Formwork sheet, formwork unit, and method for manufacturing formwork unit
The resin formwork sheet with defined folding lines and attachment methods addresses the issue of concrete adhesion to wooden formwork side surfaces, enabling easy separation and reuse of the formwork.
Patent Information
- Application Number
- JP2020129605
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-07-30
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2040-07-30
AI Technical Summary
Concrete tends to adhere to the side surfaces of wooden formwork, making it difficult to separate the formwork from the concrete, especially when multiple formworks are installed side by side.
A formwork sheet made of resin is attached to a wooden formwork, featuring a pouring surface facing portion and a side surface facing portion that covers the entire concrete pouring surface and adjacent side surfaces, with defined folding lines and attachment methods to ensure proper alignment and adherence.
The resin formwork sheet facilitates easy separation of concrete from the formwork side surfaces, preventing adhesion and allowing for efficient removal and reuse of the formwork, while maintaining structural integrity and preventing damage.
Smart Images

Figure 0007576788000001 
Figure 0007576788000002 
Figure 0007576788000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a form sheet, a form unit, and a method for manufacturing a form unit. [Background technology]
[0002] Conventionally, concrete formwork has been known (see, for example, Patent Document 1). This concrete formwork is constructed by attaching a wooden damming board to one side of a wooden frame body. The damming board is composed of a wooden board material attached to one side of the frame body, and a plastic board material attached to the surface of the wooden board material that comes into contact with the concrete. If concrete is poured directly onto the surface of the wooden board material, the concrete adheres to the surface of the board material and the concrete is difficult to peel off from the surface of the board material. Therefore, a plastic board material is provided on the surface of the damming board that comes into contact with the concrete, and by preventing the concrete from coming into direct contact with the surface of the wooden board material, the damming board is made easier to peel off from the concrete. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Utility Model Application Publication No. 06-054840 Summary of the Invention [Problem to be solved by the invention]
[0004] Incidentally, the above-mentioned concrete formworks are often arranged in a row to surround the space into which concrete is poured. When concrete is poured into a space where the concrete formworks are arranged in a row, the concrete is likely to enter the gaps between the adjacent concrete formworks. When the above-mentioned concrete formworks are used in such construction, the concrete adheres to the side of the wooden frame, making it difficult for the concrete to peel off from the concrete formworks.
[0005] The present invention was invented in consideration of the above-mentioned conventional problems, and its object is to provide a formwork sheet, a formwork unit, and a method for manufacturing a formwork unit that make it easy to peel off concrete even if concrete adheres to the side of the formwork adjacent to the concrete pouring surface. [Means for solving the problem]
[0006] In order to solve the above problems, one embodiment of the present invention provides a form sheet made of resin that is attached to a wooden formwork having a concrete pouring surface and a formwork side surface that is adjacent to and intersects with the concrete pouring surface. The form sheet includes a pouring surface facing portion that faces the entire surface of the concrete pouring surface, and a side facing portion that is continuous with the pouring surface facing portion and faces the formwork side surface.
[0007] In order to solve the above problems, one embodiment of the present invention provides a formwork unit comprising a wooden formwork and a resin formwork sheet attached to the formwork. The formwork has a concrete pouring surface and a formwork side surface adjacent to and intersecting with the concrete pouring surface. The formwork sheet has a pouring surface facing portion facing the entire surface of the concrete pouring surface, and a side facing portion continuous with the pouring surface facing portion facing the formwork side surface.
[0008] In order to solve the above problems, one embodiment of the present invention relates to a method for manufacturing a form unit comprising a wooden form and a resin form sheet attached to the form, the form having a concrete pouring surface and a form side surface adjacent to and intersecting with the concrete pouring surface, the form sheet having a pouring surface facing portion facing the entire surface of the concrete pouring surface and a side surface facing portion continuous with the pouring surface facing portion facing the form side surface.
[0009] The manufacturing method includes a temporary fixing step and a fold line forming step. The temporary fixing step is a step of temporarily fixing the form sheet at a predetermined position of the form. The fold line forming step is a step of forming a fold line at the boundary between the casting surface facing portion and the side surface facing portion. Effect of the Invention
[0010] With the form sheet, form unit, and method for manufacturing a form unit according to the present invention, even if concrete adheres to the side of the form adjacent to the concrete pouring surface, the concrete can be easily peeled off. [Brief description of the drawings]
[0011] [Figure 1] Fig. 1A is a perspective view of a mold according to a first embodiment, and Fig. 1B is a bottom view of the mold. [Diagram 2] Fig. 2A is a plan view of the form sheet according to the embodiment, and Fig. 2B is a perspective view of the form sheet with ruled lines formed thereon. [Diagram 3] FIG. 3 is a perspective view of the form unit according to the embodiment of the present invention. [Figure 4] FIG. 4 is a partial perspective view of a form unit illustrating a temporary fixing step according to the embodiment. [Diagram 5] Fig. 5A is a partial perspective view of a form unit for explaining a fold line forming step according to the embodiment of the present invention, and Fig. 5B is a partial perspective view of the form unit in which a fold line has been formed by the fold line forming step according to the embodiment of the present invention. [Figure 6] FIG. 6 is a partial perspective view of the form unit for explaining the removing step according to the embodiment. [Figure 7] 7A is a perspective view of a form unit according to a second embodiment, FIG 7B is a cross-sectional view of the form unit, and FIG 7C is a perspective view including a cut surface of a hollow structure of the form unit. [Figure 8] FIG. 8 is a plan view of a form sheet according to a modified example. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] The present invention relates to a form sheet, a form unit, and a method for manufacturing the form unit, and more particularly to a resin form sheet that is attached to a wooden formwork having a concrete pouring surface and formwork sides, and a formwork to which the form sheet is attached. Hereinafter, the form sheet, form unit, and method for manufacturing the form unit according to the present invention will be described with reference to the embodiments shown in the attached drawings.
