Repair method for concrete structures for boat docks
The method addresses insufficient formwork support in concrete structure repairs by using vertical girders, cross beams, and brackets to ensure formwork remains in place, preventing joint exposure and enhancing repair durability and quality.
Patent Information
- Application Number
- JP2021097366
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-06-10
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2041-06-10
AI Technical Summary
Existing methods for repairing concrete structures in wharves, such as those described in Patent Document 1, face issues with insufficient formwork support, leading to potential seawater erosion and weak spots due to exposed seams after concrete pouring.
A method involving the installation of formwork supports using vertical girders, cross beams, and upper fixed girders on the top surface of the concrete structure, with the lower ends of the formwork supported by Sanwa soil or brackets, ensuring the formwork remains in place post-concrete pouring, and separate concrete placement for underwater and aerial parts.
The method provides firm support for the formwork, preventing exposure of joints and potential weak spots, enhancing the durability and quality of the repair by maintaining the formwork integrity and improving concrete quality.
Smart Images

Figure 0007590271000001 
Figure 0007590271000002 
Figure 0007590271000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for repairing a concrete structure constructed as a dock. [Background technology]
[0002] There are docks made of concrete structures that are surrounded by the sea on three sides (the front and both sides). Over time, such concrete structures will inevitably deteriorate (be damaged) due to the erosion of seawater, and will require repairs (renovations).
[0003] Patent Document 1 discloses a method for repairing an underwater wall surface (an underwater wall surface including a repair wall surface at least partially damaged) of a concrete structure such as a breakwater. In this method, a concrete form support plate is placed on the water bottom, and a steel form is placed with its lower end supported by the form support plate, and the form faces the underwater wall surface including the repaired wall surface of the concrete structure. The form is also supported by the underwater wall surface with form support ropes. Underwater concrete is then poured into the space between the underwater wall surface and the form, and the form is then detached from the form support ropes and removed. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2017-025585 A Summary of the Invention [Problem to be solved by the invention]
[0005] However, in the repair method described in Patent Document 1, the formwork is supported on the underwater wall surface by cables (formwork support ropes), which may result in insufficient support for the formwork. In addition, the formwork is removed after the concrete is poured. Concrete is generally poured in layers of 30 to 40 cm each, which means there are joints. When the formwork is removed, the joints become exposed, leaving weak areas that are susceptible to erosion by seawater.
[0006] In consideration of the above-mentioned circumstances, the present invention aims to provide a method for repairing a concrete structure for a dock, which can be used effectively to repair a concrete structure constructed as a dock, in particular the three sides (front and both side faces) that are surrounded by the sea. [Means for solving the problem]
[0007] The present invention The first to fourth aspects A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; The front of the existing concrete structure facing the sea is supported by the formwork support material. and side a formwork installation process of installing a formwork including a front formwork and a side formwork so as to surround the surface; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; and the formwork is left in place. This is a method for repairing a concrete structure for a dock. In a first aspect of the present invention, the formwork support installation process includes a process of installing vertical and horizontal beams in a lattice pattern on the upper surface of the existing concrete structure, and a process of installing upper fixed beams to support the front formwork and side formwork at the tips of the vertical and horizontal beams and along the front and side edges of the existing concrete structure. In a second aspect of the present invention, the method for repairing a concrete structure for a dock further includes a step of pouring concrete for leveling unevenness into the earthen floor at the front of the existing concrete structure prior to installing the formwork, and in the formwork installation step, the lower end of the front formwork is supported on the earthen floor. In a third aspect of the present invention, the method for repairing a concrete structure for a dock further includes a bracket installation step of installing a bracket on a side of the existing concrete structure for supporting a lower end of the side formwork prior to installing the formwork, and in the formwork installation step, the lower end of the side formwork is supported by the bracket. In a fourth aspect of the present invention, the concrete pouring step includes a step of pouring underwater concrete in an underwater portion, and a step of pouring aerial concrete in an aerial portion so as to bury the form support material. Effect of the Invention
[0008] According to the present invention, formwork supports are provided on the upper surface of an existing concrete structure, and formwork (front formwork and side formwork) is supported by these, so that the formwork can be firmly supported. In addition, since the formwork is left in place, removal work is not required, and even if joints are formed in the poured concrete, they will not be exposed, preventing the occurrence of weak parts. [Brief description of the drawings]
[0009] [Figure 1] FIG. 1 is a plan view and a right side view of an existing wharf shown as an embodiment of the present invention. [Diagram 2] Plan view of the process of installing formwork at the wharf [Diagram 3] Side view of the process of installing formwork on the sea-facing front of the wharf [Figure 4] Front view of the process of installing formwork on the side of the wharf [Diagram 5] Side view of the process of installing formwork on the side of the wharf DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] Hereinafter, an embodiment of the present invention will be described in detail. The embodiment described here is an example of repairing (refurbishing) a wharf on an artificial island as shown in FIG.
