Novel pillarless short-hole shrinkage mining method with inter-pillar recovery

By constructing roadways and connecting roads in the footwall of the ore body, and then mining and filling the intermediate pillars before mining the stope, the problem of high ore loss and waste rock mixing rate of the intermediate pillars in the traditional shallow hole ore retention method is solved, thus achieving efficient resource recovery and improved stope stability.

WO2026237285A1PCT designated stage Publication Date: 2026-11-19SINOSTEEL MAANSHAN INST OF MINING RES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2025/133281
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2025-05-12
Filing Date
2025-11-07
Publication Date
2026-11-19

AI Technical Summary

Technical Problem

Traditional shallow-hole ore retention methods suffer from severe ore loss and high dilution rates in intermediate pillars. Furthermore, shallow-hole ore retention without bottom pillars and subsequent backfilling mining methods suffer from excessive waste rock incorporation, high construction difficulty, and high construction costs.

Method used

A novel bottomless shallow-hole ore-keeping mining method with pillar recovery is adopted. By constructing intermediate transport roadways, pillar ore extraction roadways, and external ventilation shafts in the footwall of the ore body, combined with pillar connecting roadways and stope connecting roadways, the pillars are first mined and backfilled before the stope is mined. Micro-delay blasting and remote-controlled loaders are used for ore recovery. High-density polyethylene pipes and C25 quick-setting concrete are used for backfilling to ensure backfilling quality.

Benefits of technology

It significantly improves the recovery rate of mineral resources, reduces resource waste, increases the economic benefits of mines, enhances the stability of mining areas, and solves the problem of the difficulty in recovering intermediate pillars using traditional methods, increasing the recovery rate to over 88%.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2025133281_19112026_PF_FP_ABST
    Figure CN2025133281_19112026_PF_FP_ABST
Patent Text Reader

Abstract

Disclosed in the present invention is a novel pillarless short-hole shrinkage mining method with inter-pillar recovery, wherein an ore body is stoped from top to bottom; after the stoping of the ore body in an upper level is completed, a stope to be mined (9.1) and an inter-pillar to be mined (8.1) in a lower level are stoped; an inter-pillar (8.2) being stoped is in communication with an off-vein manway ventilation and fill raise (6) arranged on a footwall rock of the ore body, via an inter-pillar crosscut; the off-vein manway ventilation and fill raise (6) has a lower end in communication with the top of an inter-pillar ore-drawing drift (10) in this level, and a top end in communication with an inte-pillar ore-drawing drift (10) in the upper level; and the right end of the inter-pillar ore-drawing drift (10) in the upper level is in communication with a haulage drift (2) in the upper level. The present invention solves the problems of large ore loss and difficult recovery of inter-pillars in the conventional short-hole shrinkage mining method, and has an increased resource recovery rate of 88% or more, such that the compressive strength of artificial inter-pillars after filling is greater than that of natural pillars, and the stability of stopes is significantly improved.
Need to check novelty before this filing date? Find Prior Art

Description

A novel bottomless shallow-hole ore-keeping mining method with interstitial pillar recovery Technical Field

[0001] This invention belongs to the field of underground mining technology, specifically relating to a novel bottomless shallow-hole ore-keeping mining method that includes pillar recovery. It is particularly suitable for mining medium-thick steeply dipping ore bodies with a thickness of 3-8m, a dip angle of 50-85°, and moderate to high rock stability. Its advantages are particularly prominent in the mining of high-grade precious metals, rare metals, and non-metallic minerals such as fluorite. Background Technology

[0002] Shallow hole sawing is a widely used mining method in underground mining, playing a vital role in the mining of precious metals, rare metals, and non-metallic minerals such as fluorite due to its relatively simple construction process. However, under the current industry context of increasingly stringent requirements for mine resource recovery rates, the drawbacks of traditional shallow hole sawing are gradually becoming apparent, with significant ore loss being particularly prominent, urgently requiring effective solutions.

[0003] Traditional shallow-hole stope mining methods typically employ pillars, originally intended to support the stops and ensure safety during mining. However, in normal mining operations, these pillars often fail to yield the ore, resulting in significant permanent loss of ore. This is particularly severe when the ore body is high-grade, valuable, large-scale, and has a large number of stops, with cumulative pillar ore losses reaching 15%–30%. This not only significantly reduces the mine's resource recovery rate but also causes substantial resource waste, severely impacting the economic benefits of mining companies. Furthermore, even with subsequent dedicated pillar recovery in actual mining operations, challenges remain, including low recovery rates and high dilution rates.

