Roof wall material and installation method of roof wall material

The roof wall material system allows for outdoor installation, maintaining indoor operations by using a base material with sandwiching plates secured by bolts and nuts, addressing the need for uninterrupted indoor activities during repairs.

JP2024148760AInactive Publication Date: 2024-10-18MITSUBISHI HEAVY IND LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023062163
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-06
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 2024148760000001_ABST
    Figure 2024148760000001_ABST
Patent Text Reader

Abstract

To provide roof wall material and an installation method of the roof wall material eliminating removal of indoor facilities and the like upon work and capable of operating the indoor facilities during a work period.SOLUTION: The roof wall material is provided with: a plate-like substrate; a first sandwich plate sandwiching a part of a roof between the substrate and itself, which is installed on a first end part at one side in a specific direction of a first surface of the substrate, and connected on the substrate with a first bolt and a first nut; and a second sandwich plate sandwiching a part of a surrounding roof between the substrate and itself, installed on a second end part side of the other side in a specific direction of a second surface of a rear surface side of the first surface of the substrate apart from the second end part and connected on the substrate with a second bolt and a second nut.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] FIELD OF THE DISCLOSURE The present disclosure relates to roofing and wall coverings and methods of installing roofing and wall coverings. [Background technology]

[0002] 2. Description of the Related Art When repairing the roof of a building such as a factory or warehouse, a configuration is known in which metal fittings are attached, for example, inside the building so as to eliminate the need for erecting large-scale scaffolding (see, for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent No. 6647011 Summary of the Invention [Problem to be solved by the invention]

[0004] In the technology of Patent Document 1, since it is not possible to directly approach the vicinity of the roof from inside the building, it is necessary to place, for example, a high-altitude work vehicle or a lifter inside the building. In this case, it is necessary to remove indoor equipment and materials, and the indoor equipment cannot be operated during the work period.

[0005] The present disclosure has been made in consideration of the above, and aims to provide a roof / wall material and a method for setting the roof / wall material that enables indoor equipment to be operated during work without the need to remove indoor equipment when work is performed. [Means for solving the problem]

[0006] The roof wall material of the present disclosure comprises a plate-shaped base material, a first clamping plate arranged at a first end on one side of a first surface of the base material in a predetermined direction and connected to the base material by a first bolt and a first nut, and clamping a portion of the roof between the base material and the first clamping plate, and a second clamping plate arranged at a distance from the second end on the other side of the predetermined direction on a second surface, which is the back side of the first surface of the base material, and connected to the base material by a second bolt and a second nut, and clamping a portion of the surrounding roof between the base material and the first clamping plate.

[0007] The method of installing a roof / wall material according to the present disclosure is a method of installing the above-mentioned roof / wall material, and includes an opening forming step of forming an opening in a portion of the roof where the roof / wall material is to be installed, an upper clamping step of placing the first end of the base material on the underside of an upper end edge of the opening in the roof and placing the first clamping plate on the upper side of the upper end edge to clamp the upper end edge between the base material and the first clamping plate, and a step of clamping the base material against the opening while the upper end edge is clamped. and a fixing step of fixing the base to the roof by fastening the first bolt and the first nut, and the second bolt and the second nut, respectively, with the upper end edge and the lower end edge respectively sandwiched between the base and the second clamping plate. Effect of the Invention

[0008] According to the present disclosure, it is possible to provide a roof / wall material and a method for setting the roof / wall material that eliminates the need to remove indoor equipment when performing work and allows indoor equipment to be operated during the work period. [Brief description of the drawings]

[0009] [Figure 1] FIG. 1 is a diagram showing an example of a roof / wall material according to this embodiment. [Diagram 2]FIG. 2 is a diagram showing an example of a roof / wall material according to this embodiment. [Diagram 3] FIG. 3 is a diagram showing an example of a roof / wall material according to this embodiment. [Figure 4] FIG. 4 is a flowchart showing an example of a method for installing a roof / wall material according to this embodiment. [Diagram 5] FIG. 5 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 6] FIG. 6 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 7] FIG. 7 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 8] FIG. 8 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 9] FIG. 9 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 10] FIG. 10 is a process diagram showing an example of a method for installing a roof / wall material. [Figure 11] FIG. 11 is a diagram showing an example of a jig used in the method for installing a roof / wall material. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] Hereinafter, an embodiment of the roof / wall material and the installation method of the roof / wall material according to the present disclosure will be described with reference to the drawings. Note that the present invention is not limited to this embodiment. In addition, the components in the following embodiments include those that are replaceable and easy for a person skilled in the art, or those that are substantially the same.

