The drainage system for concrete dams uses external pipes arranged along the structure's wall and expandable branches to efficiently drain green cutting water, ensuring structural integrity and uninterrupted pouring.

JP7590276B2Active Publication Date: 2024-11-26SHIMIZU CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2021102972
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-06-22
Publication Date
2024-11-26
Estimated Expiration
2041-06-22

AI Technical Summary

Technical Problem

Conventional drainage methods for green cutting work in concrete dam construction, which involve burying pipes inside or raising them from the dam body, compromise the structural integrity and increase labor, and interfere with concrete pouring work.

Method used

A drainage system comprising a first pipe installed laterally along the concrete structure's wall and a second pipe extending towards the joint surface, arranged in branches and expandable vertically, allowing for external drainage without interfering with concrete pouring.

Benefits of technology

The system effectively drains green cutting water without compromising the concrete structure's integrity or interfering with pouring work, facilitating efficient and labor-saving construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007590276000001
    Figure 0007590276000001
  • Figure 0007590276000002
    Figure 0007590276000002
Patent Text Reader

Abstract

To provide a drainage system of green cut working water without using the inside of concrete, which does not interfere with concrete placement work, and a drainage method.SOLUTION: A drainage system 10 for draining green cut working water for treating a concrete joint surface 12, which is generated when constructing concrete structure 20 includes: drainage means 14 that is provided outside the concrete structure 20 for draining the green cut working water; a first pipe 16 that is connected to the drainage means 14 and arranged along a working aisle 28 laterally on a wall 22 of the concrete structure 20; and a second pipe 18 that is connected to the first pipe 16 extending toward the concrete joint surface 12.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a drainage device and a drainage method suitable for green cutting work on concrete joint surfaces in the RCD construction method. [Background technology]

[0002] Conventionally, the cruise RCD method has been adopted in concrete dam construction and the like. This method improves the overall pouring speed by pouring the inner concrete, which has a faster pouring speed, before the outer concrete, which has a slower pouring speed. When applying such an RCD method to concrete dam construction, green cutting work is performed to remove laitance that occurs on the concrete joint surface. Conventional green cutting work has been performed using water supplied from piping buried inside the dam embankment or piping extended from both banks of the dam embankment along the top edge over the entire embankment (see, for example, Patent Documents 1 and 2). In addition, water generated during the work was discharged downstream from piping buried inside the dam embankment or drainage pipes erected from the bottom of both banks of the dam embankment. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 6-81466 [Patent Document 2] Japanese Patent Application Publication No. 6-81465 Summary of the Invention [Problem to be solved by the invention]

[0004] However, burying pipes inside the dam body may weaken the dam body due to their presence. In addition, the pipes must be buried and removed every time the dam body's height is raised by pouring concrete, which increases the amount of work required. In addition, using drainage pipes that rise from the bottom of both banks of the dam body requires the drainage hose to be routed at the top of the dam body, which may interfere with concrete pouring work using the RCD method and other methods. For this reason, there was a demand for drainage technology for green cut work water that does not utilize the inside of the concrete and does not interfere with concrete pouring work.

[0005] The present invention has been made in consideration of the above, and aims to provide a drainage device and a drainage method for water used in green cutting work that do not utilize the inside of the concrete and do not interfere with concrete pouring work. [Means for solving the problem]

[0006] In order to solve the above-mentioned problems and achieve the object, the drainage device of the present invention is a drainage device that drains green cut work water for treating concrete joint surfaces generated when constructing concrete for a concrete structure, and is characterized by comprising: drainage means provided on the outside of the concrete structure for draining the green cut work water; a first piping connected to the drainage means and arranged along the equipment installed horizontally on the wall surface of the concrete structure; and a second piping connected to the first piping and extending toward the concrete joint surface.

[0007] Furthermore, another drainage device according to the present invention is characterized in that, in the above-mentioned invention, the second pipe is arranged to branch off from the first pipe in multiple branches at predetermined intervals, and is arranged so that it can be extended or expanded in the vertical direction.

[0008] Further, another drainage device according to the present invention is characterized in that, in the above-mentioned invention, the facility is a working passageway.

[0009] In addition, the drainage method of the present invention is a drainage method for draining green cut work water generated when constructing concrete for a concrete structure, and is characterized by having a step of providing a drainage means for draining the green cut work water on the outside of the concrete structure, a step of connecting to the drainage means and arranging a first piping along equipment installed horizontally on the wall surface of the concrete structure, and a step of connecting to the first piping and arranging a second piping extending toward the concrete joint surface.

