the finished product were not taken into account. Also, in many cases, the breakdown of material consumption was unclear and yield analysis was insufficient. In addition, in terms of cost management, the unnecessary materials mentioned above are often treated as shelf differences, and are often not considered as consumption per order.

[0017] Therefore, in this embodiment, when a product is molded from resin using a molding machine, the yield rate is calculated with high accuracy by taking into account the consumption of parts that are discarded in addition to the finished product.In addition, the actual weight of the runner and information on unnecessary materials in the purging work are stored in the system, and this information is used to calculate the material consumption.In addition, by comparing with the reference weight and reference runner weight stored in the master, and the reference purge amount when restarting each piece of equipment, etc., the yield rate is used for yield analysis.

[0018] According to this embodiment, when molding products from resin using a molding machine, the yield rate can be calculated with high accuracy by taking into account the consumption of parts that are discarded in addition to the finished product. Also, by calculating the material consumption amount including unnecessary materials due to runners and purging work, the material consumption amount can be refined and cost management can be improved. Also, by calculating the yield rate for each equipment used and product, it is possible to grasp the deterioration of yield due to equipment factors, and it can be used for considering the equipment used and making decisions on maintenance, capital investment, etc.

[0019] The yield calculation device of the present invention can be widely used in industries such as chemicals.

[0020] [2. Configuration] The configuration of a yield calculation device 100 according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing an example of the configuration of the yield calculation device 100 according to this embodiment.

[0021] The yield calculation device 100 is a commercially available desktop personal computer. The yield calculation device 100 is not limited to a stationary information processing device such as a desktop personal computer, but may be a portable information processing device such as a commercially available notebook personal computer, a PDA (Personal Digital Assistant), a smartphone, or a tablet personal computer.

[0022] 1, the yield calculation device 100 includes a control unit 102, a communication interface unit 104, a storage unit 106, and an input / output interface unit 108. Each unit included in the yield calculation device 100 is connected to each other so as to be able to communicate with each other via an arbitrary communication path.

[0023] The communication interface unit 104 communicatively connects the yield calculation device 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via the communication line. Here, the network 300 has a function of connecting the yield calculation device 100 and the server 200 to be able to communicate with each other, and is, for example, the Internet or a LAN (Local Area Network). The data stored in the storage unit 106 described later may be stored in the server 200.

[0024] The input / output interface unit 108 is connected to an input device 112 and an output device 114. The output device 114 may be a monitor (including a home television), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that cooperates with a mouse to realize a pointing device function. In the following, the output device 114 may be referred to as the monitor 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112. In addition, "output" includes displaying on the monitor of the output device 114 and printing on the printer of the output device 114. In addition, a user's operation on the information displayed on the monitor 114 using the input device 112 or the like may be referred to as a "user operation via a UI."

[0025] The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs for cooperating with an OS (Operating System) to give instructions to a CPU (Central Processing Unit) to perform various processes. For example, memory devices such as RAM (Random Access Memory) and ROM (Read Only Memory), fixed disk devices such as hard disks, flexible disks, and optical disks can be used as the storage unit 106. The storage unit 106 also stores a manufacturing configuration master (parent) 106a, a manufacturing configuration master (child) 106b, an item master 106c, an equipment master 106d, manufacturing performance data, a yield calculation sheet, and the like. FIG. 2 is a diagram showing an example of the configuration of the manufacturing configuration master (parent) 106a. FIG. 3 is a diagram showing an example of the configuration of the manufacturing configuration master (child) 106b. FIG. 4 is a diagram showing an example of the configuration of the item master 106c. FIG. 5 is a diagram showing an example of the configuration of the equipment master 106d.

[0026] The manufacturing configuration master (parent) 106a is a master that sets the standard runner weight (g) and standard yield rate for each product, and can be configured as a table or the like that associates and registers the parent item, standard runner weight (g), and standard yield rate, as shown in Fig. 2. The parent item is the key item. In the example shown in the figure, the first line has the parent item "A001", standard runner weight (g) "0.8", and standard yield rate "0.97".

