Construction method for precast floor slab

The method of installing precast floor slabs with vertically penetrating holes on steel frames enables continuous installation and efficient steel frame joining, reducing construction time and improving safety by allowing simultaneous crane use for both processes.

JP2024162149APending Publication Date: 2024-11-21SHIMIZU CORP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023077426
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-09
Publication Date
2024-11-21

AI Technical Summary

Technical Problem

Conventional construction methods for high-rigidity perforated precast floor slabs on steel frames require complete steel frame joining before slab installation, limiting continuous installation and efficiency, especially in environments where immediate production is desired.

Method used

A method involving precast floor slabs with vertically penetrating holes allows for continuous installation by enabling steel frame joining from below the slab through a first hole and from above through a second hole, facilitating simultaneous crane use for both steel frame erection and slab installation.

Benefits of technology

This approach shortens construction periods, enhances workability, and improves safety by allowing continuous installation of precast slabs during steel frame erection, enabling efficient and safe steel frame joining with cranes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024162149000001_ABST
    Figure 2024162149000001_ABST
Patent Text Reader

Abstract

To provide a construction method for a precast floor slab that contributes to shortening construction time even when the step includes the installation of the precast floor slab in the steel frame erection cycle.SOLUTION: The steel frame construction step includes a steel frame erection step for erecting the steel frame, and a steel frame joining step for joining steel frame joints 23. A first cutout portion 41 (first hole portion) through which a welding worker 7 (a worker who joins the steel frame) can pass is formed in the precast floor slab 1. The precast floor slab installation step is performed consecutively after the steel frame erection step, and the steel frame joining step is performed after the precast floor slab installation step, in which the welding worker 7 passes through the first cutout portion 41 and moves from above the precast floor slab 1 onto a scaffolding 6 temporarily installed below the precast floor slab 1, and joins the steel frame from below the precast floor slab 1.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction method for precast deck slabs. [Background technology]

[0002] Conventionally, precast decks have been used in the construction of structures to save labor and reduce costs (see, for example, Patent Document 1). In production facilities that produce semiconductors and precision equipment, there are an increasing number of cases where high-rigidity perforated precast decks, which have multiple holes that penetrate vertically to prevent the occurrence of micro-vibrations, are being adopted. When using high-rigidity perforated precast decks, it is possible to use conventional construction methods, but in light of the current tight labor situation and the unique situation of production facilities where production operations need to be started immediately, the main structural framework is planned to be made of steel, and high-rigidity perforated precast decks are used for the floors. In such cases, in order to make the structural frame on which the high-rigidity perforated precast deck slab is placed a high-rigidity frame, the steel beams, columns, etc. must be rigidly joined. These joints are welded rather than bolted. Note that welded joints are often used rather than bolted due to construction ease and cost considerations. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2019-2251 A Summary of the Invention [Problem to be solved by the invention]

[0004] When a precast deck such as a high-rigidity perforated precast deck is installed on top of a structural frame, the joints of the steel frame are hidden by the precast deck, so the steel frame joints must be completed before the precast deck is installed. This means that the precast deck cannot be installed immediately after the steel frame is erected, and the need to complete the steel frame joints also creates the problem of inefficiency when using a build-and-run method in which construction is performed while moving a crane.

[0005] Therefore, an object of the present invention is to provide a construction method for precast deck slabs that contributes to shortening construction time by including the installation of precast deck slabs in the steel frame erection cycle. [Means for solving the problem]

[0006] In order to achieve the above-mentioned object, the precast deck construction method of the present invention comprises a steel frame construction process for constructing a steel frame, and a precast deck installation process for installing a precast deck on the steel frame, and the steel frame construction process comprises a steel frame erection process for erecting a steel frame, and a steel frame joining process for joining the steel frame, and a first hole portion that penetrates the precast deck in the vertical direction and through which a worker who joins the steel frame can pass is formed, and the precast deck installation process is performed consecutively after the steel frame erection process, and the steel frame joining process is performed after the precast deck installation process, and a downward steel frame joining process is performed in which a worker who joins the steel frame moves from above the precast deck through the first hole portion onto scaffolding temporarily set up below the precast deck, and joins the steel frame from below the precast deck.

[0007] In the present invention, since the first hole is formed in the precast deck, even when the precast deck is installed on the steel frame, the worker can move from above to below the precast deck and join the steel frame from below the precast deck by using the first hole. Therefore, the precast deck can be installed on the steel frame continuously after the steel frame is erected, so that the crane can be used continuously for erecting the steel frame and installing the precast deck, and the work can be performed efficiently. As a result, the construction period can be shortened even when the process includes the installation of the precast deck during the steel frame erection cycle.

[0008] In the precast deck construction method of the present invention, the precast deck is formed with a second hole portion located above the steel frame joint and penetrating in the vertical direction, and in the precast deck installation process, the precast deck is installed so that the second hole portion is located above the steel frame joint, and the steel frame joining process may include an upper steel frame joining process in which the steel frame is joined from above the precast deck through the second hole portion.

