Production management system and production management method

The production management system optimizes lead times and waiting times in manufacturing environments with high-mix, low-volume production by incorporating provisional and target lead times, addressing inefficiencies and mismatches in existing systems to enhance operational efficiency and align production plans with actual factory operations.

JP2024157659APending Publication Date: 2024-11-08平塚 信介

Patent Information

Application Number
JP2023072134
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-26
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Existing production management systems struggle with accurately setting delivery lead times and managing work-in-progress (WIP) in manufacturing environments with high-mix, low-volume production, leading to inefficiencies and mismatches between planned and actual production situations due to varying workplace lead times and unaccounted processing waiting times.

Method used

A production management system that incorporates provisional and target lead times, including processing and inspection waiting times, to adjust and optimize the manufacturing process, allowing for efficient processing and inspection by setting appropriate waiting times and adjusting lead times based on actual production data and capacity.

Benefits of technology

The system ensures smoother production by accurately managing lead times and WIP, reducing waiting times, and improving the alignment of production plans with actual factory operations, thereby enhancing operational efficiency and reducing production deviations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024157659000001_ABST
    Figure 2024157659000001_ABST
Patent Text Reader

Abstract

To provide a production management system and a production management method for a factory having a plurality of processing workplaces and inspection workplaces or a combination factory which manufactures products and parts by combining the factories, the system and method providing time as waiting time prior to processing and inspection, adjusting the waiting time prior to processing and inspection with secured time for various processing and inspection on unfinished goods in the plurality of processing workplaces and inspection workplaces, and simply and easily performing production management in order to solve the problem that a longer period of time is required, than for processing and inspection, for measures against a stay of the unfinished goods, setup of processing and inspection, etc. that likely occur in the plurality of processing workplaces and inspection workplaces for performing various processing, inspection, etc. in the factory.SOLUTION: Each lead time part in target lead time is configured by waiting time and time for processing or inspection. The processing or inspection in each workplace is performed after waiting time or less elapses.SELECTED DRAWING: Figure 21
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a production management system and a production management method for a factory having a plurality of workplaces such as processing workplaces and inspection workplaces, or for an assembled factory in which such factories are combined to manufacture products or parts. [Background technology]

[0002] Conventionally, as a production management system of this kind, for example, a production management system described in the following Patent Document 1 has been proposed. This production management system manages the production of multiple types of manufacturing target parts at a manufacturing factory in order to supply multiple types of manufacturing target parts that are the subject of orders, i.e., orders, to an assembly factory via a material warehouse, a manufacturing factory, and multiple finished product warehouses that constitute a supply chain. Note that the assembly factory is a factory where the manufacturing target parts, which are each the finished parts supplied from the multiple finished product warehouses, are assembled together.

[0003] In a supply chain, a material warehouse is a warehouse that stores each material workpiece, which is the material for each different manufacturing target part produced in a manufacturing factory. The manufacturing factory has multiple processing workplaces, and the manufacturing factory is a factory where each different material workpiece from the material warehouse is input as a work in progress, and the in progress parts are processed in sequence in the multiple processing workplaces to be completed as each different manufacturing target part. The multiple finished product warehouses are warehouses that store each different manufacturing target part that has been completed as a finished part in the manufacturing factory.

[0004] In the production management system configured as above, when an order for a part to be manufactured is placed with a manufacturing factory, a delivery LT is set for the part to be manufactured. The delivery LT is determined as the sum of the input waiting time, the factory transit LT, and the inventory margin time.

[0005] In the delivery LT, the input waiting time refers to the time from the predetermined planned input date to the actual input to the manufacturing plant. Here, the predetermined planned input date refers to the input timing of the material workpiece to the manufacturing plant, which is determined by going back by the delivery LT from the delivery date requested by the order.

[0006] Factory transit LT refers to the time it takes for a material workpiece to be completed as a finished part after being input from the material warehouse to the manufacturing plant. Here, the factory transit LT refers to the sum of the workplace LTs of each processing plant through which the workpiece passes. Additionally, workplace LT refers to the time it takes for the workpiece to be completed after being input to the processing plant. Inventory surplus time refers to the inventory time from when the workpiece becomes a finished product at the manufacturing plant until it is delivered to the assembly plant. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] JP 2020-166548 A Summary of the Invention [Problem to be solved by the invention]

[0008] In the above-mentioned production management system, from the viewpoint of production management, it is desirable that the input of the material work from the material warehouse to the manufacturing plant is carried out on the planned input date set in advance as described above according to the production plan. For this reason, in the above-mentioned delivery LT, the input waiting time is set to zero.

[0009] In addition, the factory transit LT of the delivery LT is the sum of the workplace LT of each processing workplace that each in-process part passes through, so in order to determine the factory transit LT, it is necessary to find the workplace LT of each processing workplace that each in-process part passes through.

[0010] However, the workplace LT differs for each part in process, and in the case of high-mix low-volume production, the production volume at the manufacturing plant differs for each part to be manufactured that is the subject of an order.

[0011] For this reason, the workplace LT is identified according to whether the production volume of manufacturing target parts is equal to or greater than a predetermined number or whether the production volume is less than the predetermined number, as follows.

[0012] First, when the production volume of the manufacturing target parts is equal to or greater than a predetermined number, the parts are identified by the past work sites LT of the processing plants through which the parts in process pass. The past work sites LT are stored in a database.

[0013] On the other hand, when the production volume of the manufacturing object parts is less than the above-mentioned predetermined number, since the track record is poor, the workplace LT is estimated by inputting the category and material of the manufacturing object parts into the workplace LT estimation model.

[0014] Here, the workplace LT estimation model refers to a trained model constructed for each machining workplace by having a machine learning model learn the relationship between input and output using learning data for each machining workplace, in which the material of the parts to be manufactured is used as input and the actual workplace LT of the machining workplace that performed work on the parts to be manufactured is used as output.

[0015] As described above, when setting the delivery LT and making the input waiting time zero, the identification of the workplace LT for each processing workplace must be done separately for cases where the production number of parts to be manufactured is equal to or greater than a predetermined number, and when the production number of parts to be manufactured is less than the predetermined number, it is necessary to rely on a complex workplace LT estimation model such as that described above, which is problematic.

[0016] To elaborate on this point, in the manufacturing process at a manufacturing plant, usually, one processing workplace is congested with in-process parts input from multiple other processing workplaces. For this reason, a certain number of in-process parts waiting to be processed are always backed up at each processing workplace. Even if each LT is classified and specified as described above on the premise of such backlog, it is unclear whether the processing of in-process parts at each processing workplace can be performed smoothly, and even if it can be performed smoothly, the above-mentioned problems will still occur. Therefore, a production plan using the above-mentioned workplace LT estimation model will not match the actual production situation, and a serious problem will occur in which the plan is not accurate. Therefore, as described above, it is not realistic to set the input waiting time to zero in the delivery LT.

[0017] In addition, when setting it to zero as described above, when a material workpiece is input from the material warehouse to the manufacturing plant, it is necessary that the number of other work-in-progress parts that belong together with the material workpiece in the category to which the material workpiece belongs as a work-in-progress part be maintained below the WIP upper limit.

[0018] However, if the WIP upper limit (the maximum number of workpieces existing in the factory) is not set to an appropriate number, a problem will occur in which the condition required to set the input waiting time to zero is not met, even if the number of other work-in-progress parts that belong to the category to which the raw workpiece belongs as a work-in-progress part is below the WIP upper limit.

[0019] Here, even if the WIP upper limit number can be optimized so as to ensure the necessary processing output at a processing workplace, taking into consideration the processing capacity at the processing workplace and the number of work-in-progress parts input to the processing workplace, such optimization leads to the inconvenience of requiring the cumbersome task of repeatedly updating the WIP upper limit number.

[0020] In addition, in this production management system, although the processing time is taken into account in both the factory transit time LT and the workplace LT, the waiting time for processing of work-in-progress parts at the processing workplace is not taken into account at all.

[0021] When this point is examined in detail, as mentioned above, normally, a certain number of work-in-progress parts waiting to be processed always remain at each processing workplace.

[0022] Here, the more the number of pending in-process parts, the more troublesome the task of selecting the in-process part to be processed first becomes. Even if it is possible to select the in-process part to be processed first, since each in-process part has different specifications such as material and shape, different setup work is required for processing each in-process part.

[0023] For this reason, each processing plant needs to wait for each in-process part before processing it. Here, depending on the processing plant, processing other than processing may be performed, such as painting or inspection, so the above-mentioned waiting time can be said to be a processing waiting time including processing, painting, inspection, etc.

[0024] Therefore, in the above-mentioned production management system, since the processing waiting time at each processing plant is not taken into consideration in the factory transit time LT and the plant LT, the derived production plan does not match the actual production situation, and deviations from the plan occur, causing confusion, and smooth processing at each processing plant cannot be realized.

[0025] As explained above, even if the waiting time for inputting the delivery LT can be set to zero by optimizing the WIP upper limit and, based on this optimization, maintaining the number of other work-in-progress parts that belong together with the work-in-progress in the category to which the material work belongs at or below the WIP upper limit when inputting the material work from the material warehouse to the manufacturing plant, not only will the above-mentioned problems occur, but the processing waiting time of the work-in-progress parts in the processing workplace is not taken into consideration at all, which will lead to the problem that the processing of the work-in-progress parts in the processing workplace cannot be performed efficiently. Such problems occur more significantly the more the number of work-in-progress parts is retained in the processing workplace.

[0026] Therefore, in order to address the above, the present invention has an object to provide a production management system and production management method for a factory having a plurality of processing workplaces and inspection workplaces or a combination factory which manufactures products and parts by combining such factories, which provides a production management system and a production management method for a factory having a plurality of processing workplaces and inspection workplaces, or a combination factory which manufactures products and parts by combining such factories, by setting aside the time required to deal with the backlog of work-in-progress that tends to occur in a plurality of processing workplaces and inspection workplaces where various types of processing and inspection are performed in a factory, and by adjusting the waiting time prior to said processing or inspection, while ensuring time for various types of processing and inspection of work-in-progress at the plurality of processing workplaces and inspection workplaces, thereby making production management easy and simplified. [Means for solving the problem]

[0027] In order to solve the above problem, the production management system according to the present invention comprises, according to claim 1: This applies to both an in-house factory (20) having multiple workplaces (20a-20d) as in-house processing workplaces (20a-20c) and in-house inspection workplace (20d), and outsourced factories (SF1, SF2) having at least one outsourced processing workplace.

[0028] In the production management system, a provisional lead time setting means (113) which includes a provisional lead time (LT1) consisting of a leading lead time section (LT1A-LT1D) and a trailing lead time section (LT1E) following the leading lead time section, and which sets the provisional lead time so that the provisional lead time is comprised in the leading lead time section of processing wait times (T1A-T1D) and processing times (H1A-H1D) required for processing each corresponding material of a corresponding material group for each ordered part of an ordered part group by a processing means provided in any one of a plurality of in-house processing workplaces or an outsourced processing workplace, and is comprised in the trailing lead time section of inspection wait times (T1E) and inspection times (H1E) required for inspecting each corresponding material of the corresponding material group after processing by an inspection means provided in the in-house inspection workplace; a target leadtime setting means (131) which includes a target leadtime (LT13) consisting of a leading target leadtime portion and a trailing target leadtime portion subsequent to the leading target leadtime portion, and sets the target leadtime such that the processing wait time and processing time constituting the leading leadtime portion of the tentative leadtime related to the setting by the tentative leadtime setting means are configured as target processing wait time and target processing time in the leading target leadtime portion, and the inspection wait time and inspection time constituting the trailing leadtime portion of the tentative leadtime are configured as target inspection wait time and target inspection time in the trailing target leadtime portion; The system is characterized by comprising a conversion setting means (131b, 132) for converting and setting temporary manufacturing instruction data representing a temporary manufacturing instruction (PBFa) obtained by inputting a target processing wait time, a target processing time, a target inspection wait time, and a target inspection time, into regular manufacturing instruction data representing a regular manufacturing instruction (Q) obtained by displaying each input content to the temporary manufacturing instruction.

[0029] According to this configuration, the set tentative lead time is composed of an advance lead time portion and a follow-up lead time portion. Here, the advance lead time portion is composed of each processing time of the corresponding material of the ordered part required for processing by a processing means arranged at any one of the in-house processing workplaces or the outsourced processing workplace, and the processing wait time. Also, the follow-up lead time portion is composed of the inspection time of the corresponding material after the processing required for inspection by an inspection means arranged at the in-house inspection workplace, and the inspection wait time.

[0030] By utilizing such a set tentative lead time, the target lead time is composed of an advanced lead time section which has the processing wait time and processing time of the advanced lead time section of the set tentative lead time as the target processing wait time and target processing time, and a subsequent lead time section which has the inspection wait time and inspection time of the set tentative lead time as the target inspection wait time and target inspection time.

[0031] Furthermore, the provisional manufacturing instruction data representing the provisional manufacturing instruction formed by inputting the target processing wait time, the target processing time, the target inspection wait time, and the target inspection time is converted and set into the formal manufacturing instruction data representing the formal manufacturing instruction formed by displaying each input content to the provisional manufacturing instruction.

[0032] With the above-mentioned configuration, when a corresponding material group consisting of corresponding materials to which a primary production instruction printed based on primary production instruction data is attached is input to any one of the in-house processing plants or the outsourced processing plants, the corresponding material group is awaited to be processed by the processing means at any one of the in-house processing plants or the outsourced processing plants within the target processing wait time of the primary production instruction, and as the target processing wait time elapses, the corresponding material group is processed by the processing means at the target processing time of the primary production instruction, Thereafter, at the company's own inspection site, the corresponding group of processed materials is subjected to inspection by the inspection means within the target inspection waiting time of the original production instruction, and as the target inspection waiting time elapses, the corresponding group of processed materials is inspected by the inspection means at the target inspection time of the original production instruction.

[0033] In other words, in the actual situation where a plurality of backlogged work-in-progress products are congested in any one of the in-house processing workplaces or the outsourced processing workplaces or the in-house inspection workplaces where various processing and inspection are performed in a factory, in addition to the time required for processing and inspection, waiting time for processing and inspection is required. This means that the above-mentioned leading lead time portion or trailing lead time portion is composed of the waiting time for processing or inspection and the time for processing or inspection.

[0034] Here, since the waiting time for the processing or inspection is longer than the time required for the processing or inspection, the time required for the processing or inspection can be easily adjusted by utilizing the waiting time for the processing or inspection, without relying on the complex configurations and processing of the conventional technology described at the beginning of this specification.

[0035] Therefore, although the target lead time is composed of the sum of the leading lead time section having the target processing waiting time and target processing time, and the trailing lead time section having the target inspection waiting time and target inspection time, unlike the conventional technology, it does not depend on the overall target lead time, but based on the leading lead time section and trailing lead time section configured as described above, the necessary setups can be properly carried out and processing and inspection can be properly and easily performed based on the target processing waiting time and target processing time at any one of the company's own processing workplaces or outsourced processing workplaces, and the target inspection waiting time and target inspection time at the company's inspection workplace.

[0036] According to claim 2, the present invention provides a production management system according to claim 1, a work-in-progress quantity setting means (115) for calculating the future work-in-progress quantity of the corresponding material in accordance with the number of ordered parts based on the work-in-progress performance data (IPD1 to IPD4, IPDSF1, IPDSF2) of the corresponding material and setting the calculated work-in-progress quantity in the future; a work-in-progress quantity determination means (120) for determining whether the calculated future work-in-progress quantity of the corresponding material is excessive or not; When the in-process quantity determination means determines that the calculated future in-process quantity of the corresponding material is excessive, the target processing time or the target inspection time of the corresponding material is expressed as a target time based on the processing capacity of any one of the in-house processing plants or the outsourced processing plants and the target in-process quantity of the corresponding material or the inspection capacity of the inspection plant and the target in-process quantity, and the target time is calculated by the following formula (1): Target time = Target number of works in progress ÷ Processing capacity (1) A target time calculation means (121) for calculating a target time based on the above. a waiting time adjustment means (123) for adjusting waiting time when the calculated work-in-process quantity is excessive, which subtracts a processing waiting time until the preceding lead time portion of the tentative lead time related to the setting of the corresponding material is reduced to a target time, and adjusts the processing waiting time as a subtraction processing waiting time (T1Aβa to T1Dβa), and subtracts an inspection waiting time until the succeeding lead time portion of the tentative lead time (LT1) related to the setting is reduced to a target time, and adjusts the processing waiting time as a subtraction inspection waiting time (T1Eβa); a tentative leadtime update setting means (124) for updating a processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting by the subtracted processing wait time, and updating an inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting by the subtracted inspection wait time, and setting both update results together with the processing time and the inspection time as an updated tentative leadtime (LT11), The target lead time is set as a first target lead time, and the target processing wait time, target processing time, target inspection wait time and target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, and the target lead time setting means (131) is set to include a second target lead time (LT11) in addition to the first target lead time, and the second target lead time is set to be composed of a leading lead time section having the subtraction processing wait time of the leading lead time section of the updated tentative lead time together with processing time as a second target processing wait time, and a subsequent lead time section having the subtraction inspection wait time of the subsequent lead time section of the updated tentative lead time together with inspection time as a second target inspection wait time, The conversion setting means (131b, 132) is further configured to convert and set the provisional manufacturing instruction data representing the second provisional manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time into a regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying each input content into the second provisional manufacturing instruction, as a first provisional manufacturing instruction and a first regular manufacturing instruction, respectively.

[0037] With this configuration, since the future calculated in-process quantity of the corresponding material is excessively large, the processing wait time at any one of the in-house processing plants or outsourced processing plants is shortened to the point where the entire lead time portion is reduced to the target time calculated using formula (1).

[0038] Accordingly, when a corresponding material group consisting of corresponding materials with second primary manufacturing instructions printed based on primary manufacturing instruction data attached thereto is input into any one of the in-house processing workplaces or outsourced processing workplaces, the corresponding material group will be processed within the second target processing wait time, which is shortened to the second target processing wait time of the second primary manufacturing instruction, at any one of the in-house processing workplaces or outsourced processing workplaces, and as the second target processing wait time passes, the corresponding material group will be processed within the processing time of the second primary manufacturing instruction; and, at the in-house inspection facility, the corresponding material group after processing will be inspected within the second target inspection wait time, which is shortened to the second target inspection wait time of the second primary manufacturing instruction, and as the second target inspection wait time passes, the corresponding material group after processing will be inspected within the inspection time of the second primary manufacturing instruction.

[0039] Therefore, if the calculated future work-in-progress quantity of the corresponding materials is excessive, the processing time at any one of the in-house processing workplaces or outsourced processing workplaces can be maintained as is while the processing wait time is shortened as described above, thereby bringing the input date of the corresponding material group to that one of the in-house processing workplaces or outsourced processing workplaces closer to the processing date, thereby suppressing the residence time of the corresponding materials at that one of the in-house processing workplaces or outsourced processing workplaces and enabling the corresponding materials to be processed appropriately.

[0040] In other words, even if the calculated future in-process quantities of the corresponding materials are excessively large, by shortening the processing wait time as described above, it is possible to expedite the processing of the next group of corresponding materials while properly processing the corresponding group of materials at one of the in-house processing plants or outsourced processing plants.

[0041] According to claim 3, the present invention provides a production management system according to claim 2, The in-process quantity determination means determines the in-process quantity to be excessive when the calculated in-process quantity of the corresponding material in the future increases by at least a predetermined in-process increase number (θ) beyond the in-process target quantity of the extracted in-process target data of the corresponding material. This makes it possible to more appropriately ensure the effect of the invention of claim 2.

[0042] According to claim 4, the present invention provides a production management system according to claim 1, A sudden decrease determination means (130) for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; an order quantity sudden drop wait time adjustment means (134a) for adjusting, when the future calculated in-process quantity of the corresponding material suddenly drops, the order quantity of the ordered parts is judged to have suddenly dropped by the sudden drop judgment means, so as to add a predetermined relaxation time (α) to the processing wait time in the preceding lead time portion of the tentative lead time related to the setting, and set the result as an additional processing wait time, and also add the predetermined relaxation time to the inspection wait time in the succeeding lead time portion of the tentative lead time related to the setting, and set the result as an additional inspection wait time; a tentative leadtime update setting means (134) for updating a processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting by an added processing wait time, and updating an inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting by an added inspection wait time, and setting both update results together with the processing time as an updated tentative leadtime (LT12), The target lead time (LT13) is set as a first target lead time, and the target processing wait time, target processing time, target inspection wait time and target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, and the target lead time setting means (131) is set to include a second target lead time (LT12) in addition to the first target lead time, and the second target lead time is set to be composed of a leading lead time part having an added processing wait time in the leading lead time part of the updated tentative lead time together with the processing time as a second target processing wait time, and a subsequent lead time part having an added inspection wait time in the subsequent lead time part of the updated tentative lead time together with the inspection time as a second target inspection wait time, The conversion setting means (131b, 132) is further configured to convert and set the provisional manufacturing instruction data representing the second provisional manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time into a regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying each input content into the second provisional manufacturing instruction, as a first provisional manufacturing instruction and a first regular manufacturing instruction, respectively.

[0043] According to this configuration, when the number of orders suddenly decreases, the processing wait time at any one of the in-house processing plants or the outsourced processing plants is set by adding a predetermined relaxation time to the target processing wait time of the leading lead time part of the tentative lead time, and the inspection wait time at the inspection plant is set by adding a predetermined relaxation time to the inspection wait time of the trailing lead time part of the tentative lead time.

[0044] In other words, in the event of a sudden decrease in the number of orders, the processing waiting time at any one of the in-house processing plants or outsourced processing plants will be extended by a specified relaxation time, and the additional inspection waiting time at the in-house inspection plant will be extended by the specified relaxation time.

[0045] Therefore, in the event of a sudden decrease in the number of orders, the processing wait time at any one of the in-house processing workplaces or outsourced processing workplaces is extended or adjusted within a specified relaxation time, thereby ensuring an appropriate number of corresponding materials to be processed for the corresponding material group at any one of the in-house processing workplaces or outsourced processing workplaces, and enabling the processing to be carried out appropriately while suppressing a decrease in operating rate.

[0046] In addition, even if the number of orders suddenly drops, the waiting time for testing at the in-house testing workplace is extended by the predetermined relaxation time as described above, so the number of corresponding materials to be tested for the corresponding material group at the in-house testing workplace can be secured, and the testing can be carried out appropriately while suppressing a decrease in the operating rate. Other effects are the same as those of the invention of claim 1.

[0047] According to claim 5 of the present invention, in the production management system according to claim 4, In the sudden decrease means, the sudden decrease is specified by a sudden decrease speed within a predetermined sudden decrease speed range and a sudden decrease rate within a predetermined sudden decrease rate range. With this, the effect of the invention described in claim 4 can be achieved more specifically.

[0048] According to claim 6, the present invention provides a production management system according to claim 2, A sudden decrease determination means (130) for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; a means (133) for determining whether or not both the excessiveness and the sudden decrease have been eliminated when the means for determining the amount in process determines that the future calculated amount in process of the corresponding material is excessive and when the means for determining the sudden decrease determines that the number of orders for the ordered parts has suddenly decreased when the means for determining the amount in process of the corresponding material in the future suddenly decreases; an excess maintenance / sudden decrease elimination determination means (133a) for determining whether or not the sudden decrease has been eliminated while the excess is maintained, when the excess / sudden decrease elimination determination means determines that both the excess and the sudden decrease have not been eliminated; and a sudden decrease maintenance / excessive elimination determination means (134) for determining whether or not the excessive state has been eliminated while the sudden decrease is maintained, when the excessive state maintenance / sudden decrease elimination determination means determines that the sudden decrease has not been eliminated while the excessive state is maintained, when the excessive / rapid decrease both resolution determining means determines that both the excessive amount and the sudden decrease have been resolved, the determination of excessive amount by the work-in-process quantity determining means and the determination of sudden decrease by the sudden decrease determining means are resolved, and the tentative lead time is set by the tentative lead time setting means based on the non-excessive amount of the calculated work-in-process quantity in the future and the non-sudden decrease in the number of orders, the target lead time is set by the target lead time setting means, and the conversion setting means converts the data into the regular production instruction data. when the excessive amount maintenance / sudden decrease elimination determining means determines that the sudden decrease has been eliminated while the excessive amount is maintained, the sudden decrease determining means cancels the determination that the order quantity has suddenly decreased, and sets a tentative lead time by the tentative lead time setting means based on the excessive amount of the calculated future work-in-process quantity and the non-sudden decrease in the order quantity, sets a target lead time by the target lead time setting means, and sets conversion to regular production instruction data by the conversion setting means; The sudden decrease maintenance / excessive elimination determination means eliminates the excessive determination made by the work-in-process quantity determination means and maintains the sudden decrease in the number of orders, and sets a tentative lead time by the tentative lead time setting means based on the future calculated work-in-process quantity being not excessive and the sudden decrease in the number of orders, sets a target lead time by the target lead time setting means, and sets conversion to regular production instruction data by the conversion setting means.

[0049] According to this configuration, even if the number of orders is determined to be suddenly decreased after the future work-in-process quantity is determined to be excessive as described above, if the excess is eliminated by the sudden decrease and the sudden decrease is also eliminated, processing similar to the processing based on the configuration of the invention described in claim 1 will be performed under the assumption that the future work-in-process quantity is not excessive and the number of orders is not suddenly decreased, and if the sudden decrease is eliminated while the excess is maintained, processing similar to the processing based on the configuration of the invention described in claim 2 will be performed, and if the sudden decrease is maintained while the future work-in-process quantity is not excessive, processing similar to the processing based on the configuration of the invention described in claim 4 will be performed.

[0050] According to claim 7, the present invention provides a production management system according to claim 1, 2, 4 or 6, A plurality of terminal means (P0 to P13) provided in any one of the in-house processing workplace, the in-house inspection workplace, and the outsourced processing workplace; A plurality of receiving means (R0 to R13) corresponding to the plurality of receiving means, a processing means (CPU) and a registration device (Sb); a processing plant receipt data output means (151) for outputting the processing plant receipt data from the corresponding receiving means to a registration device when the processing plant terminal means of the plurality of terminal means, which is disposed at the one of the in-house processing plants or the outsourced processing plants, transmits processing plant receipt data representing receipt information of the corresponding material group to a corresponding receiving means of the plurality of receiving means for the processing plant terminal means via a network (N) in response to the input of the corresponding material group with the original production instruction attached thereto at the one of the in-house processing plants or the outsourced processing plants; a processing plant sending data output means (151b) for outputting the processing plant sending data representing sending information of the corresponding material group after processing from the processing plant terminal means to the corresponding receiving means via the network (N) after the corresponding material group after processing is sent to the in-house inspection plant by processing the corresponding material group by the processing plant means during the processing time after the corresponding material group is received at any one of the in-house processing plants or outsourced processing plants, and an inspection workplace receipt data output means (152f) for outputting the inspection workplace receipt data from the other receiving means to a registration device when the inspection workplace terminal means, among the multiple terminal means, which is disposed in the company's inspection workplace, transmits the inspection workplace receipt data representing receipt information of the corresponding material group after the processing to another receiving means among the multiple receiving means corresponding to the inspection workplace terminal means via a network, in response to the receipt of the corresponding material group at the company's inspection workplace after the processing is completed; and an inspection workplace sending data output means (152g) for outputting the inspection workplace sending data from the other receiving means to a registration device when the inspection workplace receives the corresponding group of processed materials and inspects the corresponding group of processed materials by the inspection means during the inspection time after waiting for a target inspection waiting time to elapse, and the corresponding group of inspected materials is sent out as a group of material parts consisting of finished material parts. The registration device is characterized in that it updates the in-process performance data already registered therein based on the processing plant receiving data from the processing plant receiving data output means, the processing plant sending data from the processing plant sending data output means, the inspection plant receiving data from the inspection plant receiving data output means, and the inspection plant sending data from the inspection plant sending data output means.

