Design and manufacturing methods for spill prevention fences

The design method for spill prevention fences optimizes pillar spacing and material selection to absorb collision energy efficiently, reducing costs and installation scale while ensuring structural integrity against large floating objects.

JP7590283B2Active Publication Date: 2024-11-26JAPAN RAILWAY KOBELCO BUILDING MATERIALS CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2021118184
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-07-16
Publication Date
2024-11-26
Estimated Expiration
2041-07-16

AI Technical Summary

Technical Problem

Existing spill prevention fences face challenges in effectively absorbing the high collision energy of large floating objects like ships and vehicles while maintaining cost-effectiveness and reducing installation scale.

Method used

A design method for spill prevention fences that involves setting pillar spacing to accommodate collision energy absorption by bending and deforming columns, using low-cost steel pipes, and selecting materials that can absorb collision and drag forces without plastic deformation.

Benefits of technology

The method reduces manufacturing costs and installation scale while enhancing the fences' ability to absorb collision energy from drifting objects, preventing plastic deformation and maintaining structural integrity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007590283000001
    Figure 0007590283000001
  • Figure 0007590283000002
    Figure 0007590283000002
  • Figure 0007590283000003
    Figure 0007590283000003
Patent Text Reader

Abstract

To provide a design method and a manufacturing method for an outflow prevention fence which can reduce a manufacturing cost, and suppress the scale of installation work while improving absorption capacity of collision energy.SOLUTION: A design method for an outflow prevention fence 1 includes: a collision energy acquisition step of acquiring a value of collision energy when a drift 102 collides with an outflow prevention fence 1; and a support material selection step of selecting, as a support material, a steel pipe capable of completely absorbing collision energy corresponding to a value acquired in the collision energy acquisition step in both a first collision energy absorption form of bending and deforming a first collided support 24 by collision of the drift 102 with the first collided support 24, bending and deforming two adjacent supports 25 by drawing, and thereby absorbing collision energy, and a second collision energy absorption form of bending and deforming two second collided supports 26 by collision of the drift 102 with two adjacent second collided supports 26, and thereby absorbing collision energy.SELECTED DRAWING: Figure 7
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for designing and manufacturing a drift prevention fence that prevents drifting objects swept away by waves from the quays of a port from being washed out to sea. [Background technology]

[0002] When a tsunami or high tide occurs, waves may surge over the quays of a port and sweep away ships, containers, vehicles, etc. that are on the quay and cause them to drift away. For this reason, outflow prevention fences that are installed on the quays of a port to capture such drifting objects and prevent them from drifting out to sea have been conventionally known. Patent Document 1 listed below discloses a drifting object capture fence as an example of such an outflow prevention fence.

[0003] The driftwood capture fence disclosed in Patent Document 1 below comprises two end posts arranged at both ends thereof, an intermediate post arranged between the two end posts, and a number of wire ropes stretched between the two end posts, passing through the intermediate posts. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent No. 6611320 Summary of the Invention [Problem to be solved by the invention]

[0005] However, drifting objects are large objects such as ships, containers, or vehicles, and when the drifting objects are captured by the outflow prevention fence, the collision energy of the drifting objects applied to the outflow prevention fence is very large, so the outflow prevention fence is required to have a high collision energy absorption capacity. It is possible to increase the collision energy absorption capacity of the outflow prevention fence by using high-strength materials for the posts that make up the posts of the outflow prevention fence, or by installing the posts at closer intervals to increase the number of posts that collide with the drifting objects, but in that case, there are problems such as increased manufacturing costs for the outflow prevention fence and an increase in the scale of construction work for installing the outflow prevention fence.

[0006] The object of the present invention is to provide a design and manufacturing method for an outflow prevention fence that improves the fence's ability to absorb the collision energy of driftwood while reducing the manufacturing costs and limiting the scale of installation work for the outflow prevention fence. [Means for solving the problem]

[0007] The design method of an outflow prevention fence provided by the present invention is a method for designing an outflow prevention fence having a plurality of posts erected at a predetermined interval on a quay wall of a port and a plurality of beams connecting adjacent posts of the plurality of posts, for preventing drifting objects swept away by waves from the quay wall from being washed away into the sea. This outflow prevention fence design method includes a collision energy acquisition process for acquiring the value of the collision energy when the drifting object collides with the outflow prevention fence, a post spacing setting process for setting the installation spacing of the plurality of posts to a spacing greater than half the width of the drifting object and smaller than the width of the drifting object, and a step of setting a first collided post, which is any one of the plurality of posts, so that the first collided post is bent and deformed so as to tilt, and the two adjacent posts on both sides of the first collided post are pulled by the bending deformation of the first collided post via the beams. and a pillar material selection process for selecting, as a pillar material for the pillar, a steel pipe capable of completely absorbing collision energy equivalent to the value acquired in the collision energy acquisition process in either a first collision energy absorption form in which the drifting object's collision energy is absorbed by bending and deforming so as to tilt, or a second collision energy absorption form in which the drifting object collides with two second collided pillars, which are adjacent pillars among the plurality of pillars, and the two second collided pillars are bent and deformed so as to tilt, thereby absorbing the collision energy of the drifting object.

[0008] According to this design method for an outflow prevention fence, even if a driftwood collide with only one first collided pillar or only two adjacent second collided pillars in a vertical or similar direction, which is a form that makes it difficult to absorb collision energy, a support material is selected that is capable of fully absorbing the collision energy of the driftwood, thereby improving the outflow prevention fence's ability to absorb the collision energy of the driftwood.In addition, because the support material is selected by specifying the absorption form of the collision energy of the driftwood to be completely absorbed by the joint bending deformation of two or three pillars, which limits the collision energy absorption capacity required for each pillar, low-cost steel pipes with reduced collision energy absorption capacity can be used as the support material for each pillar, reducing the manufacturing costs of the outflow prevention fence and preventing an excessive increase in the number of pillars installed, thereby reducing the scale of the outflow prevention fence installation work.

[0009] Specifically, in the design method of the driftwood prevention fence according to the present invention, in the post spacing setting process, the installation spacing of the multiple posts is set to a spacing greater than half the width of the driftwood and less than the width of the driftwood, so that the spacing between the posts is set so that when a driftwood collides with the driftwood prevention fence in the longitudinal direction along the length direction perpendicular to the width direction or in a direction close to that, it collides with only one of the posts, the first collided post, or only two adjacent second collided posts. Then, in the post material selection process, a first impact structure is set in which the driftwood collides with the first collided post, causing the first collided post to bend and deform, and the two adjacent posts on either side are pulled to bend and deform in response to the bending deformation of the first collided post, thereby absorbing the collision energy of the driftwood. In both the first collision energy absorption form and the second collision energy absorption form in which a drifting object collides with two adjacent second collided struts and the two second collided struts are bent and deformed to absorb the collision energy of the drifting object, a drifting object collision prevention fence can be designed that can absorb the collision energy of the drifting object even in a case where the drifting object collides with only one first collided strut or only two adjacent second collided struts in a vertical direction or a direction close to the vertical direction, which is a form that is difficult for absorbing collision energy, and the drifting object collision energy absorption capacity of the drifting object collision prevention fence can be improved. Moreover, in the design method according to the present invention, the absorption form of the collision energy of the drifting object, which is a premise for the design of the drifting object, is specified by setting the installation interval of the struts in the strut interval setting process, and the collision energy absorption capacity required for each strut can be limited thereby. This allows the use of low-cost steel pipes with reduced impact energy absorption capacity as the support material for each support, reducing the manufacturing cost of the outflow prevention fence. In addition, in order to increase the impact energy absorption capacity of the outflow prevention fence, it is possible to reduce the intervals between the supports and increase the number of supports that can collide with drifting objects when they collide vertically or in a direction close to that to three or more, but in this case, the scale of construction work for the outflow prevention fence will increase significantly.In contrast, in the design method of the present invention, the installation spacing of multiple posts is set to a spacing greater than half the width of the driftwood and less than the width of the driftwood in the post spacing setting process, so that the posts are installed at an appropriate spacing such that the number of posts with which the driftwood will collide is two or less, thereby preventing an increase in the scale of the construction work for installing the escape prevention fence due to an excessive increase in the number of posts.

[0010] The design method for the escape prevention fence further includes a first absorbed energy calculation process for calculating a first absorbed energy, which is the total absorbed energy by the first collided pillar and the two adjacent pillars when the first collided pillar bends and deforms from an upright position to a predetermined inclination angle and the two adjacent pillars bend and deform from an upright position to an inclination angle that is half the predetermined inclination angle in the first collision energy absorption form, and a second absorbed energy calculation process for calculating a second absorbed energy, which is the total absorbed energy by the two second collided pillars when both of the two second collided pillars bend and deform from an upright position to the predetermined inclination angle in the second collision energy absorption form, and it is preferable that in the pillar material selection process, a steel pipe is selected as the pillar material such that both of the calculated value of the first absorbed energy calculated in the first absorbed energy calculation process and the calculated value of the second absorbed energy calculated in the second absorbed energy calculation process are greater than the value of the collision energy acquired in the collision energy acquisition process.

[0011] In this way, a pillar material selection process can be realized in which a steel pipe capable of fully absorbing the value of the drifting object's collision energy acquired in the collision energy acquisition process can be selected as a pillar material in both the first collision energy absorption form and the second collision energy absorption form.

