Rapid construction method for hard rock horizontal blasting hole, and guide device

By using drilling and guiding devices with a depth of more than 10 meters during the construction of the hard rock overflow surface, combined with a millisecond detonating tube differential detonation network, the problems of low construction efficiency and drilling deformation in the existing technology are solved, and the problem is achieved The result is more efficient construction and less mountain disturbance.

WO2024221884A1PCT designated stage expired Publication Date: 2024-10-31CHINA GEZHOUBA (GRP) FIRST ENG CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/133708
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-04-23
Filing Date
2023-11-23
Publication Date
2024-10-31

AI Technical Summary

Technical Problem

The existing horizontal drilling and blasting construction method is inefficient in the construction of hard rock overflow surfaces, and horizontal drilling is easy to deform, resulting in poor blasting effects. Especially in the surrounding rock conditions of grade III and above, construction is difficult and the construction period is long.

Method used

Drilling holes with a depth of more than 10 meters are combined with a millisecond detonation tube differential detonation network, and the drill pipe inclination is reduced through a guidance device, including a guidance frame and a guidance ring, which provides support to extend the drilling distance and improve construction efficiency.

Benefits of technology

The construction efficiency of the hard rock overflow surface has been greatly improved, the amount of construction trench excavation and the number of blastings have been reduced, the construction period has been shortened, the disturbance to the mountain has been reduced, and the inclination error of the borehole has been corrected.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023133708_31102024_PF_FP_ABST
    Figure CN2023133708_31102024_PF_FP_ABST
Patent Text Reader

Abstract

A rapid construction method for a hard rock horizontal blasting hole, and a guide device. The method comprises the following steps: S1, excavating a construction groove (2) in the width direction of an overflow face; S2, providing a drilling machine (3) at the position in the construction groove (2) having a certain distance from the top, the drilling machine (3) being fixedly provided on a drilling frame (1), and the drilling machine (3) constructing drill holes in the length direction of the overflow face; S3, the length of each drill hole exceeding 10 meters, arranging a plurality of guide devices (6, 7) in the length direction of the drill holes, the guide devices (6, 7) being used for providing support for a drill rod (5) so as to reduce downward inclination; S4, constructing a plurality of drill holes in the width direction of the overflow face; S5, mounting an explosive in the drill holes; S6, connecting the explosive with a millisecond detonating tube micro-difference initiation network, and the explosive located at the bottoms of the drill holes being delayed to be detonated; S7, cleaning a construction face; and S8, sinking towards the bottom of the construction groove (2) by a certain distance, constructing a plurality of drill holes in the width direction of the overflow face again, and repeating the steps S5 to S7 above, so that rapid construction of a hard rock overflow face is achieved by means of the steps above. According to the rapid construction method for the hard rock horizontal blasting hole and the guide device, the excavation construction efficiency is greatly improved, and the construction volume of excavation of the construction groove is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Fast construction method and guiding device for hard rock horizontal blasting holes Technical Field

[0001] The invention relates to the field of dam overflow facility construction, in particular to a hard rock horizontal blasting hole rapid construction method and a guiding device. Background Art

[0002] The construction of a certain dam's overflow surface requires the excavation of part of the mountain. To reduce disturbance to the mountain, the horizontal drilling and blasting method is used for construction. The existing horizontal drilling and blasting construction method is to first excavate a construction trench along the width of the overflow surface, set up a drilling rig in the construction trench, drill horizontal holes, and arrange multiple horizontal holes along the construction trench. Then, fill the horizontal holes with explosives, use the explosives to fracture the rock, and then advance after cleaning the blasting surface. Usually, the length of each blast is less than 3 meters. This is because the construction trench does not have enough space, making it difficult to arrange large drilling equipment, which limits the drilling distance. In addition, the horizontally arranged drill rods are easily deformed, causing the borehole to tilt downward, affecting the blasting effect. If the mountain has rock mass conditions of Grade III or above, the construction is difficult and inefficient, which seriously hinders the construction period. No better solution has been found in the existing technology. Technical Solutions

[0003] The technical problem to be solved by the present invention is to provide a rapid construction method for hard rock horizontal blasting holes, which can greatly improve the construction efficiency of hard rock overflow surfaces.

