Power generation plan creation device, bidding support system, and power generation plan creation program
The power generation planning device optimizes power generation and bidding plans by simulating market conditions, addressing the underutilization of market transactions in existing systems and enhancing profitability through improved market integration.
Patent Information
- Application Number
- JP2020219123
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-12-28
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2040-12-28
AI Technical Summary
Existing power generation planning systems fail to fully utilize market transactions due to limitations in creating power generation plans that consider market conditions, leading to suboptimal planning and potential underutilization of market opportunities.
A power generation planning device that collects and simulates generator information, including fuel unit prices and output limits, to create simultaneous power generation and bidding plans in electricity markets, using predicted market prices and conditions to optimize transactions.
Enables the creation of appropriate power generation plans that maximize market transactions, thereby increasing business profitability and optimizing electricity generation.
Smart Images

Figure 0007565792000005 
Figure 0007565792000006 
Figure 0007565792000007
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a power generation plan creation device, a bidding support system, and a power generation plan creation program that create a power generation plan. [Background technology]
[0002] Power generation companies that own power generation facilities and supply the electricity generated by the power generation facilities generally supply electricity under contracts such as retail contracts and bilateral contracts, separate from market transactions. In order to supply electricity under these contracts, power generation companies forecast the amount of electricity demand and create power generation plans according to the amount of demand.
[0003] Meanwhile, full liberalization of the retail electricity market has begun, and electricity is traded through the Japan Electric Power Exchange (JEPX). There are two types of transactions at the JEPX: the day-ahead market, also known as the spot market, and the hour-ahead market, also known as the intraday market. The above transactions at the JEPX are conducted by computer, and each participating power company submits bids via the Internet or other means. When participating in transactions in the electricity trading market, power generation companies formulate power generation plans and bidding plans, taking into account factors such as demand, the costs required for power generation, the maximum output of the generators, and the market price.
[0004] In Patent Document 1, a power generation plan is created based on a forecasted demand value and the cost required for power generation, a marginal cost indicating the increase in cost when demand increases is calculated, a market trading plan is created using the marginal cost and the market trading price, and the power generation plan is revised using the market trading plan. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2019-83601 A Summary of the Invention [Problem to be solved by the invention]
[0006] In the technology described in Patent Document 1, a power generation plan is created, then a market trading plan is created and the power generation plan is corrected using the market trading plan, so the market trading plan depends on the power generation plan created earlier. For this reason, for example, since a plan that takes market trading into consideration is created under the assumption that a certain generator will be operated, there is a limit to the market trading volume that can be taken into consideration, and there is a possibility that market trading cannot be fully utilized. Therefore, in the procedure described in Patent Document 1 in which a power generation plan is formulated first, there is a possibility that an appropriate power generation plan that takes market trading into consideration cannot be created.
[0007] The present disclosure has been made in consideration of the above, and has an object to provide a power generation plan creation device capable of creating an appropriate power generation plan that takes market transactions into consideration. [Means for solving the problem]
[0008] In order to solve the above-mentioned problems and achieve the object, the power generation plan creation device according to the present disclosure provides information for calculating the cost required for power generation of each generator. including fuel cost, lower limit output and upper limit output Generator Information 、 A memory unit for storing the The market price is set as the fuel unit price of the simulated generator, the trading volume in the electricity market is set as the power output of the simulated generator, the minimum bid amount in the electricity market is set as the lower limit output of the simulated generator, and the upper limit of the bid amount in the electricity market is set as the upper limit output of the simulated generator. and a generator information generating unit that generates information for calculating costs required for transactions in the electricity market as generator information of a simulated generator using a predicted value of a market price in the electricity market and bidding conditions in the electricity market, and stores the information in the storage unit. The power generation plan creating device further includes a plan creating unit that uses the generator information stored in the storage unit and a predicted value of demand for a period for which the plan is created to simultaneously create a power generation plan and a bidding plan in the electricity market. The bidding conditions include the minimum bid amount and the upper limit of the bid amount in the electricity market. . Effect of the Invention
[0009] According to the present disclosure, an effect is achieved in that an appropriate power generation plan can be created that takes market transactions into consideration. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a diagram showing a configuration example of a power generation plan creation device according to a first embodiment; [Diagram 2] FIG. 1 is a diagram showing a configuration example of a computer system that realizes a power generation plan creation device according to a first embodiment. [Diagram 3] A flowchart showing an example of a power generation plan creation process procedure in the power generation plan creation device according to the first embodiment. [Figure 4] FIG. 1 is a diagram showing an example of generator information according to the first embodiment; [Diagram 5] FIG. 1 shows an example of a power generation plan and a bidding plan displayed by a display unit according to the first embodiment. [Figure 6] FIG. 13 is a diagram showing a configuration example of a bidding support system according to a second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A power generation plan creating device, a bid support system, and a power generation plan creating program according to embodiments will be described below in detail with reference to the accompanying drawings.
