Vertical displacement measuring tool and vertical displacement measuring method for cement-based materials

The jig with a rod-shaped member and edge-cutting member allows for accurate vertical displacement measurement of cement-based materials by adhering to the cement and following its displacement, addressing the adhesion breakage issue in existing methods.

JP7589919B2Active Publication Date: 2024-11-26KAJIMA CORP +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2021141869
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-08-31
Publication Date
2024-11-26
Estimated Expiration
2041-08-31

AI Technical Summary

Technical Problem

Existing methods for measuring vertical displacement of cement-based materials, such as soil-cement walls, fail to accurately measure vertical displacement independently of the core material due to potential adhesion breakage between the cement and core materials, especially under weight-induced stress.

Method used

A jig comprising an outer tube attached to a core material with a rod-shaped member and an edge-cutting member is used to penetrate and adhere to the cement-based material, allowing for independent measurement of vertical displacement by ensuring the rod-shaped member follows the cement's displacement without being restrained by the surrounding solidified cement.

Benefits of technology

Accurately measures vertical displacement of cement-based materials by preventing adhesion breakage and ensuring the rod-shaped member follows the cement's displacement, thereby providing reliable measurement data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007589919000001
    Figure 0007589919000001
  • Figure 0007589919000002
    Figure 0007589919000002
  • Figure 0007589919000003
    Figure 0007589919000003
Patent Text Reader

Abstract

To measure the vertical displacement of a cement-based material.SOLUTION: A vertical displacement measurement jig 100 for a cement-based material 1 comprises: an outer tube 10 which is attached to a core material 2 along an insertion direction of the core material 2; a rod-shaped member 20 which is movably inserted into the outer tube 10 and whose tip portion 21 protruding from the outer tube 10 penetrates the unhardened cement-based material 1; and an edge cutting member 30 which is provided across a tip portion 11 of the outer tube 10 and the tip portion 21 of the rod-shaped member 20 to cut off the rod-shaped member 20 from the cement-based material 1. As the cement-based material 1 solidifies, the tip portion 21 of the rod-shaped member 20 adheres to the cement-based material 1, and the vertical displacement of the rod-shaped member 20 is measured as the vertical displacement of the cement-based material 1.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a jig for measuring vertical displacement of a cement-based material and a method for measuring vertical displacement. [Background technology]

[0002] Underground structures such as earth retaining walls may be displaced vertically and horizontally due to excavation, installation of supports such as struts and ground anchors, and the weight of structures constructed above ground, and in such cases, it is necessary to measure the displacement of the underground structures. For example, Patent Document 1 discloses a method for measuring the out-of-plane horizontal displacement of an earth retaining wall consisting of a soil cement wall and a core material. In the method disclosed in Patent Document 1, a core material to which multiple detectors are attached in advance is driven into an unsolidified soil cement wall formed underground to construct the earth retaining wall, and the detectors are used to measure the out-of-plane horizontal displacement of the earth retaining wall. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-197082 A Summary of the Invention [Problem to be solved by the invention]

[0004] In the method disclosed in Patent Document 1, a detection unit is attached to a core material, and the displacement measured by the detection unit is the displacement of the core material.

[0005] However, in soil cement walls constructed to be one piece, the adhesion between the cementitious material and the core material may break due to the weight of the structure, etc. The method disclosed in Patent Document 1 is for measuring the horizontal displacement of the retaining wall, so in horizontal measurements, the break in adhesion between the cementitious material and the core material is not thought to have a significant effect on the horizontal measurement results. However, in measuring vertical displacement caused by the weight of the structure, the break in adhesion between the cementitious material and the core material means that the cementitious material and the core material are displaced independently, and so there is an effect. For this reason, when the measurement target is vertical displacement, it is required to measure the vertical displacement of the cementitious material in the underground structure independently of the displacement of the core material. If the adhesion breaks, the vertical displacement of the soil cement cannot be measured by the method in which the detector is attached to the core material. [Means for solving the problem]

[0006] The present invention aims to measure the vertical displacement of cement-based materials.