[0013] A form sheet, a form unit, and a method for manufacturing a form unit according to the first embodiment will be described with reference to Figures 1A to 6. First, the form will be described with reference to Figures 1A and 1B.
[0014] The formwork 1 is a wooden frame used when pouring concrete. Specifically, the formwork 1 is preferably made of solid wood, but may be made of a wooden material such as plywood or a fiberboard such as MDF (Medium Density Fiberboard). The formwork 1 has a concrete pouring surface 11 and a formwork side surface 12 that is adjacent to and intersects with the concrete pouring surface 11.
[0015] In the first embodiment, the formwork 1 has a dam board portion 13 and a crosspiece 14. The dam board portion 13 is a flat wooden plate. The dam board portion 13 has a rectangular shape when viewed from a direction perpendicular to the plate surface (referred to as a front view). One plate surface of the dam board portion 13 becomes the concrete pouring surface 11. The concrete pouring surface 11 is flat. The crosspiece 14 is attached to the plate surface opposite the concrete pouring surface 11 of the dam board portion 13 (referred to as a back surface).
[0016] The crosspiece 14 is made of a wooden rod-shaped member. The crosspiece 14 is attached to the ends along both long sides of the sheathing plate portion 13. The crosspiece 14 has a rectangular cross section perpendicular to the longitudinal direction, and one of the four sides, which is a flat surface, is attached to the back surface of the sheathing plate portion 13. The longitudinal length of the crosspiece 14 is formed to be the same as the length of the long side of the sheathing plate portion 13. The side surface adjacent to the long side of the concrete pouring surface 11 of the sheathing plate portion 13 and the side surface of the crosspiece 14 continuing to this side form a form side surface 121 on the long side. The side surface adjacent to the short side of the concrete pouring surface 11 of the sheathing plate portion 13 and the longitudinal end surface of the crosspiece 14 continuing to this side form a form side surface 122 on the short side. The form side surface 12 is a flat surface having a rectangular shape.
[0017] Next, the form sheet 2 will be described with reference to FIG. 2A.
[0018] The form sheet 2 is a resin sheet that mainly covers the concrete pouring surface 11 of the formwork 1. The form sheet 2 is attached to the formwork 1. In the first embodiment, the form sheet 2 is configured of a polypropylene sheet having a thickness of 0.4 mm. The form sheet 2 has a pouring surface facing portion 21 and a side surface facing portion 22.
[0019] The pouring surface facing portion 21 is a portion that faces the entire surface of the concrete pouring surface 11. The pouring surface facing portion 21 has a rectangular shape of the same shape and size as the concrete pouring surface 11. In other words, the pouring surface facing portion 21 corresponds to the concrete pouring surface 11 without excess or deficiency.
[0020] The side surface facing portion 22 is continuous with the pouring surface facing portion 21. The side surface facing portion 22 is a portion facing the formwork side surface 12. In the first embodiment, the side surface facing portion 22 is provided with a side surface facing portion 221 on the long side facing the formwork side surface 121 on the long side of the formwork 1, and a side surface facing portion 222 on the short side facing the formwork side surface 122 on the short side of the formwork 1.
[0021] In the first embodiment, the longitudinal length of the side surface facing portion 221 on the long side is formed to be the same as the longitudinal length of the formwork side surface 121 on the long side, and the longitudinal length of the side surface facing portion 222 on the short side is formed to be the same as the longitudinal length of the formwork side surface 122 on the short side. Also, the lateral length of the side surface facing portion 221 on the long side is formed to be the same as the lateral length of the formwork side surface 121 on the long side, and the lateral length of the side surface facing portion 222 on the short side is formed to be the same as the lateral length of the formwork side surface 122 on the short side. That is, the side surface facing portion 221 on the long side has a rectangular shape of the same shape and size as the formwork side surface 121 on the long side, and the side surface facing portion 222 on the short side has a rectangular shape of the same shape and size as the formwork side surface 122 on the short side. The area of the side surface facing portion 22 is the same as the area of the formwork side surface 12. The area of the side surface facing portion 22 may be smaller than the area of the side surface 12 of the formwork, and may be, for example, 80% or more and 95% or less of the area of the side surface 12 of the formwork.
