Hybrid full bridge power converter with transformer

The power converter efficiently manages input voltage variations by switching between boost and buck modes, optimizing duty cycles to maintain stable output voltage and reduce losses in transformer windings and switches.

WO2026232524A1PCT designated stage Publication Date: 2026-11-12AES GLOBAL HLDG PTE LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2025/093951
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2025-05-09
Publication Date
2026-11-12

AI Technical Summary

Technical Problem

Power converters face challenges in achieving high efficiency across a wide input voltage range while minimizing conduction losses in transformer windings and power switches, particularly in high power situations.

Method used

A power converter design incorporating a transformer with primary and secondary windings, inductors, and switches controlled by a controller to operate in boost and buck modes based on input voltage levels, optimizing duty cycles to maintain efficient voltage conversion.

Benefits of technology

The solution enables high efficiency and minimized conduction losses across varying input voltages by dynamically switching between boost and buck modes, ensuring stable output voltage regulation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2025093951_12112026_PF_FP_ABST
    Figure CN2025093951_12112026_PF_FP_ABST
Patent Text Reader

Abstract

A power converter comprises a plurality of switches including a first switch serially coupled with a second switch via a first node, a third switch serially coupled with a fourth switch via a second node, a fifth switch serially coupled with the second switch via a third node, and a sixth switch serially coupled with the fourth switch via a fourth node. A transformer comprises a primary winding and first and second secondary windings serially coupled together via a fifth node. The first and second secondary windings are coupled between the third node and the fourth node. An inductor is serially coupled with a seventh switch of the plurality of switches between the fifth node and an output, a sixth node serially coupled between the inductor and the seventh switch, and an eighth switch of the plurality of switches coupled between the sixth node and a seventh node.
Need to check novelty before this filing date? Find Prior Art

Description

HYBRID FULL BRIDGE POWER CONVERTER WITH TRANSFORMERTECHNICAL FIELD

[0001] Aspects of the disclosure relate to output power distribution and, more particularly, to power converter efficiency across a wide input voltage range.BACKGROUND

[0002] A power converter is an electrical device that supplies electric power to an electrical load. Indeed, power converters typically have a power input connection, which receives energy in the form of electric current from a source, and one or more power output connections that deliver current to the load. The primary function of a power converter is to convert input electric voltage and current from a source to a target output voltage, current, and / or frequency to power a load. Indeed, a power converter may perform a variety of functions, such as, but not limited to, power conversion, alternating current to direct current (AC-DC) or DC-DC conversion, adjusting voltage levels and ac frequency, and providing backup power during power grid outages.

[0003] Power converters are often provided with a range of acceptable voltage inputs for conversion to a target output voltage. It can be preferred to have a fully regulated output voltage in the whole input voltage range. Managing high conduction losses in transformer windings and power switches while operating in high power situations can lead to design choices between converter efficiency and fully regulated output voltage performance. It is, therefore, desirable to achieve high efficiency over the whole input voltage range while minimizing conduction losses.SUMMARY

[0004] In accordance with one aspect of the present disclosure, a power converter comprises a plurality of switches including a first switch serially coupled with a second switch via a first node, a third switch serially coupled with a fourth switch via a second node, a fifth switch serially coupled with the second switch via a third node, and a sixth switch serially coupled with the fourth switch via a fourth node. A transformer comprises a primary winding coupled between the first node and the second node and a first secondary winding serially coupled with a second secondary winding via a fifth node. The first and second secondary windings are coupled between the third node and the fourth node. An inductor is serially coupled with a seventh switch of the plurality of switches between the fifth node and an output, a sixth node serially coupled between the inductor and the seventh switch, and an eighth switch of the plurality of switches coupled between the sixth node and a seventh node.

[0005] In accordance with another aspect of the present disclosure, a method of controlling a voltage converter having a first plurality of switches serially coupled together, a second plurality of switches serially coupled together, a transformer having primary and secondary windings coupled between the first and second pluralities of switches, an inductor coupled with the secondary windings, a pair of switches coupled with the inductor, and a controller coupled with the first and second pluralities of switches. The method comprises controlling the first and second pluralities of switches to operate in a boost mode of operation in response to an input voltage level of an input voltage being within a boost mode voltage range to convert the input voltage into an output voltage having an output voltage level different than the input voltage level. The method also comprises controlling the first and second pluralities of switches to operate in a buck mode of operation in response to the input voltage level being within a buck mode voltage range to convert the input voltage into the output voltage having the output voltage level.

[0006] In accordance with another aspect of the present disclosure, a converter comprises first plurality of switches serially coupled together, a second plurality of switches serially coupled together, and a transformer. The transformer comprises a primary winding coupled between a first switch of the first plurality of switches and a first switch of the second plurality of switches, and a pair of secondary windings coupled between a second switch of the first plurality of switches and a second switch of the second plurality of switches. The converter also comprises an inductor coupled with the pair of secondary windings, a pair of switches coupled with the inductor, and a controller coupled with the first and second pluralities of switches. The controller is configured to determine a first duty cycle based on a comparison between an output voltage and a reference voltage, control the first and second pluralities of switches to operate in a boost mode of operation in response to the first duty cycle being greater than a saturation duty cycle, and control the first and second pluralities of switches to operate in a buck mode of operation in response to the first duty cycle being less than or equal to the second duty cycle.BRIEF DESCRIPTION OF THE DRAWINGS

[0007] The drawings illustrate embodiments presently contemplated for carrying out the invention.