[0007] The present invention relates to a jig used for measuring the vertical displacement of a cement-based material in an underground structure comprising a cement-based material underground and a core material inserted into the cement-based material, the jig comprising an outer tube attached to the core material along the insertion direction of the core material, a rod-shaped member that is inserted movably into the outer tube and has a tip that protrudes from the outer tube and penetrates into the unsolidified cement-based material, and an edge-cutting member that is provided between the tip of the outer tube and the tip of the rod-shaped member and cuts the rod-shaped member off from the cement-based material, and as the cement-based material solidifies, the tip of the rod-shaped member adheres to the cement-based material, and the vertical displacement of the rod-shaped member is measured as the vertical displacement of the cement-based material.

[0008] The present invention also provides a method for measuring the vertical displacement of a cement-based material in an underground structure comprising a cement-based material in the ground and a core material inserted into the cement-based material, using the above-mentioned vertical displacement measuring jig, the method comprising: an attachment step of attaching an outer pipe to the core material along the insertion direction of the core material; a core material inserting step of inserting the core material into unsolidified cement-based material in the ground; a rod-shaped member penetrating step of moving a rod-shaped member relative to the outer pipe and penetrating a tip end of the rod-shaped member into the unsolidified cement-based material; and a measurement step of measuring the vertical displacement of the rod-shaped member as the vertical displacement of the cement-based material after solidification of the cement-based material. Effect of the Invention

[0009] According to the present invention, the vertical displacement of a cement-based material can be measured. [Brief description of the drawings]

[0010] [Figure 1] FIG. 13 is a diagram for explaining the construction procedure of an earth retaining wall. [Diagram 2] FIG. 2 is a schematic diagram of a vertical displacement measuring jig for a cement-based material according to an embodiment of the present invention, showing a cross section taken along line II-II shown in FIGS. [Diagram 3] 1A and 1B are diagrams for explaining a method for measuring vertical displacement of cement-based materials according to an embodiment of the present invention, in which (a) is a cross-sectional view of a vertical displacement measuring jig in an installation process, and (b) is a cross-sectional view of a vertical displacement measuring jig in a core material insertion process. [Figure 4] FIG. 4 is a diagram for explaining a modified example of the embodiment of the present invention, and corresponds to FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] Hereinafter, a method for measuring vertical displacement of a cement-based material and a vertical displacement measuring jig according to an embodiment of the present invention will be described with reference to the drawings. Here, a case will be described in which the cement-based material is soil cement 1 in an earth retaining wall (underground structure) W. The earth retaining wall W is constructed to prevent the collapse of the ground during construction work for a structural part including a basement floor, for example.

[0012] First, the construction procedure of the earth retaining wall W will be described with reference to Fig. 1. Fig. 1 is a diagram for explaining the construction procedure of the earth retaining wall W. Fig. 1(a) and (c) are plan views of the earth retaining wall W in the construction process of the earth retaining wall W, and Fig. 1(b) and (d) are cross-sectional views taken along the IB-IB line and the ID-ID line shown in Fig. 1(a) and (c), respectively.

[0013] 1(a) and 1(b), in constructing the retaining wall W, first, cement slurry is injected into the ground while excavating the ground, and the in-situ soil and the cement slurry are mixed to generate soil cement 1 in the ground. A kneading auger (not shown) is used to excavate the ground, inject the cement slurry, and mix the in-situ soil and the cement slurry.

[0014] Next, as shown in Figures 1(c) and (d), the core material 2 is inserted (built into) the unsolidified soil cement 1. A crane (not shown) is used to insert the core material 2. The core material 2 is, for example, an H-shaped steel. This completes the construction of the retaining wall W. The soil cement 1 of the retaining wall W solidifies over time and develops strength.

[0015] The vertical force acting on the soil cement 1 due to the weight of the above-ground structure flows into the ground surrounding the soil cement 1. When a vertical force flows into the surrounding ground, the vertical force borne by the soil cement 1 itself decreases accordingly as the depth increases. Therefore, the vertical displacement of the soil cement 1 decreases the deeper it is. To confirm that the load of the above-ground structure acts on the soil cement 1 and that the planned vertical support performance is being obtained, it is necessary to understand the local vertical displacement of the soil cement 1. Furthermore, understanding the local vertical displacement of the soil cement 1 contributes to the construction of a design model for the earth retaining wall W, enabling a more rational design of the earth retaining wall W. It can also be confirmed whether the integrity of the core material 2 and the soil cement 1 is maintained.

[0016] This embodiment is used to measure the vertical displacement of the soil cement 1 locally.

