Elevator for construction and counterweight device

The construction elevator addresses the weight reduction issue by placing the extra winding drum on the opposite side of the wire, using frames with cushioning material and rollers, maintaining stability and efficiency while extending lifting height.

JP2024152448APending Publication Date: 2024-10-25SHIMIZU CORP +2
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023066649
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-14
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

Conventional construction elevators face a reduction in loadable weight due to the weight of the extra winding drum when extending the lifting height, as the excess wire is wound around it, which can exceed 1 ton, limiting the weight that can be carried.

Method used

The construction elevator design includes an extra winding drum part arranged on the other side of the wire, with a weight part and frames connected via a cushioning material, allowing the weight of the extra winding drum to be offset, and the frames are guided by rollers along a guide rail to stabilize and prevent contact with surrounding members.

Benefits of technology

This design prevents a reduction in loadable weight by offsetting the extra winding drum's weight, maintains a compact cross-sectional shape, and reduces vibrations and contact risks, enhancing stability and work efficiency by allowing the extra winding drum to be positioned below the weight section.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024152448000001_ABST
    Figure 2024152448000001_ABST
Patent Text Reader

Abstract

To provide an elevator for a construction and a counterweight device capable of improving a loadable weight of a carrier part.SOLUTION: An elevator 10 for a construction comprises a mast part 11 capable of extending a lift, a carrier part 12 and a weight part 13 arranged vertically movably on the side of the mast part 11, a wire rope 15 supported by the top sheave 14 of the mast part 11, and connected by the carrier part 12 on its one side and connected by the weight part 13 via the top sheave 14 on its other side, a driving part 16 provided on the carrier part 12 and to drive up / down the carrier 12, and a dead turn drum part 17 to wrap the excess part of the wire rope 15 to house it. The dead turn drum part 17 is arranged on the other side of the wire rope 15 together with the weight part 13.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction elevator and counterweight device. [Background technology]

[0002] There are known construction elevators that can extend the lifting height of the mast section. For example, the following Patent Document 1 proposes a construction elevator in which a carriage section that can be raised and lowered by a guide rail and a counterweight are connected by a wire, and the wire is fixed by winding a part of the wire around a surplus winding drum on the carriage section, and the carriage section side of the wire is connected to the carriage section via a tail attachment means. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 11-189381 Summary of the Invention [Problem to be solved by the invention]

[0004] However, in construction elevators that can extend the lift of the mast, the surplus wire is stored by winding it around a surplus winding drum. The wound wire includes the length required to extend the lift of the mast, so when constructing a high-rise building, the weight increases, and the wound wire can sometimes exceed 1 ton. However, in conventional construction elevators, the extra winding drum is loaded on the carrier, which has the problem that the load capacity of the carrier is reduced by the weight of the extra winding drum with the wire wound around it.

[0005] The present invention has been made in consideration of the above circumstances, and an object of the present invention is to provide a construction elevator and a counterweight device that can increase the load capacity of the carrier section. [Means for solving the problem]

[0006] The construction elevator of the present invention, which solves the above problems, is a construction elevator that includes a mast section capable of extending its lift, a carriage section and a weight section arranged to be raised and lowered relative to the mast section, a wire supported by the top sheave section of the mast section, with the carriage section connected to one side and the weight section connected to the other side via the top sheave section, a drive section provided on the carriage section for driving the carriage section to rise and fall, and an excess winding drum section for winding and storing the excess of the wire, wherein the excess winding drum section is arranged on the other side of the wire together with the weight section, the mast section has a guide rail extending vertically, the weight section has a first frame that rises and falls along the guide rail and a weight block fixed to the first frame, the excess winding drum section has a second frame that rises and falls along the guide rail and an excess winding drum fixed to the second frame, and the first frame and the second frame are connected vertically via a buffer material.

