Method for conveniently and significantly improving power generation efficiency of steam turbine
By adding water for heating in the steam turbine boiler and adopting wet steam power generation mode, the problem of water erosion caused by low back pressure of the low-pressure cylinder is solved, the power generation efficiency is significantly improved, the process is simplified, carbon emissions are reduced, and the scientific revolution of power generation is promoted. Help solve the climate crisis.
Patent Information
- Application Number
- PCT/CN2023/139903
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-06-27
- Filing Date
- 2023-12-19
- Publication Date
- 2024-10-31
AI Technical Summary
In existing steam turbine power generation technology, the low back pressure of the low-pressure cylinder causes water erosion problems, which limits the application of wet steam, which in turn leads to low power generation efficiency. Large-scale engineering modifications are difficult to achieve efficiency improvements, making it difficult to eliminate the climate crisis.
By adding water to the steam turbine boiler until it is full and heating it to the highest temperature, the steam turbine power generation is controlled, and the wet steam power generation mode is adopted to avoid engineering modifications, retain the existing intermediate reheat steam system, and directly improve the power generation efficiency.
Wet steam power generation was achieved without engineering modifications, significantly improving power generation efficiency, reducing carbon emissions, simplifying the power generation process, reducing fuel consumption, promoting the scientific revolution in power generation, and helping to solve the climate crisis.
Smart Images

Figure CN2023139903_31102024_PF_FP_ABST
Abstract
Description
A simple and efficient method to increase steam turbine power generation efficiency Technical Field
[0001] The present invention relates to the technical field of steam turbine power generation, and in particular to a simple and efficient method for increasing the power generation efficiency of a steam turbine. Background Art
[0002] In view of the official approval of the U.S. invention patent - US 11,473,451B2, a new and revolutionary power generation theory that can achieve the maximum increase in water vapor power generation efficiency has been disclosed - including a power generation theory based on engineering and technical modifications of a certain scale or above, with wet steam as its most fundamental feature, which has formed a new generation of existing power generation technology, which we define as "globally optimized power generation theory."
[0003] The "existing technology" in the field of new-generation power generation achieved based on the formal approval of the above-mentioned U.S. invention patent represents a revolutionary power generation theory, namely the "global optimization power generation theory", which has since created the greatest foundation for the scientific revolution in power generation. It comes from the fact that the "wet steam" used in steam power generation, which was originally thought to be impossible to apply to the most in-depth application, that is, the turbine power generation process, can completely replace "dry steam" and achieve the highest efficiency traditional power generation process.
[0004] The most important foundation of this comes from the most important discoveries in modern physics, including: the longest-term on-site engineering practice of steam turbine power generation based on Chinese invention patents 201510714150.3 and 201610557443.X, including the study of thousands of pages of various conclusions in the "Turbine Steam Path" series of monographs by American steam turbine engineering expert William P. Sanders. Overall, it can finally be generally understood that only when the "back pressure is too low" in the low-pressure cylinder of the steam turbine will "water erosion" occur near the last-stage blades of the low-pressure cylinder, thus forming the power generation industry's refusal to adopt the deepest "wet steam". This is the fundamental reason for refusing to formally adopt "wet steam" in various power generation processes such as fossil energy and solar thermal, including waste-to-energy.
[0005] The fundamental reason for the success of the "existing technology" implemented by the aforementioned global optimization power generation theory is that historical power generation theory has always been based on the "classical theory of water erosion," emphasizing that "water vapor must be based on superheated, dry steam at the highest temperature." However, the aforementioned US invention patent proves that "superheated, dry steam at the highest temperature" only leads to "hollowing" of the power generation process. This means that the work efficiency of water vapor is always too low due to the mass density of the power generation medium, resulting in a complete "slump" in power generation efficiency. The most important reason for the success of this theory is precisely that to prevent "water erosion," it is only necessary to maintain the current operating "back pressure" of the steam turbine at or above the current "blocking back pressure," also known as the critical back pressure.
[0006] On the contrary, the most important factor that determines the efficiency of power generation is the power generation medium. That is, if the power generation medium can be immediately improved at no cost, This fundamental scientific principle in the field of traditional power generation is the simplest natural science behind the fact that carbon dioxide (CO2) can be used as a traditional power generation medium, achieving a historic "demonstration"—i.e., trial—as a basic "power generation medium."
[0007] However, the "existing technology" implemented by the above-mentioned global optimization power generation theory is not absolutely perfect, and still has some of the most profound flaws - it is precisely the largest-scale engineering transformation project that must be based on the historical power generation process.