[0027] The manufacturing configuration master (child) 106b is a master that sets the components that make up a product and their number of components, and can be configured with a table or the like that associates and registers parent items, component numbers, component items, and component numbers (g) as shown in Fig. 3. The parent items and component numbers are key items. In the example shown in the figure, the first line has parent item "A001", component number "10", component item "B001", and component number (g) "10g", and the second line has parent item "A001", component number "20", component item "B002", and component number (g) "20g".

[0028] The item master 106c is a master in which a name and unit are set for each item, and can be configured with a table in which items, names, and units are registered in association with each other, as shown in Fig. 4. The item is the key item. In the example shown in the figure, the first line is item "A001", name "product A", and unit "piece", the third line is item "B001", name "resin A", and unit "g", and the fourth line is item "B002", name "resin B", and unit "g".

[0029] The manufacturing configuration master (parent) 106a, the manufacturing configuration master (child) 106b, and the item master 106c are collectively referred to as "master." The manufacturing configuration master (parent) 106a, the manufacturing configuration master (child) 106b, and the item master 106c may be configured as an integrated master or may be configured as separate masters.

[0030] The equipment master 106d is a master that sets the purchase date, previous maintenance, and standard purge amount for each piece of equipment, and can be configured as a table or the like that associates and registers equipment, name, purchase date, previous maintenance, and standard purge amount, as shown in FIG. 5. Equipment is a key item. In the example shown in the figure, the first line is equipment "A", name "equipment A", purchase date "2015 / 4 / 1", previous maintenance "2022 / 4 / 1", and standard purge amount "100", and the second line is equipment "B", name "equipment B", purchase date "2022 / 10 / 1", and standard purge amount "90".

[0031] The production performance data may include production performance number, production date, received item code, received item, total quantity, received number, number of defects, equipment, product weight / piece (product weight per piece), runner weight / piece (runner weight per piece), number of restarts, purging amount, total resin amount, and reference resin amount.

[0032] The control unit 102 is a CPU or the like that comprehensively controls the yield rate calculation device 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, and required data, and executes various information processing based on these stored programs.

[0033] The control unit 102 is configured to be able to access the manufacturing configuration master (parent) 106a, the manufacturing configuration master (child) 106b, the item master 106c, the equipment master 106d, the manufacturing performance data, the yield calculation sheet, and the like stored in the storage unit 106. Note that the manufacturing configuration master (parent) 106a, the manufacturing configuration master (child) 106b, the item master 106c, the equipment master 106d, the manufacturing performance data, the yield calculation sheet, and the like may be stored in other locations (e.g., the server 200) as long as the control unit 102 is able to access them.

[0034] The control unit 102 conceptually includes a manufacturing performance input unit 102a, a yield analysis processing unit 102b, a master maintenance unit 102c, and a screen display control unit 102d.

[0035] For example, when the manufacturing record number, manufacturing date, accepted item which is the product, order quantity, number of defects, product weight per unit, runner weight per unit, and purge amount are specified in response to the operator's operation on the manufacturing record input screen displayed on the monitor 114, the manufacturing record input unit 102a calculates the total resin amount as (accepted quantity+number of defects)×(product weight per unit+runner weight per unit)+purge amount, calculates the standard resin amount as the sum of the standard usage amounts calculated for each resin of the constituent items obtained from the first master using the accepted item as a key, by (accepted quantity+number of defects)×the constituent number of that resin in the first master, and calculates the yield rate as the standard resin amount / total resin amount.

[0036] The production history input unit 102a further registers production history data in the memory unit 106, including production history number, production date, received item, total quantity, received number, number of defects, equipment, product weight per unit, runner weight per unit, number of restarts, purging amount, total resin amount, and reference resin amount.

[0037] The yield analysis processing unit 102b creates a product-by-product yield statement that summarizes the manufacturing performance data for the current month for each product, outputs the result to the monitor 114 for display on the yield analysis screen, and registers the result in the storage unit 106.

[0038] In addition, the yield analysis processing unit 102b creates a yield statement by facility and product by aggregating the manufacturing performance data for the current month by facility and product, displays it on the yield analysis screen displayed on the monitor 114, and registers it in the memory unit 106.