[0004] Another technical problem to be solved by the present invention is to provide a guiding device that can reduce the downward tilt deformation of the horizontal drill hole, extend the distance of a single horizontal drilling, and improve the construction efficiency of horizontal drilling and blasting.

[0005] To solve the above technical problems, the technical solution of the present invention is: a method for rapid construction of hard rock horizontal blasting holes, comprising the following steps:

[0006] S1. Excavate the construction trench along the width of the overflow surface;

[0007] S2. A drilling rig is set up at a distance from the top of the construction trench. The drilling rig is fixed on a drill frame and drills holes in the length direction of the overflow surface.

[0008] S3. The length of each borehole exceeds 10 meters;

[0009] S4. Construct multiple boreholes along the width of the overflow surface;

[0010] S5. Installing explosives in the drill hole;

[0011] S6, using a millisecond detonation network to connect the explosives to the explosives at the bottom of the borehole for delayed detonation;

[0012] S7. Clean the construction surface;

[0013] S8, sinking a distance to the bottom of the construction trough, constructing multiple drill holes again along the width direction of the overflow surface, and repeating steps S5 to S7;

[0014] The above steps can realize the rapid construction of hard rock overflow surface.

[0015] In the preferred solution, step S9 is further included, after sinking blasting for 2 to 3 sections, excavating the construction trench as in step S1 again at the end of the blasting surface, and continuing the construction along the length direction of the overflow surface with the blasting surface;

[0016] After the entire overflow surface is constructed, steps S1 to S9 are repeated again.

[0017] In a preferred embodiment, the drill hole is a stepped hole, which is divided into multiple apertures along the depth of the drill hole. The aperture close to the drill rig is larger, and the aperture far from the drill rig is smaller. The aperture is 42mm~110mm.

[0018] In a preferred solution, a plurality of guide devices are arranged along the length of the borehole, and the guide devices are used to provide support for the drill rod and reduce downward tilt;

[0019] The guiding device is a guiding frame, which includes a fixed bracket, a telescopic rod, an extension rod and a guiding rod;

[0020] The telescopic rod is fixedly connected to the fixed bracket, the telescopic rod is arranged vertically, the telescopic end of the telescopic rod is fixedly connected to the top of the extension rod, the bottom of the extension rod is fixedly connected to the guide rod, and the guide rod is provided with a guide hole.

[0021] In the preferred solution, in step S4, after the drill rod has drilled a certain distance, a vertical hole is drilled at the front end of the drilling direction, a fixed bracket is fixed to the mouth of the vertical hole, and the length of the guide rod is adjusted by the extension rod so that the guide hole on the guide rod is located on the path of the drilling hole. When the drill rod passes through the guide hole, the telescopic rod moves to lift the guide rod to provide support for the drill rod.

[0022] In a preferred solution, the telescopic rod adopts a cylinder, a hydraulic cylinder or an electric push rod, and the telescopic rod outputs a preset constant pulling force.

[0023] In a preferred solution, a plurality of guide devices are arranged along the length of the borehole, and the guide devices are used to provide support for the drill rod and reduce downward tilt;

[0024] The guiding device is a guiding ring, which includes an outer ring and an inner ring that are connected to each other. An arc-shaped protrusion and an arc-shaped groove are provided between the outer ring and the inner ring. The arc-shaped protrusion and the arc-shaped groove are slidably connected. The arc-shaped protrusion and the arc-shaped groove divide the inner ring into a first gravity section and a second gravity section. The first gravity section is located in a direction close to the drilling rig, and the length of the first gravity section is greater than the length of the second gravity section.

[0025] A slurry groove is provided on the arc-shaped protrusion or the arc-shaped groove, and a grouting hole is provided on the outer ring. The grouting hole is communicated with the slurry groove, and the grouting hole is used for injecting a time-delayed curing adhesive.

[0026] In the preferred solution, the guide ring has multiple different outer diameters, which match the inner diameters of the stepped holes respectively. Before construction, a delayed-curing adhesive is injected into the grouting hole, and the guide ring is sent to the bottom of the stepped section with the corresponding inner diameter using a drill rod. The drill rod is taken out, and the inner sleeve in the guide ring tilts upward under the action of gravity and is cured by the adhesive after a period of time to guide the drill rod upward.

