Power system operation plan generating device and power system operation plan generating method

The power system operation plan generation device and method address uncertainty in renewable energy and electric vehicle charging by dividing the planning problem into three layers, ensuring robustness and efficient calculation through Benders decomposition, thereby minimizing theoretical worst-case system operation KPIs.

JP7572911B2Active Publication Date: 2024-10-24HITACHI LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2021088077
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-05-26
Publication Date
2024-10-24
Estimated Expiration
2041-05-26

AI Technical Summary

Technical Problem

Existing power system operation planning methods fail to adequately address uncertainty in renewable energy sources and electric vehicle charging, leading to increased calculation times and reduced reliability due to the need for extensive scenario analysis, which can result in significant cost increases and constraint violations.

Method used

A power system operation plan generation device and method that divides the planning problem into three layers: operation plan determination, most severe scenario determination, and same-day control amount determination, using Benders decomposition to ensure robustness against prediction errors and consider constraints across time zones, without requiring extensive scenario preparation.

Benefits of technology

The solution achieves a balance of short calculation times, robustness against prediction errors, and consideration of constraints across time zones, resulting in an operation plan that minimizes theoretical worst-case system operation KPIs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007572911000019
    Figure 0007572911000019
  • Figure 0007572911000020
    Figure 0007572911000020
  • Figure 0007572911000021
    Figure 0007572911000021
Patent Text Reader

Abstract

To provide a power system operation plan generation device and a power system operation plan generation technology capable of acquiring an operation plan which satisfy three points of a short calculation time, robustness to erroneous prediction, and consideration of constraint over time zones.SOLUTION: A power system operation plan generation device 10 for determining an operation plan variable to be determined and a control variable on the day which can be determined in real time while taking an uncertainty parameter in a power system into account, and performing an operation plan of the power system includes: an operation plan generation part 20 for acquiring information on the operation plan variable and information on the control variable on the day in the power system and creating an operation plan proposal to an object function value in the severest scenario that assumes a sever state of the power system; a severest scenario generation part 30 for calculating the severest scenario and an object function value at that time from fluctuation information on the uncertainty parameter, the operation plan proposal, and the object function value of the control variable on the day; and a control amount on the day generation part 40 for determining an operation plan using system information on the power system, demand information, and the severest scenario.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a power system operation plan generating device and a power system operation plan generating method. [Background technology]

[0002] The introduction of renewable energy sources that do not emit greenhouse gases is progressing in power systems. The output of solar and wind power, which are typical renewable energy sources, fluctuates depending on weather conditions. In addition, with the spread of electric vehicles, the number of quick charging stations is increasing and their capacity is increasing, and this demand for electricity may affect the power system. There is a need for system operation that takes into account parameters with uncertainty (hereinafter referred to as "uncertain parameters"), such as the output of renewable energy sources and the charging demand for electric vehicles.

[0003] Meanwhile, there are two types of variables in system operation: variables that should be determined in advance, such as the day before (hereinafter referred to as operation planning variables), and variables that can be determined in real time (hereinafter referred to as intraday control variables). For example, operation planning variables in a power distribution system include the tap position of tap adjustment devices (e.g., LRT: Load Ratio control Transformer, SVR: Step Voltage Regulator), and the reserved amount of balancing margin of distributed energy resources (DER: Detributed Energy Resources) owned by consumers, such as private generators, storage batteries, and electric vehicles. In addition, intraday control variables include the activation command amount of balancing margin of distributed energy resources (DERs) owned by consumers that have made a reservation, such as SVCs (Static Var Compensators), distributed energy resources (DERs) such as storage batteries for the system owned by system operators, and distributed energy resources (DERs) owned by consumers that have made a reservation.

[0004] The first method that comes to mind for determining operational planning variables is to assume that the predictions of the uncertain parameters are correct and select the combination of values ​​that optimizes the system operation KPIs (e.g., violations of voltage tolerance and line capacity, response costs, etc.). This method does not take into account cases where the predictions are incorrect, and depending on the fluctuation pattern of the uncertain parameters, there is a possibility that the system operation KPIs may deteriorate drastically (e.g., violations of constraints such as voltage tolerance and line capacity, and drastic increases in costs due to additional responses, etc.).