[0051] According to this, the in-process performance data in the registration device is updated based on the processing plant received data from the processing plant received data output means, the processing plant sent data from the processing plant sent data output means, the inspection plant received data from the inspection plant received data output means, and the inspection plant sent data from the inspection plant sent data output means, so that the in-process performance data required for production management can always be secured with the latest information. As a result, the operational effects of the invention described in claim 1, 2, 4 or 6 can be further improved.

[0052] According to claim 8, the present invention provides a production management system according to claim 1, 2, 4 or 6, At least one of the outsourcing factories is characterized in that it is included as at least one processing workplace among the multiple in-house processing workplaces.

[0053] According to this, even when utilizing the processing workplace of an outsourced factory, it is possible to integrate the system for setting lead times for processing and inspection of corresponding material groups within one's own factory, thereby making it possible to achieve the effects of the invention of claims 1, 2, 4 or 6 while making production management at one's own factory even easier.

[0054] According to claim 9, the present invention provides a production management system according to claim 7, The computer program means is made up of a processing plant receiving data output means, a processing plant sending data output means, an inspection plant receiving data output means, and an inspection plant sending data output means, and the computer program means is provided with an interrupt program means for performing an interrupt process on the main program means, The interrupt program means is characterized in that, when the processing plant send data transmitted from the processing plant terminal means is received by the corresponding receiving means, it performs processing similar to the processing by the processing plant received data output means and the processing by the processing plant send data output means, the inspection plant received data output means and the inspection plant send data output means in accordance with the main program means in connection with the input of any one of the other corresponding material groups subsequent to the corresponding material group, which are formed by attaching a regular manufacturing instruction to which the input contents of the temporary manufacturing instruction have already been input, to the in-house processing plant or the outsourced processing plant.

[0055] According to this, by providing an interrupt program means which performs an interrupt process on the main program means, as the corresponding receiving means in the main program means receives the machining work station send data transmitted from the machining work station terminal means, processing similar to the processing by the machining work station received data output means and the processing by the machining work station sent data output means, the inspection work station received data output means and the inspection work station sent data output means is performed on other corresponding material groups following the corresponding material group in accordance with the main program means.

[0056] Therefore, processing of the other corresponding material groups at one of our in-house processing plants or outsourced plants is carried out upon completion of processing of the corresponding material groups at one of our in-house processing plants or outsourced plants. Accordingly, inspection of the other corresponding material groups at one of our in-house inspection plants is carried out upon completion of inspection of the corresponding material groups at our in-house inspection plant or.

[0057] This means that processing at any one of the in-house processing plants or outsourced plants is performed continuously from one corresponding material group to another corresponding material group, and inspection at the in-house inspection plant is performed continuously from one corresponding material group to another corresponding material group. As a result, while achieving the effect of the invention of claim 6, the operating rate of each worker at any one of the in-house processing plants or outsourced plants and the inspection workplace can be well secured.

[0058] According to claim 10, the production management method of the present invention comprises: This applies to both an in-house factory (20) having multiple workplaces (20a-20d) as in-house processing workplaces (20a-20c) and in-house inspection workplace (20d), and outsourced factories (SF1, SF2) having at least one outsourced processing workplace.

[0059] In the production management method, a provisional lead time setting step (113) including a provisional lead time (LT1) consisting of a leading lead time section (LT1A-LT1D) and a trailing lead time section (LT1E) following the leading lead time section, the provisional lead time being set so that the provisional lead time is comprised in the leading lead time section of processing waiting times (T1A-T1D) and processing times (H1A-H1D) required for processing each corresponding material of a corresponding material group for each ordered part of an ordered part group by a processing means provided in any one of a plurality of in-house processing workplaces or an outsourced processing workplace, and is comprised in the trailing lead time section of inspection waiting times (T1E) and inspection times (H1E) required for inspecting each corresponding material of the corresponding material group after processing by an inspection means provided in an in-house inspection workplace; a target leadtime setting step (131) for setting a target leadtime (LT13) comprising a leading target leadtime portion and a trailing target leadtime portion subsequent to the leading target leadtime portion, such that the processing wait time and processing time constituting the leading leadtime portion of the tentative leadtime related to the setting in the tentative leadtime setting step are configured as target processing wait time and target processing time in the leading target leadtime portion, and the inspection wait time and inspection time constituting the trailing leadtime portion of the tentative leadtime are configured as target inspection wait time and target inspection time in the trailing target leadtime portion; and a conversion setting step (131b, 132) for converting and setting temporary manufacturing instruction data representing a temporary manufacturing instruction (PBFa) obtained by inputting a target processing wait time, a target processing time, a target inspection wait time, and a target inspection time, into regular manufacturing instruction data representing a regular manufacturing instruction (Q) obtained by displaying each input content to the temporary manufacturing instruction.

[0060] This makes it possible to provide a production management method that can achieve the effect of the invention of claim 1.

[0061] According to claim 11, the present invention provides a production management method according to claim 10, A work-in-process quantity setting step (115) for calculating the future work-in-process quantity of the corresponding material according to the number of ordered parts based on the work-in-process performance data (IPD1 to IPD4, IPDSF1, IPDSF2) of the corresponding material and setting the calculated work-in-process quantity as the future work-in-process quantity; a step (120) of determining whether the calculated future in-process quantity of the corresponding material is excessive or not; When it is determined in the in-process quantity determination step that the calculated future in-process quantity of the corresponding material is excessive, the target processing time or the target inspection time of the corresponding material is expressed as a target time based on the processing capacity of any one of the in-house processing plants or the outsourced processing plants and the target in-process quantity of the corresponding material or the inspection capacity of the inspection plant and the target in-process quantity, and the target time is calculated by the following formula (1): Target time = Target number of works in progress ÷ Processing capacity (1) A target time calculation step (121) for calculating a target time based on the above. a wait time adjustment step (123) when the calculated work-in-process quantity is excessive, in which a processing wait time is subtracted until the preceding lead time portion of the tentative lead time related to the setting of the corresponding material is reduced to a target time, and the subtraction wait time is adjusted as a subtraction wait time for processing (T1Aβa to T1Dβa), and an inspection wait time is subtracted until the succeeding lead time portion of the tentative lead time (LT1) related to the setting is reduced to a target time, and the subtraction wait time is adjusted as a subtraction wait time for inspection (T1Eβa); a tentative leadtime update setting step (124) for updating a processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting by the subtracted processing wait time, and updating an inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting by the subtracted inspection wait time, and setting both update results together with the processing time and the inspection time as an updated tentative leadtime (LT11), The target lead time is set as a first target lead time, and the target processing wait time, target processing time, target inspection wait time and target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, in a target lead time setting step (131), a second target lead time (LT11) is provided in addition to the first target lead time, and the second target lead time is set so as to be composed of a leading lead time portion having the subtraction processing wait time of the leading lead time portion of the updated tentative lead time together with processing time as a second target processing wait time, and a subsequent lead time portion having the subtraction inspection wait time of the subsequent lead time portion of the updated tentative lead time together with inspection time as a second target inspection wait time, The provisional manufacturing instruction and the regular manufacturing instruction are respectively set as a first provisional manufacturing instruction and a first regular manufacturing instruction, and in the conversion setting step (131b, 132), provisional manufacturing instruction data representing a second provisional manufacturing instruction obtained by inputting a second target processing wait time, a second target processing time, a second target inspection wait time, and a second target inspection time is converted and set into regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying each input content into the second provisional manufacturing instruction.

[0062] This makes it possible to provide a production management method that can achieve the effect of the invention of claim 10.

[0063] According to claim 12, the present invention provides a production management method according to claim 10, a sudden decrease determination step (130) for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; a waiting time adjustment step (134a) for adjusting the waiting time when the future calculated in-process quantity of the corresponding material suddenly decreases, when it is determined in the sudden decrease determination step that the number of orders for the ordered parts has suddenly decreased, to add a predetermined relaxation time (α) to the processing waiting time in the preceding lead time portion of the tentative lead time related to the setting, and set the result as an additional processing waiting time, and to add the predetermined relaxation time to the inspection waiting time in the succeeding lead time portion of the tentative lead time related to the setting, and set the result as an additional inspection waiting time; a tentative leadtime update setting step (134) for updating a processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting by an added processing wait time, and updating an inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting by an added inspection wait time, and setting both update results together with the processing time as an updated tentative leadtime (LT12), The target lead time (LT13) is set as a first target lead time, and the target processing wait time, target processing time, target inspection wait time and target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, in a target lead time setting step, in addition to the first target lead time, a second target lead time (LT12) is provided, and the second target lead time is set to be composed of a leading lead time section having an added processing wait time in the leading lead time section of the updated tentative lead time together with the processing time as a second target processing wait time, and a subsequent lead time section having an added inspection wait time in the subsequent lead time section of the updated tentative lead time together with the inspection time as a second target inspection wait time, The provisional manufacturing instruction and the regular manufacturing instruction are respectively set as a first provisional manufacturing instruction and a first regular manufacturing instruction, and in the conversion setting step (131b, 132), provisional manufacturing instruction data representing the second provisional manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time is converted and set into regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying the contents of the input to the second provisional manufacturing instruction.

[0064] This makes it possible to provide a production method that can achieve the effect of the invention described in claim 4.

[0065] The reference symbols in parentheses for each of the above means indicate the corresponding relationship with the specific means described in the embodiments described later. [Brief description of the drawings]

[0066] [Figure 1] 1 is a block diagram showing a first embodiment of a production management system according to the present invention which is applied to the company's own factories and both subcontracted factories. FIG. [Diagram 2] FIG. 2 is a block circuit diagram showing the production management system of FIG. 1. [Diagram 3] 3 is a block circuit diagram showing the relationship between the home server device and terminals in FIG. 2. [Figure 4] 4 is a detailed block circuit diagram showing the relationship between the receiving circuits and the terminals in FIG. 3. [Diagram 5] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 6] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 7] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 8] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 9] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 10] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 11] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 12] 4 is a part of a flowchart showing a computer program executed by a CPU in the first embodiment. [Figure 13] 13A is a diagram showing an order data table in the first embodiment, and FIG. 13B is a diagram showing a tentative lead time data table in the first embodiment. [Figure 14]FIG. 1(a) is a diagram showing the lead time portions at each workplace and each subcontract factory of the provisional lead time for round bar material in the first embodiment, and FIG. 1(b) is a diagram showing the lead time portions at each workplace of the provisional lead time for sheet metal material in the first embodiment. [Figure 15] 13 is a diagram showing a work-in-progress result data table in the first embodiment. [Figure 16] FIG. 2A is a diagram showing a blank form of a provisional manufacturing instruction in the first embodiment, and FIG. 2B is a diagram showing an input state of the blank form. [Figure 17] 13 is a diagram showing a target work-in-progress data table in the first embodiment. [Figure 18] 13 is a diagram showing a target lead time data table in the first embodiment. [Figure 19] 13A is a detailed diagram showing a target lead time when the quantity in process is excessive and the number of orders does not decrease suddenly, and FIG. 13B is a diagram showing a normal production instruction sheet when the quantity in process is excessive and the number of orders does not decrease suddenly. [Figure 20] 13A is a detailed diagram showing a target lead time when the work-in-process quantity is not excessive and the number of orders has suddenly decreased, and FIG. 13B is a diagram showing a normal production instruction when the work-in-process quantity is not excessive and the number of orders has suddenly decreased. [Figure 21] 1A is a detailed diagram showing a target lead time when the work-in-process quantity is not excessive and the number of orders is not suddenly decreasing, and FIG. 1B is a diagram showing a normal production order when the work-in-process quantity is not excessive and the number of orders is not suddenly decreasing. [Figure 22] FIG. 11 is a block diagram showing a second embodiment of a production management system according to the present invention that is applied only to one company. [Diagram 23] 13 is a diagram showing a main part of a third embodiment of a production management system according to the present invention. [Figure 24] 13 is a part of a flowchart of a computer program in the third embodiment. [Diagram 25] 13 is a part of a flowchart of a computer program in the third embodiment. [Figure 26]13 is a part of a flowchart of a computer program in the third embodiment. [Figure 27] 13 is a flowchart of a first interrupt program executed by a CPU in the third embodiment. [Figure 28] 13 is a flowchart of a second interrupt program executed by a CPU in the third embodiment. [Figure 29] 13 is a flowchart of a third interrupt program executed by a CPU in the third embodiment. [Diagram 30] 13 is a flowchart of a fourth interrupt program executed by a CPU in the third embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0067] Hereinafter, embodiments of the present invention will be described with reference to the drawings. (First embodiment) Fig. 1 shows a first embodiment of the production management system according to the present invention, which is applied to the company itself and the first and second outsourced factories. Here, the company itself is indicated by the symbol OC, the first outsourced factory is indicated by the symbol SF1, the second outsourced factory is indicated by the symbol SF2, and the production management system is indicated by the symbol S (see Fig. 1).

[0068] The company's OC has a warehouse 10 (hereinafter referred to as the company's warehouse 10) and a factory 20 (hereinafter referred to as the company's factory 20). The company's warehouse 10 is located near the company's factory 20, and is a warehouse that stores various materials. In the first embodiment, examples of parts that can be ordered at the company's OC include round bar parts, square bar parts, triangular bar parts, and sheet metal parts. Accordingly, among the various materials, round bar materials, square bar materials, triangular bar materials, and sheet metal materials are stored in the company's warehouse 10.

[0069] In the company's own factory 20, first to fourth workplaces 20a to 20d are disposed in separate locations as shown in FIG.

[0070] The first workplace 20a is a processing workplace where the materials fed from the company's warehouse 10 are cut and processed by a cutting machine (not shown). The cutting machine is installed in the first workplace 20a. The second workplace 20b is a processing workplace where the fed materials are pressed by a press machine (not shown). The press machine is installed in the second workplace 20b.

[0071] The third station 20c is a processing station for coating the fed materials with a coating device (not shown). The coating device is disposed within the third station 20c. The fourth station 20d is an inspection station for inspecting the fed materials with an inspection device (not shown). The inspection device is disposed within the fourth station 20d.

[0072] The first outsourcing factory SF1 is a processing factory for cutting the sent-in materials with a cutting machine (not shown). The cutting machine is located within the first outsourcing factory SF1. The second outsourcing factory SF2 is a processing factory for heat treating the sent-in materials with a heat treatment processing device (not shown). The heat treatment processing device is located within the second outsourcing factory SF2. In FIG. 1, the symbol DW indicates the delivery warehouse. Also, the symbol E indicates another company that outsources to the first outsourcing factory SF1.

[0073] The production management system S plays a role of managing the production of ordered parts received at the company's OC, and as shown in FIG. 2, the production management system S includes a home server device Sa, a registration device Sb, and a printing device Sc.

[0074] As shown in FIG. 2, the home server device Sa includes a computer 30 which is a server, an operating device 40, and a display device 50, and the computer 30 is connected between the operating device 40, the display device 50, the registration device Sb, and the printing device Sc.

[0075] As shown in FIG. 3, the computer 30 includes a CPU 31, a ROM 32, a RAM 33, and a receiving circuit group R. The CPU 31 executes a computer program according to the flowcharts shown in FIG. 5 to FIG. 12. During execution, the CPU 31, together with the RAM 33 and the registration device Sb, performs arithmetic processing required for creating and updating various data such as work-in-progress performance data, based on the operation output of the operation device 40 and the output of the receiving circuit group R, and also performs arithmetic processing required for display on the display device 40 and printing on the printing device Bb. In the first embodiment, the above-mentioned computer program is previously stored in the ROM 32 so as to be readable. The ROM 32 is a read-only memory element, and the RAM 33 is a temporary memory element.

[0076] The operation device 40 is composed of a keyboard, a mouse, etc., and inputs operation output to the computer 30 in response to the operation of the operation device 40. The display device 50 performs display processing based on the output from the computer 30.

[0077] As shown in FIG. 3, the receiving circuit group R receives transmission outputs from the terminal group P via the network N, and the receiving circuit group R is made up of a plurality of receiving circuits R0 to R13 (see FIG. 4).

[0078] Meanwhile, the terminal group P is made up of a plurality of tablet terminals P0 to P13. Each of the plurality of tablet terminals P01 to P13 is configured to transmit an operation output to the network N in response to a tap operation on the display surface, and the transmission is performed by a transmission circuit Pa built into each of the plurality of tablet terminals P0 to P13. In the present first embodiment, hereinafter, the tablet terminals will be simply referred to as terminals.

[0079] In this embodiment, the locations of the multiple terminals P0 to P13 of the terminal group P will be described with reference to Fig. 1. The terminal P0 is installed in the company's warehouse 10. When the terminal P0 receives a regular production instruction Q (described later) as data from the home server system S, the terminal P0 is tapped. With this tapping operation, the terminal P0 transmits data representing the regular production instruction Q to the network N as an operation output through its transmission circuit Pa. Here, the receipt information for the data representing the regular production instruction Q is composed of the contents and receipt date of the regular production instruction Q at the company's warehouse 10.

[0080] Both terminals P1 and P2 are installed in the first workplace 20a. When the material is received at the first workplace 20a from the company's warehouse 10, the terminal P1 is tapped. In response to this tapping operation, the terminal P1 transmits information indicating the receipt of the material (hereinafter also referred to as material receipt data) as an operation output to the network N through its transmission circuit Pa. The above-mentioned material receipt data is composed of the type of received material, the date and time of receipt, and the receiving and processing workplace (the first workplace 20a).

[0081] On the other hand, terminal P2 is tapped when the cut material is to be sent out as a result of the completion of cutting of the received material at the first workplace 20a. With this tapping operation, terminal P2 transmits, via its transmission circuit Pa, sending data for the cut material as an operation output to the network N. The sending data for the cut material is composed of the type of material, the sending date and time, and the sending processing workplace (first workplace 20a).

[0082] Both terminals P3 and P4 are disposed in the second workplace 20b. When the second workplace 20b receives the material cut and processed in the first workplace 20a, the terminal P3 is tapped. In response to this tapping operation, the terminal P3 transmits the material receipt data from the first workplace 20a to the network N as an operation output through its transmission circuit Pa. The above-mentioned material receipt data is composed of the type of received material, the date and time of receipt, and the receiving and processing workplace (the second workplace 20b).

[0083] On the other hand, the terminal P4 is tapped when the press-processed material is sent out after the press processing of the received material at the second workplace 20b is completed. With this tapping operation, the terminal P2 transmits the sending data of the material that has been press-processed at the second workplace 20b as an operation output to the network N through its transmission circuit Pa. The sending data of the material by the terminal P2 described above is composed of the type of the received material at the second workplace 20b, the sending date and time, and the sending processing workplace (second workplace 20b).

[0084] Both terminals P5 and P6 are disposed in the third workplace 20c. The terminal P5 is tapped when the third workplace 20c receives a material that has been pressed in the second workplace 20b or machined in the second outsourcing factory SF2. In response to this tapping operation, the terminal P5 transmits, via its transmission circuit Pa, data on the receipt of the material from the second workplace 20b or the second outsourcing factory SF2 to the network N as an operation output. The data on the receipt of the material from the second workplace 20b or the second outsourcing factory SF2 is composed of the type of the received material, the date and time of receipt, and the receiving and processing workplace (the third workplace 20c).

[0085] On the other hand, the terminal P6 is tapped when the painted material is sent out as the painting of the received material is completed at the third workplace 20c. With this tapping operation, the terminal P6 transmits, via its transmission circuit Pa, the sending data of the material that has been painted at the third workplace 20c as an operation output to the network N. The sending data of the material that has been painted at the third workplace 20c described above is composed of the type of material, the sending date and time, and the sending processing workplace (the third workplace 20c) from the second workplace 20b or the second outsourcing factory B.

[0086] Both terminals P7 and P8 are disposed in the fourth workplace 20d. When the fourth workplace 20d receives the material that has been painted in the third workplace 20b, the terminal P7 is tapped. In response to this tapping operation, the terminal P7 transmits the receipt data of the material from the third workplace 20b as an operation output to the network N through its transmission circuit Pa. The receipt data of the material from the third workplace 20b described above is composed of the type of material received from the third workplace 20c, the date and time of receipt, and the receiving and processing workplace (the fourth workplace 20d).

[0087] On the other hand, terminal P8 is tapped when the inspection of the received material at the fourth workplace 20b is completed and the inspected material is to be sent. With this tapping operation, terminal P8 transmits the sending data of the material from the fourth workplace 20b as an operation output to the network N through its transmission circuit Pa. The sending data of the material from the fourth workplace 20b described above is composed of the type of the received material, the sending date and time, and the sending processing workplace (fourth workplace 20d) at the fourth workplace 20c.

[0088] Both terminals P9 and P10 are installed in the first outsourcing factory SF1. The terminal P9 is tapped when the first outsourcing factory SF1 receives the material cut and processed in the first workplace 20b. In response to this tapping operation, the terminal P9 transmits the receipt data of the material from the first workplace 20a as an operation output to the network N through its transmission circuit Pa. The receipt data of the material from the first workplace 20a described above is composed of the type of the received material from the first workplace 20a, the receipt date and time, and the receiving site (first outsourcing factory SF1).

[0089] On the other hand, the terminal P10 is tapped when the cutting process of the received material is completed at the first outsourcing factory SF1 and the material is sent after the cutting process. With this tapping operation, the terminal P10 transmits the sending data of the material after the cutting process at the first outsourcing factory SF1 as an operation output to the network N through its transmission circuit Pa. The sending data of the material after the cutting process at the first outsourcing factory SF1 described above is composed of the type of the received material at the first outsourcing factory B, the sending date and time, and the sending source (first outsourcing factory SF1).

[0090] Both terminals P11 and P12 are installed in the second outsourcing factory SF2. The terminal P11 is tapped when the second outsourcing factory SF2 receives the material machined at the first outsourcing factory SF1. With this tapping operation, the terminal P11 transmits the receipt data of the material from the first outsourcing factory SF1 as an operation output to the network N through its transmission circuit Pa. The receipt data of the material from the first outsourcing factory SF1 described above is composed of the type of the received material from the first outsourcing factory SF1, the receipt date and time, and the receipt site (second outsourcing factory SF2).

[0091] On the other hand, the terminal P12 is tapped when the received material is sent after the heat treatment process at the second outsourcing factory SF2 is completed. With this tapping operation, the terminal P12 transmits the sending data of the material as an operation output to the network N through its transmission circuit Pa. The sending data of the material from the second outsourcing factory SF2 described above is composed of the type of the received material, the sending date and time, and the sending field (second outsourcing factory SF2) at the second outsourcing factory SF2.

[0092] The terminal P13 is installed in the destination warehouse DW. The terminal P13 is tapped when the inspected material from the fourth workplace 20d of the company's factory 20 is received as a finished product at the destination warehouse DW. With this tapping operation, the terminal P13 transmits the receipt data of the finished product from the fourth workplace 20d as an operation output to the network N through its transmission circuit Pa. The receipt data of the finished product described above is composed of the type of the finished product received from the second workplace 20d, the receipt date and time, and the receipt location (destination warehouse DW).

[0093] Next, the relationship between the multiple terminals P0 to P13 of the terminal group P and the multiple receiving circuits R0 to R13 of the receiving circuit group R will be described with reference to Fig. 4. The receiving circuit R0 receives an operation output from the terminal P0 of the company warehouse 10 via the network N.

[0094] The receiving circuit R1 receives, via the network N, an operation output from a terminal P1 in the first workplace 20a, and the receiving circuit R2 receives, via the network N, an operation output from a terminal P2 in the first workplace 20a.

[0095] The receiving circuit R3 receives an operation output from a terminal P3 of the second workplace 20b via the network N, and the receiving circuit R4 receives an operation output from a terminal P4 of the second workplace 20b via the network N. The receiving circuit R5 receives an operation output from a terminal P5 of the third workplace 20c via the network N, and the receiving circuit R6 receives an operation output from a terminal P6 of the third workplace 20c via the network N. In addition, the receiving circuit R7 receives an operation output from a terminal P7 of the fourth workplace 20d via the network N, and the receiving circuit R8 receives an operation output from a terminal P8 of the fourth workplace 20d via the network N.

[0096] The receiving circuit R9 receives an operation output from the terminal P9 of the first outsourced factory SF1 via the network N, and the receiving circuit R10 receives an operation output from the terminal P10 of the first outsourced factory SF1 via the network N. The receiving circuit R11 receives an operation output from the terminal P11 of the second outsourced factory SF2 via the network N, and the receiving circuit R12 receives an operation output from the terminal P12 of the second outsourced factory SF2 via the network N. In addition, the receiving circuit R13 receives an operation output from the terminal P13 of the delivery warehouse D via the network N. Each of the receiving circuits R0 to R13 outputs the received operation output to the CPU 31.

[0097] The registration device Sb is made up of a hard disk, and registers various data such as work-in-progress performance data as various tables and updates the tables under the control of the CPU 31. The printing device Sc performs printing processing of the manufacturing instructions and output processing thereof under the control of the CPU 31.

[0098] In the first embodiment configured as above, when the production management system S is put into operation, the computer 30 of the home server device Sa starts executing the computer program in the CPU 31 according to the flowcharts shown in Figs. 5 to 12. Below, the explanation will be given separately for a mode for creating a regular production instruction based on a newly ordered part and a mode for manufacturing the newly ordered part. Note that the regular production instruction refers to the production instruction required to manufacture each lot of the newly ordered part. 1. Formation mode of regular production orders based on new order parts In the mode of forming the regular manufacturing instructions, the regular manufacturing instructions are formed for each lot of the total number of lots of newly ordered parts. Furthermore, among the regular manufacturing instructions for each lot, the first regular manufacturing instruction is formed based on a temporary manufacturing instruction, which will be described later, and the subsequent regular manufacturing instructions are formed based on the preceding regular manufacturing instruction. (1) When the future work-in-progress quantity of the selected material is excessive As described above, when the execution of the computer program is started, the CPU 31 judges whether or not a new order has been received in step 100 of Fig. 5. If new order data exists in the order data table 1 (see Fig. 13(a)) in the registration device Sb, it means that a new order has been received, and the judgment in step 100 becomes YES.

[0099] In the first embodiment, the order data table 1 is registered in the registration device Sb. As shown in Fig. 13(a), the order data table 1 is configured for each order by order data consisting of the order recipient, ordered parts, order date, order lot size, and delivery date.

[0100] At this stage, it is assumed that both order data OD1 and OD2 have been newly registered in the order data table 1. The order data OD1 is composed of order recipient: K1, ordered parts: G1, order date: M1, order lot size: L1, and delivery date: M11. The order data OD2 is composed of order recipient: K1, ordered parts: G2, order date: M2, order lot size: L2, and delivery date: M: 22.

[0101] Here, in the order data OD1, the order part G1 represents a round bar part. Meanwhile, in the order data OD2, the order part G2 represents a sheet metal part. The order data table 1 is updated in the registration device Sb with each new order.

[0102] After the process of step 100, in step 110, it is determined whether the newly ordered part is within a predetermined part range. In this first embodiment, the predetermined part range is round bar parts, square bar parts, triangular bar parts, and sheet metal parts. Here, ordered parts G1 and G2 are round bar parts and sheet metal parts, respectively, and are parts within the predetermined part range, so the determination in step 110 is YES.