[0004] Chinese patent CN202210861113.5 discloses a method for recovering interstitial pillars in a shallow-hole ore-holding and subsequent backfilling mining method without bottom pillars. The method for recovering interstitial pillars includes the following steps:

[0005] d1) Drill multiple rows of shallow holes arranged upwards into each column;

[0006] d2) The bottom row of inter-column in the middle section is blasted and mined in sections. The blasted ore naturally falls into the external transport roadway of the middle section footwall and is discharged by mine cars. After the ore is discharged, steel parts are inserted into the surrounding rock of the footwall and footwall of the row of inter-column to block the waste rock in the void area.

[0007] d3) Repeat step d2) to complete the ore extraction of all inter-pillars from bottom to top;

[0008] d4) After all the inter-pillars have been mined, the voids between the inter-pillars are filled with waste rock in a non-cemented manner to control the ground pressure, thereby completing the recovery of the top and inter-pillars in the middle section.

[0009] Although this method can recover the remaining interstitial columns, the waste rock backfill is easily mixed into the ore body during blasting and ore extraction, resulting in an excessively high waste rock mixing rate. In addition, the construction of steel components to isolate the waste rock backfilling areas on both sides after mining presents problems such as high construction difficulty, complex construction technology, and high construction cost. Summary of the Invention

[0010] The purpose of this invention is to address the problems of severe ore loss and high dilution rate in traditional shallow-hole ore retention methods, as well as the high waste rock mixing rate, high construction difficulty, complex construction process, and high construction cost in subsequent backfilling mining methods for shallow-hole ore retention without bottom pillars. The invention provides a novel shallow-hole ore retention mining method with pillar recovery, which has a high resource recovery rate, high stope stability, and relatively simple construction process. Furthermore, the compressive strength of the artificial pillars after backfilling is superior to that of the original pillars.

[0011] To achieve the above-mentioned objectives of this invention, a novel shallow-hole ore-holding method with pillar recovery is provided. In this method, the ore-to-be-mined stope and the pillars to be mined are arranged at intervals along the strike of the ore body within the intermediate section. On both sides of the ore-to-be-mined stope, there are pillars being mined and pillar stopes being filled. The upper part of the pillar of the ore-to-be-mined stope is the upper-middle section stope that has been mined out. The lower part of the pillars being mined is the ore stored in the pillar stope. The upper part of the pillars being mined and the pillar stopes being filled are the upper-middle section filled pillar stopes. The lower part of the ore-to-be-mined stope is the ore stored in the stope, and the sides are the filled pillar stopes. The method is characterized by the following steps:

[0012] S1 preparation engineering layout

[0013] ① In the footwall of the ore body, a mid-section transport roadway is constructed along the strike direction of the ore body. The cross-sectional dimensions of the mid-section transport roadway are: 2.5-4.0m wide and 2.6-3.5m high. The distance between the mid-section transport roadway and the ore body is 5-15m.

[0014] ② Along the middle section transport roadway, at intervals of 5-6m, a stope exit roadway is excavated perpendicularly or obliquely at 45-60° towards the stope to be mined. The stope exit roadway extends from the stope to the contact surface between the ore body and the hanging wall. The net cross-sectional dimensions of the stope exit roadway are: width 2.2-3.0m, height 2.4-3.0m.

[0015] ③ A column ore extraction roadway is excavated perpendicularly or obliquely to the column to be mined along the middle section transport roadway. The column ore extraction roadway extends through the column to be mined to the contact surface between the ore body and the hanging wall. The net cross-sectional dimensions of the column ore extraction roadway are: width 2.2-3.0m and height 2.4-3.0m.

[0016] ④ Construct an external ventilation shaft upwards from the top of the ore body's footwall surrounding rock within a 5-8m range of the footwall of the ore body's column 8.1. The external ventilation shaft has the following dimensions: length 1.8-2.0m and width 1.8-2.0m. The slope of the external ventilation shaft is consistent with the dip angle of the ore body. The top of the external ventilation shaft is connected to the corresponding upper-middle section ore body's column ...

[0017] ⑤ Construct a connecting road between the columns every 3-5m vertically to the column to be mined in the external ventilation shaft. On both sides of the external ventilation shaft, construct a connecting road to the ore chambers on both sides of the column to be mined, stopping when the ore body is just exposed, without penetrating the ore body. The connecting roads between the columns and the connecting roads to the ore chambers are arranged alternately, with a vertical distance of ≥1.5m between them. The contact surface between the ore chamber and the connecting road to the ore chamber is at least 2m away from the boundary of the column to be mined. The cross-sectional dimensions of the connecting road to the columns are: width 1.8-2.0m, height 2.0-2.2m, and length 5-8m. The cross-sectional dimensions of the connecting road to the ore chambers are: width 1.8-2.0m, height 2.0-2.2m, and length 5-8m.