[0005] For this reason, it is necessary to determine operational planning variables so that system operation KPIs (e.g., voltage tolerance range, violations of line capacity, response costs) do not deteriorate excessively (hereinafter referred to as "robust") even when the predictions of uncertain parameters fluctuate.

[0006] As one of the techniques for determining operation plan variables aimed at robust system operation, Patent Document 1 describes "Operation plan formulation device, operation plan formulation method, and operation plan formulation program." In Patent Document 1, in order to handle the uncertainty of the output of renewable energy sources in the optimization problem for solving the start and stop schedule of generators, a method is used to express this uncertainty using multiple scenarios. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] JP 2016-63609 A Summary of the Invention [Problem to be solved by the invention]

[0008] In general, increasing the number of scenarios increases the computation time for the optimization problem. Therefore, for example, when computation time is limited, it is not possible to use a sufficient number of scenarios, which can lead to a problem that the reliability of the obtained solution decreases.

[0009] In order to solve the above problem, Patent Document 1 assumes that the optimization problem can be simplified to one that is independent for each time period, with the aim of expressing uncertainty with a small number of scenarios. However, tap adjustment devices used in distribution systems have constraints that span time periods, such as an upper limit on the number of tap position adjustments per day. Therefore, it is not possible to simplify the optimization problem to one that is independent for each time period.

[0010] The present invention has been made in consideration of the above, and has an object to provide a power system operation plan generation device and a power system operation plan generation technology that are capable of generating an operation plan that satisfies three requirements: short calculation time, robustness against mispredictions, and consideration of constraints across time zones. [Means for solving the problem]

[0011] In view of the above, the present invention provides "a power system operation plan generation device that takes into consideration uncertainty parameters in a power system, determines operation plan variables that should be determined in advance and current day control variables that can be determined in real time, and performs operation planning for the power system, characterized in that it comprises an operation plan generation unit that obtains information on the operation plan variables and information on the current day control variables in the power system, and creates a draft operation plan for an objective function value in a most severe scenario that assumes a severe state of the power system, a most severe scenario generation unit that determines the most severe scenario and the objective function value at that time from fluctuation information on the uncertainty parameters, the draft operation plan, and the objective function values ​​of the current day control variables, and a current day control variable generation unit that determines an operation plan using system information, demand information, and the most severe scenario of the power system."

[0012] Furthermore, the present invention is a "power system operation plan generation method which takes into consideration uncertain parameters in a power system, determines operation plan variables that should be determined in advance and on-day control variables that can be determined in real time, and performs operation planning for the power system, wherein information on the operation plan variables and on-day control variables in the power system are obtained, and regarding the power system operation planning problem of creating a proposed operation plan for the objective function value in the most severe scenario assuming a severe state of the power system, the power system operation planning problem is divided into an operation plan determination problem which is a main problem, and a dependent problem, and the dependent problem is further divided into a most severe scenario determination problem which is a main problem, and a dependent problem, of determining on-day control variables, thereby performing operation planning for the power system as a solution of the triple-layered power system operation planning problem." Effect of the Invention

[0013] The present invention has the effect of making it possible to obtain an operation plan that satisfies three requirements: short calculation time, robustness against mispredictions, and consideration of constraints across time zones. [Brief description of the drawings]

[0014] [Figure 1] FIG. 2 is a diagram showing the processing contents in a calculation unit of the power system operation plan generating device as representative processing function units. [Diagram 2] A diagram showing how the proposed operational plan xp is obtained as a solution to the operational plan decision problem. [Diagram 3] FIG. 11 is a diagram showing an example of uncertain parameter variation information. [Figure 4] A diagram showing an example of the most extreme scenario. [Diagram 5] 1 is a process flow of a power system operation plan generation method. [Figure 6] FIG. 13 is a diagram showing the difference in effect when the present invention is compared with a conventional method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] Hereinafter, an embodiment of the power system operation plan generating device and the power system operation plan generating technology according to the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to the embodiment. Each embodiment can be appropriately combined as long as the processing contents are not contradictory.