[0008] Given that the global power generation industry is shouldering the most important scientific mission in history to try to eliminate the "climate crisis" as soon as possible, this inevitable need for the largest-scale engineering transformation project will inevitably lead to a scientific mission of soaring power generation efficiency, resulting in a huge delay in the timing of the collective decision-making process of the power generation industry - even the greatest loss in history.
[0009] This historic and complete hesitation may well evolve into an infinitely long thinking process, which will result in the fact that although the power generation theory has taken off, it is difficult to change the most pessimistic reality of the power generation project with extremely low power generation efficiency.
[0010] From the perspective of the global power industry, this greatest industry in modern history must undergo a harsh historical process of self-revolution. Its fundamental and thorough hesitation represents a tremendous time cost, which will inevitably lead to a fundamental loss of opportunities for the common well-being of all mankind. This will inevitably result in an undue, enormous, and horrific historical delay. This fundamental and historical hesitation could completely prevent the highest mission of global natural science, namely, to eliminate the "climate crisis." Otherwise, the goal of significantly improving power generation efficiency based on "existing technology" will inevitably be difficult to achieve in the long term.
[0011] Summary of the Invention
[0012] The technical problem to be solved by the present invention is to address the deficiencies of the existing technology and provide a simple and efficient method for increasing the power generation efficiency of a steam turbine.
[0013] The technical solution of the present invention for the simplest and most efficient method of increasing the power generation efficiency of a steam turbine is as follows:
[0014] Add water to the steam turbine boiler until the boiler is full;
[0015] Heat the water in the boiler to the highest steam temperature;
[0016] Control steam turbine power generation.
[0017] On the basis of the above scheme, the simplest super method of the present invention to realize the surge in steam turbine power generation efficiency can also be improved as follows.
[0018] Furthermore, the process of adding water to the boiler of the steam turbine until the boiler is full includes:
[0019] Start the water supply system of the steam turbine condensate system;
[0020] Start the condensate pump of the steam turbine and open the #5 low-pressure heater electric door to start supplying condensate to the deaerator and increase the water level in the deaerator to within the preset deviation of the preset value;
[0021] Open the main steam regulating valve and each sequence valve;
[0022] Start the vacuum pumping system to pump the operating back pressure of the steam turbine to within the preset deviation of the back pressure standard of the vacuum pressure;
[0023] Step 5: Start the electric feed water pump system of the generator set boiler system and add water to the boiler for the first time until the boiler water level is within the preset deviation;
[0024] Open the respective inlet or outlet electric valves of the high-pressure and low-pressure bypass pipes of the steam turbine;
[0025] Close the main steam regulating valve and each sequence valve;
[0026] Add water to the boiler a second time through the electric feed water pump system until the boiler is full.
[0027] Further, the water in the boiler is heated to the maximum temperature of the steam, including:
[0028] Start the boiler combustion system of the generator set to heat the water in the boiler to the maximum steam temperature.
[0029] Furthermore, controlling the steam turbine to generate electricity includes:
[0030] Closing brake motor;
[0031] Open the main steam regulating valve, increase the initial opening of the first sequence valve, and increase the turbine speed to within the preset deviation of the rated speed;
[0032] Synchronize the generator set and the large power grid;
[0033] Close the high-pressure and low-pressure bypass pipeline valves of the steam turbine;
[0034] Increase the opening of each sequence valve;
[0035] According to the original regulations of the steam turbine, open the electric valves of each level of steam extraction pipeline.
[0036] Furthermore, controlling the steam turbine to generate electricity also includes:
[0037] For the total water supply opening signal of the DCS control system of the generator set load, including the total opening control signal of the sequence valve, a synchronous relationship with the load demand is added.
[0038] Furthermore, controlling the steam turbine to generate electricity also includes:
[0039] By closing the flue gas damper opening of the reheat steam, the heat absorption of the reheater is reduced, so that the steam temperature of the turbine cylinder after entering the high-pressure cylinder is lower than the rated steam temperature of the main steam, until it is close to the exhaust temperature of the high-pressure cylinder.
[0040] Furthermore, controlling the steam turbine to generate electricity also includes:
[0041] By reducing the burner inclination angle, the heat absorption of the reheater is reduced, reaching a temperature higher than the high-pressure cylinder exhaust temperature and lower than the rated steam temperature of the main steam.