[0011] Figures 1 to 3 are diagrams showing an example of a roof / wall material according to this embodiment. Figure 1 is a plan view, Figure 2 is an AA cross-sectional view in Figure 1, and Figure 3 is a BB cross-sectional view in Figure 1. The roof / wall material 100 shown in Figures 1 to 3 is used as a replacement roof / wall material when repairing the roof of a building such as a factory or warehouse. The roof / wall material 100 according to this embodiment is used, for example, as a member corresponding to a skylight on a roof.

[0012] As shown in FIGS. 1 to 3, a roof / wall material 100 includes a base material 10, an upper sandwiching plate (first sandwiching plate) 20, and a lower sandwiching plate (second sandwiching plate) 30.

[0013] The substrate 10 is a flat rectangular plate. The substrate 10 is formed using a light-transmitting material such as a resin material. For example, a corrugated sheet is used as the substrate 10. As shown in FIG. 3, the substrate 10 is formed with curved concave and convex portions arranged alternately. The concave and convex portions extend along a predetermined direction D. In this embodiment, when the substrate 10 is attached to a roof, one side of the predetermined direction D is used as the upper side, and the other side of the predetermined direction D is used as the lower side.

[0014] The upper sandwiching plate 20 is disposed on one side of the first surface 11 of the base material 10 in the predetermined direction D, i.e., on the upper first end portion 13. The upper sandwiching plate 20 has a flat rectangular plate shape. The upper sandwiching plate 20 is formed using a light-transmitting material such as a resin material.

[0015] The upper clamping plate 20 is connected to the base material 10 by a first bolt 41a and a first nut 41b. Before being attached to the roof, the first bolt 41a and the first nut 41b are arranged in a loose state. This allows the upper clamping plate 20 to move along the first bolt 41a in a direction toward and away from the base material 10. Note that by fastening the first bolt 41a and the first nut 41b, the upper clamping plate 20 can clamp a part of the roof between itself and the base material 10.

[0016] The lower sandwiching plate 30 is disposed on the other side of the second surface 12 of the base material 10 in the predetermined direction D, i.e., on the lower second end 14 side, with a gap between the second end 14 and the second end 14. The lower sandwiching plate 30 is a flat rectangular plate. The lower sandwiching plate 30 is formed using a light-transmitting material such as a resin material. The dimension of the lower sandwiching plate 30 in the predetermined direction D is smaller than that of the upper sandwiching plate 20.

[0017] The lower clamping plate 30 is connected to the base material 10 by the second bolt 42a and the second nut 42b. Before being attached to the roof, the second bolt 42a and the second nut 42b are arranged in a loose state. This allows the lower clamping plate 30 to move downward in the direction of gravity along the second bolt 42a when being attached to the roof. Note that by fastening the second bolt 42a and the second nut 42b, the lower clamping plate 30 can clamp a part of the roof between itself and the base material 10.

[0018] Furthermore, the distance L1 in the specified direction D from the first end 13 of the base material 10 to the first bolt 41a and the first nut 41b is greater than the distance L2 in the specified direction D from the second end 14 to the second bolt 42a and the second nut 42b.

[0019] Next, a method for installing the roof / wall material 100 configured as described above on a roof will be described. Fig. 4 is a flow chart showing an example of the method for installing the roof / wall material according to this embodiment. As shown in Fig. 4, the method for installing the roof / wall material includes an opening forming step S10, an upper clamping step S20, a lower clamping step S30, and a fixing step S40.

[0020] Figures 5 to 10 are process diagrams showing an example of a method for installing a roof / wall material. Figure 7 shows the state shown in Figure 6 as viewed from diagonally above. Figure 11 is a diagram showing an example of a jig used in the method for installing a roof / wall material.

[0021] In the opening formation step S10, as shown in Fig. 5, a high-altitude work vehicle is positioned close to the roof 50. A worker forms an opening 52 in a portion of the roof 50 where the roof wall material 100 is to be installed. For example, the worker cuts the periphery of a skylight 51 in the roof 50 with a tool or the like, and drops the skylight 51 and its surrounding portion indoors. A net or the like is placed indoors in advance to catch the skylight 51 and its surrounding portion that falls.