[0027] A guiding device for the above-mentioned hard rock horizontal blast hole rapid construction method, comprising a fixed bracket, a telescopic rod, an extension rod and a guiding rod;

[0028] The telescopic rod is fixedly connected to the fixed bracket, the telescopic rod is arranged vertically, the telescopic end of the telescopic rod is fixedly connected to the top of the extension rod, the bottom of the extension rod is fixedly connected to the guide rod, and the guide rod is provided with a guide hole;

[0029] The pilot hole is a slotted hole;

[0030] The telescopic rod adopts a pneumatic cylinder, a hydraulic cylinder or an electric push rod. When working, the telescopic rod outputs a preset constant pulling force.

[0031] A guiding device for the above-mentioned method of rapid construction of hard rock horizontal blasting holes comprises an outer ring and an inner ring that are connected to each other, with an arc-shaped protrusion and an arc-shaped groove provided between the outer ring and the inner ring, the arc-shaped protrusion and the arc-shaped groove being slidably connected, and the arc-shaped protrusion and the arc-shaped groove dividing the inner ring into a first gravity section and a second gravity section, the first gravity section being located in a direction close to the drilling rig, and the length of the first gravity section being greater than the length of the second gravity section;

[0032] A slurry groove is provided on the arc-shaped protrusion or the arc-shaped groove, and a grouting hole is provided on the outer ring. The grouting hole is communicated with the slurry groove, and the grouting hole is used for injecting a time-delayed curing adhesive. Beneficial effects

[0033] The present invention provides a method for rapid construction of hard rock horizontal blasting holes and a guiding device. By adopting a drilling depth exceeding 10 meters and combining a millisecond detonating cord micro-difference detonation network, the blasting surface of a single blasting construction is increased, the excavation construction efficiency is greatly improved, and the construction volume of the excavation construction trench is reduced. The guiding device of the present invention can reduce the degree of downward inclination of the drill rod, so that the drilling depth can exceed 10 meters. The guiding ring is relatively convenient to construct and can correct the inclination angle of the drill rod within 3°. In combination with the structure of the stepped hole, the error of the inclination distance within 10 meters is less than 5 cm. The guiding frame is constructed from the ground, which can obtain a larger inclination correction angle and can correct inclination angles of more than 10 meters and within 5°. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] The present invention will be further described below with reference to the accompanying drawings and examples:

[0035] FIG1 is a schematic structural diagram of the present invention during construction.

[0036] FIG2 is a schematic structural diagram of the guide ring of the present invention.

[0037] FIG3 is a schematic structural diagram of the guide ring of the present invention when in use.

[0038] FIG4 is a schematic structural diagram of the guide frame of the present invention.

[0039] In the figure: drill frame 1, construction groove 2, drilling rig 3, stepped hole 4, drill rod 5, guide ring 6, outer collar 61, inner collar 62, arc-shaped protrusion 63, grouting hole 64, slurry groove 65, arc-shaped groove 66, first gravity section 67, second gravity section 68, guide frame 7, telescopic rod 71, fixed bracket 72, extension rod 73, foot nail 74, guide rod 75, guide hole 76, battery 77, vertical hole 8. Modes for Carrying Out the Invention

[0040] Example 1:

[0041] As shown in Figure 1, a method for rapid construction of hard rock horizontal blast holes includes the following steps:

[0042] S1, excavate construction trench 2 along the width direction of the overflow surface;

[0043] S2. A drilling rig 3 is set at a distance from the top of the construction trench 2. Preferably, the distance from the top is 80 cm to 100 cm. The drilling rig 3 is fixed on the drilling rig 1. The drilling rig 1 adopts a truss drilling rig structure to ensure a stable foundation. The drilling rig 3 drills a hole in the length direction of the overflow surface.

[0044] S3. The length of each borehole exceeds 10 meters; preferably, the borehole length in this example is 12 to 15 meters.

[0045] S4. Construct multiple boreholes along the width of the overflow surface; the spacing between each borehole is 80cm~100cm.