[0007] According to the construction elevator of the present invention, the excess winding drum, which winds and stores the excess wire, is disposed on the other side of the wire together with the weight section, so the weight of the excess winding drum is not a load on the carrier section. Therefore, it is possible to prevent the weight of the excess winding drum from reducing the loadable weight, and it is possible to increase the loadable weight of the carrier section. In addition, even if the weight section and the extra winding drum section are arranged on the other side of the wire, the cross-sectional shape can be kept small by arranging the weight section and the extra winding drum section one above the other, and they can be raised and lowered as a unit. Therefore, even if the arrangement space around the mast section is limited by the carrier section and the work object, the weight section and the extra winding drum section can be arranged on the other side of the wire. Furthermore, because the first and second frames are connected via a shock absorber, even if a lateral force acts on the weight section and causes vibration when climbing over uneven steps in the guide rails during lifting and lowering, the force is attenuated by the shock absorber and is not easily transmitted to the extra winding drum section. This makes it possible to prevent vibration from being transmitted to the wire and causing lateral vibration, and also prevents the wire, which is placed in a limited space, from coming into contact with surrounding members or other wires and being damaged.

[0008] In the construction elevator of the present invention, the first frame and the second frame may have a plurality of rollers that roll while sandwiching the guide rail. In this way, the guide rail is clamped by multiple rollers, so the weight section and the extra winding drum section are stably supported by the guide rail, and the distance from the guide rail is unlikely to change during lifting and lowering. Therefore, even if the weight section and the extra winding drum section are arranged in a limited arrangement space, they can be prevented from coming into contact with surrounding members such as the carrier section and the work object during lifting and lowering.

[0009] In the construction elevator of the present invention, the plurality of rollers may be configured so that their arrangement with respect to the first frame and the second frame is adjustable. In this way, the orientation and distance of the weight portion and the surplus winding drum portion relative to the guide rail can be adjusted, making it possible to more reliably prevent contact with surrounding components such as the carrier portion and the work object during lifting and lowering.

[0010] In the construction elevator of the present invention, the first frame and the second frame may be connected to each other so as to be capable of relative displacement in the lateral direction. In this way, since the first frame and the second frame can be displaced relative to each other in the lateral direction, even if a rotational force is generated in the extra winding drum during lifting and lowering, the rotational force is not transmitted from the extra winding drum to the weight part, and the weight part can be stably guided by the guide rail.

[0011] In the construction elevator of the present invention, one or more weight blocks each having a preset total weight may be fixed to the first frame. In this way, since multiple first frames to which the weight blocks are fixed are not connected, problems such as the device position or relative orientation changing between multiple first frames when raised and lowered are eliminated, and the weight section can be stably guided by the guide rails.

[0012] In the construction elevator of the present invention, the second frame may be disposed below the first frame. In this way, since the extra winding drum is disposed below the weight, the extra winding drum can be disposed near the ground when performing climbing work (extending the lifting height) with the extra winding drum and weight lowered to the lowest position. Therefore, scaffolding for adjusting the wire during climbing work is not required, and work efficiency can be improved.

[0013] In the construction elevator of the present invention, the cross-sectional shape of the weight block may have a continuous recess over its entire length, and the wire may be disposed within the recess. In this way, the wire extending upward can be positioned near the center of gravity of the weight block, making it easier to suppress fluctuations in the orientation and inclination of the weight part when it is raised and lowered, and preventing uneven loads from acting on multiple rollers or one-sided contact with the guide rail.

[0014] The counterweight device of the present invention which solves the above-mentioned problems is a counterweight device in which the mast section is configured to be able to extend the lifting height and has a top sheave section, and is connected to one side of a wire to which a carrier section is connected via the top sheave section, and is characterized in that it has an excess winding drum section for winding and storing the excess of the wire, and a weight section connected to the excess winding drum section, and the weight section has a first frame that rises and falls along a guide rail and a weight block fixed to the first frame, and the excess winding drum section has a second frame that rises and falls along the guide rail and a excess winding drum fixed to the second frame, and the first frame and the second frame are connected vertically via a cushioning material. According to the counterweight device of the present invention, it is possible to construct a construction elevator as described above. Effect of the Invention

[0015] According to the construction elevator and counterweight device of the present invention, it is possible to increase the load capacity of the carrier section. [Brief description of the drawings]