[0012] Embodiment 1 FIG. 1 is a diagram showing a configuration example of a power generation plan creation device according to a first embodiment. As shown in FIG. 1, the power generation plan creation device 1 of this embodiment includes a market price prediction value acquisition unit 11, a bidding condition acquisition unit 12, a demand prediction information acquisition unit 13, a power generator information generation unit 14, a storage unit 15, a plan creation unit 16, a plan transmission unit 17, and a display unit 18. The power generation plan creation device 1 of this embodiment creates a power generation plan and a bidding plan in an electricity trading market to support a business operator who manages a power generator, such as a power generation business operator. The power generation plan creation device 1 transmits the created bidding plan to a bidding support device 3, and transmits the created power generation plan and bidding plan to a supply and demand management device 2. The power generation plan creation device 1 and the bidding support device 3 configure a bidding support system of this embodiment.
[0013] The market price prediction value acquisition unit 11 acquires a prediction value of the market price in the electricity trading market. For example, the market price prediction value acquisition unit 11 may acquire the prediction value of the market price by accepting an input from an operator, or may acquire the prediction value of the market price by receiving the prediction value of the market price from another device not shown. The market price prediction value acquisition unit 11 outputs the acquired prediction value of the market price to the power generator information generation unit 14. Note that when multiple trading markets are taken into consideration, such as a spot market and an advance market, the market price prediction value acquisition unit 11 acquires a prediction value of the market price for each trading market.
[0014] The bidding condition acquisition unit 12 acquires bidding conditions in the electricity trading market. For example, the bidding condition acquisition unit 12 may acquire the bidding conditions by accepting an input from an operator, or may acquire the bidding conditions by receiving the bidding conditions from another device (not shown). The bidding conditions include, for example, a minimum bid amount, a bid amount increment, a minimum bid price, and an upper limit of the bid amount. The bidding condition acquisition unit 12 outputs the acquired bidding conditions to the generator information generation unit 14. When multiple trading markets are taken into consideration, the bidding condition acquisition unit 12 acquires the bidding conditions for each trading condition.
[0015] The demand forecast information acquisition unit 13 acquires, from the supply and demand management device 2, demand forecast information indicating a forecast value of demand, which is electricity supplied to a demander by a business supported by the power generation plan creation device 1, and stores the acquired demand forecast information in the storage unit 15. The supply and demand management device 2 is a device that manages the demand and supply of electricity in the business supported by the power generation plan creation device 1. The supply and demand management device 2 predicts the demand amount using, for example, past performance values and temperature. Note that, here, an example is described in which the power generation plan creation device 1 is provided separately from the supply and demand management device 2, but the power generation plan creation device 1 may be integrated with the supply and demand management device 2. That is, the power generation plan creation device 1 may be a part of the supply and demand management device 2. When the power generation plan creation device 1 is a part of the supply and demand management device 2, the demand forecast information acquisition unit 13 acquires a forecast value of demand from a functional unit that predicts the demand amount in the supply and demand management device 2. Note that, although an example is shown here in which the demand forecast information is stored in the memory unit 15 and then input to the plan creation unit 16, this is not limited to the above, and the demand forecast information may be directly input from the demand forecast information acquisition unit 13 to the plan creation unit 16.
[0016] The generator information generating unit 14 regards transactions in the electricity market as a simulated generator with the transaction volume in the electricity market as the power generation output, and generates information for calculating the cost required for transactions in the electricity market using the predicted market price in the electricity market and bidding conditions as generator information of the simulated generator and stores it in the storage unit 15. The generator information is information used to create a power generation plan and a bidding plan, which will be described later, and is information for calculating the cost required for power generation. The generator information is, for example, information for determining the unit price and operation constraints for power generation. The generator information will be described in detail later.
[0017] The storage unit 15 stores demand forecast information and generator information. The generator information is information for calculating the cost required for power generation by a generator, and is stored for each generator. The generator information stored in the storage unit 15 includes the generator information generated by the generator information generating unit 14 described above, and the generator information of real generators that generate power such as thermal power generation and hydroelectric power generation. The generator information of real generators may be input by an operator and stored in the storage unit 15, or may be received from another device (not shown) and stored in the storage unit 15.
[0018] The plan creation unit 16 creates a power generation plan and a bidding plan simultaneously using the demand forecast information and the power generator information stored in the memory unit 15, and outputs the created power generation plan and bidding plan to the plan transmission unit 17 and the display unit 18. The operation of the plan creation unit 16 will be described later.
[0019] The plan transmission unit 17 transmits the power generation plan and the bidding plan to the supply and demand management device 2, and outputs the bidding plan to the bidding support device 3. The supply and demand management device 2 creates a supply and demand plan using the received power generation plan and bidding plan and demand forecast information. The bidding support device 3 performs bidding processing for electricity trading systems such as the Japan Electric Power Exchange, using the bidding plan created by the power generation plan creation device 1. The display unit 18 displays the power generation plan and the bidding plan.
[0020] The power generation plan creation device 1 of this embodiment treats the power trading market as a simulated generator, generates generator information showing the characteristics of the simulated generator in the same way as a generator, and creates a power generation plan and a bidding plan simultaneously using the generator information of the simulated generator and the real generator. Therefore, compared to creating a power generation plan first and then creating a bidding plan later, it is possible to make the most of the power market transactions and create an appropriate power generation plan to maximize the profits of the business operator supported by the power generation plan creation device 1.