[0008] In the drawings:

[0009] FIG. 1 illustrates a schematic diagram of a power converter according to one or more embodiments.

[0010] FIG. 2 illustrates control waveforms for contolling the power converter of FIG. 1 using buck mode control according to one or more embodiments.

[0011] FIGS. 3-5 illustrate current flow diagrams through the power converter of FIG. 1 based on the control waveforms of FIG. 2 according to one or more embodiments.

[0012] FIG. 6 illustrates control waveforms for contolling the power converter of FIG. 1 using boost mode control according to one or more embodiments.

[0013] FIG. 7-11 illustrate current flow diagrams through the power converter of FIG. 1 based on the control waveforms of FIG. 6 according to one or more embodiments.

[0014] FIG. 12 illustrates a flowchart for contolling the power converter of FIG. 1 using the buck and boost mode controls according to one or more embodiments.

[0015] FIG. 13 illustrates a flowchart of a duty cycle algorithm according to one or more embodiments.

[0016] FIG. 14 illustrates a transition diagram showing alternative intermediary transient mode controls in addition to the buck and boost mode controls for the power converter of FIG. 1 according to one or more embodiments.

[0017] FIG. 15 illustrates a flowchart for contolling the power converter of FIG. 1 based on the buck, boost, and transient mode controls according to one or more embodiments.

[0018] While the present disclosure is susceptible to various modifications and alternative forms, specific embodiments thereof have been shown by way of example in the drawings and are herein described in detail. It should be understood, however, that the description herein of specific embodiments is not intended to limit the present disclosure to the particular forms disclosed, but on the contrary, the intention is to cover all modifications, equivalents, and alternatives falling within the spirit and scope of the present disclosure. Note that corresponding reference numerals indicate corresponding parts throughout the several views of the drawings.DETAILED DESCRIPTION

[0019] Examples of the present disclosure will now be described more fully with reference to the accompanying drawings. The following description is merely exemplary in nature and is not intended to limit the present disclosure, application, or uses.

[0020] Example embodiments are provided so that this disclosure will be thorough and will fully convey the scope to those who are skilled in the art. Numerous specific details are set forth such as examples of specific components, devices, and methods, to provide a thorough understanding of embodiments of the present disclosure. It will be apparent to those skilled in the art that specific details need not be employed, that example embodiments may be embodied in many different forms and that neither should be construed to limit the scope of the disclosure. In some example embodiments, well-known processes, well-known device structures, and well-known technologies are not described in detail.

[0021] Although the disclosure hereof is detailed and exact to enable those skilled in the art to practice the invention, the physical embodiments herein disclosed merely exemplify the invention which may be embodied in other specific structures. While the preferred embodiment has been described, the details may be changed without departing from the invention, which is defined by the claims.

[0022] FIG. 1 illustrates a schematic diagram of a power converter 100 according to one or more embodiments. An input voltage terminal 101 is coupled to first and second pluralities of switches 102, 103. The first and second pluralities of switches 102, 103 are coupled between the input voltage terminal 101 and a circuit ground or node 104. In a preferred embodiment, the switches of the first and second pluralities of switches 102, 103 are metal-oxide-semiconductor field-effect transistors (MOSFETs) . In other embodiments, the first and second pluralities of switches 102, 103 may be any of a variety of electronic components suitable for use as switches.

[0023] The first plurality of switches 102 includes a pair of switches including a high-side switch (Q1) 105 serially coupled with a mid-side switch (Q2) 106 via a first common node 107. A synchronous switch (Q3) 108 is also included and is serially coupled with the mid-side switch 106 via a second common node 109. The switches 105, 106, and 108 have respective gate terminals (G1) 110, (G2) 111, (G3) 112.

[0024] The second plurality of switches 103 includes another pair of switches including a high-side switch (Q4) 113 serially coupled with a mid-side switch (Q5) 114 via a third common node 115. The second plurality of switches 103 also has a synchronous switch (Q6) 116 serially coupled with the mid-side switch 114 via a fourth common node 117. Gate terminals (G4) 118, (G5) 119, (G6) 120 are included in respective switches 113, 114, 116. The first and second pluralities of switches 102, 103 form a bridge assembly.

[0025] A transformer 121 includes a primary winding 122 coupled between the first common node 107 and the third common node 115. Accordingly, the primary winding 122 is coupled with the high-side switches 105, 113. Additionally, the primary winding 122 is coupled with the mid-side switches 106, 114. A pair of secondary windings 123, 124 of the transformer 121 are serially coupled together via a fifth common node 125 in one embodiment. In another embodiment, the pair of secondary windings 123, 124 comprise respective halves of a single secondary winding having a center tap at the fifth common node 125. The pair of secondary windings 123, 124 are coupled in series between the second common node 109 and the fourth common node 117.

[0026] An output inductor 126 is coupled between the fifth common node 125 and a sixth common node 127, which is further coupled with a pair of switches including a boost low side switch (Q7) 128 and a boost high side switch (Q8) 129, each having a respective gate terminal (G7) 130, (G8) 131. The boost high side switch 129 is further coupled with a positive output voltage terminal 132 configured to supply a converted output voltage to a load 133. A negative output voltage terminal 134 is coupled to the circuit ground 104. An output capacitor 135 is coupled between the positive and negative output voltage terminals 132, 134.