[0016] [Figure 1] FIG. 1 is a front view of a construction elevator according to a first embodiment of the present invention. [Diagram 2] FIG. 1 is a side view of a construction elevator according to a first embodiment of the present invention. [Diagram 3] FIG. 1 is a plan view of a construction elevator according to a first embodiment of the present invention. [Figure 4] FIG. 1 is a side view showing a state in which a counterweight device is attached to a construction elevator according to a first embodiment of the present invention. [Diagram 5] FIG. 1 is a front view of a counterweight device for a construction elevator according to a first embodiment of the present invention. [Figure 6] 5 is a cross-sectional view taken along line AA in FIG. 4 of the counterweight device for the construction elevator according to the first embodiment of the present invention. FIG. [Figure 7]1(a) to 1(d) are diagrams illustrating a method for extending the lift of a construction elevator according to a first embodiment of the present invention. [Figure 8] FIG. 11 is a side view showing a state in which a counterweight device for a construction elevator according to a second embodiment of the present invention is attached. [Figure 9] FIG. 11 is a side view showing a counterweight device of a construction elevator according to a modified example of the present invention. [Figure 10] FIG. 11 is a front view showing a construction elevator according to another modified example of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0017] [First embodiment] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. Figures 1 to 3 are a front view, a side view, and a plan view showing a construction elevator of the present embodiment.

[0018] The construction elevator 10 includes a mast section 11, a carriage section 12 and a weight section 13 arranged to be movable up and down on the side of the mast section 11, a wire rope 15 supported by a top sheave section 14 of the mast section 11, with the carriage section 12 connected to one side and the weight section 13 connected to the other side via the top sheave section 14, a drive section 16 provided on the carriage section 12 for driving the carriage section 12 to ascend and descend, and an excess winding drum section 17 for winding and storing an excess of the wire rope 15. In this embodiment, the excess winding drum section 17 is connected to the other side of the wire rope 15 while being connected below the weight section 13, thereby forming a counterweight device 20.

[0019] The mast section 11 is erected on a foundation such as a pit, and has a wall connecting section 21 for connecting to the work object on one side, and a carriage mounting section 22 for mounting the carriage section 12 provided continuously vertically on the opposite side. Although not shown in detail, the carriage mounting section 22 is provided with a guide section and a rack gear over its entire length for guiding the lifting and lowering of the carriage section 12.

[0020] A guide rail 23 for guiding the lifting and lowering of the weight section 13 and the extra winding drum section 17 is provided along the entire length of the side surface of the mast section 11, located between the wall connecting section 21 and the carrier mounting section 22. A top sheave section 14 is provided on the upper section of the mast section 11, and the top sheave section 14 is arranged together with a drive section, a governor, etc. The mast section 11 is configured so that the lifting height can be extended as the construction of the object to be constructed progresses. The method of extending the mast section 11 will be described later.

[0021] The carrier unit 12 includes a lifting frame 25 supported on the carrier mounting unit 22 of the mast unit 11 so as to be able to rise and fall, a cage 26 fixed to the lifting frame 25, a lifting drive unit 16 for lifting and lowering the lifting frame 25, and a wire connecting unit 27 for connecting the wire rope 15 to the lifting frame 25. The drive unit 16 is configured to rotate a pinion meshing with the rack gear of the mast unit 11, thereby lifting and lowering the carrier unit 12 along the rack gear of the mast unit 11. The drive unit 16 is also provided with a braking unit.

[0022] The wire rope 15 connects the carrier section 12 and the weight section 13 via the top sheave section 14, and has a length corresponding to the extension distance to which the lifting height of the mast section 11 is extended until the construction object is completed. In this embodiment, two wire ropes 15 are used on each side.

[0023] 4 to 6 are a front view, a side view and a plan view showing the counterweight device 20 of this embodiment. The counterweight device 20 of this embodiment is configured by vertically connecting an extra winding drum part 17 and a weight part 13.

[0024] The weight section 13 includes a first frame 31 that moves up and down along a guide rail 23 provided on the mast section 11 , and a weight block 32 fixed to the first frame 31 .

[0025] The first frame 31 is provided with a block fixing portion 31 a on which one or more weight blocks 32 can be placed and fixed, and has a lower end connected to the extra winding drum portion 17 .