[0021] Next, a hardware configuration of the power generation plan creation device 1 of this embodiment will be described. In the power generation plan creation device 1 of this embodiment, a power generation plan creation program, which is a program describing the processing in the power generation plan creation device 1, is executed on a computer system, so that the computer system functions as the power generation plan creation device 1. FIG. 2 is a diagram showing an example of the configuration of a computer system that realizes the power generation plan creation device 1 of this embodiment. As shown in FIG. 2, this computer system includes a control unit 101, an input unit 102, a storage unit 103, a display unit 104, a communication unit 105, and an output unit 106, which are connected via a system bus 107.
[0022] In FIG. 2, the control unit 101 is a processor such as a CPU (Central Processing Unit), and executes a power generation plan creation program in which the processing in the power generation plan creation device 1 of this embodiment is described. The input unit 102 is composed of, for example, a keyboard, a mouse, and the like, and is used by a user of the computer system to input various information. The storage unit 103 includes various memories such as a RAM (Random Access Memory), a ROM (Read Only Memory), and a storage device such as a hard disk, and stores the program to be executed by the control unit 101, necessary data obtained in the process of processing, and the like. The storage unit 103 is also used as a temporary storage area for the program. The display unit 104 is composed of a display, an LCD (Liquid Crystal Display Panel), and the like, and displays various screens to the user of the computer system. The communication unit 105 is a receiver and a transmitter that perform communication processing. The output unit 106 is a printer, etc. Note that FIG. 2 is an example, and the configuration of the computer system is not limited to the example of FIG. 2.
[0023] Here, an example of the operation of the computer system until the power generation plan creation program of this embodiment is in an executable state will be described. In the computer system having the above-mentioned configuration, the power generation plan creation program is installed in the storage unit 103 from, for example, a CD-ROM or DVD-ROM set in a CD (Compact Disc)-ROM drive or DVD (Digital Versatile Disc)-ROM drive (not shown). Then, when the power generation plan creation program is executed, the power generation plan creation program read from the storage unit 103 is stored in the storage unit 103. In this state, the control unit 101 executes the process as the power generation plan creation device 1 of this embodiment according to the program stored in the storage unit 103.
[0024] In the above description, the program describing the processing in the power generation plan creation device 1 is provided on a CD-ROM or DVD-ROM as a recording medium. However, the present invention is not limited to this, and depending on the configuration of the computer system, the capacity of the program to be provided, etc., it is also possible to use a program provided over a transmission medium such as the Internet via the communication unit 105.
[0025] The power generator information generating unit 14 and the plan creating unit 16 shown in FIG. 1 are realized by executing the power generation plan creating program stored in the storage unit 103 shown in FIG. 2 by the control unit 101 shown in FIG. 2. The power generator information generating unit 14 and the plan creating unit 16 are realized by using the storage unit 103 shown in FIG. 2. The storage unit 15 shown in FIG. 1 is a part of the storage unit 103 shown in FIG. 2. The demand forecast information acquiring unit 13 and the plan transmitting unit 17 shown in FIG. 1 are realized by the communication unit 105 shown in FIG. 2. The market price forecast value acquiring unit 11 and the bidding condition acquiring unit 12 shown in FIG. 1 are realized by the input unit 102 or the communication unit 105 shown in FIG. 2. The display unit 18 shown in FIG. 1 is realized by the display unit 104 shown in FIG. 2. The power generation plan creating device 1 may be realized by a plurality of computer systems. The power generation plan creating device 1 may be realized by executing the power generation plan creating program in a cloud system composed of a plurality of computer systems.
[0026] For example, the power generation plan creation program of the present embodiment causes the computer to execute the steps of: storing, for each generator, generator information, which is information for calculating the cost required for power generation by the generator, in the storage unit 15; and regarding transactions in the electricity market as a simulated generator with the transaction amount in the electricity market as the power generation output, generating information for calculating the cost required for transactions in the electricity market using a predicted value of the market price in the electricity market and bidding conditions in the electricity market as generator information of the simulated generator, and storing the information in the storage unit 15. In addition, the power generation plan creation program of the present embodiment causes the computer to execute the step of simultaneously creating a power generation plan and a bidding plan in the electricity market, using the generator information stored in the storage unit and a predicted value of demand for a period for which the plan is created.
[0027] The supply and demand management device 2 and the bidding support device 3 are also realized by a computer system in the same manner.
[0028] Next, the operation of this embodiment will be described. Fig. 3 is a flowchart showing an example of a power generation plan creation processing procedure in the power generation plan creation device 1 of this embodiment. As shown in Fig. 1, the market price prediction value acquisition unit 11 acquires a predicted value of the market price (step S1). The market price prediction value acquisition unit 11 outputs the acquired predicted value of the market price to the generator information generation unit 14. The bidding condition acquisition unit 12 acquires bidding conditions (step S2). The bidding condition acquisition unit 12 outputs the acquired bidding conditions to the generator information generation unit 14.