[0022] The above-mentioned form sheet 2 is attached to the form 1 to form a form unit 3 shown in Fig. 3, which has the form 1 and the form sheet 2. A method for manufacturing the form unit 3 will be described.
[0023] The method for manufacturing the form unit 3 includes a step of preparing the form 1, a step of preparing the form sheet 2, and a step of attaching the form sheet 2.
[0024] (1) Formwork 1 preparation process The formwork 1 preparation process is a process of preparing the formwork 1 to be brought to the construction site. Preparing the formwork 1 means preparing a finished formwork 1 by manufacturing the formwork 1 or by acquiring the formwork 1 through purchase or the like. In the first embodiment, the formwork 1 preparation process is a process of manufacturing the formwork 1. This process includes a process of preparing the dam board portion 13, a process of preparing the crosspieces 14, and a process of attaching the crosspieces 14 to the dam board portion 13.
[0025] (1.1) Preparation process of the dam plate part 13 The preparation process of the dam board portion 13 is a process of forming the dam board portion 13 by cutting out a portion of a wooden board material having a predetermined shape and a predetermined size to become the dam board portion 13.
[0026] (1.2) Preparation process of crosspiece 14 The preparation process for the crosspiece 14 is a process in which a long rod-shaped member having the same cross-sectional shape as that of the crosspiece 14 is cut to a predetermined length to form the crosspiece 14. The order of the preparation process for the siding panel portion 13 and the preparation process for the crosspiece 14 is arbitrary, and these processes may be performed simultaneously.
[0027] (1.3) Step of attaching the crosspiece 14 to the dam plate portion 13 The process of attaching the crosspieces 14 to the sheathing plate portion 13 is a process of attaching the crosspieces 14 to predetermined positions on the back surface of the sheathing plate portion 13. The crosspieces 14 are attached to the sheathing plate portion 13, for example, by attaching the crosspieces 14 to the back surface of the sheathing plate portion 13 via an adhesive, thereby fixing the crosspieces 14 to the sheathing plate portion 13. Alternatively, nails are driven into the sheathing plate portion 13 from the concrete pouring surface 11 side, thereby attaching the crosspieces 14 to the back surface of the sheathing plate portion 13, and fixing the crosspieces 14 to the sheathing plate portion 13. There are no limitations on the method of attaching the crosspieces 14 to the sheathing plate portion 13. In this manner, the completed formwork 1 is obtained.
[0028] (2) Preparation process of formwork sheet 2 The process of preparing the form sheet 2 is a process of preparing the form sheet 2 to be brought to the construction site. In the first embodiment, the process of preparing the form sheet 2 includes a master shape creating process and a ruled line creating process.
[0029] (2.1) Prototype creation process The master form creation process is a process in which a portion of a predetermined shape and size that will become the form sheet 2 is cut out from a large resin sheet to create the portion that will become the master form of the form sheet 2. The master form creation process is performed by Thomson machining using a Thomson blade. Various Thomson machining devices are known for performing Thomson machining, and these can be used as appropriate, so a description thereof will be omitted.
[0030] The original part of the form sheet 2 includes a part that will become the pouring surface facing part 21 and a part that will become the side surface facing part 22. The original part of the form sheet 2 may be formed larger than the formwork 1 that is expected to be used so that it can accommodate formwork 1 of various shapes and sizes. Specifically, as shown in Fig. 2A, the original part of the form sheet 2 is formed in a substantially cross shape with the pouring surface facing part 21 at the center and side surface facing parts 22 on each side. In other words, it is formed in a rectangular shape with notches 28 formed in the four corners.
[0031] (2.2) Crease line creation process The scoring process is a process of forming scores 23 at the boundary between the adjacent side surface facing portion 22 and the casting surface facing portion 21 via the long side of the casting surface facing portion 21. The scoring process is performed by Thomson cutting using a special Thomson blade. The special Thomson blade has a rounded tip, not a sharp one. In Thomson cutting using such a special Thomson blade, the part that will become the original shape of the form sheet 2 is not cut, and a thin-walled portion that will become the score 23 is formed.
[0032] The crease 23 is formed at the boundary between the side surface facing portion 221 on one long side of the pouring surface facing portion 21 and the pouring surface facing portion 21, and at the boundary between the side surface facing portion 222 on one adjacent short side and the pouring surface facing portion 21, forming an L shape. The crease 23 is formed to make it easier to fold the side surface facing portion 22 relative to the pouring surface facing portion 21.
[0033] The scoring process using Thomson milling forms a form sheet 2 in which side surface facing portion 221 on one long side and side surface facing portion 222 on one short side are bent at scoring line 23 toward pouring surface facing portion 21, as shown in Fig. 2B. In this manner, form sheet 2 is obtained. Note that the order of the process of preparing form 1 and the process of preparing form sheet 2 may be arbitrary, and these processes may be performed simultaneously.