[0026] A plurality of guide rollers 29 are arranged vertically at intervals on the side surface of the first frame 31 facing the mast section 11. The plurality of guide rollers 29 are arranged to be rollable while sandwiching the guide rail 23 of the mast section 11, and are configured so that their arrangement relative to the first frame 31 is adjustable. By adjusting the arrangement of the guide rollers 29 relative to the first frame 31, it is possible to adjust the distance to each part of the first frame 31 relative to the guide rail 23, the inclination of the first frame 31, etc.

[0027] The weight block 32 in this embodiment has a preset weight based on the weight of the carrier 12 and the weight of the extra winding drum 17. The weight block 32 is arranged so that its horizontal cross-sectional shape has a continuous recess 32a over its entire length. The weight block 32 is formed so that its center of gravity is located within the recess 32a, and the wire rope 15 is located within the recess 32a.

[0028] The extra winding drum section 17 includes a second frame 34 that moves up and down along the guide rail 23, a drum 35 fixed to the second frame 34, and a tail 36 that fixes and connects the wire rope 15.

[0029] The second frame 34 includes a drum mounting section 34a where the drums 35 are arranged vertically, and a wire connecting section 34b where the tail 36 is arranged, with the drum mounting section 34a being arranged on the lower side and the wire connecting section 34b being arranged on the upper side. The width of the second frame 34 in a front view is formed to be the same as the width of the first frame 31 of the weight section 13 in a front view.

[0030] A plurality of guide rollers 29 are arranged at intervals vertically on the side surface of the second frame 34 facing the mast section 11. The plurality of guide rollers 29 are arranged to be rollable while sandwiching the guide rail 23 of the mast section 11, and are configured so that their arrangement relative to the second frame 34 is adjustable. By adjusting the arrangement of the guide rollers 29 relative to the second frame 34, the distance to each part of the second frame 34 relative to the guide rail 23, the inclination of the second frame 34, etc. can be adjusted.

[0031] The second frame 34 is disposed below and connected to the first frame 31. The connecting portion connects the first frame 31 and the second frame 34 to enable displacement such as relative rotation in the lateral direction, and in this embodiment, the first frame 31 is placed on the upper surface of the second frame 34 with a cushioning material 37 made of anti-vibration rubber interposed therebetween to connect them. It is also possible to connect the first frame 31 and the second frame 34 by any connecting means or the like in a state in which they are relatively displaceable so that they do not separate or shift.

[0032] The drum 35 is used to wind and store the excess of the wire rope 15, and in this embodiment, two wire ropes 15 are wound around each of the drums 35. These drums 35 are arranged above and below in the same direction.

[0033] The butt 36 is provided on the upper part of the second frame 34 above the drum 35. The butt 36 is a suspension point that connects the wire rope 15, one side of which is connected to the carrier unit 12, to the surplus winding drum unit 17 of the counterweight device 20. The butt 36 may be a part that fixes the wire rope 15 to the surplus winding drum unit 17 of the counterweight device 20 at a position in the continuous wire rope 15 between the connecting portion between the carrier unit 12 and the counterweight device 20 and the surplus portion wound around the drum 35.

[0034] In the construction elevator 10 configured as described above, the driving unit 16 provided on the carriage unit 12 rotates the pinion, causing the carriage unit 12 to rise and fall along the mast unit 11 along the carriage mounting unit 22. The counterweight device 20 is driven via two wire ropes 15 connected to the carriage unit 12, causing the carriage unit 12 to rise and fall relative to the construction target. As the construction of the construction target progresses, the lifting height of the mast unit 11 is extended at a predetermined stage.

[0035] 7(a) to (d) are diagrams illustrating a method for extending the lifting height of the mast section 11. To extend the lifting height of the mast section 11, first, as shown in Fig. 7(a), the carriage section 12 is moved to the uppermost stop position and stopped there. In this state, the carriage section 12 is fixed. This places the counterweight device 20 in the lowermost stop position. In this state, the weight block 32 of the weight section 13 is removed and temporarily placed on the base floor.