[0012] The design method for the outflow prevention fence further includes a resistance acquisition process for acquiring a value of resistance, which is the force when the driftwood pushes against the outflow prevention fence in a horizontal direction along its width after colliding with the outflow prevention fence, and in the support material selection process, it is preferable to select as the support material a steel pipe that satisfies the condition that it is capable of completely absorbing the collision energy equivalent to the value acquired in the collision energy acquisition process in both the first collision energy absorption form and the second collision energy absorption form, as well as the condition that it has an allowable bending stress that is greater than the bending stress acting on the support when a resistance equivalent to the value acquired in the resistance acquisition process acts on the outflow prevention fence.

[0013] This makes it possible to design an anti-overflow fence that can completely absorb the collision energy of the driftwood and prevent plastic bending deformation of the posts when the resistance force caused by the driftwood pushing laterally acts on the anti-overflow fence.

[0014] The design method for the escape prevention fence further includes a beam material selection process for selecting beam materials that constitute the beam, and in the beam material selection process, it is preferable to select as the beam material a component having an allowable bending stress that is greater than the bending stress acting on the beam when a resistance corresponding to the value acquired in the resistance acquisition process acts on the escape prevention fence.

[0015] This makes it possible to design an anti-flow fence that can prevent plastic bending deformation of the beam when the lateral resistance of drifting debris acts on the anti-flow fence.

[0016] It is preferable that the escape prevention fence has a beam fixing bolt that fixes the beam to the support, and the design method for the escape prevention fence further includes a beam fixing bolt selection process for selecting as the beam fixing bolt a bolt having an allowable shear stress greater than the shear stress acting on the beam fixing bolt when a resistance corresponding to the value acquired in the resistance acquisition process acts on the escape prevention fence.

[0017] In this way, an anti-flow fence can be designed that can maintain the beam's fixation to the support by the beam fixing bolts without damaging the beam fixing bolts when the lateral force of driftwood acts on the anti-flow fence.

[0018] The outflow prevention fence comprises steel pipe piles which are embedded in the ground of the wharf and which fix the bases of the posts which are inserted into the inside of the piles, and it is preferable that the design method for the outflow prevention fence further comprises a pile material selection process for selecting, as a pile material for the steel pipe piles, steel pipes which can prevent the steel pipe piles from tipping over in the ground of the wharf due to the overturning moment acting on the steel pipe piles when the driftwood collides with the outflow prevention fence, in accordance with the physical properties of the ground.

[0019] This makes it possible to design an outflow prevention fence that can prevent the steel pipe piles from tipping over in the ground of the wharf due to the overturning moment acting on the steel pipe piles when driftwood collides with the outflow prevention fence.

[0020] The outflow prevention fence has a post-fixing concrete that is provided inside the steel pipe pile and fixes the base of the post to the steel pipe pile, and the post has a post-embedding portion that is embedded in the post-fixing concrete, and it is preferable that the design method for the outflow prevention fence further includes a post-embedding length setting process that sets the length of the post-embedding portion so that the maximum compressive stress acting on the post-fixing concrete due to the bending moment generated in the post-embedding portion when the driftwood collides with the outflow prevention fence is smaller than a specified value of the short-term allowable compressive stress of concrete.

[0021] This makes it possible to design an anti-flow fence that can prevent the concrete fixing the posts from being compressed and damaged by the bending moment that occurs at the embedded part of the post when driftwood collides with the anti-flow fence.

[0022] A method for manufacturing an outflow prevention fence according to the present invention is a method for manufacturing an outflow prevention fence designed by the design method, in which a plurality of the posts, each of which is made of the steel pipe selected in the post material selection process, are erected on a quay wall of a port at the installation intervals set in the post interval setting process, and adjacent ones of the plurality of posts are connected with the beams to manufacture the outflow prevention fence.

[0023] According to this manufacturing method, for reasons similar to those of the design method described above, it is possible to produce an outflow prevention fence that improves the fence's ability to absorb the collision energy of driftwood, while reducing the manufacturing costs of the outflow prevention fence and limiting the scale of installation work for the outflow prevention fence. Effect of the Invention

[0024] As described above, according to the present invention, it is possible to provide a design and manufacturing method for an outflow prevention fence that improves the fence's ability to absorb the collision energy of driftwood while reducing the manufacturing costs of the outflow prevention fence and limiting the scale of construction work required to install the outflow prevention fence. [Brief description of the drawings]

[0025] [Figure 1] FIG. 2 is a front view of a spill prevention fence designed using a design method according to one embodiment of the present invention. [Diagram 2] FIG. 2 is a top view of the outflow prevention fence shown in FIG. 1. [Diagram 3] FIG. 2 is a cross-sectional view taken along line III-III in FIG. [Figure 4] This is a partially enlarged view showing the top of the intermediate support of the anti-flow fence shown in Figure 1 and the vicinity of the ends of the beams on both sides connected to it. [Diagram 5] This is a top view of the top of the intermediate support of the spill prevention fence shown in Figure 4 and the ends of the beams on both sides connected to it. [Figure 6] 4 is a partially enlarged view showing the vicinity of the top of the intermediate support in the cross-sectional view of FIG. 3. FIG. [Figure 7]1 is a schematic diagram showing a first collision mode when driftwood collides with a prevention fence, as viewed from above. FIG. [Figure 8] 13 is a schematic diagram showing a second collision mode when driftwood collides with a prevention fence, as viewed from above. FIG. [Figure 9] This is a diagram showing a schematic view from above of the deformation behavior of the first collided support pillar and two adjacent supports when a driftwood collides with the outflow prevention fence in the first collision mode shown in Figure 7. [Figure 10] 9 is a schematic diagram showing the deformation behavior of the two second impact pillars when a driftwood collides with the outflow prevention fence in the second collision mode shown in FIG. 8, viewed from above. [Figure 11] A diagram showing the bending deformation behavior of the first impact support when driftwood collides with the anti-floor fence. [Figure 12] This figure shows the bending deformation behavior of an adjacent support when driftwood collides with the prevention fence. [Figure 13] A diagram showing the bending deformation behavior of the second impact support when driftwood collides with the anti-floor fence. [Figure 14] This is a diagram showing a schematic view from above of the contact state between a driftwood and an outflow prevention fence when the driftwood pushes the outflow prevention fence laterally. [Figure 15] This is a diagram showing a schematic view from above of the contact state between a driftwood and an outflow prevention fence when the driftwood pushes the outflow prevention fence laterally. [Figure 16] This figure shows the state when a driftwood pushes against the outflow prevention fence laterally, causing a resistance force from the driftwood to act on the outflow prevention fence, as viewed from the direction along the extension direction of the beam. [Figure 17] FIG. 1 is a schematic diagram for explaining a method for calculating the overturning moment of a steel pipe pile, showing a steel pipe pile embedded in the ground of a quay wall as viewed from the side. [Figure 18] FIG. 1 is a schematic diagram for explaining a method for calculating the overturning moment of a steel pipe pile, showing the steel pipe pile as viewed from above. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0026] Hereinafter, an embodiment of the present invention will be described with reference to the drawings.

[0027] The outflow prevention fence 1 designed by the design method according to one embodiment of the present invention is installed on a quay 100 of a port as shown in FIG. 1, and captures drifting objects 102 (see FIG. 7, etc.) that are washed away by waves from the quay 100 and drift away to prevent the drifting objects 102 from flowing out to sea. In the design method according to this embodiment, a backwash of a tsunami, which is an example of a wave that tries to wash the drifting objects 102 from the quay 100 out to sea, is set as a target, and an outflow prevention fence 1 is designed to prevent the drifting objects 102 washed away by the backwash from flowing out to sea. The drifting objects 102 are ships, vehicles such as automobiles, or empty containers. The drifting objects 102 have a length that is a dimension in the longitudinal direction in a plan view, a width that is a dimension in a lateral direction perpendicular to the longitudinal direction in the plan view, and a height that is a dimension in a direction perpendicular to both the longitudinal direction and the lateral direction. If the drifting object 102 is a ship, the length is the overall length of the ship, the width is the overall width of the ship, and the height is the overall height of the ship. If the drifting object 102 is a vehicle, the length is the overall length of the vehicle, the width is the overall width of the vehicle, and the height is the overall height of the vehicle.

[0028] The runoff prevention fence 1 comprises a plurality of steel pipe piles 2, a plurality of posts 4, a plurality of beams 6, a plurality of beam fasteners 8 (see FIG. 4), and a plurality of concrete members 10 fixed to the posts.

[0029] The steel pipe piles 2 are embedded in the ground of the quay wall 100 at predetermined intervals along the seaward edge of the quay wall 100, and support and fix the bases 12a of the pillar bodies 12 of the pillars 4 inserted inside as described below. Each steel pipe pile 2 is made of a cylindrical steel pipe, and is embedded in the ground of the quay wall 100 in a position extending vertically.

[0030] The multiple pillars 4 are fixed to corresponding ones of the multiple steel pipe piles 2 and are erected at specified intervals along the sea-side edge of the quay wall 100. The multiple pillars 4 include a pair of end pillars 4a arranged on both ends of the runoff prevention fence 1, and multiple intermediate pillars 4b arranged between the pair of end pillars 4a.