[0039] The master maintenance unit 102c, for example, performs editing such as inputting, adding, changing, and updating data for the manufacturing configuration master (parent) 106a, the manufacturing configuration master (child) 106b, the item master 106c, the equipment master 106d, and the configuration master 106a in response to an operator's operation on a master maintenance screen displayed on the monitor 114.

[0040] The screen display control unit 102d controls the display of various screens (eg, a manufacturing performance input screen, a yield analysis screen, a master maintenance screen, etc.) displayed on the monitor 114 and the reception of inputs on the screens.

[0041] [3. Specific Examples] A specific example of the process performed by the control unit 102 of the yield calculation device 100 in this embodiment will be described with reference to FIGS.

[0042] (3-1. Overall processing) 6 is a diagram showing a flow for explaining an outline of the overall processing of the control unit 102 of the yield calculation device 100 in this embodiment. The outline of the overall processing of the control unit 102 of the yield calculation device 100 in this embodiment will be explained with reference to FIG.

[0043] In the manufacturing process, production is carried out using a molding machine based on work instructions (T1). In order to input manufacturing results, data on the number of stops, purge amount, etc. is also recorded.

[0044] Next, the results of the manufacturing (T1) are registered as data. Not only the volume of production, but also the runner weight, purge amount, number of defects, etc. are registered. Specifically, the manufacturing performance input unit 102a executes a manufacturing performance input process (T2). Specifically, in the manufacturing performance input process, when the manufacturing performance number, manufacturing date, accepted item which is the product, order number, number of defects, product weight per unit, runner weight per unit, and purge amount are specified in response to the operation of the operator on the manufacturing performance input screen displayed on the monitor 114, the manufacturing performance input unit 102a calculates the total resin amount by (accepted number + number of defects) x (product weight per unit + runner weight per unit) + purge amount, calculates the standard resin amount by the sum of the standard usage amount calculated by (accepted number + number of defects) x the number of components of the resin in the first master for each resin of the component items acquired from the first master using the accepted item as a key, and calculates the yield rate by the standard resin amount / total resin amount.

[0045] The production history input unit 102a further registers production history data in the memory unit 106, including production history number, production date, received item, total quantity, received number, number of defects, equipment, product weight per unit, runner weight per unit, number of restarts, purging amount, total resin amount, and reference resin amount.

[0046] Next, at a timing such as the end of the month, the yield rate is analyzed. Specifically, the yield analysis processing unit 102b executes the yield analysis processing (T3). Specifically, in the yield analysis processing, the yield analysis processing unit 102b creates a product-by-product yield statement that summarizes the manufacturing performance data for the current month by product or by equipment-product, and displays and outputs it on the yield analysis screen displayed on the monitor 114, while also registering it in the storage unit 106.

[0047] (3-2. Sample data) 7 to 10 are diagrams showing sample data for explaining a specific example of the process of the control unit 102 of the yield calculation device 100 in this embodiment. A specific example of the process of the control unit 102 of the yield calculation device 100 in this embodiment will be explained with reference to Figs. 7 to 10. In the following, an example in which the master configuration examples in Figs. 2 to 5 are used will be explained.

[0048] (T2: Manufacturing performance input processing) A specific example of the manufacturing performance input process will be described with reference to FIGS. For example, when the manufacturing record number, manufacturing date, accepted item which is the product, order quantity, number of defects, product weight per unit, runner weight per unit, and purge amount are specified in response to the operator's operation on the manufacturing record input screen displayed on the monitor 114, the manufacturing record input unit 102a calculates the total resin amount by (accepted quantity+number of defects)×(product weight per unit+runner weight per unit)+purge amount, calculates the standard resin amount by the sum of the standard usage amount calculated by (accepted quantity+number of defects)×the number of components of the resin in the first master using the accepted item as a key, calculates the yield rate by standard resin amount / total resin amount, and registers the manufacturing record data including the manufacturing record number, manufacturing date, accepted item, total quantity, accepted number, number of defects, equipment, product weight per unit, runner weight per unit, number of restarts, purge amount, total resin amount, and standard resin amount in the memory unit 106.

[0049] 7 is a diagram showing a display example of the production performance input screen 400. On the production performance input screen 400, the usage amount is calculated by registering the number of completed items, the actual product weight, and related consumed materials. This enables precise calculation and understanding of usage amounts. By precisely understanding the actual input amount for each product, it leads to improved accuracy in cost management for each product.