[0036] As shown in Figure 7 (b), using a tower crane or the like, the extension part 41 is connected to the upper end of the mast part 11, and if necessary, the wall connecting part 21 is installed, and the guide part and rack gear of the carrier mounting part 22, as well as the guide rail 23 of the counterweight device 20 are extended to the extension part 41.

[0037] As shown in Figure 7 (c), the fixation of the wire rope 15 by the tail 36 is released, and the wire rope 15 is unwound from the surplus winding drum section 17 while the lotus base 42 and the carrier section 12 are raised to a predetermined position at the top of the extended mast section 11.

[0038] As shown in Fig. 7(d), while moving the carrier section 12 up and down, the length of the wire rope 15 arranged between the carrier section 12 and the counterweight device 20 is adjusted, and then the wire rope 15 is fixed to the counterweight device 20 again by the tail 36. Then, if necessary, the weight of the weight block 32 of the weight section 13 is adjusted and the weight block 32 is fixed to the weight section 13. This completes the operation of extending the lifting height of the mast section 11.

[0039] According to the construction elevator 10 of the present embodiment as described above, the surplus winding drum section 17, which winds and stores the surplus of the wire rope 15, is arranged on the other side of the wire rope 15 together with the weight section 13. Therefore, the weight of the surplus winding drum section 17 is not loaded onto the carrier section 12. As a result, it is possible to prevent the weight of the surplus winding drum section 17 from reducing the loadable weight of the carrier section 12, and it is possible to increase the loadable weight of the carrier section 12.

[0040] In the construction elevator 10 of this embodiment, the mast section 11 has a guide rail 23. The weight section 13 has a first frame 31 and a weight block 32 fixed to the first frame 31. The extra winding drum section 17 has a second frame 34 and a drum 35 fixed to the second frame 34. The first frame 31 and the second frame 34 are connected vertically and configured to be able to rise and fall along the guide rail 23. Therefore, even if the weight section 13 and the extra winding drum section 17 are arranged on the other side of the wire rope 15, the cross-sectional shape can be kept small by arranging the weight section 13 and the extra winding drum section 17 vertically, and the weight section 13 and the extra winding drum section 17 can be raised and lowered integrally. As a result, even in a limited arrangement space around the mast section 11, the weight section 13 and the extra winding drum section 17 can be reliably arranged on the other side of the wire rope 15.

[0041] In the construction elevator 10 of this embodiment, the first frame 31 and the second frame 34 have multiple guide rollers 29 that roll while clamping the guide rail 23. Therefore, the weight section 13 and the extra wind drum section 17 are stably supported by the guide rail 23, and the distance from the guide rail 23 is unlikely to change during ascent and descent. This makes it possible to prevent the weight section 13 and the extra wind drum section 17 from contacting the surrounding members such as the carriage section 12 and the work object during ascent and descent, and allows for stable driving.

[0042] In the construction elevator 10 of this embodiment, the multiple guide rollers 29 are configured to be adjustable in position relative to the first frame 31 and the second frame 34. Therefore, the orientation and distance of the weight section 13 and the extra winding drum section 17 relative to the guide rail 23 can be easily adjusted, and contact with surrounding members such as the carriage section 12 and the construction target during ascent and descent can be more reliably prevented.

[0043] In the construction elevator 10 of this embodiment, the first frame 31 and the second frame 34 are connected to be relatively displaceable in the lateral direction. Therefore, even if a rotational force is generated in the extra winding drum part 17 during ascent and descent, the rotational force is unlikely to be transmitted from the extra winding drum part 17 to the weight part 13. Therefore, the weight part 13 can be stably guided by the guide rail 23, and it is possible to prevent the multiple guide rollers 29 from being subjected to an unbalanced load or from hitting one side of the guide rail 23.

[0044] In the construction elevator 10 of this embodiment, the first frame 31 and the second frame 34 are connected via a buffer material 37. Therefore, even if a lateral force acts on the weight section 13 and causes it to vibrate when climbing over a step due to an unevenness in the guide rail 23 during ascent or descent, the buffer material 37 can attenuate the vibration, and the vibration is not easily transmitted to the extra winding drum section 17. This can suppress the vibration from being transmitted to the wire rope 15 and causing lateral vibration, and can prevent the wire rope 15 arranged in a limited space from coming into contact with surrounding members or other wire ropes 15 and being damaged.