[0017] The vertical displacement measuring jig 100 of the soil cement 1 will be described with reference to Fig. 2. Fig. 2 is a schematic diagram 100 of the vertical displacement measuring jig 100, showing a cross section along the line II-II shown in Figs. 1(c) and (d). Note that the vertical displacement measuring jig 100 is omitted in Fig. 1. The vertical displacement measuring jig 100 is inserted into the soil cement 1 together with the core material 2.

[0018] As shown in Figure 2, the vertical displacement measuring jig 100 comprises an outer tube 10 attached to the core material 2 along the insertion direction of the core material 2, a rod-shaped member 20 inserted into the outer tube 10 so as to be freely movable in the insertion direction of the core material 2 and having a tip 21 protruding from the outer tube 10, and an edge cutting member 30 provided across the tip 11 of the outer tube 10 and the tip 21 of the rod-shaped member 20.

[0019] The outer pipe 10 comprises a plurality of pipe bodies 12 connected in series. One end of each of the pipe bodies 12 is formed with a female thread (pipe body connecting mechanism), and the other end is formed with a male thread (pipe body connecting mechanism). Adjacent pipe bodies 12 are connected to each other by screwing the female thread of one pipe body 12 with the male thread of the other pipe body 12. Therefore, pipe bodies 12 can be easily extended, and the outer pipe 10 can be easily lengthened. Therefore, the tip portion 11 of the outer pipe 10 can reach a depth that cannot be reached by a single pipe body 12.

[0020] The connection between the tubes 12 is not limited to the engagement between a female thread and a male thread. For example, the tubes 12 may be connected to each other by providing a female socket at one end of the tubes 12 and a male socket at the other end, and engaging the female socket with the male socket. The tubes 12 may also be connected to each other without engaging the female socket.

[0021] The rod-shaped member 20 comprises a plurality of rod bodies 22 connected in series. One end of each rod body 22 is formed with a female thread (rod body connecting mechanism), and the other end is formed with a male thread (rod body connecting mechanism). Adjacent rod bodies 22 are connected to each other by screwing the female thread of one rod body 22 with the male thread of the other rod body 22. Therefore, rod bodies 22 can be easily added, and the rod-shaped member 20 can be easily lengthened. Therefore, the tip portion 21 of the rod-shaped member 20 can reach a depth that cannot be reached by a single rod body 22.

[0022] The connection between the rod bodies 22 is not limited to the screwing of a female thread and a male thread. For example, the rod bodies 22 may be connected to each other by providing a female socket at one end of the rod body 22 and a male socket at the other end, and fitting the female socket to the male socket. The rod bodies 22 may also be connected to each other without fitting.

[0023] The rod 22 may be solid or hollow.

[0024] The rod-shaped member 20 is separated from the soil cement 1 around the outer pipe 10 by the outer pipe 10. Therefore, the vertical displacement of the rod-shaped member 20 is not restricted by the solidified soil cement 1 around the outer pipe 10.

[0025] The tip 21 of the rod-shaped member 20 is attached to the soil cement 1. Therefore, the tip 21 is displaced vertically together with the soil cement 1 around the tip 21 after the soil cement 1 hardens.

[0026] The tip 21 has an adhesion strengthening portion that strengthens the adhesion with the soil cement 1. The adhesion strengthening portion is, for example, a portion that is formed wider than the rod body 22 in a direction perpendicular to the moving direction of the rod-shaped member 20, and the manner of spreading can be various. This makes it difficult for the tip 21 to be cut off from the soil cement 1, and it is possible to more reliably displace vertically together with the soil cement 1 around the tip 21. The adhesion strengthening portion that strengthens the adhesion between the tip 21 and the soil cement 1 may be a groove or protrusion formed on the outer surface of the tip 21 and extending around an axis along the insertion direction of the core material 2, a groove or protrusion provided in the insertion direction of the core material 2, or an L-shaped shape. Furthermore, the adhesion strengthening portion may be strengthened not only by the shape but also by attaching or applying an adhesive material.

[0027] The cutting member 30 surrounds the rod-shaped member 20, and cuts off the rod-shaped member 20 from the soil cement 1 around the cutting member 30. Therefore, the vertical displacement of the rod-shaped member 20 is not restricted by the solidified soil cement 1 around the cutting member 30.