[0018] S2 Intercolumn Reclamation and Backfilling

[0019] ① Using the section of the inter-pillar ore-exit roadway that penetrates into the inter-pillar to be mined as the free face, boreholes parallel to the dip angle of the ore body are constructed upwards. The depth of the boreholes is 1.8-2.2m and the spacing between the boreholes is 0.6-0.8m. The boreholes are arranged in a fan shape. The boreholes are filled with emulsion explosives and the inter-pillar to be mined is blasted and mined. The non-electric detonating cord detonation network is used for detonation, and micro-delay blasting is adopted with a delay error of ≤25ms, thereby forming the first layer of ore-exit.

[0020] ② After blasting, a remote-controlled electric shovel is used to transport part of the ore stored in the pillar stope to the surface along the pillar ore extraction roadway. When the elevation of the upper part of the ore stored in the pillar stope is lowered to be level with the bottom elevation of the first pillar connecting roadway under the pillar being mined, the shoveling and extraction of ore is stopped. At this time, a pillar stope mining space is formed between the ore stored in the pillar stope and the pillar being mined. This pillar stope mining space serves as the working free face for the next layer of mining blasting, and the ore stored in the pillar stope serves as the working platform for the next layer. At the same time, it also plays a role in supporting the surrounding rock of the upper and lower walls of the pillar stope and maintaining the stability of the stope.

[0021] ③ From the inter-pillar ore extraction roadway → external vein ventilation shaft → inter-pillar connecting roadway → inter-pillar stope mining space, the inter-pillar being mined is mined layer by layer upwards; after each layer of blasting, a forced-in local ventilation fan (power approximately 5.5kW, air volume ≥200m³ / min) is used for extraction ventilation and exhaust to the surface;

[0022] ④ Repeat steps ② to ③ above until the inter-pillar being mined is mined to the level of the top pillar. After the mining is completed, the inter-pillar being mined is filled with ore. A remote-controlled shovel (load capacity ≥ 6t) is used to shovel and transport the ore in the ore extraction roadway at the bottom of the inter-pillar being mined. The shoveled ore is loaded into the mine cars in the intermediate transport roadway through the inter-pillar ore extraction roadway. The ore is then transported to the main shaft or to the surface through the adit by an electric locomotive pulling the mine cars.

[0023] ⑤ After the ore extraction of the pillar mining area is completed, high-density polyethylene pipes are laid from the upper and middle section transport roadway → upper and middle section pillar ore extraction roadway → external ventilation shaft → pillar connecting roadway. When filling the pillar mining area, the filling is carried out in layers from bottom to top. Every time the filling height reaches the pillar connecting roadway, a filling retaining wall is constructed to block the pillar connecting roadway. When filling to the top, pressurized grouting is used to ensure that the roof connection rate is ≥95%, thereby ensuring the quality of the filling and forming a completed pillar mining area.

[0024] S3 stope recovery

[0025] ① After all the inter-pillars to be mined and the inter-pillars currently being mined in the middle section have been mined and backfilled, or when the inter-pillar stope that has been backfilled precedes two or more inter-holes to be mined, the inter-holes to be mined shall be mined. When mining the inter-holes to be mined, the space where the ore exit roadway enters the inter-holes to be mined shall be used as the free face. Cutting roadways shall be constructed along the length of the inter-holes to be mined. The cutting roadway blasting shall adopt wedge-shaped slotting, with the slotting hole inclination angle of 55°~65°, the auxiliary hole spacing ≤0.8m, the peripheral hole spacing ≤0.5m, the peripheral hole charge coefficient ≤0.6, and the reserved light blasting layer thickness ≥200mm. The cut roadway formed shall be used as the blasting mining space for blasting mining. The blasting shall be carried out using emulsion explosives and non-electric detonating cords for initiation. One blasting shall be carried out after each step working face is completed.

