How to rebuild a building

By constructing structural pillars on existing underground frameworks and demolishing concurrently, the method accelerates building reconstruction by enabling simultaneous upper and lower level construction, reducing costs through the use of temporary pillars as permanent foundations.

JP7554720B2Active Publication Date: 2024-09-20TAISEI CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2021130410
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-08-09
Publication Date
2024-09-20
Estimated Expiration
2041-08-09

AI Technical Summary

Technical Problem

Existing methods for rebuilding buildings are inefficient and time-consuming, particularly in demolishing and reconstructing underground structures.

Method used

A method involving the construction of structural pillars on existing underground frameworks, supporting a new building's first floor framework, while simultaneously removing the existing underground structure and constructing the new underground framework from the upper floors downward, utilizing temporary pillars as permanent foundations.

Benefits of technology

Enables rapid rebuilding of buildings by allowing simultaneous construction on both upper and lower levels, reducing construction time and costs by using existing structures as permanent foundations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007554720000006
    Figure 0007554720000006
  • Figure 0007554720000005
    Figure 0007554720000005
  • Figure 0007554720000002
    Figure 0007554720000002
Patent Text Reader

Abstract

To provide a building reconstruction method capable of reconstructing a building within a short construction period.SOLUTION: This building reconstruction method overhauls an existing underground skeleton 10 to construct a new building 3. The building reconstruction method comprises: a step S2 of constructing a permanent structural column foundation 51 for supporting a permanent structural column 50 on an existing pressure board 21 of the existing underground skeleton; a step S3 of building the permanent structural column 50 on the permanent structural column foundation 51; a step S4 of constructing a first floor skeleton 34A through support by the permanent structural column 50; and steps S5A and S5B of constructing a ground skeleton 4 of the new building on the upper side of the first floor skeleton 34A and removing the existing underground skeleton 10 on the lower side of the first floor skeleton 34A to construct an underground skeleton 30 of the new building 3.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for rebuilding a building by demolishing an existing underground structure and replacing it with a new building. [Background technology]

[0002] Conventionally, the existing underground structure has been demolished and a new building reconstructed in the same location (see Patent Document 1). Patent Document 1 shows a method for constructing a building. In this method, first, the area of ​​the existing structure for erecting inverted support columns is demolished, and an artificial ground layer is formed on the foundation slab of the existing structure. The artificial ground layer is formed by fixing axial force transmission members to the foundation beams of the existing structure with anchors. Then, inverted support columns are erected on the artificial ground layer, and the new structure is constructed using the inverted support columns.

[0003] Patent Document 2 shows a method for constructing an underground structure having multiple floors. This construction method includes the steps of excavating ground surrounded by an earth retaining wall, constructing a first floor floor structure including a part of the underground outer perimeter wall on the bottom of the excavation as a pre-constructed structure and joining the pre-constructed structure to the earth retaining wall, constructing the structure above the pre-constructed structure and excavating a depth of two floors downward from the bottom of the excavation, and repeating these steps. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2018-188816 A [Patent Document 2] JP 2019-56232 A Summary of the Invention [Problem to be solved by the invention]

[0005] To provide a method for rebuilding a building, which enables rebuilding a building in a short construction period. [Means for solving the problem]

[0006] The building reconstruction method of the first invention is a building reconstruction method for demolishing an existing underground structure (e.g., an existing underground structure 10 described later) and rebuilding it with a new building (e.g., a new building 3 described later), and includes a step (e.g., step S2 described later) of constructing a structural column foundation (e.g., a structural column foundation 51 described later) for supporting a structural column (e.g., a structural column 50 described later) on a bottom part (e.g., an existing pressure plate 21 described later) of the existing underground structure, and a step (e.g., step S3 described later) of erecting the structural column on the structural column foundation (e.g., step S4 described later). The construction method includes a step of constructing a leading floor structure (for example, step S3 described below) supported by the structural columns to construct a leading floor structure (for example, first floor floor structure 34A described below) (for example, step S4 described below), and a step of constructing a ground structure of a new building (for example, ground structure 4 described below) above the leading floor structure, while removing the existing underground structure below the leading floor structure and constructing an underground structure of the new building (for example, underground structure 30 described below) (for example, steps S5A and S5B described below).

[0007] According to this invention, the structural columns are erected inside the existing underground structure, and the preceding floor structure is supported by these structural columns, so that construction can be carried out simultaneously on the upper and lower sides of the preceding floor structure. That is, the above-ground structure of the new building is constructed above the preceding floor structure. Meanwhile, the existing underground structure is removed below the preceding floor structure, and the underground structure of the new building is constructed. This allows the building to be rebuilt in a short construction period.