[0050] The production performance input screen 400 has a main area 401, a withdrawal detail 402, and a registration button (not shown). The main area 401 has fields for specifying the production performance number, business establishment, production date, received item, equipment, received quantity, number of defects, product weight / piece, runner weight / piece, number of restarts, purge amount, total resin amount, standard resin amount, and yield rate. The withdrawal detail 402 has fields for specifying the withdrawal item, usage amount, and standard usage amount for each line. When the registration button (not shown) is pressed, production performance data corresponding to the input (display) contents on the screen is registered in the memory unit 106.

[0051] The operator inputs the manufacturing record number, business establishment, manufacturing date, received item, equipment, received quantity, defective quantity, product weight / piece, runner weight / piece, number of restarts, and purge amount in the main area 401. The total resin amount, standard resin amount, and yield rate are automatically calculated and displayed by the manufacturing record input unit 102a (the operator cannot input these items).

[0052] Here, "Accepted quantity" is the number of completed good products. "Product weight / piece" is the product weight per piece (actual weight). "Runner weight / piece" is the runner weight per piece (actual weight). "Number of restarts" is the number of times the equipment has been restarted. "Purge volume" is unnecessary material in the purging process when restarting operation, etc.

[0053] "Total resin amount" is calculated by (received quantity + defective quantity) x (product weight / piece + runner weight / piece) + purged amount. Standard resin amount is calculated by the total of the standard usage amount in the delivery details. "Yield rate" is calculated by standard resin amount / total resin amount.

[0054] In the payout details 402, the payout items, usage amount, and standard usage amount are automatically calculated and displayed by the production results input unit 102a. For the payout items, the constituent items in the manufacturing configuration master (child) 106b are automatically displayed using the received item as a key. The "usage amount" is calculated from the total resin amount using the composition ratio of the resin used in the manufacturing configuration master (child) 106b. The "standard usage amount" is calculated by the production quantity of the received item (parent) (received quantity + defective quantity) x the constituent quantity in the manufacturing configuration master (child) 106b.

[0055] In the example shown in FIG. 7, in main area 401, the operator enters the manufacturing record number "SZ0001," the business location "XXXXX: XX Factory," the manufacturing date "2022 / 07 / 01," the received item "A001: Product A," the equipment "A: Equipment A," the received quantity "998 pieces," the number of defects "2 pieces," the product weight / piece "30.1 g," the runner weight / piece "0.9 g," the number of restarts "3 times," and the purge amount "320 g."

[0056] In the payout details 402, the payout items are automatically displayed as component items "B001: Resin A" and "B002: Resin B" of the manufacturing configuration master (child) 106b, using the receiving item "A001" as a key. In addition, the base usage amount of the payout item "B001: Resin A" is calculated and automatically displayed as the production quantity of the receiving item "A001" (received quantity "998" + defective quantity "2") x the component quantity "10" of "B001: Resin A" of the manufacturing configuration master (child) 106b = 10,000. In addition, the base usage amount of the payout item "B002: Resin B" is calculated and automatically displayed as the production quantity of the receiving item "A001" (received quantity "998" + defective quantity "2") x the component quantity "20" of "B002: Resin B" of the manufacturing configuration master (child) 106b = 20,000.

[0057] The synthetic resin amount in the main area 401 is calculated and automatically displayed as follows: (received quantity "998" + defective quantity "2") x (product weight / unit "30.1g" + runner weight / unit "0.9g") + purged amount "320g" = 31.320g. The usage amount of the payout item "B001: Resin A" in the payout details 402 is calculated and automatically displayed as follows: synthetic resin amount "31.320" x composition ratio "10 / (10+20)" of "B001: Resin A" in the manufacturing configuration master (child) 106b = 10.440g. The usage amount of the payout item "B001: Resin A" is calculated and automatically displayed as follows: synthetic resin amount "31.320" x composition ratio "20 / (10+20)" of "B002: Resin B" in the manufacturing configuration master (child) 106b = 20.880g.