[0042] The technical effects of the present invention's simplest and most efficient method for increasing steam turbine power generation efficiency are as follows:
[0043] Without carrying out engineering modifications, including for fossil energy power generation systems, the existing intermediate reheat steam system can continue to be retained, and "wet steam power generation" can be directly realized, which can greatly improve the power generation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] Other features, objects and advantages of the present invention will become more apparent upon reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0045] FIG1 is a flow chart of a simple and efficient method for increasing the power generation efficiency of a steam turbine according to an embodiment of the present invention. DETAILED DESCRIPTION
[0046] As shown in FIG1 , a simple and efficient method for increasing the efficiency of steam turbine power generation according to an embodiment of the present invention includes the following steps:
[0047] S1. Add water to the boiler of the steam turbine until the boiler is full;
[0048] S2, heating the water in the boiler to the highest steam temperature;
[0049] S3. Control the steam turbine to generate electricity.
[0050] Optionally, in the above technical solution, in S1, the process of adding water to the boiler of the steam turbine until the boiler is full includes:
[0051] S10, start the water supply system of the steam turbine condensate system;
[0052] S11. Start the condensate pump of the steam turbine and open the #5 low-pressure heater electric door to start supplying condensate to the deaerator and increase the water level in the deaerator to within the preset deviation of the preset value;
[0053] S12, open the main steam regulating valve and each sequence valve;
[0054] S13, starting the vacuum pumping system to reduce the operating back pressure of the steam turbine to within a preset deviation of the back pressure standard of the vacuum pressure;
[0055] S14. Start the electric feed water pump system of the generator set boiler system and add water to the boiler for the first time until the boiler water level is within a preset deviation;
[0056] S15. Open the respective inlet or outlet electric valves of the high-pressure and low-pressure bypass pipes of the steam turbine;
[0057] S16, close the main steam regulating valve and each sequence valve;
[0058] S17. Add water to the boiler for the second time through the electric water pump system until the boiler is full.
[0059] Optionally, in the above technical solution, in S2, heating the water in the boiler to the maximum temperature of the steam includes:
[0060] S20. Start the boiler combustion system of the generator set to heat the water in the boiler to the maximum steam temperature.
[0061] Optionally, in the above technical solution, in S3, controlling the steam turbine to generate electricity includes:
[0062] S30, closing brake motor;
[0063] S31. Open the main steam regulating valve, increase the initial opening of the first sequence valve, and increase the turbine speed to within the preset deviation of the rated speed;
[0064] S32, synchronize the generator set with the main power grid;
[0065] S33. Close the high-pressure and low-pressure bypass pipe valves of the steam turbine;
[0066] S34, increase the opening of each sequence valve;
[0067] S35. Open the electric valves of each level of steam extraction pipeline according to the original regulations of the steam turbine.
[0068] Optionally, in the above technical solution, in S3, controlling the steam turbine to generate electricity further includes:
[0069] S36. For the total water supply opening signal of the DCS control system of the generator set load, including the total opening control signal of the sequence valve, a synchronization relationship with the load demand is added.
[0070] Optionally, in the above technical solution, in S3, controlling the steam turbine to generate electricity further includes:
[0071] S37. By closing the opening of the flue gas damper of the reheat steam, the heat absorption of the reheater is reduced, so that the steam temperature of the turbine cylinder after entering the high-pressure cylinder reaches lower than the rated steam temperature of the main steam, until it approaches the exhaust temperature of the high-pressure cylinder.
[0072] Optionally, in the above technical solution, in S3, controlling the steam turbine to generate electricity further includes:
[0073] S38. By reducing the burner inclination angle, the heat absorption of the reheater is reduced to a temperature higher than the high-pressure cylinder exhaust temperature and lower than the rated steam temperature of the main steam.
[0074] Please pay attention to the further description of the present invention, as follows:
[0075] We believe that in the above process, in order to emphasize the realization of wet steam power generation mode, we must try our best to ensure the relative stability of the pressure, steam temperature and other parameters of the thermal energy engineering of the generator set, avoid large changes, and affect the safety and stability of the mentality of the operating personnel. Therefore, we did not adopt the method of directly increasing the water level on the boiler side during the normal operation of the unit. That is, we emphasize that the highest full water level of the boiler must be achieved before starting the power generation process.
[0076] Furthermore, this revolutionary advancement in power generation theory has ultimately revealed that, during normal generator set operation, even simply increasing the feedwater flow rate will inevitably lead to a corresponding increase in power generation efficiency. However, this phenomenon is inherently more difficult for traditional power plants, which must adhere to the "Generator Set Steam Turbine Operating Regulations," to understand and accept. This demonstrates the disruptive, or more accurately, revolutionary nature of the global optimization power generation theory proposed by the inventors. The exceptional success of their argument is truly significant and undeniable!