[0046] S5. Installing explosives in the drill hole;

[0047] Based on geological conditions, the drill hole spacing is preferably 80-100 cm, the charge diameter is 32 mm, and the linear charge density is 260-320 g / m. Furthermore, the explosives are preferably tilt-compensated, with a higher charge near the bottom of the borehole and a lower charge at the borehole entrance. The charge per hole is 2.4-3.6 kg. The plugging length is 80-120 mm. Preferably, for boreholes longer than 10 meters, an intermediate plugging section is required, with a length of 80-100 mm. The explosives are arranged using a millisecond detonator differential detonation network. In the preferred embodiment, emulsion explosives or No. 22 rock ammonium nitrate explosives are used.

[0048] S6, using a millisecond detonation network to connect the explosives to the explosives at the bottom of the borehole for delayed detonation;

[0049] Further preferably, the explosives in the boreholes on both sides are detonated 30ms to 50ms in advance, and the explosives near the borehole opening are detonated 30ms to 50ms earlier than the explosives near the bottom of the borehole.

[0050] S7. Use an excavator to clean the blasting construction surface;

[0051] S8, sinking a distance (preferably 80 cm to 100 cm) to the bottom of the construction trench 2 of the drilling rig 3, and constructing multiple holes along the width direction of the overflow surface again, and repeating steps S5 to S7;

[0052] The above steps can realize the rapid construction of hard rock overflow surface.

[0053] In the preferred solution, step S9 is further included, after sinking blasting for 2 to 3 sections, excavating the construction trench 2 in step S1 again at the end of the blasting surface, and continuing the construction along the length direction of the overflow surface with the blasting surface;

[0054] After the entire overflow surface is constructed, the blasting surface is flush with the top surface of the initial construction trench 2, and steps S1 to S9 are repeated. The construction of the entire overflow surface is completed. By adopting the construction method of the present invention, construction efficiency is increased by more than 50%, and the construction period is shortened by 60% compared to the prior art. In particular, the excavation of the construction trench 2 is reduced, the number of drilling and blasting operations is reduced, and the disturbance to the mountain on both sides is minimized.

[0055] In a preferred embodiment, as shown in Figure 1 , the drilled hole is a stepped hole 4. The stepped hole 4 is divided into multiple diameters along the depth of the drilled hole, with the diameter closer to the drill rig 3 being larger and the diameter farther from the drill rig 3 being smaller. The diameters range from 42 mm to 110 mm. Preferably, the diameters from the hole opening to the bottom are divided into four types: 110 mm at the hole opening, 88 mm, 66 mm, and 42 mm, respectively. The bottom diameter is 42 mm.

[0056] An optional solution is shown in Figure 1, where multiple guide devices are arranged along the length of the drill hole. The guide devices are used to provide support for the drill rod and reduce the downward tilt of the drill rod;

[0057] As shown in FIG4 , the guiding device is a guiding frame 7 , which includes a fixed bracket 72 , a telescopic rod 71 , an extension rod 73 and a guiding rod 75 ;

[0058] The telescopic rod 71 is fixedly connected to the fixed bracket 72. The telescopic rod 71 is arranged vertically. The telescopic end of the telescopic rod 71 is fixedly connected to the top of the extension rod 73. The telescopic end of the telescopic rod 71 and the housing are connected in a slidable, non-rotatable manner. The bottom of the extension rod 73 is fixedly connected to the guide rod 75. The guide rod 75 is provided with a guide hole 76. Preferably, the guide hole 76 is a slotted hole.

[0059] In the preferred solution, in step S4, after the drill rod 5 has drilled a certain distance, a vertical hole is drilled at the front end of the drilling direction. Before drilling, a detection device, such as a magnetic detection device, is used to accurately detect the position of the drill rod 5. The fixed bracket 72 is fixed at the mouth of the vertical hole. The fixed bracket 72 is fixed by a foot nail 74. The telescopic rod 71 adjusts the length of the guide rod 75 through extension rods 73 of different lengths so that the guide hole 76 on the guide rod 75 is located on the drilling path. When the drill rod 5 passes through the guide hole 76, the telescopic rod 71 moves to lift the guide rod 75 to provide support for the drill rod 5.