[0103] Thereafter, in the next step 110a, it is determined whether the newly ordered part is a round bar part. If the newly ordered part is a round bar part, the determination in step 110a is YES. Next, in step 111, a process for setting the part to be manufactured is performed. Here, the round bar part is set as the part to be manufactured. The part to be manufactured corresponds to one of the round bar parts in a single lot.

[0104] Accordingly, in step 112, a material selection process for the set manufacturing target part is performed. In the material selection process, since the set manufacturing target part is a round bar part, a round bar blank is selected as the material. Note that the round bar blank corresponds to any one of the round bar blanks in a single lot that corresponds to the single lot of round bar parts.

[0105] Thereafter, in step 113, a process of reading out the tentative lead time data of the selected material is performed. Here, since the selected material is a round bar material, the tentative lead time of the round bar material represents the lead time required to manufacture each round bar part (each set manufacturing target part) of a single lot of a round bar part group from each round bar material of a single lot of a round bar material group. The tentative lead time data of the round bar material is read out from the tentative lead time data table 2 in the registration device Sb (see FIG. 13(b)).

[0106] In this first embodiment, the provisional lead time data table 2 is registered in the registration device Sb, and the provisional lead time data table 2 is configured for each provisional lead time data, as shown in Figure 13(b), with provisional lead time data consisting of selected materials and their provisional lead times.

[0107] In the provisional lead time data table 2, provisional lead time data TD1 is made up of the selected material, a round bar material, and its provisional lead time LT1. Provisional lead time data TD2 is made up of the selected material, a square bar material, and its provisional lead time LT2. Provisional lead time data TD3 is made up of the selected material, a triangular bar material, and its provisional lead time LT3. Furthermore, provisional lead time data TD4 is made up of the selected material, a sheet metal material, and its provisional lead time LT4. When the ordered part is a new part, a provisional lead time for the corresponding material corresponding to the new part is set in this way, but in the case of a new repeat order from an order-receiving department that has a production record in the past, the provisional lead time is called up from the lead time table related to the current settings and used as the provisional lead time.

[0108] In the first embodiment, the tentative lead time refers to the time in the production plan from when the material is input from the company warehouse 10 to the company factory 20 until it is manufactured into a finished product. From the viewpoint of production management, it is desirable that the tentative lead time is as short as possible, assuming the delivery date of the set manufacturing target parts (ordered parts).

[0109] However, in the process from when the material is brought from the company's warehouse 10 to the company's factory 20 until it is manufactured into a finished product, the material is subjected to various necessary processing and inspections until it becomes a set manufacturing target part.

[0110] For example, in the case where the set manufacturing target part is a round bar part, the round bar material which is the raw material for the round bar part is brought from the in-house warehouse 10 into the in-house factory 20, and then passes through a route which passes through the first workplace 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third workplace 20c, and the fourth workplace 20d of the in-house factory 20 in that order (hereinafter referred to as the round bar part manufacturing route), and is sequentially processed or inspected at each of the first workplace 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third workplace 20c, and the fourth workplace 20d to become a finished product (round bar part) (see Figure 1).

[0111] Here, when cutting the round bar material at the first work station 20a, it is necessary to consider not only the cutting time of the round bar material but also the setup work suitable for cutting the round bar material. Moreover, if there is an excess of round bar material sent to the first work station 20a, the round bar material following the preceding round bar material will have to wait for the cutting process to be completed, and will have to remain in the first work station 20a. The more round bar materials sent to the first work station 20a, the longer the time the following round bar material will have to wait for cutting. In the first embodiment, the time the following round bar material waits for cutting is called the cutting process waiting time.

[0112] Therefore, in the first workplace 20a, a lead time section (hereinafter referred to as lead time section LT1A) consisting of the sum of the cutting processing waiting time (hereinafter referred to as cutting processing waiting time T1A) and the subsequent cutting processing time (hereinafter referred to as cutting processing time H1A) is required (see Figure 14(a)).

[0113] In addition, in the first outsourcing factory SF1, when cutting the cut round bar material from the first workplace 20a, it is necessary to consider the setup work suitable for cutting the cut round bar material as well as the cutting time of the cut round bar material. Moreover, if there is an excess of cut round bar material sent from the first workplace 20a to the first outsourcing factory SF1, the cut round bar material following the preceding cut round bar material will have to wait for the cutting time until the cutting of the preceding cut round bar material is completed, and will have to remain in the first outsourcing factory SF1.

[0114] In addition, in the above-mentioned state in which the cut-processed round bar material is held up in the first outsourcing factory SF1, the first outsourcing factory SF1 may receive an order from another company E (see FIG. 1) other than the company OC. Regardless of whether the material of the parts ordered from the other company E (hereinafter referred to as the outsourcing factory ordered material) is a cut-processed round bar material or not, the outsourcing factory ordered material will be held up in the first outsourcing factory SF1 for the time it takes to wait for cutting due to the above-mentioned holdup. The time it takes to wait for cutting becomes longer as the number of cut-processed round bar materials sent from the first workplace 20a to the first outsourcing factory SF1 and the number of parts ordered from the other company E to the first outsourcing factory SF1 increases. In the first embodiment, the time it takes to wait for cutting is referred to as a cutting waiting time.

[0115] Therefore, in the first outsourcing factory SF1, a lead time section (hereinafter referred to as lead time section LT1B) consisting of the sum of the cutting processing waiting time (hereinafter referred to as cutting processing waiting time T1B) and the subsequent cutting processing time (hereinafter referred to as cutting processing time H1B) is required (see Figure 14(a)).

[0116] In addition, when the second outsourcing factory SF2 heat treats the machined round bar material and materials ordered by the cutting outsourcing factory from the first outsourcing factory SF1, in addition to the heat treatment time for the machined round bar material and materials ordered by the cutting outsourcing factory, it is necessary to take into account the setup work suitable for heat treating the machined round bar material and materials ordered by the cutting outsourcing factory.

[0117] Furthermore, when the second outsourcing factory SF2 receives an excess of machined round bar blanks from the first outsourcing factory SF1, the machined round bar blanks following the preceding machined round bar blanks must wait for heat treatment until the heat treatment of the preceding machined round bar blanks is completed, and must remain at the second outsourcing factory SF2. The time to wait for heat treatment becomes longer as the number of machined round bar blanks sent from the first outsourcing factory SF1 to the second outsourcing factory SF2 increases. In the first embodiment, the time to wait for heat treatment is referred to as the heat treatment waiting time.

[0118] Therefore, at the second outsourcing factory SF2, a lead time section (hereinafter referred to as lead time section LT1C) is required which consists of the sum of the heat treatment processing waiting time (hereinafter referred to as heat treatment processing waiting time T1C) and the subsequent heat treatment processing time (hereinafter referred to as heat treatment processing time H1C) (see Figure 14(a)).

[0119] In addition, when the third workplace 20c of the company's own factory 20 paints the heat-treated round bar material from the second outsourced factory SF2, it is necessary to take into account not only the painting processing time of the heat-treated round bar material, but also the setup work suitable for painting the heat-treated round bar material.

[0120] Furthermore, if there is an excess of heat treated round bar material from the second outsourcing factory SF2 at the third workplace 20c, the heat treated round bar material following the preceding heat treated round bar material will have to wait for the painting process to be completed until the painting process of the preceding heat treated round bar material is completed, and will have to remain at the third workplace 20c.

[0121] In addition, in the above-mentioned state in which the heat-treated round bar material is stored in the third work station 20c, the third work station 20c may receive materials from the second work station 20b or other work stations. Regardless of whether the materials are heat-treated round bar materials or not, the materials will remain in the third work station 20c for the time they are waiting for painting due to the above-mentioned retention. The more heat-treated round bar materials are sent from the second outsourcing factory SF2 to the third work station 20c and the more materials are sent from the first work station 20b or other work stations, the longer the time they will wait for painting. In the first embodiment, the time they will wait for painting is called the painting waiting time.

[0122] Therefore, in the third workplace 20c, a lead time portion (hereinafter referred to as lead time portion LT1D) is required which is the sum of the painting process waiting time (hereinafter referred to as painting process waiting time T1D) and the subsequent painting process time (hereinafter referred to as painting process time H1D) (see Figure 14(a)).

[0123] In addition, when inspecting painted round bar material from the third workplace 20c at the fourth workplace 20d of the company's own factory 20, in addition to the inspection time of the round bar material after painting processing, it is necessary to take into account the setup work suitable for inspecting the round bar material after painting processing.

[0124] Furthermore, if there is an excess of painted round bar materials from the third work station 20c or materials from work stations other than the third work station 20c at the fourth work station 20d, the painted round bar materials following the preceding painted round bar materials will have to remain at the fourth work station 20d while waiting for inspection until the inspection of the preceding painted round bar material is completed. The waiting time for inspection will be longer as more painted round bar materials are fed from the third work station 20c to the fourth work station 20d. In this first embodiment, the waiting time for inspection as described above is called the inspection waiting time.

[0125] Therefore, in the fourth workplace 20d, a lead time section (hereinafter referred to as the lead time section LT1E) consisting of the sum of the inspection waiting time (hereinafter referred to as the inspection waiting time T1E) and the subsequent inspection time (hereinafter referred to as the inspection time H1E) is required (see Figure 14(a)).

[0126] According to the above, the tentative lead time of the round bar material (hereinafter referred to as tentative lead time LT1) is composed of the lead time parts LT1A, LT1B, LT1C, LT1D and LT1E added in this order (see FIG. 14(a)). This means that the tentative lead time data TD1 consists of the round bar material and the tentative lead time LT1 (see FIG. 13(b)).

[0127] Here, in the tentative lead time LT1, the lead time section LT1A is made up of a cutting waiting time T1A and a cutting time H1A, the lead time section LT1B is made up of a cutting waiting time T1B and a cutting time H1B (see FIG. 14(a)), the lead time section LT1C is made up of a heat treatment waiting time T1C and a heat treatment time H1C, the lead time section LT1D is made up of a painting waiting time T1D and a painting time H1D, and the lead time section LT1E is made up of an inspection waiting time T1E and an inspection time H1E (see FIG. 14(a)).

[0128] Furthermore, when the set production target part is a square bar part, the provisional lead time data TD2 is made up of the square bar part and its provisional lead time LT2 as described above (see FIG. 13(b)). When the set production target part is a triangular bar part, the provisional lead time data TD3 is made up of the triangular bar part and its provisional lead time LT3 as described above (see FIG. 13(b)).

[0129] Here, a square bar part or a triangular bar part has a common shape with a round bar part. Therefore, in the case of a square bar part or a triangular bar part, the material for the square bar part or the triangular bar part (square bar material or triangular bar material) goes through the same manufacturing route as a round bar part to become a finished product (square bar part or triangular bar part).

[0130] Accordingly, the tentative lead times LT2 and LT3 for the square bar material and the triangular bar material have the same structure as the tentative lead time LT1 for the round bar material described above. This means that the tentative lead times LT2 and LT3 are substantially the same as the tentative lead time LT1.

[0131] In addition, due to differences between square bar parts or triangular bar parts and round bar parts (for example, differences in forming materials, etc.), the tentative lead time LT2 or LT3 of the square bar material or triangular bar material may differ in some parts from the tentative lead time LT1 of the round bar material. For example, in the tentative lead time LT2 or LT3, the cutting processing time H1B may differ in length from the cutting processing time H1B in the tentative lead time LT1.

[0132] As described above, the provisional lead time data TD4 is composed of the sheet metal parts, which are the set manufacturing target parts, and their provisional lead time LT4 (see FIG. 13(b)). When the set manufacturing target parts are sheet metal parts, the sheet metal material, which is the raw material of the sheet metal parts, is brought from the company warehouse 10 to the company factory 20, and then cut and processed in sequence along a route that passes through the first workplace 20a, the second workplace 20b, the third workplace 20c, and the fourth workplace 20d of the company factory 20 in sequence (hereinafter referred to as the sheet metal part manufacturing route) to become a finished product (sheet metal part).

[0133] Here, in the first workplace 20a, when cutting sheet metal material, a lead time portion (hereinafter referred to as lead time portion LT4A) consisting of the sum of the cutting process waiting time (hereinafter referred to as cutting process waiting time T4A) and the subsequent cutting process time (hereinafter referred to as cutting process time H4A) is required, based on the same reasons as when cutting round bar material (see Figure 14(b)).

[0134] Furthermore, in the second workplace 20b, when the cut sheet metal material from the first workplace 20a is pressed, as in the case of other workplaces, not only is the press processing time required for the cut sheet metal material to be pressed, but also the time required to wait for the press processing due to setup work in the second workplace 20b and the retention of the cut sheet metal material (hereinafter referred to as press processing waiting time).

[0135] In short, in the second workplace 20b, a lead time section (hereinafter referred to as lead time section LT4B) consisting of the sum of the press processing waiting time (hereinafter referred to as press processing waiting time T4B) and the subsequent press processing time (hereinafter referred to as press processing time H4B) is required (see Figure 14(b)).

[0136] In addition, in the third workplace 20c, when the pressed sheet metal material from the second workplace 20b is painted, not only the painting process time but also the waiting time for the painting process is required for the same reasons as in the case of the painting process in the third workplace 20c for the heat treated round bar material described above.

[0137] In short, in the third workplace 20c, a lead time section (hereinafter referred to as lead time section LT4C) consisting of the sum of the painting processing waiting time (hereinafter referred to as painting processing waiting time T4C) and the subsequent painting processing time (hereinafter referred to as painting processing time H4C) is required (see Figure 14(b)).

[0138] In addition, in the fourth plant 20d, when inspecting the painted sheet metal material from the third plant 20c, not only the inspection time but also the waiting time for the inspection is required for the same reasons as in the case of the inspection of the painted round bar material in the fourth plant 20d described above.

[0139] In short, the fourth workplace 20c requires a lead time section (hereinafter referred to as lead time section LT4D) consisting of the sum of the inspection waiting time (hereinafter referred to as inspection waiting time T4D) and the subsequent inspection time (hereinafter referred to as inspection time H4D) (see FIG. 14(b)). In this embodiment, the above-mentioned cutting processing time, pressing processing time, machining processing time, heat treatment processing time, and painting processing time may be simply referred to as processing time. Also, the cutting processing waiting time, pressing processing waiting time, machining processing waiting time, heat treatment processing waiting time, painting processing waiting time, and inspection waiting time may be simply referred to as waiting time.

[0140] According to the above, the tentative lead time LT4 of the sheet metal material is formed by sequentially adding up the lead time portions LT4A, LT4B, LT4C and LT4D in this order (see FIG. 14(b)).

[0141] Here, in the tentative lead time LT4, the lead time section LT4A is composed of a cutting processing wait time T4A and a cutting processing time H4A, the lead time section LT4B is composed of a press processing wait time T4B and a cutting processing time H4B, and is composed of a painting processing wait time T4C and a painting processing time H4C, and the lead time section LT4D is composed of an inspection wait time T4D and an inspection time H4D (see Figure 14(b)).

[0142] After the process of step 112, in step 113, a process of reading out the tentative lead time data of the selected material is performed. At the current stage, since a round bar material is selected as the material in step 112, the tentative lead time data D1 of the round bar material is read out from the tentative lead time data table 2 of the registration device Sb (see Fig. 13(b) and Fig. 14(a)). The tentative lead time LT1 in the tentative lead time data D1 is composed of each lead time section LT1A to LT1E as described above (see Fig. 14(a)). When the ordered part is a new part, the tentative lead time of the corresponding material corresponding to the part is set, but in the case of a new repeat order of a corresponding part that has been produced in the past, the tentative lead time is called up from the lead time table in the current setting. Also, the tentative lead time LT1 and each lead time section LT1A (T1A, H1A) to LT1E (T1E, H1E) at the current stage are set to predetermined initial values.

[0143] In this embodiment, the tentative lead time LT1 corresponds to all the round bar materials in a single lot, and is the sum of the lead time portions LT1A to LT1E. Therefore, the predetermined initial value of the tentative lead time LT1 is determined based on the predetermined initial values ​​of the lead time portions LT1A to LT1E.

[0144] Here, the specified initial values ​​of each lead time section LT1A to LT1E are determined as follows by the production management department of the company's OC, with reference to drawings from the customer regarding the round bar parts that are the parts to be manufactured (hereinafter also referred to as round bar part drawings).

[0145] Of the lead time sections LT1A to LT1E, the lead time section LT1A corresponds to the first workplace 20a. Therefore, when determining the cutting processing time T1A of the lead time section LT1A, the cutting method of the round bar material is determined based on the above-mentioned round bar part drawing.

[0146] Accordingly, the cutting processing time T1A of the lead time section LT1A is determined on the premise of the determined cutting method. After that, the cutting processing waiting time H1A of the lead time section LT1A is set to a waiting time multiple (for example, 6 times the cutting processing time T1A) within a range of multiples of a predetermined waiting time (hereinafter, referred to as a predetermined waiting time multiple range). In this embodiment, the above-mentioned predetermined waiting time multiple range is, for example, a range of 5 times to 10 times. The predetermined waiting time multiple range may be appropriately changed as necessary.

[0147] In addition, both lead-time sections LT1B and LT1C correspond to the first and second outsourced factories SF1 and SF2, respectively. Therefore, when determining the cutting time T1B of the lead-time section LT1B and the heat treatment time T1C of the lead-time section LT1C, the cutting method of the round bar material after cutting and the heat treatment method after cutting are determined based on the above-mentioned round bar part drawing.

[0148] Accordingly, the cutting time T1B and the heat treatment time T1C of the lead time parts LT1B and LT1C are determined on the basis of the determined cutting method and heat treatment method. After that, the cutting waiting time H1B of the lead time part LT1B and the heat treatment waiting time H1C of the lead time part LT1C are set to waiting time multiples within the above-mentioned predetermined waiting time multiple range (for example, six times each of the cutting time T1B and the heat treatment time T1C).

[0149] Moreover, both lead-time sections LT1D and LT1E correspond to the third and fourth workplaces 20c and 20d, respectively. Therefore, in determining the painting processing time T1D of the lead-time section LT1D and the heat treatment processing time T1E of the lead-time section LT1E, the painting processing method of the round bar material after the heat treatment processing and the inspection method after the painting processing are determined based on the above-mentioned round bar part drawing.

[0150] Accordingly, the painting process time T1D of the lead time section LT1D and the inspection time T1E of the lead time section LT1E are determined based on the determined painting process method and inspection method. After that, the painting process waiting time H1D of the lead time section LT1D and the inspection waiting time H1E of the lead time section LT1E are set to waiting time multiples within the above-mentioned predetermined waiting time multiple range (for example, 6 times each of the painting process time T1D and the inspection time T1E).

[0151] Thereafter, a process of reading out the in-process record data of the selected material is performed in step 114. Here, the in-process record data of the selected material, the round bar material, is read out from the in-process record table data 3 (see FIG. 15) in the registration device Sb.

[0152] The in-process performance data table 3 is registered in the registration device Sb, and as shown in FIG. 15, the in-process performance data table 3 is composed of a plurality of in-process performance data IPD1, IPD2, IPD3, IPD4, IPDSF1 and IPDSF2.

[0153] Here, the in-process performance data IPD1 represents the in-process performance at the first workplace 20a. In the in-process performance data IPD1, among the round bar material, square bar material, triangular bar material, and sheet metal material, the round bar material and the sheet metal material are respectively included in the in-process performance data IPD1, and the receipt date (u The period, date of receipt, number of receipts, date of sending, and number of sending are registered for square bar materials and triangular bar materials.

[0154] The work-in-progress performance data IPD2 represents the work-in-progress performance at the second workplace 20b, and in this work-in-progress performance data IPD2, the receipt dates (v1, v2, ...), receipt quantities (n1, n2, ...), dispatch dates (V1, V2, ...), and dispatch quantities (N1, N2, ...) for sheet metal materials are registered for a period going back from today (y year m month d day) (for example, one month).

[0155] The in-process performance data IPD3 represents the in-process performance at the third workplace 20c, and in this in-process performance data IPD3, for round bar materials, square bar materials, triangular bars, and sheet metal materials, the receipt dates (w1, w2,...), receipt quantities (o1, o2,...), dispatch dates (W1, W2,...), and dispatch quantities (O1, O2,...) for the period going back (e.g., one month) from today (y year m month d day) are registered for round bar materials and sheet metal materials. Note that for square bar materials and triangular bar materials, the respective periods, receipt dates, receipt quantities, dispatch dates, and dispatch quantities are registered.

[0156] The in-process performance data IPD4 represents the in-process performance at the fourth workplace 20d, and in this in-process performance data IPD4, for the round bar stocks and sheet metal stocks out of the round bar stocks, square bar stocks, triangular bar stocks, and sheet metal stocks, the receipt dates (x1, x2,...), receipt quantities (r1, r2,...), dispatch dates (X1, X2,...), and dispatch quantities (R1, R2,...) for the period going back (e.g., one month) from today (y year m month d day) are registered. Note that for the square bar stocks and triangular bar stocks, the respective periods, receipt dates, receipt quantities, dispatch dates, and dispatch quantities are registered.

[0157] The in-process performance data IPDSF1 represents the in-process performance at the first outsourcing factory SF1, and in this in-process performance data IPDSF1, for round bar materials out of the round bar materials, square bar materials, and triangular bars, the receipt dates (y1, y2,...), receipt quantities (q1, q2,...), dispatch dates (Y1, Y2,...), and dispatch quantities (Q1, Q2,...) going back in time (for example, one month) from today (y year m month d day) are registered. For square bar materials and triangular bar materials, the respective periods, receipt dates, receipt quantities, dispatch dates, and dispatch quantities are registered.

[0158] The in-process performance data IPDSF2 represents the in-process performance at the second outsourcing factory SF1, and in this in-process performance data IPDSF2, for round bar materials out of the round bar materials, square bar materials, and triangular bars, the receipt dates (z1, z2,...), receipt quantities (r1, r2,...), dispatch dates (Z1, Z2,...), and dispatch quantities (R1, R2,...) for a period going back (for example, one month) from today (y year m month d day) are registered. For square bar materials and triangular bar materials, the respective periods, receipt dates, receipt quantities, dispatch dates, and dispatch quantities are registered.

[0159] Thus, in step 114, the in-process record data IPD1, IPD3, IPD4, IPDSF1 and IPDSF2 of the round bar material, which is the selected material, are read out from the in-process record data table 3 of the registration device Sb.

[0160] Next, in step 115 (see FIG. 6), a process for calculating the future in-process quantity of the selected material is performed.

[0161] Here, the term "selected materials" refers to all selected materials in the selected materials group of all lots corresponding to the ordered parts group of all ordered lots. Also, the future in-process quantity refers to the future in-process quantity of all selected materials in the selected materials group of all lots (for example, the in-process quantity for one month from today).

[0162] At the current stage, since the selected material is a round bar material, the future in-process quantities of all the round bar materials in the round bar material group of all lots corresponding to the round bar part group of all the ordered lots are calculated based on the ordered lot number L1 of the new order data OD1 (see Figure 13(a)).

[0163] Here, at the current stage, the order lot number L1 of the order data OD1 is L1 as described above. Therefore, the calculation of the future in-process quantity of the round bar raw material is performed based on the order lot number L1.

[0164] Thereafter, in the next step 116, input processing is performed for a temporary manufacturing instruction for the selected round bar material. In this input processing, data (hereinafter referred to as temporary manufacturing instruction blank form data) representing a temporary manufacturing instruction blank form PBF (see FIG. 16(a)) is read out from the registration device Sb and displayed on the display surface of the display device 50.

[0165] Accordingly, under the operation of the operation device 40 of the computer 30, the part number, lot number, input date, completion date, tentative lead time, and procedure of the round bar material as a group of round bar materials are input into the blank form PBF (see FIG. 16(b)). Note that the input date refers to the date preceding the completion date by the tentative lead time LT1.

[0166] Specifically, the part number for the round bar material group: F962, lot number: #LOT1, input date: xx day, completion date: yy day, and tentative lead time: LT1 are entered (see Figure 16(b)).

[0167] The procedure is input as follows (see FIG. 16(b)). For cutting, waiting time: T1A and processing time: H1A are input in the cutting processing column. For cutting, waiting time: T1B and processing time: H1B are input in the cutting processing column. For heat treatment, waiting time: T1C and processing time: H1C are input in the heat treatment processing column. For painting, waiting time: T1D and processing time: H1D are input in the painting processing column. For inspection, waiting time: T1E and inspection time: H1E are input in the inspection column. Each waiting time and each processing time is derived from each lead time section LT1A to LT1E in FIG. 14(a). As a result, the provisional manufacturing instruction blank form PBF is created as a provisional manufacturing instruction PBFa (see FIG. 16(b)). Thereafter, the temporary manufacturing instruction PBFa is stored in the RAM 33.

[0168] In the next step 117, the target work-in-progress data of the selected material is read out. The target work-in-progress data of the selected material indicates the future work-in-progress schedule and the target number of work-in-progress items in the production plan of the selected material. The future work-in-progress schedule refers to the work-in-progress schedule for the next day and thereafter, for example, for one month.

[0169] In the process of reading out the target work-in-progress data, since the selected material is a round bar material at the current stage, the target work-in-progress data TND1 is read out from the target work-in-progress data table 4 (see FIG. 17) in the registration device Sb.

[0170] The in-process target data table 4 is registered in the registration device Sb, and as shown in FIG. 17, the in-process target data table 4 is composed of a plurality of in-process target data TND1 to TND4.

[0171] Of these in-process target data TND1 to TND4, the in-process target data TND1 is composed of the in-process date and in-process target quantity of the round bar material. Here, the in-process dates are future in-process dates a1, a2, .... In-process date a1 refers to the day after today (x year m month d day), and in-process date a2 refers to the day after in-process date a1. Also, the in-process target quantities for the in-process dates a1, a2, ... are A1, A11, ....

[0172] The work-in-progress target data TND2 is composed of the work-in-progress dates and work-in-progress target quantities of square bar materials. Here, the work-in-progress dates of the square bar materials are future work-in-progress dates b1, b2 (the day after b1), .... Also, the work-in-progress target quantities for each of the work-in-progress dates b1, b2, ... are B1, B11, ....

[0173] The work-in-progress target data TND3 is composed of the work-in-progress dates and work-in-progress target quantities of triangular bar materials. Here, the work-in-progress dates of the triangular bar materials are future work-in-progress dates c1, c2 (the day after c1), .... Also, the work-in-progress target quantities for each of the work-in-progress dates c1, c2, ... are C1, C11, ....

[0174] The target work-in-progress data TND4 is composed of the work-in-progress dates and the target work-in-progress quantities of the sheet metal materials. Here, the work-in-progress dates of the sheet metal materials are future work-in-progress dates d1, d2 (the day after d1), .... The target work-in-progress quantities for the work-in-progress dates d1, d2, ... are D1, D11, ....

[0175] In the work-in-progress target data TND1 read out as described above, the target number of work-in-progress items on work-in-progress date a1 is A1, and the target number of work-in-progress items on work-in-progress date a2 (the day after a1) is A2, and the target numbers of work-in-progress items in the future are also determined for each date that is later than work-in-progress date a2.

[0176] Thereafter, in step 120, it is determined whether the future in-process quantity of the selected material is excessive or not. Hereinafter, the future in-process quantity of the selected material being excessive (not excessive) is also simply referred to as a future in-process quantity being excessive (not excessive).

