Reinforcing bar hanging fixture

The reinforcing bar suspension jig addresses the issue of fixed vertical spacing in existing devices by providing adjustable spacing and interference-free rotation, enhancing the efficiency of reinforcing bar assembly and transport for earthquake-resistant structures.

JP7575147B1Active Publication Date: 2024-10-29SHINWA CONSTRUCTION CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
JP2024101442
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2024-06-24
Publication Date
2024-10-29
Estimated Expiration
2044-06-24

AI Technical Summary

Technical Problem

Existing reinforcing bar support devices for temporary assembly jigs have fixed vertical spacing that does not accommodate varying bar spacings, requiring frequent reconfiguration, and interfere during assembly of earthquake-resistant structures.

Method used

A reinforcing bar suspension jig with a hanging jig body and adjustable reinforcing bar receiving members, featuring through holes at predetermined intervals, allowing flexible spacing and interference-free rotation for easy assembly and transport.

Benefits of technology

Enables versatile and efficient movement of temporarily assembled reinforcing bars with adjustable spacing, reducing interference and facilitating sequential assembly without reconfiguration, suitable for various construction sites.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007575147000001_ABST
    Figure 0007575147000001_ABST
Patent Text Reader

Abstract

To provide a highly versatile reinforcing bar hoisting jig (applicable to any site) for moving reinforcing bars provisionally assembled on the ground in advance by crane at construction sites of reinforced concrete structures such as bridge piers of expressways. [Solution] A rebar lifting jig for pre-assembling rebars on the ground at construction sites of reinforced concrete structures such as highway piers, the rebar lifting jig comprising a lifting jig main body 20 and a rebar receiving member 30 on which the rebars are placed during pre-assembly, the lifting jig main body 20 having a plurality of through holes 40 drilled at predetermined intervals, the rebar receiving member 30 having a rebar receiving portion 50 on which the rebars are placed and a through hole 60, and further comprising a fixing member for fixing the rebar receiving member 30 to the lifting jig main body 20 and a support pin member for inserting into the through hole 40 of the lifting jig main body 20 to support the rebar receiving member 30.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a reinforcing bar hoisting jig for use in moving reinforcing bars that have been temporarily assembled on the ground in advance by crane at construction sites of reinforced concrete structures such as highway bridge piers. [Background technology]

[0002] Prefabrication, in which the rebar parts (mainly the reinforcing bars) of columnar structures (reinforced concrete structures) such as highway bridge piers are temporarily assembled on the ground near the construction site and then transported to the site by crane, is known as an effective means of shortening construction time and improving construction efficiency. The advantages of prefabrication include shortening construction time by drastically reducing on-site assembly time, and reducing the risk of accidents caused by working at heights by increasing the amount of work done on the ground.

[0003] Patent Document 1 has the objective of "obtaining a support device for a rebar temporary assembly jig that is easy to assemble as the support brackets do not get in the way and that reduces costs by shortening the time required for temporary assembly of the rebars (Patent Document 1: Abstract)", and discloses a support device for a rebar temporary assembly jig (Patent Document 1: Name of Invention) in which "in a temporary assembly jig comprising a required number of temporary assembly jigs to which a plurality of support brackets are pivotally attached, holding means is provided on at least one of the temporary assembly jig or the support brackets that can be released at will so that the support brackets can be rotated from a supported state and held in an inverted state, and the holding means is a magnet (Patent Document 1: Abstract)". [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Utility Model Registration No. 3132735 Summary of the Invention [Problem to be solved by the invention]

[0005] The support receiving device of the rebar temporary assembly jig in Patent Document 1 (Patent Document 1: name of the invention) is provided with a holding means that can release the holding at will on at least one of the temporary assembly jig or the support receiving bracket so that the support receiving bracket can be rotated from the supported state and held in an inverted state, so that when the temporary assembly jig is used for transferring and moving the support receiving bracket, the lifted rebar inverts the support receiving bracket and holds it in that inverted state, so that the upper support receiving bracket does not get in the way during temporary assembly, and the rebar to be assembled into an earthquake-resistant structure can be easily assembled and constructed starting from the lowest support receiving bracket of the temporary assembly jig. However, if the (vertical) interval between the support receiving brackets is fixed as in the support receiving device of the rebar temporary assembly jig in Patent Document 1 (Patent Document 1: name of the invention), the vertical interval of the rebar often differs from site to site, so the support receiving device must be redesigned by changing the interval between the support receiving brackets each time.