[0022] After the opening 52 is formed, the upper clamping step S20 and subsequent steps are performed using the above-mentioned roof wall material 100. Note that, before the roof wall material 100 is attached, the first bolt 41a and the first nut 41b are screwed together in a loosened state, and the second bolt 42a and the second nut 42b are screwed together in a loosened state.

[0023] In the upper clamping step S20, since the first bolt 41a and the first nut 41b are in a loose state as described above, the upper clamping plate 20 is in a state where it can be moved upward from the base material 10.

[0024] In the upper clamping step S20, first, as shown in Fig. 6 and Fig. 7, a jig 60 is inserted between the base material 10 and the upper clamping plate 20 to ensure a gap between the base material 10 and the upper clamping plate 20. As shown in Fig. 11, the jig 60 has a handle portion 61 that is held by a worker, and a claw portion 62 that holds the roof wall material 100. The claw portion 62 has a plurality of first rod-shaped portions 62a, a plurality of second rod-shaped portions 62b, and a connecting portion 62c.

[0025] The first rod-shaped portions 62a and the second rod-shaped portions 62b are formed to extend along the uneven portions of the corrugated plate. The first rod-shaped portions 62a and the second rod-shaped portions 62b are inserted between the base material 10 and the upper sandwiching plate 20. The first rod-shaped portions 62a and the second rod-shaped portions 62b are arranged at intervals in a direction perpendicular to the longitudinal direction. In other words, an imaginary plane including the first rod-shaped portions 62a and an imaginary plane including the second rod-shaped portions 62b are arranged at intervals. The first rod-shaped portions 62a have a larger longitudinal dimension (longer length) than the second rod-shaped portions 62b.

[0026] 6 and 7, in the upper clamping step S20, the jig 60 is inserted between the substrate 10 and the upper clamping plate 20, so that the substrate 10 is pressed downward by the first rod-shaped portions 62a and the upper clamping plate 20 is lifted by the second rod-shaped portions 62b. This ensures a gap between the substrate 10 and the upper clamping plate 20.

[0027] With a gap secured between the base material 10 and the upper clamping plate 20, the worker places the base material 10 on the roof 50 as shown in FIG. 8. After that, the worker manipulates the handle 61 so that, for example, the multiple first rod-shaped portions 62a are placed on the underside of the upper end edge portion 53 of the opening 52 of the roof 50, and the multiple second rod-shaped portions 62b are placed on the upper side of the upper end edge portion 53. By this operation, as shown in FIG. 8, the first end portion 13 of the base material 10 of the roof wall material 100 is placed on the underside of the upper end edge portion 53, and the upper clamping plate 20 is placed on the upper side of the upper end edge portion 53. Therefore, a state is formed in which the upper end edge portion 53 is sandwiched between the base material 10 and the upper clamping plate 20. In the upper clamping step S20, the position of the roof / wall material 100 is adjusted so that the second end 14 of the base material 10 is located above the lower end edge 54 of the opening 52 and the lower clamping plate 30 is inserted inside the opening 52. Thereafter, the worker removes the jig 60 from the roof / wall material 100.

[0028] After the upper clamping step S20, the lower clamping step S30 is performed. In the lower clamping step S30, as shown in FIG. 9, the base material 10 is slid downward along the opening 52 with the upper end edge 53 clamped, and the second end 14 of the base material 10 is disposed on the upper surface side of the lower end edge 54 of the opening 52. At this time, the base material 10 is slid downward until the second bolt 42a comes into contact with the lower end edge 54 and the downward movement is restricted. This operation can be performed, for example, by an operator using a jig 60. In this case, the base material 10 can be slid in such a manner that the connecting portion 62c of the jig 60 is engaged with the first nut 41b.

[0029] As described above, since the second bolt 42a and the second nut 42b are in a loose state, in the state after the upper clamping step S20 is performed, the lower clamping plate 30 moves downward in the direction of gravity along the second bolt 42a, and a gap is formed between the lower clamping plate 30 and the second surface 12 of the base material 10. When the base material 10 is slid downward in this state, the base material 10 and the lower clamping plate 30 move together with a gap between them in the vertical direction. As a result, when the base material 10 is placed on the upper surface side of the lower end edge 54, the lower clamping plate 30 is placed on the lower surface side of the lower end edge 54. Therefore, a state in which the lower end edge 54 is clamped between the base material 10 and the lower clamping plate 30 is formed.