[0060] In a preferred embodiment, the telescopic rod 71 utilizes a pneumatic cylinder, hydraulic cylinder, or electric push rod, and outputs a preset constant pulling force. In this embodiment, an electric push rod is preferably used. A battery 77 and a main control device are also provided within the telescopic rod 71. The main control device controls the magnitude of the output torque, using constant torque output to control the magnitude of the output pulling force, thereby providing upward support for the drill rod 5 to compensate for deformation. In a preferred embodiment, an overcompensation angle is set. Before construction, a calibration is performed to set the upward compensating angle to 5°. The support force required to lift the drill rod to an upward angle of 5° is tested at a preset distance, and this support force is used as the constant pulling force output by the telescopic rod 71.

[0061] Another optional solution is shown in Figures 1 to 3, where multiple guide devices are arranged along the length of the drill hole. The guide devices are used to provide support for the drill rod and reduce downward tilt;

[0062] The guiding device is a guide ring 6, which includes an outer ring 61 and an inner ring 62 that are nested together. An arcuate protrusion 63 and an arcuate groove 66 are provided between the outer ring 61 and the inner ring 62. The arcuate protrusion 63 and the arcuate groove 66 are slidably connected, and the arcuate protrusion 63 and the arcuate groove 66 divide the inner ring 62 into a first gravity section 67 and a second gravity section 68. The first gravity section 67 is located closer to the drilling rig 3 and is longer than the second gravity section 68. Accordingly, the first gravity section 67 is heavier than the second gravity section 68. This structure allows the outer ring 61 and the inner ring 62 to swing relative to each other. That is, when the guide ring 6 is located in the drill hole, the first gravity section 67 falls due to gravity, causing the inner ring 62 to tilt upward.

[0063] A slurry groove 65 is provided in the arc-shaped protrusion 63 or the arc-shaped groove 66, and a grouting hole 64 is provided in the outer collar 61. The grouting hole 64 is connected to the slurry groove 65 and is used to inject a time-delayed curing adhesive. Preferably, PH-763 AB glue with a half-hour curing time is used, and the curing time of the adhesive is set to 30 minutes. When the guide ring 6 is inserted into the bottom of the stepped hole 4 at the corresponding step position, the adhesive begins to cure after the inner collar 62 completes its upward tilt, so that the inner collar 62 maintains its upward tilt.

[0064] In the preferred embodiment, the guide ring 6 has multiple different outer diameters, which match the inner diameters of the various stages of the stepped hole 4. Before construction, a time-delayed curing adhesive is injected into the grouting hole 64, and the guide ring 6 is sent to the bottom of the stepped section of the corresponding inner diameter using the drill rod 5. The drill rod 5 is removed, and the inner ring 62 in the guide ring 6 tilts upward under the action of gravity and is cured by the adhesive after a period of time to guide the drill rod upward.

[0065] In a preferred solution, the structures of the guide ring 6 and the guide frame 7 can be used alone or in combination.

[0066] The steps for using the guide ring 6 and the guide frame 7 in combination are as follows: first, a 110mm drill rod is used to drill the first stage step hole 4. Preferably, the length of the first stage step hole 4 is 6m. After drilling into place, the drill rod 5 is withdrawn and replaced with an 88mm drill rod. Adhesive is injected into the grouting hole 64 of the guide ring 6. The adhesive enters the slurry tank 65. The guide ring 6 is installed on the drill rod and inserted into the bottom of the current step hole 4. The drill rod 5 is removed, and the adhesive is allowed to solidify before the drill rod 5 is inserted again. The first two stages of the hole are straightened using the guide ring 6. The length of the step hole 4 in the second to fourth stages is no more than 3 meters. During the drilling process of the third and fourth stages of the step hole 4, the precise position of the drill rod 5 is detected by a magnetic detection device. Then, a vertical hole is drilled at the position of the drill rod. The guide frame 7 is inserted and the drill rod 5 is inserted into the guide hole 76. Then, the telescopic rod 71 is activated to lift the drill rod 5 with a constant pulling force to correct the downward tilt angle of the drill rod 5. After the drilling is completed, the explosives are tied to bamboo strips and sent into the drilled hole.

[0067] Example 2:

[0068] A guiding device for the above-mentioned hard rock horizontal blasthole rapid construction method. In this example, the guiding device is a guiding frame 7, which is a product that can be sold separately. It includes a fixed bracket 72, a telescopic rod 71, an extension rod 73 and a guiding rod 75;

[0069] The telescopic rod 71 is fixedly connected to the fixed bracket 72. The telescopic rod 71 is arranged vertically. The telescopic end of the telescopic rod 71 is fixedly connected to the top of the extension rod 73. The bottom of the extension rod 73 is fixedly connected to the guide rod 75. The guide rod 75 is provided with a guide hole 76.