[0027] The power converter 100 includes a controller 136 coupled to the switch gate terminals G1-G8 for controlling the conduction and non-conduction modes of the switches Q1-Q8.Based on a reference voltage 137 and feedback signals indicating the output voltage value on the Vout terminal 132, the controller 136 determines the control signals for the switch gate terminals G1-G8 to generate an output voltage. The reference voltage 137 is set to a voltage value that provides a target voltage for the output voltage of the power converter 100. For example, the reference voltage 137 may be 12 V and is used to compare the sampled output voltage to determine how close the output voltage is to the reference voltage 137. As described below with respect to FIGS. 14, 15, another feedback signal based on the Vin 101 is used for generating / determining the control signals.

[0028] The power converter 100 is controlled by the controller 136 in a boost mode of operation in response to a first range of input voltage provided to the input voltage terminal 101 and in a buck mode of operation in response to a second range of input voltage. While the boost and buck modes are types of control, the output voltage, Vout, is less than either of the first or second ranges of input voltage in some embodiments. That is, even during control according to the boost mode of operation, the output voltage is not a boosted voltage of the input voltage. Instead, as described hereinbelow (see FIG. 6) , the boost mode has some operational similarity with voltage boosting types of controllers using stored energy in an inductor and a toggling switch. The buck mode of operation, however, leaves the toggling switch in a non-conducting mode during its use.

[0029] An exemplary diagram showing waveforms generatable during the buck mode of operation is shown in FIG. 2 according to one or more embodiments. The buck mode is triggered, in this example, based on the inequality: where Vout represents the output voltage, Vin represents an input voltage supplied to the first  and second pluralities of switches, Dbrgs represents a saturation duty cycle of the first and second pluralities of switches, and Nps represents a turns ratio of the transformer. The turns ratio of the transformer is defined as: where Np represents the number of turns of the primary winding (e.g., primary winding 122)  and Ns represents the number of turns of one of the secondary windings (e.g., secondary winding 123 or secondary winding 124) where the number of turns of the secondary windings 123, 124 is the same.

[0030] As shown in FIG. 2, the control signals for the gate terminals G1 110, G2 111, G4 118, G5 119 of the high-and mid-side switches Q1 105, Q2 106, Q4 113, Q5 114 include an on pulse having a width referred to as a bridge duty cycle, Dbrg. The bridge duty cycle is the duty cycle of the on pulse within the bridge period, Tbrg. In each of the time periods t0-t12 illustrated in FIG. 2, the control signal for the gate terminal G7 of the boost low side switch Q7 128 is always off during the buck mode of operation while the control signal for the gate terminal G8 of the boost high side switch Q8 129 is always on. FIG. 2 also shows current response at the current references iP, iS1, iS2, iLout identified in the illustration of power converter 100 in FIG. 1 as the current flows in each time period explained in FIGS. 3-5 below.

[0031] FIGS. 3-5 illustrate example current flow diagrams through the power converter 100 of FIG. 1 during distinct time periods of the buck mode signals of FIG. 2. Three repeating cycles of four time periods are illustrated for the buck mode of operation. Additional cycles follow the repeating pattern. For example, FIG. 3 illustrates current flow during the time period t0-t1 of the waveforms of FIG. 2. As shown, the gate control signals for gate terminals G1, G3, and G5 are on while the gate control signals for gate terminals G2, G4, and G6 are off. Current flows from the high-side switch Q1 105 and the mid-side switch Q5 114 through the secondary winding 124 toward the fifth common node 125 and from the circuit ground 104 through the synchronous switch Q3 108 and through the secondary winding 123 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and through the boost high side switch Q8 129 (which, as stated, is always on) and provides output power through the positive output voltage terminal 132 for the load 133.

[0032] FIG. 4 illustrates current flow during the time period t1-t2 of the waveforms of FIG. 2. As shown, the gate control signals for gate terminals G3 and G6 are on while the gate control signals for gate terminals G1, G2, G4, G5 are off. Current continues to flow through the secondary windings 123, 124 even though input current from the input voltage terminal 101 is cut off. As shown, current flows from the circuit ground 104 through the synchronous switches Q3 108, Q6 116 and through the secondary windings 123, 124 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and through the boost high side switch Q8 129 and provides output power through the positive output voltage terminal 132 for the load 133.

[0033] During the time period t2-t3 of the waveforms of FIG. 2 as illustrated in FIG. 5, the gate control signals for gate terminals G2, G4, and G6 are on while the gate control signals for gate terminals G1, G3, and G5 are off. Current flows from the high-side switch Q4 113 and the mid-side switch Q2 106 through the secondary winding 123 toward the fifth common node 125 and from the circuit ground 104 through the synchronous switch Q6 116 and through the secondary winding 124 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and through the boost high side switch Q8 129 and provides output power through the positive output voltage terminal 132 for the load 133.

[0034] For the remaining time period t3-t4 of the cycle, the switch and current flow behaviors follow the illustration shown in FIG. 4. Subsequent cycles follow the pattern described above and proceed in order as shown in FIGS. 3, 4, 5, and 4.

[0035] Returning to FIG. 2, the controller 136 is configured to determine the duty cycle, Dbrg, during the buck mode of operation based on a feedback signal based on the output voltage on the positive output voltage terminal 132 and based on the reference voltage 137. For example, the determined duty cycle, Dbrg, may be smaller for a larger input voltage and may increase as the input voltage decreases. For example, based on the input voltage, the determined duty cycle may reach a threshold duty cycle, Dbrgs, which, as stated above, represents a saturation duty cycle of the switches Q1-Q6. In one embodiment, the saturation duty cycle is a maximum allowable duty cycle of the bridge assembly. In response to reaching or exceeding the threshold duty cycle, Dbrgs, the controller 136 may be configured to switch control of the power converter 100 based on the buck mode of operation to control based on the boost mode of operation.