[0016] In the following description, a power system operation plan generating device will be described in a first embodiment, a concept of generating a power system operation plan will be described in a second embodiment, and a method of generating a power system operation plan will be described in a third embodiment. EXAMPLES

[0017] In the first embodiment of the present invention, a power system operation plan generating device will be described. As an application example, the power system operation plan generating device that formulates an operation plan that is robust against fluctuations in uncertain parameters will be described, with a power distribution system including tap regulators and customer-owned DERs as a target.

[0018] First, the configuration of the power system operation plan generating device will be described. Fig. 1 is a diagram showing the processing contents in the calculation unit of the power system operation plan generating device realized by using a computer device, as its representative processing function units.

[0019] As shown in Fig. 1, the robust operation plan generation device 10 has an operation plan generation unit 20, a most severe scenario generation unit 30, and an in-day control amount generation unit 40. However, in addition to the functional units shown in Fig. 1, the operation plan development device 10 may also have, for example, a display unit that displays various information, an input unit that inputs input data, and a communication interface unit that communicates with other terminals.

[0020] To carry out its processing, the robust operation plan generating device 10 receives tap adjustment device information D1, customer-owned DER information D2, uncertain parameter fluctuation information D3, demand information D4, and system information D5 as inputs from outside.

[0021] The operation plan generation unit 20 in the robust operation plan generation device 10 obtains tap adjustment device information D1 and customer-owned DER information D2 as input data from outside, and also inputs the objective function value ηp and sensitivity information b1 calculated in the most severe scenario generation unit 30. An operation plan decision problem is generated based on these input data, and the solved operation plan proposal xp is output to the most severe scenario generation unit 30.

[0022] Among the external inputs used in this case, tap adjustment equipment information D1 includes, for example, the equipment type of each tap adjustment equipment (e.g., LRT, SVR, etc.), the installed bus ID, the number of tap stages, the tap width for each stage, the tap reference position, the response speed to control commands, the limit on the number of tap adjustments per day, the equipment cost, and the installation cost.

[0023] Among the same external inputs, the consumer-owned DER information D2 may include, for example, the type of equipment (e.g., private power generation, electric vehicle, etc.), the installed bus ID, the facility capacity, the response speed to a control command, etc. The consumer-owned DER information 110 may be input individually for each distributed energy resource DER, or may be input as a combined value of multiple distributed energy resources DER.

[0024] Here, the objective function value η represents the objective function when the most severe scenario determination problem is solved in the most severe scenario generator 30, i.e., the value of equation (14) described later. Moreover, the sensitivity information b1 is the amount of change in the objective function value ηp when the proposed operation plan xp is slightly changed.

[0025] The operation plan proposal xp is obtained as a solution to the operation plan decision problem. An example of this will be explained with reference to Fig. 2. Each row in Fig. 2 represents a time step 221, and each column represents a tap adjustment device ID 222 and a customer-owned DER ID 223. For each tap adjustment device ID 222, a tap position 224 at each time step 221 is stored. Furthermore, for each customer-owned DER ID 223, a reserved amount 225 of adjustment margin for each time step is stored. Since the reserved amount 225 of adjustment margin can take values ​​for both an increase and decrease in demand, it can also take a negative value as shown in Fig. 2.

[0026] Returning to FIG. 1, the most severe scenario generating unit 30 in the power system operation plan generating device 10 inputs uncertain parameter fluctuation information D3 as external input data, and also inputs the operation plan proposal x obtained by the operation plan generating unit 20 and the objective function value φp obtained by the day control amount generating unit 40. KPI and sensitivity information b2 are input, and a most severe scenario determination problem is generated based on these input data. The most severe scenario up that is solved is output to the day control amount generation unit 40, and the objective function value φp KPI and output the sensitivity information b2 to the most severe scenario generating unit 30.