[0058] The standard resin amount in the main area 401 is automatically displayed by calculating the total value (10,000 + 20,000) of the standard usage amount in the dispensing details 401. The "yield rate" in the main area 401 is automatically displayed by calculating the standard resin amount "30,000" / total resin amount "31.320" = 0.958.

[0059] When a registration button (not shown) is pressed, manufacturing performance data corresponding to the input (display) contents on the screen is registered.

[0060] 8 is a diagram showing an example of registered manufacturing performance data. The manufacturing performance data includes the following items: manufacturing performance number, manufacturing date, accepted item code, accepted item, total quantity, accepted number, defective number, equipment, product weight / piece (product weight per piece), runner weight / piece (runner weight per piece), number of restarts, purging amount, total resin amount, reference resin amount, and yield rate.

[0061] (T3: Yield analysis processing) A specific example of the yield analysis process will be described with reference to Fig. 9 and Fig. 10. The yield analysis processing unit 102b creates a yield statement by product or by equipment and product based on the manufacturing performance data in response to an operation by an operator on a yield analysis screen displayed on the monitor 114, for example, and displays and registers it in the storage unit 106.

[0062] In the product-specific yield statement, the manufacturing performance data is compiled for each product for the current month. Figure 9 is a diagram showing an example of a product-specific yield statement. Figure 9 shows the case where it is created based on the manufacturing performance data in Figure 8.

[0063] As shown in Figure 9, the yield calculation sheet by product includes the following fields: received item code, received item, total quantity, number of received items, number of defects, defect rate, equipment code, equipment, product weight per unit, base (standard) product weight, variance (variance) product weight, runner weight per unit, base (standard) runner weight, variance (variance) runner weight, number of restarts, purge amount, base (standard) purge amount, variance (variance) purge amount, total resin amount, base resin amount, variance (variance) resin usage, yield rate, base (standard), yield rate, and variance (variance) yield rate.

[0064] "Accepted item code" is obtained from the manufacturing performance data. Accepted items are obtained from the manufacturing performance data. "Total quantity" is the total number of acceptances in the manufacturing performance data + the total number of defects. "Accepted number" is the total number of acceptances in the manufacturing performance data. "Number of defects" is the total number of defects in the manufacturing performance data. "Defect rate" is calculated by dividing the total number of acceptances by the total number of defects. "Equipment code" is obtained from the manufacturing performance data (displayed when sorted by equipment). "Equipment" is obtained from the manufacturing performance data (displayed when sorted by equipment).

[0065] "Product weight per unit" is obtained from the product weight / unit in the production performance data. "Reference) product weight" is obtained from the total number of configurations in production configuration master (child) 106b. "Difference) product weight" is calculated by "product weight per unit" - "Reference) product weight". "Runner weight per unit" is obtained from the runner weight / unit in the production performance data. "Reference) runner weight" is obtained from the runner weight in production configuration master (parent) 106a. "Difference) runner weight" is calculated by "runner weight per unit" - "Reference) runner weight". "Number of restarts" is the total number of restarts in the production performance data.

[0066] "Purge amount" is the total of the purge amounts in the manufacturing performance data. "Reference purge amount" is calculated by multiplying the reference purge amount for each equipment in the equipment master 106d by the number of restarts in the manufacturing performance data. In the example of FIG. 9, it is 100 x 3 + 90 x 1 + 90 x 0 + 100 x 4 = 790. "Difference) purge amount" is calculated by subtracting "reference purge amount."

[0067] "Total resin amount" is the total resin amount of the manufacturing performance data. "Reference resin amount" is the sum of the reference resin amounts of the manufacturing performance data. "Difference) resin usage amount" is calculated by "total resin amount" - "reference resin amount." "Yield rate" is calculated by "reference resin amount" / "total resin amount." "Reference (yield rate)" obtains the yield rate linked to the incoming item in the manufacturing configuration master (parent) 106a. "Difference) yield rate" is calculated by "yield rate" - "reference (yield rate)."

[0068] The yield statement by equipment and product tally up the current month's production performance data by equipment and product. It is possible to check not only the current month's totals by product, but also the status of each piece of equipment. By checking each piece of equipment and checking the maintenance information, it is possible to confirm and judge which equipment is producing efficiently and whether performance is declining.