[0010] Furthermore, another drainage method according to the present invention is characterized in that, in the above-mentioned invention, the second pipe is arranged to branch off from the first pipe at a predetermined interval and is arranged so that it can be extended or expanded in the vertical direction.

[0011] Further, another drainage method according to the present invention is characterized in that, in the above-mentioned invention, the facility is a work passageway. Effect of the Invention

[0012] According to the drainage device of the present invention, there is provided a drainage device for draining green cutting work water for treating concrete joint surfaces generated when constructing concrete for a concrete structure, and the drainage device is equipped with a drainage means provided on the outside of the concrete structure for draining the green cutting work water, a first pipe connected to the drainage means and arranged along the equipment installed horizontally on the wall surface of the concrete structure, and a second pipe connected to the first pipe and extending toward the concrete joint surface, thereby providing an effect of providing a drainage device that does not utilize the inside of the concrete and does not interfere with concrete pouring work.

[0013] In addition, according to another drainage device of the present invention, the second pipe is arranged to branch off from the first pipe at a predetermined interval and is arranged so that it can be extended or expanded in the vertical direction. Therefore, even if the concrete joint surface becomes higher as the construction progresses, this can be easily accommodated by extending or expanding the second pipe.

[0014] Furthermore, according to another drainage device of the present invention, since the facility is a work passage, it is possible to utilize a work passage such as a catwalk.

[0015] In addition, according to the drainage method of the present invention, there is provided a drainage method for draining green cut work water used to treat concrete joint surfaces generated when constructing concrete for a concrete structure, and the method includes the steps of providing drainage means for draining the green cut work water on the outside of the concrete structure, connecting the drainage means to the first piping and arranging a first piping along equipment installed horizontally on the wall surface of the concrete structure, and connecting the first piping to the second piping and extending toward the concrete joint surface. This has the effect of providing a drainage method that does not utilize the inside of the concrete and does not interfere with concrete pouring work.

[0016] In addition, according to another drainage method of the present invention, the second pipe is arranged to branch off from the first pipe at a predetermined interval and is arranged so that it can be extended or expanded in the vertical direction. Therefore, even if the concrete joint surface becomes higher as the construction progresses, this can be easily accommodated by extending or expanding the second pipe.

[0017] Furthermore, according to another drainage method of the present invention, since the facility is a work passage, it is possible to utilize a work passage such as a catwalk. [Brief description of the drawings]

[0018] [Figure 1] FIG. 1 is a downstream view of a dam embankment showing an embodiment of a drainage device and a drainage method according to the present invention. [Diagram 2] FIG. 2 is an enlarged view of a main portion of FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0019] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A drainage device and a drainage method according to an embodiment of the present invention will be described in detail below with reference to the drawings. However, the present invention is not limited to the embodiment.

[0020] As shown in Fig. 1, a drainage device 10 according to an embodiment of the present invention is used to drain wash water (water for green cutting work) used in green cutting work for treating a concrete joint surface 12 in concrete dam construction using the cruise RCD method. This drainage device 10 includes a drainage means 14, a first pipe 16, and a second pipe 18. The dam embankment 20 (concrete structure) to be constructed is assumed to be a gravity concrete dam with a substantially right-angled triangular cross section, with the upstream wall surface of the dam embankment 20 being substantially vertical and the downstream wall surface 22 being inclined downstream.

[0021] The drainage means 14 is for draining water used in green cutting work, and is installed on the slope of the natural ground G on the right bank R side on the downstream side of the dam body 20. This drainage means 14 includes a drainage pipe 24 arranged along the slope, and a drainage outlet 26 provided at the lower end of the drainage pipe 24 and connected to a drainage treatment device (not shown) provided on the downstream side. The upper end of the drainage pipe 24 is connected to the first piping 16.

[0022] The first pipe 16 is a pipe provided in a substantially straight line along the upper side of a catwalk 28 (equipment) installed on the wall surface 22 on the downstream side of the dam embankment 20. This first pipe 16 can be, for example, a hose for general drainage. The catwalk 28 is a long and narrow work passage extending horizontally in the dam axial direction, and is used for work during the construction stage of the dam embankment 20, and for inspection and the like when it is left after completion. The first pipe 16 is provided with an inclination gradient so that water naturally flows down inside from the left bank L side to the right bank R side. The end of the first pipe 16 on the right bank R side is connected to the drain pipe 24 of the drainage means 14 on the right bank R, and the end of the first pipe 16 on the left bank L side is connected to a water supply pipe 30 provided along the natural ground G of the left bank L. The water supply pipe 30 is for taking in fresh water from the natural ground G of the left bank L to prevent clogging. The taken in fresh water flows naturally down the water supply pipe 30, enters the first piping 16, and then flows down inside the first piping 16 towards the right bank R.

