The described method improves penetrating pile construction efficiency by integrating a drilling device at the pile's lower end with a removable jig, enabling direct excavation and penetration, thus reducing time and effort in construction processes.

JP7590287B2Active Publication Date: 2024-11-26JAPAN HOME SHIELD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2021134852
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-08-20
Publication Date
2024-11-26
Estimated Expiration
2041-08-20

AI Technical Summary

Technical Problem

Conventional methods for driving penetrating piles into the ground face inefficiencies due to the need to replace construction equipment with excavation equipment when encountering solid layers, increasing time and effort requirements.

Method used

A method involving a penetrating pile construction process that supports a drilling device at the pile's lower end, allowing excavation and subsequent penetration without repeated attachment and detachment, using a removable excavation device connection jig to facilitate efficient ground penetration.

Benefits of technology

This approach enhances work efficiency by reducing construction time and effort, particularly for large-scale projects, by eliminating the need for repeated equipment changes and simplifying the connection of excavation devices to the pile.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007590287000001
    Figure 0007590287000001
  • Figure 0007590287000002
    Figure 0007590287000002
  • Figure 0007590287000003
    Figure 0007590287000003
Patent Text Reader

Abstract

To provide a method for constructing a penetrating pile, a jig for connecting an excavator, and a pile driving device, which can improve work efficiency by reducing the time and effort required for construction.SOLUTION: A method for constructing penetrating pile 1 that is driven into the ground and installed using construction heavy equipment 4 comprises steps of supporting an upper end of the penetrating pile 1 on the construction heavy machine 4, connecting an excavating device 3 having an excavating function to a lower end 1b of the penetrating pile 1 and excavating the ground G at the driving position of the penetrating pile 1 with the excavating device 3, removing the excavating device 3 from the lower end of the penetrating pile 1 to pull out the excavating device 3 from the ground G after the excavation by the excavating device 3, and penetrating the ground G excavated by the excavating device 3 with the penetrating pile 1. The excavating device 3 is configured to be connected to the lower end 1b of the penetrating pile 1 by an attachment 2 that can be attached and detached.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for installing a penetration pile, a jig for connecting a drilling rig, and a pile driving device. [Background technology]

[0002] Conventionally, when driving a penetration pile into the ground, a common method has been to attach a drilling device with a cutter at the drilling tip to a construction machine, and first use the drilling device to perform pre-excavation to loosen the ground at the installation location of the penetration pile, and then drive the penetration pile into the ground.

[0003] On the other hand, when the driving depth of a penetration pile to be installed in the ground is shallow, there is a method of efficiently driving the penetration pile by setting the penetration pile on a construction machine and rotating and pressing it into the ground without performing advance excavation using an excavator (for example, see Patent Document 1). Known methods of directly driving such a penetration pile into the ground include a method of driving the penetration pile while pushing and spreading the soil to the side, and a method of cutting the soil at the tip of the penetration pile and gradually removing it upwards to drive it in. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent No. 2981463 Summary of the Invention [Problem to be solved by the invention]

[0005] However, in the conventional method of driving a penetration pile directly into the ground, after the penetration pile to be driven into the ground is set on the construction machine and rotary pressing is started, there are cases in which the penetration pile cannot be driven in due to the presence of a solid layer with high ground strength at the surface of the ground to be driven. In this case, the penetration pile set on the construction heavy machinery is temporarily removed and replaced with an excavation device such as a drilling rod having an excavation function. Furthermore, after the target ground is excavated by the excavation device, the excavation device is removed from the construction heavy machinery and the penetration pile is reattached, and the penetration pile is then inserted into the target ground that has been loosened by the excavation device in advance. This results in a large amount of time and effort required for construction, which reduces work efficiency, and there is room for improvement in this regard.