[0027] An example of uncertain parameter variation information D3, which is an external input used in this case, is shown in the graph of Fig. 3. In the graph, photovoltaic power generation output is considered as an example of an uncertain parameter. The horizontal axis represents the time of day or 24 hours, and the vertical axis represents photovoltaic power generation output. The portion represented by the gray range is photovoltaic power generation output variation information 121. It is assumed that photovoltaic power generation output may vary within this gray range. The range of the variation information 121 may be determined based on actual values, or may be determined based on a weather forecast, etc.

[0028] Objective function value φp KPI represents the objective function when solving the most severe scenario decision problem, that is, the value of equation (15) described later. The sensitivity information b2 represents the objective function value φp KPI is the amount of change.

[0029] An example of the most severe scenario up is shown in the graph in Fig. 4. In the graph, photovoltaic power generation output is considered as an example of an uncertain parameter. The horizontal axis represents the time of day or 24 hours, and the vertical axis represents photovoltaic power generation output. The portion represented by the grey range is the fluctuation information 121 of the photovoltaic power generation output. The thick line 241 represents the most severe scenario up. The most severe scenario up is determined by solving the most severe scenario determination problem. Moreover, the thick line 241 falls within the grey range 121 at any time step.

[0030] Returning to FIG. 1 again, the daily control amount generation unit 40 in the power system operation plan generation device 10 obtains customer-owned DER information D2, demand information D4, and system information D5 as external input data, and also inputs the most severe scenario up obtained by the most severe scenario generation unit 30. Based on these input data, a daily control amount determination problem is generated, and the solved objective function value φp KPI and sensitivity information b2 are output to the most severe scenario generating unit 30.

[0031] In addition, the proposed operation plan xp and the objective function value ηp (=theoretical worst value of the system operation KPI) are output from the power system operation plan generating device 10 as the final solution obtained as a result of repeated processing in the operation plan generating unit 20, the most severe scenario generating unit 30, and the daily control amount generating unit 40. EXAMPLES

[0032] In the second embodiment, the concept of generating a power system operation plan will be described in detail using mathematical expressions, showing that a robust operation plan can be generated by the device shown in Fig. 1. In order to clarify the characteristics of the operation planning method according to the present invention, it is better to describe it in comparison with a normal operation planning method, so the normal operation planning method will be described first.

[0033] A typical operational planning method is characterized in that the user inputs a group of scenarios that express uncertainty in advance, and an operational plan is obtained by solving a mathematical programming problem whose objective function is to optimize the system operation KPIs. More specifically, in terms of a mathematical example, the above-mentioned mathematical programming problem is expressed in the following equations (1) and (2).

[0034]

number

[0035]

number

[0036] In formulas (1) and (2), the lowercase s represents the scenario, the uppercase S represents the set of input scenarios, the lowercase t represents the time, the uppercase T represents the set of times t included in the planning period, and φ KPI represents the grid operation KPI. The subscript of min represents the decision variable, x represents a vector of operation planning variables (e.g., tap position control amount, adjustable reserve amount of consumer-owned DER), and y represents a vector of control variables for the day (e.g., activation command amount of reserved adjustable reserve). Note that these are vectors, and equation (2) is a constraint equation that shows the grid constraint conditions for finding equation (1).

[0037] Here, the operation plan variable vector x needs to be determined at a stage when there is still a risk that the uncertain parameters will vary from the predicted values, so the same operation plan x is determined for all scenarios S input in advance by the user. In contrast, the day's control variable vector y is a variable that can be adjusted in real time after the uncertain parameters become clear (for example, after the actual photovoltaic power generation output is measured), so a different day's control y is determined for each scenario s. In normal operation planning methods, the above decision variables x and y are optimized simultaneously within a single mathematical programming problem.

[0038] In addition, the grid constraint in equation (2) is set as the constraint equation for the mathematical programming problem shown in equation (1). Examples of grid constraints include the energy balance equation for each bus, the calculation equation for the voltage of each bus, the calculation equation for the distribution loss of each line, the upper limit of the number of tap position adjustments per day for tap adjustment devices, and the upper and lower limits of the adjustment amount of consumer DER devices. Note that A1, A2, and C in equation (2) are matrices or vectors that represent the grid constraints, and the constraint equation in equation (2) is a matrix representation of the grid constraints.