[0028] Moreover, the edge cutting member 30 has elasticity and expands and contracts in accordance with the vertical displacement of the tip portion 21 of the rod-shaped member 20 relative to the outer tube 10. Therefore, the vertical displacement of the rod-shaped member 20 is not restricted by the edge cutting member 30. The edge cutting member 30 is, for example, a rubber member or a bellows-shaped member.

[0029] The cut-off member 30 is not limited to a member having elasticity. For example, it may be a member such as vinyl that does not have elasticity, or it may be a coating material that can cut off the soil cement 1.

[0030] In this manner, in the vertical displacement measuring jig 100, the rod-shaped member 20 is separated from the soil cement 1 by the outer pipe 10 and the separation member 30. Therefore, the rod-shaped member 20 is not constrained by the soil cement 1 around the outer pipe 10 and the separation member 30, and is displaced vertically together with the soil cement 1 around the tip 21 of the rod-shaped member 20. Therefore, by measuring the vertical displacement of the rod-shaped member 20 using, for example, a displacement meter 3 installed above the vertical displacement measuring jig 100, it is possible to measure the vertical displacement of the soil cement 1 at the depth where the tip 21 of the rod-shaped member 20 is located. As the displacement meter 3, for example, a laser displacement meter can be used, but it is also possible to use a contact type (stroke type or wire winding type) or an auto level.

[0031] In the example shown in Figure 2, the rod-shaped member 20 is longer than the outer tube 10, and the rear end of the rod-shaped member 20 protrudes from the outer tube 10, but the rear end of the rod-shaped member 20 does not have to protrude from the outer tube 10 as long as the vertical displacement of the rod-shaped member 20 can be measured.

[0032] For example, tip 21 of rod-shaped member 20 is formed with a pointed tip. Therefore, when tip 21 of rod-shaped member 20 of vertical displacement measuring jig 100 is penetrated into soil cement 1, the resistance that rod-shaped member 20 receives from soil cement 1 can be reduced. Therefore, breakage of rod-shaped member 20 can be prevented, and the resistance of soil cement 1 during the penetration process of rod-shaped member 20 can be reduced. In FIG. 2, a plate member with triangular front and back surfaces is used for tip 21, but tip 21 may be, for example, a triangular pyramid-shaped, conical, or quadrangular pyramid-shaped member.

[0033] Grease (filler) 40 is filled between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20. This makes it possible to prevent unsolidified soil cement 1 from flowing between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20, and also to reduce resistance between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20. This makes it possible for the rod-shaped member 20 to more reliably follow the vertical displacement of the soil cement 1.

[0034] Grease 40 is also filled between the inner peripheral surface of the edge cutting member 30 and the outer peripheral surface of the rod-shaped member 20. This makes it possible to prevent unsolidified soil cement 1 from flowing between the inner peripheral surface of the edge cutting member 30 and the outer peripheral surface of the rod-shaped member 20, and also to reduce resistance between the inner peripheral surface of the edge cutting member 30 and the outer peripheral surface of the rod-shaped member 20. This makes it possible for the rod-shaped member 20 to more reliably follow the vertical displacement of the soil cement 1.

[0035] It is preferable that the grease 40 is filled not over the entire length of the outer pipe 10 but only partway through the outer pipe 10. In this case, the resistance of the grease 40 can be reduced compared to when the grease 40 is filled over the entire length of the outer pipe 10, and the rod-shaped member 20 can more reliably follow the vertical displacement of the soil cement 1. The section filled with the grease 40 is, for example, a section from the tip 21 of the rod-shaped member 20 up to 5.5 m.

[0036] Instead of the grease 40, a lubricant or friction reducing material that swells with water may be used.

[0037] Next, a method for measuring the vertical displacement of soil cement 1 using vertical displacement measuring jig 100 will be described with reference to Fig. 2 and Fig. 3. Fig. 3 is a diagram for explaining the method for measuring the vertical displacement of soil cement 1. Fig. 3(a) is a cross-sectional view of vertical displacement measuring jig 100 in an installation step, and Fig. 3(b) is a cross-sectional view of vertical displacement measuring jig 100 in a core material insertion step.