[0031] Each end post 4 a has a post body 12 and one bracket 14 .

[0032] The pillar body 12 is made of a cylindrical steel pipe having an outer diameter smaller than the inner diameter of the steel pipe pile 2. The pillar body 12 has a base 12a that is inserted and fixed inside the corresponding steel pipe pile 2, and a top 12b that is the end opposite to the base 12a. As shown in FIG. 3, the base 12a is inserted into the inside of the steel pipe pile 2 embedded in the ground of the quay wall 100 with a gap between the inner peripheral surface of the steel pipe pile 2 and the outer peripheral surface of the base 12a, and is fixed in this state by the pillar fixing concrete 10 provided on the inside of the steel pipe pile 2. By fixing the base 12a in this way, the pillar body 12 is installed so as to extend upward in a substantially vertical direction from the upper surface of the quay wall 100. The pillar body 12 is arranged so that its base 12a is substantially concentric with the steel pipe pile 2 inserted inside (see FIG. 2).

[0033] The bracket 14 is a part to which the end of the beam 6 is connected and supports the end. The bracket 14 is attached to the outer circumferential surface of the top 12b of the support body 12 in a position protruding laterally from the top 12b. The bracket 14 is made of a curved plate material that forms a U-shape when viewed from a direction along the protruding direction of the bracket 14 from the support body 12. The bracket 14 is arranged so that the opening of the curved shape faces a direction perpendicular to both the protruding direction of the bracket 14 from the support body 12 and the axial direction (extension direction) of the support body 12. When the end support 4a is installed on the quay wall 100, the bracket 14 is arranged so that the opening of the curved shape faces the opposite side (land side) from the sea side. In addition, the bracket 14 has parts that face each other in the direction along the axial direction of the support body 12, and each of these parts has a through hole (not shown). The bracket 14 has a total of two pairs of through holes. Of the two pairs of through holes, one pair of through holes and the other pair of through holes are disposed spaced apart from each other in the direction in which the bracket 14 protrudes from the post body 12 .

[0034] The intermediate columns 4b are arranged at predetermined intervals between the pair of end columns 4a. Each intermediate column 4b has a column body 12 similar to the column body 12 of the end column 4a, and two brackets 18.

[0035] The pillar body 12 of the intermediate pillar 4b is made of a steel pipe similar to the pillar body 12 of the end pillar 4a. The pillar body 12 of the intermediate pillar 4b has a base 12a and a top 12b, similar to the pillar body 12 of the end pillar 4a, and is installed so as to extend upward in a substantially vertical direction from the upper surface of the quay wall 100 by being fixed by the pillar fixing concrete 10 provided on the inside of the steel pipe pile 2 with the base 12a inserted into the inside of the corresponding steel pipe pile 2. The pillar body 12 of the intermediate pillar 4b is also arranged so that its base 12a is substantially concentric with the steel pipe pile 2 into which it is inserted.

[0036] The two brackets 18 of the intermediate column 4b have the same structure as the bracket 14 of the end column 4a. One of the two brackets 18 is connected to an end of the beam 6 located on one side of the column body 12 to support that end, and the other bracket 18 is connected to an end of the beam 6 located on the other side of the column body 12 to support that end (see Figures 4 and 5). One bracket 18 is attached to the outer circumferential surface of the top 12b of the column body 12 of the intermediate column 4b in a position where it protrudes from the top 12b of the column body 12 of the intermediate column 4b to one side. The other bracket 18 is attached to the outer circumferential surface of the top 12b of the column body 12 of the intermediate column 4b in a position where it protrudes from the top 12b of the column body 12 of the intermediate column 4b to the opposite side to the one bracket 18. Moreover, the two brackets 18 are both arranged so that their curved openings face in a direction perpendicular to both the protruding direction of each of the two brackets 18 from the pillar body 12 and the axial direction (extension direction) of the pillar body 12 (see FIG. 6). When the intermediate pillar 4b is installed on the quay wall 100, the two brackets 18 are arranged so that their curved openings face the side opposite to the sea side (land side). Moreover, each of the two brackets 18 is provided with two pairs of through holes (not shown) similar to the bracket 14.

[0037] Each of the beams 6 is disposed between adjacent columns 4 to connect the adjacent columns 4. Each beam 6 is made of a cylindrical steel pipe and disposed between adjacent columns 4 in a position extending substantially horizontally. In other words, each beam 6 is disposed perpendicular to the adjacent columns 4 between which it is disposed. Both ends of each beam 6 in the axial direction (extension direction) are disposed inside the curved brackets 14, 18 of the corresponding column 4 and supported by the brackets 14, 18, and in this state are fastened and fixed to the brackets 14, 18 by beam fasteners 8.

[0038] Specifically, two pairs of insertion holes (not shown) are provided at both ends of each beam 6, penetrating the tube walls at both ends in the radial direction of the beam 6. One pair of the two pairs of insertion holes is disposed opposite each other in the radial direction of the beam 6. The other pair of insertion holes is disposed opposite each other in the radial direction of the beam 6, at a position spaced apart from the pair of insertion holes in the axial direction of the beam 6.

[0039] The multiple beam fasteners 8 fasten the ends of the beams 6 to the corresponding brackets 14, 18. Specifically, each beam fastener 8 is composed of a beam fixing bolt 20 and a beam fixing nut 22 that fix the ends of the beams 6 to the brackets 14, 18 of the support 4.

[0040] A beam fixing bolt 20 is inserted through a pair of through holes (not shown) provided in each bracket 14, 18 and a pair of insertion holes (not shown) provided in the end of the beam 6 supported by that bracket 14, 18, and another beam fixing bolt 20 is inserted through the other through hole (not shown) provided in that bracket 14, 18 and another pair of insertion holes (not shown) provided in the end of the beam 6 supported by that bracket 14, 18. Then, beam fixing nuts 22 are screwed onto each of the beam fixing bolts 20 and tightened, thereby fastening each bracket 14, 18 to the end of the beam 6 supported thereby.

[0041] Next, a design method according to one embodiment of the present invention for designing the outflow prevention fence 1 having the above-mentioned configuration will be described.

[0042] In the design method according to this embodiment, the outflow prevention fence 1 is designed based on the specifications of the driftwood 102 to be captured by the outflow prevention fence 1 and the local conditions of the seawater flow and ground in the harbor where the outflow prevention fence 1 is to be installed. The design method according to this embodiment includes a process of obtaining design conditions, a process of obtaining collision energy, a process of obtaining resistance, a process of setting the support pillar interval, a process of selecting components, and a process of setting the support pillar embedment length.

[0043] In the process of obtaining the design conditions, the following design conditions are obtained: the specifications of the driftwood 102 to be captured by the spillway prevention fence 1, and on-site conditions including conditions related to the seawater flow that will drift the driftwood 102 in the harbor where the spillway prevention fence 1 is to be installed, and conditions related to the ground of the quay 100.

[0044] The above-mentioned specifications of the drifting object 102 are the length L of the drifting object 102 (ship, vehicle, empty container, etc.) set as the capture target by the drifting object 1 when designing the drifting object 1. o (the longitudinal dimension of the drifting object 102 in a plan view), width B o (the dimension in the short direction perpendicular to the longitudinal direction of the drifting object 102 in a plan view), and the height H o , and mass W o and the draft D of the drifting object 102 when the drifting object 102 floats on the seawater. o (the distance from the bottom of the drifting object 102 to the water surface).

[0045] Among the on-site conditions, the conditions related to the current of the seawater that causes the drifting object 102 to drift are the speed V of the current of the seawater that causes the drifting object 102 to drift (the speed V of the current of the seawater that the drifting object 102 receives due to the backwash of the tsunami) and the drag coefficient C of the seawater when the drifting object 102 drifts. w and the flood depth H, which is the depth of the seawater on the quay 100 into which the seawater that drifts the drifting object 102 is flooded (the distance from the flooded seawater level to the top surface of the quay 100).

[0046] Among the on-site conditions, the conditions relating to the ground of the quay wall 100 are the weight per unit volume γ of the ground of the quay wall 100, the adhesion C of the ground of the quay wall 100, the internal friction angle φ of the ground of the quay wall 100, and the N-value of the ground of the quay wall 100 obtained by a standard penetration test.

[0047] The collision energy acquisition process acquires a value of collision energy when the drifting object 102 collides with the outflow prevention fence 1. In this embodiment, the collision energy acquisition process acquires a value of collision energy when the drifting object 102 collides with the outflow prevention fence 1 by calculating the value based on the specifications of the drifting object 102 acquired in the design condition acquisition process and the conditions related to the seawater flow that causes the drifting object 102 to drift, which are among the on-site conditions.