[0177] In step 120, the selected materials refer to all selected materials in the selected materials group of all lots corresponding to the ordered parts group of all ordered lots. Also, the future in-process quantity refers to the future in-process quantity of all selected materials in the selected materials group of all lots (for example, the in-process quantity for one month from today).

[0178] At this stage, since the selected material is a round bar material, it is determined whether the future in-process quantity of the round bar material, in other words, the future in-process quantity of all the round bar materials of the above-mentioned total lot number of round bar materials, is excessive. In this determination, "excessive", i.e., "excessive future in-process quantity", means that the calculated in-process quantity in step 115 has increased by a predetermined in-process increase or more than the total in-process target quantity (the sum of the in-process target quantities of the round bar materials on each date) of the in-process target data TND1 read in step 117, on the premise that the future in-process quantity of the round bar materials of the total lot number corresponding to the order lot number L1 is too large since the order lot number L1 of the round bar part group is large.

[0179] In this embodiment, the basis for introducing the predetermined in-process increase number is as follows: When the selected raw material is a round bar member, the future in-process number of all round bar raw materials in the round bar raw material group of the total received order lot number is calculated based on the received order lot number L1, as described above.

[0180] Here, in the tentative lead time LT1, the cutting processing time H1A of the lead time section LT1A, the machining processing time H1B of the lead time section LT1B, the heat treatment processing time H1C of the lead time section LT1C, the painting processing time H1D of the lead time section LT1D, and the inspection time H1E of the lead time section LT1E are all times required for various processes and inspections of all of the round bar materials in a single lot of round bar blanks corresponding to a single lot of round bar part groups, and are times that do not change regardless of whether the future in-process numbers of all of the above-mentioned round bar blanks are large or small.

[0181] In contrast, the cutting process waiting time T1A, the machining process waiting time T1B, the heat treatment process waiting time T1C, the painting process waiting time T1D, and the inspection waiting time T1E in the tentative lead time LT1 are merely waiting times provided for various processes and inspections of the whole round bar material, and therefore can be said to be variable times. The calculated in-process quantity mentioned above is a concept that increases or decreases in proportion to an increase or decrease in the future in-process quantity of all the round bar materials of the group of round bar materials of the above-mentioned total order lot number.

[0182] Therefore, the inventors have studied in detail the composition of the tentative lead time LT1. From the inventors' experience, in each workplace, there is a tendency to secure as long a waiting time for processing and waiting time for inspection as possible, taking into consideration the degree to which the round bar material is stagnating, so that workers can process and inspect the round bar material. If this tendency is followed, there is a risk that the waiting time for processing and waiting time for inspection will be unnecessarily extended. This may lead to an increase in time that is completely wasted by workers, which is undesirable from the viewpoint of production management.

[0183] On the other hand, if there is an increase in the calculated in-process quantity, in other words, an increase in the future in-process quantity of all of the round bar materials in the total ordered lot number described above, it is necessary to secure the processing time and inspection time for the round bar materials in the total ordered lot number in accordance with the calculated in-process quantity. However, it is desirable to shorten the tentative lead time LT1 for each lot of the round bar materials in the total ordered lot number by adjusting the processing wait time and inspection wait time that are assigned to manufacturing each of the round bar materials in the total ordered lot number as a finished product by the completion date.

[0184] Therefore, in the case where the total processing and inspection time for the round bar material group of all lots described above increases due to an increase in the calculated work-in-process quantity, a predetermined increase in work-in-process quantity is set as the criterion for determining whether the above-mentioned shortening of the tentative lead time LT1 for each unit lot of the round bar material group is necessary.

[0185] Therefore, when the calculated work-in-progress quantity increases by more than the above-mentioned specified work-in-progress increase amount from the above-mentioned total work-in-progress target quantity, this corresponds to an excessive future work-in-progress quantity of the above-mentioned selected material, i.e., an excessive future work-in-progress quantity.

[0186] In other words, if the calculated number of in-process items is δ, the target total number of in-process items is η, and the specified increment in in-process items is θ, then the future in-process number of the selected material is excessive when δ≧η+θ holds.

[0187] In the first embodiment, the predetermined in-process increase number θ is set to, for example, 5% of the total in-process target number. The predetermined in-process increase number θ is not limited to 5% and may be changed as necessary. The predetermined in-process increase number θ can also be applied to selected materials other than round bar materials.

[0188] In step 120, if the calculated number of pieces in process of the bar material in step 115 is greater than the target number of pieces in process of the target data for the bar material in step 117 by the predetermined increment θ or more, the result is YES, i.e., the future number of pieces in process is excessive. Accordingly, the computer program proceeds to step 121 in FIG.

[0189] In step 121, a calculation process is performed for each target time (target time for each lead time portion) required to achieve the in-process target of the selected material. Here, the in-process target of the selected material refers to the in-process target of all selected materials in the selected material group of the above-mentioned total lot number. Therefore, each of the above-mentioned target times refers to the time required to achieve the in-process target of all selected materials.

[0190] The target time refers to the target time for each lead time part in each single lot of the selected material group of the total lot number mentioned above. In the calculation process, the target time is calculated for each workplace or outsourced factory based on the following formula (1). Target time = Target number of works in progress ÷ Processing capacity (1) In the formula (1), the target number of in-process items is the sum of the target numbers A1, A1, ... of the target in-process data TND1 in the target in-process data table 4 (see Fig. 17). The processing capacity means, for round bar materials, the cutting processing capacity of the workers based on the performance of the cutting machine in the first workplace 20a, the cutting processing capacity of the workers based on the performance of the cutting machine in the first outsourcing factory SF1, the heat treatment processing capacity of the workers based on the performance of the heat treatment processing equipment in the second outsourcing factory SF2, the painting processing capacity of the workers based on the performance of the painting equipment in the third painting workshop 20c, and the inspection capacity of the workers based on the performance of the inspection equipment in the fourth workplace 20d. In this embodiment, the processing capacity can be determined, for example, by taking the actual data of when the goods passed through each of the first to fourth workplaces 20a to 20d and the first and second outsourced factories FS1 and FS2, and by calculating the number of items processed per day from the actual data, the processing capacity can be grasped based on the calculation results.

[0191] In the above step 121, since the selected material is currently a round bar material, the target times for each of the first factory 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third factory 20c, and the fourth factory 20d are calculated based on formula (1).

[0192] When the process in step 121 is completed, in the next step 123, a subtraction process is performed from each lead time portion of the selected material to each corresponding target time.

[0193] At the current stage, since the selected material is a round bar material, for each lead time portion of the current tentative lead time LT1, the corresponding target time based on formula (1) is subtracted from that lead time portion.

[0194] Specifically, in the tentative lead time LT1, if the difference to the corresponding target time at the work site 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third work site 20c, or the fourth work site 20d (hereinafter also referred to as the corresponding target time difference) is expressed as βi (i=a, b, c, d, e, . . .), the corresponding target time difference βi, i.e., βa, βb, βc, βd, and βe, are subtracted from each corresponding lead time portion. The corresponding target time difference βi differs from each other at the first work site 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third work site 20c, and the fourth work site 20d. This is because the above-mentioned processing capacities differ from each other at the first work site 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third work site 20c, and the fourth work site 20d.

[0195] Thus, as can be seen from Figures 14(a) and 19(a), in the tentative lead time LT1, the lead time portion LT1A is shortened and adjusted to a target cutting waiting time T1Aβa (=T1A-βa) by subtracting the corresponding target time difference βa, the lead time portion LT1B is shortened and adjusted to a target cutting processing waiting time T1Bβb (=T1B-βb) by subtracting the corresponding target time difference βb, the lead time portion LTc is shortened and adjusted to a target heat treatment processing waiting time T1Cβc (=T1C-βc) by subtracting the corresponding target time difference βc, the lead time portion LTd is shortened and adjusted to a target painting processing waiting time T1Dβd (=T1D-βd) by subtracting the corresponding target time difference βd, and the lead time portion Lte is shortened and adjusted to a target inspection waiting time T1Eβe (=T1E-βe) by subtracting the corresponding target time difference βe.

[0196] This is because the calculated future in-process quantity of round bar blanks has increased by more than the above-mentioned specified in-process increase θ compared to the target in-process quantity in the in-process target data for round bar blanks, i.e., the future in-process quantity of the selected blanks is excessive, and so the decision was made to respond by shortening and adjusting each of the lead time sections described above to ensure the increases in each processing time and inspection time associated with this excess are made available.

[0197] For this reason, in the tentative lead time LT1, the calculated future work-in-process quantity of round bar material has increased beyond the target work-in-process quantity in the target work-in-process data for round bar material, and therefore it is excessive. Therefore, it was decided to maintain the cutting processing time H1A of lead time section LT1A, the machining processing time H1B of lead time section LT1B, the heat treatment processing time H1C of lead time section LT1C, the painting processing time H1D of lead time section LT1D, and the inspection time H1E of lead time section LT1E as they are, while shortening the tentative lead time LT1 by subtracting the corresponding target time (based on formula (1)) from each of the lead time sections.

[0198] Here, the reason for subtracting each corresponding target time difference from each lead time portion in this way will be specifically explained. When the future in-process quantity of the round bar raw materials is excessively large as described above, it is expected that the overall processing time of the round bar raw materials to be processed at the first workplace 20a, the first subcontract factory SF1, the second subcontract factory SF2, and the third workplace 20c, and the overall inspection time of the round bar raw materials to be inspected at the fourth workplace 20d will increase due to the increase in the future in-process quantity of the round bar raw materials.

[0199] Therefore, even if the lead times are excessive as described above, in order to meet the completion date, the waiting time for processing at the first workplace 20a, the first subcontract factory SF1, the second subcontract factory SF2, and the third workplace 20c, and the waiting time for inspection at the fourth workplace 20d, in other words, the lead time portions of the tentative lead time LT1 for each lot of the round bar raw material group are shortened to the corresponding target times (based on formula (1)) while maintaining the processing times at the first workplace 20a, the first subcontract factory SF1, the second subcontract factory SF2, and the third workplace 20c, and the inspection time at the fourth workplace 20d as they are. This makes it possible to prevent unnecessary in-process materials from overflowing in front of the processing machines and inspection machines and hindering processing and inspection work.

[0200] Thereafter, in step 124, an update process of the tentative lead time data of the selected material is performed. In this update process, since the selected material is currently a round bar material, the tentative lead time LT1 of the tentative lead time data TD1 in the tentative lead time data table in the registration device Sb is updated as the tentative lead time LT11 with each processing wait time and inspection wait time, while maintaining each processing time (H1A, H1B, H1C, H1D) and inspection time (H1E) with the target processing wait times (T1Aβa, T1Bβb, T1Cβc, T1Dβd) and target inspection wait time (T1Eβe) that have been subtracted in step 123 (see FIG. 19(a)). The tentative lead time LT11 is determined by the sum of the lead time portions LT11A (=T1Aβa+H1A), LT11B (=T1Bβb+H1B), LT11C (=T1Cβc+H1C), LT11D (=T1Dβd+H1D) and LT11E (=T1Eβe+H1E) (see Figure 19(a)).

[0201] With the above-mentioned update, the computer program proceeds to step 122 in Fig. 7. In step 122, a process is performed to subtract the tentative lead time from the completion date of the selected raw material as the corresponding ordered part. At the current stage, since the selected raw material is a round bar raw material, a process is performed to subtract the tentative lead time LT11 of the round bar raw material that has been updated in step 124 described above from the completion date of the round bar raw material group as a round bar part group.

[0202] Next, a material input date setting process is performed in step 125. In this setting process, the material input date is calculated by the following formula (2). Material input date = Completion date - tentative lead time (2) However, in the previous step 122, since the tentative lead time LT11 updated in step 124 is subtracted from the completion date of the round bar raw material as a round bar part, the result of this subtraction process is set as the material input date of the round bar raw material.

[0203] When such settings are made, in the next step 126, an update process of the provisional manufacturing instruction data is performed. Here, the result of the subtraction in step 122 is input as the material input date of the round bar material by the operation device of the computer 30 into the provisional manufacturing instruction data (see FIG. 16(b)). Based on this input, the provisional manufacturing instruction data in the registration device Sb is updated. In the provisional manufacturing instruction shown in FIG. 16(b), the provisional lead time LT1 is updated to LT11, the waiting time T1A for cutting is updated to T1Aβa, the waiting time T1B for machining is updated to T1Bβb, the waiting time T1C for heat treatment is updated to T1Cβc, the waiting time T1D for painting is updated to T1Dβd, and the waiting time T1E for inspection is updated to T1Eβe. Therefore, the lead time LT11 is the sum of the lead time portions LT11A (=TAβa+H1A), LT11B (=T1Bβb+H1B), LT11C (=T1Cβc+H1C), LT11D (=T1Dβd+H1D) and LT11E (=T1Eβe+H1E).

[0204] Thereafter, in step 130, it is determined whether or not there is a sudden decrease in the number of orders. Hereinafter, a sudden decrease (or not a sudden decrease) in the number of orders will also be referred to as a sudden decrease in the number of orders (or a non-sudden decrease in the number of orders).

[0205] The reason for providing the judgment step 130 is as follows: If the number of orders for ordered parts (currently, round bar parts) suddenly decreases on a certain day in the future, the number of round bar materials to be processed or inspected at each of the workplaces 20a, 20c, 20d and each of the outsourcing factories SF1 and SF2 through which the round bar materials pass on that certain day in the future will decrease, which may cause an unnecessary decrease in the operating rate of the processing and inspection facilities and workers.

[0206] Therefore, as a measure to prevent unnecessary declines in the operating rate as described above, in order to mitigate the above-mentioned sudden declines, steps are provided that perform the processes from step 126a shown in FIG. 7 and the processes from step 130a shown in FIG. 8.

[0207] In the first embodiment, the above-mentioned sudden decrease, i.e., a sudden decrease in the number of orders, refers to a decrease in the number of orders by a predetermined decrease in the number of orders (hereinafter, referred to as a "predetermined short-term order decrease") within a predetermined short period (e.g., several weeks). Here, the predetermined short-term order decrease refers to a decrease in the number of orders that may cause an unnecessary decrease in the operating rate described above within the above-mentioned predetermined short period. (1a) In the case of no sudden decrease in orders At the current stage, the case of no sudden decrease in the order quantity is premised on an excessive future work-in-process quantity (determination of YES in step 120). In the above-mentioned step 130 (see FIG. 7), if there is no sudden decrease in the order quantity, that is, if the order quantity is no sudden decrease with the assumption that the future work-in-process quantity is excessive, the determination is NO. Next, in the next step 131, a process of setting target lead time data is performed. At the current stage, since the selected material is round bar material, a process of setting target lead time data for round bar material is performed.

[0208] As described above, since the answer to the question "YES" in step 120 is based on the assumption that the future work-in-process quantity is excessive, each lead time portion in the tentative lead time LT11 is adjusted to be shortened to the corresponding target time calculated based on formula (1) as described above. Note that there is no change in each processing time and inspection time, and since there is no sudden decrease in the number of orders, no measures are required to prevent the unnecessary decrease in the operating rate as described above. Therefore, as described above, the tentative lead time LT1 (see FIG. 13(b)) remains set as the target lead time LT11 (see FIG. 19(a)) in the target lead time data table 5.

[0209] In this embodiment, the target lead time data table 5 is configured to have each of target lead time data TD21, TD31, and TD41 in addition to the above-mentioned target lead time data TD11 (see FIG. 18).

[0210] Here, the target lead time data TD11 refers to the target lead time (see Figure 19(a)) when the future work-in-process quantity is excessive and the number of orders is not decreasing rapidly, and this target lead time data TD11 is composed of round bar raw materials and the corresponding target lead times LT11, LT12, and LT13 (see Figure 18).

[0211] Of the remaining target lead times LT12 and LT13, target lead time LT12 refers to the target lead time when the future work-in-process quantity is not excessive and the number of orders is not suddenly decreasing (see Figure 20(a)), and target lead time LT13 refers to the target lead time when the future work-in-process quantity is not excessive and the number of orders is not suddenly decreasing (see Figure 21(a)).

[0212] The target lead time data TD21 is made up of square bar raw materials and the corresponding target lead times LT21, LT22, and LT23 (see FIG. 18). Like the target lead times LT11, LT12, and LT13, the target lead times LT21, LT22, and LT23 refer to the target lead times when the number of items in process is excessive and the number of orders does not decrease suddenly, when the number of items in process is not excessive and the number of orders does not decrease suddenly, and when the number of items in process is not excessive and the number of orders does not decrease suddenly.

[0213] The target lead time data TD31 is composed of triangular bar raw materials and the corresponding target lead times LT31, LT32, and LT33 (see FIG. 18). Like the target lead times LT11, LT12, and LT13, the target lead times LT31, LT32, and LT33 refer to the target lead times when the number of items in process is excessive and the number of orders does not decrease suddenly, when the number of items in process is not excessive and the number of orders does not decrease suddenly, and when the number of items in process is not excessive and the number of orders does not decrease suddenly.

[0214] The target lead time data TD41 is composed of sheet metal materials and the corresponding target lead times LT41, LT42, and LT43 (see FIG. 18). The target lead times LT41, LT42, and LT43, like the target lead times LT11, LT12, and LT13, refer to target lead times when the number of items in process is excessive and the number of orders does not decrease suddenly, when the number of items in process is not excessive and the number of orders does not decrease suddenly, and when the number of items in process is not excessive and the number of orders does not decrease suddenly. The target lead time data table 5 described above is registered in the registration device Sb.

[0215] Thereafter, in step 131a, it is determined whether or not the name change in the provisional manufacturing instruction data has been performed. At this stage, the name change has not been performed, so the determination in step 131a is NO. The above-mentioned name change refers to changing the provisional manufacturing instruction to a regular manufacturing instruction.

[0216] Then, the name "provisional manufacturing instruction" in the temporary manufacturing instruction data representing the temporary manufacturing instruction PBFa is changed to "primary manufacturing instruction" by operating the operation device 40 of the home server device Sa. If the determination in step 131a becomes YES based on this change, a conversion process to the primary manufacturing instruction data is performed in the next step 131b. In this conversion process, the temporary instruction data (lot number unchanged) representing the temporary manufacturing instruction PBFa (see FIG. 16(b)) whose name has been changed as described above is converted to the primary manufacturing instruction data.

[0217] Next, in step 132, a setting process of the primary production instruction data is performed. In this setting process, the primary production instruction data that has been converted in step 131b (see FIG. 16(b)) is set as the primary production instruction data. This primary production instruction data represents the primary production instruction Q shown in FIG. 19(b). This means that the primary production instruction Q is formed in step 132. (1b) In the case of a sudden drop in orders On the other hand, if the judgment in step 130 described above is YES, assuming that the future work-in-process quantity is excessive due to a sudden decrease in the number of orders and the judgment in step 120 is YES, then in the next step 133 it is determined whether or not both the excessiveness (excessive future work-in-process quantity) and the sudden decrease have been resolved.

[0218] At this stage, the following three scenarios arise: a. When the future work-in-process quantity is excessive but the number of orders suddenly decreases, the future work-in-process quantity becomes non-excessive and the number of orders does not suddenly decrease b. When the excessive future work-in-process quantity is not resolved by a sudden decrease in the number of orders, and the number of orders does not decrease suddenly, but the excessive future work-in-process quantity remains as it is. c. When the future work-in-process quantity is excessive but becomes non-excessive due to a sudden decrease in the number of orders, the sudden decrease in the number of orders remains the same First, when the above-mentioned excessive future work-in-process quantity is resolved by a sudden decrease in the number of orders and becomes a non-excessive future work-in-process quantity, and accordingly the sudden decrease in the number of orders becomes a non-sudden decrease in the number of orders, the above-mentioned step 133 is judged as YES. This means that the judgments of YES in each of steps 120, 126a, and 130 are canceled. Here, when the above-mentioned excessive future work-in-process quantity is resolved by a sudden decrease in the number of orders and accordingly the sudden decrease in the number of orders becomes a non-sudden decrease in the number of orders, it means that the above-mentioned future calculated work-in-process quantity of the round bar blanks does not decrease below the total target number in work-in-process of the target work-in-process data TND1 read out in step 117 due to the sudden decrease in the number of orders, and therefore the order number becomes a non-sudden decrease in the number of orders.

[0219] Therefore, the tentative leadtime at the current stage is specified by a tentative leadtime LT13 (see FIG. 21(a)) having leadtime portions similar to those of the tentative leadtime LT1 shown in FIG. 14(a). The tentative leadtime LT13 is specified by the sum of the leadtimes LT13A (=T1A+H1A), LT13B (=T1B+H1B), LT13C (=T1C+H1C), LT13D (=T1D+H1D) and LT13E (=T1E+H1E).

[0220] Accordingly, the computer program proceeds from step 133 to step 135 (see FIG. 8), and the processing from step 135 onward is performed in the same manner as described above, assuming that the future work-in-process quantity is not excessive and the number of orders is not rapidly decreasing. Therefore, the regular production instruction at the current stage is the same as that converted from the provisional production instruction shown in FIG. 16(b).

[0221] On the other hand, if the determination in step 133 above is NO because neither the excessive state nor the sudden decrease has been resolved, then in the next step 133a, it is determined whether the excessive state is maintained and the sudden decrease has been resolved.

[0222] Here, if the above-mentioned excessive future work-in-process quantity is not resolved by the sudden decrease in the number of orders, and the sudden decrease in the number of orders becomes a non-sudden decrease in the number of orders, but the excessive future work-in-process quantity is maintained as it is, then the above-mentioned step 133a is judged as YES. This means the same as the above-mentioned judgments of YES in each of steps 120 and 126a and NO in step 130. In other words, the tentative lead time at the current stage is the tentative lead time LT11 shown in FIG. 19(a). Here, the fact that the excessive future work-in-process quantity is not resolved by the sudden decrease in the number of orders, and the number of orders becomes a non-sudden decrease in the number of orders, but the excessive future work-in-process quantity is maintained as it is means that the number of work-in-process calculated in step 115 does not decrease to less than the sum of the total target number of work-in-process quantities in the target work-in-process data TND1 read in step 117 and the above-mentioned predetermined increase in work-in-process quantities due to the sudden decrease in the number of orders, resulting in a non-sudden decrease in the number of orders.

[0223] On the other hand, if the above-mentioned conditions of maintaining the excessive state and elimination of the sudden decrease are not satisfied in step 133a, then in the next step 134, it is determined whether or not the excessive state is eliminated and the sudden decrease is maintained.

[0224] As a result, the future work-in-progress quantity that was excessive becomes the future work-in-progress quantity that is not excessive due to the sudden decrease in the number of orders. However, if the sudden decrease in the number of orders is maintained, the determination in step 134 is YES.

[0225] Next, in the next step 134a, the waiting time for processing and inspection is added. In this addition process, the cutting waiting time T1Aβa, the cutting waiting time T1Bβb, the heat treatment waiting time T1Cβc, the painting waiting time T1Dβd, and the inspection waiting time T1Eβe in the tentative lead time LT11 updated in step 124 after the determination of YES in the above-mentioned step 120 return to T1A, T1B, T1C, T1D, and T1E, respectively, due to the return to non-excessive future in-process quantity, and a predetermined relaxation time α is added and adjusted to the cutting waiting time T1A, the cutting waiting time T1, the heat treatment waiting time T1C, the painting waiting time T1D, and the inspection waiting time T1E. The predetermined relaxation time α is a time suitable for mitigating the influence of a sudden decrease in the number of orders for round bar parts when the number of orders for the round bar parts suddenly decreases as described above.

[0226] Next, in the next step 134b, the tentative lead time data of the selected material is updated. Here, the target tentative lead time LT11 is updated as the target tentative lead time LT12 by subtracting the target times βa to βe as described above, and then adding and adjusting the waiting time of each processing and inspection by a predetermined relaxation time α. Here, each processing and inspection time is maintained as it is. Therefore, the target tentative lead time LT12 is the sum of each lead time portion LT12A (=T1Aα+H1A), LT12B (=T1Bα+H1B), LT12C (=T1Cα+H1C), LT12D (=T1Dα+H1D), and LT12E (=T1Eα+H1E), as shown in FIG. 20(a).

[0227] Thereafter, in step 134c, the tentative lead time is subtracted from the completion date of the selected material. In this subtraction process, since the selected material is currently a round bar material, the tentative lead time LT12 updated in step 134b is subtracted from the completion date of the round bar material. Next, in step 134d, the material input date is set to the result of the subtraction in step 134c.

[0228] After the process of step 134d, the temporary manufacturing instruction data is updated in step 134e. In the update process, the input date already input in the temporary manufacturing instruction PBFa (see FIG. 16(b)) is updated to the set material input date in step 134d.

[0229] Thereafter, a process for setting target lead time data is performed in step 131. At the current stage, since the amount of work in progress is not excessive and the number of orders has suddenly decreased, the tentative lead time LT12 (see FIG. 20(a)) is adjusted based on the corresponding target time calculated based on formula (1) and set as the target lead time (hereinafter, target lead time LT12).

[0230] Next, as described above, by operating the operation device 40 of the home server device Sa, the name "provisional manufacturing instruction" in the temporary manufacturing instruction data representing the temporary manufacturing instruction PBFa is changed to "primary manufacturing instruction", and if the answer is YES in step 131a, the conversion process to the primary manufacturing instruction is performed in the next step 131b as described above, and then, in the setting process of the primary manufacturing instruction data in step 132, the primary manufacturing instruction data converted in step 131b (see FIG. 20(b)) is set as the primary manufacturing instruction data. The primary manufacturing instruction data represents the primary manufacturing instruction Q shown in FIG. 20(b). (2) When the future in-process quantity of the selected material is not excessive On the other hand, if the number of orders is not large and the calculated future in-process quantity of the round bar material in step 115 is not excessively larger than the in-process target quantity in the in-process target data for the round bar material in step 117, the determination is NO in step 120. Accordingly, the computer program proceeds to step 122 in FIG.

[0231] In the process of subtracting the tentative lead time from the completion date of the selected raw material as the corresponding ordered part in step 122, the tentative lead time LT1 (see FIG. 13(b)) of the round bar raw material in the above-mentioned step 113 is subtracted from the completion date of the round bar raw material as a finished product. Next, in the process of setting the raw material input date in step 125, the result of the subtraction process in the above-mentioned step 122 is set as the raw material input date of the round bar raw material as a round defense raw material group.

[0232] Once such settings have been made, the provisional production instructions are updated in the next step 126. Here, on the premise that the setting results in step 125 are based on the provisional lead time LT1 (see FIG. 13(b)) in the case where the future in-process quantity of the round bar materials is not excessive, the provisional production instructions are inputted into the provisional production instructions by the operation device of the computer 30 as the material input date for the round bar material group. Based on this input, the provisional production instructions data in the registration device Sb is updated. (2a) If there is no sudden decrease in the number of orders After the process in step 126 is performed as described above, in step 126a, it is determined whether the future in-process quantity of the selected raw material is excessive or not. At the current stage, the future in-process quantity of the selected raw material, the round bar raw material, is not excessive, so the determination is NO, as in the determination in the previous step 120.

[0233] If the result is NO, then in step 130a of FIG. 8, it is determined whether the number of orders has suddenly decreased. If the result in step 130a is NO because the number of orders has not suddenly decreased, then in the next step 135, a process of setting target lead time data for the selected round bar material is performed in the same manner as in the setting process in step 131 described above. At the current stage, the future in-process quantity of the selected material is not excessive, and the number of orders has not suddenly decreased, so the tentative lead time LT1 is set as the target lead time LT13 (see FIG. 21(a)). The target lead time LT13 is determined by the sum of the lead time parts LT13A (=T1A+H1A), LT13B (=T1B+H1B), LT13C (=T1C+H1C), LT13D (=T1D+H1D), and LT13E (=T1E+H1E) (see FIG. 21(a)). Incidentally, the tentative lead time LT1 is updated and registered as the target lead time LT13 in the target lead time data table 5 (see FIG. 18) in the registration device Sb.

