Estimation program for special demolition work and computer-readable recording medium having the program recorded thereon

The estimation program for special demolition work automatically generates site-specific estimates and manuals, addressing the inefficiencies of traditional paper-based methods by incorporating detailed information, enhancing accuracy and communication in demolition projects.

JP3249154UActive Publication Date: 2024-11-19HIMUKA EISHIN SANGYO CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2024002108U
Authority / Receiving Office
JP · JP
Patent Type
Utility models
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-11-19
Estimated Expiration
2034-06-26

AI Technical Summary

Technical Problem

Estimates for special demolition work are traditionally made on paper using published prices, which are not site-specific and lack detailed information, leading to incomplete documents and inefficient communication, especially in highly specialized projects.

Method used

An estimation program that allows for automatic creation of estimates using changeable parameters and a construction manual, incorporating detailed construction information and labor/material costs, and includes a computer-readable program to record and output the manual.

Benefits of technology

Enables the creation of site-specific estimates and construction manuals, facilitating efficient information transmission among workers and improving the accuracy and completeness of demolition work estimates.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0003249154000001_ABST
    Figure 0003249154000001_ABST
Patent Text Reader

Abstract

To provide an estimation system for special demolition work, capable of creating an estimate using changeable parameters for special demolition work and automatically creating a construction manual in accordance with the created estimate. [Solution] The estimation system for special demolition work includes an input device that accepts the selection of the type of estimate and the input of detailed information on the work required for the selected estimate, and a computer that creates an estimate for special demolition work based on the received detailed information. According to this invention, by accepting the input of detailed information on the work required for the estimate from the user, it becomes possible to automatically create an estimate that reflects labor costs, material costs, etc. according to each site.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an estimation program for special demolition work and a computer-readable recording medium having the program recorded thereon. [Background technology]

[0002] Special demolition work is a type of work that requires more specialized technology and risk management than general demolition work, and is aimed at large buildings and industrial facilities. Special overseas work accounts for more than 10 percent of the demolition work currently being carried out. As a method for estimating the cost of general demolition work, a computer processing system for building construction work has been proposed to create design drawings, estimates, etc. required for various construction-related works such as land development work, demolition work, and exterior construction work (Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 11-311023 Summary of the Invention [Problem to be solved by the invention]

[0004] However, estimates for special demolition work have traditionally been made on paper, using the published prices based on the construction cost estimate standards set by the Ministry of Land, Infrastructure, Transport and Tourism. This means that estimates take time, and there are issues with the cost of materials and labor not reflecting the actual situation on-site. Furthermore, because special demolition work is highly specialized, there is a risk that the items described in the construction manual and estimate may not be fully understood by those involved in the work, resulting in incomplete documentation and improper communication of information. The construction manual in this device refers to a flow chart of the construction process, the specific contents of the construction process, and the necessary safety measures for each process.

[0005] Therefore, the present invention aims to provide an estimate calculation program for special demolition work, which is capable of creating estimates using changeable parameters for special demolition work and automatically creating construction manuals based on the created estimates, and a computer-readable recording medium on which the program is recorded. [Means for solving the problem]

[0006] The present invention is an estimation program for special demolition work, which causes a computer to execute an estimate selection means for accepting a selection of the type of estimate from a user using an input device such as a mouse or keyboard, an input accepting means for accepting from the user input of detailed information about the work required for the estimate selected by the estimate selection means, and an estimate creation means for creating an estimate for special demolition work based on the detailed information accepted by the input accepting means.

[0007] In addition, it is preferable that the present invention further comprises a company information storage means for accepting and storing input of company information to which the user belongs, a construction manual creation means for creating a construction manual based on the company information stored in the company information storage means and the estimate created by the estimate creation means, and an output means for outputting the construction manual created by the construction manual creation means. Effect of the Invention

[0008] According to this invention, it is possible to provide an estimation program for special demolition work that automatically creates estimates that reflect labor costs, material costs, etc. appropriate for each site by accepting detailed information about the work required for calculations from the user.