[0029] The generator information generating unit 14 generates generator information of a simulated generator in which the market transaction volume is regarded as the power generation volume (step S3). In detail, the generator information generating unit 14 generates generator information of a simulated generator in which the market transaction volume is regarded as the power generation volume by using the predicted value of the market price and the bidding conditions, and stores the generator information in the storage unit 15.
[0030] FIG. 4 is a diagram showing an example of the generator information of this embodiment. In the example shown in FIG. 4, the generator information includes a generator ID (IDentifier) which is the identification information of the generator, a generator type, a start / stop cost, a fuel unit price, an upper limit output, and a lower limit output. The generator information is information which is taken into consideration as a constraint condition when creating a power generation plan and is used for cost calculation, and items differ depending on the type of generator. For this reason, although the generator information differs depending on the type of generator, each item is defined here regardless of the type of generator, and for generators for which the item does not need to be taken into consideration, the corresponding value is set to 0. Note that FIG. 4 is an example, and the specific configuration of the generator information is not limited to the example shown in FIG. 4.
[0031] The start / stop cost is the cost required when a generator changes from stopped to started. For example, when a generator changes from stopped to started, the cost required for start-up is defined by a predetermined function according to the stop time up to that point. Instead of being defined by a function, the start / stop cost may be determined as a fixed value as the cost per start. The fuel unit price is the unit price of the fuel used for power generation. The upper limit output is the upper limit of the generator's output, and the lower limit output is the lower limit of the generator's output. Although omitted in FIG. 4, the generator information generally also includes the minimum operating time, and the upper and lower limits of the rate of change of the generator's output. Furthermore, when a pumped storage generator or the like is included as a generator, the upper and lower limits of the pond's water level are determined.
[0032] In the example shown in FIG. 4, two markets, the spot market and the hourly market, are considered as electricity trading markets, and the generator ID corresponding to a buying bid in the spot market is 0, the generator ID corresponding to a selling bid in the spot market is 1, the generator ID corresponding to a buying bid in the hourly market is 2, and the generator ID corresponding to a selling bid in the hourly market is 3. Thus, in the case of a simulated generator, the fuel unit price is as follows: in the case of a buying bid, the market price Market price The price is calculated by adding the commission fee to the price forecast (unit price). Market priceThe predicted value (unit price) of the price is stored as a negative value in the fuel unit price item by adding a negative sign. Bills The upper limit of the transaction given as a condition is stored, and the lower limit is Bills given as a condition Minimum Bid The quantity, or the lower limit of the transaction, is stored. market Price forecast and input Bills By storing the conditions and the like in the corresponding items of the generator information, each trading market can be treated in the same way as a generator. For generators with a generator ID of 4 or more, information on true generators such as thermal power generators is stored. As described above, the generator information on true generators is stored in the storage unit 15 by being input in advance or received from another device.
[0033] Returning to the explanation of Fig. 3, after step S3, the demand forecast information acquisition unit 13 acquires demand forecast information (step S4). In detail, the demand forecast information acquisition unit 13 acquires, from the supply and demand management device 2, demand forecast information indicating a forecast value of demand for a period for which a power generation plan is to be created, and stores the demand forecast information in the storage unit 15.
[0034] The plan creation unit 16 creates a power generation plan and a bidding plan simultaneously (step S5). In detail, the plan creation unit 16 uses the generator information and the demand forecast information stored in the storage unit 15 to simultaneously create a power generation plan and a bidding plan so as to maximize the profits of the business operator supported by the power generation plan creation device 1. That is, the plan creation unit 16 uses the generator information and the demand forecast information to determine an objective function and constraint conditions that indicate the costs required for power generation by the generators and the simulated generators, and obtains the power generation output of the generators and the simulated generators that maximizes the determined objective function under the constraint conditions, and creates a power generation plan and a bidding plan using the obtained power generation output. The objective function corresponds to a formulation of the profits obtained by the business operator supported by the power generation plan creation device 1, so that the profits obtained by the business operator can be maximized by maximizing the objective function.
[0035] For example, the plan creation unit 16 sets the objective function F(p) shown in formula (1) and each constant in the constraint conditions shown in the following formulas (2) to (6) using the generator information. Note that p is the output when the generator is in a started state. Note that the following formulas (2) to (6) are examples of formulations assuming that the generator is a thermal power generator, and the constraint conditions are changed as appropriate depending on the type of generator.
[0036]
number
[0037]
number
[0038] t is an integer indicating the amount of time that has elapsed since the start time of the time period to be processed, i.e., the period for which a plan is to be created, and the start time of the time period to be processed is set to t=0. T is an integer indicating the length of the time period to be processed. Note that t is an integer indicating the number in Δ units, where Δ is a set time step. In other words, Δ×t indicates the amount of time that has elapsed since the start time of the time period to be processed. The value of T can be set to any value, but for example, it is a value equivalent to the length of about one week.