[0234] Then, as described above, when the determination in step 135a becomes YES by changing the name in the temporary manufacturing instruction data, the conversion process to the regular manufacturing instruction data in the next step 135b converts the temporary manufacturing instruction data at the current stage to the regular manufacturing instruction data. Accordingly, in the setting process of the regular manufacturing instruction data in step 135c, the regular manufacturing instruction data (see FIG. 21(b)) that has been converted in step 135b is set as the regular manufacturing instruction data. The regular manufacturing instruction data represents the regular manufacturing instruction (indicated by the symbol Q) shown in FIG. 21(b). (2b) In the case of a sudden drop in orders On the other hand, at the current stage, assuming that the future work-in-process quantity is not excessive, since the number of orders has suddenly decreased, if the judgment in the above-mentioned step 130a is YES, in the addition process of the processing and inspection waiting time in the next step 136 (see Figure 8), the above-mentioned predetermined relaxation time α is added to each of the cutting waiting time T1A, cutting waiting time T1B, heat treatment processing waiting time T1C, painting waiting time T1D and inspection waiting time T1E in the lead time portions LT1A to LT1E of the tentative lead time LT1 (see the tentative lead time data in step 113).

[0235] This means that the lead time section LT1A is composed of its cutting processing waiting time, T1Aα (=T1A+α), the lead time section LT1B is composed of its cutting processing waiting time, T1Bα (=T1B+α), the lead time section LT1C is composed of its heat treatment processing waiting time, T1Cα (=T1C+α), the lead time section LT1D is composed of its painting processing waiting time, T1Dα (=T1D+α), and the lead time section LT1E is composed of its inspection waiting time, T1Eα (=T1E+α) (see Figure 20(a)).

[0236] Next, in the process of updating the tentative lead-time data for the selected material in step 136a, since the selected material is a round bar material, the tentative lead-time LT1 in the tentative lead-time data table 2 in the registration device Sb is updated as the tentative lead-time LT12 (see FIG. 20(a)) after adding the predetermined relaxation time α as described above to the waiting time for each processing and inspection. The tentative lead-time LT12 is specified by the sum of the lead-time portions LT12A (T1Aα+H1A), LT12B (T1Bα+H1B), LT12C (T1Cα+H1C), LT12D (T1Dα+H1D) and LT12E (T1Eα+H1E) (see FIG. 20(a)).

[0237] Thereafter, in step 136b, the tentative lead time LT12 is subtracted from the completion date of the selected raw material, that is, from the completion date of the round bar raw material group as a round bar part group. In response to this, in the next step 136c, the result of the subtraction in step 136b is set as the raw material input date for the round bar raw material, that is, for the round bar raw material group.

[0238] After this setting, in the update process of the temporary production instruction data in step 136d, the material input date is updated with the material input date set in step 136c.

[0239] Thereafter, in the target lead time setting process in step 135, the tentative lead time LT12 updated in step 136a is set as the target lead time for the round bar material (hereinafter referred to as the target lead time LT12) and is registered in the target lead time data table 5 (see Figure 18) in the registration device Sb.

[0240] Next, in the same manner as described above, under the name change operation in the temporary manufacturing instruction data, after the determination in step 135a is YES, in the conversion process to regular manufacturing instruction data in step 135b, the temporary manufacturing instruction data whose name has been changed as described above is converted into regular manufacturing instruction data.

[0241] Thereafter, in the setting process of the primary manufacturing instruction data in step 135c, the primary manufacturing instruction data converted in step 135b (see FIG. 20(b)) is set as the primary manufacturing instruction data. The primary manufacturing instruction data represents the primary manufacturing instruction Q shown in FIG. 20(b). 2. Manufacturing mode for new order parts Thus, when the computer program proceeds from step 132 in Fig. 7 or step 135c in Fig. 8 to step 140 in Fig. 9, it is determined in step 140 whether the lot number, input date, and completion date have been input. At the current stage, if the lot number, input date, and completion date have not been input to the primary production instruction data, the determination in step 140 is NO. Here, if the lot number, input date, and completion date are input as #LOT1, xx day, and yy day in the lot number, input date, and completion date columns of the primary production instruction data, the determination in step 140 is YES.

[0242] Then, in the next step 141, a process of setting the lot number, input date, and completion date in the original manufacturing instruction data is performed. In this process, the previously input #LOT1, xx date, and yy date are set as the lot number, input date, and completion date. The process of setting refers to a storage process by the RAM 33 of the computer 30.

[0243] Thereafter, in step 142, a printing process of the primary production instruction is performed. In this printing process, the primary production instruction Q is printed by the printer Sc based on the primary production instruction data in which the lot number, input date, and completion date have been input in step 141.

[0244] At the current stage, if the work-in-process quantity is excessive and the order quantity is not decreasing rapidly, the normal production instruction Q shown in Figure 19(b) will be printed as the normal production instruction Q with the lot number, input date, and completion date already entered as described above.

[0245] Here, the waiting time and processing time in the cutting processing column are T1Aβa and H1A, respectively, the waiting time and processing time in the cutting processing column are T1Bβb and H1B, respectively, the waiting time and processing time in the heat treatment processing time column are T1Cβc and H1C, respectively, the waiting time and processing time in the painting processing column are T1Dβd and H1D, respectively, and further, the waiting time and processing time in the inspection column are T1Eβe and H1E, respectively.

[0246] Also, at the current stage, if the work-in-process quantity is not excessive and the order quantity is not rapidly decreasing, the normal production instruction Q shown in FIG. 21(b) is printed as the normal production instruction Q with the lot number, input date, and completion date already input.

[0247] Here, the waiting time and processing time in the cutting processing column are T1A and H1A, respectively, the waiting time and processing time in the machining processing column are T1B and H1B, respectively, the waiting time and processing time in the heat treatment processing time column are T1C and H1C, respectively, the waiting time and processing time in the painting processing column are T1D and H1D, respectively, and further, the waiting time and processing time in the inspection column are T1E and H1E, respectively.

[0248] Furthermore, at the current stage, if the work-in-process quantity is not excessive and the number of orders has suddenly decreased, the regular production instruction Q shown in FIG. 20(b) is printed as the regular production instruction Q with the lot number, input date, and completion date already input.

[0249] Here, the waiting time and processing time in the cutting processing column are T1Aα and H1A, respectively, the waiting time and processing time in the machining processing column are T1Bα and H1B, respectively, the waiting time and processing time in the heat treatment processing time column are T1Cα and H1C, respectively, the waiting time and processing time in the painting processing column are T1Dα and H1D, respectively, and further, the waiting time and processing time in the inspection column are T1Eα and H1E, respectively (see Figure 20(b)).

[0250] Thereafter, in the next step 143, it is determined whether the primary production instruction has been attached to the selected material. When any one of the primary production instructions Q (hereinafter also referred to as primary production instruction Q) printed as described above is attached to the selected material, that is, the round bar material, in the company warehouse 10, the terminal P0 of the company warehouse 10 is tapped. Based on the tapping operation, the terminal P0 transmits primary production instruction attachment data representing attachment information of the primary production instruction Q to the round bar material (primary production instruction attachment information representing the contents of the primary production instruction Q and the attachment date to the round bar material) as an operation output to the receiving circuit R0 of the receiving circuit group R of the computer 30 via the network N.

[0251] In response to such transmission, the CPU 31 determines YES in step 143 based on receipt of the original manufacturing instruction attachment data from the receiving circuit R0.

[0252] Next, in step 150, it is determined whether the date for inputting the selected material has arrived. Here, it is determined whether the date for inputting the material as a round bar has arrived based on the above-mentioned data attached to the main manufacturing instruction. If the input date has arrived at the current stage, the determination in step 150 is YES.

[0253] In response to this determination, the group of round bar materials with lot number #LOT1 (consisting of six round bar materials) is sent from the company's warehouse 10 to the first workplace 20a in the company's factory 20 by appropriate means.

[0254] Accordingly, data (material input data) indicating the contents of the input round bar material group and the material input date is transmitted by the terminal P0 to the receiving circuit R0 of the computer 30 via the transmitting circuit Pa and the network N. Then, in the output process of the material input date data in step 151, the CPU 31 outputs the material input data from the receiving circuit P0 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the above-mentioned material input date data in the work-in-progress performance data IPD1.

[0255] Thereafter, in step 150a of Fig. 9, it is determined whether the selected material has been received at the first plant. At this stage, since the selected material is a round bar material, it is determined whether the group of round bar materials with the above-mentioned lot number #LOT1 has been received at the first plant 20a. Here, the CPU 31 determines YES in step 150a based on the receipt of the above-mentioned main production instruction attached data. Furthermore, a check mark is entered in the material confirmation column of the main production instruction Q based on the group of round bar materials that have been received.

[0256] As a result of the determination of YES in step 150a described above, in the first workplace receipt data output process in step 151a, the first workplace receipt information indicating the receipt and the receipt date of the round bar material group with lot number #LOT1 is output to the registration device Sb by the CPU 31 as first workplace receipt data. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the first workplace receipt data in the work-in-progress performance data IPD1.

[0257] Thereafter, in step 150b, it is determined whether the selected material is to be sent from the first work station 20a. At this stage, the selected material, the round bar material, has not been sent from the first work station 20a, so the determination in step 150b is NO.

[0258] As the first workplace 20a receives the group of round bar materials, the first workplace 20a cuts each of the round bar materials in the group of round bar materials with lot number #LOT1 in sequence. The cutting process is performed according to the waiting time and processing time in the cutting process column of the main production instruction Q.

[0259] Specifically, when the future work-in-process quantity is excessive (the judgement in step 120 is YES) and the number of orders is not decreasing suddenly (the judgement in step 130 is NO), the waiting time (cutting processing waiting time) and processing time (cutting processing time) of the original production instruction Q are the cutting processing waiting time T1Aβ (=T1A-β) and cutting processing time H1A of the lead-time part LT11A in the target lead time LT11 (see FIG. 19).

[0260] Therefore, in the first workplace 20a corresponding to the lead time section LT11A, the worker time available for the setup required for cutting the round bar material due to the excessive future in-process quantity is shortened to the extent that the lead time section is smaller than the corresponding target time calculated based on formula (1) compared to the case where the future in-process quantity is not excessive. This. This means that when cutting the round bar material group in the first workplace 20a, the input date of the round bar material group to the first workplace 20a can be brought closer to the cutting processing date of the round bar material group, thereby suppressing the residence time of the round bar material in the first workplace 20a. On the other hand, the worker time available for cutting the round bar material group remains H1A, so that it can be appropriately secured. At this stage, since the number of orders is not decreasing suddenly, measures to suppress the decrease in the worker operating rate due to the sudden decrease in the number of orders are not necessary.

[0261] Also, if the future work-in-process quantity is not excessive (determination in step 120 is NO) and the order quantity is not decreasing rapidly (determination in step 130a is NO), the waiting time (cutting waiting time) of the regular production instruction Q is the cutting waiting time T1A of the lead-time part LT13A in the target lead-time LT13 (see FIG. 21(a)) (see FIG. 21(a)). Note that the processing time (cutting time) remains H1A.

[0262] Therefore, in the first workplace 20a corresponding to the lead-time department LT13A, the worker time available for the setup required for cutting the round bar material is not extended or shortened due to the non-excessive future in-process quantity and non-rapid decrease in the number of orders. The worker time available for the cutting process of the round bar material remains as H1A.

[0263] Also, when the quantity in process is not excessive (determination in step 120 is NO) and the number of orders has suddenly decreased (determination in step 130a is YES), the waiting time (cutting waiting time) of the regular manufacturing instruction Q is the cutting waiting time T1Aα (=T1A+α) of the lead-time part LT12A in the target lead-time LT12 (see FIG. 20(a)). Note that it remains as the cutting time H1A.

[0264] Therefore, in the first workplace 20a corresponding to the lead-time section LT12A, when the number of in-process items is not excessive and the number of received orders is not suddenly decreased, the time available for workers to cut the round bar materials can be appropriately secured in the same way as in the case where the number of in-process items is not excessive and the number of received orders is not suddenly decreased, while the time available for workers to do the setup required for cutting the round bar materials can be extended by the predetermined relaxation time α compared to the case where the number of in-process items is not excessive and the number of received orders is not suddenly decreased. This makes it possible to appropriately cut the round bar materials while suppressing a decrease in the operating rate in the first workplace 20a.

[0265] When the cutting process of the group of round bar blanks in the first workplace 20a is completed as described above, the group of round bar blanks after the cutting process is completed is sent to the first subcontract factory SF1. When sending the group of round bar blanks after the cutting process, a check mark indicating sending to the first subcontract factory SF1 is entered in the cutting process column of the regular production instruction sheet Q that has been affixed to the group of round bar blanks after the cutting process is completed.

[0266] Furthermore, first workplace delivery data indicating the contents of the round bar materials after cutting in the first workplace 20a and the delivery date thereof is transmitted to the CPU 31 via the network N and the receiving circuit R2 under the operation of the terminal P2.

[0267] Then, based on receipt of the above-mentioned first workplace sending data, the CPU 31 judges YES in the above-mentioned step 150b. Accordingly, in the output process of the first workplace sending data in step 151b, the CPU 31 outputs the first workplace sending data to the registration device Sb and updates the work-in-progress performance data IPD1 in the work-in-progress performance data table 3 in the registration device Sb.

[0268] After the above-mentioned process of step 151b is completed, in the next step 150c, it is determined whether the newly ordered part is a sheet metal part. At this stage, since the newly ordered part is a round bar part, the determination in step 150c is NO.

[0269] Thereafter, in the next step 150d (see FIG. 10), it is determined whether the selected material has been received at the first subcontract factory. At this stage, since the selected material is a round bar material, the CPU 31 determines YES in step 150d, based on the receipt of the first workplace sending data described above, that the group of cut round bar materials sent as described above has been received at the first subcontract factory B.

[0270] Accordingly, the first subcontract factory receipt data, which indicates the receipt and the receipt date of the cut round bar material group, is transmitted by the terminal P9 to the CPU 31 via the transmission circuit Pa, the network N, and the receiving circuit R9. Then, in the output process of the first subcontract factory receipt data in step 152, the CPU 31 outputs the first subcontract factory receipt data from the receiving circuit R9 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the first subcontract factory receipt data in the work-in-progress performance data IPDSF1.

[0271] Thereafter, in step 150e, it is determined whether the selected material has been sent from the first outsourcing factory SF1. At this stage, the selected material, that is, the round bar material, has not been sent from the first outsourcing factory SF1, so the determination in step 150e is NO.

[0272] Then, when the first subcontracting factory SF1 receives the group of cut round bar blanks, the first subcontracting factory SF1 performs cutting of the group of cut round bar blanks. The cutting is performed according to the waiting time and processing time in the cutting column of the regular production instruction Q.

[0273] Specifically, in the case of excessive future work-in-process quantity and no sudden decrease in order quantity, the cutting processing waiting time is T1Bβb (=T1B-βb) in the lead time portion LT11B of the target lead time LT11 in the normal production instruction Q (see FIG. 19). Note that the cutting processing time remains H1B.

[0274] Therefore, in the first outsourcing factory SF1, the worker time available for the setup required for cutting the group of round bar blanks due to the future excessive amount of work in progress and the non-rapid decrease in the number of orders is shortened to the extent that the lead time portion is smaller than the corresponding target time calculated based on formula (1) compared to the case where the work in progress is not excessive and the number of orders is not suddenly decreased. Note that the worker time available for cutting the round bar blanks is the same as the case where the work in progress is not excessive and the number of orders is not suddenly decreased.

[0275] As a result, in the case of excessive work in progress and no sudden decrease in the number of orders, by shortening the cutting waiting time until the lead time portion is less than the corresponding target time calculated based on formula (1), the date of input of the group of round bar blanks after cutting to the first subcontracting factory SF1 can be brought closer to the date of cutting of the group of round bar blanks, while the time required for cutting by workers due to excessive work in progress can be appropriately secured. Note that, at this stage, since the number of orders is not decreasing suddenly, there is no need to take measures to prevent a decrease in the operating rate of workers.

[0276] In addition, when the work-in-process quantity is not excessive and the number of orders is not rapidly decreasing, in the lead time portion LT13B required for cutting processing of the target lead time LT13 of the normal production instruction Q, the cutting processing waiting time is T1B (see FIG. 21). In addition, the cutting processing time is H1B.

[0277] Therefore, in the first outsourcing factory SF1, due to the fact that the number of in-process items is not excessive and the number of orders is not rapidly decreasing, the worker time available for the setup required for cutting the group of round bar blanks is not extended or shortened, and is the same as the content entered in the above-mentioned temporary production instructions (see FIG. 14). The same is true for the worker time available for cutting the group of round bar blanks.

[0278] In addition, when the work-in-process quantity is not excessive and the number of orders is suddenly decreased, the lead time portion LT12B required for cutting processing in the target lead time LT12 (see FIG. 20) in the normal manufacturing instruction Q is the cutting processing waiting time T1Bα (=T1B+α). Note that the cutting processing time remains H1B.

[0279] Therefore, in the first outsourcing factory SF1, the time available for workers to spend on the setup required for cutting the group of round bar blanks due to the future in-process quantity not being excessive and the number of orders not suddenly decreasing is extended by the predetermined relaxation time α compared to the case where the in-process quantity is not excessive and the number of orders not suddenly decreasing. Note that the time available for workers to spend on cutting the group of round bar blanks is the same as the case where the in-process quantity is not excessive and the number of orders not suddenly decreasing.

[0280] As a result, in the case where the work-in-process quantity is not excessive and the number of orders is suddenly reduced, the cutting processing waiting time can be extended by the specified relaxation time α, thereby suppressing the decrease in worker utilization rate that tends to occur due to a sudden decrease in the number of orders, while appropriately securing the time required for cutting processing by workers based on the cutting processing time H1B.

[0281] When the cutting process of the group of round bar blanks is completed in the first subcontracting factory SF1 as described above, the group of round bar blanks is sent to the second subcontracting factory SF2 after the cutting process is completed. At the time of sending, a check indicating sending to the second subcontracting factory SF2 is entered in the cutting process column of the regular production instruction sheet Q.

[0282] In addition, in conjunction with the sending of the group of post-cut round bar materials to the second outsourcing factory SF2 as described above, in the first outsourcing factory SF1, the first outsourcing factory sending data indicating the sending and sending date of the group of post-cut round bar materials is sent to the CPU 31 by the terminal P10 via the network N and the receiving circuit R10 under its operation.

[0283] After the process in step 152 described above, in step 150e, it is determined whether the selected material is sent from the first outsourcing factory. Here, since the selected material is a round bar material, the CPU 31 determines YES in step 150e based on the first outsourcing factory sending data from the receiving circuit R10.

[0284] Accordingly, in the output process of the first outsourcing factory sending data in step 152a, the CPU 31 outputs the first outsourcing factory sending data from the receiving circuit R10 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the first outsourcing factory sending data in the work-in-progress performance data IPDSF1.

[0285] Thereafter, in the next step 150f (see FIG. 10), it is determined whether the selected material has been received at the second outsourcing factory. At this stage, since the selected material is a round bar material, the CPU 31 determines YES in step 150f, which means that the second outsourcing factory SF2 has received the post-machining round bar material group, based on the first outsourcing factory transmission data from the receiving circuit R10.

[0286] When the determination in step 150f is YES, the second outsourcing factory receipt data indicating the receipt of the machined round bar material group and the receipt date is transmitted from the terminal P11 to the CPU 31 via the network N and the receiving circuit R11. Then, in the output process of the second outsourcing factory receipt data in step 152b, the CPU 31 outputs the second outsourcing factory receipt data from the receiving circuit R11 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the second outsourcing factory receipt data in the work-in-progress performance data IPDSF2.

[0287] Thereafter, in step 150g, it is determined whether the selected material is to be sent from the second outsourcing factory SF2. At this stage, the selected round bar material has not been sent from the second outsourcing factory SF2 as a group of round bar materials, so the determination in step 150g is NO.

[0288] Upon receipt of the group of post-machining round bar blanks from the second outsourcing factory SF2, the second outsourcing factory SF2 performs heat treatment on the group of post-machining round bar blanks. The heat treatment is performed according to the waiting time and processing time in the heat treatment column of the regular production order Q.

[0289] Specifically, in the case of excessive future work-in-process quantity and no sudden decrease in order quantity, in the lead-time portion LT11C of the target lead-time LT11 in the normal production order Q, the heat treatment processing waiting time is T1Cβ (=T1C-β) (see FIG. 19). Note that the heat treatment processing time remains H1C.

[0290] Therefore, in the second outsourcing factory SF2, the worker time available for the setup required for the heat treatment processing of the group of round bar blanks due to the future excessive amount of work in progress and no sudden decrease in the number of orders is shortened to the extent that the lead time portion is less than the corresponding target time calculated based on formula (1) compared to the case where the work in progress is not excessive and the number of orders is not suddenly decreased. Note that the worker time available for the heat treatment processing of the group of round bar blanks is the same as in the case where the work in progress is not excessive and the number of orders is not suddenly decreased.

[0291] As a result, in the case of excessive work in progress and no sudden decrease in the number of orders, the heat treatment waiting time is shortened by the above-mentioned corresponding target time, so that the input of the round bar material group to the second outsourcing factory SF2 for heat treatment processing is brought closer to the heat treatment processing date, suppressing the backlog of the round bar material at the second outsourcing factory SF2, while appropriately securing the time required for heat treatment processing by workers due to excessive work in progress under the heat treatment processing time H1C. Note that since the number of orders is not suddenly decreasing, there is no need to take measures to reduce the operating rate of workers.

[0292] In addition, when the future work-in-process quantity is not excessive and the number of orders is not rapidly decreasing, the cutting processing waiting time is T1C in the lead time portion LT13C required for heat treatment processing of the target lead time LT13 (see FIG. 21) in the normal production order Q. The cutting processing time remains H1C.

[0293] Therefore, in the second outsourcing factory SF2, due to the fact that the future in-process quantity is not excessive and the number of orders is not rapidly decreased, the worker time available for the setup required for the heat treatment processing of the group of round bar materials is not extended or shortened, and is the same as the content entered in the above-mentioned provisional production instructions (see FIG. 14). The worker time available for the heat treatment processing of the group of round bar materials is H1C.

[0294] In addition, when the future work-in-process quantity is not excessive and the number of orders is suddenly decreased, the lead time portion LT12C required for heat treatment processing in the target lead time LT12 of the normal manufacturing instruction Q is the heat treatment processing waiting time T1Cα (=T1C+α) (see FIG. 20). Note that the cutting processing time remains H1C.

[0295] Therefore, in the second outsourcing factory SF2, the time available for workers to spend on the setup required for the heat treatment processing of the group of round bar blanks due to the future in-process quantity not being excessive and the number of orders not being suddenly decreased is extended by the predetermined relaxation time α compared to the case where the in-process quantity is not excessive and the number of orders not being suddenly decreased. Note that the time available for workers to spend on the heat treatment processing of the group of round bar blanks is the same as the case where the in-process quantity is not excessive and the number of orders not being suddenly decreased.

[0296] As a result, in the case where the number of work-in-process items is not excessive and the number of orders is suddenly reduced, the waiting time for heat treatment processing is extended by the specified relaxation time α, which makes it possible to suppress a decrease in worker availability that tends to occur due to a sudden decrease in the number of orders, and to ensure the appropriate number of round bar materials required for heat treatment processing by workers when the number of work-in-process items is not excessive, thereby making it possible to properly ensure the heat treatment processing.

[0297] When the heat treatment of the group of round bar blanks is completed in the second outsourcing factory SF2 as described above, the group of round bar blanks is sent to the third plant 20c after the heat treatment is completed. When sending the group of round bar blanks, a check mark indicating sending to the third plant 20c is entered in the heat treatment column of the regular production instruction Q.

[0298] In addition, in conjunction with the sending of the group of round bar materials after the completion of the above-mentioned heat treatment processing to the third workplace 20c, in the second outsourcing factory SF2, second outsourcing factory sending data indicating the sending and the sending date of the group of round bar materials after the completion of the heat treatment processing is transmitted to the CPU 31 by the terminal P12 through the network N and the receiving circuit R12 under its operation.

[0299] Then, in step 150g, the CPU 31 judges YES based on the second outsourcing factory sending data from the receiving circuit R12. Accordingly, in the output process of the second outsourcing factory sending data in step 152c, the CPU 31 outputs the second outsourcing factory sending data from the receiving circuit R12 to the registration device Sb. As a result, the work-in-progress performance data table 3 in the registration device Sb is updated based on the second outsourcing factory sending data in the work-in-progress performance data IPDSF2.

[0300] In addition, when the group of heat treated round bar materials is sent to the third workplace 20c as described above, and the group of heat treated round bar materials is received at the third workplace 20c, third workplace receipt data indicating the receipt and receipt date of the group of heat treated round bar materials is transmitted by the terminal P5 to the CPU 31 via the network N and the receiving corridor R5.

[0301] Then, in the next step 150h (see FIG. 11), it is determined whether the selected material has been received at the third workplace. At this stage, since the selected material is a round bar material, the CPU 31 determines YES in step 150h based on the third workplace receipt data from the receiving circuit R5, which means that the post-heat treatment round bar material group has been received at the third workplace 20c.

[0302] If the determination in step 150h is YES, then in the third workplace received data output process in step 152d, the CPU 31 outputs the third workplace received data from the receiving circuit R5 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the third workplace received data in its work-in-progress performance data IPD3.

[0303] Thereafter, in step 150i, it is determined whether the selected workpiece is to be sent from the third work station 20c. At this stage, the group of round bar materials (group of round bar materials after painting processing) that is the selected workpiece has not yet been sent from the third work station 20c, so the determination in step 150i is NO.

[0304] As described above, when the round bar material group is received at the third plant 20c after the heat treatment, the round bar material group is painted at the third plant 20c. The painting process is carried out according to the waiting time and processing time in the painting process column of the main production instruction Q.

[0305] Specifically, in the case of excessive future work-in-process quantity and no sudden decrease in order quantity, in the lead time portion LT11D of the lead time LT11 of the normal production order Q, the paint processing waiting time is T1Dβ (=T1D-β) (see FIG. 19). Note that the paint processing time remains H1D.

[0306] Therefore, in the third workplace 20c, the worker time available for the preparation and so on required for the painting process of the group of round bar materials due to the future excessive amount of work in progress and no sudden decrease in the number of orders is shortened to the extent that the lead time portion is less than the corresponding target time calculated based on formula (1) compared to the case where the work in progress is not excessive and the number of orders is not suddenly decreased. The worker time available for the painting process of the round bar materials is the same as the case where the work in progress is not excessive and the number of orders is not suddenly decreased.

[0307] As a result, in the case of excessive work in progress and no sudden decrease in the number of orders, the paint waiting time is shortened until the lead time portion is less than the corresponding target time, and the day when the round bar materials are input to the third workplace 20c for painting is brought closer to the day when the round bar materials are painted, suppressing the accumulation of the round bar materials at the third workplace 20c, while appropriately securing the time required for workers to paint due to the excessive future work in progress under the painting processing time H1D. Note that since the number of orders is not suddenly decreasing, there is no need to take measures to reduce the operating rate of workers.