[0036] An exemplary diagram showing waveforms generatable during the boost mode of operation is shown in FIG. 6 according to one or more embodiments. The boost mode is triggered, in this example, based on the inequality: where Dbstm represents a minimum duty cycle of operation of the pairs of switches G1 / G5 and  G2 / G4 during the boost mode of operation.

[0037] As shown in FIG. 6, the control signals for the gate terminals G1, G2, G4, G5 of the high-and mid-side switches Q1 105, Q2 106, Q4 113, Q5 114, repectively, include an on pulse having a width set to the max duty cycle width, Dbrgs. While the buck mode of operation described above with respect to FIG. 2 includes determining the width of the on pulses for the gate terminals G1, G2, G4, G5, the boost mode of operation shown in FIG. 6 includes determining the width of the on pulses for the gate terminal 130 of the boost low side switch Q7 128. FIG. 6 also shows current response at the current references iP, iS1, iS2, iLout identified in the illustration of power converter 100 in FIG. 1 as the current flows in each time period explained in FIGS. 7-11 below.

[0038] FIGS. 7-11 illustrate example current flow diagrams through the power converter 100 of FIG. 1 during distinct time periods of the boost mode signals of FIG. 6. Three repeating cycles of six time periods are illustrated for the boost mode of operation. Additional cycles follow the repeating pattern. For example, FIG. 7 illustrates current flow during the time period t0-t1 of the waveforms of FIG. 6. As shown, the gate control signals for gate terminals G1, G3, G5, and G7 are on while the gate control signals for gate terminals G2, G4, G6, and G8 are off. Current flows from the high-side switch Q1 105 and the mid-side switch Q5 114 through the secondary winding 124 toward the fifth common node 125 and from the circuit ground 104 through the synchronous switch Q3 108 and through the secondary winding 123 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and to ground through the boost low side switch Q7 128 for the brief time period t0-t1 to store energy in the magnetic field about the inductor 126. During this time period, no current or energy is supplied to the positive output voltage terminal 132.

[0039] FIG. 8 illustrates current flow during the time period t1-t2 of the waveforms of FIG. 6. As shown, the gate control signals are similar to those of time period t0-t1 except that the boost low side switch Q7 128 and the boost high side switch Q8 129 switch conduction modes. As shown, the boost low side switch Q7 128 turns off while the boost high side switch Q8 129 turns on. As such, the magnetic field created during the time period t0-t1 will be reduced in energy to maintain the current through the inductor 126. The current from both the voltage source (e.g., through the switches G1, G3, G5 and secondary windings 123, 124) and the inductor 126 will add together and be redirected through the boost high side switch Q8 129 to provide output power through the positive output voltage terminal 132 for the load 133.

[0040] The subsequent time period t2-t3 illustrated in FIG. 9 follows the behavior of FIG. 4 above. That is, the gate control signals for gate terminals G3, G6, and G8 are on while the gate control signals for gate terminals G1, G2, G4, G5, and G7 are off. Current continues to flow through the secondary windings 123, 124 even though input current from the input voltage terminal 101 is cut off. As shown, current flows from the circuit ground 104 through the synchronous switches Q3 108, Q6 116 and through the secondary windings 123, 124 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and through the boost high side switch Q8 129 and provides output power through the positive output voltage terminal 132 for the load 133.

[0041] FIG. 10 illustrates a second half of the repeating cycle shown in FIG. 6. As shown during the time period t3-t4, the gate control signals for gate terminals G2, G4, G6, and G7 are on while the gate control signals for gate terminals G1, G3, G5, and G8 are off. Current flows from the high-side switch Q4 113 and the mid-side switch Q2 106 through the secondary winding 123 toward the fifth common node 125 and from the circuit ground 104 through the synchronous switch Q6 116 and through the secondary winding 124 toward the fifth common node 125. From the fifth common node 125, current flows through the inductor 126 and to ground through the boost low side switch Q7 128 to store energy in the magnetic field about the inductor 126. During this time period, no current or energy is supplied to the positive output voltage terminal 132.

[0042] FIG. 11 illustrates current flow during the time period t4-t5 of the waveforms of FIG. 6. As shown, the gate control signals are similar to those of time period t3-t4 except that the boost low side switch Q7 128 and the boost high side switch Q8 129 switch conduction modes. As shown, the boost low side switch Q7 128 turns off while the boost high side switch Q8 129 turns on. As such, the magnetic field created during the time period t3-t4 will be reduced in energy to maintain the current through the inductor 126. The current from both the voltage source (e.g., through the switches G2, G4, G6 and secondary windings 123, 124) and the inductor 126 will add together and be redirected through the boost high side switch Q8 129 to provide output power through the positive output voltage terminal 132 for the load 133.

[0043] For the remaining time period t5-t6 of the cycle, the switch and current flow behaviors follow the illustration shown in FIG. 9. Subsequent cycles follow the pattern described above and proceed in order as shown in FIGS. 7, 8, 9, 10, 11, and 9.