[0030] As described above, the distance L1 in the predetermined direction D from the first end 13 of the base material 10 to the first bolt 41a and the first nut 41b is greater than the distance L2 in the predetermined direction D from the second end 14 to the second bolt 42a and the second nut 42b. Therefore, even if the base material 10 is slid downward from a state in which the upper end edge portion 53 is sandwiched between the base material 10 and the upper clamping plate 20, the sandwiched portion does not fall out, and the sandwiched state of the upper end edge portion 53 can be maintained.

[0031] After the lower clamping step S30, a fixing step S40 is performed. In the fixing step S40, as shown in Fig. 10, in a state in which the upper end side edge portion 53 and the lower end side edge portion 54 are clamped, the first bolt 41a and the first nut 41b, and the second bolt 42a and the second nut 42b are fastened, respectively, to fix the base material 10 to the roof 50.

[0032] As described above, according to the first aspect of the present disclosure, a roof wall material 100 is provided, comprising: a plate-shaped base material 10; an upper clamping plate 20 arranged at a first end 13 on one side of a first surface 11 of the base material 10 in a predetermined direction D, connected to the base material 10 by a first bolt 41a and a first nut 41b, and clamping a part of a roof 50 between the base material 10; and a lower clamping plate 30 arranged at a distance from the second end 14 on the other side of the predetermined direction D on a second surface 12, which is the back side of the first surface 11 of the base material 10, at a second end 14, connected to the base material 10 by a second bolt 42a and a second nut 42b, and clamping a part of the surrounding roof 50 between the base material 10.

[0033] According to this configuration, the roof wall material 100 can be fixed to the roof 50 by fastening the first bolt 41a and the first nut 41b and the second bolt 42a and the second nut 42b in a state where a part of the roof 50 is sandwiched between the base material 10 and the upper sandwiching plate 20, and a part of the roof 50 is sandwiched between the base material 10 and the lower sandwiching plate 30. Therefore, it is not necessary to perform the work from inside the building, and it is possible to perform the work outdoors, for example. Therefore, it is not necessary to remove indoor equipment when performing the work, and it is possible to operate the indoor equipment during the work period.

[0034] According to the second aspect of the present disclosure, in the roof / wall material 100 relating to the first aspect, corrugated sheets are used as the base material 10, the upper sandwiching plate 20 and the lower sandwiching plate 30.

[0035] According to this configuration, when repairing the roof 50 formed of corrugated sheets, the roof / wall material 100 can be appropriately positioned.

[0036] According to the third aspect of the present disclosure, in the roof wall material 100 relating to the first or second aspect, the upper clamping plate 20 has a larger dimension in the specified direction D than the lower clamping plate 30, and the distance L1 in the specified direction D from the first end 13 of the base material 10 to the first bolt 41a and the first nut 41b is larger than the distance L2 in the specified direction D from the second end 14 to the second bolt 42a and the second nut 42b.

[0037] According to this configuration, even if the base material 10 is slid downward from a state in which the upper end edge portion 53 is sandwiched between the base material 10 and the upper clamping plate 20, the sandwiched portion does not fall out, and the sandwiched state of the upper end edge portion 53 can be maintained.

[0038] According to the fourth aspect of the present disclosure, in the roof / wall material 100 relating to any one of the first to third aspects, the base material 10, the upper sandwiching plate 20 and the lower sandwiching plate 30 are light-transmitting.

[0039] According to this configuration, the roof / wall material 100 can be used as a light transmitting portion such as a skylight on the roof 50.

[0040] According to a fifth aspect of the present disclosure, there is provided a method for installing a roof wall material 100 according to any one of the first to fourth aspects on a roof 50, the method including an opening formation step S10 for forming an opening in a portion of the roof 50 where the roof wall material 100 is to be installed, an upper clamping step S20 for placing a first end 13 of a base material 10 on the underside of an upper end edge of the opening in the roof 50 and placing an upper clamping plate 20 on the upper side of the upper end edge to clamp the upper end edge between the base material 10 and the upper clamping plate 20, and a step S21 for clamping the base material 10 with the upper end edge clamped. a lower clamping step S30 in which a second end 14 of the base material 10 is positioned on the upper side of the lower edge of the opening by sliding the lower clamping plate 30 downward along the opening, and the lower clamping plate 30 is positioned on the underside of the lower edge to clamp the lower edge between the base material 10 and the lower clamping plate 30, and a fixing step S40 in which, with the upper edge and the lower edge respectively clamped, a first bolt 41a and a first nut 41b, and a second bolt 42a and a second nut 42b are respectively tightened to fix the base material 10 to the roof 50.