[0006] The present invention provides a method for constructing a penetration pile, a jig for connecting a drilling rig, and a pile driving device that can improve work efficiency by reducing the time and effort required for construction. [Means for solving the problem]

[0007] In order to achieve the above-mentioned object, the construction method for a penetration pile of the present invention is a construction method for a penetration pile that is installed by driving it into the ground using a construction heavy machine, and is characterized by comprising the steps of: supporting the upper end of the penetration pile on the construction heavy machine; connecting a drilling device having an excavation function to the lower end of the penetration pile and excavating the ground at the driving position of the penetration pile with the drilling device; after excavation by the drilling device, pulling the drilling device out of the ground and removing it from the lower end of the penetration pile; and penetrating the penetration pile into the ground excavated by the drilling device.

[0009] In the present invention, for example, when the surface layer of the ground to be driven with the penetration pile is a solid layer, a drilling device having a drilling function is connected to the lower end of the penetration pile supported by the construction heavy machine, and the surface layer is excavated by the drilling device. After excavation by the drilling device, the drilling device is once pulled out of the ground and removed from the lower end of the penetration pile, and the penetration pile can be penetrated into the ground excavated by the drilling device. In this case, the conventional work process of attaching and detaching the penetration pile to the construction heavy machine to replace it with the drilling device can be omitted, so that the time and effort required for construction can be reduced, and the work efficiency can be improved. In particular, when the number of penetration piles to be constructed is large, the amount of construction per day can be increased, and the construction period and construction costs can be shortened.

[0010] In addition, in the method for installing a penetration pile according to the present invention, the drilling equipment may be connected to the lower end of the penetration pile by a detachable drilling equipment connecting jig.

[0012] In this case, by providing a jig for connecting the drilling equipment, the drilling equipment can be easily connected to the lower end of the penetration pile using the jig for connecting the drilling equipment without requiring special processing to the lower end of the penetration pile and the upper end of the drilling equipment.

[0013] In addition, the excavation equipment connecting jig according to the present invention is a jig for connecting an excavation equipment having an excavation function to a penetration pile that is driven into the ground using a construction heavy machine, and includes a first connecting part that detachably connects the lower end of the penetration pile while restricting rotation in the rotational direction of the penetration pile, and a second connecting part that detachably connects to the upper end of the excavation equipment while restricting rotation in the rotational direction of the penetration pile. The penetration pile includes a pile body extending in the pile axis direction, and a flat expansion wing having a lower end of the pile body and a plate surface perpendicular to the pile axis direction, the flat expansion wing being expanded from the outer circumferential surface of the pile body when viewed from the pile axis direction. The first connection portion has a storage portion capable of storing the expansion wing and an opening through which the expansion wing can enter from above. The storage portion is provided so as to be rotatable around the pile axis by a predetermined rotation angle between an entry position where the expansion wing enters from the opening and an engagement position where the expansion wing is restricted from moving in the up and down direction. When the expansion wing is in the engagement position, the expansion wing is connected to the penetration pile. It is characterized by the following. In addition, the pile driving device of the present invention is a pile driving device that uses the above-mentioned excavation equipment connecting jig, and is equipped with the construction heavy machinery that supports the upper end of the penetration pile to be driven into the ground and installed, and the excavation equipment that is detachably connected to the lower end of the penetration pile supported by the construction heavy machinery and has an excavation function, wherein the excavation equipment connecting jig is detachably provided on the lower end of the penetration pile, and the excavation equipment is connected to the penetration pile by the excavation equipment connecting jig.

[0014] In the present invention, the drilling equipment can be easily connected to the lower end of the penetration pile by a simple structure in which the drilling equipment connecting jig is provided with a first connecting portion and a second connecting portion.

[0016] In this case, by rotating the expansion wing that has entered the storage section from the opening around the pile axis, the up-down movement of the expansion wing relative to the first connection section is restricted, and the drilling device can be connected to the lower end of the penetration pile using the drilling device connection jig. When the penetration pile is penetrated, by rotating the penetration pile in the same direction as the direction in which the penetration pile is rotated from the entry position to the locking position, the drilling device connection jig can be penetrated without coming off the penetration pile. Effect of the Invention

[0017] According to the penetration pile construction method, drilling rig connection jig, and pile driving device of the present invention, the time and effort required for construction can be reduced, thereby improving work efficiency. [Brief description of the drawings]