[0044] FIG. 12 illustrates a flowchart of a method 1200 for contolling the power converter of FIG. 1 using the buck and boost mode controls according to one or more embodiments. Following a method start at step 1201, the method 1200 sets a value for the bridge saturation duty cycle, Dbrgs, at step 1202, which represents a threshold duty cycle for the first and second pluralities of switches. Setting the value for the bridge saturation duty cycle may include obtaining the value from memory, the value having been provided by the manufacturer of the switches in some examples or determined by evaluation in other examples such as during testing of the manufacturing of the power converter 100. In one embodiment, the controller 136 may include the memory storage for storing the value of the bridge saturation duty cycle. In other embodiments, the power converter 100 may include separate memory storage components. When the duty cycle (Dbrg) is less than or equal to this threshold, the buck mode of operation will be used. When the duty cycle is greater than this threshold, the boost mode of operation will be used. The output voltage Vout is sampled at step 1203. For example, the controller 136 may sample the signal indicative of Vout. In another embodiment, another component such as a voltage sensor may provide sampled voltages to the controller 136. Both the bridge saturation duty cycle, Dbrgs, and the sampled output voltage are sent to and used by a duty cycle algorithm at step 1204. The duty cycle algorithm 1204 is described with respect to FIG. 13 below. Following execution of the duty cycle algorithm at step 1204, the method 1200 ends at step 1205.

[0045] FIG. 13 illustrates a flowchart of the duty cycle algorithm 1204 according to one or more embodiments. Following a method start at step 1300, the duty cycle algorithm 1204 determines a desired duty cycle, D, at step 1301 based on the bridge saturation duty cycle, Dbrgs, from step 1202 of the method 1200, based on the sampled output voltage from step 1203 of the method 1200, and based on the reference voltage 137 (see FIG. 1) . The duty cycle, D, is determined independently of which control mode is used (e.g., the buck mode or the boost mode) . In this manner, the control mode to be used can be chosen in subsequent steps.

[0046] At step 1302, the determined duty cycle, D, is compared with the determined bridge saturation duty cycle, Dbrgs, from step 1202 of the method 1200. Based on the determined duty cycle, D, being less than the bridge saturation duty cycle, Dbrgs (step 1303) , the buck mode of control 1304 is used. The buck mode of control 1304 includes setting, at step 1305, the bridge duty cycle, Dbrg, to the value of the determined duty cycle (from step 1301) . The bridge duty cycle, Dbrg, is the duty cycle of the controlled switches (e.g., switches G1 / G5 and G2 / G4 as shown in FIG. 2) . Since the boost mode of operation is not used, the value for the boost duty cycle, Dbst, is set to zero at step 1306, which controls the boost low side switch Q7 128 into a non-conduction mode during a portion of the control cycle.

[0047] At step 1307, the control signals according to the updated duty cycle values are generated. The duty cycle algorithm 1204 ends at step 1308.

[0048] Returning to step 1302, if the determined duty cycle, D, is greater (1309) than the saturation duty cycle, Dbrgs, the boost mode of control 1310 is used. At step 1311, the bridge duty cycle, Dbrg, is set to the value of the saturation duty cycle, Dbrgs. As such, the duty cycles of any of the high-or mid-side switches 105, 106, 113, 114 do not extend beyond the time set by the saturation duty cycle, Dbrgs, at step 1202 of the method 1200. Since the boost mode of control 1310 is used, switching control of the boost low side switch Q7 128 and the boost high side switch Q8 129 is performed (such as depicted in FIGS. 6-10) . Accordingly, at step 1312, the boost duty cycle, Dbst, is set according to the equation: Dbst=k· (D-Dbrgs) (Eqn. 4) , where k represents a scalar value configured to optimize the boost duty cycle. As shown in FIG.  6, the switching frequency of the bridge switches (e.g., switches G1 / G5 and G2 / G4) is half of the switch frequency of the boost low and high side switches Q7 and Q8. The duty cycle, D, being determined based on the switching frequency of the bridge switches may need some adjustment to account for the difference in switching frequencies. The value for k may be determined and set during testing, for example, to adjust and optimize operation of the power converter 100 of FIG. 1 during the boost mode of operation of FIG. 6.

[0049] Following the boost mode of control 1310, the duty cycle algorithm 1204 proceeds to step 1307 for generating control signals as described above. For instance, when the control switches G1-G8 are implemented as MOSFETs, the controller 136 may generate gate drive signals as described above with respect to FIGS. 2-11. For example, based on the buck mode of control 1304, the controller 136 may generate gate drive signals to control the switches G1-G8 as described above with respect to FIGS. 2-5, whereas based on the boost mode of control 1310, the controller 136 may generate gate drive signals to control the switches G1-G8 as described above with respect to FIGS. 6-11.

[0050] In some cases, the voltage zone around the switching point between the buck and boost modes of control can cause jitter in the output voltage. For example, based on a maximum duty cycle of the saturation duty cycle Dbrgs in the buck mode of operation and the minimum duty cycle Dbstm of the boost mode of operation, an input voltage range may exist in an undefined zone between the maximum input voltage of the boost mode and the minimum voltage of the buck mode. Should the input voltage fall within the undefined zone, a burst or quasi-boost mode may be implemented where the boost low side switch Q7 128 is controlled into the conduction mode during some of the control signal cycles and into the non-conduction mode during other control signal cycles. A jitter in the output voltage may be the result.