[0048] There are two types of collision of the drifting object 102: a first collision type in which the drifting object 102 drifts along its length and collides with the outflow prevention fence 1 in a vertical direction perpendicular to the direction in which the posts 4 of the outflow prevention fence 1 are aligned, and a second collision type in which the drifting object 102 drifts while rotating slightly in a plan view and collides with the outflow prevention fence 1 with its length direction inclined diagonally to the direction in which the posts 4 of the outflow prevention fence 1 are aligned. When the drifting object 102 collides with the outflow prevention fence 1 in the first collision type, the collision energy E of the drifting object 102 is calculated by the following formula (1), and when the drifting object 102 collides in the second collision type, the collision energy E of the drifting object 102 is calculated by the following formula (2). E=n W V 2 / (2 g) (1) E=n W V 2 / (4 g) (2)

[0049] When the drifting object 102 is a ship, the ship generally drifts with the current of seawater while rotating due to the irregular flow direction of the tsunami, and therefore the collision mode is generally the second collision mode. Therefore, when the drifting object 102 is a ship, the collision energy E of the drifting object 102 is usually calculated by the above formula (2). However, even when the drifting object 102 is a ship, if priority is given to designing the outflow prevention fence 1 so as to increase the certainty of absorbing the collision energy of the drifting object 102, the collision energy E of the drifting object 102 is calculated by the above formula (1) corresponding to the first collision mode in which the value of the collision energy is large.

[0050] Furthermore, when the drifting object 102 is a vehicle or an empty container, the vehicle or container generally drifts with the current of the seawater without causing any rotational motion even if the flow direction of the tsunami is irregular, so the collision type is generally the first collision type. Therefore, when the drifting object 102 is a vehicle or an empty container, the collision energy E of the drifting object 102 is usually calculated by the above formula (1). However, even if the drifting object 102 is a vehicle or an empty container, if it is expected that the vehicle or container will drift while rotating due to some factor, the collision energy E of the drifting object 102 is calculated by the above formula (2) corresponding to the second collision type.

[0051] In the above formulas (1) and (2), n is the number of collisions of the drifting object 102 with the outflow prevention fence 1. For example, after the drifting object 102 initially collides with the outflow prevention fence 1, the drifting object 102 may bounce back and repeatedly collide with the outflow prevention fence 1. In the case where such repeated collisions are assumed and an outflow prevention fence 1 is designed to cope with such a case, the number of collisions is used as the value of n. In the case where the drifting object 102 collides with the outflow prevention fence 1 only once and an outflow prevention fence 1 is designed to cope with such a case, 1 is used as the value of n. In the above formulas (1) and (2), W is the virtual weight of the drifting object 102 when it drifts, V is the speed of the seawater flow that causes the drifting object 102 to drift, which is one of the conditions related to the seawater flow in the on-site conditions, and g is the gravitational acceleration.

[0052] The virtual weight W of the drifting object 102 is calculated by subtracting the mass W of the drifting object 102 from the parameters of the drifting object 102. o , length L o and draft D o and the specified unit weight of seawater γ w and the circular constant π, using the following equation (3): W=W o +(π / 4) D o 2 L o ·γ w (3)

[0053] In the resistance acquisition process, a value of resistance is acquired, which is a force applied when the drifting object 102 pushes against the outflow prevention fence 1 in a lateral direction along the width direction of the drifting object 102 after colliding with the outflow prevention fence 1. In this embodiment, in the resistance acquisition process, a value of resistance is calculated with which the drifting object 102 pushes against the outflow prevention fence 1 in the lateral direction due to the flow of seawater acting on the drifting object 102 due to the backwash of the tsunami. This is because, after colliding with the outflow prevention fence 1, the drifting object 102 often turns sideways due to the influence of the seawater flow and comes into contact with the outflow prevention fence 1, and continues to push against the outflow prevention fence 1 in the lateral direction due to the flow of seawater, and therefore the value of the resistance of the drifting object 102 in such a lateral direction is calculated. This resistance F is calculated based on the drag coefficient C w , the flood depth H, the velocity V of the seawater flow that drifts the drifting object 102, the shielding ratio φ, which is the ratio of the space between the posts 4 of the outflow prevention fence 1 through which seawater can pass, that is, the shielding ratio by the drifting object 102 pushing the outflow prevention fence 1 in the lateral direction, and the unit volume weight γ of seawater, which is a specified value. w and the gravitational acceleration g, it is calculated by the following equation (4). F=C w φ γ w H V 2 / (2 g) (4)

[0054] When emphasis is placed on increasing the reliability of preventing plastic bending deformation of the posts 4 due to the resistance of the driftwood 102 pushing laterally against the outflow prevention fence 1, the resistance F may be calculated by setting a condition for shielding by the driftwood 102 in the lateral direction, that is, the condition under which the resistance applied from the driftwood 102 to the outflow prevention fence 1 is maximized, that is, that all spaces between the posts 4 of the outflow prevention fence 1 are shielded by the driftwood 102 in the lateral direction. In this case, 1 is applied to the shielding rate φ in the formula (4) for calculating the resistance F.

[0055] In the post spacing setting process, the installation intervals of the multiple posts 4 included in the outflow prevention fence 1 are set to intervals that are greater than half the width of the drifting object 102 and smaller than the width of the drifting object 102. In other words, the installation intervals of the posts 4 are set so that when the drifting object 102 collides with the outflow prevention fence 1 in the vertical direction, it will collide with one of the multiple posts 4 included in the outflow prevention fence 1 or two adjacent posts 4.

[0056] In addition, in the component member selection process, the component member selection process is performed to select members that constitute the runoff prevention fence 1. This component member selection process includes a post material selection process, a beam material selection process, a beam fixing bolt selection process, and a pile material selection process.

[0057] The pillar material selection process is a process for selecting pillar materials that constitute the pillar body 12 of each pillar 4. In this pillar material selection process, two types of collision energy absorption mode (see FIG. 9) are selected, in which the drifting object 102 vertically collides with only the first collided pillar 24, which is any one of the multiple pillars 4 (intermediate pillars 4b) of the outflow prevention fence 1, and the drifting object 102 vertically collides with only the second collided pillars 26, which are two adjacent pillars 4 (intermediate pillars 4b) of the outflow prevention fence 1, in the first collision mode (see FIG. 7). In either the first collision energy acquisition process or the second collision energy absorption form (see Figure 10) which absorbs the collision energy of the driftwood 102, a steel pipe capable of completely absorbing collision energy equivalent to the value of the collision energy acquired in the collision energy acquisition process and capable of preventing plastic bending deformation of the pillar body 12 of each pillar 4 when a resistance equivalent to the value of the resistance acquired in the resistance acquisition process acts on the outflow prevention fence 1 is selected as the pillar material constituting the pillar body 12 of each pillar 4.

[0058] Specifically, in the first collision energy absorption form (see Figure 9) when a driftwood 102 collides with the prevention fence 1 in the first collision form, the first collided support 24 bends and deforms so that it tilts at a predetermined angle (15° in this embodiment) in the collision direction of the driftwood 102, and the two adjacent supports 25, which are the supports 4 on either side of the first collided support 24, are pulled by the bending deformation of the first collided support 24 via the beam 6 and bend and deform so that they tilt at an angle of half the predetermined angle (7.5° in this embodiment) in the collision direction of the driftwood 102, thereby absorbing the collision energy of the driftwood 102. In addition, in the second collision energy absorption form (see Figure 10) when the driftwood 102 collides with the anti-flow fence 1 in the second collision form, the two adjacent second collision supports 26 are bent and deformed so as to tilt at a predetermined angle (15° in this embodiment) in the collision direction of the driftwood 102, thereby absorbing the collision energy of the driftwood 102.

[0059] The component member selection process of the design method according to this embodiment includes a first absorbed energy calculation process, assuming that steel pipes as candidate pillar materials are applied to the pillar body 12 of each pillar 4, for calculating a first absorbed energy, which is the total absorbed energy by the first struck pillar 24 and the two adjacent pillars 25 when the first struck pillar 24 bends and deforms from an upright position to a predetermined angle and the two adjacent pillars 25 bend and deform from an upright position to an angle that is half of the predetermined angle, in the first collision energy absorption form, and a second absorbed energy calculation process, which calculates a second absorbed energy, which is the total absorbed energy by the two second struck pillars 26 when both of them bend and deform from an upright position to the predetermined angle in the second collision energy absorption form.

[0060] Then, in the pillar material selection process, if both the calculated value of the first absorbed energy calculated in the first absorbed energy calculation process and the calculated value of the second absorbed energy calculated in the second absorbed energy calculation process are greater than the value of the collision energy acquired in the collision energy acquisition process, i.e., if the smaller of the calculated first absorbed energy and second absorbed energy is greater than the calculated value of the collision energy, it is determined that if the steel pipe candidate for the pillar material is applied to the pillar body 12 of each pillar 4, it will be possible to completely absorb the collision energy when the driftwood 102 collides in the vertical direction, and it is determined that the steel pipe candidate for the pillar material can be applied to the pillar body 12 of each pillar 4. On the other hand, if at least one of the calculated first absorbed energy and second absorbed energy is less than or equal to the value of the collision energy acquired in the collision energy acquisition process, i.e., if the value of the smaller of the calculated first absorbed energy and second absorbed energy is less than or equal to the calculated value of the collision energy, it is determined that if the steel pipe candidate for the pillar material is applied to the pillar body 12 of each pillar 4, it may not be able to fully absorb the collision energy when the driftwood 102 collides in the vertical direction, and it is determined that the steel pipe candidate for the pillar material cannot be applied to the pillar body 12 of each pillar 4.