[0026] ② After blasting, partial extraction of ore from the stope is carried out. A remote-controlled electric loader is used to load and transport the ore from the stope along the ore extraction roadway. Extraction is stopped when the upper pile of ore in the stope is lowered to a distance of 1.8 to 2.0 meters from the stope being mined in the vertical direction. At this time, a stope mining space with a height of 1.8 to 2.0 meters is formed between the ore in the stope and the stope being mined, so as to facilitate the next cycle of operation. The stope mining space serves as the working free face for the next layer of mining blasting in the stope being mined. The remaining ore in the stope serves as the next drilling platform.

[0027] ③ Before workers enter the mining space, mechanical ventilation is required for the mining block. A local exhaust fan is installed in the mining connection tunnel on the other side of the mining block to bring fresh air into the mining space through the external ventilation shaft and the mining connection tunnel. After washing the working face, the polluted air is discharged to the surface through the mining connection tunnel on the other side of the ore body and the external ventilation shaft into the upper and middle section transport roadway.

[0028] ④ In order to facilitate workers to carry out rock drilling and blasting operations on the ore in the mine storage tunnel, the surface of the remaining ore in the mine storage tunnel should be leveled after partial ore discharge; during leveling, the loosened but not fallen ore and rock on the roof and sides should be pried off to ensure the safety of subsequent operations; large pieces that fall during blasting and roof prying should be broken up during leveling to facilitate ore extraction.

[0029] ⑤ Repeat steps ① to ④ above until the stope being mined reaches the top pillar, at which point all remaining ore in the stope should be released at once; the ore should be transported from the stope exit roadway to the intermediate transport roadway for loading and transport to the surface; after the final mining is completed, the stope should be completely sealed off in a timely manner to prevent personnel from accidentally entering and to facilitate mine ventilation.

[0030] Furthermore, the ore body is mined from top to bottom, divided into several intermediate sections, each 30-60m high. Within each intermediate section, the ore-to-be-mined chambers and inter-mining pillars are arranged along the strike of the ore body. The width of the ore-to-be-mined chambers is consistent with the thickness of the ore body, the length of the ore block is 40-60m, and the height is 30-60m. The length of the top pillar is 40-60m, the height is 4-8m, and its width is consistent with the thickness of the ore body. The width of the inter-mining pillars is 6-10m, the height is 30-60m, and its width is consistent with the thickness of the ore body.

[0031] Furthermore, the ore outlet roadway is located below the ore storage hole in the stope, and the right end of the ore outlet roadway is connected to the middle transport roadway.

[0032] Furthermore, the pillars being mined are connected to the external ventilation and filling shafts located in the footwall of the ore body via pillar connecting passages.

[0033] Furthermore, in step ③ of S2, the fresh airflow is generated by a forced-in local ventilation fan, which travels through pipelines from the middle transport roadway to the inter-pillar ore extraction roadway, then through the external ventilation shaft, the inter-pillar connecting roadway, and the inter-pillar stope recovery space. The polluted air is forced out and then travels from the inter-pillar connecting roadway to the external ventilation shaft, then through the upper and middle inter-pillar ore extraction roadway, then through the upper and middle transport roadway, and finally to the surface.

[0034] Furthermore, the already filled pillar stope, pillar ore extraction roadway, and pillar connecting roadway are sealed off by filling retaining walls.

[0035] Furthermore, in step S3, when the width of the ore-to-be-mined chamber is less than 3m, the width of the cutting roadway is the same as the width of the ore-to-be-mined chamber; when the width of the ore-to-be-mined chamber exceeds 3m, the width of the cutting roadway is 2-3m; the height of the cutting roadway is 2-4m, and the length is the same as the length of the ore-to-be-mined chamber.

[0036] Furthermore, in step S3, when partially extracting ore from the stope, the amount extracted each time is 30% to 35% of the blasting amount, and the remaining ore in the stope is used as the next drilling platform.

[0037] Furthermore, in step S3, ③, workers can only enter the mining space for construction after the concentration of harmful substances in the mined stope has reached the permissible level.

[0038] Furthermore, the upper and middle section transport roadways are spaced 5 to 6 meters apart, and construction is carried out in a vertical or oblique direction of 45 to 60 degrees. Construction stops when the roadway penetrates the upper and middle section of the mined stope to the newly exposed ore body at the contact surface with the hanging wall.

[0039] This invention discloses a novel bottomless shallow-hole stope mining method with pillar recovery. It employs an external riser layout and incorporates connecting passages for pillars and stopes. The pillars are first treated as a small stope for backfilling, and finally the stopes are mined. This method solves the problems of high ore loss and difficulty in pillar recovery in traditional shallow-hole stope mining methods, achieving safe stope recovery. Specifically, it has the following positive effects:

[0040] (1) It significantly improves the recovery rate of mineral resources. Through the effective recovery of interstitial pillars, it reduces the waste of resources and increases the economic benefits of the mine.