[0009] With this configuration, even when the precast deck is installed on the steel frame, the steel frame joint is exposed by the second hole, so the steel frame can be joined from above the precast deck. Therefore, the precast deck can be installed on the steel frame immediately after the steel frame is erected, so that the crane can be used continuously to erect the steel frame and install the precast deck, and the work can be carried out efficiently. As a result, the construction period can be shortened. Furthermore, the work of joining the steel frame can be carried out with the precast deck installed, which improves workability and safety.

[0010] In the precast floor slab construction method according to the present invention, in the upper steel frame joining step, the steel frame may be joined from above the precast floor slab through the first hole portion.

[0011] With this configuration, the first hole portion through which the worker passes can also be used for joining steel frames. Effect of the Invention

[0012] According to the present invention, the installation of precast deck slabs is also included in the steel frame erection cycle, which contributes to shortening the construction period. [Brief description of the drawings]

[0013] [Figure 1] This is a plan view showing the precast deck placed on the steel frame. [Diagram 2] FIG. 2 is a plan view of a precast deck. [Diagram 3] 2 is a cross-sectional view taken along line AA in FIG. 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] Hereinafter, a construction method for a precast deck according to an embodiment of the present invention will be described with reference to Figs. 1 to 3. A precast deck 1 according to this embodiment shown in Fig. 1 is used for the floor of a production facility that produces semiconductors, precision equipment, and the like. A plurality of precast decks 1 are arranged on a steel frame 2 assembled from steel columns 21 and steel beams 221, 222. The precast deck 1 is installed on the steel frame 2 with its outer edge placed on the steel beams 221, 222. Adjacent precast decks 1, 1 are joined with concrete filled between them. The precast floor slab 1 of this embodiment is made of reinforced concrete and is a highly rigid perforated precast floor slab having a plurality of holes 3 formed therein that penetrate in the vertical direction.

[0015] As shown in Figures 1 to 3, the precast deck 1 is in the shape of a long flat plate. Cutouts 4 are formed at the four corners of the precast deck 1. When the precast deck 1 is installed on the steel frame 2, the cutouts 4 are located above steel joints 23, such as the joint between the steel column 21 and the steel beam 221 and the joint between the steel beams 221, 222. When the precast deck 1 is installed on the steel frame 2, the steel joints 23 are exposed by the cutouts 4. The cutout portion 4 has a first cutout portion 41 (first hole portion) and a second cutout portion 42 (second hole portion) that are different in size. The first cutout portion 41 is a cutout portion through which a welding worker 7 (see FIG. 3) can pass in the vertical direction when the precast floor slab 1 is installed on the steel frame structure 2. The opening of the first cutout portion 41 is, for example, about 400 mm×650 mm. The second cutout portion 42 is a cutout portion that is smaller than the first cutout portion 41 and is not intended for a person to pass through in the vertical direction when the precast floor slab 1 is installed on the steel frame structure 2. The opening of the second cutout portion 42 is, for example, about 200 mm×200 mm.

[0016] In this embodiment, a precast deck 11 having second cutout portions 42 formed in all four corners and a precast deck 12 having first cutout portions 41 formed in two corners are arranged on top of a steel frame structure 2.

[0017] The precast deck construction method according to this embodiment includes a steel frame construction process and a precast deck installation process. The steel frame construction process includes a steel frame erection process for erecting the steel frame of the steel frame 2, and a welding process for tightening and on-site welding the steel joints 23 of the steel frame 2. First, the steel frame of the steel frame structure 2 is erected (steel frame erection process). In the steel frame erection process, the erected steel frame is temporarily fastened. Next, before the welding process, a precast deck installation process is performed. In the precast deck installation process, the precast deck 1 is installed on the steel frame 2. The precast deck 1 is installed by a crane, following the erection of the steel frame. In the precast deck installation process, the precast deck 1 is installed so that the first cutout portion 41 or the second cutout portion 42 is positioned above a steel joint 23, such as the joint between a steel column 21 and a steel beam 221, or the joint between steel beams 221, 222.

[0018] After the precast floor slab 1 is installed, a suspended scaffolding 6 is temporarily installed below the precast floor slab 1. The suspended scaffolding 6 is suspended from and supported by the precast floor slab 1.

[0019] Next, the steel frame joints 23 are tightened and welded on-site (welding process). Welding of the upper side of the steel joint 23, for example, welding between the steel column 21 and the upper flange of the steel beam 221, and welding between the upper flanges of the steel beams 221, 222, is performed from above the precast deck 1 through the second cutout portion 42. Welding of the lower side of the steel joint 23, welding of the steel column 21 to the lower flange or web of the steel beam 221, and welding of the lower flanges and webs of the steel beams 221, 222 together are performed by a welding worker 7 who moves from above the precast deck 1 through the first cutout 41 to above the suspended scaffolding 6 below the precast deck 1, and performs the welding from below the precast deck 1.