[0018] [Figure 1] FIG. 2 is a perspective view showing a construction state using a pile driving device according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a perspective view showing the configuration of a penetration pile. [Diagram 3] FIG. 2 is a side view showing the configuration of a penetration pile. [Figure 4] FIG. 2 is a plan view of the enlarged wing of the penetration pile viewed from above. [Diagram 5] FIG. 4 is a side view showing the configuration before the excavation device is attached to the attachment. [Figure 6] FIG. 4 is a perspective view showing a configuration of a first connection portion of the attachment. [Figure 7] FIG. 7 is a diagram showing the state in which the enlarged wing of the penetration pile is attached to the attachment in FIG. 6. [Figure 8] 8 is a plan view of the attachment shown in FIG. 7 as viewed from above. [Figure 9] 1(a) to (e) are side views of the main part showing the construction procedure of the penetration pile. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0019] Hereinafter, a construction method for a penetration pile, a jig for connecting a drilling rig, and a pile driving device according to an embodiment of the present invention will be described with reference to the drawings.

[0020] 1 and 2, the construction method for a penetration pile of this embodiment is a construction method for installing a penetration pile 1 in the ground G. The construction method of this embodiment is a construction method in which an excavation device 3 is attached and detached to the penetration pile 1 using an attachment 2 (a jig for connecting the excavation device), and the penetration pile 1 is driven into the ground G by a construction heavy machine 4 using a rotational force and a downward load (pressing).

[0021] The pile driving device 10 includes a construction heavy machine 4 that supports an upper end 1a of a penetration pile 1 to be driven into the ground G, an attachment 2 (a jig for connecting an excavation device) that is detachable from a lower end 1b of the penetration pile 1 supported by the construction heavy machine 4, and an excavation device 3 that is detachably connected to the lower end of the attachment 2 and has an excavation function. In other words, the excavation device 3 can be connected to the penetration pile 1 via the attachment 2.

[0022] The penetration pile 1 used in this construction method comprises a pile body 11 made of a steel pipe, and a flat expansion wing 12 whose lower end 11a of the pile body 11 is blocked by a plate surface perpendicular to the pile axis O direction, and which is expanded from the outer peripheral surface 11b of the pile body 11 when viewed from the pile axis O direction and has cutting claws 13 on its outer peripheral edge 12c.

[0023] A rectangular steel pipe with a square cross section is used for the pile body 11. The lower end 11a of the pile body 11 is perpendicular to the pile axis O. A rectangular steel pipe with a relatively small cross section, in which a first width dimension L1 of one side shown in FIG. 3 is, for example, 75 to 150 mm, is used for the pile body 11. The pile body 11 is configured to a predetermined length by connecting multiple pieces in the longitudinal direction according to the length of the penetration pile 1.

[0024] The above-mentioned pile axis O is an axis passing through the central axis of the pile main body 11. In the penetration pile 1, the side of the expansion wing 12 in the pile axis O direction is defined as the lower side, and the side opposite the expansion wing 12 is defined as the upper side. In the following description, the direction going around the pile axis O as viewed from the pile axis O direction is defined as the circumferential direction. In this embodiment, the penetration pile 1 is rotationally pressed in in the clockwise direction as viewed from above in the pile axis O direction (the direction of arrow E shown in Figures 1 and 2).

[0025] As shown in FIG. 1, the expansion wing 12 has a function of cutting the ground G when the penetration pile 1 is penetrated, and is a member for pressing the ground G around the lower end 11a of the pile main body 11 downward to ensure sufficient tip bearing force. As shown in FIG. 2 and FIG. 3, the expansion wing 12 is a plate-shaped member having a certain thickness D. The expansion wing 12 is integrally joined by a fixing means such as welding, for example, at a factory or a work site, with the plate surface center aligned with the pile axis O and one surface (upper surface 12a) of the expansion wing 12 abutting against the lower end 11a of the pile main body 11. The expansion wing 12 is provided so that the plate surfaces (upper surface 12a and lower surface 12b) are oriented in a direction perpendicular to the pile axis O.