[0077] However, as described in this manual, "normal temperature water" before the normal start of the generator set is directly added into the generator set to achieve "full water level", and the heating process of the boiler system is directly started, and then the overall process of the power generation process is started. Since there is no preheating preparation process of the generator set that gradually heats up, it is inevitable that the temperature will rise instantly, causing "thermal stress deformation" of the corresponding equipment, which may completely lead to the power plant's refusal to accept it - the ultimate obstacle to the implementation of the project.
[0078] Furthermore, the inventors designed this particular "invention" solely to serve as an "intermediate implementation process" or demonstration project specifically designed to accelerate the realization of the "global optimal power generation theory." Therefore, to prevent the aforementioned ultimate obstacle to project implementation, the implementation process of the present invention can be initiated immediately or as soon as possible during normal unit operation, that is, immediately after shutting down. This implementation process or schedule ensures that the initial temperature system of the generator set equipment system is essentially normal, preventing both the occurrence of "transition processes" and the occurrence of "thermal stress deformation"—in other words, eliminating the need to consider the interference of "transition processes" or "thermal stress deformation" with the principles of the present invention.
[0079] The following is a detailed description of a simple and efficient method for increasing the power generation efficiency of a steam turbine according to the present invention through a complete embodiment:
[0080] The steam turbine has a turbine circulation system composed of multiple cylinders. At the same time, based on the realization of "full water level" as the most important theoretical premise feature, the "wet steam" power generation process of the generator set is started.
[0081] The duty officer of the generator set is entrusted to assume the responsibility of operation supervision, especially starting the unit load from zero during the startup process, starting the initial steam seal system of the steam turbine, and continuously improving the process, that is, the normal switching operation from the initial seal system to the normal seal system, and finally realizing the most formal wet steam power generation process startup procedure of the generator set, including the following processes:
[0082] S101, start the water supply system of the steam turbine condensate system;
[0083] S102: Start the condensate pump of the steam turbine and open the #5 low-pressure heater electric door to start supplying condensate to the deaerator and increase the water level in the deaerator to within a preset deviation of a preset value. Specifically:
[0084] Start the condensate pump of the steam turbine, open the #5 low-pressure heater electric door, and begin to supply condensate to the deaerator, gradually increase the water level of the deaerator until it is close to the set value of the deaerator water level. The set value of the deaerator water level is the preset value, and the preset deviation of the preset value can be set according to actual conditions.
[0085] S103, open the main steam regulating valve and each sequence valve, specifically: open the main steam regulating valve and each sequence valve;
[0086] S104: Start the vacuum pumping system to reduce the operating back pressure of the steam turbine to within a preset deviation of the back pressure standard of the vacuum pressure. Specifically:
[0087] Start the vacuum system and wait for the turbine operating back pressure to approach or reach the back pressure standard that meets the "vacuum pressure". The preset deviation of the back pressure standard can be set according to actual conditions.
[0088] S105. Start the electric feed water pump system of the generator set boiler system and add water to the boiler for the first time until the boiler water level is within a preset deviation. Specifically:
[0089] Start the electric feed water pump system of the generator set boiler system, and pay attention to the feed water progress for the first time: that is, pay attention to the water supply progress: and wait for the feed water to be added to the original normal standard close to its current water level. The preset deviation of the boiler water level can be set according to actual conditions.
[0090] S106. Open the respective inlet or outlet electric valves of the high-pressure and low-pressure bypass pipes of the steam turbine. Specifically:
[0091] Open the respective inlet or outlet electric valves of the high-pressure and low-pressure bypass pipes of the steam turbine to realize the "bypass" function of the steam system, that is, to ensure the normal operation of the water supply system as soon as possible.
[0092] S107, close the main steam regulating valve and each sequence valve;
[0093] S108. Add water to the boiler a second time through the electric water supply pump system until the boiler is full. Specifically:
[0094] This is the second time that we have focused on the progress of water supply. We have used the "vacuum condition" of the original dry steam pipeline space above the original normal water level standard to further increase the water supply level, and to increase the water level elevation - including for drum boilers, the water level must exceed the original "midpoint" of the drum water level, for direct current boilers, including the water level above the steam-water separation point, and for other boiler types, until it is completely filled with the highest water level above - that is, it can fill the drum and all steam pipelines, including all superheater pipelines, and all pipelines before the main steam valve - including all branch pipelines.