[0008] The building reconstruction method of the second invention is characterized in that in the process of constructing the underground structure of the new building, a structure (e.g., an additional structure 53 described below) is poured around the structural column foundation and the base of the structural column to form the foundation of the new building.

[0009] The foundations for a new building include foundation footings, foundation beams, and foundation slabs. According to this invention, the foundation of a newly constructed building is created by pouring additional body around the structural column foundation and the base of the structural column. Since the structural column foundation, which is a temporary structure, can be used as a permanent foundation, construction costs can be reduced.

[0010] The building reconstruction method of the third invention is characterized in that, in the step of constructing the underground structure of the new building, the underground structure of the new building is constructed from the upper floors to the lower floors while demolishing the existing underground structure (for example, steps S11 to S14 described below), or the underground structure of the new building is constructed from the lower floors to the upper floors while demolishing the existing underground structure.

[0011] According to this invention, the underground structure of a new building can be smoothly constructed by using a reverse construction method, in which the underground structure of the new building is constructed from the upper floors to the lower floors while demolishing the existing underground structure, or a forward construction method, in which the underground structure of the new building is constructed from the lower floors to the upper floors while demolishing the existing underground structure. Effect of the Invention

[0012] According to the present invention, a method for rebuilding a building can be provided that enables a building to be rebuilt in a short construction period. [Brief description of the drawings]

[0013] [Figure 1] 1 is a vertical cross-sectional view of an existing building to which a reconstruction method according to one embodiment of the present invention is applied. [Diagram 2] FIG. 1 is a vertical cross-sectional view of a newly constructed building constructed using a reconstruction method according to one embodiment of the present invention. [Diagram 3] 1 is a flowchart of the procedure for replacing an existing building with a new building. [Figure 4] This is an explanatory diagram of the procedure for replacing an existing building with a new building (Part 1, with the structural columns installed). [Diagram 5] This is an explanatory diagram of the procedure for replacing an existing building with a new building (Part 2, showing the first floor structure of the new building after it has been constructed). [Figure 6]This is a flowchart of the procedure for constructing the underground structure in the space below the first floor floor structure. [Figure 7] This is an explanatory diagram of the construction procedure for the underground structure in the space below the first floor floor structure (Part 1, showing the state after the basement 2nd and 3rd floor rises of the existing underground structure have been dismantled). [Figure 8] This is an explanatory diagram of the construction procedure for the underground structure in the space below the first floor floor structure (Part 2, the state after the second basement floor structure of a newly built building has been constructed). [Figure 9] This is an explanatory diagram of the construction procedure for the underground structure in the space below the first floor floor structure (Part 3, showing the existing underground structure's foundation and the rise to the fourth basement floor after being dismantled). [Figure 10] This is an enlarged view of the structural column foundation and the base of the structural column. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] This invention is a method for rebuilding a building in which structural columns are installed on the existing pressure-resistant plate of the existing underground structure, a preliminary floor structure supported by these structural columns is constructed at the first floor level, and then a new building is simultaneously constructed above and below the preliminary floor structure. Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a vertical cross-sectional view of an existing building 1 to which a reconstruction method according to one embodiment of the present invention is applied. The existing building 1 has an existing underground structure 10 made of reinforced concrete up to the fourth basement floor, and an existing above-ground structure 2 constructed on the existing underground structure 10. The existing underground structure 10 has a foundation 11, a fourth basement floor rise 12, a third basement floor rise 13, a second basement floor rise 14, and a first basement floor rise 15. The foundation 11 includes an existing foundation beam (underground beam) 20, an existing pressure plate 21, and a 4th basement floor slab 22. Hereinafter, the nth basement floor rise includes the nth basement floor columns, the nth basement floor walls, the (n+1)th basement floor beams, and the (n+1)th basement floor.

[0015] FIG. 2 is a vertical cross-sectional view of a new building 3 constructed by the rebuilding method according to this embodiment. The new building 3 has an underground structure 30 up to the third basement floor, and an above-ground structure 4 constructed on the underground structure 30. The underground structure 30 has a newly constructed foundation 31 made of reinforced concrete, a third basement floor rise 32 made of steel-reinforced concrete, a second basement floor rise 33 made of steel-reinforced concrete, and a first basement floor rise 34 made of steel-reinforced concrete. The new foundation 31 includes a new foundation beam (underground beam) 40, a new pressure-resistant plate 41, and a third basement floor slab 42. The new foundation beam 40 is joined to the foundation beam 20 located on the outer periphery of the existing building 1. The new pressure-resistant plate 41 is constructed on top of the existing pressure-resistant plate 21.