[0034] (3) Installation process The attaching step is a step of attaching the form sheet 2 to the form 1. In the first embodiment, the attaching step includes a temporary fixing step, a folding line forming step, a final fixing step, and a removing step.
[0035] (3.1) Temporary Fixation Process The temporary fixing step is a step of temporarily fixing the form sheet 2 at a predetermined position on the form 1. In this step, first, a double-sided tape (not shown) is attached to the surface of the casting surface facing portion 21 of the form sheet 2 facing the concrete casting surface 11. Next, as shown in FIG. 4, the position of the corner of the L-shaped ruled line 23 is aligned with the position of the corner of the concrete casting surface 11. In this case, the side surface facing portion 221 on the long side and the side surface facing portion 222 on the short side, which are bent relative to the casting surface facing portion 21, are brought into contact with the formwork side surface 121 on the long side and the formwork side surface 122 on the short side, respectively, so that the alignment can be easily performed. In other words, the side surface facing portion 221 on the long side and the side surface facing portion 222 on the short side function as guides for alignment.
[0036] After alignment, the pouring surface facing part 21 is attached to the concrete pouring surface 11 using double-sided tape. The line 23 (see FIG. 2B ) between the side surface facing part 221 on the long side and the pouring surface facing part 21 is aligned with one long side of the concrete pouring surface 11, and the line 23 between the side surface facing part 222 on the short side and the pouring surface facing part 21 is aligned with one short side of the concrete pouring surface 11.
[0037] (3.2) Folding line forming process The fold line forming process is a process of forming fold lines 24 along the long and short sides of the casting surface facing portion 21 on the side where the crease 23 is not formed. The fold lines 24 are formed to make it easier to fold the side surface facing portion 22 relative to the casting surface facing portion 21, similar to the crease 23. As shown in Fig. 5A, the fold lines 24 are formed by a worker using a scribing tool 25. A commonly used scribing needle is used as the scribing tool 25.
[0038] The worker places the form sheet 2 on the workbench so that the form 1 is on the upper side. Then, along the long side and short side of the casting surface facing portion 21 on the side where the crease 23 is not formed, the crease is made with the crease tool 25, using the form side 121 on the long side and the form side 122 on the short side as guides, to form the fold line 24. As a result, as shown in FIG. 5B, either the crease 23 or the fold line 24 is formed over the entire circumference of the casting surface facing portion 21. The side surface facing portion 22 that is bent at the crease 23 is bent more than the side surface facing portion 22 that is bent at the fold line 24, and has a smaller R. If neither the crease 23 nor the fold line 24 is formed at the boundary between the casting surface facing portion 21 and the side surface facing portion 22, the worker will have to fold the flat portion of the form sheet 2 by hand at the construction site. In this case, the formwork sheet 2 will not conform to the concrete pouring surface 11 and formwork side surface 12 of the formwork 1, and the concrete pouring surface 11 and the pouring surface facing portion 21 of the formwork sheet 2 will be misaligned, which is undesirable because it may result in gaps being formed between the concrete pouring surface 11 and the pouring surface facing portion 21 or wrinkles being formed in the pouring surface facing portion 21.
[0039] (3.3) Main fixing process The main fixing process is a process for permanently fixing the form sheet 2 to the formwork 1. In the temporary fixing process, the form sheet 2 is fixed to the formwork 1 with double-sided tape, whereas in the main fixing process, a stapler (not shown) is used to drive staples 26 (see FIG. 3) into the formwork 1 through the form sheet 2, thereby fixing the form sheet 2 to the formwork 1.
[0040] (3.4) Removal process The removing step is a step of cutting off the excess part of the form sheet 2 fixed to the form 1. In the first embodiment, the excess part of the form sheet 2 refers to a part that does not follow the surface of the form 1. As shown in FIG. 6, the worker cuts the form sheet 2 with a cutting tool 27. Specifically, a part of the side surface facing part 222 on the short side is cut off with the cutting tool 27 made of a cutter knife. Here, the worker cuts the side surface facing part 222 on the short side with the cutting tool 27 using the end of the dam board part 13 and the end of the crosspiece 14 as guides to remove the unnecessary part. The side surface facing part 22 may be formed in a part that is 40 cm or more and 60 cm or less, preferably 45 cm or more and 55 cm or less, from the upper end (side adjacent to the concrete pouring surface 11) of the form side surface 12 of the form 1. The part where the side surface facing part 221 on the folded long side and the side surface facing part 222 on the short side overlap is cut off so that they do not overlap. In other words, when the side surface facing portion 221 on the long side and the side surface facing portion 222 on the short side overlap, the thickness increases at the overlapping portion, and when the formwork units 3 are arranged side by side, gaps are likely to occur between these formwork units 3, which is not preferable.