[0041] (2) The pillars after mining and backfilling replace the original pillars in maintaining safety and stability. Moreover, the artificial pillars cast by the artificial cast have a more prominent advantage in maintaining the stability of the mining area compared with the ore pillars.

[0042] (3) The innovative technology of first mining the pillars and then mining the chamber in this invention solves the difficult problems of high recovery difficulty and low recovery rate when the pillars are specially recovered in the traditional shallow hole ore retention method.

[0043] (4) The lower plate external well will not be mined out due to the mining of the inter-column. After the mining is completed, it can still play the role of connecting the upper and lower middle sections, ensuring the integrity of the ventilation and other systems between the middle sections of the mine. Attached Figure Description

[0044] Figure 1 is a front view of the preparation engineering layout in a novel bottomless shallow hole ore-holding mining method with inter-pillar recovery.

[0045] Figure 2 is a front view of the intermediate pillar recovery and backfilling of a novel bottomless shallow hole ore-holding mining method with intermediate pillar recovery according to the present invention;

[0046] Figure 3 is a side view of section AA in Figure 2;

[0047] Figure 4 is a side view of the BB section in Figure 2;

[0048] Figure 5 is a top view of the CC section in Figure 2;

[0049] Figure 6 is a front view of the intermediate stope mining in a novel bottomless shallow hole ore-holding mining method with interstitial pillar recovery according to the present invention.

[0050] Figure 7 is a side view of the DD section in Figure 6.

[0051] Figure 8 is a side view of the EE cross section in Figure 6.

[0052] Figure 9 is a top view of the FF cross section in Figure 6.

[0053] The diagram is marked as follows: 1-Upper-middle section filled pillar stope; 2-Upper-middle section transport roadway; 3-Upper-middle section pillar ore extraction roadway; 4-Roof pillar; 5-Pillar connecting roadway; 6-External ventilation shaft; 7-Stop connecting roadway; 8.1-Pillar to be mined; 8.2-Pillar under mining; 8.3-Pillar stope under filling; 8.4-Pillar stope fully filled; 9.1-Stop stope to be mined; 9.2-Stop stope under mining. 9.3 - Completed stope mining; 10 - Inter-pillar ore extraction roadway; 11 - Stope ore extraction roadway; 12 - Blasting hole; 13 - Inter-pillar stope mining space; 14 - Inter-pillar stope ore storage hole; 15 - Backfilling retaining wall; 16 - Footwall of ore body; 17 - Middle section transport roadway; 18 - Contact surface between ore body and footwall; 19 - Stope mining space; 20 - Stope ore storage hole; 21 - Upper and middle section stope ore extraction roadway; 22 - Cutting roadway. Detailed Implementation

[0054] To better describe the present invention, the following detailed description, in conjunction with the accompanying drawings, describes a novel bottomless shallow-hole ore-holding mining method with interstitial pillar recovery.

[0055] As shown in Figure 1, the main view of the preparatory engineering layout in a novel bottomless shallow-hole ore-holding method with inter-pillar recovery demonstrates, the ore body is mined sequentially from top to bottom. After the mining of the previous intermediate section is completed, the next intermediate section's unmined stope 9.1 and unmined inter-pillar 8.1 are mined. Within the intermediate section, the unmined stope 9.1 and unmined inter-pillar 8.1 are arranged at intervals along the strike of the ore body.

[0056] Figure 2 shows a front view of the intermediate pillar mining and backfilling of a novel bottomless shallow-hole ore-holding mining method with intermediate pillar recovery according to the present invention. Combined with Figures 3, 4, and 5, it can be seen that intermediate pillars 8.2 under mining and intermediate pillar stopes 8.3 under backfilling are located on both sides of the ore-to-be-mined stope 9.1. The upper part of the top pillar 4 of the ore-to-be-mined stope 9.3 is the completed stope 9.3. The upper part of the top pillar 4 of the intermediate pillars 8.2 under mining and the intermediate pillar stopes 8.3 under backfilling is the upper-middle section filled intermediate pillar stope 1. The intermediate pillars 8.2 under mining are connected to the external ventilation and backfilling shaft 6 arranged in the footwall 16 of the ore body via an intermediate pillar connecting passage 5. The lower end of the external ventilation and backfilling shaft 6 is connected to the top of the intermediate pillar ore-exit roadway 10 in this middle section, and the top end is connected to the upper-middle section intermediate pillar ore-exit roadway 3. The right end of the upper-middle section intermediate pillar ore-exit roadway 3 is connected to the upper-middle section transport roadway 2. The lower part of the pillar 8.2 being mined is the pillar stope storage ore 14. The lower part of the pillar stope storage ore 14 is the pillar ore extraction roadway 10. The right end of the pillar ore extraction roadway 10 is connected to the middle section transport roadway 17.