[0095] S109. Start the boiler combustion system of the generator set to heat the water in the boiler to the maximum steam temperature. Specifically:
[0096] Start the boiler combustion system of the generator set, that is, start the supply and exhaust air fans of the heat source, and its boiler system heat exchange system, that is, to form the normal operation of the heat source system; that is, ignite the boiler combustion system, that is, start heating the steam, or achieve a continuous increase in the steam temperature, and after several hours achieve the maximum steam temperature - this maximum steam temperature must be stabilized at the only saturation temperature under the current end pressure of the water supply system.
[0097] S110, close the cranking motor to realize the "cranking operation" mode of the turbine from zero speed.
[0098] S111. Open the main steam regulating valve, increase the initial opening of the first sequence valve, and increase the turbine speed to within the preset deviation from the rated speed. Specifically:
[0099] Gradually open the main steam regulating valve, that is, by avoiding the resonance area, increase the sequence valve opening, and gradually increase the speed to near the rated speed. The rated speed can be 3000r / min, and the preset deviation of the rated speed can be set according to actual conditions.
[0100] S112. Synchronize the generator set and the large power grid. Specifically:
[0101] By gradually approaching the synchronization moment based on the generator set's rotor power angle, the generator set's "closing" operation is timely achieved, thus achieving synchronous grid connection with the main power grid. This allows the generator set to gradually increase its output from zero, and by increasing the sequence valve opening until it can bear a lower load.
[0102] S113. Close the high-pressure and low-pressure bypass pipe valves of the steam turbine;
[0103] S114, increasing the opening of each sequence valve, specifically:
[0104] Gradually increase the opening of each sequence valve, that is, increase the power generation output, so as to basically meet the normal load demand of the actual output of the generator set.
[0105] S115. Open the electric valves of each level of steam extraction pipeline according to the original regulations of the steam turbine. Specifically:
[0106] Gradually open the electric valves of each level of steam extraction pipeline according to the procedural requirements of the original regulations, that is, realize the steam extraction process of the heat recovery system from #6 to #1, that is, realize the maximum improvement of the power generation efficiency of the heat recovery system.
[0107] Through the above steps, the power generation process with wet steam power generation as the main feature can be fully realized under the premise of ensuring the safety and stability of the boiler and turbine systems.
[0108] The present invention provides a simple and efficient method for increasing steam turbine power generation efficiency, comprising: adding water to the steam turbine boiler until the boiler is full; heating the water in the boiler to the maximum steam temperature; and controlling the steam turbine to generate electricity. The method comprises the following sub-processes: starting the make-up water system of the steam turbine condensate system; starting the steam turbine condensate pump and opening the #5 low-pressure heater electric valve to begin supplying condensate to the deaerator and increase the water level in the deaerator to within a preset deviation of a preset value; opening the main steam regulating valve and various sequence valves; starting the vacuum system to reduce the operating back pressure of the steam turbine to within a preset deviation of the vacuum pressure back pressure standard; starting the electric feedwater pump system of the generator set boiler system to initially add water to the boiler to within a preset deviation of the boiler water level; opening the respective inlet or outlet electric valves of the high- and low-pressure bypass pipes of the steam turbine; closing the main steam regulating valve and various sequence valves; and adding water to the boiler a second time via the electric feedwater pump system until the boiler is full. Furthermore, the present invention can directly realize "wet steam power generation" without engineering modification, including for fossil energy power generation systems, and can continue to retain the existing intermediate reheat steam system, and can greatly improve power generation efficiency.
[0109] Positive effects of the present invention:
[0110] Given that the aforementioned US invention patent has demonstrated for the first time that the intractable global "climate crisis" is leading to humanity's most pressing "extinction crisis"—the primary root cause of this "extinction crisis" lies in the continued rise in greenhouse gas and carbon emissions from traditional power generation processes—the existing technology based on the aforementioned US invention patent requires the effective implementation of thermal system modifications to achieve a significant increase in power generation efficiency. The present invention, however, eliminates all of the aforementioned engineering modifications and thus provides at least a relatively complete wet steam power generation technology system, including the ability to be implemented quickly and effectively achieve a significant increase in power generation efficiency. In other words, the present invention primarily achieves "wet steam power generation" directly without requiring engineering modifications, including for fossil fuel power generation systems, by retaining the existing intermediate reheat steam system.
[0111] Under normal operating conditions, to ensure that the wet steam power generation method does not revert to the original dry steam power generation method at any time, the present invention, through S36, can immediately adjust the feedwater pressure according to the actual increase or decrease in the current power generation load, simply by gradually adjusting the sequence valve opening to achieve power generation load regulation. This can maintain the relative stability of the wet steam power generation method.