[0045] In the construction elevator 10 of this embodiment, one or more weight blocks 32 with a preset total weight are fixed to one first frame 31. Therefore, by not connecting multiple first frames 31 to which weight blocks 32 are fixed, the device position and relative orientation do not change between the multiple first frames 31, 31 during ascent and descent, and the weight section 13 can be stably guided by the guide rails 23.

[0046] In the construction elevator 10 of this embodiment, the second frame 34 is disposed below the first frame 31, so the extra wind drum part 17 is disposed below the weight part 13. In addition, by providing the extra wind drum part 17 on the weight part 13 side, wire adjustment work during climbing work may have to be performed at a high place. However, by disposing the extra wind drum part 17 below the weight part 13, when performing climbing work (work to extend the lift) with the extra wind drum part 17 and the weight part 13 lowered to the lowest part, the extra wind drum part 17 can be disposed near the ground. As a result, scaffolding for wire replacement work accompanying climbing work is not required, and there is no need to install scaffolding every time climbing work is performed and remove it after work, which improves work efficiency.

[0047] In the construction elevator 10 of this embodiment, the cross-sectional shape of the weight block 32 has a continuous recess 32a over the entire length, and the wire rope 15 is arranged in the recess 32a. Therefore, the wire rope 15 extending in the vertical direction can be arranged near the center of gravity of the weight block 32. This makes it easier to suppress fluctuations in the direction and inclination of the weight part 13 during ascent and descent, and prevents the multiple guide rollers 29 from being subjected to an unbalanced load or from being hit on one side of the guide rail 23. In addition, if the extra winding drum part 17 is provided below the weight part 13, the weight part 13 is pushed up from below, resulting in an unstable hanging shape and a risk of an unbalanced load being applied to the guide rollers 29. However, by arranging the wire rope 15 in the recess 32a, it is possible to suppress the unbalanced load from being applied to the guide rollers 29.

[0048] Moreover, the counterweight device 20 of this embodiment is configured to include an excess winding drum section 17 for winding and storing the excess of the wire rope 15, and a weight section 13 connected to the excess winding drum section 17. Therefore, in an elevator in which the mast section 11 is configured to be able to extend the lifting height, the carriage section 12 is connected to one side of the wire rope 15, and the excess winding drum section 17 is connected to the other side via the top sheave section 14, thereby making it possible to construct a construction elevator 10 that can prevent the weight of the excess winding drum section 17 from reducing the loadable weight.

[0049] [Second embodiment] FIG. 8 is a side view and a cross-sectional view showing a part of the construction elevator of the second embodiment. The construction elevator 100 of the second embodiment is configured similarly to the first embodiment, except that the configuration of the counterweight device 20 is different.

[0050] In the counterweight device 20 of the second embodiment, multiple weight blocks 32 are fixed to the first frame 31 and connected in series along the guide rail 23. A preset set weight is realized by connecting multiple weight blocks 32 and first frames 31. The connection structure of the upper and lower first frames 31, 31 and the connection structure between the first frame 31 and the second frame 34 are similar to the frame connection portion between the first frame 31 and the second frame 34 of the first embodiment.

[0051] Even with this configuration, it is possible to obtain the same advantageous effects as in the first embodiment, such as preventing the loadable weight of the carrier section 12 from being reduced due to the weight of the surplus winding drum section 17 and increasing the loadable weight of the carrier section 12.

[0052] The above-described embodiments can be modified as appropriate within the scope of the present invention. For example, in the above embodiment, an example has been described in which the extra winding drum part 17 is disposed below the weight part 13, but as shown in Fig. 9, the extra winding drum part 17 may be disposed above the weight part 13, and the weight part 13 may be suspended from the extra winding drum part 17. In this case, the first frame 31 of the weight part 13 disposed below the second frame 34 of the extra winding drum part 17 may be swingably connected to the second frame 34 by a pin or the like, and similarly, the multiple first frames 31, 31 may also be swingably connected to each other by a pin or the like.