[0023] In addition, the first piping 16 may be installed anywhere along the equipment extending in the left-right direction (horizontal direction) along the wall surface 22 such as the catwalk 28, not limited to the upper side, and may be installed, for example, along the lower side of the equipment.

[0024] The second pipe 18 is connected to the first pipe 16 and extends upward along the downstream wall surface 22 of the dam embankment 20, and a catchment basin 32 is provided at its upper end. The second pipe 18 is arranged by branching out from the first pipe 16 at a predetermined interval. The second pipe 18 can be made of, for example, a lightweight corrugated pipe. The second pipe 18 is arranged so that it can be extended or expanded in the vertical direction. The example of FIG. 2 shows a case where the second pipe 18 is extended using a joint 34. By making the second pipe 18 extendable or expandable in the vertical direction, it is possible to easily accommodate the increase in the height of the concrete joint surface 12 as the construction progresses.

[0025] A plurality of third pipes (not shown) are connected to the catchment basin 32 from various points on the concrete joint surface 12 at the top. The third pipes can be made of flexible hoses, for example. The third pipes are easy to attach and detach from the catchment basin 32, and have a short range so that used cleaning water discharged from the concrete joint surface 12 near the catchment basin 32 can be collected. By shortening the third pipes, they can be easily handled at the concrete top, and installation and removal work can be performed quickly. The reduced handling work improves workability. These prevent them from interfering with the RCD method.

[0026] The operation and function of the above configuration will now be described. As shown in FIG. 1, first, drainage means 14 for draining water for green cutting work is installed along the ground G of the right bank R on the downstream side of the dam embankment 20. Meanwhile, the first piping 16 is installed above the catwalk 28 along the catwalk 28. The first piping 16 is also connected to the drainage means 14 on the right bank R. The first piping 16 may be installed at the same time as the catwalk 28 is installed on the dam embankment 20. This reduces the amount of work required and improves ease of construction.

[0027] Next, the second pipe 18 is connected to the first pipe 16 and extended upward along the downstream wall surface 22 of the dam body 20. Furthermore, a third pipe is connected to the catch basin 32 at the upper end of the second pipe 18 and extended toward various points on the concrete joint surface 12 in the vicinity. This completes the installation of the drainage device 10. The first pipe 16 and the second pipe 18 may be installed at the same time as the installation work of the catwalk 28. This further reduces the amount of work required and improves workability.

[0028] The high-pressure washing water used in the green cutting work passes through the third pipe, the second pipe 18, the first pipe 16, and the drainage means 14 in this order as used drainage water, and is discharged to a drainage treatment facility (not shown) downstream of the dam embankment 20. Thereafter, the water is purified in the drainage treatment facility, and then discharged into a downstream river, etc. By using the drainage device 10, the efficiency of the green cutting work can be improved and the process can be shortened.

[0029] According to this embodiment, the first pipe 16 is arranged above the catwalk 28 on the downstream side of the dam embankment 20, and the second pipe 18 is arranged along the wall surface 22 on the downstream side of the dam embankment 20. Therefore, the first pipe 16 and the second pipe 18 are not buried inside the dam embankment 20, nor are they arranged on the concrete top. The third pipe is arranged on the concrete top, but can be easily installed and removed as necessary. Therefore, according to this embodiment, it is possible to provide a drainage device that does not utilize the inside of the concrete and does not interfere with concrete pouring work such as the RCD method. In addition, this drainage device 10 can be used until the completion of the dam embankment 20, and since it is not buried inside the dam embankment 20, there is no risk of the strength of the dam embankment 20 decreasing. As long as there is a facility such as the catwalk 28 on the wall surface 22 on the downstream side of the dam embankment 20, it can be implemented at low cost at any time, and can be easily introduced later even if it is not included in the initial plan.

[0030] As described above, the drainage device of the present invention is a drainage device that drains green cutting work water for treating concrete joint surfaces generated when constructing concrete for a concrete structure, and is equipped with drainage means provided on the outside of the concrete structure for draining the green cutting work water, a first piping connected to the drainage means and arranged along the equipment installed horizontally on the wall surface of the concrete structure, and a second piping connected to the first piping and extending toward the concrete joint surface, so that it is possible to provide a drainage device that does not utilize the inside of the concrete and does not interfere with concrete pouring work.