[0009] In addition, according to this invention, a construction manual is automatically created at the same time according to the created estimate, so that the manual can be used to smoothly communicate information between people involved in the construction work. [Brief description of the drawings]

[0010] [Figure 1] 1 is an overall configuration diagram of a program 1 according to the present invention. [Diagram 2] FIG. 2 is a flowchart showing a process executed by a program 1 according to the present invention. [Diagram 3] 13 is an example of a screen for accepting input of detailed construction information required for estimates from a user according to the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] The present invention will be described in detail with reference to preferred embodiments. However, the following embodiments are merely examples of the present invention, and the effects of the present invention are not limited to those described in the embodiments of the present invention.

[0012] Program 1 is an estimation program for special demolition work that causes computer 2 to automatically create estimates that reflect labor costs, material costs, etc., appropriate for each site. The program 1 may be stored on the cloud, or may be stored on a computer-readable recording medium such as a Universal Serial Bus memory (USB memory) or a Compact Disk Read Only Memory (CD-ROM).

[0013] The computer 2 is, for example, a computer such as a desktop personal computer, a notebook computer, a server, etc. Furthermore, the computer 2 may be realized, for example, by a single computer, or may be realized by multiple computers such as a cloud computer. In this specification, a cloud computer refers to a computer that uses any computer in a scalable manner to perform a specific function, or a computer that includes multiple functional modules to realize a certain system, and has those functions, etc., and has devices, etc. as a communication unit that enable communication with other terminals, devices, etc.

[0014] The computer 2 includes a control unit such as a central processing unit (CPU), a graphics processing unit (GPU), a random access memory (RAM), and a read only memory (ROM). The computer 2 also includes a data storage unit such as a hard disk, a semiconductor memory, a recording medium, a memory card, etc. The data may be stored in a cloud service, a database, etc. The computer 2 also includes a device as a communication unit for enabling communication with other terminals, devices, etc. The communication method may be wireless or wired. The computer 2 also has, as an input unit, functions necessary for enabling operation of the computer 2. Examples include a liquid crystal display that realizes a touch panel function, a keyboard, a mouse, hardware buttons on the device, a microphone for performing voice recognition, and the like. Furthermore, the computer 2 is assumed to have a function as an output unit required to enable operation of the computer 2. Examples include display and audio output such as a liquid crystal display, a PC display, or projection on a projector.

[0015] The configuration of the estimation program 1 for special demolition work according to the embodiment of the present invention will be described with reference to Fig. 1. Fig. 1 is an overall configuration diagram of the program 1 according to the present invention.

[0016] The program 1 causes a computer 2 to implement an estimate selection module 10, an input reception module 11, and an estimate creation module 12.

[0017] In addition, the program 1 may cause the computer 2 to realize a company information storage module 13, a construction manual creation module 14, and an output module 15.

[0018] It should be noted that the program 1 does not need to realize all modules at once in the computer 2, and it may be in a state where only certain modules are realized.

[0019] Next, an overview of the processing executed by the program 1 will be described with reference to Fig. 2. Fig. 2 is a diagram showing a flowchart of the processing executed by the program 1 according to the present invention. As shown in FIG. 2, by the program 1, the computer 2 is provided with an estimate selection means (step S10) for accepting a selection of the type of estimate from the user, an input receiving means (step S11) for receiving from the user input of detailed information on the work required for the estimate selected by the estimate selection means, an estimate creation means (step S12) for creating an estimate for special demolition work based on the detailed information received by the input receiving means, a company information storage means (step S13) for inputting and storing information on the company to which the user belongs, a construction manual creation means (step S14) for creating a construction manual based on the company information stored in the company information storage means and the estimate created by the estimate creation means, and an output means (step S15) for outputting the construction manual created by the construction manual creation means.

[0020] In the calculation selection module 10, the computer 2 accepts the selection of the type of calculation from the user (step S10). Examples of the types of calculation include wall saw calculation, core drilling calculation, wire saw calculation, and floor board cutter calculation.