[0039] This mathematical programming problem can be solved as mixed integer programming (MILP) or mixed integer quadratic cone programming (MISOCP) using a mathematical programming solver such as CPLEX or Gurobi. The solution results in an operation plan x that minimizes (=optimizes) the system operation KPI during the planning period T for the input scenario s. This operation plan x is expected to prevent extreme deterioration of the system operation KPI due to violations of voltage tolerances, etc., for the input scenario s.

[0040] However, when the input scenario set S does not include scenario u that causes the worst deterioration of the grid operation KPIs (hereinafter referred to as the most severe scenario), there is a possibility that an extreme deterioration of the grid operation KPIs may occur. Therefore, in order to obtain an operation plan x that is robust against any fluctuation pattern, it is necessary to include the most severe scenario u in the input scenario set S. However, it is difficult to appropriately select the most severe scenario u in advance for the following two reasons.

[0041] The first reason is that there are a huge number of candidates for the most severe scenario u. In particular, if the number of uncertain parameters increases due to the spread of renewable energy sources and electric vehicles, the number of candidates will increase explosively.

[0042] The second reason is that the most severe scenario u varies depending on the operational plan x, and therefore it is difficult to appropriately select the most severe scenario u at a stage prior to deciding on the operational plan x.

[0043] On the other hand, a method of inputting all possible candidates for the most severe scenario u is also conceivable, but the number of input scenarios would be enormous, which would increase the calculation time and may not complete the calculation within a given time limit.

[0044] Due to the above problems with the conventional operational planning methods, the present invention proposes the following operational planning method. The proposed operational planning method (hereinafter, the proposed method) has the following two advantages over the conventional operational planning methods.

[0045] The first point is that whereas conventional operational planning methods require the preparation of a set of scenarios that express uncertainty, the proposed method requires only the input of the variation range of the uncertain parameters, and does not require the preparation of a set of scenarios.

[0046] The first point is that while conventional operational planning methods can only guarantee robustness against the set of input scenarios, the proposed method can guarantee robustness against any fluctuation pattern within the fluctuation range.

[0047] The mathematical programming problem (hereinafter, robust operation planning problem) to be solved by the proposed method according to the present invention is shown in the following equations (3) and (4). Note that the explanation of the matters that have already been explained may be omitted.

[0048]

number

[0049]

number

[0050] In equation (3), u is a vector of uncertain parameters, and like x and y, it is a decision variable for the power system operation planning problem. As the objective function and constraint equation, φ, which is the system operation KPI, is used as in the normal operation planning method. KPI And equation (4) is set as the grid constraint.

[0051] A feature of this power system operation planning problem is that the objective function has a three-layer structure with min and max. Starting from the outside of equation (3), there is a part that determines the operation plan x that minimizes (=optimizes) the system operation KPI, a part that determines the value of the uncertain parameter u (=worst scenario) that maximizes (=worst deterioration) the system operation KPI, and a part that determines the day's control y that minimizes the system operation KPI.

[0052] By solving this problem, the most severe scenario u, which is the fluctuation pattern within the fluctuation range that causes the system operation KPI to deteriorate the most, is determined. At the same time, an operation plan x and an on-day control y that optimize the system operation KPI in the most severe scenario u are determined. Furthermore, the value of the system operation KPI at this time becomes the theoretical worst value, and even if any other fluctuation pattern occurs, it will not deteriorate beyond this theoretical worst value. Therefore, by solving this power system operation planning problem, an operation plan x that is robust against any fluctuation pattern can be obtained. Furthermore, since the most severe scenario u is generated while solving the power system operation planning problem, there is no need to prepare a candidate scenario s in advance.

[0053] In addition, the objective function, the system operation KPI (φ KPI ) is defined, for example, by the following equation (5).

[0054]

number

[0055] In this equation (5), φ cost , φ loss , φ penalty represent the operation cost, transmission loss, and constraint violation penalty, respectively. W c ,W l ,W p represent the weighting coefficients for operation cost, transmission loss, and constraint violation penalty, respectively. The ratio of the weighting coefficients is generally set as shown in equation (6). Note that terms other than these may be added to the system operation KPIs.