[0051] To address this situation, FIG. 14 illustrates a transition diagram 1400 showing an intermediary transient mode control in addition to the buck and boost mode controls for the power converter of FIG. 1 according to one or more embodiments. A boost mode of control 1401 is used between a low input voltage threshold V1 1402 and an upper input voltage threshold V3 1403. The boost mode of control 1401 is controlled as described above. As the input voltage 1404 increases beyond the upper voltage threshold V3 1403, a transient mode of control 1405 is used. That is, control of the first and second pluralities of switches 102, 103 is switched from the boost mode of control 1401 to the transient mode of control 1405 in response to the input voltage 1404 crossing the upper threshold V3 1403 between a prior input voltage 1404 (e.g., reported in a prior output voltage feedback signal) being less than the upper threshold V3 1403 and a subsequent voltage value (e.g., reported in a subsequent output voltage feedback signal) being greater than the upper threshold V3 1403.

[0052] To engage the transient mode of control 1405 in response to crossing the upper threshold V3 1403, the threshold or saturation duty cycle, Dbrgs, is changed. In one example, the Dbrgs is set to a value of 0.49 while mode control is in the boost mode of control 1401. By changing the Dbrgs to a lower value, operation according to the same boost mode of control 1401 can be maintained while the upper threshold V3 1403 is extended at the same time. In this example, a change in the Dbrgs from 0.49 to 0.47 extends the upper threshold V3 1403 of the boost mode of control 1401 to the transient mode upper threshold V5 1406 as illustrated. During the transient mode of control 1405, the Dbrgs is set to the lower value than in the boost mode of control 1401; however, the protocols used during the boost mode of control 1401 are maintained in the transient mode of control 1405. While the transient mode of control 1405 is enabled in response to the input voltage 1404 increasing beyond the upper threshold V3 1403, once the Dbrgs is changed, the transient mode lower threshold V2 1407 becomes the active lower threshold for determining when to transition back to the boost mode of control 1401.

[0053] In response to a continued increase of the input voltage 1404 beyond the transient mode upper threshold V5 1406, mode control switches to the buck mode of control 1408. That is, control of the first and second pluralities of switches 102, 103 is switched from the transient mode of control 1405 to the buck mode of control 1408 in response to the input voltage 1404 crossing the transient mode upper threshold V5 1406 between a prior input voltage level (e.g., reported in a prior output voltage feedback signal) being less than the transient mode upper threshold V5 1406 and a subsequent voltage value (e.g., reported in a subsequent output voltage feedback signal) being greater than the transient mode upper threshold V5 1406. Switching to the buck mode of control 1408 from the transient mode of control 1405 includes changing the Dbrgs value back to the higher value. So, for example, the Dbrgs is changed from 0.47 during the transient mode of control 1405 back to 0.49 during the buck mode of control 1408. The buck mode of control 1408 is controlled as described above.

[0054] Due to a hysteresis zone 1409, the buck mode of control 1408 remains being used in response to the input voltage 1404 falling below the transient mode upper threshold V5 1406. While the input voltage 1404 is below the transient mode upper threshold V5 1406 but above a lower voltage threshold V4 1410 of the buck mode of control 1408, no transition back to the transient mode of control 1405 is begun. However, in response to the input voltage falling below the lower voltage threshold V4 1410, the transient mode of control 1405 is used by again changing the Dbrgs such as to a lower value as described in the example herein. That, is, control of the first and second pluralities of switches 102, 103 is switched from the buck mode of control 1408 to the transient mode of control 1405 in response to the input voltage 1404 crossing the lower voltage threshold V4 1410 between a prior input voltage 1404 (e.g., reported in a prior output voltage feedback signal) being greater than the lower voltage threshold V4 1410 and a subsequent voltage value (e.g., reported in a subsequent output voltage feedback signal) being less than the lower voltage threshold V4 1410.

[0055] As above, during the transient mode of control 1405, the Dbrgs is set to a different value, but the protocols of the boost mode of control 1401 are used. The transient mode lower threshold V2 1407 becomes the active lower threshold for transitioning back to the boost mode of control 1401. Below this threshold V2 1407, control switches back to the boost mode of control 1401. That, is, control of the first and second pluralities of switches 102, 103 is switched from the transient mode of control 1405 to the boost mode of control 1401 in response to the input voltage 1404 crossing the transient mode lower threshold V2 1407 between a prior input voltage 1404 (e.g., reported in a prior output voltage feedback signal) being greater than the transient mode lower threshold V2 1407 and a subsequent voltage value (e.g., reported in a subsequent output voltage feedback signal) being less than the transient mode lower threshold V2 1407. The hysteresis zone 1411 prevents a transition to the transient mode of control 1405 in response to the input voltage rising above the transient mode lower threshold V2 1407 while remaining below the boost mode upper threshold V3 1403.

[0056] FIG. 15 illustrates a flowchart of a method 1500 for contolling the power converter of FIG. 1 based on the buck, boost, and transient mode controls illustrated in FIG. 14 according to one or more embodiments. Referring to FIGS. 14 and 15, following a method start at step 1501, a value for the bridge saturation duty cycle, Dbrgs, is set at step 1502. As described above, the value for Dbrgs is preferably a first value for the boost and buck modes of control and a second, lower value during the transient mode of control. At step 1503, the output voltage Vout is sampled. The sampled output voltage Vout and the input voltage Vin are analyzed at step 1504. As shown in FIG. 14, increases and decreases in the input voltage Vin affect control mode usage. As such, the method 1500 tracks the input voltage Vin to evaluate whether it increases or decreases based on earlier or previous values. Based on the input voltage Vin being in one of the voltage ranges shown in FIG. 14 and based on the direction of its changing value, if any, an operation mode is chosen at step 1505. For example, based on an increase in input voltage Vin beyond the upper voltage threshold V3 1403, the transient mode of control 1405 may be chosen. In another example, the current mode of control (e.g., the boost mode of control 1401, the buck mode of control 1408, or the transient mode 1405) may be chosen based on no threshold crossing.