[0308] In addition, when the future work-in-process quantity is not excessive and the number of orders is not rapidly decreasing, the lead time portion LT11D required for the painting process of the target lead time LT13 in the normal production instruction Q is the painting process waiting time T1D (see FIG. 21). The painting process time is H1D.

[0309] Therefore, in the third workplace 20c, due to the fact that the future in-process quantity is not excessive and the number of orders is not rapidly decreasing, the worker time available for the preparation and other work required for the painting of the round bar material is not extended or shortened, and is the same as the contents entered in the above-mentioned temporary production instructions (see FIG. 16). The worker time available for the painting of the round bar material is H1D.

[0310] In addition, when the future work-in-process quantity is not excessive and the number of orders is suddenly decreased, the paint processing waiting time is T1Dα (=T1D+α) in the lead time portion LT12D (see FIG. 20) required for the paint processing of the target lead time LT12 in the normal production order Q. Note that the paint processing time remains H1D.

[0311] Therefore, in the third workplace 20c, the time available for workers to spend on preparations required for the painting process of the group of round bar materials due to the future in-process quantity not being excessive and the number of orders not being suddenly decreased is extended by the predetermined relaxation time α compared to the case where the in-process quantity is not excessive and the number of orders not being suddenly decreased. This means that the time required for workers to paint the group of round bar materials can be appropriately secured under the painting process time H1D while suppressing the decrease in the worker availability rate that tends to occur due to a sudden decrease in the number of orders.

[0312] When the painting process of the group of round bar blanks at the third plant 20c is completed as described above, the group of round bar blanks is sent to the fourth plant 20d after the painting process is completed. When sending the group of round bar blanks, a check mark indicating sending to the fourth plant 20d is entered in the painting process column of the main production instruction Q.

[0313] In conjunction with the sending of the group of painted round bar materials to the fourth workplace 20d, in the third workplace 20c, third workplace sending data indicating the sending and the sending date of the group of painted round bar materials is transmitted to the CPU 31 via the network N and the receiving circuit R6 by the terminal P6 operated by the terminal P6.

[0314] After the processing of step 152d, in step 150i, it is determined whether or not the selected material is to be sent from the third workplace. Here, since the selected material is a round bar material, the CPU 31 determines YES in step 150i based on the receipt of the third workplace sending data, which indicates that the painted round bar material group is to be sent to the fourth workplace 20d.

[0315] In response to such a determination of YES in step 150i, in the output process of the third workplace sent data in step 152e, the CPU 31 outputs the third workplace sent data from the receiving circuit R6 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the third workplace sent data in the work-in-progress performance data IPD3.

[0316] In addition, when the painted round bar materials are sent to the fourth workplace 20c as described above, and the painted round bar materials are received at the fourth workplace 20c, fourth workplace receipt data indicating the receipt and receipt date of the painted round bar materials is transmitted by the terminal P7 to the CPU 31 via the network N and the receiving corridor R7.

[0317] Thus, in step 150j (see FIG. 11), it is determined whether the selected workpiece has been received at the fourth worksite. Since the selected workpiece is a round bar at this stage, the CPU 31 determines YES in step 150j based on the fourth worksite receipt data from the receiving circuit R7, which indicates that the painted round bar workpieces have been received at the fourth worksite 20c.

[0318] If the determination in step 150j is YES, then in the fourth workplace received data output process in step 152f, the CPU 31 outputs the fourth workplace received data from the receiving circuit R7 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the third workplace received data in the work-in-progress performance data IPD4.

[0319] Thereafter, in step 150k, it is determined whether the selected workpiece is to be sent from the fourth work station 20c. At this stage, the group of round bar materials (group of round bar materials after inspection) consisting of the selected round bar materials has not yet been sent from the fourth work station 20c, so the determination in step 150k is NO.

[0320] As described above, when the group of painted round bar materials is received at the fourth plant 20d, the group of painted round bar materials is inspected at the fourth plant 20d. The inspection is carried out according to the waiting time and processing time in the inspection column of the original production order Q.

[0321] Specifically, in the case of excessive future work-in-process quantity and no sudden decrease in order quantity, in the lead time portion LT11E of the target lead time LT11 in the normal production order Q, the inspection waiting time is T1Eβ (=T1E-β) (see FIG. 19). Note that the inspection time remains H1E.

[0322] Therefore, in the fourth workplace 20d, the worker time available for the setup required for the inspection of the round bar material due to the future excessive amount of work in progress and the non-rapid decrease in the number of orders is shortened to the extent that the lead time portion is less than the corresponding target time calculated based on formula (1) compared to the case where the work in progress is not excessive and the number of orders is not suddenly decreased. The worker time available for the inspection of the round bar material is the same as the case where the work in progress is not excessive and the number of orders is not suddenly decreased.

[0323] In this way, when there is an excessive amount of work in progress and no sudden decrease in the number of orders, the inspection waiting time is shortened by the corresponding target time. This means that, during inspection, the date on which the round bar blanks are introduced into the fourth workplace 20d is brought closer to the inspection date, suppressing the residence time of the round bar blanks in the fourth workplace 20d, while appropriately securing the time required for inspection by workers under the inspection time H1E.

[0324] In addition, when the future work-in-process quantity is not excessive and the order quantity is not suddenly decreased, in the lead time portion LT13E required for inspection of the target lead time LT13 in the normal production instruction Q, the inspection waiting time is T1E (see FIG. 21). Note that the inspection time is H1E.

[0325] Therefore, in the fourth workplace 20d, due to the fact that the number of in-process items is not excessive and the number of orders is not suddenly decreasing, the time that can be consumed by workers for the setup required for inspecting the group of round bar blanks is not extended or shortened, and is the same as the content entered in the provisional production instructions described above (see FIG. 16).

[0326] In addition, when the future work-in-process quantity is not excessive and the number of orders is suddenly decreased, the lead time portion LT12E required for inspection of the target lead time LT12 in the normal production order Q is the inspection waiting time T1Eα (= T1E + α) (see FIG. 20). Note that the inspection time remains H1E.

[0327] Therefore, in the fourth workplace 20d, the time that workers can consume for the setup required for the inspection of the group of round bar blanks due to the future in-process quantity not being excessive and the number of orders not being suddenly decreased is extended by the predetermined relaxation time α compared to the case where the in-process quantity is not excessive and the number of orders is not suddenly decreased. This means that the time required for the workers to inspect the group of round bar blanks can be appropriately secured under the inspection time H1E while suppressing the decrease in the worker availability rate that tends to occur due to a sudden decrease in the number of orders.

[0328] When the inspection of the round bar blanks at the fourth workplace 20c is completed as described above, the round bar blanks are sent to the destination warehouse DW after the inspection is completed. When sending the round bar blanks, a check mark indicating sending to the destination warehouse DW is entered in the inspection column of the main production instruction Q.

[0329] In addition, in conjunction with the sending of the group of round bar materials after the above-mentioned inspection is completed to the delivery warehouse DW, in the fourth workplace 20d, the fourth workplace sending data indicating the sending and the sending date of the group of round bar materials after the inspection is completed is transmitted to the CPU 31 by the terminal P8 through the network N and the receiving circuit R8 under its operation.

[0330] After the process of step 152f, in step 150k, it is determined whether the selected material is to be sent from the fourth workplace. Here, the CPU 31 determines YES in step 150k based on the fourth workplace sending data from the receiving circuit R8, which means that the post-inspection round bar material group is to be sent to the delivery warehouse DW.

[0331] In response to the determination of YES in step 150k, in the output process of the fourth workplace sent data in step 152g, the CPU 31 outputs the fourth workplace sent data from the receiving circuit R8 to the registration device Sb. Accordingly, the work-in-progress performance data table 3 in the registration device Sb is updated based on the fourth workplace sent data in the work-in-progress performance data IPD4.

[0332] In addition, when the group of round bar materials after the above-mentioned inspection is sent to the destination warehouse DW and the group of round bar materials after the inspection is received at the destination warehouse DW, destination warehouse receipt data indicating the receipt and receipt date of the group of round bar materials after the inspection is sent to the CPU31 by the terminal P13 via the network N and the receiving corridor R13.

[0333] Then, in step 150m, it is determined whether or not the selected raw material has been received by the delivery destination warehouse. Since the selected raw material is a round bar raw material, the CPU 31 determines YES in step 150m based on the delivery destination warehouse receipt data from the receiving circuit R13, which means that the post-inspection round bar raw material group has been received at the delivery destination warehouse DW.

[0334] Next, in the output process of the destination warehouse receipt data in step 152h, the CPU 31 outputs the destination warehouse receipt data from the receiving circuit R13 to the registration device Sb. Accordingly, the in-process result data table 3 in the registration device Sb is updated based on the destination warehouse receipt data in the in-process result data. The in-process result data constitutes the result data table 3 together with the in-process result data IPD1 to IPDSF2 described above.

[0335] Thereafter, in step 150n, it is determined whether #LOTn>#LOTmax. Here, #LOTn (n=1, 2, 3, . . . ) specifies the lot number of the selected material group. Also, #LOTmax represents the maximum lot number of the selected material group.

[0336] At the current stage, since #LOTn=#LOT1, the determination in step 150n is NO. Thereafter, the computer program returns to step 140 (see FIG. 9). Here, since the input of the next lot number has not been performed, the determination in step 140 is NO.

[0337] At this stage, since the lot number has already been set to #LOT1 in step 141, the next lot number is #LOT2. Accordingly, the lot number is input as #LOT2 through the operation of the operation device 40 of the home server Sa, and the input date and completion date of the group of round bar materials with that lot number are also input.

[0338] Accordingly, in step 141, a process of setting the lot number, input date, and completion date in the primary manufacturing instruction data is performed. As a result, the lot number column of the primary manufacturing instruction Q in the primary manufacturing instruction data is updated to #LOT2, and the input date and completion date columns are updated. Thereafter, in accordance with the process from step 142 onwards, the processing and inspection of the round bar material group with lot number #LOT2 and its sending to the delivery destination warehouse DW are performed in the same manner as described above. Thereafter, such a process is repeated until the determination in step 150n becomes YES. Thus, when the determination in step 150n becomes YES, the delivery of the round bar parts, which are the ordered parts, to the delivery destination warehouse DW as the round bar material group can be completed. When the determination in step 150n becomes YES, the computer program proceeds to the end step.

[0339] If the determination in step 110a (see FIG. 5) is NO, then in step 110b it is determined whether the newly ordered part is a square bar part. If the determination in step 110b is NO, then in step 110c it is determined whether the newly ordered part is a triangular bar part. If the determination in step 110c is NO, then in the next step 110d it is determined whether the newly ordered part is a sheet metal part.

[0340] If the determination is YES in step 110b or step 110c, the part to be manufactured is treated as a square bar part or a triangular bar part, and the processing from step 111 onwards is carried out in the same manner as when the part to be manufactured is a round bar part.

[0341] Furthermore, if the determination in step 110d is YES, the processing from step 111 (see FIG. 5) to step 126 (see FIG. 7) is performed for the manufacturing target part as a sheet metal part in the same manner as in the case of a round bar part.

[0342] In addition, the processes from step 133 to step 132 in response to the determination of YES in both steps 126a and 130, or the processes from step 131 to step 132 in response to the determination of NO in step 130, are performed in the same manner as in the case of a round bar part.

[0343] Here, in the provisional manufacturing instruction data updated in step 126 (see FIG. 7), the lead time is the provisional lead time LT4 for the sheet metal material (see FIG. 14(b)), which is different from the provisional lead time LT1 for the round bar material (see FIG. 14(a)).

[0344] The target lead times for the round bar material associated with the target lead time data setting process in step 131 are LT11, LT12, and LT13, corresponding to excessively large and not rapidly decreasing, not excessively large and not rapidly decreasing, and not excessively large and not rapidly decreasing (see Fig. 19(a), Fig. 20(a), Fig. 21(a)). In contrast, the target lead times for the sheet metal material are LT41, LT42, and LT43 (not shown), which correspond to the target lead times LT11, LT12, and LT13, respectively.

[0345] Therefore, these target lead times LT41, LT42 and LT43 correspond to excessively large and not decreasing sharply, not excessively large and not decreasing sharply and not excessively large and not decreasing sharply, like the target lead times LT11, LT12 and LT13.

[0346] Here, the manufacturing route for the round bar blank is configured to pass through the first workplace 20a, the first outsourced factory SF1, the second outsourced factory SF2, the third workplace 20c, and the fourth workplace 20d, whereas the manufacturing route for the sheet metal blank is configured to pass through the first workplace 20a, the second workplace 20b, the third workplace 20c, and the fourth workplace 20d (see FIG. 1). Therefore, although the manufacturing route for the sheet metal blank differs from that for the second workplace 20b, it is common to the manufacturing route for the round bar blank in that it passes through the first workplace 20a, the third workplace 20c, and the fourth workplace 20d.

[0347] Therefore, if the target lead time of the sheet metal material is composed of first to fourth lead time sections (corresponding to the first to fourth workplaces 20a to 20d), the first lead time section is composed of the cutting processing waiting time and cutting processing time of the sheet metal material, the second lead time section is composed of the press processing waiting time and press processing time of the sheet metal material, the third lead time section is composed of the painting processing waiting time and painting processing time of the sheet metal material, and the fourth lead time section is composed of the inspection waiting time and inspection time of the sheet metal material.

[0348] Accordingly, in the case where the future work-in-process quantity is excessive and the order quantity is not rapidly decreasing, the first, third and fourth lead time portions of the target lead time LT41 are configured in the same manner as the lead time portions LT11A, LT11D and LT11E of the target lead time LT11. In the case where the future work-in-process quantity is not excessive and the order quantity is not rapidly decreasing, the first, third and fourth lead time portions of the target lead time LT42 are configured in the same manner as the lead time portions LT12A, LT12D and LT12E of the target lead time LT12. Also, in the case where the future work-in-process quantity is not excessive and the order quantity is not rapidly decreasing, the first, third and fourth lead time portions of the target lead time LT43 are configured in the same manner as the lead time portions LT13A, LT13D and LT13E of the target lead time LT13.

[0349] In addition, in any of the target lead times LT41 to LT43, although the second lead time section uses a different processing method from the cutting processing of the round bar material, it is set substantially the same as the cutting processing waiting time and the cutting processing time, taking into account βi or α.

[0350] In step 132, the regular production instruction data is set as regular production instruction data for the sheet metal material group of the sheet metal material corresponding to the sheet metal part, instead of the round bar material group.

[0351] Here, the original production instruction Q represented by the original production instruction data differs from the original production instruction Q for the round bar material group described above in the following points: The part number for the sheet metal material group is different from the part number F962 for the round bar material group in the original production instruction Q.

[0352] The lead times are different from the lead times in the normal manufacturing instruction Q for the round bar material group described above. That is, in the normal manufacturing instruction Q for the sheet metal material group, the lead times are the above-mentioned target lead times LT41, LT42, and LT43 for excessive and non-rapid decrease, non-excessive and sudden decrease, and non-excessive and non-sudden decrease.

[0353] Furthermore, the processes from step 140 (see FIG. 9) to step 151b are carried out for the sheet metal blanks instead of the round bar blanks in the same manner as in the case of the round bar blanks.

[0354] Thereafter, in the next step 150c, if the newly ordered part is a sheet metal part and the answer is YES, the computer program proceeds to step 160 (see FIG. 12).

[0355] Then, in step 160, it is determined whether or not the selected material has been received at the first workplace. At this stage, since the selected material is a sheet metal material, the sheet metal material group made up of sheet metal materials has not been received at the first workplace 20a, and the determination in step 160 is NO.

[0356] Thus, when the sheet metal material is input and received from the company warehouse 10 to the first workplace 20a as a sheet metal material group with lot number #LOT1 (with the sheet metal material group's original manufacturing instruction sheet Q attached), first workplace receipt data indicating the receipt and receipt date of the sheet metal material group is transmitted by the terminal P1 through the network N and the receiving circuit R1 to the CPU 31. Then, the CPU 31 judges YES in step 160 based on the first workplace receipt data from the receiving circuit R1.

[0357] In the next step 161, a first workplace receipt data output process, the first workplace receipt data is output to registration device Sb by CPU 31. Accordingly, the work-in-progress performance data table 3 in registration device Sb is updated with the first workplace receipt data in the work-in-progress performance data IPD1.

[0358] When the group of sheet metal blanks is received at the first workplace 20a, the group of sheet metal blanks is cut at the first workplace 20a. During the cutting process, the group of sheet metal blanks is cut while making the necessary arrangements for cutting the group of sheet metal blanks during the cutting process waiting time T4Aβa (in the case of excessive or non-sudden decrease), T4Aα (in the case of non-excessive or non-sudden decrease), or T4A (in the case of non-excessive or non-sudden decrease) that has been entered in the main production instruction Q. After the cutting process waiting time has elapsed, each sheet metal blank of the group of sheet metal blanks is cut during the cutting process time H4A that has been entered in the main production instruction Q.

[0359] Once the cutting process of the group of sheet metal blanks has been completed in this manner, a check mark is entered in the cutting process column of the main production instruction sheet Q affixed to the group of sheet metal blanks, and the group of sheet metal blanks after the cutting process is sent to the second workplace 20b.

[0360] Accordingly, the first workplace sending data indicating the sending and sending date of the group of cut sheet metal materials is sent by the terminal P2 via its sending circuit Po and the network N to the receiving circuit R2 of the computer 30. Then, the CPU 31 judges YES in step 160a based on the first workplace sending data from the receiving circuit R2. Note that a check has been entered in the cutting column of the main production instruction Q that has been affixed to the group of cut sheet metal materials sent as described above.

[0361] In the next step 162, which is a process of outputting the first workplace sending data, the CPU 31 outputs the first workplace sending data to the registration device Sb, and updates the in-process result data table 3 in the registration device Sb with the in-process result data IPD2.

[0362] Next, in step 160b, it is determined whether the selected material has been received at the second workplace. When the group of cut sheet metal materials sent to the second workplace 20b as described above is received at the second workplace 20b, second workplace receipt data indicating the receipt and receipt date of the group of cut sheet metal materials is transmitted to the CPU 31 via the network N and the receiving circuit R3 under the operation of the terminal P3. Accordingly, the CPU 31 determines YES in step 160b.

[0363] Then, in the next step 163, which is a process of outputting second workplace receipt data, the CPU 31 outputs the second workplace receipt data to the registration device Sb and updates the in-process result data table 3 in the registration device Sb with the in-process result data IPD2.

[0364] Thereafter, in step 160c, it is determined whether or not the selected workpiece is to be sent from the second workplace. Here, since the selected workpiece, that is, the sheet metal workpiece, has not been sent as a sheet metal workpiece group, the determination in step 160c is NO.

[0365] Thus, when the group of sheet metal blanks after cutting is pressed by the press machine disposed in the second workplace 20b, the group of sheet metal blanks is waited for the press processing wait time T4Bβ (in the case of excessively large and not abruptly decreasing), T4Bα (in the case of not excessively large and not abruptly decreasing), or T4B (in the case of not excessively large and not abruptly decreasing) that has been entered in the regular production instruction Q, while making the arrangements required for the press processing of the group of sheet metal blanks, and after the press processing wait time has elapsed, the group of sheet metal blanks is press processed for the press processing time H4B that has been entered in the regular production instruction Q.

[0366] When the press working of the group of sheet metal blanks is completed in this manner, a check mark is entered in the press working column of the main production instruction sheet Q affixed to the group of sheet metal blanks, and the group of sheet metal blanks after the press working is sent to the third workplace 20c.

[0367] Accordingly, the second workplace delivery data, which indicates the delivery and delivery date of the group of press-worked sheet metal blanks, is transmitted to the CPU 31 via the network N and the receiving circuit R4 under the operation of the terminal P4.

[0368] Then, the CPU 31 determines YES in step 160c as the sending of the press-worked sheet metal blanks from the second workplace 20b based on the second workplace sending data. In addition, in the output process of the second workplace sending data in step 164, the CPU 31 outputs the second workplace sending data from the receiving circuit R4 to the registration device Sb and updates the work-in-progress performance data table 3 in the registration device Sb with the second workplace sending data in the work-in-progress performance data IPD2.

[0369] In the next step 160d, it is determined whether the selected material has been received at the third workplace. When the group of pressed sheet metal blanks sent to the third workplace 20c as described above is received at the third workplace 20c, third workplace receipt data indicating the receipt and receipt date of the group of pressed sheet metal blanks at the third workplace 20c is transmitted by the terminal P5 to the CPU 31 via the network N and the receiving circuit R5. Accordingly, the CPU 31 determines YES in step 160d based on the third workplace receipt data from the receiving circuit R5.

[0370] Accordingly, in the third workplace receipt data output process in step 165, the CPU 31 outputs the third workplace receipt data to the registration device Sb and updates the work-in-progress performance data table 3 in the registration device Sb with the work-in-progress performance data IPD3 based on the third workplace receipt data.

[0371] After the press processing in the third workplace 20c, the sheet metal material group is received and painted in the third workplace 20c. During the painting processing wait time T4Cβ (in the case of excessive or non-sudden decrease), T4Cα (in the case of non-excessive or sudden decrease), or T4C (in the case of non-excessive or non-sudden decrease) already entered in the main production instruction Q, the sheet metal material group is prepared for painting and the like while waiting for a certain time. After the painting processing wait time has elapsed, each sheet metal material in the sheet metal material group is painted for the painting processing time H4C already entered in the main production instruction Q.

[0372] When the painting process of the group of sheet metal blanks is completed in this manner, a check is entered in the painting process column of the main production instruction sheet Q attached to the group of sheet metal blanks, and the group of painted sheet metal blanks is sent to the fourth workplace 20d. Accordingly, third workplace sending data indicating the sending and sending date of the group of painted sheet metal blanks is sent to the CPU 31 via the network N and the receiving circuit R6 under the operation of the terminal P6. As a result, the CPU 31 judges YES in step 160e based on the third workplace sending data from the receiving circuit R6.

[0373] Then, in the third workplace sending data output process in step 166, the CPU 31 outputs the third workplace sending data to the registration device Sb and updates the work-in-progress performance data table 3 in the registration device Sb with the third workplace sending data in the work-in-progress performance data IPD3.

[0374] After processing step 166, in step 150j (see FIG. 11), it is determined whether the selected material has been received at the fourth post station. When the group of painted sheet metal blanks sent to the fourth workplace 20d as described above is received at the fourth workplace 20d, fourth workplace receipt data indicating the receipt and receipt date of the group of painted sheet metal blanks is transmitted by terminal P7 to CPU 31 via network N and receiving circuit R7. Accordingly, in step 150j, CPU 31 determines YES based on the fourth workplace receipt data from receiving circuit R7.

[0375] Accordingly, in the fourth workplace receipt data output process in step 152f, the CPU 31 outputs the fourth workplace receipt data from the receiving circuit R7 to the registration device Sb, and updates the work-in-progress performance data IPD4 in the work-in-progress performance data table 3 of the registration device Sb with the fourth workplace receipt data.

[0376] Next, in step 150k, it is determined whether the selected workpiece is to be sent from the fourth work station 20d. At this stage, the selected workpiece, that is, the sheet metal workpiece, has not been sent from the fourth work station 20d, so the determination in step 150k is NO.

[0377] As described above, when the painted sheet metal blank group is sent to the fourth workplace 20d, the painted sheet metal blank group is inspected at the fourth workplace 20d. During the inspection waiting time T4Dβd (in the case of excessive or non-sudden decrease), T4dα (in the case of non-excessive or non-sudden decrease), or T4D (in the case of non-excessive or non-sudden decrease) already entered in the regular production instruction Q, the inspection wait time is performed while making the arrangements required for the inspection of the sheet metal blank group, and after the inspection waiting time has elapsed, each sheet metal blank in the sheet metal blank group is inspected by an inspection device during the inspection time H4D already entered in the regular production instruction Q.

[0378] When the inspection of the sheet metal material group is completed in this way, a check is entered in the inspection column of the regular manufacturing instruction sheet Q attached to the post-inspection sheet metal material group, and the production of the sheet metal parts group, which are the finished products of the sheet metal material group with lot number #LOT1, is completed. At the same time, the sheet metal parts group is sent to the delivery warehouse DW.

[0379] Then, the fourth workplace sending data indicating the sending and the sending date of the sheet metal parts group is transmitted to the CPU 31 through the network N and the receiving circuit R8 by the terminal P8 under its operation. Then, the CPU 31 judges YES in step 150k based on the receipt of the fourth workplace sending data.

[0380] Accordingly, in the output processing of the fourth workplace sent data in step 152g, the CPU 31 outputs the fourth workplace sent data from the receiving circuit R8 to the registration device Sb, and updates the work-in-progress performance data IPD4 in the work-in-progress performance data table 3 of the registration device Sb with the fourth workplace sent data.

[0381] As described above, when the inspected sheet metal blank group is sent to the destination warehouse DW and the inspected sheet metal blank group is received at the destination warehouse DW, destination warehouse data indicating the receipt and receipt date of the inspected sheet metal blank group is transmitted to the CPU 31 via the network N and the receiving circuit R13 under the operation of the terminal P13. Therefore, the CPU 31 judges YES in step 150m based on the receipt of the destination warehouse receipt data.

[0382] Thereafter, in the delivery destination warehouse receipt data output process in step 152h, the CPU 31 outputs the delivery destination warehouse receipt data to the registration device Sb and updates the work-in-progress performance data table in the lighting device Bb.

[0383] When the processing of step 152h is thus completed, in the next step 150n, it is determined whether or not #LOTm>#LOTmax. At the current stage, since #LOTm=#LOT1, the determination in step 150n is NO. It should be noted that #LOTm and #LOTmax are common to both sheet metal material (sheet metal parts) and round bar material (round bar parts). It should be noted that #LOTmax refers to the maximum value of the lot number.

[0384] After the determination in step 150n is NO, the computer program proceeds to step 140 in Fig. 9. Accordingly, the processing from step 140 onwards is repeated as described above. After that, when the lot number #LOTm=#LOTmax, the determination in step 150h becomes YES. This completes the delivery of the sheet metal material group to the delivery warehouse DW.

[0385] As described above, in the first embodiment, when manufacturing a new ordered part, for example, a round bar part from a corresponding round bar material, the lead time for the round bar material required for production management is set as a tentative lead time LT1 (see FIG. 14(a)) consisting of a plurality of lead time sections LT1A to LT1E. The plurality of lead time sections LT1A, LT1B, LT1C, LT1D, and LT1E correspond to the first workplace 20a, the first subcontract factory SF1, the second subcontract factory SF2, the third workplace 20c, and the fourth workplace 20d.

[0386] Here, the lead time portion LT1A is made up of a cutting waiting time T1A and a cutting time H1A for cutting in the first workplace 20a, and the lead time portion LT1B is made up of a cutting waiting time T1B and a cutting time H1B for cutting in the first outsourced factory SF1.

[0387] In addition, the lead time LTC is made up of the heat treatment processing waiting time T1C and the heat treatment processing time H1C for the heat treatment processing at the second outsourced factory SF2, the lead time LTD is made up of the painting processing waiting time T1D and the painting processing time H1D for the painting processing at the third workplace 20c, and the lead time LTE is made up of the inspection processing waiting time T1E and the inspection time H1E for the inspection at the fourth workplace 20d.

[0388] However, the waiting time for cutting, machining, heat treatment, painting and inspection in each lead-time section is set to the waiting time normally required in each corresponding workplace. Also, the waiting time for cutting, machining, heat treatment, painting and inspection in each lead-time section is set to the processing and inspection time normally required in each corresponding workplace (for example, when the future work-in-process quantity is not excessive and the number of orders is not suddenly reduced).