[0056]

number

[0057] Also, the transmission loss φ loss For example, is expressed by the following formula (7). However, in formula (7), the lowercase time t and the uppercase time T, which is the set of times t included in the planning period, are in the relationship t∈T.

[0058]

number

[0059] In this equation (7), j is the bus number, N tap is the set of bus numbers with tap adjustment devices such as SVR, N der represents the set of bus numbers for which customer-owned DERs exist. j tap represents the cost per tap adjustment in the tap adjustment equipment. Note that C j tap The value of x can be calculated by dividing the sum of the tap adjustment equipment price and installation cost by the number of tap adjustments required until the equipment reaches the end of its life. j,t tap represents the number of tap adjustments in the tap adjustment device. j,t der_r , c j,t der_c represents the incentive unit price for the adjustment margin reservation of consumer-owned DERs and the incentive unit price for intraday control. x j,t der , y j,t der represents the reserved amount of adjustment margin of the consumer-owned DER and the activation command amount for that day.

[0060] As a result, the first term on the right side of equation (7) corresponds to the adjustment cost of the tap adjustment device, the second term corresponds to the incentive cost for the adjustment margin reservation, and the third term corresponds to the incentive cost for the actual control command. Note that x j,t tap , y j,t der is the vector x of the above operation planning variables, j,t der is included in the vector y of control variables for the day.

[0061] In addition, the transmission loss φ loss For example, is expressed by the following formula (8): In formula (8), the lowercase time t and the uppercase time T, which is the set of times t included in the planning period, are in the relationship t∈T.

[0062]

number

[0063] In equation (8), B represents a set of lines. ij represents the resistance value of the line from bus i to bus j, and lij,s,t represents the absolute value of the current in the line from bus i to bus j at scenario s and time t.

[0064] In addition, the constraint violation penalty φ penalty For example, is expressed by the following formula (9). However, in formula (9), the lowercase time t and the uppercase time T, which is the set of times t included in the planning period, are in the relationship t∈T.

[0065]

number

[0066] In addition, in equation (9), ζ ij,t represents the excess of the line constraint on the line connecting bus i to bus j, and η j,t represents the deviation of the voltage at bus j from the allowable range. B represents the set of buses.

[0067] 1 solves the power system operation planning problem shown in the above formulas (1) to (9). However, since the power system operation planning problem has a three-layer structure as described above, mathematical programming solvers such as CPLEX and Gurobi do not support mathematical programming problems with multiple layers, and therefore cannot solve the problem as is.

[0068] Therefore, below we will explain an example of how to solve the problem using Benders decomposition, a typical decomposition method. In Benders decomposition, a mathematical programming problem is decomposed into two problems: a primary problem and a subordinate problem. First, the primary problem is solved, and the solution is used as a constraint to solve the subordinate problem. A constraint equation called a Benders cut is passed to the primary problem for the subordinate problem. This constraint equation of the primary problem is added to limit the search area for the solution, and then the problem is solved. By repeating the above process, a globally optimal solution is found.

[0069] Since the power system operation planning problem has a three-layer structure, the Benders decomposition is applied twice. First, the outermost min part is separated into the main problem (hereinafter referred to as the operation plan decision problem), and the rest is separated into dependent problems. Since this dependent problem has a double structure of max and min, the Benders decomposition is applied again, and it is again separated into the main problem and dependent problem (hereinafter referred to as the most severe scenario decision problem and the daily control amount decision problem, respectively). In this way, the three-layered power system operation planning problem can be decomposed into the following three mathematical programming problems.

[0070] These are the operation plan determination problem, the most severe scenario determination problem, and the daily control amount determination problem. The operation plan determination problem is processed by the operation plan generation unit 20 in Figure 1, the most severe scenario determination problem is processed by the most severe scenario generation unit 30, and the daily control amount determination problem is processed by the daily control amount generation unit 40.

[0071] In this relationship, the operation plan decision problem is the main problem, and its subordinate problem is the most severe scenario decision problem. At the same time, the most severe scenario decision problem is the main problem for the daily control amount decision problem, and the daily control amount decision problem is its subordinate problem.