[0057] Figure 6, a front view of the stope recovery in a novel bottomless shallow-hole stope mining method with pillar recovery according to the present invention, and in conjunction with Figures 7, 8, and 9, show that the lower part of the stope 9.1 to be mined is the stope storage ore 20, and the two sides are the already filled pillar stopes 8.4. The lower part of the stope storage ore 20 is the stope extraction roadway 11, and the right end of the stope extraction roadway 11 is connected to the intermediate transport roadway 17. The already filled pillar stopes 8.4, the pillar extraction roadway 10, and the pillar connecting roadway 5 are sealed off by a filling retaining wall 15.

[0058] Referring to Figures 1-8, in this embodiment, the present invention discloses a novel bottomless shallow-hole ore-keeping mining method with inter-pillar recovery. The ore body is mined from top to bottom, divided into several intermediate sections, each 30-60m high. Within each intermediate section, the ore-to-be-mined stope 9.1 and the inter-pillar 8.1 are arranged along the strike of the ore body. The width of the ore-to-be-mined stope 9.1 is consistent with the thickness of the ore body, the length of the ore block is 40-60m, and the height is 30-60m. The top pillar 4 is 40-60m long and 4-8m high, with its width consistent with the thickness of the ore body. The inter-pillar 8.1 has a width of 6-10m and a height of 30-60m, with its width consistent with the thickness of the ore body. The specific process steps are as follows:

[0059] 1) In the footwall surrounding rock 16 of the ore body, a mid-section transport roadway 17 is constructed along the strike direction of the ore body. The cross-sectional dimensions of the mid-section transport roadway 17 are: 2.5-4.0m wide and 2.6-3.5m high. The mid-section transport roadway 17 is 5-15m away from the ore body.

[0060] 2) Every 5-6m along the middle transport roadway 17, a ore outlet roadway 11 is excavated perpendicularly or obliquely at 45-60° toward the ore-to-be-mined stope 9.1. The ore outlet roadway 11 extends from the ore-to-be-mined stope 9.1 to the contact surface 18 between the ore body and the hanging wall. The net cross-sectional dimensions of the ore outlet roadway 11 are: width 2.2-3.0m and height 2.4-3.0m.

[0061] 3) A column ore extraction roadway 10 is excavated perpendicularly or obliquely to the column 8.1 to be mined along the middle section transport roadway 17. The column ore extraction roadway 10 extends from the column 8.1 to the contact surface 18 between the ore body and the hanging wall. The net cross-sectional dimensions of the column ore extraction roadway 10 are: width 2.2-3.0m and height 2.4-3.0m.

[0062] 4) Construct an external ventilation shaft 6 upwards from the top of the ore body's footwall 10 within the 5-8m range of the footwall of the unmined pillar 8.1. The external ventilation shaft 6 has the following dimensions: length 1.8-2.0m and width 1.8-2.0m. The slope of the external ventilation shaft 6 is consistent with the dip angle of the ore body, typically 60°-80°. The top of the external ventilation shaft 6 is connected to the corresponding upper-middle section ore body ...

[0063] 5) Construct a vertical connecting road 5 perpendicular to the target column 8.1 every 3-5m along the vertical direction of the external ventilation shaft 6. Construct a stope connecting road 7 on each side of the target column 8.1, connecting the target stopes 9.1 on both sides, until the ore body is just exposed, without penetrating the ore body. The connecting road 5 and the stope connecting road 7 are staggered, with a vertical distance of ≥1.5m between them. The contact surface between the stope connecting road 7 and the target stope 9.1 is at least 2m away from the boundary of the target column 8.1. The cross-sectional dimensions of the connecting road 5 are: width 1.8-2.0m, height 2.0-2.2m, and length 5-8m. The cross-sectional dimensions of the stope connecting road 7 are: width 1.8-2.0m, height 2.0-2.2m, and length 5-8m.