[0061] The first absorbed energy EP1 is calculated by the following formula (5). EP1=F y δ 15 +2·F y δ 7.5 (5)

[0062] In this formula (5), δ 15 is the horizontal displacement of the load application position, which is the height position at which the load of the collision of the drifting object 102 acts, when the pillar body 12 of the first collided pillar 24 is bent and deformed so as to tilt at 15° from the upright position as shown in Fig. 11 due to the collision of the drifting object 102, and is calculated from the height h1 of the load application position from the upper surface of the wharf 100 by the following formula (6). In this embodiment, the height h1 of the load application position is assumed to be equal to the height of the runoff prevention fence 1 from the upper surface of the wharf 100. δ 15 =h1 tan15° (6)

[0063] In addition, in formula (5), δ 7.5 is the horizontal displacement of the load application position when the pillar body 12 of the adjacent pillar 25 is bent and deformed so as to tilt 7.5° from the upright position as shown in Figure 12 due to the above-mentioned bending deformation of the first collided pillar 24, and is calculated from the height h1 of the load application position from the top surface of the quay wall 100 using the following equation (7). δ 7.5 =h1 tan 7.5° (7)

[0064] In addition, in the formula (5), F y is the yield external force of the pillar body 12 (pillar material). This yield external force F y is calculated by the following equation (8). F y =(Z p σ yd ) / h1···(8)

[0065] In this formula (8), Z p is the section modulus of the pillar body 12 (pillar material) in plastic state, and is calculated from the diameter D1 of the steel pipe candidate for the pillar material and the thickness t1 of the wall of that steel pipe by the following formula (9). Z p =1 / 6 D1 3 {1-(1-2 t1 / D1) 3} ···(9)

[0066] In addition, in the formula (8), σ yd is the dynamic yield stress of the column body 12 (column material), and the yield stress σ of the column body 12 (column material) is expressed by the following equation (10): y This can be calculated by multiplying by 1.2. σ yd =1.2σ y (10)

[0067] The yield stress σ yWhen the steel pipe candidate for the pillar material is, for example, a general structural carbon steel pipe STK400 specified in JIS G 3444, and the ratio D1 / t1 of the diameter D1 of the steel pipe to the pipe wall thickness t1 is greater than 8 and less than 110, is calculated by the following formula (11). σ y =527.5 (D1 / t1) -0.104 (11)

[0068] In addition, when the steel pipe candidate for the support material is a general structural carbon steel pipe STK490 specified in JIS G 3444, and the ratio D1 / t1 of the diameter D1 of the steel pipe to the thickness t1 of the pipe wall is greater than 8 and less than 110, the yield stress σ y is calculated by the following equation (12). σ y =703.3 (D1 / t1) -0.104 (12)

[0069] Moreover, the second absorbed energy EP2 is calculated by the following formula (13). EP2=2·F y δ 15 (13)

[0070] In this formula (13), δ 15 is the horizontal displacement of the load acting height position when the support body 12 of the second support pillar 26 is bent and deformed so as to tilt by 15° from the upright position as shown in FIG. 13 due to the collision of the driftwood 102, and the displacement δ used in the above formula (5) is 15 Similarly, it is calculated by the above formula (6). In addition, in formula (13), F y is the yield force F used in the above formula (5). y Similarly, this is the yield external force of the pillar body 12 (pillar material) and is calculated by the above formula (8).

[0071] In addition, when selecting a support material capable of preventing plastic bending deformation of the support body 12 of each support 4 when a resistance equivalent to the resistance value obtained in the resistance acquisition process acts on the outflow prevention fence 1, the bending stress acting on the support body 12 of each support 4 that is involved (in contact with) the lateral driftwood 102 that exerts the resistance when a resistance equivalent to the resistance value obtained in the resistance acquisition process acts on the outflow prevention fence 1 is calculated, and a steel pipe having a short-term allowable bending stress greater than the calculated bending stress is selected as the support material for the support body 12 of each support 4.

[0072] The bending stress σ acting on the strut body 12 of each strut 4 involved in the lateral drifting object 102 exerting the drag force p is calculated by the following equation (14). σ p =M p / Z1···(14)

[0073] In this formula (14), Z1 is the section modulus of the column material constituting the column body 12, that is, the section modulus of the steel pipe candidate for the column material. p is the bending moment acting on the pillar body 12, and is calculated by the following equation (15). M p =F' / h1 (15)

[0074] In this formula (15), F' is the resistance acting on the pillar body 12 of each pillar 4 when the drifting object 102 floating sideways in a drifting state pushes the outflow prevention fence 1 as shown in FIG. 16, and is a value obtained by dividing the value of the resistance obtained in the resistance acquisition process by the number of spans between the pillars 4 involved when the drifting object 102 pushes the outflow prevention fence 1 in the horizontal direction (the number of involved spans). For example, when the drifting object 102 pushes the outflow prevention fence 1 in the horizontal direction with both ends of the drifting object 102 positioned between adjacent pillars 4 as shown in FIG. 14, the spans involved by both ends of the drifting object 102 in the vertical direction are considered to be 0.5 each, and the number of involved spans of the drifting object 102 is set to 6. In addition, when the drifting object 102 pushes the outflow prevention fence 1 in the horizontal direction so that both ends of the drifting object 102 in the vertical direction hit the corresponding pillars 4 as shown in FIG. 15, the number of involved spans of the drifting object 102 is also 6.

[0075] The bending stress σ of the steel pipes that are candidates for the support material is calculated as above. p If the steel pipe has a short-term allowable bending stress greater than σ, it is determined that applying that steel pipe to the support body 12 of each support 4 will prevent plastic bending deformation from occurring in the support body 12 of the support 4 involved when the drag force of the driftwood 102 pushing the outflow prevention fence 1 in the lateral direction acts on the outflow prevention fence 1, and therefore it is determined that the steel pipe can be applied to the support body 12 of each support 4. On the other hand, if the steel pipe candidate for the support material has a bending stress σ calculated as above, p If the steel pipe has the following short-term allowable bending stress, it is determined that if the steel pipe is applied to the pillar body 12 of each pillar 4, it will not be possible to prevent plastic bending deformation from occurring in the pillar body 12 of the pillar 4 involved when the resisting force of the driftwood 102 pushing laterally against the outflow prevention fence 1 acts on the outflow prevention fence 1, and therefore it is determined that the steel pipe cannot be applied to the pillar body 12 of each pillar 4.

[0076] Then, in the selection of pillar materials capable of absorbing the collision energy equivalent to the value of the collision energy acquired in the collision energy acquisition process, a steel pipe that is determined to be applicable to the pillar body 12 of each pillar 4 and that is determined to be applicable to the pillar body 12 of each pillar 4 in the selection of pillar materials capable of preventing plastic bending deformation of the pillar body 12 of each pillar 4 when a resistance equivalent to the value of the resistance acquired in the resistance acquisition process acts on the escape prevention fence 1 is adopted as the pillar material that constitutes the pillar body 12 of each pillar 4.

[0077] The beam material selection process is a process for selecting beam materials constituting each beam 6. In this beam material selection process, a steel pipe capable of preventing plastic bending deformation of each beam 6 when a resistance equivalent to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 is selected as the beam material of each beam 6. Specifically, in this beam material selection process, a bending stress acting on each beam 6 involving a lateral drifting object 102 exerting a resistance equivalent to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 is calculated, and a steel pipe having a short-term allowable bending stress greater than the calculated bending stress acting on each beam 6 is selected as the beam material of each beam 6.

[0078] The bending stress σ acting on each beam 6 involved in the transverse drifting object 102 exerting the drag force b is calculated by the following equation (16). σ b =M b / Z2···(16)

[0079] In this formula (16), Z2 is the section modulus of the beam material constituting the beam 6, that is, the section modulus of the steel pipe candidate for the beam material. Also, M b is the bending moment acting on the beam 6 and is calculated by the following equation (17). M b =(F' S) / (4 N) (17)

[0080] In this formula (17), S is the distance between adjacent posts 4. N is the number of beams 6 in the height direction of the outflow prevention fence 1, and in this embodiment, the number of beams 6 is 1. Furthermore, F' is the resistance acting on each beam 6, and is a value obtained by dividing the value of the resistance acquired in the resistance acquisition process by the number of beams 6 involved when the driftwood 102 pushes the outflow prevention fence 1 in the lateral direction. The number of beams 6 involved when the driftwood 102 pushes the outflow prevention fence 1 in the lateral direction is the same as the number of spans involved when the driftwood 102 pushes the outflow prevention fence 1 in the lateral direction. For this reason, the same value as F' in formula (17) is used as F' in formula (15).

[0081] The bending stress σ of the steel pipe that is the candidate for the beam material is calculated as above. b If the steel pipe has a short-term allowable bending stress greater than σ, it is determined that applying that steel pipe to each beam 6 will prevent plastic bending deformation in the beam 6 involved when the drag force of the drifting object 102 pushing the outflow prevention fence 1 in the lateral direction acts on the outflow prevention fence 1, and the steel pipe is adopted as the beam material for each beam 6. On the other hand, if the steel pipe candidate for the beam material has a bending stress σ calculated as above, b If the steel pipe has the following short-term allowable bending stress, it is determined that if the steel pipe is applied to each beam 6, it will not be possible to prevent plastic bending deformation from occurring in the beam 6 involved when the resistance force caused by the driftwood 102 pushing laterally against the outflow prevention fence 1 acts on the outflow prevention fence 1, and therefore the steel pipe will not be adopted as the beam material for each beam 6.