[0011] Therefore, first, the artificial island and its wharf in Fig. 1 will be described. Fig. 1(A) is a plan view, and Fig. 1(B) is a right side view corresponding to the view seen from the arrow B in Fig. 1(A).
[0012] The artificial island 1 in Figure 1 is made by piling up tetra-shaped wave-dissipating blocks 2 on the seabed and pouring concrete on top of them to form an artificial base 3.
[0013] A dock 4 is formed by pouring concrete in a rectangular shape in plan view facing a part of the ground 3 and protruding toward the sea. Therefore, the pier 4 is a rectangular parallelepiped concrete structure protruding toward the sea, and is surrounded by the sea on three sides (the front 4a and both side surfaces 4b, 4b).
[0014] In addition, a clay section 5 is formed on the seabed on the front side 4a side, continuing to the lower end of the front side 4a. On the other hand, wave dissipating blocks 2 are placed on the seabed on the side faces 4b, 4b side, and their height gradually increases from the sea side to the island side.
[0015] Such concrete structure wharves are exposed to the elements for a long time and are corroded by seawater, causing deterioration including cracks, peeling, and damage to the concrete, and further damage can cause the wave-dissipating blocks buried inside to become exposed. Therefore, repairs (renovations) are necessary.
[0016] Next, a method for repairing the wharf (existing concrete structure) of FIG. 1 will be described with reference to FIGS. 2 to 5 as one embodiment of the present invention.
[0017] Figure 2 is a process diagram for installing formwork at the dock, shown in a plan view, Figure 3 is a process diagram for installing formwork on the sea front of the dock, shown in a side view (arrow III in Figure 2), Figure 4 is a process diagram for installing formwork on the side of the dock, shown in a front view (arrow IV in Figure 2), and Figure 5 is a process diagram for installing formwork on the side of the dock, shown in a side view (arrow V in Figure 2).
[0018] [Deteriorated part removal process] In the deteriorated part removal process, deteriorated parts of the concrete (peeled or damaged parts, and even protruding parts of wave-dissipating blocks protruding from the inside due to surface peeling) are removed prior to repairing the wharf (existing concrete structure) 4. In particular, for the top surface of the existing concrete structure, removing the deteriorated parts makes it sufficiently smooth so that the form support material can be correctly positioned in the form support material installation process.
[0019] [Pouring clay concrete] In the step of pouring concrete for the mortar, prior to setting up the formwork, concrete for leveling the unevenness is poured into the mortar portion 5 (see FIG. 1) in front of the wharf 4a. Since the lower end of the front formwork 21 is to be supported on the concrete of the moat section 5 at the bottom of the front of the pier 4a, it is necessary to adjust the unevenness of the concrete of the moat section 5 and make the height uniform (for example, DL-2.0 m) using underwater non-segregating concrete.
[0020] Specifically, L-shaped steel members for checking the top height are installed with oar anchors at the front of the pier 4a, and then anti-leakage sheets and small sandbags are laid down as a retaining frame for the underwater concrete. After the underwater formwork is installed, the underwater non-segregating concrete is poured. The concrete is produced on the plant barge, and the nozzle of the pouring hose is held by a crawler crane mounted on a self-elevating work barge, and the concrete is poured at the signal of the diver.
[0021] [Formwork support installation process] In the formwork support fixing process, steel formwork supports (vertical beams 11, horizontal beams 12, and upper fixed beams 13, 14) are installed on the top surface (top edge) of the existing concrete structure, which has had deteriorated portions removed to make it almost smooth.
[0022] This process includes a process of installing vertical beams 11 and horizontal beams 12 in a lattice pattern on the upper surface (top) of the existing concrete structure as shown in Figure 2(A) (vertical beam / horizontal beam installation process), and a process of installing upper fixed beams 13, 14 to support the front formwork 21 and the side formwork 22 along the front and side edges of the existing concrete structure by supporting them at the tips of the vertical beams 11 and horizontal beams 12 as shown in Figure 2(B) (upper fixed beam installation process).