[0041] According to this configuration, an opening 52 is formed in a portion where the roof wall material 100 is to be installed, a first end 13 of the base material 10 is disposed on the underside of an upper edge 53 of the opening 52, an upper clamping plate 20 is disposed on the upper side of the upper edge 53, and the upper edge 53 is sandwiched between the base material 10 and the upper clamping plate 20. With the upper edge 53 sandwiched, the base material 10 is slid downward along the opening 52, whereby a second end 13 of the base material 10 is disposed on the upper side of a lower edge 54 of the opening 52. 4 is placed, the lower clamping plate 30 is placed on the underside of the lower edge 54, and the lower edge 54 is clamped between the base material 10 and the lower clamping plate 30, and the first bolt 41a and the first nut 41b, and the second bolt 42a and the second nut 42b are fastened in a state in which the upper edge 53 and the lower edge 54 are clamped, respectively, to fix the base material 10 to the roof 50. Therefore, the roof wall material 100 can be appropriately installed on the roof 50 from outdoors without forming scaffolding, etc. This makes it possible to operate the indoor equipment during the work period without the need to remove indoor equipment, etc. when performing the work.

[0042] According to a sixth aspect of the present disclosure, in the roof wall material installation method relating to the fifth aspect, in the upper clamping process S20, the first bolt 41a and the first nut 41b are loosened so that the upper clamping plate 20 is capable of moving upward from the base material 10.

[0043] According to this configuration, in the upper clamping step S20, the upper clamping plate 20 can be moved upward from the base material 10. Therefore, the upper end edge portion 53 can be easily clamped between the base material 10 and the upper clamping plate 20.

[0044] According to the seventh aspect of the present disclosure, in the roof wall material installation method relating to the fifth or sixth aspect, in the upper clamping step S20, a jig 60 is inserted between the base material 10 and the upper clamping plate 20 to ensure a gap between the base material 10 and the upper clamping plate 20.

[0045] According to this configuration, by using the jig 60, the upper end edge portion 53 can be easily sandwiched between the base material 10 and the upper clamping plate 20.

[0046] According to an eighth aspect of the present disclosure, in the method for installing a roof wall material according to the seventh aspect, corrugated sheets are used as the base material 10, the upper clamping plate 20 and the lower clamping plate 30, and the jig 60 has a handle portion 61 that is held by an operator and a claw portion 62 that is provided on the handle portion 61 and holds the roof wall material 100. The claw portion 62 is formed to extend along the uneven portions of the corrugated sheets and has a plurality of first rod-shaped members that are inserted between the base material 10 and the upper clamping plate 20. The multiple first rod-shaped portions 62a and the multiple second rod-shaped portions 62b are arranged at intervals in a direction perpendicular to the longitudinal direction, and in the upper clamping process S20, the jig 60 presses the substrate 10 downward with the multiple first rod-shaped portions 62a and lifts the upper clamping plate 20 with the multiple second rod-shaped portions 62b, thereby securing a gap between the substrate 10 and the upper clamping plate 20.

[0047] According to this configuration, the jig 60 presses the substrate 10 downward with the multiple first rod-shaped portions 62a and lifts the upper clamping plate 20 with the multiple second rod-shaped portions 62b, thereby ensuring a gap between the substrate 10 and the upper clamping plate 20, so that the upper edge portion 53 can be easily clamped between the substrate 10 and the upper clamping plate 20.

[0048] According to the ninth aspect of the present disclosure, in the roof wall material installation method relating to the fifth to eighth aspects, in the lower clamping process S30, the second bolt 42a and the second nut 42b are loosened so that the lower clamping plate 30 is moved downwardly away from the base material 10 by gravity.

[0049] According to this configuration, after the upper clamping step S20, the lower clamping plate 30 moves downward in the direction of gravity along the second bolt 42a, and a gap is formed between the lower clamping plate 30 and the second surface 12 of the base material 10. When the base material 10 is slid downward in this state, the base material 10 and the lower clamping plate 30 move together with a gap between them in the vertical direction. As a result, when the base material 10 is placed on the upper surface side of the lower end edge 54, the lower clamping plate 30 is placed on the lower surface side of the lower end edge 54. Therefore, the base material 10 and the lower clamping plate 30 can easily clamp the lower end edge 54.