[0006] The object of the present invention is to provide a highly versatile rebar lifting jig (suitable for use at any construction site) for use in moving rebar that has been pre-assembled on the ground by crane at construction sites of reinforced concrete structures such as highway piers. [Means for solving the problem]

[0007] In order to solve the above problems, the invention described in claim 1 is a reinforcing bar hoisting tool for moving reinforcing bars that have been pre-assembled on the ground at a construction site of a reinforced concrete structure such as a bridge pier of a highway, using a crane, It is equipped with a lifting jig body and a rebar support member for placing rebar during temporary assembly. The hoisting jig body has a plurality of through holes drilled at predetermined intervals, The reinforcing bar receiving member has a reinforcing bar receiving portion on which a reinforcing bar is placed and a through hole, Furthermore, a fixing member for fixing the reinforcing bar receiving member to the hoisting jig body; A support pin member is inserted into the through hole of the lifting jig body to support the reinforcing bar receiving member. The fixing member and the support pin member are connected via a wire. The present invention is characterized in that it is a reinforcing bar hanging jig having the above features.

[0008] The invention described in claim 2 is the invention described in claim 1, This is a rebar hanging jig that is characterized in that, when the rebar receiving members are installed on the hanging jig body, adjacent rebar receiving members in the vertical direction are installed on different sides of the hanging jig body. Effect of the Invention

[0010] The present invention is a reinforcing bar hoisting jig for moving reinforcing bars that have been temporarily assembled on the ground in advance by a crane at a construction site of a reinforced concrete structure such as a bridge pier of a highway. The reinforcing bar hoisting jig includes a hoisting jig body and a reinforcing bar receiving member on which the reinforcing bar is placed during temporary assembly. The hoisting jig body has a plurality of through holes drilled at a predetermined interval, and the reinforcing bar receiving member has a reinforcing bar receiving portion on which the reinforcing bar is placed and a through hole. Therefore, when the reinforcing bar receiving member is fixed to the hoisting jig body, it is possible to select from the through holes drilled at a predetermined interval for each site. Therefore, when the reinforcing bar receiving member is installed on the hoisting jig body, the interval between the reinforcing bar receiving member and the reinforcing bar receiving member can be freely selected according to the site.

[0011] When installing the rebar support members on the lifting jig body, vertically adjacent rebar support members are installed so that they are on different sides of the lifting jig body. Therefore, when the temporarily assembled rebars (mainly reinforcing bars) are removed from the rebar lifting jig after being moved by crane on the ground (at construction sites of reinforced concrete structures such as highway piers), the fixing members (bolts and nuts) that secure the rebar support members are loosened, and the support pin members are removed from the through holes (of the rebar support member) and the rebar support member is rotated downward (using the fixing members as the rotation axis) without interference from adjacent rebar support members in the downward direction. [Brief description of the drawings]

[0012] [Figure 1] FIG. 2 is an exploded view of the reinforcing bar suspension jig according to the present invention. [Diagram 2] FIG. [Diagram 3] This is a diagram showing the state in which a rebar hoisting jig is installed on a temporarily assembled rebar. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] <Structure of rebar hanging jig> An embodiment of a reinforcing bar suspension jig 10 according to the present invention will be described in detail below with reference to Figures 1 to 3. Figure 1 is an exploded view of a reinforcing bar suspension jig 10 according to the present invention.