[0023] [Vertical girder / horizontal girder installation process] In the stringer / cross beam installation process, referring to Figures 2(A), 3(A) and 4(A), the positions of the base plate 10 for fixing the stringers and cross beams are marked out in a matrix on the top surface (top) of the existing concrete structure, anchor bolt holes are drilled, Chemical Anchors (registered trademark) are inserted and mixed, and the base plate 10 is bolted. Then, the stringers 11 are installed using the base plate 10, the cross beams 12 are installed so as to intersect with the stringers 11, and the stringers 11 and cross beams 12 are bolted together using splice plates.
[0024] [Upper fixed girder installation process] In the upper fixed girder installation process, referring to Figures 2(B) and 3(B), an upper fixed girder 13 is installed, which is supported by the sea-side tips of the multiple vertical beams 11 and extends horizontally along the front surface 4a. Also, referring to Figures 2(B) and 4(B), upper fixed beams 13, 14 are installed, which are supported by the left and right ends of the multiple horizontal beams 12 and extend vertically along both side surfaces 4b, 4b. The upper fixed girders 13, 14 are bolted to the vertical girders 11 and horizontal girders 12 while being suspended by a crawler crane, and the upper fixed girders 13, 14 are also bolted to each other with splice plates.
[0025] The vertical and horizontal beam installation process and the upper fixed beam installation process do not need to be performed consecutively, and the upper fixed beam installation process may be performed after the vertical and horizontal beam installation process is completed, and after the lower fixed beam installation process and bracket installation process underwater. Alternatively, the upper fixed beam installation process may be performed in parallel with the lower fixed beam installation process and bracket installation process underwater.
[0026] [Lower fixed girder installation process] In the lower fixed girder installation process, prior to installation of the front formwork 21, the lower fixed girder 15 is installed on the timber floor 5 as shown in Fig. 3(B) to be used for supporting and fixing the lower end of the front formwork 21. The lower fixed girder 15 is hoisted down onto the timber floor 5 by a crawler crane, and fixed onto the timber floor 5 by underwater work using chemical anchors.
[0027] [Bracket installation process] In the bracket installation process, prior to installing the side formwork 22, a bracket 16 is installed on the side surface 4b of the existing concrete structure for use in supporting and fixing the lower end portion of the side formwork 22, as shown in Figures 4(B) and 5(A).
[0028] Because there is a clay section 5 on the seabed on the front side 4a of the dock, the lower end of the front formwork 21 is supported on the concrete clay on the seabed side, but because there are wave-dissipating blocks 2 on the seabed on the side 4b of the dock, making it difficult to adjust the unevenness, the lower end of the side formwork 22 is supported by brackets 16 fixed to the side 4b of the dock.
[0029] Specifically, the bracket installation process involves the following steps: (1) determining the bracket bolt hole position and drilling, (2) mixing / filling the resin adhesive and fixing the bolts, and (3) installing the bracket. Here, in order to accurately measure the bracket position on the side surface 4b of the existing concrete structure, a ruler for drilling anchor holes is attached to the installed vertical beams 11 and horizontal beams 12. Then, using the ruler as a guide, a diver drills bolt holes for mounting the bracket 16, fixes the bolts with chemical anchors, and installs the bracket 16.
[0030] After the above-mentioned process of removing deteriorated parts, pouring the clay concrete, installing the vertical and horizontal beams, installing the lower fixed beam, installing the brackets, and installing the upper fixed beam, we move on to the formwork installation process shown in Figures 2(C), 3(C), 4(C), 5(A), and 5(B).
[0031] [Formwork installation process] In the formwork installation process, a formwork 20 consisting of a front formwork 21 and side formworks 22, 22 is installed so as to surround the sea-facing front 4a and both side surfaces 4b, 4b of the existing concrete structure, supported by upper fixed girders 13, 14, which serve as formwork support materials. Here, the formwork 20 (front formwork 21 and side formwork 22) is made of stainless steel since it is not removed (de-molded) after the concrete pouring process but is left in place.
[0032] The formwork 20 is U-shaped in plan view and can be divided into a front formwork 21 and side formworks 22, 22. Therefore, the formwork installation process can be divided into a front formwork installation process and left and right side formwork installation processes.
[0033] The front formwork 21 is made up of an outer formwork panel 21a and reinforcing steel members 21b provided inside as appropriate. The side formwork 22 is also made up of an outer formwork panel 22a and reinforcing steel members 22b provided inside as appropriate.
[0034] [Front formwork installation process] The front formwork 21 is suspended by a crawler crane and lowered onto the wooden floor section 5 as shown in Figure 3 (C), and the lower end is bolted to the lower fixed girder 15 and the upper end is bolted to the upper fixed girder 13 using underwater work. Here, between the lower end of the front formwork 21 and the mortar section 5 or the lower fixed girder 15, a filler material is interposed to prevent concrete from leaking during pouring.