[0112] The present invention is based on the contents of S37 and S38, and is precisely combined with specific equipment conditions such as whether there is an intermediate reheat steam system, so as to maximize the power generation efficiency of the fossil fuel power generation system.
[0113] On the contrary, the present invention more importantly includes:
[0114] If the output of the feedwater pumps, including those of the steam-driven feedwater pumps, is moderately restricted, the resulting reduction in feedwater will inevitably lead to a decrease in water volume, ultimately causing the high-humidity steam in the superheater to lose its basic humidity balance. This long-term imbalance will inevitably lead to the formation of superheated dry steam. By continuing to use this superheated dry steam method, the generator set's original "superheated dry steam" power generation method will be achieved. In other words, abandoning the wet steam power generation method will naturally return to the "superheated dry steam" power generation method, without any theoretical or practical obstacles.
[0115] This demonstrates that this invention will undoubtedly achieve the crucial role of immediately and thoroughly reducing carbon emissions in the global power generation industry, thereby restoring a normal, sustainable mode of existence for all humanity and providing the greatest scientific prospect for "wet steam power generation." Furthermore, the original "superheated dry steam" power generation method can be returned to at any time without incurring any losses.
[0116] Therefore, the inventors have made a detailed analysis of the parameter variation characteristics of the relatively complete wet steam power generation thermal system as follows:
[0117] According to the present invention:
[0118] First, the maximum steam inlet pressure is achieved based on the total feed water pressure head minus the internal pressure drop loss of the feed water system. For example, for a 300MW subcritical single-reheat generator set, saturated wet steam above 16Mpa is used.
[0119] The enthalpy value of this wet steam is extremely lower than that of superheated steam, and its mass density will definitely be higher, thus forming the biggest premise for improving work capacity. That is, the increase in its mass density as a work medium will inevitably lead to a year-on-year increase in power generation efficiency.
[0120] That is, the enthalpy value of this wet steam formation is lower than the enthalpy value of the original superheated steam, that is, the initial high humidity, high density, but lower enthalpy high humidity, high density steam is formed, which causes the water vapor discharged after the high-pressure cylinder to become wet steam with lower temperature and enthalpy value, higher humidity and higher density.
[0121] This wet steam will inevitably lead to a substantial increase in the mass flow rate ratio of the heat recovery extraction steam of the high-pressure cylinder, that is, it will inevitably achieve higher power generation efficiency, and then after the reheating process of the intermediate reheat steam that is still retained, the reheated steam formed based on the above steps is of a lower temperature, that is, dry steam that is closer to wet steam, that is, more "low superheated" dry steam, and reheated steam that is closer to wet steam enters the intermediate-pressure cylinder, which at the same time leads to a substantial increase in the heat recovery mass flow rate ratio of the intermediate-pressure cylinder.
[0122] The wet steam then flows out of the intermediate pressure cylinder outlet and into the low pressure cylinder. Finally, after a huge increase in the heat recovery mass flow rate in the low pressure cylinder, the work process is completed, resulting in higher power generation efficiency and lower enthalpy wet steam at the tail of the low pressure cylinder, which is finally discharged to the condenser.
[0123] That is, the cold end system of the steam turbine is finally formed, which has a steam enthalpy value lower than the enthalpy value of the original exhaust steam, that is, the cold end loss with the least energy and the exhaust gas with the lowest energy - discharged into the condenser, and becomes the final condensate inside the condenser. From then on, it can continue to enter the various levels from the low-pressure heater, to the deaerator, to the high-pressure heater to form a continuous, cyclical, wet steam power generation process.
[0124] As mentioned above, this high-density wet steam working medium, which can be immediately realized without modifying the power generation equipment, and the mass flow rate of all heat recovery systems can achieve the most critical proportional increase, will definitely achieve more ideal power generation efficiency, that is, it will definitely achieve a power generation process with lower cold-end losses, that is, it is more likely to achieve a surge in power generation efficiency, that is, this relatively complete wet steam power generation technology system will achieve a surge in power generation efficiency, which has been finally proven in theory.
[0125] That is, this "simplest super method to achieve a surge in turbine power generation efficiency" that is more revolutionary in power generation science will definitely achieve a relatively sufficient and huge surge in power generation efficiency, and the most formal and ultimate conclusion can be drawn.