[0039] The first term in [ ] on the right-hand side of equation (1) represents the profits that can be obtained from contracts other than those traded in the electricity market, such as retail contracts and bilateral contracts. D s,t is the demand for electricity to be supplied to a contract partner such as a retail contract or a bilateral contract at the time corresponding to the elapsed time t. The demand for electricity is calculated based on the demand forecast information. S(D s,t ) is the profit for each contract partner, such as retail contracts and bilateral contracts. For retail contracts and bilateral contracts, the calculation method for electricity charges is determined by the terms and conditions, so S(D s,t ) is calculated according to the terms and conditions. s is the numerical value corresponding to each contract.
[0040] The second term in brackets [ ] on the right-hand side of equation (1) represents the fuel cost of the generator. p g,tis the output of the generator at the time corresponding to the elapsed time t. g is a number indicating each generator, and corresponds to the generator ID mentioned above. f(p g,t ) indicates the fuel cost for each generator. The fuel cost is calculated by multiplying the unit price of fuel included in the generator information by p g,t As mentioned above, the generators from g=0 to g=3 are simulated generators that correspond to market transactions. When the simulated generators correspond to selling bids, the fuel unit price is a negative value, so a - is added to the second term of the above formula (1), but the negative value is subtracted, resulting in a positive value, and profits according to the selling bid volume are obtained.
[0041] The third term in brackets [ ] on the right-hand side of equation (1) represents the startup and shutdown cost of the generator. g,t indicates the state of each generator at the time corresponding to the elapsed time t. When the generator is running, u g,t is 1, and when the generator is stopped, u g,t is 0. U(u g,t ) indicates the start-up and shutdown cost for each generator. The start-up and shutdown cost is u g,t When changes from 0 to 1, that is, u g,t is 1, and u g,t-1 When the startup cost becomes 0, the startup cost is determined by a predetermined function according to the downtime up to that point, and is 0 otherwise.
[0042] In addition, in formula (1), the objective function includes profits from contracts such as retail contracts and bilateral contracts, which are terms that are not dependent on the power generation plan and bidding plan, but this term does not need to be included if there are no contracts such as retail contracts and bilateral contracts. If profits from contracts such as retail contracts and bilateral contracts are not included, the value of the objective function may become negative, but the profits of the business operator can be maximized by maximizing the objective function while taking into account the positive and negative signs, i.e., in the case of negative values, a value with a smaller absolute value is considered to be greater than a value with a larger absolute value.
[0043] Equation (2) shows the constraints for matching the electricity demand and supply. In other words, the sum of the power generation amount by the generator, i.e., the power output, and the amount bought and sold in the electricity market is the demand amount D t The condition is that it matches.
[0044] Equation (3) is a constraint that the output of each generator is within the upper and lower limits of the output of each generator. Equation (4) is a constraint that the rate of change of the output of each generator is within the upper and lower limits of the rate of change of the output of each generator. change,g,t indicates the lower limit of the rate of change of the generator output, and p change,g,t indicates the upper limit of the rate of change of the generator output.
[0045] Equation (5) is a constraint that the continuous operation time of each generator must be greater than or equal to the minimum operation time. g,t After it becomes 1, u g,t Since it is necessary to ensure that the continuous operation time is equal to or greater than the minimum operation time for each period from 1 to 0, equation (5) is a constraint imposed on each continuous operation period. min_operation,g is an integer that discretizes the minimum operation time of each generator in units of Δ.
[0046] Equation (6) is a constraint that the continuous outage time of each generator must be greater than or equal to the minimum outage time. g,t After it becomes 0, u g,t Since it is necessary to ensure that the continuous stop time is equal to or greater than the minimum stop time for each period from 0 to 1, equation (6) is a constraint imposed on each continuous stop period. min_stop,g is an integer that discretizes the minimum outage time of each generator in units of Δ.
[0047] The plan creation unit 16 uses the objective function shown in the above formula (1) and the constraint conditions shown in formulas (2) to (6) to calculate the power generation amount p of each generator that maximizes the objective function. g,tThe method of solving the optimization problem to maximize the objective function can be, for example, any method known as a method for solving mixed integer quadratic programming problems. By solving the optimization problem, the power generation amount p g,t The determined power generation amount p g,t Among these, g=0 to g=3 are actually trading volumes in market transactions, so the plan creation unit 16 creates a bidding plan using these as buying and selling bid volumes. Generators with g of 4 or more are true generators, so the plan creation unit 16 reflects the solution to the optimization problem for generators with g of 4 or more in the power generation plan. In this way, in this embodiment, the power generation plan and the bidding plan can be created simultaneously. The plan creation unit 16 outputs the power generation plan and the bidding plan to the plan transmission unit 17 and the display unit 18.
[0048] After step S5, the display unit 18 displays the power generation plan and the bidding plan (step S6). Fig. 5 is a diagram showing an example of the power generation plan and the bidding plan displayed by the display unit of this embodiment. In this manner, the display unit 18 can display the power generation plan and the bidding plan determined simultaneously in a superimposed manner. Note that the display unit 18 may also be capable of displaying the power generation plan and the bidding plan separately.