[0057] At step 1506, a mode change is determined. If the present or same mode of control is to be maintained (1507) , the step 1204 is executed as previously described. However, if a mode change is chosen (1508) , steps for a mode change 1509 are performed. At step 1510, the duty cycle D for the opposite mode is pre-determined. For example, if the current mode is the boost mode of control 1401, the duty cycle D for the buck mode of control 1408 is determined at step 1510. Alternatively, if the current mode is the buck mode of control 1408, the duty cycle D for the boost mode of control 1401 is determined at step 1510. The pre-determined duty cycle D for the alternate mode of control is used together with the alternate mode of control at step 1511. In this step, the opposite or alternate mode of control is forced into use despite the current mode of control being an operational choice based on the output voltage Vout. The alternate mode of control is changed to the current mode of control at step 1512. In some embodiments, changing the control mode may include updating or switching between loop compensation parameters (or other operating parameters) , which may be used as part of the buck and / or boost operating modes. The method 1500 ends at step 1513.

[0058] The methods and processes described herein may be performed by the controller 136 of the power supply 100 of FIG. 1 in one embodiment. For example, the controller 136 may be configured to perform at least the buck and boost mode control processes described in FIGS. 12-15. The controller 136 is representative of any system or collection of systems with which the various operational architectures, processes, scenarios, and sequences disclosed herein for performing buck and boost mode control processes may be employed. The controller 136 may be implemented as a single apparatus, system, or device or may be implemented in a distributed manner as multiple apparatuses, systems, or devices. In another embodiment, portions of the buck and boost mode control processes described herein may be run or executed on one or more separate controller / processor devices (outside of the power supply 100) that provides information to the controller 136 for generating the described control signals, for example.

[0059] While the invention has been described in detail in connection with only a limited number of embodiments, it should be readily understood that the invention is not limited to such disclosed embodiments. Rather, the invention can be modified to incorporate any number of variations, alterations, substitutions, or equivalent arrangements not heretofore described, but which are commensurate with the spirit and scope of the present disclosure. Additionally, while various embodiments of the present disclosure have been described, it is to be understood that aspects of the present disclosure may include only some of the described embodiments. Accordingly, the invention is not to be seen as limited by the foregoing description but is only limited by the scope of the appended claims.