[0014] The reinforcing bar hoisting jig 10 according to the present invention is a reinforcing bar hoisting jig for moving reinforcing bars that have been temporarily assembled on the ground in advance by crane at a construction site of a reinforced concrete columnar structure such as a bridge pier for a highway, etc. As shown in Fig. 1, the reinforcing bar hoisting jig 10 is composed of a hoisting jig main body 20 and a reinforcing bar receiving member 30 on which the reinforcing bar is placed during temporary assembly (see Fig. 1: exploded view).

[0015] The hoisting jig body 20 is a steel plate (SS400) with a total length of approximately 1,100 mm, a width of approximately 120 mm, and a thickness of approximately 12 mm, and has a plurality of through holes 40 (Φ12 mm (for fixing members 70) or Φ11 mm (for support pin members 80) drilled at specified intervals (25 mm intervals). To describe the through holes 40 in a little more detail, the through holes 40 are drilled in two rows along the vertical direction of the hoisting jig body 20. One of the vertical rows is a through hole 40 for the fixing members 70, and the other vertical row is a through hole 40 for the support pin members 80.

[0016] The reinforcing bar receiving member 30 is a steel plate (SS400) measuring 150 mm wide x 70 mm long and approximately 6 mm thick, and is provided with a reinforcing bar receiving portion 50 (recess width approximately 40 mm, recess curvature R approximately 20 mm) on which the reinforcing bar is placed, and a through hole 60 (Φ12 mm (for the fixing member 70)).

[0017] Furthermore, the reinforcing bar hanging jig 10 is equipped with a fixing member 70 for fixing the reinforcing bar receiving member 30 to the hanging jig body 20, and a support pin member 80 that is inserted into the through hole 40 of the hanging jig body 20 to support the reinforcing bar receiving member 30. Note that the fixing member 70 and the support pin member 80 are connected to each other with a wire (such as a stainless steel wire) in consideration of workability.

[0018] 2 is an overall view of the reinforcing bar suspension jig 10. When the reinforcing bar receiving members 30 are installed on the suspension jig body 20, the reinforcing bar receiving members 30 adjacent in the vertical direction are installed on different faces of the suspension jig body 20. By installing vertically adjacent reinforcing bar receiving members 30 on different sides (front and back) of the hanging jig body 20, when the temporarily assembled reinforcing bars (mainly reinforcing bars) are removed from the reinforcing bar hanging jig 10 after the reinforcing bars have been temporarily assembled on the ground and moved by crane, the fixing members 70 (bolts and nuts) that secure the reinforcing bar receiving members 30 are loosened, the support pin members 80 are removed from the through holes (of the reinforcing bar receiving member), and the reinforcing bar receiving member 30 is rotated downward (around the fixing members 70 as the rotation axis) (the fixing members 70 (bolts and nuts) that secure the reinforcing bar receiving member 30 can also be loosened).

[0019] <How to use rebar hoisting fixture> Fig. 3 is a diagram showing the state in which the reinforcing bar hoisting jig 10 is installed on the temporarily assembled reinforcing bars. That is, it is a diagram for explaining the method of using the reinforcing bar hoisting jig 10. As shown in Fig. 3, multiple reinforcing bar hoisting jigs 10 are attached to the reinforcing bars (mainly the arranged reinforcing bars) temporarily assembled on the ground, and the tips of the multiple reinforcing bar hoisting jigs 10 are secured (using hooks attached to a crane) and the temporarily assembled reinforcing bars (mainly the arranged reinforcing bars) are lifted together with the multiple reinforcing bar hoisting jigs 10 and moved to the construction site (see Fig. 3).

[0020] The reinforcing bars that have been temporarily assembled on the ground are moved to the construction site by a crane, and after installation of the reinforcing bars (mainly reinforcing bar arrangement) is completed at the construction site, the fixing members 70 (bolts and nuts) that fix the reinforcing bar receiving member 30 are loosened, the support pin members 80 are removed from the through holes 60 (of the reinforcing bar receiving member), and the fixing members 70 (bolts and nuts) that fix the reinforcing bar receiving member 30 are loosened after the support pin members 80 have been removed from the through holes 60 (of the reinforcing bar receiving member), and the reinforcing bar receiving member 30 is rotated downward (with the fixing members 70 as the rotation axis) to remove the (multiple) reinforcing bar lifting jigs 10 from the temporarily assembled reinforcing bars (moved to the construction site by a crane).