[0041] Through the above steps, the mounting process is completed and the finished form unit 3 shown in Fig. 3 is manufactured. In the form unit 3 of the first embodiment, the side surface facing portions 22 of the form sheet 2 cover the form side surfaces 12 of the form 1, so that it is possible to prevent concrete from entering between the juxtaposed form units 3 and coming into direct contact with the form side surfaces 12, which would make it difficult to peel the concrete from the form side surfaces 12. Even if concrete adheres to the form sheet 2 and hardens, the resin has good releasability from the concrete (at least when compared with releasability from wood or wood-based materials), so the concrete has good releasability from the form unit 3. For this reason, whereas in the past concrete adhering to the concrete pouring surface 11 and the side surface 12 of the formwork 1 was scraped off with a spatula, in the first embodiment concrete adhering to the resin pouring surface facing portion 21 and the side surface facing portion 22 can be wiped off with a towel or the like, making it easy to peel the concrete off the formwork unit 3 and also making the formwork unit 3 less likely to be scratched. If the formwork unit is scratched, the scratched area can be repaired with a sealant. Furthermore, corrosion of the wooden formwork 1 is prevented, allowing the formwork 1 to be used for a long period of time.
[0042] In addition, when the form units 3 are arranged side by side, it is preferable to provide a resin sealant between the opposing side surface portions 12. This can prevent concrete from entering between the form units 3 arranged side by side and coming into direct contact with the form side surface 12, which makes it difficult for the concrete to peel off from the form side surface 12.
[0043] In addition, since chipping of the outer periphery of the concrete pouring surface 11 of the formwork 1 can be prevented, when multiple formworks 1 are arranged side by side, gaps caused by chipping of the outer periphery of the concrete pouring surface 11 are less likely to occur between the formworks 1, and concrete is prevented from easily getting between the formworks 1.
[0044] Since the linear expansion coefficient and dimensional tolerances of the wooden formwork 1 and the resin formwork sheet 2 are different due to the difference in material, if the formwork sheet 2 is pre-processed with ruled lines 23 and then attached to the formwork 1, there is a risk that the concrete pouring surface 11 and the opposing pouring surface 21 will be slightly misaligned. For this reason, it is necessary to attach the formwork sheet 2 to each formwork 1. In addition, since the degree of linear expansion differs depending on the season, it is necessary to attach the formwork sheet 2 to each formwork 1.
[0045] Moreover, the area of the side surface facing portion 22 is the same as the area of the formwork side surface 12, and the side surface facing portion 22 covers the entire surface of the formwork side surface 12, reliably preventing concrete from adhering to the formwork side surface 12. Moreover, since there are no parts of the side surface facing portion 22 that do not cover the formwork side surface 12 and are left floating in the air, the formwork unit 3 can be easily handled.
[0046] In addition, since the ruled lines 23 are formed in advance at the boundary between the pouring surface facing portion 21 and the side surface facing portion 22, it is easy to prevent the formwork sheet 2 from floating up from the formwork 1 without conforming to the surface of the formwork 1.
[0047] Furthermore, since the ruled line 23 is L-shaped, the side surface facing portion 221 on the long side and the side surface facing portion 222 on the short side function as guides, making it easy to align the pouring surface facing portion 21 so that it overlaps the concrete pouring surface 11.
[0048] Next, a second embodiment will be described with reference to Figures 7A to 7C. Note that since the second embodiment is mostly the same as the first embodiment, the description of parts that overlap with the first embodiment will be omitted, and the description will be focused mainly on parts that differ from the first embodiment.
[0049] In the first embodiment, the crosspieces 14 are attached only to the ends along both long sides of the sheathing board portion 13, whereas in the second embodiment, the crosspieces 14 are attached to the ends along both long sides and short sides of the sheathing board portion 13 to form a square shape. This improves the rigidity and strength of the form unit 3.
[0050] In the first embodiment, the area of the side surface facing portion 22 is the same as the area of the formwork side surface 12, whereas in the second embodiment, the area of the side surface facing portion 22 is 80% or more and 95% or less of the area of the formwork side surface 12. In this way, by making the area of the side surface facing portion 22 95% or less of the area of the formwork side surface 12, no excess portion is formed on the formwork sheet 2 fixed to the formwork 1, and the removal step required in the first embodiment is not required. Furthermore, by making the area of the side surface facing portion 22 80% or more of the area of the formwork side surface 12, it is possible to make it difficult for concrete to adhere to the formwork side surface 12, and the formwork unit 3 can maintain good releasability of the concrete.
[0051] The formwork unit 3 has a resin hollow structure 4 between the concrete pouring surface 11 and the pouring surface facing portion 21. As shown in FIG. 7C, the hollow structure 4 has a core layer 41 having a honeycomb structure and skin layers 42 formed on both sides of the core layer 41 by welding or the like. As such a hollow structure 4, various known hollow structures can be appropriately used, and detailed description will be omitted. The formwork unit 3 has the hollow structure 4, so that the heat retention of the formwork unit 3 can be improved when curing the poured concrete.
[0052] Next, a modified example will be described.
[0053] The formwork 1 may contain materials other than wood and wood-based materials, for example, it may have a resin coating on all or part of the concrete pouring surface 11, but wood and wood-based materials are exposed on at least a portion of the formwork side surface 12.