[0064] 6) Using the portion of the inter-pillar ore extraction roadway 10 penetrating into the inter-pillar 8.1 to be mined as the free face, boreholes 12 parallel to the dip angle of the ore body are constructed upwards, with a diameter of 42mm. The boreholes 12 are arranged in a fan shape, with a depth of 1.8-2.2m and a spacing of 0.6-0.8m. The boreholes 12 are filled with emulsion explosive (density 1.1g / cm³), with an explosive consumption of 0.3-0.4kg / t. The detonation is initiated by a non-electric detonating cord network, using micro-delay blasting with a micro-delay interval of 25ms.

[0065] 7) After blasting, a remote-controlled electric shovel is used to transport part of the ore stored in the pillar stope 14 out along the pillar ore extraction roadway 10. When the upper storage elevation of the ore stored in the pillar stope 14 is lowered to be level with the bottom elevation of the first pillar connecting roadway 5 under the pillar 8.2 being mined, the shoveling and extraction of ore is stopped. At this time, a pillar stope mining space 13 is formed between the ore stored in the pillar stope 14 and the pillar 8.2 being mined. The pillar stope mining space 13 serves as the working free face for the next layer mining blast, and the ore stored in the pillar stope 14 serves as the working platform for the next layer.

[0066] 8) The inter-pillar ore extraction roadway 10 → external ventilation shaft 6 → inter-pillar connecting roadway 5 → inter-pillar stope mining space 13 is mined layer by layer upwards to the inter-pillar 8.2 that is being mined; after each layer of blasting, the fresh air flow is through a forced-in local ventilation fan (power 5.5kW, air volume ≥200m³ / min), through the pipeline route of the middle section transport roadway 17 → inter-pillar ore extraction roadway 10 → external ventilation shaft 6 → inter-pillar connecting roadway 5 → inter-pillar stope mining space 13, the generated polluted air is forced out, and then the ventilation sequence is from inter-pillar connecting roadway 5 → external ventilation shaft 6 → upper middle section inter-pillar ore extraction roadway 3 → upper middle section transport roadway 2 → surface.

[0067] 9) Repeat steps 7) to 8) above until the mining of the inter-pillar 8.2 reaches the level of the top pillar 4; after mining is completed, use a remote-controlled loader (load capacity ≥ 6t) to carry out centralized shoveling and ore removal in the inter-pillar ore extraction roadway 10 at the bottom of the mining inter-pillar 8.2.

[0068] 10) After the ore extraction of the inter-pillar stope 8.2, which is currently being mined, Φ150mm high-density polyethylene pipes are laid from the upper-middle section transport roadway 2 → upper-middle section inter-pillar ore extraction roadway 3 → external ventilation shaft 6 → inter-pillar connecting roadway 5. When filling the inter-pillar stope 8.3, which is currently being filled, the filling is carried out in layers from bottom to top, with each layer being 3m high. Before each filling height reaches the inter-pillar connecting roadway 5, a filling retaining wall 15 is constructed. The filling retaining wall 15 is made of C25 quick-setting concrete (with 3% quick-setting agent), with a thickness of 0.5m and an internal Φ8mm steel mesh (spacing 200mm). When filling to the top, pressure grouting is applied to ensure a roof contact rate of ≥95%, forming the completed inter-pillar stope 8.4. The filling material is a mixture of graded tailings (particle size ≤5mm) and ordinary Portland cement (PO42.5), with a cement-sand ratio of 1:8 and a concentration of 70%. The 28-day compressive strength of the filling body is ≥1.5MPa.

[0069] 11) After all the inter-pillars 8.1 to be mined and the inter-pillars 8.2 currently being mined in the middle section have been mined and backfilled, or when the inter-pillar stope 8.4 that has been backfilled is mined before two or more inter-holes 9.1, then the inter-hole 9.1 to be mined shall be mined. When mining the inter-hole 9.1, the space where the ore exit roadway 11 enters the inter-hole 9.1 shall be used as the free face, and a cutting roadway 22 shall be constructed along the length of the inter-hole 9.1. The cutting roadway 22 shall be blasted using wedge-shaped slotting, with the slotting hole inclination angle of 55°~65°, the auxiliary hole spacing ≤0.8m, the peripheral hole spacing ≤0.5m, the peripheral hole charge coefficient ≤0.6, and the reserved light blasting layer thickness ≥200mm. The cutting roadway 22 formed shall be used as the blasting mining space for blasting mining. The blasting shall be carried out using emulsion explosives and non-electric detonating cords. One blast shall be carried out after each step working face is completed. When the width of the ore-to-be-mined chamber 9.1 is less than 3m, the width of the cutting roadway 22 is the same as the width of the ore-to-be-mined chamber 9.1; when the width of the ore-to-be-mined chamber 9.1 exceeds 3m, the width of the cutting roadway 22 is 2 to 3m; the height of the cutting roadway 22 is 2 to 4m, and the length is the same as the length of the ore-to-be-mined chamber 9.1.