[0026] The expansion wing 12 has a square shape when viewed from the direction of the pile axis O. The expansion wing 12 is arranged in a similar shape to the pile main body 11 when viewed from the direction of the pile axis O. As shown in FIG. 3, the second width dimension L2 of one side of the expansion wing 12 is set to be larger than the first width dimension L1 of one side of the pile main body 11, and can be set to, for example, 75 to 300 mm. The thickness D of the expansion wing 12 can be, for example, 12 to 19 mm.

[0027] When the pile shaft O of the pile body 11 is driven into the ground G, the bottom surface 12b of the expansion wing 12 is in direct contact with the ground G to be excavated. As shown in Figs. 3 and 4, the cutting claws 13 provided on the outer peripheral edge 12c of the expansion wing 12 are arranged at one diagonal corner 12d of the expansion wing 12. Specifically, as shown in Fig. 4, the cutting claws 13 are provided on one side of the outer peripheral edge 12c of the expansion wing 12 when viewed from above, on the upstream side (the right side of the paper at the lower side and the left side of the paper at the upper side in Fig. 4) of the rotation direction (symbol E in this embodiment) when the penetration pile 1 is excavated and driven into the ground G. As shown in Fig. 3, the pair of cutting claws 13 protrude laterally from the outer peripheral edge 12c and protrude downward from the bottom surface 12b of the expansion wing 12. That is, when the penetration pile 1 is penetrated into the ground G (see FIG. 2), the cutting claw 13 precedes the expansion wing 12 and cuts the ground G on the underside of the expansion wing 12 .

[0028] As shown in Fig. 4, the expansion wing 12 rotates in the circumferential direction (arrow E indicates the direction of rotation during excavation and pressing) together with the pile body 11 around the pile axis O. In addition to the cutting function using the cutting claws 13, the expansion wing 12 has a cutting function of cutting the ground G located around the corner 12d by rotating in the circumferential direction. Since the center of the expansion wing 12 coincides with the rotation center of the penetration pile 1, the rotation trajectory of the cutting claws 13 (symbol W shown in Fig. 4) is circular.

[0029] As shown in Fig. 1, the construction heavy equipment 4 includes a leader (not shown) and a rotary drive unit (not shown) that is guided up and down by the leader. The penetration pile 1 has a pile body 11 supported by the rotary drive unit, and a downward load P (pressure) is applied by the weight of the rotary drive unit and the weight of the penetration pile 1 itself, and the penetration pile 1 is rotated in a predetermined direction by the rotary drive of the rotary drive unit. In this embodiment, the pile axis O of the penetration pile 1 is arranged in the vertical direction, but depending on the construction conditions, the pile axis O may be oriented in a direction inclined relative to the vertical direction during construction.

[0030] As shown in Fig. 5, the drilling device 3 comprises a tubular rotating shaft portion 31, the upper end portion 3a of which can be connected to the attachment 2, and a bit portion 32 connected to the lower end of the rotating shaft portion 31. The rotating shaft portion 31 and the bit portion 32 are provided so as to be separable. Fig. 5 shows the rotating shaft portion 31 and the bit portion 32 in a separated state. A mating male portion 31a that fits inside the mating female portion 32a of the bit portion 32 is formed at the lower end of the rotating shaft portion 31.

[0031] The bit section 32 has a support shaft 33, a drilling bit 34 provided at the lower end of the support shaft 33, and a plurality of stirring blades 35 provided on the circumferential surface of the support shaft 33. The support shaft 33 is formed in a tubular shape with a circular cross section, and is connected to the attachment 2 coaxially with the penetration pile 1 (pile shaft O). The tip 33a of the support shaft 33 is provided with a superhard part 331 having a cutting function. A cutting blade 341 is provided on the lower surface of the drilling bit 34. The cutting blade 341 is located below the superhard part 331 of the rotating shaft section 31. The plurality of stirring blades 35 are arranged above the drilling bit 34 and are rotatably provided within a range of the same diameter as the drilling bit 34 or a slightly smaller diameter.