[0021] <Effect of rebar hanging fixture> The reinforcing bar suspension jig 10 has through holes 40 drilled at predetermined intervals in the suspension jig body 20, allowing the installation interval of the reinforcing bar receiving members 30 to be freely selected. Therefore, when fixing the reinforcing bar receiving members 30 to the suspension jig body 20, by selecting through holes 40 (drilled at predetermined intervals (25 mm)) for each site, when installing the reinforcing bar receiving members 30 on the suspension jig body 20, the spacing between the reinforcing bar receiving members 30 can be freely selected to suit the site.

[0022] When the reinforcing bar receiving members 30 are installed on the hanging jig main body 20, vertically adjacent reinforcing bar receiving members 30 are installed so that they are on different sides (front and back) of the hanging jig main body 20. Therefore, when the temporarily assembled reinforcing bars (mainly bar arrangement) are removed from the reinforcing bar hanging jig 10 after the reinforcing bars are moved by crane on the ground (at a construction site of a reinforced concrete structure such as a highway pier), the fixing members 70 (bolts and nuts) that fix the reinforcing bar receiving members 30 are loosened, and then the support pin members 80 are removed from the through holes 60 (of the reinforcing bar receiving member 30) and the reinforcing bar receiving member 30 is rotated downward (with the fixing members 70 as the rotation axis), there is no interference between the reinforcing bar receiving members 30 that are adjacent downward.

[0023] <Example of modification of rebar hanging jig> The reinforcing bar hanging jig of the present invention is not limited to the aspects of the above-mentioned embodiments, and the configurations of the hanging jig main body, reinforcing bar receiving member, through hole (hanging jig main body), reinforcing bar receiving portion, through hole (reinforcing bar receiving member), fixing member, support pin member, etc. can be appropriately modified as necessary within the scope of the spirit of the present invention. [Industrial Applicability]

[0024] Since the reinforcing bar hoisting jig of the present invention has the excellent effects as described above, it can be suitably used as a reinforcing bar hoisting jig for moving reinforcing bars that have been pre-assembled on the ground by crane at construction sites of reinforced concrete structures such as highway piers. [Explanation of symbols]

[0025] 10. Steel bar lifting fixture 20··Hanging jig body 30 Reinforcement bar support member 40··Through hole (hanging jig body) 50··Reinforced bar support 60··Through hole (reinforcing bar support member) 70 Fixing member 80··Support pin member

Claims

1. A rebar hoisting jig for moving rebars that have been preassembled on the ground by crane at construction sites of reinforced concrete structures such as highway bridge piers, It is equipped with a lifting jig body and a rebar support member for placing rebar during temporary assembly. The hoisting jig body has a plurality of through holes drilled at predetermined intervals, The reinforcing bar receiving member has a reinforcing bar receiving portion on which a reinforcing bar is placed and a through hole, Furthermore, a fixing member for fixing the reinforcing bar receiving member to the hoisting jig body; A reinforcing bar suspension jig comprising a support pin member that is inserted into a through hole of the suspension jig body to support the reinforcing bar receiving member, and the fixing member and the support pin member are connected via a wire.

2. The reinforcing bar suspension jig described in claim 1, characterized in that when the reinforcing bar receiving members are installed on the suspension jig body, adjacent reinforcing bar receiving members in the vertical direction are installed so that they are on different sides of the suspension jig body.

Citation Information

Patent Citations

  • JP1980065363U

  • Reinforcement work execution method and temporary reinforcement assembly jig used for the method

    JP2000104404A

  • Mounting member for shear reinforcement

    JP2005098103A

  • Reinforcing steel bar placing method by substitutive transfer of temporary assembled steel bar unit

    JP2008223458A

  • Assembling unit and reinforcement assembling device

    JP2009235711A