[0054] The dam plate portion 13 (concrete pouring surface 11) does not have to be rectangular when viewed from the front, and may be, for example, a square or any other shape other than a rectangle, and the shape is not limited.
[0055] The concrete pouring surface 11 does not have to be flat.
[0056] The crosspiece 14 may be attached only to the end along the short side of the dam plate portion 13. The cross section of the crosspiece 14 does not have to be rectangular, and may be, for example, a square or any other shape other than a quadrangle, and is not limited to this shape. The longitudinal length of the crosspiece 14 does not have to be the same as the length of the side of the dam plate portion 13.
[0057] The formwork side surface 12 does not have to be rectangular, and does not have to be flat.
[0058] The form sheet 2 may be made of a transparent resin sheet, or may be made of a translucent or opaque resin sheet. As the material of the form sheet 2, other than polypropylene, for example, polyethylene, polyethylene terephthalate, vinyl chloride, fluororesin, silicone-added resin, etc. are preferably used, but are not limited to these. The thickness of the form sheet 2 is not particularly limited, but is preferably 0.3 mm or more and 1.0 mm or less, and more preferably 0.4 mm or more and 0.8 mm or less.
[0059] When storing or transporting the form sheet 2, several form sheets 2 may be stacked and bundled by hanging a string or the like through the notches 28 (see FIG. 2A) at diagonal positions. Furthermore, several bundles of form sheets 2 bundled in this manner may be stacked on top of each other. Since each form sheet 2 is flat, the bundle of form sheets 2 can be laid so that the upper surface is approximately horizontal, and even if several bundles are stacked, they are unlikely to collapse.
[0060] The pouring surface facing portion 21 does not have to completely correspond to the concrete pouring surface 11, and does not have to cover a portion of the concrete pouring surface 11.
[0061] When viewed from the front, the pouring surface facing portion 21 does not have to be rectangular, but may be, for example, a square or a shape other than a rectangle, and the shape is not limited, but has a shape and size corresponding to the concrete pouring surface 11.
[0062] The side surface facing portion 22 does not have to be rectangular when viewed from the front, and may be, for example, a square or any other shape other than a rectangle, and the shape is not limited.
[0063] The area of the side surface facing portion 22 relative to the area of the formwork side surface 12 is not limited.
[0064] FIG. 8 shows a modified form of the form sheet 2. In this modified form, the form sheet 2 has lines 23 formed to fit two sizes of formwork 1. First, a first line 231 is formed to fit the larger formwork 1. This is generally the same as the formwork 1 in the first embodiment, which is replaced by the larger formwork 1 in this modified form. However, the form sheet 2 in the first embodiment has lines 23 formed in an L-shape on two sides of the portion 21 facing the casting surface, as shown in FIG. 2A, whereas the form sheet 2 in this modified form has lines 23 formed on all four sides of the portion 21 facing the casting surface. Furthermore, the form sheet 2 in the first embodiment has notches 28 formed at the four corners, whereas the form sheet 2 in this modified form has notches formed at only one of the four corners.
[0065] Then, a second score line 232 is formed to fit the smaller formwork 1. The second score line 232 is formed in a portion that corresponds to an edge of the formwork 1 when one corner of the smaller formwork 1 is aligned with one of the four corners of the casting surface facing portion 21 where the notch 28 is formed. However, the second score line 232 is not formed in the casting surface facing portion 21, but is formed only in the side surface facing portion 22. This makes it possible to accommodate formwork 1 of two different sizes.
[0066] Also, in the outer periphery of the form sheet 2, a folding line 24 may be provided in accordance with the size of the form 1, and a notch (slit) may be provided to facilitate bending.
[0067] In the master form creation step, a sheet of a predetermined size may be cut out from a sheet roll and punched with a Thomson blade to create the master form of the form sheet 2. At this time, multiple sheets may be stacked and punched with the Thomson blade to simultaneously create multiple master forms of the form sheet 2. Also, the sheet may be punched with a press die instead of a Thomson blade to create the master form of the form sheet 2.
[0068] The step of creating the scoring lines does not have to be performed by Thomson machining using a Thomson blade, and may be performed by other methods.
[0069] The above-mentioned method for manufacturing the form unit 3 is an example, and the method for manufacturing the form unit 3 is not limited to the above-mentioned method.
[0070] In the temporary fixing step, the form sheet 2 is temporarily fixed to the form 1 by using a double-sided tape, and instead, for example, an adhesive may be used, and the method of temporary fixing is not limited. In addition, the temporary fixing step is an optional step, and does not have to be included in the installation step.
[0071] As the scribing tool 25, various tools such as the back of a cutter knife can be appropriately used instead of a scribing needle, and there is no particular limitation.
[0072] In the final fixing step, the form sheet 2 is fixed to the form 1 without using the staples 26. Instead, for example, an adhesive may be used, and the method of final fixing is not limited.