Claims

1.A power converter comprising:a plurality of switches comprising:a first switch serially coupled with a second switch via a first node;a third switch serially coupled with a fourth switch via a second node;a fifth switch serially coupled with the second switch via a third node; anda sixth switch serially coupled with the fourth switch via a fourth node;a transformer comprising:a primary winding coupled between the first node and the second node; anda first secondary winding serially coupled with a second secondary winding via a fifth node;wherein the first and second secondary windings are coupled between the third node and the fourth node;an inductor serially coupled with a seventh switch of the plurality of switches between the fifth node and an output;a sixth node serially coupled between the inductor and the seventh switch; andan eighth switch of the plurality of switches coupled between the sixth node and a seventh node.2.The power converter of claim 1 further comprising a voltage input coupled to each of the first switch and the third switch;wherein the fifth switch and the sixth switch are further coupled with the seventh node; andwherein the seventh node comprises a circuit ground.3.The power converter of claim 2 further comprising a controller coupled with the plurality of switches and configured to:receive a output feedback signal based on a voltage level of the output; andcontrol the plurality of switches based on the feedback signal to produce a desired output voltage.4.The power converter of claim 3, wherein the controller is configured to:determine a duty cycle of a plurality of control signals configured to control operation of the first, second, third, and fourth switches to generate the voltage level based on a reference voltage;control the plurality of switches to operate in a boost mode of operation in response to the duty cycle being greater than a maximum duty cycle; andcontrol the plurality of switches to operate in a buck mode of operation in response to the duty cycle being less than the maximum duty cycle.5.The power converter of claim 3, wherein the controller is configured to:receive a voltage input feedback signal based on a voltage level of the voltage input;control the plurality of switches to operate in a boost mode of operation in response to the voltage level of the voltage input being within a boost mode voltage range; andcontrol the plurality of switches to operate in a buck mode of operation in response to the voltage level of the voltage input being with a buck mode voltage range.6.The power converter of claim 5, wherein the boost mode voltage range is lower than the buck mode voltage range.7.The power converter of claim 5, wherein the controller is configured to:control the plurality of switches to operate in a transient mode in response to the voltage level of the voltage input rising above an upper voltage limit of the boost mode voltage range; andcontrol the plurality of switches to operate in the transient mode in response to the voltage level of the voltage input falling below a lower voltage limit of the buck mode of operation.8.The power converter of claim 5, wherein the controller is configured to:maintain the seventh switch in a conduction mode during the buck mode of operation; andmaintain the eighth switch in a non-conduction mode during the buck mode of operation.9.The power converter of claim 5, wherein the controller is configured to:control the seventh switch to operate in each of the conduction mode and the non-conduction mode during the boost mode of operation;control the eighth switch to operate in the conduction mode in response to controlling the seventh switch to operate in the non-conduction mode during the boost mode of operation; andcontrol the eighth switch to operate in the non-conduction mode in response to controlling the seventh switch to operate in the conduction mode during the boost mode of operation.10.A method of controlling a voltage converter having a first plurality of switches serially coupled together, a second plurality of switches serially coupled together, a transformer having primary and secondary windings coupled between the first and second pluralities of switches, an inductor coupled with the secondary windings, a pair of switches coupled with the inductor, and a controller coupled with the first and second pluralities of switches, the method comprising:controlling the first and second pluralities of switches to operate in a boost mode of operation in response to an input voltage level of an input voltage being within a boost mode voltage range to convert the input voltage into an output voltage having an output voltage level different than the input voltage level; andcontrolling the first and second pluralities of switches to operate in a buck mode of operation in response to the input voltage level being within a buck mode voltage range to convert the input voltage into the output voltage having the output voltage level.11.The method of claim 10, wherein the voltage converter comprises a bridge assembly comprising the first and second pluralities of switches; andfurther comprising:setting a value of a saturation duty cycle of the bridge assembly equal to a maximum allowable duty cycle of the bridge assembly;acquiring the output voltage level;comparing the output voltage level to a reference voltage;determining a current duty cycle based on the comparison; andcomparing the current duty cycle with the value of the saturation duty cycle.12.The method of claim 11, wherein controlling the first and second pluralities of switches to operate in the boost mode of operation comprises controlling the first and second pluralities of switches to operate in the boost mode of operation in response to the current duty cycle being greater than the value of the saturation duty cycle; andwherein controlling the first and second pluralities of switches to operate in the buck mode of operation comprises controlling the first and second pluralities of switches to operate in the buck mode of operation in response to the current duty cycle being less than the value of the saturation duty cycle.13.The method of claim 11 further comprising:switching control of the first and second pluralities of switches in the boost mode of operation to control of the first and second pluralities of switches in a transient mode of operation in response to the input voltage level crossing a first transient voltage threshold between a prior input voltage level being less than the first transient voltage threshold and a subsequent voltage value being greater than the first transient voltage threshold; andswitching control of the first and second pluralities of switches in the buck mode of operation to control of the first and second pluralities of switches in the transient mode of operation in response to the input voltage level crossing a second transient voltage threshold between the prior input voltage level being greater than the second transient voltage threshold and the subsequent voltage value being less than the second transient voltage threshold.14.The method of claim 13, wherein the first transient voltage threshold comprises an upper limit of the boost mode voltage range; andwherein the second transient voltage threshold comprises a lower limit of the buck mode voltage range.15.The method of claim 13 further comprising:switching control of the first and second pluralities of switches in the transient mode of operation to control of the first and second pluralities of switches in the buck mode of operation in response to the input voltage level crossing a third transient voltage threshold between the prior input voltage level being less than the third transient voltage threshold and the subsequent voltage value being greater than the third transient voltage threshold; andswitching control of the first and second pluralities of switches in the transient mode of operation to control of the first and second pluralities of switches in the boost mode of operation in response to the input voltage level crossing a fourth transient voltage threshold between the prior input voltage level being greater than the fourth transient voltage threshold and the subsequent voltage value being less than the fourth transient voltage threshold.16.A converter comprising:first plurality of switches serially coupled together;a second plurality of switches serially coupled together;a transformer comprising:a primary winding coupled between a first switch of the first plurality of switches and a first switch of the second plurality of switches; anda pair of secondary windings coupled between a second switch of the first plurality of switches and a second switch of the second plurality of switches;an inductor coupled with the pair of secondary windings;a pair of switches coupled with the inductor; anda controller coupled with the first and second pluralities of switches and configured to:determine a first duty cycle based on a comparison between an output voltage and a reference voltage;control the first and second pluralities of switches to operate in a boost mode of operation in response to the first duty cycle being greater than a saturation duty cycle; andcontrol the first and second pluralities of switches to operate in a buck mode of operation in response to the first duty cycle being less than or equal to the second duty cycle.17.The converter of claim 16, wherein, during control of the first and second pluralities of switches to operate in the buck mode of operation, where Vout comprises the output voltage, Vin comprises an input voltage supplied to the first and second pluralities of switches, Dbrgs comprises a second duty cycle of the first and second pluralities of switches, and Nps comprises a turns ratio of the transformer.18.The converter of claim 17, wherein, during control of the first and second pluralities of switches to operate in the boost mode of operation, where Dbstm comprises a minimum duty cycle of operation of the pair of switches during the boost mode of operation.19.The converter of claim 16, wherein the controller is further configured to:control the first and second pluralities of switches to operate in a transient mode of operation in response to an input voltage supplied to the first and second pluralities of switches crossing a first transition voltage threshold between a prior input voltage level being less than the first transition voltage threshold and a subsequent voltage value being greater than the first transition voltage threshold; andcontrol the first and second pluralities of switches to operate in the transient mode of operation in response to the input voltage crossing a second transition voltage threshold between the prior input voltage level being greater than the second transition voltage threshold and the subsequent voltage value being less than the second transition voltage threshold.20.The converter of claim 19, wherein the controller is further configured to:switching control of the first and second pluralities of switches in the transient mode of operation to control of the first and second pluralities of switches in the buck mode of operation in response to the input voltage crossing a third transition voltage threshold between the prior input voltage level being less than the third transition voltage threshold and the subsequent voltage value being greater than the third transition voltage threshold; andswitching control of the first and second pluralities of switches in the transient mode of operation to control of the first and second pluralities of switches in the boost mode of operation in response to the input voltage crossing a fourth transition voltage threshold between the prior input voltage level being greater than the fourth transition voltage threshold and the subsequent voltage value being less than the fourth transition voltage threshold.