[0038] 3(a), the outer pipe 10 of the vertical displacement measuring jig 100 is attached to the core material 2 along the insertion direction of the core material 2 (attachment process). The outer pipe 10 may be attached to the core material 2 in a state where the rod-shaped member 20 is inserted into the outer pipe 10, or the rod-shaped member 20 may be inserted into the outer pipe 10 after the outer pipe 10 is attached to the core material 2.

[0039] 3(b), the core material 2 is inserted into the unsolidified soil cement 1 (core material insertion step). Specifically, the core material 2 is hoisted and moved above the soil cement 1 using a crane (not shown), and the core material 2 is lowered and inserted into the soil cement 1. By inserting the core material 2, the vertical displacement measuring jig 100 is inserted into the soil cement 1. Since the outer pipe 10 is inserted into the soil cement 1 while attached to the core material 2, which is more rigid than the outer pipe 10, breakage of the outer pipe 10 can be prevented, and breakage of the rod-shaped member 20 inserted into the outer pipe 10 can also be prevented.

[0040] When inserting the core material 2 into the soil cement 1, the tip 21 of the rod-shaped member 20 is brought as close as possible to the tip 11 of the outer pipe 10. This makes it possible to protect the rod-shaped member 20 by the outer pipe 10, and to prevent the rod-shaped member 20 from breaking.

[0041] Furthermore, when inserting the core material 2 into the soil cement 1, the tip 21 of the rod-shaped member 20 is not allowed to protrude from the core material 2 in the insertion direction. This allows the tip 21 to be inserted into the soil cement 1 following the tip of the core material 2, thereby reducing the resistance that the tip 21 receives from the soil cement 1. This prevents the rod-shaped member 20 from breaking.

[0042] After inserting the core material 2 into the soil cement 1 to a predetermined depth, the rod-shaped member 20 is moved relative to the outer pipe 10, and the tip 21 of the rod-shaped member 20 penetrates the unsolidified soil cement 1 (rod-shaped member penetration process). This makes the vertical displacement measuring jig 100 ready to measure the displacement of the soil cement 1 (see FIG. 2). The tip 21 penetrates, for example, by pushing the rear end of the rod-shaped member 20 in manually. If it is difficult to penetrate the tip 21 manually, a pushing device such as a jack can also be used.

[0043] Tip portion 21 is formed, for example, with a pointed tip, and therefore, when tip portion 21 penetrates soil cement 1, the resistance that tip portion 21 receives from soil cement 1 can be reduced. Therefore, breakage of tip portion 21 can be prevented.

[0044] After the soil cement 1 has solidified, the vertical displacement of the rod-shaped member 20 is measured (measurement step). The rod body 22 of the rod-shaped member 20 is separated from the soil cement 1 by the outer tube 10 and the separating member 30, and the tip 21 of the rod-shaped member 20 adheres to the soil cement 1, so that the rod-shaped member 20 is displaced vertically together with the soil cement 1 around the tip 21. Therefore, the vertical displacement of the rod-shaped member 20 can be measured as the vertical displacement of the soil cement 1 at the depth where the tip 21 is located.

[0045] According to the above embodiment, the following advantageous effects are achieved.

[0046] In the vertical displacement measuring jig 100, the rod-shaped member 20 is separated from the soil cement 1 by the outer pipe 10 and the separating member 30. Therefore, the rod-shaped member 20 is not constrained by the soil cement 1 around the outer pipe 10 and the separating member 30, and is displaced vertically together with the soil cement 1 around the tip 21 of the rod-shaped member 20. Therefore, by measuring the vertical displacement of the rod-shaped member 20, the vertical displacement of the soil cement 1 at the depth where the tip 21 of the rod-shaped member 20 is located can be measured.

[0047] Furthermore, tip portion 21 of rod-shaped member 20 is formed with a pointed tip. Therefore, when tip portion 21 penetrates soil cement 1, the resistance that tip portion 21 receives from soil cement 1 can be reduced. Therefore, breakage of tip portion 21 can be prevented.

[0048] In addition, a filler is filled between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20. This makes it possible to prevent unsolidified soil cement 1 from flowing between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20, and also to reduce resistance between the inner peripheral surface of the outer pipe 10 and the outer peripheral surface of the rod-shaped member 20. This makes it possible for the rod-shaped member 20 to more reliably follow the vertical displacement of the soil cement 1.