[0035] [Side formwork installation process] As shown in Figures 4(C) and 5(A)→(B), the side formwork 22 is suspended onto the brackets 16 by a crawler crane, bolted to the brackets 16 through underwater work, and the upper end is bolted to the upper fixed girder 14. Here, in order to prevent concrete from leaking from the lower end of the side formwork 22 when pouring, a closing plate is provided and supported by the bracket 16, and filler material is appropriately interposed.
[0036] The front form 21 and the side form 22 are connected with an appropriate joint member after installation. Note that the front form 21 and the side form 22 may each be divided into multiple pieces and assembled, and the divided pieces may be connected with a joint member such as a joint plate. After the formwork 20 (front formwork 21 and side formwork 22) has been installed, the process proceeds to the concrete pouring process.
[0037] [Concrete pouring process] In the concrete pouring process, concrete is poured between the formwork 20 (front formwork 21 and side formwork 22) and the existing concrete structure (its front face 4a and side face 4b). In addition, concrete is poured onto the top edge of the existing concrete structure within the formwork 20 (front formwork 21 and side formwork 22). Therefore, the concrete pouring process can be divided into an underwater concrete pouring process in the underwater section and an aerial concrete pouring process in the aerial section.
[0038] [Underwater concrete pouring process] In the underwater concrete pouring process, underwater concrete (underwater non-segregating concrete) is poured up to, for example, DL+1.2 m.
[0039] [Air concrete pouring process] In the air concrete pouring process, after the reinforcing bars are installed in the air, the air concrete is poured up to, for example, DL+1.8m so as to bury the formwork support materials (vertical beams 11, horizontal beams 12, and upper fixed beams 13, 14).
[0040] After the concrete pouring process, the formwork 20 (the front formwork 21 and the side formwork 22) is left in place and is not removed (de-molded). For this reason, the formwork 20 (including the brackets 16, etc.) is made of stainless steel for rust prevention.
[0041] According to this embodiment, formwork supports (vertical beams 11, horizontal beams 12, and upper fixed beams 13, 14) are provided on the upper surface of the existing concrete structure, and the formwork 20 (front formwork 21 and side formwork 22) is supported by these, so that the formwork 20 can be firmly supported. Moreover, since the formwork 20 is left in place, removal work is not required, and even if joints are formed in the poured concrete, they will not be exposed, preventing the occurrence of weak parts.
[0042] Furthermore, according to this embodiment, in the formwork support installation process, vertical girders 11 and horizontal girders 12 are installed in a lattice pattern on the upper surface of the existing concrete structure, and upper fixed girders 13, 14 are installed so as to be supported at the tips of these vertical girders 11 and horizontal girders 12 and run along the front and side edges of the existing concrete structure, thereby enabling the front formwork 21 and side formwork 22 to be supported with high precision.
[0043] In addition, according to this embodiment, prior to installing the front formwork 21, concrete for leveling is poured into the mortar section 5 on the front 4a of the existing concrete structure, thereby enabling the lower end of the front formwork 21 to be supported with high precision.
[0044] Furthermore, according to this embodiment, by installing the brackets 16 on the side surfaces 4b of the existing concrete structure prior to installation of the side surface formwork 22, the lower ends of the side surface formwork 22 can be supported with high precision.
[0045] Furthermore, according to this embodiment, by managing the process separately into an underwater concrete pouring process in the underwater section and an aerial concrete pouring process in the aerial section, it is possible to improve concrete quality and workability.
[0046] Furthermore, according to this embodiment, by removing deteriorated portions of an existing concrete structure prior to repairing the existing concrete structure, it is possible to reliably obtain the smoothness of the reference surface required for repair, etc.
[0047] Although the above has been explained using an example of repairing a dock on an artificial island, the application of the present invention is not limited to this, and it is applicable to the general repair of docks constructed in a shape that protrudes out into the sea.