[0032] As shown in Figs. 6 to 8, the attachment 2 is a connection jig for connecting an excavation device 3 having an excavation function to a penetration pile 1 which is driven into the ground G by using a construction heavy machine 4 and installed therein. The attachment 2 is equipped with a first connection part 2A that detachably connects the lower end of the penetration pile 1 while restricting rotation in the rotation direction E of the penetration pile 1, and a second connection part 2B (see Figure 5) that detachably connects to the upper end of the drilling rig 3 while restricting rotation in the rotation direction E of the penetration pile 1.

[0033] In the first connection part 2A, rectangular upper plate 21 and lower plate 22 are arranged in parallel with a gap between them in the vertical direction, and upper plate 21 and lower plate 22 are connected by a plurality of (four in this case) connecting pins 23. A storage section 2C capable of storing expansion wing 12 is formed between upper plate 21 and lower plate 22. The height of storage section 2C (the distance between upper plate 21 and lower plate 22) is set to be at least greater than the thickness D of expansion wing 12 (see FIG. 3).

[0034] The upper plate 21 has a frame shape with an opening 24 formed in the center in a plan view. The opening 24 is shaped so that the expansion wing 12 equipped with a pair of cutting claws 13 can pass through. The opening 24 is formed to be slightly larger than the expansion wing 12, with a shape substantially the same as the planar shape of the expansion wing 12 as viewed from the pile axis O direction. The opening 24 has a first opening 24A having a shape substantially the same as the expansion wing 12 in a plan view, and a second opening 24B having a shape substantially the same as the pair of cutting claws 13. When connecting the penetration pile 1, the expansion wing 12 passes through the opening 24 without interfering with the upper plate 21 and is disposed in the storage section 2C between the upper plate 21 and the lower plate 22.

[0035] The lower plate 22 is provided with a cutout 25 at the lower portion of each of the pair of second openings 24B of the openings 24 formed in the upper plate 21. The cutting claws 13 of the expansion wing 12 that has entered the storage section 2C are dropped into and positioned in the cutout 25. The cutout 25 is cut out so that the cutting claws 13 can move in the rotation direction E when the expansion wing 12 stored in the storage section 2C is rotated toward the rotation direction E of the penetration pile 1 in the plan view shown in FIG.

[0036] The expansion wing 12 of the penetration pile 1 is rotated in the rotation direction E while being inserted into the storage section 2C from the opening 24, so that the cutting claw 13 abuts against the connecting pin 23. As a result, the expansion wing 12 is restricted from moving in the vertical direction relative to the first connection section 2A, and the first connection section 2A and the expansion wing 12 are connected. In this way, the storage section 2C is provided so as to be rotatable around the pile axis O at a predetermined rotation angle between the entry position T1 where the expansion wing 12 enters from the opening 24 and the locking position T2 where the expansion wing 12 is restricted from moving in the vertical direction. The expansion wing 12 at the locking position T2 is restricted from moving in the vertical direction because the portion where the cutting claw 13 is placed is sandwiched between the upper plate 21 and the lower plate 22.

[0037] As shown in Fig. 5, the second connection part 2B detachably connects the drilling device 3 to the lower part of the attachment 2. The second connection part 2B has a connection pipe 26 that protrudes downward from the center of the lower surface 22a of the lower plate 22. The pipe axis of the connection pipe 26 is arranged so as to be coaxial with the pile axis O of the penetration pile 1 to which the attachment 2 is attached. The connection pipe 26 is fitted non-rotatably into the upper end female part 31b formed on the upper end part 3a of the drilling device 3.

[0038] Next, a construction method for the penetration pile 1, which is driven into the ground G by using a construction heavy machine 4, will be described with reference to the drawings. As shown in Figures 9(a) to (e), this construction method includes the steps of supporting the upper end 1a of the penetration pile 1 on a construction heavy machine 4 shown in Figure 1, connecting a drilling device 3 having an excavation function to the lower end 1b of the penetration pile 1 via an attachment 2 and excavating the ground G at the driving position of the penetration pile 1 with the drilling device 3, pulling out the drilling device 3 from the ground G after excavation by the drilling device 3 and removing the drilling device 3 from the lower end of the penetration pile 1, and penetrating the penetration pile 1 into the ground G excavated by the drilling device 3.