[0072] The operation plan determination problem processed by the operation plan generating unit 20 is expressed by the following equations (10) and (11).

[0073]

number

[0074]

number

[0075] In these equations, θ, the objective function of the operation plan decision problem, represents the estimated value of the objective function value ηp of the most severe scenario decision problem (= the estimated value of the system operation KPI). The decision variables are θ and x. The proposed operation plan xp obtained by solving this is determined so as to minimize the estimated value of the system operation KPI. Note that variables with the symbol p indicate constant values ​​obtained as a calculation result.

[0076] A Benders cut is set as a constraint in equation (11) and is added for each iteration. b1 is sensitivity information defined as the amount of change in ηp when the proposed operation plan xp is changed slightly, and is also called the shadow price. The sensitivity information is found as the solution to the dual problem of the dependent problem. The Benders cut equation constructed above can be regarded as a linear approximation of η with respect to x. By sequentially adding this, the estimation accuracy of θ is improved and the proposed operation plan xp is updated.

[0077] The most severe scenario determination problem processed by the most severe scenario generating unit 30 is expressed by the following equation (9).

[0078]

number

[0079]

number

[0080] In these equations, θ of the objective function of the most severe scenario determination problem is the objective function value φp KPI (=system operation KPI). The decision variables are θ and x. The proposed operation plan xp obtained by solving this is determined so as to minimize the estimated value of the system operation KPI. A bender's cut is set as the constraint in equation (13) and is added for each iteration. b2 is the change in φ when the scenario up is slightly changed. KPIBy sequentially adding this information, the estimation accuracy of is improved and the most severe scenario up is updated.

[0081] The problem of determining the daily control amount processed by the daily control amount generating unit 40 is expressed by the following equations (14) and (15). The decision variable is the daily control y, and the problem is determined so as to minimize the estimated value of the system operation KPI by solving this.

[0082]

number

[0083]

number

[0084] In these equations, the objective function φ KPI represents the system operation KPI. System constraints are set in the constraint conditions of equation (15). Therefore, in the problem of determining the control amount for the day, the system operation KPI is calculated directly based on the system constraints.

[0085] The three decomposed mathematical programming problems are solved alternately by iterative calculation as described above. The end condition of the iterative calculation is expressed by the following equation (16).

[0086]

number

[0087] In this formula, ε is the allowable error rate, and is set to, for example, 0.0001. UB and LB represent the upper and lower limits of the objective function value, respectively. In the case of repeated calculations between the operation plan decision problem and the most severe scenario decision problem, UB and LB are calculated by the following formula (17).

[0088]

number

[0089] In this equation, θp is the value of θ determined by the operation plan decision problem. In other words, it can be interpreted as repeating the calculation until θ, the estimated value of η, becomes sufficiently close to the true value of η. In the case of repeating the calculation between the most severe scenario decision problem and the day's control plan, UB and LB are calculated by the following equation (18).

[0090]

number

[0091] In this equation, ηp is the value of η determined by the uncertain parameter determination problem. KPI The estimated value of η is the true value of φ KPI This can be interpreted as repeating the calculation until the value becomes sufficiently close to EXAMPLES

[0092] In the third embodiment, a method for generating a power system operation plan will be described with reference to the process flow of FIG.

[0093] In the flow of Fig. 5, when processing is started, in processing step S2, the operation plan generation unit 20 functions to find a solution to the operation plan determination problem, which is equations (10) and (11). However, in this case, in order to make the operation plan determination problem the main problem and the other parts dependent problems, in processing step S1, the vendor's cut is generated and added using equations (10) and (11), and processing step S2 is performed with this as a condition. Note that the input of operation plan variables used at this time (tap adjustment device input 100, consumer-owned DER information 110) and the conditions of the most severe scenario (objective function value η, sensitivity information b1) are as shown in Fig. 1.