[0048] Furthermore, it goes without saying that the illustrated embodiments are merely schematic illustrations of the present invention, and that the present invention encompasses various improvements and modifications made by those skilled in the art within the scope of the claims, in addition to those directly shown in the described embodiments. The claims as originally filed were as follows: [Claim 1] A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; A form installation process in which a form consisting of a front form and a side form is installed so as to be supported by the form support material and surround the front and side of the existing concrete structure on the sea side; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; wherein the formwork is left in place. [Claim 2] The method for repairing a concrete structure for a dock as described in claim 1, characterized in that the formwork support installation process includes a process of installing vertical and horizontal beams in a lattice pattern on the upper surface of the existing concrete structure, and a process of installing upper fixed beams to support the front and side formworks on the tips of the vertical and horizontal beams and along the front and side edges of the existing concrete structure. [Claim 3] The method further includes a step of pouring concrete for unevenness adjustment into the sanwa soil part in front of the existing concrete structure prior to the installation of the formwork, 3. The method for repairing a concrete structure for a dock according to claim 1, wherein in the formwork installation step, a lower end of the front formwork is supported on the mortar. [Claim 4] The method further includes a bracket installation step of installing a bracket on a side surface of an existing concrete structure prior to the installation of the formwork to support a lower end portion of the side surface formwork, 4. The method for repairing a concrete structure for a dock according to claim 1, wherein in the formwork installation step, a lower end of the side formwork is supported by the bracket. [Claim 5] 5. A method for repairing a concrete structure for a dock as described in any one of claims 1 to 4, characterized in that the concrete pouring process includes a process of pouring underwater concrete in an underwater portion, and a process of pouring aerial concrete in an aerial portion so as to bury the formwork support material. [Claim 6] 6. A method for repairing a concrete structure for a dock as described in any one of claims 1 to 5, further comprising a deteriorated portion removal step of removing deteriorated portions of the existing concrete structure prior to repairing the existing concrete structure. [Explanation of symbols]
[0049] 1 artificial island 2. Wave-dissipating blocks 3 Ground 4. Boat Dock 4a Front of the pier 4b Wharf side 5. Sanwadobe (Sanwado concrete) 10 Base plate 11 Stringer 12 crossbeam 13, 14 Upper fixed beam 15 Lower fixed beam 16 Bracket 20 Formwork 21 Front formwork 22 Side formwork 21a, 22a Formwork panels 21b, 22b Reinforcement steel
Claims
1. A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; A form installation process in which a form consisting of a front form and a side form is installed so as to be supported by the form support material and surround the front and side of the existing concrete structure on the sea side; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; A method for repairing a concrete structure for a boat pier, comprising the steps of: The formwork support installation process is a method for repairing a concrete structure for a dock, which includes the steps of: installing vertical and horizontal beams in a lattice pattern on the top surface of the existing concrete structure; and installing upper fixed beams to support the front and side formworks on the tips of the vertical and horizontal beams and along the front and side edges of the existing concrete structure.
2. A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; A form installation process in which a form consisting of a front form and a side form is installed so as to be supported by the form support material and surround the front and side of the existing concrete structure on the sea side; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; A method for repairing a concrete structure for a boat pier, comprising the steps of: The method further includes a step of pouring concrete for unevenness adjustment into the sanwa soil part in front of the existing concrete structure prior to the installation of the formwork, In the formwork installation step, the lower end of the front formwork is supported on the mortar. This is a method for repairing a concrete structure for a dock.
3. A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; A form installation process in which a form consisting of a front form and a side form is installed so as to be supported by the form support material and surround the front and side of the existing concrete structure on the sea side; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; A method for repairing a concrete structure for a boat pier, comprising the steps of: The method further includes a bracket installation step of installing a bracket on a side surface of an existing concrete structure prior to the installation of the formwork to support a lower end portion of the side surface formwork, A method for repairing a concrete structure for a dock, wherein in the formwork installation step, the lower end of the side formwork is supported by the bracket.
4. A method for repairing a concrete structure constructed as a dock, comprising the steps of: A form support installation process for installing a form support on an upper surface of an existing concrete structure; A form installation process in which a form consisting of a front form and a side form is installed so as to be supported by the form support material and surround the front and side of the existing concrete structure on the sea side; A concrete pouring process of pouring concrete between the formwork and an existing concrete structure; A method for repairing a concrete structure for a boat pier, comprising the steps of: The concrete pouring step includes a step of pouring underwater concrete in an underwater portion, and a step of pouring aerial concrete in an aerial portion so as to bury the formwork support material, in a method for repairing a concrete structure for a boat dock.
5. The method for repairing a concrete structure for a dock according to any one of claims 1 to 4, further comprising a deteriorated portion removing step of removing a deteriorated portion of the existing concrete structure prior to repairing the existing concrete structure.
Citation Information
Patent Citations
Mounting method of molding frame
JP1994240637A
Embedded form and execution method therefor
JP1997256341A
Permanent form for dam levee body, and raising method of dam levee body
JP1999117265A
Construction method for concrete structure
JP2001311247A
Permanent form for use in concrete quay, and construction method for concrete quay using the same
JP2015169013A