[0389] By configuring multiple lead times LT1A to LT1E in this manner, it is possible to easily and smoothly set the tentative lead times required to manufacture round bar parts from round bar raw material without relying on the complex configurations and processes of the conventional technology described in this specification.

[0390] Therefore, in the case where the future work-in-process quantity is not excessive and the number of orders is not decreasing rapidly, by utilizing the tentative lead time LT1 set as described above as the target lead time LT13, the manufacture of ordered round bar parts from round bar material can be carried out easily and smoothly based on the configuration of the lead time portions LT13A to LT13E of the target lead time LT13, without relying on the complex configurations and processes of the conventional technology described in this specification.

[0391] In addition, in the case of excessive future work-in-process quantity and no sudden decrease in order quantity (YES judgement in step 120 and NO judgement in step 130), since the future work-in-process quantity of the round bar raw material is too high, the target time (target processing time or target inspection time) is calculated using formula (1), and the difference between the calculated target time and the tentative lead time portion is subtracted from each waiting time of each lead time portion LT1A to LT1E of the above-mentioned tentative lead time LT1 (see Fig. 14(a)) (see Fig. 19(a)). In this way, the target lead time LT11 in the case of excessive future work-in-process quantity and no sudden decrease in order quantity is set based on the result of this subtraction.

[0392] By setting the target lead time LT11 in this manner, based on the waiting times T1Aβa to T1Eβe of each lead time section LT11A to LT11E of the target lead time LT11, the waiting times for cutting, machining, heat treatment, painting and inspection are shortened by the difference βa between lead time section T1A+H1A and the corresponding target time, the difference βb between lead time section T1B+H1B and the corresponding target time, the difference βc between lead time section T1C+H1C and the corresponding target time, the difference βd between lead time section T1D+H1D and the corresponding target time, and the difference βe between lead time section T1E+H1E and the corresponding target time, respectively.

[0393] Accordingly, the input dates of the round bar materials to the first workplace 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third workplace 20c, and the fourth workplace 20d for cutting, machining, heat treatment, painting, and inspection can be brought closer to the cutting date, machining date, heat treatment date, painting date, and inspection date, respectively. This makes it possible to perform the cutting, machining, heat treatment, painting, and inspection of the round bar materials while suppressing the residence time of the round bar materials at the first workplace 20a, the first outsourcing factory SF1, the second outsourcing factory SF2, the third workplace 20c, and the fourth workplace 20d.

[0394] Furthermore, when the quantity in process is not excessive and the number of orders has suddenly dropped (when the judgment is NO in step 120 and YES in step 130), although the future quantity of work in process for round bar raw materials is not excessive, since the number of orders has suddenly dropped, simply setting the target lead time LT11 from the tentative lead time LT1 as described above cannot prevent a drop in the utilization rate of workers at each workplace, which is likely to occur when the number of orders has suddenly dropped.

[0395] For this reason, a predetermined relaxation time α is added to the waiting time of each lead time portion of the above-mentioned tentative lead time LT1 (see FIG. 20(a)).

[0396] This allows the target lead time LT12 to be set from the tentative lead time LT1 when the work-in-process quantity is not excessive and the order quantity is suddenly reduced. As a result, by extending the waiting time T1Aα, T1Bα, T1Cα, T1Dα, and T1Eα of each lead time portion LT12A to LT12E of the target lead time LT12, the operating rate of workers, etc. can be suppressed, and cutting and other processing and inspection can be performed appropriately under each processing time H1A, H1B, H1C, H1D, and H1E.

[0397] As explained above, the work in progress is appropriately controlled by extending or shortening each lead time portion. The lead time that can be appropriately controlled is calculated and subtracted from the delivery date to determine the material input date, so the material input date will not be delayed. Second embodiment 22 shows the main part of the second embodiment of the production management system according to the present invention. In this second embodiment, the fifth workplace 20e and the sixth workplace 20f arranged in the company's own factory 20 are adopted instead of the first outsourcing factory SF1 and the second outsourcing factory SF2 described in the first embodiment. In this second embodiment, the first and second outsourcing factories SF1 and SF2 and the other company's factory E described in the first embodiment are abolished.

[0398] In the second embodiment, the fifth workplace 20e is a workplace that performs cutting processing of the selected material, similar to the first outsourcing factory SF1, and the sixth workplace 20f is a workplace that performs heat treatment processing of the selected material, similar to the second outsourcing factory SF2.

[0399] Accordingly, both terminals P9 and P10 described in the first embodiment are arranged in the fifth workplace 20e as shown in FIG. 22, and both terminals P11 and P12 described in the first embodiment are arranged in the sixth workplace 20f as shown in FIG. 22.

[0400] In the flow chart (see FIG. 10) described in the first embodiment, the term "first subcontracted factory" is changed to "fifth workplace," and the term "second subcontracted factory" is changed to "sixth workplace." The other configurations are the same as those in the first embodiment.

[0401] In the second embodiment thus configured, the cutting processing of the selected material, for example, a round bar material, in the first outsourcing factory SF1 described in the first embodiment is carried out in the fifth workplace 20e, and the heat treatment processing of the selected material, for example, a round bar material, in the second outsourcing factory SF2 described in the first embodiment is carried out in the sixth workplace 20e.

[0402] Therefore, in the second embodiment, unlike the first embodiment, the cutting, machining, heat treatment, painting and inspection of the round bar material can all be performed within the company's own factory 20. Therefore, in the second embodiment, it is easier for the production management system to collect information required for production management compared to the case of using an outsourced factory as in the first embodiment. This means that production management of ordered parts is easier to perform compared to the first embodiment. Other effects are substantially the same as in the first embodiment. Third embodiment FIG. 23 shows a main part of a third embodiment of the production management system according to the present invention. In this third embodiment, a case where the selected material is a round bar material will be described. FIG. 23 shows a target lead time group LTG(n). Here, in LTG(n), n=0, 1, 2, 3, . . . The target lead time group LTG(n) is composed of five target lead times LTM5n+1, LTM5n+2, LTM5n+3, LTM5n+4, and LTM5n+5, as shown in FIG. 23. Here, in the target lead time group LTG(n), for example, when n=0, in the five target lead times, LTM5n+1 is LTM1, LTM5n+2 is LTM2, LTM5n+3 is LTM3, LTM5n+4 is LTM4, and LTM5n+5 is LTM5. Therefore, the target lead time group LTG(0) is made up of five target lead times LTM1, LTM2, LTM3, LTM4 and LTM5.

[0403] The reason why the target lead time group LTG(n) is composed of multiple lead times is as follows. In the first embodiment, for example, if the selected material is a round bar material, the in-process work of the succeeding round bar material group is not started until all the round bar materials of the preceding round bar material group are manufactured into finished products. In this case, the workplaces that have completed the in-process work remain out of operation, resulting in a low operating rate.

[0404] In contrast to this, in the third embodiment, the in-process work for the following group of round bar blanks is started when the in-process work in the first workplace 20a in the lead time portion (for example, LT11A (see FIG. 19)) of the preceding group of round bar blanks is completed. This allows each workplace to start in-process work again every time the in-process work is completed, which is expected to improve the operating rate.

[0405] The target lead time group LTG(n) is composed of five lead times because the number of target lead time parts of the round bar material is five.

[0406] In the third embodiment, since the selected raw material is a round bar raw material, the target lead times LTM5n+1 to LTM5n+5 correspond to the target lead times LT11, LT12 and LT13 (see FIG. 18), respectively.

[0407] Here, the target lead time LT11 is made up of lead time sections LT11A-LT11E (see FIG. 19(a)) in the case where the in-process quantity is excessive and the order quantity does not decrease suddenly, as described in the first embodiment. The target lead time LT12 is made up of lead time sections LT12A-LT12E (see FIG. 20(a)) in the case where the in-process quantity is not excessive and the order quantity does not decrease suddenly, as described in the first embodiment. The target lead time LT13 is made up of lead time sections LT13A-LT13E (see FIG. 21(a)) in the case where the in-process quantity is not excessive and the order quantity does not decrease suddenly, as described in the first embodiment. Note that FIG. 23 shows an example of each lead time section in the case where the in-process quantity is excessive and does not decrease suddenly for a round bar material.

[0408] In the above first embodiment, when the ordered part is a round bar part, a lot number #LOTi (i = 1, 2, 3, ..., j, ...) is assigned to each group of six round bar blanks corresponding to the round bar part. The maximum lot number of the round bar blank group is #LOTmax. The lot number of the group of six round bar parts, which is the finished product, is the same as the lot number of the round bar blank group.

[0409] In contrast, in the third embodiment, the lot numbers of the round bar material group are indicated as #LOT5m+1, #LOT5m+2, #LOT5m+3, #LOT5m+4, and #LOT5m+5. Here, in each lot number, m indicates m=0, 1, 2, . . . Therefore, for example, when m=0, each lot number is #LOT5m+1=#LOT1, #LOT5m+2=#LOT2, #LOT5m+3=#LOT3, #LOT5m+4=#LOT4, and #LOT5m+5=#LOT5. Note that #LOT1 to #LOT5 refer to the round bar material groups #LOT1 to #LOT5 in the first embodiment. Also, "m" in the lot number in the third embodiment corresponds to "n" in the target lead time group LTG(n).

[0410] In view of the above, in this third embodiment, among the flowcharts of Figures 5 to 12 described in the first embodiment, the flowchart of Figure 9 is replaced by the flowcharts of Figures 24 and 25, and the flowchart of Figure 26 is replaced by the flowchart of Figure 11.

[0411] Therefore, in this third embodiment, the computer 30 described in the first embodiment above executes, by its CPU 31, the computer program described in the first embodiment above as a computer program in this third embodiment in accordance with the flowcharts of Figures 5 to 8, the flowcharts of Figures 24 and 25 which replace the flowchart of Figure 9, the flowchart of Figure 10, the flowchart of Figure 26 which replaces the flowchart of Figure 11, and the flowchart of Figure 12.

[0412] Furthermore, in the third embodiment, the first to fourth interrupt programs are further adopted according to the respective flow charts shown in Fig. 27 to Fig. 30. Accordingly, the CPU 31 executes the first to fourth interrupt programs together with the computer program in the third embodiment. Note that the respective interrupts of the first to fourth interrupt programs are executed at different interrupt timings.

[0413] Here, the computer program in the third embodiment corresponds to the processing of the target lead time LTM5n+1. Accordingly, the first to fourth interrupt programs correspond to the processing of the target lead times LTM5n+2, LTM5n+3, LTM5n+4, and LTM5n+5, respectively. The other configurations of the third embodiment are the same as those of the first embodiment.

[0414] In the third embodiment configured as described above, when the production management system is placed in an operating state similar to the first embodiment, the CPU 31 starts executing computer programs in accordance with the flowcharts of Figures 5 to 8, the flowchart of Figure 25, the flowchart of Figure 10, the flowchart of Figure 26, and the flowchart of Figure 12, and starts executing the first to fourth interrupt programs in accordance with the flowcharts of Figures 27 to 30.

[0415] At the current stage, in the first interrupt program, in step 200 of Fig. 27, it is determined whether or not the first workplace sending data for the selected material with lot number #LOT5m+1 has been output. Here, if, at the current stage, n=0 in the target lead time group LTG(n) and m=0 in lot number #LOT5m+1, the selected material group (round bar material group) with lot number #LOT5m+1 corresponds to the round bar material group with lot number #LOT1 in the first embodiment above, so in the output processing of the first workplace sending data in step 151b of Fig. 9, it is determined whether or not the first workplace sending data has been output. Here, if the first workplace sending data has not been output, the determination in step 200 is NO.

[0416] In the second interrupt program, in step 300 in Fig. 28, it is determined whether the first workplace sending data for the selected material with lot number #LOT5m+2 (m=0) has already been output. Here, since the output process of the first workplace sending data in step 241 in Fig. 27 has not yet been performed, the determination in step 300 in Fig. 28 is NO.

[0417] In the third interrupt program, in step 400 in Fig. 29, it is determined whether the first workplace sending data for the selected material with lot number #LOT5m+3 (m=0) has already been output. Here, since the output process of the first workplace sending data in step 341 in Fig. 28 has not yet been performed, the determination in step 400 in Fig. 29 is NO.

[0418] In the fourth interrupt program, in step 500 in Fig. 30, it is determined whether the first workplace sending data for the selected material with lot number #LOT5m+4 (m=0) has already been output. Here, since the output process of the first workplace sending data in step 441 in Fig. 29 has not yet been performed, the determination in step 500 in Fig. 30 is NO.

[0419] In this state, when the main production instruction data setting process is performed in step 132 in Figure 7 or step 135c in Figure 8 as described in the first embodiment above, it is determined in step 144 in Figure 24 whether the first workplace sent data corresponding to the selected material with lot number #LOT5m+5 has already been output. At this stage, in the first workplace sent data output process in step 541 in Figure 30 of the fourth interrupt program, the first workplace sent data has not yet been output, so the determination in step 144 is NO.

[0420] Then, in the next step 144a, since n=0 at the current stage, the lead time group LTG(n) (see FIG. 23) is set to LTG(0). Accordingly, in step 144b, the target lead time LTM5n+1 is set to the target lead time LTM1 based on n=0. Here, the remaining target lead times LTM5n+2, LTM5n+3, LTM5n+4, and LTM5n+5 are set to LTM2, LTM3, LTM4, and LTM5, respectively (see FIG. 23).

[0421] Then, in the next step 144c, the lot number #LOT5m+1 is set to #LOT1 under m=0.

[0422] Thereafter, in step 140 of Fig. 25, it is determined whether or not the lot number has been input, as described in the first embodiment above. At this stage, the lot number has not been input, so the determination in step 140 is NO. Accordingly, when the lot number is input as #LOT1 using the operation device 40 of the home server Sa, the determination in step 140 is YES.

[0423] Next, in step 141, as described in the first embodiment, the lot number (#LOT1), input date, and completion date of the round bar material group are input into the respective fields of the lot number, input date, and completion date of the primary production instruction data by operating the operation device 40. Accordingly, in the printing process of the primary production instruction in step 142, the primary production instruction Q is printed out as described in the first embodiment.

[0424] Thereafter, in step 143, it is determined whether the original production instruction has been attached to the selected material. If the original production instruction has not been attached at this stage, the determination in step 143 is NO. Here, when the printed original production instruction Q is attached to the round bar material, which is the selected material, the CPU 31 determines YES in step 143 based on the reception output from the receiving circuit R0 in response to the transmission from the terminal P0 in the company warehouse 10 that accompanies the attachment.

[0425] Next, similarly to the process based on Fig. 9 described in the first embodiment, when the processes from step 151 to step 150a in Fig. 25 are completed, it is determined in the next step 150b in Fig. 25 whether the selected material is to be sent from the first workplace. At the current stage, if the sending out of the group of round bar materials with lot number #LOT1 after cutting has been completed, the determination in step 150b will be YES.

[0426] Accordingly, when the terminal P2 in the first workplace 20a operates to transmit information indicating the sending of the round bar material group with lot number #LOT1 after cutting and the sending date as first workplace sending data to the receiving circuit R2 of the computer 30 via the transmitting circuit Pa and the network N, the first workplace sending data from the receiving circuit R2 is output by the CPU 31 in the output processing of the first workplace sending data in the next step 151b. This means that in the lead time section LT11A of the target lead time LT11, the cutting of each round bar material in the round bar material group with lot number #LOT5m+1=#LOT1 in the first workplace 20a is completed, and the round bar material group is sent as the first workplace sending data after the completion. The first workplace sending data is output by the CPU 31 to the registration device Sb and registered and updated in the work-in-progress performance data table 3 in the registration device Sb.

[0427] Thereafter, in response to a NO determination in step 150c in the same manner as in the first embodiment, steps 150d to 152c in Fig. 10 and steps 150h to 152h in Fig. 26 are performed in the same manner as in the first embodiment. This completes the manufacture and delivery of each round bar material of the group of round bar materials with lot number #LOT1 in target lead time LT11 in this third embodiment as a finished product (round bar part). (First interrupt process) As described above, when the output process of the first workplace sending data is performed in step 151b in FIG. 25, the determination in step 200 in FIG. 27 becomes YES in the first interrupt program.

[0428] Accordingly, in the next step 201, the target lead time LTM5n+1 → LTM5n+2 and lot number #LOT5m+1 → #LOT5m+2 are processed. At the current stage, based on n=0, the target lead time group LTG(n)=LTG(0), so the target lead time LTM5n+1=LTM1. Therefore, the target lead time LTM5n+2 is set to the target lead time LTM2. Also, at the current stage, based on m=0, the lot number #LOT5m+1=#LOT1, so the lot number #LOT5m+2 is set to the lot number #LOT2.

[0429] This means that in the first interrupt program, the round bar blank group with lot number #LOT2 is processed and inspected under the target lead time LTM2.

[0430] Thereafter, in step 210, it is determined whether or not the lot number has been input. At this stage, the lot number #LOT2 has not been input, so the determination in step 210 is NO. Here, when #LOT2 is input into the lot number field of the original manufacturing instruction data by operating the operation device 40 of the home server Sa, the determination in step 210 is YES.

[0431] Accordingly, in the process of setting the lot number in the primary production instruction data in step 211, #LOT2 is input and updated in the lot number column of the primary production instruction data.

[0432] Next, in the printing process of the primary production instruction in step 212, the lot number #LOT2 and the entered primary production instruction are printed in the same manner as described above. After that, in step 220, it is determined whether the primary production instruction has been attached to the selected material. At this stage, the primary production instruction Q updated with the lot number #LOT2 has not been attached to the selected material group (round bar material group) of lot number #LOT2. Therefore, the determination in step 220 is NO.

[0433] In response to this, after lot number #LOT2 and the updated original production instruction Q are affixed to the round bar material group with lot number #LOT2 in our own warehouse 10, when the attachment information indicating that lot number #LOT2 and the updated original production instruction Q have been affixed to the round bar material group with lot number #LOT2 and the attachment date is transmitted as affixed data by terminal P0 through network N and receiving circuit R0 to CPU 31, the CPU 31 judges YES in step 220.

[0434] Next, after the group of round bar materials with lot number #LOT2 to which the original production instruction sheet has been attached is input from the company warehouse 10 to the first workplace 20a, receipt information indicating the receipt and receipt date of the group of round bar materials with lot number #LOT2 at the first workplace 20a is transmitted as first workplace receipt data by the terminal P1 through the network N and the receiving circuit R1 by tapping. Accordingly, in step 230, the determination is YES upon receipt of the first workplace receipt data.

[0435] Thereafter, in the next step 231, the first workplace receipt data output process, the first workplace receipt data is output to the registration device Sb in the same manner as described above, and is registered and updated in work-in-progress result data table 3.

[0436] Thus, in the first workplace 20a, as the cutting process of each of the round bar materials of the group of round bar materials with lot number #LOT2 is completed, the group of cut round bar materials is sent to the first outsourcing factory SF1. Accordingly, when the terminal P2 operates to transmit the sending information indicating the sending of the group of cut round bar materials with lot number #LOT2 and the sending date as the first workplace sending data to the CPU 31 via the network N and the receiving circuit R2, the CPU 31 judges YES in step 240.

[0437] Accordingly, in the next step 241, a process of outputting the first workplace sending data, the first workplace sending data is output by the CPU 31 to the registration device Sb and registered in the work-in-progress result data table 3 for updating.

[0438] Thereafter, in routine (or step) 250, the processes of step 150 in FIG. 25, step 150d to step 152c in FIG. 10, step 150h to the end step in FIG. 26, and step 160 to step 166 in FIG. 12 are performed in the same manner as described above.

[0439] In this way, as the lead time portion LT11A of the target lead time LTM1 elapses (end of cutting processing of each round bar material in the round bar material group of lot number #LOT2), the lead time portion LT11A of the target lead time LTM2 elapses (cutting processing of each round bar material in the round bar material group of lot number #LOT2), and when the target lead time LTM2 has elapsed, the manufacture of each round bar material in the round bar material group of lot number #LOT2 as a finished product (round bar part) is completed.

[0440] Therefore, following the completion of cutting of each round bar material of the group of round bar materials with lot number #LOT1 in the lead-time section LT11A of the target lead-time LTM1, cutting of each round bar material of the group of round bar materials with lot number #LOT2 in the lead-time section LT11A of the target lead-time LTM2 is performed, so the operating rate of the first workplace 20a can be improved. Also, the lead-time section LT11B following the lead-time section LT11A is also in a state where it can be operated in the same way. (Second interrupt processing) As described above, when the output process of the first workplace sending data is performed in step 241 in FIG. 27, the determination in step 300 in FIG. 28 becomes YES in the second interrupt program.

[0441] Accordingly, in the next step 301, the target lead time LTM5n+2 → LTM5n+3 and the lot number #LOT5m+2 → #LOT5m+3 are processed. At the current stage, based on n=0, the target lead time group LTG(n)=LTG(0), so the target lead time LTM5n+2=LTM2. Therefore, the target lead time LTM5n+3 is set to LTM3. Also, at the current stage, based on m=0, the lot number #LOT5m+2=#LOT2, so the lot number #LOT5m+3 is set to lot number #LOT3.

[0442] This means that in the second interrupt program, the round bar blank group with lot number #LOT3 is processed and inspected under the target lead time LTM3.

[0443] Thereafter, in step 310, it is determined whether or not the lot number has been input. At this stage, the lot number #LOT3 has not been input, so the determination in step 310 is NO. Here, when #LOT3 is input into the lot number field of the original manufacturing instruction data by operating the operation device 40 of the home server Sa, the determination in step 310 is YES.

[0444] Accordingly, in the process of setting the lot number in the primary production instruction data in step 311, #LOT3 is input and updated in the lot number column of the primary production instruction data.

[0445] Next, in the printing process of the primary production instruction in step 312, the lot number #LOT3 and the entered primary production instruction are printed in the same manner as described above. After that, in step 320, it is determined whether the primary production instruction has been attached to the selected material. At this stage, the primary production instruction Q updated with the lot number #LOT3 has not been attached to the selected material group (round bar material group) of lot number #LOT3. Therefore, the determination in step 320 is NO.

[0446] In response to this, in our own warehouse 10, after lot number #LOT3 and the updated original production instruction Q are affixed to the round bar material group with lot number #LOT3, the attachment information indicating that lot number #LOT3 and the updated original production instruction Q have been affixed to the round bar material group with lot number #LOT2 and the attachment date is transmitted as affixed data by terminal P0 through network N and receiving circuit R0 to CPU 31. In step 320, the CPU 31 judges YES.

[0447] Next, after the group of round bar materials with lot number #LOT3 to which the original production instruction sheet is attached is input from the company warehouse 10 to the first workplace 20a, receipt information indicating the receipt and receipt date of the group of round bar materials with lot number #LOT3 at the first workplace 20a is transmitted as first workplace receipt data by the terminal P1 through the network N and the receiving circuit R1 by tapping. Accordingly, in step 330, the determination is YES upon receipt of the first workplace receipt data.

[0448] Accordingly, in the next step 331, the first workplace receipt data output process, the first workplace receipt data is output to the registration device Sb in the same manner as described above, and is registered and updated in work-in-progress result data table 3.

[0449] Thereafter, in the next step 340, it is determined whether or not the selected material has been sent out from the first work station 20a. At this stage, the selected material, the round bar material, has not been sent out from the first work station 20a, so the determination in step 340 is NO.

[0450] After the determination in step 340 is NO, when the cutting process of each of the round bar materials of the group of round bar materials with lot number #LOT3 is completed in the first workplace 20a, the group of cut round bar materials is sent to the first outsourcing factory SF1. Here, when the terminal P2 operates to transmit sending information indicating the sending of the group of cut round bar materials with lot number #LOT3 and the sending date as the first workplace sending data to the CPU 31 via the network N and the receiving circuit R2, the CPU 31 determines in step 340 as YES.

[0451] Accordingly, in the next step 341, which is a process of outputting the first workplace sending data, the first workplace sending data is output to the registration device Sb and registered in the work-in-progress result data table 3 for updating.

[0452] Thereafter, in a routine (or step) 350, the same processing as in the routine (or step) 250 in FIG. 27 is carried out.

[0453] In this way, as the lead time section LT11A of the target lead time LTM2 elapses (end of cutting processing of each round bar material in the round bar material group with lot number #LOT2), the lead time section LT11A of the target lead time LTM3 begins (cutting processing of each round bar material in the round bar material group with lot number #LOT3), and when the target lead time LT3 has elapsed, the manufacture of each round bar material in the round bar material group with lot number #LOT3 as a finished product (round bar part) is completed.

[0454] Therefore, following the completion of cutting of each round bar material of the group of round bar materials with lot number #LOT2 in the lead-time section LT11A of the target lead-time LTM2, cutting of each round bar material of the group of round bar materials with lot number #LOT3 in the lead-time section LT11A of the target lead-time LTM3 is performed, so that the operating rate of the first workplace 20a can be improved. Also, work can be performed in the same way after the lead-time section LT11B. (Third interrupt processing) As described above, when the output process of the first workplace sending data is performed in step 341 in FIG. 28, the determination in step 400 in FIG. 29 becomes YES in the third interrupt program.

[0455] Accordingly, in the next step 401, the target lead time LTM5n+3→LTM5n+4 and the lot number #LOT5m+3→#LOT5m+4 are processed. At the current stage, based on n=0, the target lead time group LTG(n)=LTG(0), so the target lead time LTM5n+3=LTM3. Therefore, the target lead time LTM5n+4 is set to LTM4. Also, at the current stage, based on m=0, the lot number #LOT5m+3=#LOT3, so the lot number #LOT5m+4 is set to lot number #LOT4.

[0456] This means that in the third interrupt program, the round bar raw material group with lot number #LOT4 is processed and inspected under the target lead time LTM4.

[0457] Thereafter, when the answer to step 410 is YES following the input operation of lot number #LOT4, in the process of setting the lot number in the primary production instruction data in step 411, #LOT4 is input and updated in the lot number column of the primary production instruction data.

[0458] Next, in the printing process of the primary production instruction in step 412, the lot number #LOT4 and the input primary production instruction are printed in the same manner as described above. Thereafter, when the lot number #LOT4 and the updated primary production instruction Q are pasted to the selected material group (round bar material group) of lot number #LOT4, pasting information indicating the pasting of the lot number #LOT4 and the updated primary production instruction Q to the round bar material group of lot number #LOT4 and the pasting date is transmitted as pasted data by the terminal P0 through the network N and the receiving circuit R0 to the CPU 31 under its operation. Accordingly, the determination in step 420 is YES.

[0459] Then, after the group of round bar materials with lot number #LOT4 to which the original production instruction sheet is attached is input from the company warehouse 10 to the first workplace 20a, receipt information indicating the receipt and receipt date of the group of round bar materials with lot number #LOT4 at the first workplace 20a is transmitted as first workplace receipt data by the terminal P1 through the network N and the receiving circuit R1 by tapping the terminal P1. Accordingly, in step 430, the determination is YES upon receipt of the first workplace receipt data.

[0460] Accordingly, in the next step 431, the first workplace receipt data output process, the first workplace receipt data is output to the registration device Sb in the same manner as described above, and is registered and updated in work-in-progress result data table 3.

[0461] Thereafter, in the next step 440, it is determined whether the selected material has been sent out from the first work station 20a. At this stage, the selected material, the round bar material, has not been sent out from the first work station 20a, so the determination in step 440 is NO.