[0021] The input reception module 11 receives input of detailed information on the construction work required for the trial calculation selected by the trial calculation selection means from the user (step S11). The detailed information input at this time is information required for creating an estimate, and will be specifically explained using Fig. 3. Fig. 3 is an example of a screen that receives input of detailed information on the construction work required for the trial calculation from the user according to the present invention. As an example, we will explain the detailed construction information required when performing a wall saw calculation. First, input of the client name and the name of the work is accepted. Next, the type of reinforcement can be selected from low reinforcement, medium reinforcement, etc., and the cutting depth can be selected from 10cm to 50cm. Additionally, input of the fuel unit price, such as the type of fuel (diesel, gasoline, etc.) and the unit price for each use (vehicle, generator, etc.) is accepted. Additionally, input of the unit price and number of special and regular workers is accepted. Additionally, input of special notes and the name of the person in charge can be accepted. The detailed information of the construction work received in step S11 is not limited to the above, and can be appropriately changed as necessary.

[0022] Depending on the item, the input in step S11 may be in the form of inputting numerical data or language data using an external device such as a keyboard, or in the form of selecting the appropriate item from a pull-down menu using an external device such as a mouse.

[0023] The estimate creation module 12 creates an estimate for the special demolition work based on the detailed information received in step S11 (step S12). The items of the estimate created at this time are the total cost of the work, direct costs, and the unit price of the materials to be used.

[0024] The company information storage module 13 accepts and stores the input of the company information to which the user belongs (step S13). The company information accepted at this time is information capable of identifying the company, such as the trade name, representative, company address, postal code, telephone number, facsimile number, email address, and homepage URL. Note that step S13 may be performed at any time before step S14.

[0025] The construction manual creation module 14 creates a construction manual based on the company information stored in step S13 and the estimate created in step S12 (step S14). The construction manual created at this time includes a flowchart of the construction process according to the construction information input in step S11, specific details of the construction process, and necessary safety measures for each process. These may be created based on data previously stored in the program 1, or new input and editing may be accepted in step S14.

[0026] The output module 15 outputs the construction manual created by the construction manual creation means (step S15). The output at this time may be displayed on the screen of the computer 2 or may be printed on paper from the computer 2 via an external device. The data may also be transmitted from computer 2 to other computers, external devices, and applications via the Internet connected via wired or wireless connections.

[0027] Through the above process, by accepting detailed construction information required for calculations from the user, it is possible to automatically create estimates that reflect labor costs, material costs, etc. appropriate for each site. In addition, by simultaneously creating a construction manual based on the created estimate, printing out the manual, and sharing it, it becomes possible to smoothly communicate information between people involved in the construction work.

[0028] The present invention is not limited to the above-described embodiment, and modifications and improvements within the scope of the invention that can achieve the object of the invention are included in the present invention. [Explanation of symbols]

[0029] 1: Program 2: Computer 10: Estimation Selection Module 11: Input reception module 12: Estimate creation module 13: Company information storage module 14: Construction manual creation module 15: Output module

Claims

1. An estimation program for special demolition work, On the computer, an estimate selection means for receiving a selection of a type of estimate from a user using an input device such as a mouse or a keyboard; an input receiving means for receiving input of detailed information of the construction work required for the estimate selected by the estimate selection means from a user; An estimate creation means for creating an estimate for special demolition work based on the detailed information received by the input reception means; The present invention relates to a method for estimating a demolition work item.

2. The estimation program is A company information storage means for receiving and storing company information input from a user; a construction manual creation means for creating a construction manual based on the company information stored in the company information storage means and the estimate created by the estimate creation means; An output means for outputting the construction manual created by the construction manual creation means; The estimate program for special demolition work according to claim 1, further comprising:

3. On the computer, an estimate selection means for accepting a selection of a type of estimate from a user; an input receiving means for receiving input of detailed information of the construction work required for the estimate selected by the estimate selection means from a user; An estimate creation means for creating an estimate for special demolition work based on the detailed information received by the input reception means; A computer-readable recording medium having a program recorded thereon for executing the above.

Citation Information

Patent Citations

  • Computer processing system for building construction starting work

    JP1999311023A