[0049] The plan transmitting unit 17 transmits the power generation plan and the bidding plan (step S7). In detail, the plan transmitting unit 17 transmits the power generation plan and the bidding plan to the supply and demand management device 2, and transmits the bidding plan to the bid support device 3. This completes the power generation plan creation process.
[0050] As a bidding condition, information indicating the probability of a predicted value of the market price, such as the probability that the predicted market price will not be correct, may be set as a parameter, and the plan creation unit 16 may create a power generation plan and a bidding plan by taking this parameter into consideration. For example, the market price may be defined as a probability density function or a stepped value obtained by discretizing the probability density function, and used as the fuel cost in the above-mentioned generator information. Alternatively, the market price may be set as an expected value taking into consideration the probability density function.
[0051] As described above, in this embodiment, the generator information is generated by regarding transactions in the electricity market as simulated generators, and the power generation plan and the bidding plan are simultaneously created by taking into account the generator information in the same way as a real generator. Therefore, it is possible to create an appropriate power generation plan that takes market transactions into account.
[0052] Embodiment 2 Next, a bidding support system according to the second embodiment will be described. Fig. 6 is a diagram showing a configuration example of the bidding support system according to the present embodiment. The bidding support system according to the present embodiment includes a power generation plan creation device 1 and a bidding support device 3 similar to those of the first embodiment, and also includes a market price prediction device 4. Components having the same functions as those of the first embodiment are given the same reference numerals as those of the first embodiment, and duplicated explanations will be omitted. Below, differences from the first embodiment will be mainly described.
[0053] The market price prediction device 4 of this embodiment obtains a predicted value of the market price that reflects, for example, a predicted value of the amount of power generated by a power generation facility including at least one of a solar power generation facility and a wind power generation facility. In detail, the market price prediction device 4 predicts the market price with high accuracy by using past market prices and actual values of bid amounts, and past related information that affects demand. Furthermore, the market price prediction device 4 reflects the amount of power generated by a variable power generation facility with large fluctuations in power output, such as a solar power generation facility and a wind power generation facility, in a prediction model of the market price, and predicts the market price by taking into account fluctuations in the variable power generation facility using forecast values such as weather for the prediction period. The market price prediction device 4 may also predict the market price with high accuracy by using a prediction model that takes into account market segmentation. Due to restrictions on the power system, power cannot be transmitted in excess of the capacity of the interconnection line connecting the areas, so the wholesale power market performs contract processing after taking into account the interconnection line capacity. Specifically, in the wholesale electricity market, after performing the contract process without considering the interconnection line capacity, it is checked whether the power transmission exceeds the interconnection line capacity, and if the capacity is exceeded, the interconnection line is fixed in a disconnected state and the contract process is performed again. This is market fragmentation, and when market fragmentation occurs, the contract price fluctuates significantly. By using a prediction model that considers market fragmentation, it is possible to improve the accuracy of prediction. Note that the method of predicting the market price in the market price prediction device 4 is not limited to this example, and any method that can predict the market price with high accuracy may be used.
[0054] The market price prediction device 4 is realized by a computer system, similar to the power generation plan creation device 1 of the first embodiment.
[0055] In FIG. 6, the market price prediction device 4 is provided separately from the power generation plan creation device 1 and the bidding support device 3, but the power generation plan creation device 1 or the bidding support device 3 may have the function of the market price prediction device 4.
[0056] The market price predicted value acquisition unit 11 of the power generation plan creation device 1 acquires a highly accurate predicted value of the market price from the market price prediction device 4, and outputs it to the power generator information generation unit 14. The operation of the power generation plan creation device 1 is similar to that of the first embodiment.
[0057] As described above, in this embodiment, a highly accurate market price forecast value is obtained, and the obtained forecast value is used to generate generator information by regarding transactions in the electricity market as simulated generators as in the first embodiment, and a power generation plan and a bidding plan are simultaneously created by considering the generator information in the same way as a real generator. Therefore, the same effects as in the first embodiment are achieved, and by using a highly accurate market price, the difference between the profit predicted at the time of planning and the actual profit of the business operator supported by the power generation plan creation device 1 can be reduced compared to the first embodiment.
[0058] Embodiment 3 Next, the power generation plan creation device 1 of the present embodiment 3 will be described. The configuration of the power generation plan creation device 1 of the present embodiment is the same as that of the embodiment 1. Components having the same functions as those of the embodiment 1 are given the same reference numerals as those of the embodiment 1, and duplicated explanations will be omitted. Below, differences from the embodiment 1 will be mainly described.
[0059] In the first embodiment, a spot market and a time-ahead market called the energy market are exemplified as the electricity trading market. The energy market is a market for buying and selling electricity. Meanwhile, in addition to the energy market, an adjustment power market called the supply and demand adjustment market for buying and selling adjustment power is scheduled to be opened in 2021 as an electricity trading market. Adjustment power is the ability to make adjustments to achieve simultaneous equal amounts of electricity when fluctuations from planned values occur. This adjustment is made by the electricity transmission and distribution business operator. The electricity transmission and distribution business operator secures both an upward adjustment power, which is the ability to adjust when a shortage occurs, and a downward adjustment power, which is the ability to adjust when a surplus occurs, so that it can adjust whether a shortage or surplus of electricity occurs. In the future, it is expected that power generation business operators will also participate in transactions in the supply and demand adjustment market.