[0082] The beam fixing bolt selection process is a process for selecting a bolt to be used as the beam fixing bolt 20 of the beam fastener 8. In this beam fixing bolt selection process, a bolt that can prevent the beam fixing bolt 20 of each beam fastener 8 from being damaged when a resistance corresponding to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 is selected as the beam fixing bolt 20. Specifically, in this beam fixing bolt selection process, a shear stress that acts on the beam fixing bolt 20 when a resistance corresponding to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 is calculated, and a bolt having a short-term allowable shear stress intensity greater than the calculated shear stress is selected as the bolt to be used as the beam fixing bolt 20.

[0083] The shear stress τ acting on the beam fixing bolt 20 is calculated by the following equation (18). τ=F' / (A N b ) ···(18)

[0084] In this formula (18), A is the effective cross-sectional area of ​​the beam fixing bolt 20. b is the number of beam fixing bolts 20 that fix one beam 6, which is 4 in this embodiment. Also, F' in this equation (18) is the resistance acting on one beam 6, and uses the same value as F' in the above equation (17).

[0085] If a candidate bolt to be adopted as the beam fixing bolt 20 has a short-term allowable shear stress intensity greater than the shear stress τ calculated as above, it is determined that if that bolt is adopted as the beam fixing bolt 20, damage to the beam fixing bolt 20 can be avoided when the drag force of the driftwood 102 pushing laterally against the outflow prevention fence 1 acts on the outflow prevention fence 1, and so that bolt is adopted as the beam fixing bolt 20. On the other hand, if a candidate bolt to be adopted as the beam fixing bolt 20 has a short-term allowable shear stress intensity equal to or less than the shear stress τ calculated as above, it is determined that if that bolt is adopted as the beam fixing bolt 20, damage to the beam fixing bolt 20 may occur when the drag force of the driftwood 102 pushing laterally against the outflow prevention fence 1 acts on the outflow prevention fence 1, and so that bolt is not adopted as the beam fixing bolt 20.

[0086] The pile material selection process is a process for selecting pile materials constituting each steel pipe pile 2. In this pile material selection process, a steel pipe capable of preventing the steel pipe pile 2 from falling in the ground of the wharf 100 due to the force applied to the outflow prevention fence 1 when a drifting object 102 collides with the outflow prevention fence 1 in the vertical direction and capable of preventing the steel pipe pile 2 from sinking in the ground due to the own weight of the outflow prevention fence 1 is selected as the pile material of each steel pipe pile 2. Specifically, this pile material selection process includes the selection of a pile material capable of preventing the wharf 100 from falling in the ground and the selection of a pile material capable of preventing the wharf 100 from sinking in the ground.

[0087] First, in selecting pile materials that can prevent overturning in the ground, the safety factor F against overturning of the steel pipe pile 2, calculated by the following formula (19), is s Steel pipes with a value of 1.5 or more are selected as pile materials. F s =M r / M2···(19)

[0088] In this formula (19), M2 is the overturning moment acting on the steel pipe pile 2 when the drifting object 102 collides with the outflow prevention fence 1 in the vertical direction. This overturning moment M2 is calculated by the yield external force F of the pillar body 12 calculated by the above formula (8). yThe height h1 of the load application position and the embedded length L2 of the steel pipe pile 2 are used to calculate the embedded length L2 of the steel pipe pile 2 according to the following formula (20). In this embodiment, the steel pipe pile 2 is embedded in the ground of the quay wall 100 so that the upper end of the steel pipe pile 2 is aligned with the upper surface of the quay wall 100, so that the embedded length L2 of the steel pipe pile 2 is set to a length equal to the length of the steel pipe candidate to be used as the pile material. M2=F y (h1+0.7 L2) (20)

[0089] In addition, in the formula (19), M r is the moment that resists the overturning of the steel pipe pile 2 embedded in the ground of the quay wall 100. This moment M r is the embedment length L2 of the steel pipe pile 2 and the ultimate horizontal bearing capacity R of the ground of the quay wall 100 into which the steel pipe pile 2 is embedded. p and the ultimate horizontal bearing capacity S of the bottom of the steel pipe pile 2 u and the unbalanced force P in the horizontal direction, is calculated by the following equation (21). M r =1 / 3 0.7 L2 R p +0.3 L2 S u +1 / 2 0.3 L2 P (21)

[0090] Ultimate horizontal bearing capacity R of the ground p is calculated by the following equation (22). R p ={W A ·(cosα+sinα·tanφ)+C·Ac} / (sinα-cosα·tanφ) ···(22)

[0091] In this formula (22), α is the slip angle, and more specifically, it is the angle between the steel pipe pile 2 and a slip surface 104, which is the boundary surface between part A (sliding soil mass: the part hatched with dots in Fig. 17) that is pushed and moved by the steel pipe pile 2 when driftwood 102 in the ground of the wharf 100 collides vertically with the outflow prevention fence 1 and an overturning moment acts on the steel pipe pile 2, and the immovable ground. φ is the internal friction angle of the ground of the wharf 100 among the conditions related to the ground of the wharf 100 in the on-site conditions, and C is the adhesion of the ground of the wharf 100 among the conditions related to the ground of the wharf 100.

[0092] In addition, in the formula (22), W A is the weight of the part A and is calculated by the following formula (23). W A =[{0.7·L2·c1·d1·(1 / 2)·(1 / 3)·2+0.7·L2·c1·(1 / 2)·D2}-{f·g·j·(1 / 2)·(1 / 3)·2}]·γ ···(23)

[0093] In this formula (23), c1 is the distance from the upper end of the steel pipe pile 2 to the slide surface 104 in the horizontal direction. Additionally, d1 (see FIG. 18) is the spread width of the slide surface 104 at the same height as the upper end of the steel pipe pile 2. Additionally, L2 (see FIG. 17) is the embedded length of the steel pipe pile 2, and D2 is the diameter of the steel pipe that is the candidate for the pile material. Furthermore, f, g, and j (see Figures 17 and 18) are values ​​indicating the dimensions of an overlapping portion of part A of the ground that is pushed and moved by a steel pipe pile 2 when an overturning moment acts on the steel pipe pile 2 and that overlaps with part A of the ground that is pushed and moved by the adjacent steel pipe pile 2 when an overturning moment acts on the adjacent steel pipe pile 2 in a similar manner, where f is the dimension of the overlapping portion in the direction perpendicular to the arrangement and height directions of the steel pipe piles 2, g is the dimension of the overlapping portion in the height direction, and j is the dimension of the overlapping portion in the arrangement direction of the steel pipe piles 2. Furthermore, γ is the weight per unit volume of the ground of the quay wall 100 among the conditions related to the ground of the on-site conditions.

[0094] In addition, in the formula (22), Ac is the area of ​​the slide surface 104, and is calculated by the following formula (24). Ac=(d1+D2)·l1-(j 2 l1) / d1 (24)

[0095] The values ​​of d1, D2, and j in this formula (24) are the same as those of d1, D2, and j described above. In addition, in formula (24), l1 is the length in the direction along the slope of the slide surface 104 from the lower end of the slide surface 104 that contacts the steel pipe pile 2 to the same height position as the upper end of the steel pipe pile 2 (the height position of the upper surface of the wharf 100).

[0096] In addition, the ultimate horizontal bearing capacity S of the bottom surface of the steel pipe pile 2 in the above formula (21) u is the weight N of the support 4 made of the steel pipe selected in the support material selection process. w The embedded length L1 of the support 4, which is set in the support embedded length setting process as described below, and the weight per unit length of the steel pipe of the pile candidate W w From the embedment length L2 of the steel pipe pile 2 and the internal friction angle φ of the ground of the quay wall 100 among the conditions related to the ground of the quay wall 100 in the on-site conditions, the following formula (25) is used to calculate the embedment length L2 of the steel pipe pile 2 and the internal friction angle φ of the ground of the quay wall 100. S u ={N w (h1+L1)+W w ·L2}·tan{(2 / 3)·φ} ···(25)

[0097] In addition, in the above formula (21), the unbalanced force P in the horizontal direction is calculated by dividing the ultimate horizontal bearing capacity R of the ground of the quay wall 100 calculated as described above. p and the yield external force F of the support body 12 y and the ultimate horizontal bearing capacity S of the bottom surface of the steel pipe pile 2 calculated by the above formula (25) u From this, it is calculated by the following equation (26). P=R p -F y -S u (26)

[0098] In addition, in selecting a pile material capable of preventing sinking in the ground, the necessary pile length L, which is the length of the steel pipe pile 2 required to prevent the steel pipe pile 2 from sinking in the ground of the quay wall 100 in the vertical direction, which is its extension direction, is selected. a Calculate the required pile length L using the following formula (27). a In the following formula (27), the weight N of the support 4 using the steel pipe selected in the support material selection process is calculated. w The height H1 of the runoff prevention fence 1 from the top surface of the wharf 100, the embedded length L1 of the support 4 set in the support embedded length setting process as described below, and the weight W per unit length of the steel pipe candidate for the pile material. w The embedded length L2 of the steel pipe pile 2, the safety factor sf, the perimeter U of the steel pipe of the pile material candidate, and the peripheral friction force f acting on the steel pipe pile 2 embedded in the ground of the quay wall 100 i Therefore, the required pile length L a is calculated. L a ={N w (H1+L1)+W w L2}sf / (Uf i ) ···(27)

[0099] In this equation (27), the safety factor sf is set to 3. This condition of safety factor sf = 3 is a condition that makes it possible to prevent the friction piles in the ground from sinking even during an earthquake.