[0126] Although the inventors do not currently have the conditions to present any calculation results or provide proof of the results of engineering implementation, the basis for achieving this surge in power generation efficiency - including a substantial increase in the density of the power generation medium, a huge increase in the proportion of heat recovery work, and many other extremely critical factors that will lead to a significant reduction in cold-end losses and are extremely beneficial to the surge in power generation efficiency - cannot be denied.
[0127] Therefore, this most revolutionary power generation theory can at least immediately and significantly improve power generation efficiency, and can fully guarantee its most important inevitability. However, the failure to solve the reheating system will inevitably lead to certain energy losses, which will inevitably make it difficult to ensure the most complete realization of a completely ideal steam turbine power generation method - that is, it is impossible to achieve the highest efficiency mode of all fossil energy power generation systems and traditional steam turbine power generation systems.
[0128] As a result, the global power generation industry will surely accelerate the completion of the scientific revolution in power generation, and all mankind will surely be free from the "climate crisis" - that is, the power generation industry will surely be free from the biggest root cause of the "climate crisis", the complete loss of the reputation of the greatest industry, and will surely achieve an immediate surge in global power generation efficiency, that is, a leap forward in the greatest contemporary history of modern mankind.
[0129] The best way to implement the present invention is:
[0130] This invention can be immediately and directly applied to any traditional power generation unit in the global power industry. The greatest inevitability of the resulting surge in traditional power generation efficiency has been realized, that is, the possibility of a scientific revolution in power generation has become more realistic, which is sufficient to resolve the super-tense fundamental situation of the global "climate crisis".
[0131] In order to ensure that wet steam will not cause insufficient capacity of the drain system of the heat recovery system, and that the water level may rise and cause unexpected alarms, the inventors recommend starting the initial test at a lower load level below 50%.
[0132] If the present invention enters a power generation site and is vigorously implemented, it will be easy to find the following at the power generation site:
[0133] The most significant role of the present invention is to achieve a surge in power generation efficiency - that is, the technical effect of the present invention does not require any inspection process based on any engineering test, and will be directly reflected in the fuel consumption of the generator set, that is, the substantial reduction in coal consumption.
[0134] This invention will undoubtedly increase the global power industry's understanding and implementation of the above-mentioned U.S. invention patent, and drive the revolutionary power generation theory of the U.S. invention patent into power generation sites. As a result, this invention will undoubtedly provide a historic and critical theoretical foundation for resolving the "climate crisis."
[0135] Finally, the inventor should state:
[0136] Modern human survival depends most crucially on the most fundamental characteristic of modern history—the widespread and continuous development of electricity, the largest energy source in the modern era. Consequently, relying solely on large-scale electricity has become the most crucial foundation for modern human survival, becoming the core material foundation of all human existence.
[0137] In other words, only the largest-scale electricity can constitute the fundamental material basis for the survival of all mankind. If any problems arise in this fundamental condition for the survival of all mankind, it will inevitably have a serious and undeniable impact on the future destiny of all mankind.
[0138] Furthermore, if the generation of massive amounts of electricity inevitably affects the balance of matter in Earth's atmosphere, it will lead to the most profound and complete destruction of Earth, humanity's only and most sacred home. This will accelerate the inevitable reality of the unviable existence of all humanity. In other words, the continued worsening of the "climate crisis" will inevitably lead to a "crisis of extinction" for all of humanity.
[0139] Furthermore, throughout the history of large-scale power generation, the efficiency of traditional fossil fuel generation has always been "absolutely low," at an extremely low level of around 40%. Naturally, no scientist or inventor has ever been able to "shake" this traditionally low efficiency level. This means that traditional fossil fuel generation inevitably results in the conversion of approximately 60% of fossil fuels into an overwhelming amount of "carbon emissions." These massive "carbon emissions" immediately enter the Earth's atmosphere, becoming the fundamental and enormous source of the intractable "climate crisis" and the most fundamental and irrational reason for the continued rise in global temperatures.
[0140] Therefore, the world must quickly achieve a dramatic increase in conventional power generation efficiency. Only in this way can humanity survive. This invention must be submitted to national and regional patent offices, approved, and implemented as soon as possible to save humanity's very survival.
[0141] As a solar thermal power generation unit applicable to renewable energy, the present invention can greatly improve the power generation theory based on the principle of solar thermal power generation, that is, to achieve a surge in the power generation efficiency of renewable energy. Therefore, in order to obtain support from actual data on the surge in power generation efficiency, the inventor can complete on-site experiments of power generation projects on various solar thermal power generation units as soon as possible.