[0053] In addition, in the above embodiment, an example has been described in which the carrier section 12 and the counterweight device 20 are attached to one mast section 11. However, as shown in FIG. 10, it is also possible to install multiple mast sections 11, attach the carrier section 12 so that it is bridged between the mast sections 11, 11, and attach a counterweight device 20 to each mast section 11.

[0054] In addition, in the above embodiment, the guide rail 23 is clamped by the guide rollers 29 provided on the first frame 31 and the second frame 34, but this is not particularly limited and the guide rail 23 may be guided by other members.

[0055] Furthermore, in the above embodiment, the first frame 31 and the second frame 34, and the first frames 31 are connected to each other so as to be able to move relative to each other in the lateral direction, with cushioning material 37 interposed between them, but other connecting means can be used, and the frames may be firmly integrated.

[0056] In the above embodiment, the weight block 32 is configured to have a recess 32a, but the weight block 32 may be configured to not have a recess 32a, or a cylindrical weight block may be used with the wire rope 15 inserted into the cylindrical interior.

[0057] The "Sustainable Development Goals (SDGs)" are 17 international goals that were adopted at the United Nations Summit in September 2015. The welding device according to this embodiment can contribute to the achievement of, for example, goal 9 "Build resilient infrastructure, promote inclusive and sustainable industrialization, and foster innovation and foster innovation" out of the 17 SDGs. [Explanation of symbols]

[0058] 10 Construction Elevator 11 Mast section 12 Carriage unit 13 Weight section 14 Top sheave section 15 Wire Rope 16 Drive unit 17 Extra winding drum section 20 Counterweight device 21 Wall joint 22 Carrier mounting section 23 Guide rail 25 Lifting frame 26 Cage 27 Wire connection part 29 Guide roller 31 1st Frame 31a Block fixing part 32 Weight Block 32a Recess 34 2nd Frame 34a Drum placement section 35 Drums 36 Shitte 37 Cushioning material 41 Extension 42 Lotus stand

Claims

1. A mast section capable of extending the lifting height; A carriage section and a weight section arranged so as to be liftable and lowerable relative to the mast section; a wire supported by a top sheave portion of the mast portion, the wire having one side to which the carrier portion is connected and the other side to which the weight portion is connected via the top sheave portion; A drive unit provided on the carriage for driving the carriage up and down; A construction elevator equipped with an excess winding drum part for winding and storing the excess of the wire, The extra winding drum portion is disposed on the other side of the wire together with the weight portion, The mast portion has a guide rail extending vertically, The weight portion has a first frame that moves up and down along the guide rail and a weight block fixed to the first frame, The extra winding drum unit has a second frame that moves up and down along the guide rail and a spare winding drum fixed to the second frame, A construction elevator, wherein the first frame and the second frame are connected vertically via a buffer material.

2. The construction elevator according to claim 1 , wherein the first frame and the second frame have a plurality of rollers that roll while sandwiching the guide rail.

3. 3. The construction elevator according to claim 2, wherein the plurality of rollers are configured so that their arrangements with respect to the first frame and the second frame are adjustable.

4. 2. The construction elevator according to claim 1, wherein the first frame and the second frame are connected to each other so as to be capable of relative displacement in the lateral direction.

5. 2. The construction elevator according to claim 1, wherein one or more weight blocks each having a preset total weight are fixed to the first frame.

6. The construction elevator according to claim 1 , wherein the second frame is disposed below the first frame.

7. 2. The construction elevator according to claim 1, wherein the cross-sectional shape of the weight block has a continuous recess over its entire length, and the wire is disposed within the recess.

8. A counterweight device in which a mast section is configured to be able to extend a lifting range and includes a top sheave section, and a carrier section is connected to one side of a wire via the top sheave section, an excess winding drum section for winding and storing the excess of the wire; A weight portion connected to the extra winding drum portion, The weight portion has a first frame that moves up and down along a guide rail and a weight block fixed to the first frame, The extra winding drum unit has a second frame that moves up and down along the guide rail and a spare winding drum fixed to the second frame, A counterweight device in which the first frame and the second frame are connected vertically via a buffer material.

Citation Information

Patent Citations

  • Elevator for construction work

    JP1999189381A