[0050] The technical scope of the present invention is not limited to the above embodiment, and can be modified as appropriate without departing from the spirit of the present invention. For example, in the above embodiment, the base material 10, the upper clamping plate 20, and the lower clamping plate 30 are corrugated, but the present invention is not limited to this configuration. The base material 10, the upper clamping plate 20, and the lower clamping plate 30 may be in other shapes, such as flat plates. [Explanation of symbols]

[0051] 10 Base material 11 Page 1 12 Side 2 13 First end 14 Second end 20 Upper clamp plate 30 Lower clamp plate 41a First bolt 41b First nut 42a Second bolt 42b Second Nut 50 Roof 51 Skylight 52 Opening 53 Upper edge 54 Lower edge 60 Jig 61 Handle 62 Claw part 62a First rod-shaped part 62b Second rod-shaped part 62c connection part 100 Roof and wall materials D Specified direction L1,L2 distance S10 Opening formation process S20 Upper clamping process S30 Lower clamping process S40 Fixed process

Claims

1. A plate-shaped substrate; a first clamping plate that is disposed at a first end portion on one side of a first surface of the base material in a predetermined direction, is connected to the base material by a first bolt and a first nut, and clamps a portion of the roof between the base material and the first clamping plate; a second clamping plate that is disposed on a second end side of a second surface, which is a back side of the first surface of the base material, on the other side in the predetermined direction, with a gap between the second end and the second end, and is connected to the base material by a second bolt and a second nut, and clamps a portion of the surrounding roof between the base material and the second clamping plate; A roof and wall material comprising:

2. Corrugated sheets are used as the base material, the first sandwiching plate, and the second sandwiching plate. The roof and wall material according to claim 1.

3. The first clamping plate has a larger dimension in the predetermined direction than the second clamping plate, A distance in the predetermined direction from the first end to the first bolt and the first nut is greater than a distance in the predetermined direction from the second end to the second bolt and the second nut. The roof and wall material according to claim 1.

4. The base material, the first sandwiching plate, and the second sandwiching plate are light-transmitting. The roof and wall material according to claim 1.

5. A method for installing the roof / wall material according to any one of claims 1 to 4 on a roof, comprising: An opening forming process for forming an opening in a portion of the roof where the roof wall material is to be installed; an upper clamping step of placing the first end of the base material on the underside of an upper edge of the opening of the roof, and placing the first clamping plate on the upper side of the upper edge, and clamping the upper edge between the base material and the first clamping plate; a lower clamping step of sandwiching the lower edge between the base material and the second clamping plate by sliding the base material downward along the opening while sandwiching the upper edge, thereby arranging the second end of the base material on the upper surface side of the lower edge of the opening and disposing the second clamping plate on the lower surface side of the lower edge; a fixing process of fastening the first bolt and the first nut, and the second bolt and the second nut, respectively, in a state in which the upper end side edge portion and the lower end side edge portion are sandwiched between the first bolt and the first nut, and fixing the base material to the roof; A method for installing roof and wall materials, including:

6. In the upper clamping step, the first bolt and the first nut are loosened to allow the first clamping plate to move upward from the base material. A method for installing the roof / wall material according to claim 5.

7. In the upper clamping step, a jig is inserted between the base material and the first clamping plate to ensure a gap between the base material and the first clamping plate. A method for installing the roof / wall material according to claim 5.

8. Corrugated plates are used as the base material, the first sandwiching plate, and the second sandwiching plate, The jig is The roof wall material is supported by a handle portion that is held by a worker, and a claw portion that is provided on the handle portion and that holds the roof wall material. The claw portion has a plurality of first rod-shaped portions and a plurality of second rod-shaped portions that are formed to extend along the uneven portions of the corrugated plate and are inserted between the base material and the first clamping plate, The first rod-shaped portions and the second rod-shaped portions are spaced apart in a direction perpendicular to the longitudinal direction, In the upper clamping step, the jig presses the base material downward with the first rod-shaped portions and lifts the first clamping plate with the second rod-shaped portions, thereby securing a gap between the base material and the first clamping plate. A method for installing the roof / wall material according to claim 7.

9. In the lower clamping step, the second bolt and the second nut are loosened so that the second clamping plate is moved downwardly away from the base material by gravity. A method for installing the roof / wall material according to claim 5.