[0094] Next, in the process of the most severe scenario generating unit 30, a solution to the most severe scenario determination problem, equations (12) and (13), is found in process step S4. However, in order to make the most severe scenario determination problem the main problem and the daily control amount determination problem the dependent problem, a vendor's cut is generated and added in process step S3 using equations (12) and (13), and process step S4 is carried out using this as a condition. Note that the uncertain parameter fluctuation information (output of renewable energy power sources and charging demand for electric vehicles), the daily control amount conditions (objective function value η, sensitivity information b2), and the proposed operation plan xp used at this time are as shown in FIG. 1.

[0095] Next, in the process of the current day control amount generating unit 40, a solution to the current day control amount determination problem, equations (14) and (15), is found in process step S5. However, the current day control amount determination process in process step S5 is repeatedly executed until it is determined in process step S6 that the most severe scenario determination problem has converged using equations (16) and (18) that the calculation has ended, and in process step S7 that the operation plan determination problem has converged using equations (16) and (17) that the calculation has ended. The demand information and system information used at this time are as shown in FIG. 1.

[0096] Fig. 6 is a diagram showing the difference in effect when comparing the present invention with the conventional method. The final output of the power system operation plan generating device in Fig. 1 is displayed on a monitor screen or the like, and is shown as an image diagram of that case.

[0097] According to this notation, in the conventional case, the system operation KPI in the case of one scenario assumed in advance is obtained as point information, but in the present invention, the most severe scenario is generated internally, and the system operation KPI value 270 (theoretical worst value) for it is calculated. Therefore, no matter what conceivable scenario occurs, the system operation KPI value is output in a format that falls within a range. In other words, compared to the conventional case, it is obtained as a range rather than a point. [Explanation of symbols]

[0098] 10: Power system operation plan generator 20: Operation plan generation unit 30: Most severe scenario generation section 40: Today's control amount generation unit

Claims

1. A power system operation plan generating device that takes into account uncertainty parameters in a power system, determines operation plan variables that should be determined in advance and on-day control variables that can be determined in real time, and performs an operation plan for the power system, 1. A power system operation plan generation device comprising: an operation plan generation unit that obtains information on operation plan variables and information on current day control variables in a power system, and creates a proposed operation plan for an objective function value in a most severe scenario that assumes a severe state of the power system; a most severe scenario generation unit that obtains the most severe scenario and its objective function value from information on fluctuations in uncertainty parameters, the proposed operation plan, and objective function values ​​of current day control variables; and a current day control variable generation unit that determines an operation plan using system information and demand information of the power system, and the most severe scenario.

2. The power system operation plan generating apparatus according to claim 1, The power system operation plan generating device is characterized in that the operation plan variables include one or more of a tap position of a tap adjustment device and a regulation margin of a distributed energy resource owned by a consumer.

3. The power system operation plan generating apparatus according to claim 1, The power system operation plan generating device is characterized in that the control variables for the day include one or more of the activation command amounts of the adjustment margin of distributed energy resources owned by a power system operator and distributed energy resources owned by a reserved consumer.

4. A power system operation plan generation method for determining operation plan variables to be determined in advance and on-day control variables that can be determined in real time, taking into account uncertainty parameters in the power system, and performing an operation plan for the power system, comprising: A power system operation plan generation method for a power system operation planning problem in which information on operation plan variables and information on on-day control variables in a power system are obtained, and a proposed operation plan is created for an objective function value in a most severe scenario that assumes a severe state of the power system, the power system operation planning problem is divided into a main problem of an operation plan determination problem and a subordinate problem, and the subordinate problem is further divided into a main problem of a most severe scenario determination problem and a subordinate problem of on-day control amount determination problem, thereby performing an operation plan for the power system as a solution to a three-tiered power system operation planning problem.

Citation Information

Patent Citations

  • Energy management system, power demand plan optimization method and power demand plan optimization

    JP2016032337A

  • Operational planning formulation device, formulation method for operational planning and operational planning formulation program

    JP2016063609A

  • Load allowance calculation device, load allowance calculation method, and program

    JP2016116290A

  • Power equipment planning method, power equipment manufacturing method, power equipment planning apparatus, and program

    JP2018148753A

  • Simultaneous optimization of energy production and frequency regulation of power generation systems

    JP2019535225A