[0049] The outer pipe 10 comprises a plurality of pipe bodies 12 connected in series, and both ends of each of the plurality of pipe bodies 12 are provided with a connection mechanism for connecting to other pipe bodies 12. Therefore, it is easy to add pipe bodies 12, and the outer pipe 10 can be easily lengthened. Therefore, the tip 11 of the outer pipe 10 can easily reach a depth that cannot be reached by a single pipe body 12.

[0050] The rod-shaped member 20 includes a plurality of rod bodies 22 connected in series, and both ends of each of the plurality of rod bodies 22 are provided with a connecting mechanism for connecting to other rod bodies 22. This makes it easy to add rod bodies 22, and the rod-shaped member 20 can be easily lengthened. This allows the tip 21 of the rod-shaped member 20 to easily reach a depth that cannot be reached by a single rod body 22.

[0051] In the vertical displacement measuring method, the outer pipe 10 is attached to the core material 2 along the insertion direction of the core material 2, the core material 2 is inserted into unsolidified soil cement 1 in the ground, the rod-shaped member 20 is moved relative to the outer pipe 10, the tip 21 of the rod-shaped member 20 is penetrated into the unsolidified soil cement 1, and after the soil cement 1 is solidified, the vertical displacement of the rod-shaped member 20 is measured as the vertical displacement of the soil cement 1. Since the outer pipe 10 is inserted into the soil cement 1 while attached to the core material 2 having higher rigidity than the outer pipe 10, breakage of the outer pipe 10 can be prevented, and breakage of the rod-shaped member 20 inserted into the outer pipe 10 can be prevented. In addition, in the core material inserting step, since the rod-shaped member 20 is in a state before being moved relative to the outer pipe 10, the rod-shaped member 20 can be protected by the outer pipe 10, and breakage of the rod-shaped member 20 can be prevented. Therefore, the displacement of the soil cement 1 can be accurately measured.

[0052] (Modification) A modified example according to an embodiment of the present invention will be described with reference to Fig. 4. Fig. 4 is a diagram for explaining the modified example, and corresponds to Fig. 2.

[0053] As shown in Fig. 4, in this modification, a plurality of vertical displacement measuring jigs 100, 101 are used. The outer tubes 10 of the plurality of vertical displacement measuring jigs 100, 101 are attached to a core material 2. The tip portions 21 of the rod-shaped members 20 are inserted into the soil cement 1 to different depths. Therefore, the rod-shaped members 20 are displaced in accordance with the displacement of the soil cement 1 at different depths. Therefore, by measuring the displacement of the rod-shaped members 20, the displacement of the soil cement 1 at different depths can be measured.

[0054] In addition, in the modified example, it is possible to measure the vertical displacement of the core material 2 using a plurality of vertical displacement measuring jigs 200, 201. Measurement of the vertical displacement of the core material 2 using the vertical displacement measuring jig 200 will be briefly described below.

[0055] In the vertical displacement measuring jig 100, the tip 21 of the rod-shaped member 20 is attached to the soil cement 1, whereas in the vertical displacement measuring jig 200, the tip 221 of the rod-shaped member 220 is not attached to the soil cement 1 but is joined to the core material 2. Therefore, the rod-shaped member 220 is displaced vertically together with the portion of the core material 2 where the tip 221 is joined. Therefore, by measuring the vertical displacement of the rod-shaped member 220, the vertical displacement of the core material 2 at the depth where the tip 221 of the rod-shaped member 220 is joined can be measured.

[0056] The outer tube 210, edge cutting member 230, and grease 240 of the vertical displacement measuring jig 200 are the same as the outer tube 10, edge cutting member 30, and grease 240 of the vertical displacement measuring jig 100, so their description will be omitted here.

[0057] Tip 221 of vertical displacement measuring jig 201 is joined to core material 2 at a depth different from the depth of tip 221 of vertical displacement measuring jig 200. Therefore, vertical displacement measuring jig 201 can measure the vertical displacement of core material 2 at a depth different from that of vertical displacement measuring jig 200. In other words, vertical displacement measuring jig 200, 201 can measure the displacement of core material 2 at different depths.

[0058] Although the embodiments of the present invention have been described above, the above-mentioned embodiments merely show some of the application examples of the present invention, and it is not intended that the technical scope of the present invention be limited to the specific configurations of the above-mentioned embodiments.

[0059] In the above embodiment, the core material 2 is an H-shaped steel. However, the core material 2 may be a steel pipe pile, a precast concrete pile body, a cross H-shaped steel, or the like.