[0069] Fig. 10 is a diagram showing an example of a yield statement for equipment-product analysis. Fig. 10 shows a case where the statement is created based on the manufacturing performance data in Fig. 8.

[0070] As shown in Figure 10, the yield calculation sheet by equipment and product has the following fields: equipment code, equipment name, installation date, maintenance date, standard purge amount (standard purge amount in equipment master 106d), accepted item code, accepted item, total quantity, accepted number, number of defects, defect rate, equipment code, equipment, product weight per unit, standard product weight, variance product weight, runner weight per unit, standard runner weight, variance runner weight, number of restarts, purge amount, standard purge amount, variance purge amount, total resin amount, standard resin amount, variance resin usage, yield rate, standard, yield rate, variance yield rate.

[0071] In the example shown in the figure, equipment A has a higher number of restarts than equipment B (equipment A restarts "7 + 9", equipment B restarts "1 + 2"), and a lot of defective material is generated during the purging process (equipment A purge volume "700 + 980", equipment B purge volume "90 + 180"). The defect rates are also high (Equipment A's defect rates are 0.4%, 0.7%, Equipment B's defect rates are 0.2%, 0.1%). As such, Equipment A has a worse yield than Equipment B (Equipment A's yield rates are 0.956, 0.884%, Equipment B's yield rates are 0.964, 0.905%). For this reason, it can be predicted that Equipment A's performance is declining. In this way, equipment-product specific yield calculations can be used when inspecting equipment and considering repurchasing, etc.

[0072] As described above, according to this embodiment, when the parent item, which is the product, one or more resins, which are materials for molding the parent item, and the constituent number of each resin are registered in association with each other in the master, and the manufacturing record number, manufacturing date, received item, which is the product, order number, number of defects, product weight per unit, runner weight per unit, and purge amount are specified in response to the operator's operation on the manufacturing record input screen, the total resin amount is calculated by (received number + number of defects) x (product weight per unit + runner weight per unit) + purge amount, the standard resin amount is calculated for each resin obtained from the master using the received item as a key, as the sum of the standard usage amounts calculated by (received number + number of defects) x the constituent number of the resin in the master, and the yield rate is calculated by the standard resin amount / the total resin amount. Therefore, when a product is molded from resin using a molding machine, it is possible to calculate the yield rate with high accuracy by taking into account the consumption amount of the portion that will be discarded in addition to the finished product.

[0073] [4. Contribution to the United Nations-led Sustainable Development Goals (SDGs)] This embodiment can contribute to improving business efficiency and promoting appropriate management decisions by companies, thereby contributing to goals 8 and 9 of the SDGs.

[0074] Furthermore, this embodiment can contribute to reducing waste and promoting paperless and electronic systems, thereby contributing to the achievement of SDGs Goals 12, 13, and 15.

[0075] Furthermore, this embodiment can contribute to strengthening control and governance, making it possible to contribute to Goal 16 of the SDGs.

[0076] 5. Other embodiments The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.

[0077] For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using known methods.

[0078] In addition, the processing procedures, control procedures, specific names, information including parameters such as registered data and search conditions for each process, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.

[0079] Moreover, with regard to the yield calculation device 100, each of the components shown in the figures is a functional concept, and does not necessarily have to be physically configured as shown in the figures.

[0080] For example, the processing functions of the yield calculation device 100, particularly the processing functions performed by the control unit 102, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded in a non-transient computer-readable recording medium that includes programmed instructions for causing the information processing device to execute the processes described in this embodiment, and is mechanically read by the yield calculation device 100 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive). This computer program is executed by being loaded into a RAM, and cooperates with the CPU to form a control unit.

[0081] In addition, this computer program may be stored in an application program server connected to the yield calculation device 100 via any network, and it is also possible to download all or part of it as needed.

[0082] In addition, the program for executing the process described in this embodiment may be stored in a non-transient computer-readable recording medium, or may be configured as a program product. Here, the "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.

[0083] Moreover, a "program" is a data processing method written in any language or description method, and may be in any form, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration as multiple modules or libraries, and a program that works with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in the embodiments, as well as the installation procedure after reading, may use well-known configurations and procedures.

[0084] The various databases etc. stored in the memory unit 106 are storage means such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files etc. used for various processes and providing websites.