[0039] In addition, this construction method will be explained assuming that the surface layer of the ground G has a solid layer with great ground strength. The penetration pile 1 to be used is prefabricated in a factory or on a work site by joining the expansion wings 12 to the lower end 11a of the pile body 11 by a fixing means such as welding.

[0040] First, the processed penetration pile 1 is attached to a construction machine 4 (see Fig. 1). As shown in Fig. 1, the penetration pile 1, in which the expansion wing 12 is integrally joined to the lower end 11a of the pile body 11, is placed on the ground G. At this time, the pile axis O faces vertically, so the lower surface 12b of the expansion wing 12 is horizontal. The penetration pile 1 is held by the construction machine 4 so that the pile axis O faces vertically.

[0041] Next, as shown in Fig. 1 and Fig. 9(a), the penetration pile 1 is lowered by the above-mentioned heavy construction machine 4, so that a downward load P due to the weight of the rotary drive unit and the weight of the penetration pile 1 is applied to the penetration pile 1. As a result, the penetration pile 1 is pressed into the ground G by the expansion wing 12 to which pressure is applied, and sinks. After that, the rotary drive unit is rotated at the same time as the downward load P is applied to the penetration pile 1, and a rotational force is applied to the penetration pile 1 to rotate it in the rotation direction E. As a result, the expansion wing 12 rotates in a horizontal plane around the pile axis O, and the pair of cutting claws 13 act to cut the non-deformed portion of the ground G that has not been deformed by the pressing.

[0042] Here, as shown in FIG. 9(b), when it becomes difficult to cut the ground G by the penetration pile 1, the penetration pile 1 is once pulled out from the ground G, and the drilling device 3 having a drilling function is connected to the lower end 1b of the penetration pile 1 using the attachment 2. Specifically, as shown in FIG. 7 and FIG. 8, the expansion wing 12 of the penetration pile 1 that has been pulled up is first advanced into the storage section 2C through the opening 24 of the attachment 2 to the advanced position T1, and then rotated in one direction (the direction of the arrow E) around the pile axis O to abut against the connecting pin 23 to the locking position T2. ​​As a result, the first connecting part 2A of the attachment 2 is connected to the penetration pile 1 in a state in which the movement of the first connecting part 2A in the vertical direction relative to the expansion wing 12 is restricted. Next, as shown in FIG. 5, the upper end female part 31b of the rotating shaft part 31 of the drilling device 3 is fitted into the connecting pipe 26 of the second connecting part 2B of the attachment 2 connected to the penetration pile 1, and the drilling device 3 is connected to the lower part of the penetration pile 1 via the attachment 2.

[0043] Next, as shown in Figure 9 (c), the excavation device 3 is rotated together with the penetration pile 1 by a construction heavy machine 4 (see Figure 1), thereby excavating the ground G at the driving position of the penetration pile 1, thereby loosening the solid layer of ground G that is difficult to cut with the penetration pile 1.

[0044] 9(d), the drilling device 3 is temporarily pulled out from the ground G, and the drilling device 3 is removed from the lower end 1b of the penetration pile 1. Specifically, the drilling device 3 is removed from the attachment 2, and the attachment 2 is removed from the lower end 1b of the penetration pile 1.

[0045] Next, as shown in Fig. 9(e), with the underside 12b of the expansion wing 12 of the penetration pile 1 in direct contact with the ground G loosened by the excavation device 3, downward pressure is applied to the penetration pile 1 to press the expansion wing 12 into the ground G, and the penetration pile 1 is rotated to excavate the ground G. Specifically, as shown in Fig. 1, by continuously applying a downward load P and a rotational force to the penetration pile 1, the ground G is cut by the cutting claws 13 of the expansion wing 12, and the expansion wing 12 is pressed into the ground G on the underside 12b side and lowered, and the penetration pile 1 is driven into the ground G.

[0046] As shown in Figures 1 and 2, an earth discharge area S is formed between the expansion wing 12 and the borehole wall Ga, and the excavated soil is discharged from this earth discharge area S above the expansion wing 12. By passing the excavated soil directly below the expansion wing 12 through the earth discharge area S formed around the expansion wing 12, the surrounding ground at the tip of the penetration pile 1 is disturbed less, and it is possible to penetrate the penetration pile 1 into the ground G with a small pressure force.