[0060] In this embodiment, the power generation plan and the bidding plan are created taking into consideration transactions in the supply and demand adjustment market. For example, in this embodiment, in step S5 shown in Fig. 3, the plan creation unit 16 solves an optimization problem for maximizing the objective function shown in the following formula (7) instead of formula (1). At this time, in addition to the constraints of formulas (2) to (6) described in embodiment 1, the constraints shown in the following formulas (8) and (9) are also taken into consideration.
[0061]
number
[0062]
number
[0063] The first term in [ ] on the right side of the above formula (7) represents the profit gained from the supply and demand adjustment market. The second term is the sum of two terms in Σ, where the first term in Σ represents the profit from the upward adjustment power and the second term in Σ represents the profit from the downward adjustment power. A up,am,t indicates the amount of buying and selling of the upward adjustment power in the supply and demand adjustment market when electricity at the time corresponding to the elapsed time t is treated as a commodity. A down,am,t indicates the amount of downward adjustment power traded in the supply and demand adjustment market when electricity at the time corresponding to the elapsed time t is treated as a commodity. up,am,t ) is the profit related to the upward adjustment power through transactions in the supply and demand adjustment market when electricity at the time corresponding to the elapsed time t is treated as a commodity.
[0064] The profits from buying and selling in the supply and demand adjustment market are the profit based on the contracted amount of adjustment capacity, i.e., the sales volume, obtained by the adjustment capacity itself being contracted, and the profit based on the amount of adjustment capacity activated when the adjustment capacity is activated. The unit price for calculating these two profits is calculated as the predicted value of the contract price in the adjustment capacity market. Therefore, for example, AMup(A up,am,t ) is the forecast value of the contract price in the supply and demand adjustment market and A up,am,t and the predicted value of the amount of adjustment reserve activation. down,am,t) is the profit related to the downward adjustment power through trading in the supply and demand adjustment market when the electricity at the time corresponding to the elapsed time t is treated as a commodity. For example, AMdown(A down,am,t ) is the forecast value of the contract price in the supply and demand adjustment market and A down,am,t and the predicted value of the amount of adjustment capacity to be activated. am is a value corresponding to the type of supply and demand adjustment market. When there are multiple types of supply and demand adjustment markets, the profits in each supply and demand adjustment market are added together.
[0065] Moreover, the above formula (8) is a constraint that the sales amount of the upward control capacity is equal to or less than the sum of the maximum upward control capacity of the generators. max,g,t indicates the upper limit of the output of each generator at the elapsed time t. If the upper limit of the output does not depend on time, the upper limit of the output of each generator is p max,g The maximum up-regulation capability of each generator is p max,g From the above, p, which is the generator output at the time corresponding to the elapsed time t, g,t Equation (9) is a constraint that the sales volume of down regulation capacity must be less than or equal to the sum of the maximum down regulation capacity of the generators. min,g,t indicates the lower limit of the output of each generator at the elapsed time t. If the lower limit of the output does not depend on time, the upper limit of the output of each generator is p min,g The maximum down regulation of each generator is p g,t From p min,g This is a reduction of .
[0066] The predicted value of the contract price in the supply and demand adjustment market may be acquired by the market price predicted value acquisition unit 11 and stored in the storage unit 15 as a part of the power generator information, or may be stored in the storage unit 15 separately from the power generator information. The plan creation unit 16 reads out the predicted value of the contract price stored in the storage unit 15 and uses it to calculate the solution of the optimization problem. Through the above process, the plan creation unit 16 of this embodiment creates a bidding plan in the supply and demand adjustment market in addition to the power generation plan and the bidding plan in the energy market described in the first embodiment. The plan creation unit 16 outputs the bidding plan in the supply and demand adjustment market to the display unit 18 and the plan transmission unit 17. The display unit 18 can display the bidding plan in the supply and demand adjustment market in addition to the power generation plan and the bidding plan in the energy market. The plan transmission unit 17 transmits the power generation plan and the bidding plans in the energy market and the supply and demand adjustment market to the supply and demand management device 2, and transmits the bidding plans in the energy market and the supply and demand adjustment market to the bidding support device 3. In addition, bidding support devices for supporting bidding in the energy market and the supply and demand adjustment market may be provided separately, in which case the plan transmission unit 17 transmits a bidding plan for the energy market to the bidding support device corresponding to the energy market, and transmits a bidding plan for the supply and demand adjustment market to the bidding support device corresponding to the supply and demand adjustment market. The operation of this embodiment other than that described above is the same as that of embodiment 1.
[0067] The operation of this embodiment may be applied when using the highly accurate market price prediction value described in the second embodiment. In this case, the prediction value of the contract price in the supply and demand adjustment market may be calculated by the market price prediction device 4, may be calculated by another device, or may be input by an operator. Also, as with the energy market transactions, the supply and demand adjustment market may be regarded as a simulated power generator, information on costs may be held as power generator information, and the first term in [ ] on the right side of formula (7) may be integrated with the second term.