[0060] In the above embodiment, the cement-based material is the soil cement 1. However, in the present invention, the cement-based material may be cement milk or concrete.

[0061] The present invention is also applicable to a combination of an unsolidified cement-based material and a core material made of highly rigid artificial materials (H-shaped steel, steel pipe piles, precast concrete pile bodies, etc.). The cement-based material may be used in the base protection part of a precast concrete pile or the base protection part of a parent pile (H-shaped steel) in a parent pile horizontal sheet pile construction method. The present invention is also applicable to a combination in which the cement-based material is a ground improvement body made of a cement-based solidification material used in soft ground, and the core material is an underground structure. [Explanation of symbols]

[0062] 100, 101: Vertical displacement measuring fixture 1. Soil cement (cement-based material) 2. Core material 10...outer tube 11...Tip of outer tube 12... Body 20... Rod-shaped member 21....Tip of rod-shaped member 22... Rod body 30... Edge cutting member 40 Grease (filler) W··· Earth retaining wall (underground structure)

Claims

1. A jig used for measuring vertical displacement of a cement-based material in an underground structure, the jig comprising: a cement-based material underground; and a core material inserted into the cement-based material, an outer tube attached to the core member along an insertion direction of the core member; a rod-shaped member that is movably inserted into the outer pipe and has a tip that protrudes from the outer pipe and penetrates into the unsolidified cement-based material; a cutting member provided between the tip of the outer pipe and the tip of the rod-shaped member, cutting the rod-shaped member from the cement-based material; As the cement-based material solidifies, the tip of the rod-shaped member adheres to the cement-based material, and the vertical displacement of the rod-shaped member is measured as the vertical displacement of the cement-based material. A fixture for measuring vertical displacement of cement-based materials.

2. The tip of the rod-shaped member is formed to be pointed. A jig for measuring vertical displacement of a cement-based material according to claim 1.

3. Grease is filled between the inner peripheral surface of the outer tube and the outer peripheral surface of the rod-shaped member. A jig for measuring vertical displacement of a cement-based material according to claim 1 or 2.

4. The outer tube includes a plurality of tube bodies connected in series, Each of the plurality of pipes is provided at both ends with a pipe connection mechanism for connection to the other pipes. The vertical displacement measuring tool for a cement-based material according to any one of claims 1 to 3.

5. The rod-shaped member includes a plurality of rod bodies connected in series. Both ends of each of the plurality of rod bodies are provided with a rod body connecting mechanism for connecting with other rod bodies. A jig for measuring vertical displacement of a cement-based material according to any one of claims 1 to 4.

6. A method for measuring a vertical displacement of a cement-based material in an underground structure, the method comprising: a mounting step of mounting the outer tube to the core member along an insertion direction of the core member; a core material inserting step of inserting the core material into the unsolidified cement-based material in the ground; a rod-shaped member penetrating step of moving the rod-shaped member relative to the outer pipe so as to penetrate the tip portion of the rod-shaped member into the unsolidified cement-based material; and a measuring step of measuring a vertical displacement of the rod-shaped member as a vertical displacement of the cement-based material after the cement-based material has solidified. Method for measuring vertical displacement of cement-based materials.

7. In the mounting step, a plurality of vertical displacement measuring jigs are prepared, and the outer pipes of the plurality of vertical displacement measuring jigs are mounted on the core material such that the tip portions of the outer pipes are at different depths; In the rod-shaped member penetrating step, the tip portions of the rod-shaped members of the plurality of vertical displacement measuring jigs are penetrated into the unsolidified cement-based material to different depths; In the measuring step, the vertical displacement of each of the rod-shaped members in the plurality of vertical displacement measuring jigs is measured as the vertical displacement of the cement-based material at different depths. The method for measuring vertical displacement of a cement-based material according to claim 6.

Citation Information

Patent Citations

  • Device for confirming supporting force of laid-in pile

    JP1989284611A

  • System for measuring settlements by stratum, method of measuring settlements by stratum

    JP2011246911A

  • Construction method of earth-retaining wall

    JP2013194460A

  • Installation method for stratified settlement gauge and stratified settlement measuring system

    JP2015200096A

  • Penetration testing machine for drilling rod connection, and pile construction management method

    JP2017186850A