[0047] The work of constructing the penetration pile 1 in the ground G is completed by driving the penetration pile 1 excavated in this manner into the ground G until it reaches a predetermined depth.

[0048] Next, the operation of the method for constructing a penetration pile, the excavation rig connecting jig, and the pile driving device according to this embodiment will be described in detail with reference to the drawings.

[0049] 3 and 7, in this embodiment, when the surface layer of the ground into which the penetration pile 1 is to be driven is a solid layer as described above, a drilling device 3 having a drilling function can be connected to the lower end 1b of the penetration pile 1 supported by a construction heavy machine 4, and the surface layer can be excavated by the drilling device 3. After excavation by the drilling device 3, the drilling device 3 can be temporarily pulled out of the ground G and removed from the lower end 1b of the penetration pile 1, and the penetration pile 1 can be penetrated into the ground G excavated by the drilling device 3. In this case, the conventional work process of attaching and detaching the penetration pile 1 to and from the construction heavy machine 4 in order to replace it with the excavation device 3 can be omitted, so the time and effort required for construction can be reduced, improving work efficiency. In particular, when a large number of penetration piles 1 are to be installed, the amount of construction per day can be increased, shortening the construction period and reducing construction costs.

[0050] Furthermore, in this embodiment, by providing the attachment 2, the first connection part 2A can be connected to the lower end part 1b of the penetration pile 1, and the second connection part 2B can be connected to the upper end part 3a of the drilling device 3. In this way, with the simple structure of providing the attachment 2 with the first connection part 2A and the second connection part 2B, it is possible to easily connect the drilling device 3 to the lower end part 1b of the penetration pile 1 using the attachment 2, without performing any special processing on the lower end part 1b of the penetration pile 1 or the upper end part 3a of the drilling device 3.

[0051] Moreover, in this embodiment, by rotating the expansion wing 12 that has entered the storage section 2C from the opening 24 around the pile axis O, the upward and downward movement of the expansion wing 12 relative to the first connection section 2A is restricted, and the drilling device 3 can be connected to the lower end of the penetration pile 1 using the attachment 2. When the penetration pile 1 is to be penetrated, the attachment 2 can be penetrated without coming off the penetration pile 1 by rotating the penetration pile 1 in the same direction as the direction in which the penetration pile 1 is rotated from the entry position T1 to the locking position T2.

[0052] As described above, the penetration pile construction method, the drilling rig connection jig, and the pile driving device according to the present embodiment can improve work efficiency by reducing the time and effort required for construction.

[0053] Although the method for constructing a penetration pile, the jig for connecting a drilling rig, and the pile driving device according to the present invention have been described above, the present invention is not limited to the above-described embodiments.

[0054] For example, in the above embodiment, an example is shown in which, without attaching the excavation device 3 to the lower end 1b of the penetration pile 1, excavation of the surface layer ground G, which has high ground strength, is started with the penetration pile 1, and then the penetration pile 1 is pulled up and the excavation device 3 is connected to the lower end 1b of the penetration pile 1 by the attachment 2, but it is also possible to omit the step of excavating the surface layer ground G with the penetration pile 1. In other words, if it is known in advance that the surface layer ground is a hard solid layer, the construction efficiency can be further improved by connecting the excavation device to the lower end 1b of the penetration pile 1 by using the attachment 2 and first excavating the surface layer ground G with the excavation device 3.

[0055] In this embodiment, the drilling device 3 is connected to the lower end 1b of the penetration pile 1 using the attachment 2, but it is also possible to omit the attachment 2. In other words, if the lower end 1b of the penetration pile 1 and the upper end 3a of the drilling device 3 are configured to be connectable, it is also possible to connect the drilling device 3 directly to the lower end 1b of the penetration pile 1. Furthermore, the configuration of the attachment 2 is not limited to this embodiment, but can be changed as appropriate to suit the structure of the penetration pile or excavation device.