[0068] As described above, in this embodiment, the energy market transactions are regarded as simulated generators to generate generator information, and the generator information is taken into consideration in the same way as for real generators, and the power generation plan and the bidding plan are simultaneously created by taking into consideration buying and selling in the supply and demand adjustment market. That is, in this embodiment, the objective function includes the cost due to the transactions in the supply and demand adjustment market, and the plan creation unit 16 creates bidding plans in the energy market and the supply and demand adjustment market, respectively, as the bidding plan. Therefore, the same effects as those in the first embodiment can be achieved, and by taking into consideration the supply and demand adjustment market, the profits of the business operators supported by the power generation plan creation device 1 can be maximized by more effectively utilizing market transactions.
[0069] The configurations shown in the above embodiments are merely examples, and may be combined with other known technologies, or the embodiments may be combined with each other. Also, parts of the configurations may be omitted or modified without departing from the spirit of the invention. [Explanation of symbols]
[0070] 1 power generation plan creation device, 2 supply and demand management device, 3 bidding support device, 4 market price prediction device, 11 market price prediction value acquisition unit, 12 bidding condition acquisition unit, 13 demand prediction information acquisition unit, 14 generator information generation unit, 15 memory unit, 16 plan creation unit, 17 plan transmission unit, 18 display unit.
Claims
1. a storage unit that stores, for each generator, generator information for calculating a cost required for generating electricity by the generator, the generator information including a fuel unit price, a lower limit output, and an upper limit output; a generator information generating unit that regards trading of electricity in the electricity market as power generation by the simulated generator by setting a market price in the electricity market as a fuel unit price of a simulated generator, a trading volume in the electricity market as the power generation output of the simulated generator, a minimum bid volume in the electricity market as a lower limit output of the simulated generator, and an upper limit of the bid volume in the electricity market as an upper limit output of the simulated generator, thereby generating information for calculating costs required for trading in the electricity market as generator information of the simulated generator using a predicted market price in the electricity market and bidding conditions in the electricity market, and stores the information in the storage unit; a plan creation unit that uses the power generator information stored in the storage unit and a forecast value of demand for a period for which the plan is created to simultaneously create a power generation plan and a bidding plan for the electricity market; Equipped with The power generation plan creating device, wherein the bidding conditions include the minimum bid amount and an upper limit of the bid amount in the electricity market.
2. 2. The power generation plan creation device according to claim 1, wherein the plan creation unit uses the power generator information and the demand forecast value stored in the memory unit to determine an objective function and constraint conditions indicating the cost required for power generation by the power generator and the simulated power generator, calculates the power generation output of the power generator and the simulated power generator that maximizes the determined objective function under the constraint conditions, and creates the power generation plan and the bidding plan using the calculated power generation output.
3. the electricity market is an energy market; The objective function includes a cost due to transactions in the electricity supply and demand adjustment market, 3. The power generation plan creation device according to claim 2, wherein the plan creation unit creates, as the bidding plan, a bidding plan in each of the energy market and the power supply and demand adjustment market.
4. 4. The power generation plan creating device according to claim 1, wherein the bidding conditions include information indicating a probability of the predicted value of the market price.
5. 5. The power generation plan creation device according to claim 1, wherein the predicted value of the market price is a predicted value that reflects a predicted value of the power generation amount of a power generation facility including at least one of a solar power generation facility and a wind power generation facility.
6. a display unit for displaying the power generation plan and the bidding plan; 6. The power generation plan creating device according to claim 1, further comprising:
7. A power generation plan creation device according to any one of claims 1 to 6, a bidding support device that processes bidding using the bidding plan created by the power generation plan creation device; A bidding support system comprising:
8. storing, in a storage unit, generator information for calculating the cost required for generating electricity by each generator, the generator information including a fuel unit price, a lower limit output, and an upper limit output; a step of treating a market price in an electricity market as a fuel unit price of a simulated generator, a trading volume in the electricity market as the power generation output of the simulated generator, a minimum bid volume in the electricity market as a lower limit output of the simulated generator, and an upper limit of the bid volume in the electricity market as an upper limit output of the simulated generator, thereby regarding trading of electricity volume in the electricity market as power generation by the simulated generator, and generating information for calculating costs required for trading in the electricity market using a predicted market price in the electricity market and bidding conditions in the electricity market as generator information of the simulated generator and storing the information in the storage unit; creating a power generation plan and a bidding plan for the electricity market at the same time, using the power generator information stored in the storage unit and a forecast value of demand for a period for which the plan is to be created; on the computer, The power generation plan creating program, wherein the bidding conditions include the minimum bid amount and an upper limit of the bid amount in the electricity market.
Citation Information
Patent Citations
Power market analysis support system and method, and program
JP2007065954A
Energy supply-demand planning device and energy supply-demand planning program
JP2017134556A
Electricity transaction formulation apparatus
JP2019040483A
Power generation planning device, power generation planning method and power generation planning program
JP2019083601A
Bid support system
JP2020067919A