[0462] After the determination in step 440 is NO, when the cutting process of each of the round bar materials of the group of round bar materials with lot number #LOT4 is completed in the first workplace 20a, the group of cut round bar materials is sent to the first outsourcing factory SF1. Then, when the terminal P2 operates to transmit sending information indicating the sending of the group of cut round bar materials with lot number #LOT4 and the sending date as the first workplace sending data to the CPU 31 via the network N and the receiving circuit R2, the CPU 31 determines in step 440 as YES.

[0463] Accordingly, in the next step 441, a process of outputting the first workplace sending data, the first workplace sending data is output to the registration device Sb by the CPU 31, and is registered and updated in the work-in-progress result data table 3.

[0464] Thereafter, in a routine (or step) 450, the same processing as in the routine (or step) 350 of FIG. 28 is performed.

[0465] In this way, as the lead time portion LT11A of the target lead time LTM3 elapses (end of cutting processing of each round bar material in the round bar material group with lot number #LOT3), the lead time portion LT11A of the target lead time LTM4 (cutting processing of each round bar material in the round bar material group with lot number #LOT4) begins, and when the target lead time LTM4 has elapsed, the manufacture of each round bar material in the round bar material group with lot number #LOT4 as a finished product (round bar part) is completed.

[0466] Therefore, following the completion of cutting of each round bar material of the group of round bar materials with lot number #LOT3 in the lead-time section LT11A of the target lead-time LTM3, cutting of each round bar material of the group of round bar materials with lot number #LOT4 in the lead-time section LT11A of the target lead-time LTM4 is performed, so the operating rate of the first workplace 20a can be improved. In addition, the lead-time sections LT11B and after are also in a state where they can continue to work in the same manner. (4th interrupt processing) As described above, when the output process of the first workplace sending data is performed in step 441 in FIG. 29, the determination in step 500 in FIG. 30 becomes YES in the fourth interrupt program.

[0467] Accordingly, in the next step 501, the target lead time LTM5n+4→LTM5n+5 and the lot number #LOT5m+4→#LOT5m+5 are processed. At the current stage, based on n=0, the target lead time group LTG(n)=LTG(0), so the target lead time LTM5n+4=LTM4. Therefore, the target lead time LTM5n+5 is set to LTM5. Also, at the current stage, based on m=0, the lot number #LOT5m+4=#LOT4, so the lot number #LOT5m+5 is set to the lot number #LOT5.

[0468] This means that in the fourth interrupt program, the round bar raw material group with lot number #LOT5 is processed and inspected under the target lead time LTM5.

[0469] Thereafter, when the answer to step 510 is YES following the input operation of lot number #LOT5, in the process of setting the lot number in the primary production instruction data in step 511, #LOT5 is input and updated in the lot number column of the primary production instruction data.

[0470] Next, in the printing process of the primary production instruction in step 512, the lot number #LOT5 and the input primary production instruction are printed in the same manner as described above. After that, when the lot number #LOT5 and the updated primary production instruction Q are pasted to the selected material group (round bar material group) of lot number #LOT5, pasting information indicating the pasting of the lot number #LOT5 and the updated primary production instruction Q to the round bar material group of lot number #LOT5 and the pasting date is transmitted as pasted data by the terminal P0 through the network N and the receiving circuit R0 to the CPU 31 under its operation. Accordingly, the determination in step 520 is YES.

[0471] Then, after the group of round bar materials with lot number #LOT5 to which the original production instruction sheet is attached is input from the company warehouse 10 to the first workplace 20a, receipt information indicating the receipt and receipt date of the group of round bar materials with lot number #LOT5 at the first workplace 20a is transmitted as first workplace receipt data by the terminal P1 through the network N and the receiving circuit R1 by tapping the terminal P1. Accordingly, in step 530, the determination is YES upon receipt of the first workplace receipt data.

[0472] Accordingly, in the next step 531, the first workplace receipt data output process, the first workplace receipt data is output to the registration device Sb in the same manner as described above, and is registered and updated in work-in-progress result data table 3.

[0473] Thereafter, in the next step 540, it is determined whether the selected material has been sent out from the first work station 20a. At this stage, the selected material, the round bar material, has not been sent out from the first work station 20a, so the determination in step 540 is NO.

[0474] After the determination in step 540 is NO, when the cutting process of each of the round bar materials of the group of round bar materials with lot number #LOT5 is completed in the first workplace 20a, the group of cut round bar materials is sent to the first outsourcing factory SF1. Accordingly, when the terminal P2 operates to transmit, as the first workplace transmission data, transmission information indicating the transmission of the group of cut round bar materials with lot number #LOT5 and the transmission date, to the CPU 31 via the network N and the receiving circuit R2, the CPU 31 determines in step 540 as YES.

[0475] Accordingly, in the next step 541, a process of outputting the first workplace sending data, the first workplace sending data is output to the registration device Sb by the CPU 31, and is registered and updated in the work-in-progress result data table 3.

[0476] Thereafter, in a routine (or step) 550, the same processing as in the routine (or step) 450 in FIG. 29 is performed.

[0477] In this way, as the lead time portion LT11A of the target lead time LTM4 elapses (end of cutting processing of each round bar material in the round bar material group with lot number #LOT4), the lead time portion LT1A of the target lead time LT5 (cutting processing of each round bar material in the round bar material group with lot number #LOT5) begins, and when the target lead time LTM5 has elapsed, the manufacture of each round bar material in the round bar material group with lot number #LOT5 as a finished product (round bar part) is completed.

[0478] Therefore, following the completion of cutting of each round bar material of the group of round bar materials with lot number #LOT4 in the lead-time section LT11A of the target lead-time LTM4, cutting of each round bar material of the group of round bar materials with lot number #LOT5 in the lead-time section LT11A of the target lead-time LTM5 is performed, so the operating rate of the first workplace 20a can be improved. In addition, the lead-time sections LT11B and after are also similarly able to continue work.

[0479] After each round bar material of each round bar material group of lot numbers #LOT1 to #LOT5 is manufactured into a finished round bar part in the above manner, the first workplace sending data has already been output in step 541 of Fig. 30 as described above, so that the result is YES in step 144 of Fig. 24. Accordingly, in step 145, the target lead time group LTG(n) is updated to LTG(1) under n=1.

[0480] Next, in step 146, under n=1, the target lead time LTM5n+1 is updated to target lead time LTM6. Here, the remaining target lead times LTM5n+2, LTM5n+3, LTM5n+4, and LTM5n+5 under n=1 are updated to LTM7, LTM8, LTM9, and LTM10, respectively.

[0481] Next, in step 147, under m=1, lot number #LOT5m+1 is updated to lot number #LOT6. The remaining lot numbers #LOT5m+2 to #LOT5m+5 are updated to #LOT7 to #LOT10.

[0482] Thereafter, the processing from step 140 onward in Fig. 25 is carried out in the same manner as described above. Accordingly, each of the round bar blanks in each group of round bar blanks ranging from lot number #LOT6 to lot number #LOT10 is manufactured into a finished product.

[0483] As described above, in the third embodiment, in addition to the computer program, the first to fourth interrupt programs are provided to perform interrupt processing on the computer program, and the first to fourth interrupt programs start interrupt processing (see Figs. 27 to 30) each time the receiving circuit R4 receives data sent from the terminal P4 of the first workplace 20a. Accordingly, the same processing as that for the round bar material group with lot number #LOT1 is performed on each of the round bar material groups with lot numbers #LOT2 and onward, which are successive to the round bar material group with lot number #LOT1.

[0484] Therefore, the cutting process of each successive group of round bar blanks in the first work station 20a starts each time the preceding cutting process in the first work station 20a is completed. This means that the cutting process of the succeeding group of round bar blanks in the first work station 20a starts each time the preceding group of round bar blanks in the first work station 20a is completed.

[0485] Accordingly, the cutting process in the first workshop 20a is performed continuously for each group of subsequent round bar materials. This means that the same is true for the subsequent first outsourcing factory SF1, second outsourcing factory SF2, third workshop 20c, and fourth workshop 20d. As a result, the operating rates of the workers in the first workshop 20a, first outsourcing factory SF1, second outsourcing factory SF2, third workshop 20c, and fourth workshop 20d can be well secured.

[0486] In the third embodiment, as described above, the case where each target lead time in the target lead time statement group LTG(n) in Fig. 23 is excessive or not rapidly decreasing for a round bar material has been described, but the present invention is not limited to this, and the case where the target lead time is not excessive or not rapidly decreasing or not excessive or not rapidly decreasing for a round bar material is also processed in substantially the same manner. Moreover, the present invention is not limited to round bar materials, and the processing is substantially the same for sheet metal materials as for round bar materials.

[0487] It should be noted that the present invention is not limited to the above-described embodiments, and various modifications may be made as follows. (1) In carrying out the present invention, each pair of terminals provided at each workplace or each subcontract factory may be a single terminal provided at each workplace or each subcontract factory. Accordingly, each receiving circuit may also be a single circuit so as to correspond to each single terminal. If the part is a type that has been produced in the past, the existing tentative lead time may be used as the tentative lead time. Also, it is possible to instruct the production of multiple parts of the same type in one lot. (2) In addition, in implementing the present invention, in the above third embodiment, processing of the first leadtime portion (corresponding to the first workplace 20a) of the succeeding target leadtime (e.g., target leadtime LTM5n+2) is started upon completion of processing of the first leadtime portion (e.g., target leadtime LTM5n+1) as soon as processing of the first leadtime portion (corresponding to the first workplace 20a) of the succeeding target leadtime (e.g., target leadtime LTM5n+2) is completed. However, instead of this, processing of the first leadtime portion (corresponding to the first workplace 20a) of the succeeding leadtime (e.g., target leadtime LTM5n+2) may be started upon completion of processing of a leadtime portion other than the first leadtime portion of the preceding target leadtime (e.g., target leadtime LTM5n+1). [Explanation of symbols]

[0488] 20...Our own factory, 20a-20d...Workplaces 1-4, 113, 115, 120, 121, 123, 131b, 132... steps, SF1: 1st outsourcing factory, SF2: 2nd outsourcing factory, H1A~H1D: processing time, H1E…Inspection time, IPD1~IPD4, IPDSF1, IPDSF2...Work in progress performance data, LT1: tentative lead time, LT1A~LT1E: lead time section, LT11~LT13: Target lead time, PBFa: Provisional manufacturing instructions, Q...Normal manufacturing instructions, T1A~T1D...Processing waiting time, T1E...Inspection waiting time, α: predetermined relaxation time, θ: predetermined increase in work in progress.

Claims

1. In a production management system that is applied to both an in-house factory having multiple in-house processing workplaces and in-house inspection workplaces and an outsourced factory having at least one outsourced processing workplace, a provisional lead time setting means for setting the provisional lead time, which comprises a leading lead time section and a trailing lead time section following the leading lead time section, so that the provisional lead time is comprised in the leading lead time section of a processing waiting time and a processing time required for processing each corresponding material of a corresponding material group for each ordered part of an ordered part group by a processing means disposed in any one of the in-house processing workplaces of the plurality of in-house processing workplaces or the outsourced processing workplace, and is comprised in the trailing lead time section of an inspection waiting time and an inspection time required for inspecting each corresponding material of the corresponding material group after processing by an inspection means disposed in the in-house inspection workplace; a target leadtime setting means for setting a target leadtime consisting of a leading target leadtime section and a trailing target leadtime section following the leading target leadtime section, wherein the target leadtime is set so that the processing wait time and the processing time constituting the leading leadtime section of the tentative leadtime related to the setting by the tentative leadtime setting means are configured as a target processing wait time and a target processing time in the leading target leadtime section, and the inspection wait time and the inspection time constituting the trailing leadtime section of the tentative leadtime are configured as a target inspection wait time and a target inspection time in the trailing target leadtime section; a conversion setting means for converting and setting temporary manufacturing instruction data representing a temporary manufacturing instruction formed by inputting the target processing wait time, the target processing time, the target inspection wait time, and the target inspection time, into regular manufacturing instruction data representing a regular manufacturing instruction formed by displaying each input content into the temporary manufacturing instruction.

2. a work-in-progress quantity setting means for calculating a future work-in-progress quantity of the corresponding material in accordance with the number of the ordered parts based on the work-in-progress performance data of the corresponding material and setting the calculated work-in-progress quantity in the future; a work-in-progress quantity determination means for determining whether the calculated future work-in-progress quantity of the corresponding material is excessive or not; When the in-process quantity determination means determines that the future calculated in-process quantity of the corresponding material is excessive, the target processing time or the target inspection time of the corresponding material is expressed as a target time based on the processing capacity of any one of the in-house processing plants or the outsourced processing plants and the target in-process quantity of the corresponding material or the inspection capacity and the target in-process quantity of the inspection plant, and the target time is expressed as a target time based on the following formula (1): Target time = Target number of works in progress ÷ Processing capacity (1) A target time calculation means for calculating a target time based on the above. a waiting time adjustment means for adjusting a waiting time when a calculated work-in-process quantity is excessive, which adjusts the processing waiting time by subtracting the preceding lead time portion of the tentative lead time related to the setting of the corresponding material until the preceding lead time portion is reduced to the target time, and adjusts the processing waiting time by subtracting the inspection waiting time until the succeeding lead time portion of the tentative lead time related to the setting is reduced to the target inspection time; a tentative leadtime update setting means for updating the processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting with the subtracted processing wait time, and updating the inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting with the subtracted inspection wait time, and setting both update results together with the processing time and the inspection time as an updated tentative leadtime, the target lead time is set as a first target lead time, and the target processing wait time, the target processing time, the target inspection wait time and the target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, and the target lead time setting means is set to include a second target lead time in addition to the first target lead time, and the second target lead time is configured with an advanced lead time section having the subtracted processing wait time of the advanced lead time section of the updated tentative lead time together with the processing time as a second target processing wait time, and a subsequent lead time section having the subtracted inspection wait time of the subsequent lead time section of the updated tentative lead time together with the inspection time as a second target inspection wait time, 2. The production management system according to claim 1, wherein the conversion setting means converts and sets temporary manufacturing instruction data representing a second temporary manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time into regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying each input content into the second temporary manufacturing instruction, as a first temporary manufacturing instruction and a first regular manufacturing instruction, respectively.

3. 3. The production management system according to claim 2, wherein the in-process quantity determination means determines the in-process quantity to be excessive when the future calculated in-process quantity of the corresponding material increases beyond the in-process target quantity of the extracted in-process target data for the corresponding material by at least a predetermined in-process increase number.

4. A sudden decrease determination means for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; an order quantity sudden decrease wait time adjustment means for adjusting, when the future calculated in-process quantity of the corresponding material suddenly decreases, the order quantity of the ordered part is judged to have suddenly decreased by the sudden decrease judgment means, so as to add a predetermined relaxation time to the processing wait time in the preceding lead time portion of the tentative lead time related to the setting and set it as an added processing wait time, and also add the predetermined relaxation time to the inspection wait time in the succeeding lead time portion of the tentative lead time related to the setting and set it as an added inspection wait time; a tentative leadtime update setting means for updating the processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting with the added processing wait time, and updating the inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting with the added inspection wait time, and setting both update results together with the processing time as an updated tentative leadtime, the target lead time is a first target lead time, and the target processing wait time, the target processing time, the target inspection wait time and the target inspection time are respectively a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, and the target lead time setting means has a second target lead time in addition to the first target lead time, and sets the second target lead time to be configured with a leading lead time section having the added processing wait time in the leading lead time section of the updated tentative lead time together with the processing time as a second target processing wait time, and a trailing lead time section having the added inspection wait time in the trailing lead time section of the updated tentative lead time together with the inspection time as a second target inspection wait time, 2. The production management system according to claim 1, wherein the conversion setting means converts and sets temporary manufacturing instruction data representing a second temporary manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time into regular manufacturing instruction data representing a second regular manufacturing instruction obtained by displaying each input content into the second temporary manufacturing instruction, as a first temporary manufacturing instruction and a first regular manufacturing instruction, respectively.

5. 5. A production management system according to claim 4, wherein in said sudden decrease means, said sudden decrease is specified by a sudden decrease speed within a predetermined sudden decrease speed range and a sudden decrease rate within a predetermined sudden decrease rate range.

6. A sudden decrease determination means for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; when the future calculated in-process quantity of the corresponding material is determined to be excessive by the in-process quantity determination means and when the future calculated in-process quantity of the corresponding material is suddenly decreased and the sudden decrease determination means determines that the number of orders for the ordered parts has suddenly decreased, a means for determining whether or not both the excessive quantity and the sudden decrease have been resolved; an excessiveness maintenance / sudden decrease elimination determination means for determining whether or not the sudden decrease has been eliminated while the excessiveness is maintained, when the excessiveness / sudden decrease elimination determination means determines that both the excessiveness and the sudden decrease have not been eliminated; a sudden decrease maintenance / excessive elimination determination means for determining whether or not the excessive state has been eliminated while the sudden decrease is maintained when the excessive state maintenance / sudden decrease elimination determination means determines that the sudden decrease has not been eliminated while the excessive state is maintained, when the excessive / rapid decrease both elimination determination means determines that both the excessiveness and the sudden decrease have been eliminated, the determination of excessiveness by the work-in-process quantity determination means and the determination of sudden decrease by the sudden decrease determination means are eliminated, and the tentative lead time is set by the tentative lead time setting means based on a non-excessiveness of the calculated work-in-process quantity in the future and a non-sudden decrease in the number of orders, the target lead time is set by the target lead time setting means, and the conversion setting means converts and sets the data to the regular production instruction data, when the excessive-maintenance / sudden-decrease elimination determination means determines that the sudden decrease has been eliminated while the excessive amount is maintained, the sudden decrease determination means cancels the determination that the number of orders has suddenly decreased, and the tentative lead time is set by the tentative lead time setting means based on the excessive amount of the calculated future work-in-process quantity and the non-sudden decrease in the number of orders, the target lead time is set by the target lead time setting means, and the conversion setting means converts the data into the regular production instruction data. The production management system according to claim 2, further comprising: a means for determining whether or not the quantity in process is excessive; a means for determining whether or not the quantity in process is excessive; a means for determining whether or not the quantity in process is excessive; a means for determining whether or not the quantity in process is excessive; a means for determining whether or not the quantity in process is excessive;

7. A plurality of terminal means are provided in any one of the in-house processing workplaces, the in-house inspection workplace, and the outsourced processing workplace; A plurality of receiving means, a processing means, and a registration device corresponding to the plurality of receiving means; a processing plant receiving data output means for outputting the processing plant receiving data from a processing plant terminal means disposed in one of the plurality of terminal means at the processing plant of the company or the outsourced processing plant, which indicates receiving information of the corresponding material group with the original manufacturing instruction attached thereto, to the corresponding receiving means of the processing plant terminal means of the plurality of receiving means via a network, to the corresponding receiving means of the processing plant terminal means of the plurality of receiving means; a processing plant sending data output means for outputting the processing plant sending data representing sending information of the corresponding material group after processing from the processing plant terminal means to the corresponding receiving means via the network to the corresponding receiving means to the registration device when the corresponding material group after processing is sent to the in-house inspection plant by processing the corresponding material group by the processing means during the processing time after waiting for the passage of the target processing waiting time when the corresponding material group is received at any one of the in-house processing plants or the outsourced processing plants; an inspection workplace receipt data output means for outputting the inspection workplace receipt data from the other receiving means to the registration device when the inspection workplace terminal means, among the plurality of terminal means, which is disposed at the company's inspection workplace, transmits inspection workplace receipt data representing receipt information of the corresponding material group after the processing to another receiving means corresponding to the inspection workplace terminal means among the plurality of receiving means via the network in response to the receipt of the corresponding material group at the company's inspection workplace after the processing; an inspection workplace sending data output means for transmitting inspection workplace sending data representing sending information of the corresponding material group after the inspection to the other receiving means via the network by the inspection workplace terminal means when the corresponding material group after the processing is received at the company's inspection workplace and the corresponding material group after the processing is inspected by the inspection means during the inspection time after waiting for the passage of the target inspection waiting time, and the corresponding material group after the inspection is sent out as a material part group consisting of material parts that are finished products, by the inspection workplace terminal means, and outputting the inspection workplace sending data from the other receiving means to the registration device, 7. The production management system according to claim 1, 2, 4 or 6, wherein said registration device updates the in-process result data already registered therein based on said processing plant receiving data from said processing plant receiving data output means, said processing plant sending data from said processing plant sending data output means, said inspection plant receiving data from said inspection plant receiving data output means, and said inspection plant sending data from said inspection plant sending data output means.

8. 7. The production management system according to claim 1, 2, 4 or 6, wherein the at least one outsourcing factory is included as at least one processing plant among the plurality of in-house processing plants.

9. the computer program means consisting of the processing plant receiving data output means, the processing plant sending data output means, the inspection plant receiving data output means and the inspection plant sending data output means is used as a main program means, and an interrupt program means is provided for performing an interrupt process on the main program means, 8. A production management system according to claim 7, wherein said interrupt program means, when said processing plant sending data transmitted from said processing plant terminal means is received by said corresponding receiving means, performs processing similar to the processing by said processing plant received data output means and the processing by said processing plant sent data output means, said inspection plant received data output means and said inspection plant sent data output means in accordance with said main program means in connection with the input of another corresponding material group subsequent to said corresponding material group, which other corresponding material group has a regular manufacturing instruction attached to it to which the input contents of said temporary manufacturing instruction have been input, into said one of said in-house processing plants or said outsourced processing plants.

10. In a production management method that is applied to both an in-house factory having multiple in-house processing workplaces and in-house inspection workplaces (multiple workplaces) and an outsourced factory having at least one outsourced processing workplace, a provisional lead time setting step, comprising a provisional lead time consisting of a leading lead time section and a trailing lead time section following the leading lead time section, the provisional lead time being set so that the provisional lead time is comprised in the leading lead time section of a processing waiting time and a processing time required for processing each corresponding material of a corresponding material group for each ordered part of an ordered part group by a processing means arranged in any one of the plurality of in-house processing workplaces or the outsourced processing workplace, and is comprised in the trailing lead time section of an inspection waiting time and an inspection time required for inspecting each corresponding material of the corresponding material group after processing by an inspection means arranged in the in-house inspection workplace; a target leadtime setting step for setting a target leadtime consisting of a leading target leadtime section and a trailing target leadtime section subsequent to the leading target leadtime section, such that the processing wait time and the processing time constituting the leading leadtime section of the tentative leadtime related to the setting in the tentative leadtime setting step are configured as a target processing wait time and a target processing time in the leading target leadtime section, and the inspection wait time and the inspection time constituting the trailing leadtime section of the tentative leadtime are configured as a target inspection wait time and a target inspection time in the trailing target leadtime section; a conversion setting step of converting and setting temporary manufacturing instruction data representing a temporary manufacturing instruction obtained by inputting the target processing wait time, the target processing time, the target inspection wait time, and the target inspection time, into regular manufacturing instruction data representing a regular manufacturing instruction obtained by displaying each input content into the temporary manufacturing instruction.

11. a work-in-progress quantity setting step of calculating a future work-in-progress quantity of the corresponding material in accordance with the number of the ordered parts based on the work-in-progress performance data of the corresponding material and setting the calculated work-in-progress quantity as a future calculated work-in-progress quantity; a work-in-progress quantity determination step for determining whether the calculated future work-in-progress quantity of the corresponding material is excessive or not; When it is determined in the in-process quantity determination step that the calculated future in-process quantity of the corresponding material is excessive, the target processing time or the target inspection time of the corresponding material is expressed as a target time based on the processing capacity of any one of the in-house processing plants or the outsourced processing plants and the target in-process quantity of the corresponding material or the inspection capacity and the target in-process quantity of the inspection plant, and the target time is expressed as the following formula (1): Target time = Target number of works in progress ÷ Processing capacity (1) A target time calculation step of calculating a target time based on the above. a wait time adjustment step when a calculated work-in-process quantity is excessive, which subtracts the processing wait time until the leading lead time portion of the tentative lead time related to the setting of the corresponding material is reduced to the target time, and adjusts the processing wait time as a subtraction wait time, and subtracts the inspection wait time until the trailing lead time portion of the tentative lead time related to the setting is reduced to the target time, and adjusts the processing wait time as a subtraction wait time; a tentative leadtime update setting step for updating the processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting with the subtracted processing wait time, and updating the inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting with the subtracted inspection wait time, and setting both update results together with the processing time and the inspection time as an updated tentative leadtime, the target lead time is set as a first target lead time, and the target processing wait time, the target processing time, the target inspection wait time and the target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, in the target lead time setting step, a second target lead time is provided in addition to the first target lead time, and the second target lead time is set to be composed of an advanced lead time section having the subtracted processing wait time of the advanced lead time section of the updated tentative lead time together with the processing time as a second target processing wait time, and a subsequent lead time section having the subtracted inspection wait time of the subsequent lead time section of the updated tentative lead time together with the inspection time as a second target inspection wait time; 11. The production management method according to claim 10, further comprising the steps of: converting and setting the provisional manufacturing instruction and the primary manufacturing instruction as a first provisional manufacturing instruction and a first primary manufacturing instruction, respectively, in the conversion setting step, converting and setting provisional manufacturing instruction data representing a second provisional manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time, into primary manufacturing instruction data representing a second primary manufacturing instruction obtained by displaying each input content into the second provisional manufacturing instruction.

12. a sudden decrease determination step for determining whether or not there is a sudden decrease in the number of orders for the ordered parts; a waiting time adjustment step for adjusting the waiting time when the future calculated in-process quantity of the corresponding material suddenly decreases, when it is determined in the sudden decrease determination step that the order quantity of the ordered part has suddenly decreased, by adding a predetermined relaxation time to the processing waiting time in the preceding lead time portion of the tentative lead time related to the setting and setting it as an added processing waiting time, and by adding the predetermined relaxation time to the inspection waiting time in the succeeding lead time portion of the tentative lead time related to the setting and setting it as an added inspection waiting time; a tentative leadtime update setting step for updating the processing wait time in the preceding leadtime portion of the tentative leadtime related to the setting with the added processing wait time, and updating the inspection wait time in the succeeding leadtime portion of the tentative leadtime related to the setting with the added inspection wait time, and setting both update results together with the processing time as an updated tentative leadtime, the target lead time is set as a first target lead time, and the target processing wait time, the target processing time, the target inspection wait time and the target inspection time are set as a first target processing wait time, a first target processing time, a first target inspection wait time and a first target inspection time, respectively, in the target lead time setting step, a second target lead time is provided in addition to the first target lead time, and the second target lead time is set to be composed of a leading lead time portion having the added processing wait time in the leading lead time portion of the updated tentative lead time together with the processing time as a second target processing wait time, and a trailing lead time portion having the added inspection wait time in the trailing lead time portion of the updated tentative lead time together with the inspection time as a second target inspection wait time, 11. The production management method according to claim 10, further comprising the steps of: setting the provisional manufacturing instruction and the primary manufacturing instruction as a first provisional manufacturing instruction and a first primary manufacturing instruction, respectively, in the conversion setting step, converting and setting provisional manufacturing instruction data representing a second provisional manufacturing instruction obtained by inputting the second target processing wait time, the second target processing time, the second target inspection wait time, and the second target inspection time, into primary manufacturing instruction data representing a second primary manufacturing instruction obtained by displaying each input content into the second provisional manufacturing instruction.

Citation Information

Patent Citations

  • Production management system and production management method

    JP2020166548A

Cited By

  • Production plan creation method and production plan creation device

    WO2026167918A1