[0142] Given that solar thermal power generation units can fulfill their heat source function solely through heat exchange with a thermal energy storage system, this power generation method will undoubtedly achieve a radical simplification of the power generation system, enabling direct-flow furnace generation without the need for a heat recovery system. Therefore, we will adopt a more direct approach, increasing the current level of feedwater flow to achieve wet steam power generation.
[0143] The present invention can immediately achieve a surge in the power generation efficiency of all waste-to-energy plants around the world. Therefore, the present invention will surely make the greatest contribution to protecting the living environment for all mankind.
[0144] At the same time, the present invention can temporarily not change the engineering system structure of the waste heat boiler, and can ensure that the normal operation of the power generation site is not disturbed.
[0145] The present invention can directly improve the power generation efficiency of garbage power plants, that is, it can significantly reduce the economic cost of garbage treatment and directly improve the operating efficiency level of environmental protection enterprises.
[0146] In the above embodiments, although the steps are numbered S1, S2, etc., these are only specific embodiments given in this application. Those skilled in the art can adjust the execution order of S1, S2, etc. according to actual conditions, which is also within the scope of protection of the present invention. It can be understood that in some embodiments, some or all of the above embodiments may be included.
[0147] Although the embodiments of the present invention have been shown and described above, it is understandable that the above embodiments are exemplary and cannot be understood as the most fundamental limitation of the present invention. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present invention, which will also constitute a direct infringement of the patent technology of the present invention.
Claims
1. A simple and efficient method for achieving a high efficiency of steam turbine power generation, characterized in that: include: Add water to the steam turbine boiler until the boiler is full; Heat the water in the boiler to the highest temperature of steam; Control steam turbine to generate electricity.
2. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 1, characterized in that: The process of adding water to the boiler of a steam turbine until the boiler is full includes: Start the water supply system of the steam turbine condensate system; Start the condensate pump of the steam turbine and open the #5 low-pressure heater electric door to start supplying condensate to the deaerator and add the water level in the deaerator to the preset deviation of the preset value; Open the main steam regulating valve and each sequence valve; Start the vacuum pumping system to pump the operating back pressure of the steam turbine to within the preset deviation of the back pressure standard of the vacuum pressure; Start the electric feed water pump system of the generator set boiler system and add water to the boiler for the first time to within the preset deviation of the boiler water level; Open the respective inlet or outlet electric valves of the high-pressure and low-pressure bypass pipelines of the steam turbine; Close the main steam regulating valve and each sequence valve; Add water to the boiler a second time through the electric feed water pump system until the boiler is full.
3. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 2, characterized in that: Heating the water in the boiler to the maximum temperature of steam includes: Start the boiler combustion system of the generator set to heat the water in the boiler to the maximum steam temperature.
4. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 3, characterized in that: Control of steam turbine power generation, including: Closing brake motor; Open the main steam regulating valve, increase the initial opening of the first sequence valve, and increase the turbine speed to within the preset deviation of the rated speed; Synchronize the generator set and the large power grid; Close the high-pressure and low-pressure bypass pipeline valves of the steam turbine; Increase the opening of each sequence valve; According to the original regulations of the steam turbine, open the electric valves of each level of steam extraction pipeline.
5. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 4, characterized in that: Controlling steam turbine power generation, including: For the total water supply opening signal of the DCS control system of the generator set load, including the total opening control signal of the sequence valve, a synchronization relationship with the load demand is added.
6. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 4, characterized in that: Controlling steam turbine power generation, including: By closing the flue gas damper opening of the reheat steam, the heat absorption of the reheater is reduced, so that the steam temperature of the turbine cylinder after entering the high-pressure cylinder is lower than the rated steam temperature of the main steam, until it is close to the exhaust temperature of the high-pressure cylinder.
7. The simplest super method for realizing a surge in steam turbine power generation efficiency according to claim 4, characterized in that: Controlling steam turbine power generation, including: By reducing the burner inclination angle, the heat absorption of the reheater is reduced, so that the temperature can be higher than the high-pressure cylinder exhaust temperature and lower than the rated steam temperature of the main steam.
Citation Information
Patent Citations
vertical boiler
AT218206B
System and method for supplying heat to combined circulation machine group of last stage blades of cooling steam turbine
CN110486098A
High back pressure type circulating water heat supply device
CN213686764U
Water recyling setm genertor
KR1020070009021A
Cited By
System and method for shortening starting time of unit by using waste heat of gas turbine cooling system
CN120312366A
System and method for reducing start-up time of a unit using waste heat from a gas turbine cooling system
CN120312366B