[0016] The procedure for demolishing the existing building 1 and replacing it with a new building 3 will be described with reference to the flow chart of FIG. In step S1, as shown in FIG. 4, the existing above-ground structure 2 is demolished, and the first basement floor rise 15 of the existing underground structure 10 is demolished while leaving the outer periphery of the existing underground structure 10. In step S2, as shown in Fig. 4, a reinforced concrete structural column foundation 51 for supporting a steel structural column 50 is constructed on the existing pressure plate 21 as the bottom of the existing underground structure 10. A protrusion 52 is provided on this structural column foundation 51 (see Fig. 10). Also, an opening is provided in the part of the floor slab of each floor that interferes with the structural column 50, and the structural column 50 is passed through this opening.

[0017] In step S3, as shown in FIG. 4, the structural column 50 is erected on the structural column foundation 51. In step S4, as shown in Fig. 5, the first floor floor structure (first floor beams and first floor floor slab) 34A of the new building 3 is constructed as a preceding floor structure supported by structural columns 50. As a result, the first floor floor structure 34A separates the upper and lower spaces. The ends of the steel beams of the first floor floor structure 34A are fixed to the post-installed anchors by driving them into the outer periphery of the existing underground structure 10. In step S5A, the ground structure 4 of the new building 3 is constructed in the space above the first floor floor structure 34A. In step S5B, the remaining existing underground structure 10 is removed in the space below the first floor floor structure 34A, and the underground structure 30 of the new building 3 is constructed. Specifically, the underground structure 30 of the new building 3 is constructed from the upper floors toward the lower floors while the existing underground structure 10 is being demolished.

[0018] The detailed procedure of this step S5B will be described with reference to the flowchart of FIG. That is, in step S11, as shown in Fig. 7, the second basement floor rise 14 and the third basement floor rise 13 of the existing underground structure 10 are demolished while leaving the outer periphery of the existing underground structure 10. As a result, the third basement floor of the existing underground structure 10 becomes the construction ground. In step S12, as shown in Fig. 8, the second basement floor structure (second basement floor beams and second basement floor slab) 32A of the new building 3 is constructed. Also, steel beams 33A at the first basement floor level are erected. The ends of the steel beams of the second basement floor structure 32A and the steel beams 33A at the first basement floor level are fixed to the outer periphery of the existing underground structure 10 with post-installed anchors. As a result, the second basement floor structure 32A separates the upper and lower spaces. In step S13A, as shown in Fig. 9, the basement structure 30 of the new building 3 is constructed in the space above the second basement floor structure 32A in a sequential pouring manner. Specifically, the second basement floor rise 33 and the first basement floor rise 34 are constructed in that order. As the first floor floor structure 34A has already been constructed, the columns and walls of the first basement floor rise 34 are constructed by pressing concrete into the formwork.

[0019] In step S13B, as shown in FIG. 9, in the space below the second basement floor structure 32A, the foundation 11 and the fourth basement floor rise 12 of the existing underground structure 10 are demolished, leaving only the outer periphery and bottom (existing pressure plate 21) of the existing underground structure 10. In step S14, as shown in Fig. 2, the underground framework 30 of the new building 3 is constructed in order. Specifically, the foundation 31 is constructed, followed by the third basement floor rise 32. As the second basement floor framework 32A has already been constructed, the columns and walls of the third basement floor rise 32 are constructed by pressing concrete into the formwork. 10, a part of the newly constructed foundation 31 is formed by constructing a reinforced concrete additional body 53 around the base of the structural column foundation 51 and the structural column 50. At this time, by embedding the protrusion 52 of the structural column foundation 51 in the additional body 53, a cotter is formed between the structural column foundation 51 and the additional body 53, and the structural column foundation 51 and the additional body 53 are firmly joined.

[0020] In this way, the structural column foundation 51 becomes part of the new foundation 31 by constructing the additional cast-in-place body 53 around it. Therefore, the structural column foundation 51 is ensured to have a minimum height and size of planar shape so that punching failure does not occur in the structural column foundation 51 due to the vertical load borne by the structural column 50 during the period from erecting the structural column 50 to constructing the foundation 31. For example, if the structural column 50 is a steel pipe of 1200 mm x 1200 mm and this steel pipe is joined in four sections vertically (11th floor above ground), the structural column foundation 51 is an approximately rectangular parallelepiped shape with a bottom surface of 1500 mm x 1500 mm and a height of 2400 mm. In addition, the protruding dimension of the protrusion 52 of the structural column foundation 51 is 60 mm.