[0020] After welding of the steel joints 23 is completed, reinforcement is applied between the adjacent precast floor slabs 1, 1, and then concrete is filled between the adjacent precast floor slabs 1, 1 to join the adjacent precast floor slabs 1, 1. At this time, the cutouts 4 are also filled with concrete. In the case of the build-and-run method, in which construction is carried out while the crane is moving, the above process is repeated while the crane is moving.

[0021] Next, the action and effect of the precast floor slab construction method according to this embodiment will be described. In the construction method of the precast floor slab according to the present embodiment, the first cutout portion 41 and the second cutout portion 42 are formed in the precast floor slab 1, so that even when the precast floor slab 11 is installed on the steel frame 2, the steel frame joint portion 23 is exposed by the second cutout portion 42, so that the upper side of the steel frame joint portion 23 can be welded, and the first cutout portion 41 allows the precast floor slab 1 to be moved from above to below and the lower side of the steel frame joint portion 23 to be welded from below the precast floor slab 1. Therefore, the precast floor slab 1 can be installed on the steel frame 2 continuously after the steel frame is erected, so that the crane can be used continuously for the erection of the steel frame and the installation of the precast floor slab 1, and the work can be performed efficiently. As a result, the construction period can be shortened even when the process includes the installation of the precast floor slab 1 during the steel frame erection cycle. Furthermore, welding between the steel column 21 and the steel beam 221, and welding between the steel beams 221, 222 can be performed with the precast floor slab 1 in place, thereby improving workability and safety.

[0022] In this embodiment, the first cutout portion 41 through which the welding operator 7 passes can also be used for welding the upper side of the steel frame joint portion 23.

[0023] The above describes an embodiment of the precast deck construction method according to the present invention, but the present invention is not limited to the above embodiment and can be modified as appropriate without departing from the spirit of the present invention. For example, in the above embodiment, the joints of the steel frames (the joints between the steel columns 21 and the steel beams 221, and the joints between the steel beams 221, 222) are welded, but they may be joined by means of bolts or other means other than welding. In the above embodiment, the precast deck 1 is formed with both the first hole portion (first cutout portion 41) through which the welding worker 7 passes and the second hole portion (second cutout portion 42) through which welding is performed from above the precast deck 1, but only the first hole portion may be formed. In such a case, the precast deck 1 may be configured to join the steel column 21 and the steel beam 221, and to join the steel beams 221, 222 together.

[0024] In the above embodiment, the first hole portion for the welding worker 7 to pass through and the second hole portion for joining the steel frame from above the precast deck 1 are the first cutout portion 41 and the second cutout portion 42 formed at the four corners of the precast deck 1. The first hole portion and the second hole portion may be formed at any position of the precast deck 1 in accordance with the position of the steel frame joint portion 23. The first hole portion and the second hole portion may be in the shape of a cutout like the first cutout portion 41 and the second cutout portion 42, or may be in the shape of a hole such as a round hole or each hole.

[0025] In the above embodiment, the first cutout portion 41 (first hole portion) is formed at a position overlapping above the steel frame joint 23 and is also used for joining the steel frame, but it may also be formed at a position that does not overlap with the steel frame joint 23 and is not used for joining the steel frame. In the above embodiment, the scaffolding temporarily installed below the precast floor slab 1 is the suspended scaffolding 6 suspended from the precast floor slab 1, but it may be a scaffolding other than a suspended scaffolding. [Explanation of symbols]

[0026] 1,11,12 Precast deck 2 Steel frame structure 6 Suspended scaffolding (scaffolding) 7 Welder (worker) 21 Steel column 23 Steel joints (steel joints) 41 First cutout portion (first hole portion) 42 Second cutout portion (second hole portion) 221,222 Steel beams

Claims

1. A steel frame construction process for constructing a steel frame; A precast floor slab installation process for installing a precast floor slab on the steel frame structure, In the steel frame construction process, A steel frame erection process, in which the steel frame is erected; A steel frame joining process for joining steel frames, The precast deck has: A first hole portion is formed through which a worker who joins the steel frame can pass through by penetrating in the vertical direction, The precast deck installation process is carried out continuously after the steel frame erection process, The steel frame joining process is carried out after the precast deck installation process, A precast floor slab construction method comprising a downward steel frame joining process in which a worker performing the joining of the steel frame moves through the first hole portion from above the precast floor slab onto scaffolding temporarily set up below the precast floor slab, and joins the steel frame from below the precast floor slab.

2. The precast deck has: A second hole portion is formed, the second hole portion being located above the joint portion of the steel frame and penetrating in the vertical direction, In the precast floor slab installation step, the precast floor slab is installed so that the second hole portion is located above the joint portion of the steel frame, The steel frame joining process includes: The precast deck construction method according to claim 1 , further comprising an upper steel frame joining step of joining the steel frame from above the precast deck through the second hole portion.

3. The precast deck construction method according to claim 2 , wherein in the upper steel frame joining step, the steel frame can be joined from above the precast deck through the first hole portion.