[0056] In this embodiment, the expansion wing 12 (penetration pile 1) is rotated clockwise (in the direction of arrow E) when viewed from above to excavate and press in, but it may be rotated counterclockwise. When rotating the expansion wing 12 counterclockwise to excavate and press in, the mounting position of the cutting claws 13 provided on the expansion wing 12, the position of the notch of the attachment, and other configurations are also set in positions corresponding to the counterclockwise rotation direction during excavation and press in.

[0057] The configurations of the penetration pile 1 and the excavation device 3 are not limited to those of the above-mentioned embodiment, and may be other configurations. For example, in this embodiment, a steel pipe pile with a square cross section is used as the penetration pile 1, and a flat expansion wing 12 is provided at the lower end of the steel pipe pile, but the shape of the expansion wing 12 and the cross-sectional shape of the pile body 11 can be changed as appropriate. Also, a penetration pile without the expansion wing 12 may be used. Furthermore, a concrete pile may be used instead of a steel pipe pile.

[0058] In addition, the components in the above-described embodiments can be replaced with well-known components as appropriate without departing from the spirit of the present invention. [Explanation of symbols]

[0059] 1. Penetrating pile 1b Lower end 2 Attachment (drilling equipment connection jig) 2A 1st connection 2B Second connection part 2C Storage section 3. Drilling Rig 3a Upper end 4 Heavy construction equipment 11 Pile body 12 Expanded Wings 13 Cutting jaw 24 Opening 25 Notch 26 Connecting pipe O Pile shaft

Claims

1. A method for constructing a penetration pile that is driven into the ground using a construction heavy machine, comprising the steps of: Supporting the upper end of the penetration pile on the construction heavy machine; A step of connecting a drilling device having a drilling function to the lower end of the penetration pile and excavating the ground at the driving position of the penetration pile with the drilling device; After excavation by the excavation device, pulling the excavation device out of the ground and removing the excavation device from the lower end of the penetration pile; A step of penetrating the penetration pile into the ground excavated by the excavation device; A method for constructing a penetration pile, comprising the steps of:

2. 2. The method for constructing a penetration pile according to claim 1, wherein the drilling device is connected to the lower end of the penetration pile by a detachable drilling device connecting jig.

3. A drilling equipment connecting jig for connecting a drilling equipment having a drilling function to a penetration pile that is driven into the ground using a construction heavy machine, A first connection portion that connects the lower end portion of the penetration pile in a detachable manner and restricts rotation of the penetration pile in a rotational direction; A second connection part that is detachably attached to the upper end part of the excavation device and connects to the upper end part of the excavation device while restricting rotation in the rotation direction of the penetration pile; Equipped with The penetration pile includes a pile body extending in the pile axial direction, and a flat-plate-shaped expansion wing having a plate surface perpendicular to the pile axial direction at the lower end of the pile body and expanded from the outer peripheral surface of the pile body when viewed from the pile axial direction. The first connection portion has a housing portion capable of housing the expansion wing and an opening portion through which the expansion wing can enter from above, The storage section is provided so as to be rotatable around the pile axis at a predetermined rotation angle between an entry position where the expansion wing enters from the opening and a locking position where the expansion wing is restricted from moving in the vertical direction, A jig for connecting a drilling rig, characterized in that the expansion wing is connected to the penetration pile when in the locked position.

4. A pile driving device using the drilling device connection jig described in claim 3, The construction heavy machine supports the upper end of the penetration pile that is driven into the ground and installed; The excavation device is detachably connected to the lower end of the penetration pile supported by the construction heavy machine and has an excavation function, The drilling equipment connection jig is detachably provided to the lower end of the penetration pile, The pile driving device, characterized in that the drilling device is connected to the penetration pile by the drilling device connecting jig.

Citation Information

Patent Citations

  • JP1986146536U

  • Method for inserting steel pipe pile, bearing pile, and friction pile

    JP2011074726A

  • Pile penetration device

    JP2014141801A

  • Obstruction ground pile driving device and method for driving steel pipe pile into obstruction ground

    JP2015113683A

  • Tip support plate type steel pipe pile and method for supporting steel pipe pile with plate-shaped member

    JP2981463B1