[0070] The pilot hole 76 is a slotted hole;

[0071] The telescopic rod 71 adopts a cylinder, a hydraulic cylinder or an electric push rod. When working, the telescopic rod 71 outputs a preset constant pulling force.

[0072] Example 3:

[0073] A guide device for use in the aforementioned method for rapid construction of hard rock horizontal blastholes. In this example, the guide device is a guide ring 6, which is a separately sold product and includes an outer ring 61 and an inner ring 62 that are interconnected. An arcuate protrusion 63 and an arcuate groove 66 are provided between the outer ring 61 and the inner ring 62. The arcuate protrusion 63 and the arcuate groove 66 are slidably connected. The arcuate protrusion 63 and the arcuate groove 66 divide the inner ring 62 into a first gravity section 67 and a second gravity section 68. The first gravity section 67 is located closer to the drilling rig 3 and is longer than the second gravity section 68.

[0074] The above embodiments are merely preferred technical solutions of the present invention and should not be construed as limiting the present invention. The embodiments and features in the embodiments of this application may be arbitrarily combined with each other unless they conflict. The scope of protection of the present invention shall be the technical solutions described in the claims, including equivalent alternatives to the technical features of the technical solutions described in the claims. Equivalent alternatives and improvements within this scope are also within the scope of protection of the present invention.

Claims

1. A method for rapid construction of hard rock horizontal blasting holes, characterized in that The following steps are involved: S1, excavating a construction trench (2) along the width direction of the overflow surface; S2, setting a drilling rig (3) at a distance from the top of the construction trench (2), the drilling rig (3) being fixedly mounted on the drilling frame (1), and drilling holes in the length direction of the overflow surface; S3. The length of each borehole exceeds 10 meters; S4, construct multiple boreholes along the width direction of the overflow surface; S5. installing explosives in the drill hole; S6, connecting the explosives with the millisecond detonation network of the detonating cord to delay the detonation of the explosives at the bottom of the borehole; S7. Clean the construction surface; S8, sinking a distance to the bottom of the construction groove, constructing multiple holes along the width direction of the overflow surface again, and repeating steps S5 to S7; The above steps can realize rapid construction of hard rock overflow surface.

2. The method for rapid construction of hard rock horizontal blasting holes according to claim 1 is characterized by: The method further comprises step S9, after 2-3 sections of sinking blasting, excavating the construction groove (2) in step S1 again at the end of the blasting surface, and continuing the construction in the length direction of the overflow surface with the blasting surface; After the entire overflow surface is constructed, steps S1 to S9 are repeated again.

3. The method for rapid construction of hard rock horizontal blasting holes according to claim 1 or 2, characterized in that: The drilled hole is a stepped hole (4), which is divided into a plurality of apertures along the depth of the drilled hole, the aperture close to the drill rig (3) being larger, and the aperture far from the drill rig (3) being smaller, and the aperture ranges from 42 mm to 110 mm.

4. The method for rapid construction of hard rock horizontal blasting holes according to claim 1, characterized in that: A plurality of guide devices are arranged along the length of the borehole, and the guide devices are used to provide support for the drill rod and reduce downward tilt; The guiding device is a guiding frame (7), comprising a fixed bracket (72), a telescopic rod (71), an extension rod (73) and a guiding rod (75); The telescopic rod (71) is fixedly connected to the fixed bracket (72), the telescopic rod (71) is arranged vertically, the telescopic end of the telescopic rod (71) is fixedly connected to the top of the extension rod (73), the bottom of the extension rod (73) is fixedly connected to the guide rod (75), and the guide rod (75) is provided with a guide hole (76).

5. The method for rapid construction of hard rock horizontal blasting holes according to claim 4 is characterized in that: In step S4, after the drill rod (5) has drilled a certain distance, a vertical hole is drilled at the front end in the drilling direction of the hole, and the fixed bracket (72) is fixed to the opening of the vertical hole. The length of the guide rod (75) is adjusted by the extension rod (73) so that the guide hole (76) on the guide rod (75) is located on the path of the drilling hole. When the drill rod (5) passes through the guide hole (76), the telescopic rod (71) moves to lift the guide rod (75) to provide support for the drill rod (5).