[0085] The yield calculation device 100 may be configured as an information processing device such as a known personal computer or a workstation, or may be configured as the information processing device to which any peripheral device is connected. The yield calculation device 100 may be realized by installing software (including programs or data, etc.) that causes the device to realize the processing described in this embodiment.

[0086] Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the drawings, and all or part of them can be functionally or physically distributed and integrated in any unit according to various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively. [Explanation of symbols]

[0087] 100 Yield rate calculation device 102 Control section 102a Manufacturing performance input section 102b Yield analysis processing section 102c Master Maintenance Department 102d Screen display control unit 104 Communication interface section 106 Storage section 106a Manufacturing configuration master (parent) 106b Manufacturing configuration master (child) 106c Item Master 106d Equipment Master 108 Input / Output Interface Section 112 Input Devices 114 Output Device 200 Servers 300 Network

Claims

1. A yield rate calculation device including a control unit, the yield rate being calculated when a product is molded from resin using a molding machine, The control unit is The system is configured to be able to access a master that associates and registers a parent item, which is a product, one or more resins that are materials for molding the parent item, and the number of components of each resin, a production history input means for inputting a production history number, a production date, an accepted product, an order number, a number of defects, a product weight per unit, a runner weight per unit, and a purge amount in response to an operator's operation on a production history input screen; a total resin amount is calculated as (accepted number + number of defects) x (product weight per unit + runner weight per unit) + purge amount; a standard resin amount is calculated as the sum of standard usage amounts calculated for each resin obtained from the master using the accepted item as a key, by (accepted number + number of defects) x the number of components of that resin in the master; and a yield rate is calculated as standard resin amount / total resin amount.

2. 2. The yield calculation device according to claim 1, wherein the production performance input means registers production performance data including a production performance number, a production date, an accepted item, a total quantity, an accepted number, a defective number, equipment, a product weight per unit, a runner weight per unit, a number of restarts, a purging amount, a total resin amount, and a reference resin amount in a storage area.

3. The control unit further 3. The yield calculation device according to claim 2, further comprising a yield analysis means for preparing a product-by-product yield statement that sums up said production performance data for each product for the current month.

4. The control unit further 3. The yield calculation device according to claim 2, further comprising a yield analysis means for preparing a facility-by-product yield statement that aggregates the manufacturing performance data for each facility and each product for the current month.

5. A yield rate calculation method executed by an information processing device having a control unit, The control unit is The system is configured to be able to access a master that associates and registers a parent item, which is a product, one or more resins that are materials for molding the parent item, and the number of components of each resin, Executed in the control unit: a manufacturing history input step of calculating a yield rate by specifying a manufacturing history number, manufacturing date, accepted product item, order quantity, number of defects, product weight per unit, runner weight per unit, and purge amount in response to an operator's operation on a manufacturing history input screen, calculating a total resin amount as (accepted quantity + number of defects) x (product weight per unit + runner weight per unit) + purge amount, calculating a standard resin amount as the sum of standard usage amounts calculated for each resin obtained from the master using the accepted item as a key, the standard usage amount being calculated as (accepted quantity + number of defects) x the number of components of that resin in the master, and calculating a yield rate as the standard resin amount / total resin amount.

6. A yield rate calculation program to be executed by an information processing device having a control unit, The control unit is The system is configured to be able to access a master that associates and registers a parent item, which is a product, one or more resins that are materials for molding the parent item, and the number of components of each resin, In the control unit, A yield calculation program for causing a computer to execute a manufacturing performance input process in which, when a manufacturing performance number, manufacturing date, accepted item which is the product, order quantity, number of defects, product weight per unit, runner weight per unit, and purge amount are specified in response to an operator's operation on a manufacturing performance input screen, the program calculates a total resin amount as (accepted quantity + number of defects) x (product weight per unit + runner weight per unit) + purge amount, calculates a standard resin amount as the sum of standard usage amounts calculated for each resin obtained from the master using the accepted item as a key, by (accepted quantity + number of defects) x the number of components of that resin in the master, and calculates a yield rate as standard resin amount / total resin amount.

Citation Information

Patent Citations

  • Yield analyzer and yield analytical method

    JP2005277290A