[0100] Further, the circumferential length U of the steel pipe of the candidate pile material is calculated from the diameter D2 of the steel pipe of the candidate pile material and pi by the following formula (28). U = D2 π (28)

[0101] In addition, the peripheral friction force f i is twice the N value (2N) of the ground of the quay 100 among the conditions related to the ground in the above-mentioned site conditions. i The value is applied when the geology of the ground of the wharf 100 is sandy soil and the steel pipe pile 2 is installed in the ground by the inner excavation pile construction method.

[0102] In addition, in the selection of pile materials capable of preventing overturning in the ground, the safety factor F s The pile material is selected as a pile material that is capable of preventing sinking in the ground and has a necessary pile length L a The steel pipe selected as the pile material because it has a length greater than is adopted as the pile material for the steel pipe pile 2.

[0103] The pillar embedment length setting process is a process for setting the length of the pillar embedment portion 30, which is the portion of each pillar 4 that is embedded in the pillar fixing concrete 10. In this pillar embedment length setting process, the length of the pillar embedment portion 30 is set so that the maximum compressive stress acting on the pillar fixing concrete 10 due to the bending moment generated in the pillar embedment portion 30 when the driftwood 102 collides vertically with the outflow prevention fence 1 is smaller than the short-term allowable compressive stress of the concrete, which is a specified value.

[0104] The maximum compressive stress σ acting on the concrete 10 fixed to the column c1 is the diameter D1 of the steel pipe selected as the support material in the support material selection process, the embedded length L1 of the support 4, and the shear force Q acting on the support 4 due to the collision of the drifting object 102 with the outflow prevention fence 1 in the vertical direction. o1 and the bending moment M1 generated at the central part of the pillar embedded part 30 in the axial direction of the pillar main body 12, according to the following formula (29). σ c1 ={Q o1 / (D1 L1)}+{6 M1 / (D1 L1 2 )} ···(29)

[0105] In this equation (29), the shear force Q o1 The yield external force F y Apply a value equal to

[0106] In addition, the bending moment M1 is o1 From the height h1 of the load acting position and the embedded length L1 of the pillar 4, it is calculated by the following formula (30). M1=Q o1(h1+L1 / 2) (30)

[0107] In addition, the short-term allowable compressive stress of concrete, f c is a value determined by the following formula (31) based on the design strength of concrete Fc. c For example, 18N / mm 2 It is. f c =1.5·(F c / 4) ···(31)

[0108] The maximum compressive stress σ of the concrete 10 fixed to the support column calculated as above c1 is the short-term allowable compressive stress of concrete f c The embedded length L1 of the support 4 is set to be smaller than the above.

[0109] In the design method of the outflow prevention fence 1 according to the present embodiment, in the process of setting the interval between the supports, the installation interval between the supports 4 of the outflow prevention fence 1 is set to the width B of the drifting object 102. o and the width B of the drifting object 102 oBy setting the interval between the struts 4 to be smaller than 102, the interval between the struts 4 is set so that when the drifting object 102 collides with the flow-prevention fence 1 in the vertical direction or a direction close to it, it collides with only one of the struts 4, which is the first collided strut 24, or only with two adjacent struts 4, which are the second collided struts 26. Then, in the strut material selection process, the drifting object 102 collides with the first collided strut 24, which is bent and deformed, and the bending deformation of the first collided strut 24 also causes the two adjacent struts 4 on either side to bend and deform. In both the first collision energy absorption form in which the adjacent support 25 is bent to absorb the collision energy of the drifting object 102, and the second collision energy absorption form in which the drifting object 102 is vertically collided with two adjacent second collided supports 26 and the two second collided supports 26 are bent to absorb the collision energy of the drifting object 102, a steel pipe capable of completely absorbing the collision energy of the drifting object 102 corresponding to the value of the collision energy acquired during the collision energy acquisition process is selected as the support material. Therefore, even if the drifting object 102 collides in a form that is difficult for absorbing collision energy, such as colliding with only one first collided support 24 or only two adjacent second collided supports 26 in the vertical direction or a direction close to it, it is possible to design an outflow prevention fence 1 capable of completely absorbing the collision energy of the drifting object 102, and the ability of the outflow prevention fence 1 to absorb the collision energy of the drifting object 102 can be improved.

[0110] Moreover, in the design method according to this embodiment, the manner in which the collision energy of the driftwood 102 is absorbed, which is the premise for the design of the spillway prevention fence 1, is specified by setting the installation interval of the posts 4 in the post interval setting process, and this makes it possible to limit the collision energy absorption capacity required for each post 4. This makes it possible to use low-cost steel pipes with reduced collision energy absorption capacity as the support material for each post 4, specifically steel pipes with reduced diameter and wall thickness, and thus reduces the manufacturing cost of the spillway prevention fence 1.

[0111] In order to increase the collision energy absorption capacity of the outflow prevention fence 1, it is also possible to reduce the installation intervals of the posts 4 and increase the number of posts 4 that can collide with the driftwood 102 to three or more when the driftwood 102 collides with the driftwood in a vertical direction or a direction close to that, but in this case, the scale of the installation work for the outflow prevention fence 1 will increase significantly. In contrast, in the design method of this embodiment, the installation intervals of the multiple posts 4 are set to be greater than half the width of the driftwood 102 and smaller than the width of the driftwood 102 in the post interval setting process, so that the posts 4 are installed at appropriate intervals such that the number of posts 4 with which the driftwood 102 collides is two or less (only one first collision post 24, or two second collision posts 26), and an increase in the scale of the installation work for the outflow prevention fence 1 due to an excessive increase in the number of posts 4 installed can be prevented.

[0112] In the design method for the outflow prevention fence 1 according to this embodiment, a resistance value is obtained in the resistance acquisition process, which is the force with which the drifting object 102 pushes the outflow prevention fence 1 in the lateral direction along its width direction due to the flow of seawater acting on the drifting object 102, and in the post material selection process, a steel pipe having an allowable bending stress greater than the bending stress acting on the post body 12 of the post 4 when a resistance equivalent to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1. This makes it possible to design an outflow prevention fence 1 that can prevent plastic bending deformation from occurring in the post 4 when the resistance of the drifting object 102 pushing in the lateral direction acts on the outflow prevention fence 1.

[0113] Furthermore, in the design method for the outflow prevention fence 1 according to this embodiment, in the beam material selection process, a steel pipe having an allowable bending stress greater than the bending stress acting on the beam 6 when a resistance equivalent to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 is selected as the beam material. Therefore, it is possible to design an outflow prevention fence 1 that can prevent plastic bending deformation from occurring in the beam 6 when a resistance force generated by the drifting object 102 pushing laterally acts on the outflow prevention fence 1.

[0114] Furthermore, in the design method for the outflow prevention fence 1 according to this embodiment, in the beam fixing bolt selection process, bolts having an allowable shear stress greater than the shear stress acting on the beam fixing bolts 20 when a resistance equivalent to the resistance value acquired in the resistance acquisition process acts on the outflow prevention fence 1 are selected as the beam fixing bolts 20. Therefore, it is possible to design an outflow prevention fence 1 that can maintain the fixation of the beam 6 to the brackets 14, 18 of the support pillar 4 by the beam fixing bolts 20 without damaging the beam fixing bolts 20 when a resistance force caused by the driftwood 102 pushing laterally acts on the outflow prevention fence 1.

[0115] In the design method for the outflow prevention fence 1 according to this embodiment, in the pile material selection process, a steel pipe that can prevent the steel pipe pile 2 from tipping over in the ground of the wharf 100 due to the tipping moment acting on the steel pipe pile 2 when driftwood 102 collides with the outflow prevention fence 1 in the vertical direction is selected as the pile material constituting the steel pipe pile 2 according to the physical properties of the ground of the wharf 100. Therefore, it is possible to design an outflow prevention fence 1 that can prevent the steel pipe pile 2 from tipping over in the ground of the wharf 100 due to the tipping moment acting on the steel pipe pile 2 when driftwood 102 collides with the outflow prevention fence 1 in the vertical direction.

[0116] In the design method for the outflow prevention fence 1 according to this embodiment, in the process of setting the post embedment length, the embedment length L1 of the post 4, which is the length of the post embedment part 30, is set so that the maximum compressive stress acting on the post-fixed concrete 10 due to the bending moment generated in the post embedment part 30 when the driftwood 102 collides with the outflow prevention fence 1 in the vertical direction is smaller than the short-term allowable compressive stress of concrete, which is a specified value. Therefore, it is possible to design an outflow prevention fence 1 that can prevent the post-fixed concrete 10 from being compressed and damaged by the bending moment generated in the post embedment part 30 when the driftwood 102 collides with the outflow prevention fence 1 in the vertical direction.

[0117] In addition, in the manufacturing method of the outflow prevention fence 1 according to this embodiment, the outflow prevention fence 1 designed by the design method described above is manufactured.