[0021] According to this embodiment, the following effects are obtained. (1) The structural columns 50 are erected on the existing pressure-resistant plate 21 of the existing underground structure 10, and the first floor floor structure 34A, which is the preceding floor structure, is supported by these structural columns 50, so that construction can be carried out simultaneously on the upper and lower sides of the first floor floor structure 34A. That is, above the first floor floor structure 34A, the above-ground structure 4 of the new building 3 is constructed. Meanwhile, below the first floor floor structure 34A, the existing underground structure 10 is removed and the underground structure 39 of the new building 3 is constructed. This allows the building to be rebuilt in a short construction period. In addition, since the structural pillars 50 are constructed on the existing pressure-resistant plate 21, rather than on the ground beneath the existing building 1, the structural pillars 50 can be installed with high work efficiency. In addition, since the structural pillars 50 are erected inside the existing underground framework 10, new piles for fixing the column bases of the structural pillars 50 are not required, compared to constructing new piles and then constructing the structural pillars on the new piles, so the existing building 1 can be replaced with the new building 3 in a short period of time.

[0022] (2) After the structural column foundation 51 is constructed in advance, an additional pouring frame 53 is constructed around the base of the structural column foundation 51 and the structural column 50 to form a new foundation 31. Therefore, the structural column foundation 51, which is a temporary structure, can be used as the permanent foundation 31, thereby reducing construction costs. In addition, the structural column foundation 51 is ensured to have a minimum height and a planar shape size capable of supporting the vertical load borne by the structural column 50 during the period from erecting the structural column 50 to constructing the foundation 31. Therefore, the structural column foundation 51 can be constructed without removing as much of the framework of the existing building 1 as possible. (3) The underground structure 30 of the new building 3 can be constructed smoothly by using a reverse construction method in which the underground structure 30 of the new building 3 is constructed from the upper floors to the lower floors while the existing underground structure 10 is demolished.

[0023] The present invention is not limited to the above-described embodiment, and modifications and improvements within the scope of the present invention that can achieve the object of the present invention are included in the present invention. For example, in the above-described embodiment, the underground structure 30 of the newly constructed building 3 was constructed from the top floor to the bottom floor, but this is not limited to this, and it may be constructed from the bottom floor to the top floor while demolishing the existing underground structure 10. [Explanation of symbols]

[0024] 1...Existing building 2...Existing ground structure 3...New building 4...Ground structure 10...Existing underground structure 11...Existing foundation 12...4th basement floor rise 13…3rd basement floor rise 14…2nd basement floor rise 15…1st basement floor rise 20...Existing foundation beam 21...Existing pressure plate 22...4th basement floor slab 30...Underground structure of new building 31...Foundation of new building 32…3rd basement floor rise 32A…2nd basement floor structure 33…Rising to the 2nd basement floor 33A…Steel beam at the 1st basement floor level 34…B1F rise 34A…1F floor structure (preceding floor structure) 40...New foundation beam 41...New pressure plate 42...3rd basement floor slab 50...Structural column 51...Structural column base 52...Protrusion 53...Additional construction body

Claims

1. A method for rebuilding a building by demolishing an existing underground structure and replacing it with a new building, A step of constructing a substantially rectangular parallelepiped structural column foundation for supporting a structural column on a bottom portion of the existing underground structure; A step of erecting the structural column on the structural column foundation; A step of constructing a preliminary floor structure by supporting it with the structural columns; A step of constructing a ground structure of a new building above the preceding floor structure, while removing the existing underground structure below the preceding floor structure and constructing an underground structure of the new building below the preceding floor structure, A method for rebuilding a building, characterized in that in the process of constructing the underground structure of the new building, the existing underground structure is demolished leaving only the outer periphery and the bottom of the existing underground structure, and then a reinforced concrete structure is constructed around the structural column foundations and the bases of the structural columns to form the foundation of the new building.

2. The method for rebuilding a building according to claim 1, characterized in that in the process of constructing the underground structure of the new building, the underground structure of the new building is constructed from the lower floors to the upper floors while demolishing the existing underground structure.

Citation Information

Patent Citations

  • Connection structure between column and bottom plate

    JP2003027591A

  • Rebuilding method

    JP2008255645A

  • Building construction method, and underground skeleton of new building

    JP2014111891A

  • Building construction method and building structure

    JP2018188816A

  • Construction method of underground structure

    JP2019056232A