[0031] In addition, according to another drainage device of the present invention, the second pipe is arranged to branch off from the first pipe at a predetermined interval and is arranged so that it can be extended or expanded in the vertical direction. Therefore, even if the concrete joint surface becomes higher as the construction progresses, this can be easily accommodated by extending or expanding the second pipe.

[0032] Furthermore, according to another drainage device of the present invention, since the facility is a work passage, a work passage such as a catwalk can be utilized.

[0033] Furthermore, according to the drainage method of the present invention, there is provided a drainage method for draining green cut work water used to treat concrete joint surfaces generated when constructing concrete for a concrete structure, the method comprising the steps of providing drainage means for draining the green cut work water on the outside of the concrete structure, connecting the drainage means to the first piping and arranging the first piping along the equipment installed horizontally on the wall surface of the concrete structure, and connecting the first piping to the second piping and extending toward the concrete joint surface. Therefore, it is possible to provide a drainage method that does not utilize the inside of the concrete and does not interfere with concrete pouring work.

[0034] Furthermore, according to another drainage method of the present invention, the second pipe is arranged to branch off from the first pipe at a predetermined interval and is arranged so that it can be extended or expanded in the vertical direction. Therefore, even if the concrete joint surface becomes higher as the construction progresses, this can be easily accommodated by extending or expanding the second pipe.

[0035] Furthermore, according to another drainage method of the present invention, since the facility is a work passage, a work passage such as a catwalk can be utilized. [Industrial Applicability]

[0036] As described above, the drainage device and drainage method of the present invention are useful for green cutting work in dam concrete construction, and are particularly suitable for draining water used in green cutting work without utilizing the inside of the concrete and without interfering with concrete pouring work. [Explanation of symbols]

[0037] 10 Drainage system 12 Concrete joint surface 14 Drainage means 16 First piping 18 Second piping 20 Dam body (concrete structure) 22 Wall 24 Drain pipe 26 Drain 28 Catwalk (Facilities) 30 Water supply pipe 32 Catchment basin 34 Joint G. Ground L left bank R right bank

Claims

1. A drainage device for draining green cut work water for treating concrete joint surfaces generated when constructing concrete for a concrete dam body, The system comprises: drainage means provided on the outside of the concrete dam body for draining water used in green cutting work; a first pipe connected to the drainage means and arranged along equipment installed laterally on the downstream wall of the concrete dam body; a second pipe branching out from the first pipe at predetermined intervals and extending upward toward the concrete joint surface along the downstream wall of the concrete dam body and arranged so as to be extendable or expandable in the vertical direction; and a catchment basin provided at the upper end of the second pipe. The drainage means is installed on a slope of the natural ground on the left bank or the right bank on the downstream face side of the concrete dam body, and has a drainage pipe arranged along the slope, A drainage device characterized in that the first pipe extends in the dam axis direction of the concrete dam body and is inclined so that water flows naturally down inside from one side to the other, the other end of the first pipe is connected to the drainage pipe of the drainage means, and the one end of the first pipe is connected to a water supply pipe provided along the ground on the right bank or the left bank.

2. The drainage system according to claim 1, wherein the facility is a work passageway.

3. A drainage method for draining green cut work water for treating concrete joint surfaces generated when constructing concrete for a concrete dam body, comprising: The method comprises the steps of providing drainage means for draining water used in green cutting outside the concrete dam body, arranging a first pipe connected to the drainage means and along equipment installed laterally on the downstream wall of the concrete dam body, arranging second pipes branching out at predetermined intervals from the first pipe and extending upward toward the concrete joint surface along the downstream wall of the concrete dam body so that the second pipes can be extended or expanded in the vertical direction, and arranging a catchment basin at the upper end of the second pipe. The drainage means is installed on a slope of the natural ground on the left bank or the right bank on the downstream face side of the concrete dam body, and has a drainage pipe arranged along the slope, A drainage method characterized in that the first pipe extends in the dam axis direction of the concrete dam body and is inclined so that water flows naturally down inside from one side to the other, the other end of the first pipe is connected to the drainage pipe of the drainage means, and the one end of the first pipe is connected to a water supply pipe provided along the ground on the right bank or the left bank.

4. The drainage method according to claim 3, wherein the facility is a work passageway.

Citation Information

Patent Citations

  • Recovery method for laitance and sludge in green cut work

    JP1994081465A

  • Green cut working method

    JP1994081466A

  • Structure and method of carrying out green cut-muck

    JP1997059960A

  • Water sealing muck recovery device

    JP2004211493A

  • Decontamination device and decontamination method for radioactive contaminated rainwater

    JP2019032322A