[0118] Specifically, in this manufacturing method, a number of pillars 4 made of steel pipes selected in the pillar material selection process are erected on the quay of the port 100 at the installation intervals set in the pillar spacing setting process, and adjacent ones of the multiple pillars 4 are connected with a number of beams 6 to manufacture the runoff prevention fence 1.

[0119] In addition, in this manufacturing method, the steel pipes selected in the beam material selection process are used as the beam materials of the multiple beams 6 that respectively connect adjacent ones of the multiple columns 4. Furthermore, the bolts selected in the beam fixing bolt selection process are used as the beam fixing bolts 20 that fix the beams 6 to the brackets 14, 18 of the columns 4 when connecting the adjacent columns 4 with the beams 6.

[0120] In addition, in this manufacturing method, before erecting the plurality of supports 4 on the quay 100 of the port, a plurality of steel pipe piles 2 using the steel pipes selected in the pile material selection process as pile materials are embedded at a predetermined interval into the ground of the quay 100. At this time, each steel pipe pile 2 is installed in a vertically extending position so that one end of the extension direction of each steel pipe pile 2 is aligned with the position of the upper surface of the quay 100. Then, the support fixing concrete 10 is poured inside each steel pipe pile 2, and the base 12a of the support body 12 of each support 4 is inserted inside each steel pipe pile 2 and embedded in the support fixing concrete 10. At this time, the length of the support embedding portion 30 of each support 4 embedded in the support fixing concrete 10 is adjusted to a length equal to the embedding length L1 set in the support embedding length setting process.

[0121] (Modification) The design method for the outflow prevention fence according to the present invention is not necessarily limited to the above. For example, the following configurations can be adopted for the design method for the outflow prevention fence according to the present invention.

[0122] The prevention fence designed by the design method according to the present invention is not necessarily limited to one that prevents drifting objects caused by the backwash of a tsunami from being washed out to sea, but may also be one that prevents drifting objects caused by the backwash of a storm surge from being washed out to sea. In this case, when calculating the value of the collision energy of the drifting object in the collision energy acquisition process, a collision energy value that takes into account the influence of the wind on the drifting object in addition to the ocean water flow on the drifting object is calculated, and when calculating the value of the resistance of the drifting object pushing sideways against the prevention fence in the drag acquisition process, a resistance value that takes into account the influence of the wind on the drifting object in addition to the ocean water flow on the drifting object is calculated.

[0123] The collision energy acquisition process in the design method according to the present invention is not necessarily limited to acquisition by calculating the value of the collision energy of the drifting object, and may be acquired, for example, by obtaining information on the value of the collision energy of the drifting object prepared in advance. The drag acquisition process in the design method according to the present invention is not necessarily limited to acquisition by calculating the value of the drag with which the drifting object pushes against the outflow prevention fence in the lateral direction, and may be acquired, for example, by obtaining information on the value of the collision energy of the drifting object prepared in advance.

[0124] The fixing structure of each support pillar of the runoff prevention fence to the quay is not necessarily limited to the above embodiment in which the base of the support pillar is inserted into a steel pipe pile buried in the ground of the quay and fixed with support fixing concrete. For example, the following fixing structure can be adopted for each support pillar of the runoff prevention fence to the quay according to the present invention: a fixing structure in which the base of the support pillar is fixed to a base plate installed on the upper surface of the quay and fixed to the quay with anchor bolts, or a fixing structure in which the quay includes concrete poured on its upper part, an anchor plate is embedded in the concrete, a base plate installed on the upper surface of the concrete at the top of the quay is fixed to the anchor plate with anchor bolts, and the base of the support pillar is fixed to the base plate.

[0125] In addition, the spill prevention fence according to the present invention may be provided with multiple stages of beams arranged vertically side by side between adjacent posts. [Explanation of symbols]

[0126] 1. Flow prevention fence 2 Steel pipe pile 4 pillars 6 Beam 10 Pillar fixing concrete 20 Beam fixing bolt 24 1st collided support 25 Adjacent pillar 26 2nd colliding support column 100 Quay 102 Flotsam

Claims

1. A method for designing a floating prevention fence having a plurality of posts erected at a predetermined interval on a quay wall of a port and a plurality of beams connecting adjacent ones of the plurality of posts, the method preventing drifting objects swept away by waves from the quay wall from being carried out into the sea, comprising the steps of: a collision energy acquisition step of acquiring a value of a collision energy when the drifting object collides with the outflow prevention fence; a strut spacing setting process for setting the installation spacing of the plurality of struts to a spacing greater than half the width of the drifting object and smaller than the width of the drifting object; a pillar material selection process for selecting, as a pillar material for the pillars, a steel pipe that is capable of absorbing the collision energy equivalent to the value acquired in the collision energy acquisition process in either a first collision energy absorption form in which the drifting object collides with a first collided pillar, which is any one of the multiple pillars, causing the first collided pillar to bend and deform so as to tilt, and also causing two adjacent pillars on either side of the first collided pillar to bend and deform so as to tilt due to the bending deformation of the first collided pillar via the beam, thereby absorbing the collision energy of the drifting object, or a second collision energy absorption form in which the drifting object collides with two second collided pillars, which are adjacent pillars of the multiple pillars, causing the two second collided pillars to bend and deform so as to tilt together, thereby absorbing the collision energy of the drifting object.

2. a first absorbed energy calculation process for calculating a first absorbed energy, which is a total absorbed energy by the first impacted pillar and the two adjacent pillars when the first impacted pillar is bent and deformed from an upright position to a predetermined inclination angle and the two adjacent pillars are bent and deformed from an upright position to an inclination angle that is half of the predetermined inclination angle in the first collision energy absorption mode; a second absorbed energy calculation process for calculating a second absorbed energy, which is a total absorbed energy by the two second impacted struts when the two second impacted struts are both bent and deformed from an upright position to the predetermined inclination angle in the second collision energy absorption form, A design method for an escape prevention fence as described in claim 1, wherein in the support material selection process, a steel pipe is selected as the support material such that both the calculated value of the first absorbed energy calculated in the first absorbed energy calculation process and the calculated value of the second absorbed energy calculated in the second absorbed energy calculation process are greater than the value of the collision energy acquired in the collision energy acquisition process.

3. and a drag acquisition step of acquiring a drag value, which is a force exerted by the drifting object when the drifting object pushes against the outflow prevention fence in a lateral direction along its width direction after the drifting object collides against the outflow prevention fence, A design method for an escape prevention fence as described in claim 1 or 2, wherein in the support material selection process, a steel pipe is selected as the support material that satisfies the condition that it is capable of completely absorbing collision energy equivalent to the value acquired in the collision energy acquisition process in both the first collision energy absorption form and the second collision energy absorption form, as well as the condition that it has an allowable bending stress greater than the bending stress acting on the support when a resistance equivalent to the value acquired in the resistance acquisition process acts on the escape prevention fence.

4. Further comprising a beam material selection step of selecting a beam material constituting the beam, A design method for an escape prevention fence as described in claim 3, wherein in the beam material selection process, a member having an allowable bending stress greater than the bending stress acting on the beam when a resistance corresponding to the value acquired in the resistance acquisition process acts on the escape prevention fence is selected as the beam material.

5. The runoff prevention fence has a beam fixing bolt that fixes the beam to the support, The design method for an outflow prevention fence as described in claim 3 or 4, further comprising a beam fixing bolt selection process for selecting as the beam fixing bolt a bolt having an allowable shear stress intensity greater than the shear stress acting on the beam fixing bolt when a resistance corresponding to the value acquired in the resistance acquisition process acts on the outflow prevention fence.

6. The runoff prevention fence includes steel pipe piles that are embedded in the ground of the quay and that fix the bases of the supports inserted inside the steel pipe piles, The design method for an outflow prevention fence as described in any one of claims 1 to 5, further comprising a pile material selection process for selecting, as a pile material for the steel pipe pile, a steel pipe that can prevent the steel pipe pile from tipping over in the ground of the wharf due to the overturning moment acting on the steel pipe pile when the driftwood collides with the outflow prevention fence, in accordance with the physical properties of the ground.

7. The runoff prevention fence has a post fixing concrete provided inside the steel pipe pile and fixing a base of the post to the steel pipe pile, The support has a support embedding portion which is embedded in the support fixing concrete, The design method for an outflow prevention fence as described in claim 6, further comprising a post embedment length setting process for setting the length of the post embedment portion so that the maximum compressive stress acting on the post-fixed concrete due to the bending moment generated in the post embedment portion when the driftwood collides with the outflow prevention fence is smaller than the short-term allowable compressive stress of the concrete, which is a specified value.

8. A method for manufacturing an outflow prevention fence designed by the design method according to any one of claims 1 to 3, comprising the steps of: A method for manufacturing an escape prevention fence, comprising erecting a plurality of posts, each of which is made of steel pipes selected in the post material selection process, on a quay wall of a port at the installation intervals set in the post spacing setting process, and connecting adjacent ones of the plurality of posts with the beams to manufacture the escape prevention fence.

Citation Information

Patent Citations

  • Construction to protect ground structure against tsunami

    JP2007302281A

  • Concrete protective column structure and protective column structure

    JP2009013743A

  • Tsunami drift guard fence

    JP2015183376A

  • Columnar support structure and tsunami barrier

    JP2018025007A

  • Safety management method and safety management system for harbor pier

    JP2020169536A