[0073] In the removing step, the method of cutting the form sheet 2 is not limited to the method of cutting with a cutter knife.
[0074] As is clear from the embodiments and modifications described above, the first aspect is a resin formwork sheet 2 attached to a wooden formwork 1 having a concrete pouring surface 11 and a formwork side surface 12 that is adjacent to and intersects with the concrete pouring surface 11. The formwork sheet 2 comprises a pouring surface facing portion 21 that faces the entire surface of the concrete pouring surface 11, and a side surface facing portion 22 that is continuous with the pouring surface facing portion 21 and faces the formwork side surface 12.
[0075] According to the first aspect, the side surface opposing portion 22 covers the formwork side surface 12, thereby preventing concrete from adhering directly to the formwork side surface 12 and preventing the concrete from becoming difficult to peel off from the formwork side surface 12, and making it easy to peel off the concrete adhered to the formwork sheet 2.
[0076] The second aspect can be realized by combining with the first aspect. In the second aspect, the area of the side surface facing portion 22 is 80% or more and 95% or less of the area of the side surface 12 of the formwork.
[0077] According to the second aspect, by making the area of the side surface facing portions 22 95% or less of the area of the formwork side surface 12, excess portions of the formwork sheet 2 fixed to the formwork 1 are unlikely to be formed, and there is no need to remove the excess portions. Also, by making the area of the side surface facing portions 22 80% or more of the area of the formwork side surface 12, concrete is unlikely to adhere to the formwork side surface 12, and good releasability of the concrete can be maintained.
[0078] The third aspect can be realized by combining with the first or second aspect. In the third aspect, the pouring surface facing part 21 has a rectangular shape.
[0079] The formwork sheet 2 has a ruled line 23 at the boundary between the adjacent side surface facing portion 22 and the pouring surface facing portion 21 via the long side of the pouring surface facing portion 21.
[0080] According to the third aspect, it is easy to prevent the form sheet 2 from floating up from the form 1 without fitting along the surface of the form 1 .
[0081] The fourth embodiment can be realized by combining with the first or second embodiment. In the fourth embodiment, the pouring surface facing portion 21 has a rectangular shape. The formwork sheet 2 has an L-shaped ruled line 23 consisting of a boundary between the side surface facing portion 22 and the pouring surface facing portion 21 adjacent to each other through the long side of the pouring surface facing portion 21, and a boundary between the side surface facing portion 22 and the pouring surface facing portion 21 adjacent to each other through the short side of the pouring surface facing portion 21.
[0082] According to the fourth aspect, in addition to making it easier to prevent the formwork sheet 2 from floating away from the formwork 1 rather than conforming to the surface of the formwork 1, the side facing portion 22 functions as an alignment guide, making it easier to align the pouring surface facing portion 21 so that it overlaps the concrete pouring surface 11.
[0083] The fifth embodiment is a wooden formwork 1 to which a resin formwork sheet 2 is attached. The formwork 1 has a concrete pouring surface 11 and a formwork side surface 12 that is adjacent to and intersects with the concrete pouring surface 11. The formwork sheet 2 has a pouring surface facing portion 21 that faces the entire surface of the concrete pouring surface 11, and a side surface facing portion 22 that is continuous with the pouring surface facing portion 21 and faces the formwork side surface 12.
[0084] According to the fifth aspect, the side surface opposing portion 22 covers the formwork side surface 12, thereby preventing concrete from adhering directly to the formwork side surface 12 and preventing concrete from being difficult to peel off from the formwork side surface 12, and making it possible to easily peel off the concrete adhering to the formwork sheet 2 from the formwork unit 3.
[0085] The sixth aspect can be realized by combining with the fifth aspect. In the sixth aspect, the formwork 1 has a hollow structure made of resin between the concrete pouring surface 11 and the portion 21 facing the pouring surface.
[0086] According to the sixth aspect, it is possible to improve the heat retention of the form unit 3 when the poured concrete is cured.
[0087] The seventh aspect is a manufacturing method for a form unit 3 including a wooden form 1 and a resin form sheet 2 attached to the form 1. The form 1 has a concrete pouring surface 11 and a form side surface 12 that is adjacent to the concrete pouring surface 11 and intersects with the concrete pouring surface 11. The form sheet 2 has a pouring surface facing portion 21 that faces the entire surface of the concrete pouring surface 11, and a side surface facing portion 22 that is continuous with the pouring surface facing portion 21 and faces the form side surface 12.
[0088] The manufacturing method of the formwork unit 3 includes a temporary fixing step and a fold line forming step. The temporary fixing step is a step of temporarily fixing the formwork sheet 2 at a predetermined position of the formwork 1. The fold line forming step is a step of forming a fold line 24 at the boundary between the casting surface facing portion 21 and the side surface facing portion 22.
[0089] According to the seventh aspect, it is possible to prevent a worker from folding the flat portion of the form sheet 2 by hand, which would cause the form sheet 2 to float above the formwork 1. In addition, since the fold lines 24 can be formed at the construction site, the form sheet 2 can be folded to fit formwork 1 of various sizes.