6. The method for rapid construction of hard rock horizontal blasting holes according to claim 5 is characterized by: The telescopic rod (71) adopts a cylinder, a hydraulic cylinder or an electric push rod, and the telescopic rod (71) outputs a preset constant pulling force.

7. The method for rapid construction of hard rock horizontal blasting holes according to claim 3 is characterized by: A plurality of guide devices are arranged along the length of the borehole, and the guide devices are used to provide support for the drill rod and reduce downward tilt; The guiding device is a guiding ring (6), which comprises an outer ring (61) and an inner ring (62) which are sleeved together, an arc-shaped protrusion (63) and an arc-shaped groove (66) are provided between the outer ring (61) and the inner ring (62), the arc-shaped protrusion (63) and the arc-shaped groove (66) are slidably connected, and the arc-shaped protrusion (63) and the arc-shaped groove (66) divide the inner ring (62) into a first gravity section (67) and a second gravity section (68), the first gravity section (67) is located in a direction close to the drilling rig (3), and the length of the first gravity section (67) is greater than the length of the second gravity section (68); A slurry groove (65) is provided on the arc-shaped protrusion (63) or the arc-shaped groove (66), and a grouting hole (64) is provided on the outer ring (61). The grouting hole (64) is connected to the slurry groove (65), and the grouting hole (64) is used to inject a time-delayed curing adhesive.

8. The method for rapid construction of hard rock horizontal blasting holes according to claim 7 is characterized by: The guide ring (6) has a plurality of different outer diameters, which respectively match the inner diameters of the stepped hole (4). Before construction, a time-delayed curing adhesive is injected into the grouting hole (64), and the guide ring (6) is sent to the bottom of the stepped section with the corresponding inner diameter by the drill rod (5). The drill rod (5) is removed, and the inner sleeve ring (62) in the guide ring (6) tilts upward under the action of gravity and is cured by the adhesive after a period of time, so as to guide the drill rod upward.

9. A guiding device for the rapid construction method of hard rock horizontal blasting holes according to any one of claims 1 to 8, characterized in that: It comprises a fixed bracket (72), a telescopic rod (71), an extension rod (73) and a guide rod (75); The telescopic rod (71) is fixedly connected to the fixed bracket (72), the telescopic rod (71) is arranged vertically, the telescopic end of the telescopic rod (71) is fixedly connected to the top of the extension rod (73), the bottom of the extension rod (73) is fixedly connected to the guide rod (75), and the guide rod (75) is provided with a guide hole (76); The pilot hole (76) is a slotted hole; The telescopic rod (71) is a cylinder, a hydraulic cylinder or an electric push rod. When in operation, the telescopic rod (71) outputs a preset constant pulling force.

10. A guiding device for the rapid construction method of hard rock horizontal blasting holes according to any one of claims 1 to 8, characterized in that: The invention comprises an outer ring (61) and an inner ring (62) which are sleeved together, an arc-shaped protrusion (63) and an arc-shaped groove (66) are provided between the outer ring (61) and the inner ring (62), the arc-shaped protrusion (63) and the arc-shaped groove (66) are slidably connected, the arc-shaped protrusion (63) and the arc-shaped groove (66) divide the inner ring (62) into a first gravity section (67) and a second gravity section (68), the first gravity section (67) is located in a direction close to the drilling machine (3), and the length of the first gravity section (67) is greater than the length of the second gravity section (68); A slurry groove (65) is provided on the arc-shaped protrusion (63) or the arc-shaped groove (66), and a grouting hole (64) is provided on the outer ring (61). The grouting hole (64) is connected to the slurry groove (65), and the grouting hole (64) is used to inject a time-delayed curing adhesive.

Citation Information

Patent Citations

  • Drilling method for accurately controlling hole deflection under complicated stratum and guide device

    CN101619655A

  • Blast construction method

    CN102778183A

  • Construction method of foundation pit digging system

    CN109577338A

  • High slope presplitting blasting construction method

    CN113340166A

  • Hard rock excavation method

    CN114855809A