[0090] The eighth embodiment can be realized by combining with the seventh embodiment. In the eighth embodiment, the pouring surface facing portion 21 has a rectangular shape and has an L-shaped ruled line 23 consisting of a boundary between the side surface facing portion 22 and the pouring surface facing portion 21 adjacent to each other through the long side of the pouring surface facing portion 21 and a boundary between the side surface facing portion 22 and the pouring surface facing portion 21 adjacent to each other through the short side of the pouring surface facing portion 21. In the temporary fixing step, when the pouring surface facing portion 21 is aligned so as to overlap with the concrete pouring surface 11, the side surface facing portion 22 bent relative to the pouring surface facing portion 21 at the ruled line 23 is brought into contact with the formwork side surface 12, and the side surface facing portion 22 serves as a guide.
[0091] According to the eighth aspect, it is easy to align the pouring surface facing portion 21 so that it overlaps the concrete pouring surface 11. [Explanation of symbols]
[0092] 1 Formwork 11 Concrete casting surface 12 Formwork side 121 Long side of formwork 122 Short side of formwork 13 Weir plate section 14 Crosspiece 2 Formwork sheets 21. Concrete surface facing part 22 Side facing part 221 Side facing part on long side 222 Side facing part on the short side 23 Ruled Lines 24 fold line 25 Scribing tool 26 Staples 27 Cutting tools 28 Notch 3 Formwork Unit 4 Hollow structure 41 Core layer 42 Skin Layer
Claims
1. A resin form sheet attached to a wooden form having a concrete pouring surface and a form side adjacent to the concrete pouring surface and intersecting the concrete pouring surface, A pouring surface facing portion facing the entire concrete pouring surface; A side surface facing portion that faces the formwork side surface and is continuous with the pouring surface facing portion, The casting surface facing portion has a rectangular shape, The boundary between the side facing portion and the casting surface facing portion adjacent to each other through the long side of the casting surface facing portion and the boundary between the side facing portion and the casting surface facing portion adjacent to each other through the short side of the casting surface facing portion are formed into an L-shaped ruled line, An L-shaped fold line is formed along the long side and the short side of the pouring surface facing portion on the side where the crease is not formed, The radius of curvature of the portion of the side facing portion that is bent at the crease is smaller than the radius of curvature of the portion that is bent at the fold line. Formwork sheet.
2. The area of the side facing portion is 80% or more and 95% or less of the area of the side surface of the formwork. The formwork sheet according to claim 1.
3. A formwork unit comprising a wooden formwork and a resin formwork sheet attached to the formwork, The formwork has a concrete pouring surface and a formwork side surface adjacent to the concrete pouring surface and intersecting the concrete pouring surface, The form sheet has a pouring surface facing portion that faces the entire surface of the concrete pouring surface, and a side facing portion that faces the form side surface and is continuous with the pouring surface facing portion, The casting surface facing portion has a rectangular shape, The boundary between the side facing portion and the casting surface facing portion adjacent to each other through the long side of the casting surface facing portion and the boundary between the side facing portion and the casting surface facing portion adjacent to each other through the short side of the casting surface facing portion are formed into an L-shaped ruled line, An L-shaped fold line is formed along the long side and the short side of the pouring surface facing portion on the side where the crease is not formed, The radius of curvature of the portion of the side facing portion that is bent at the crease is smaller than the radius of curvature of the portion that is bent at the fold line. Formwork unit.
4. A hollow structure made of resin is provided between the concrete pouring surface and the portion facing the pouring surface. The formwork unit according to claim 3.
5. A method for manufacturing a form unit including a wooden form and a resin form sheet attached to the form, comprising: The formwork has a concrete pouring surface and a formwork side surface adjacent to the concrete pouring surface and intersecting the concrete pouring surface, The formwork sheet has a pouring surface facing portion that faces the entire surface of the concrete pouring surface, and a side facing portion that faces the formwork side surface and is continuous with the pouring surface facing portion, The manufacturing method includes a folding line forming step, The bend line forming step is a step of forming a bend line at the boundary between the pouring surface facing portion and the side facing portion, The pouring surface facing portion has a rectangular shape and has an L-shaped ruled line consisting of a boundary between the side facing portion and the pouring surface facing portion adjacent to each other through a long side of the pouring surface facing portion, and a boundary between the side facing portion and the pouring surface facing portion adjacent to each other through a short side of the pouring surface facing portion, When the pouring surface facing portion is aligned so as to overlap the concrete pouring surface, the side facing portion bent toward the pouring surface facing portion at the ruled line is placed against the side surface of the formwork, and the side facing portion is used as a guide. Manufacturing method of formwork units.
Citation Information
Patent Citations
JP1980044959U
Sheathing board for concrete formwork
JP1990153163A
Concrete formwork
JP1994054840U
Concrete placing form, and form sheet
JP1996326308A
Sheet for mcr construction method and fitting method thereof
JP1999093407A