[0070] 12) After blasting, partial extraction of ore from the stope 20 is carried out. A remote-controlled electric loader is used to load and transport the ore from the stope 20 along the stope extraction roadway 11. Extraction is stopped when the upper pile elevation of the ore from the stope 20 is lowered to a distance of 1.8–2.0m from the corresponding stope 9.2 being mined in the vertical direction. At this time, a stope mining space 19 with a height of 1.8–2.0m is formed between the ore from the stope 20 and the stope 9.2 being mined. The stope mining space 19 serves as the working free face for the next layer mining blast of the stope 9.2 being mined. The remaining ore from the stope 20 serves as the next drilling platform. When partially extracting ore from the stope 20, the amount extracted each time is 30%–35% (about one-third) of the blasting amount.

[0071] 13) Before workers enter the stope mining space 19 for construction, mechanical ventilation must be provided to the stope 9.2 that is currently being mined. An exhaust-type local ventilation fan should be installed in the stope connecting tunnel 7 on the other side of the stope 9.2 to draw fresh air from the external ventilation shaft 6 through the stope connecting tunnel 7 into the stope mining space 19. After washing the working face, the polluted air will be discharged to the surface through the stope connecting tunnel 7 on the other side of the ore body and the external ventilation shaft 6 into the upper-middle section transport roadway 2. Workers may only enter the stope mining space 19 for construction after the concentration of harmful substances in the stope 9.2 has reached the permissible level.

[0072] 14) In order to facilitate workers to carry out rock drilling and blasting operations on the ore storage 20 in the mine, the surface of the remaining ore storage 20 in the mine should be leveled after partial ore release; during leveling, the loosened but not fallen ore and rock on the roof and both sides should be pried off to ensure the safety of subsequent operations; large pieces that fall during blasting and roof prying should be broken up during leveling to facilitate ore extraction.

[0073] 15) Repeat steps 11) to 14) until the stope 9.2 being mined reaches the top pillar 4, at which point all the remaining stope ore 20 is released at once; the ore is transported from the stope exit roadway 11 to the intermediate transport roadway 17 for loading and transport to the surface; after the final mining is completed, the stope should be completely sealed off in a timely manner to prevent personnel from accidentally entering and to facilitate mine ventilation.

[0074] Furthermore, the layout of the upper-middle section ore extraction roadway 21 is consistent with that of the stope ore extraction roadway 11: the interval between the upper-middle section transport roadways 2 is also 5-6m, and construction is carried out vertically or obliquely at 45-60°, penetrating the ore body just exposed in the already mined stope 9.3 and stopping at the contact surface 18 of the hanging wall. In the vertical projection direction, the upper-middle section ore extraction roadway 21 corresponds one-to-one with the stope ore extraction roadway 11. The net cross-sectional dimensions of the upper-middle section ore extraction roadway 21 are 2.2-3.0m (width) × 2.4-3.0m (height).

[0075] This invention solves the problems of high ore loss (15%–30%) and difficult recovery in traditional shallow-hole ore-holding methods by arranging external ventilation shafts, adding connecting passages between pillars and stopes, and prioritizing the mining and backfilling of pillars as independent stopes before remining stopes. By replacing ore pillars with artificial pillars, this invention increases the resource recovery rate to over 88%. The compressive strength of the artificial pillars after backfilling is superior to that of the original pillars, significantly improving stope stability. This invention is suitable for the efficient mining of medium-thick, steeply dipping ore bodies such as precious metals, rare metals, and fluorite. Specific steps include: construction of intermediate transport roadways and ore-exit roadways; excavation of external ventilation shafts, connecting passages between pillars and stopes; layered blasting mining of pillars; backfilling operations; and stope mining.

[0076] This invention has been successfully applied to a new shallow-hole ore-holding method in a gold mine. Statistics show that using this invention can increase the recovery rate of inter-pillars to over 88%, generating economic benefits of over 18 million yuan per year; moreover, the compressive strength of the filled artificial inter-pillars is superior to that of the original pillars, effectively improving the safety of the stope.

[0077] It should be noted that the terms "upper", "lower", "left", "right", "inner", "outer", "front", "rear", "top / bottom", etc., used in this invention to indicate the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this invention and simplifying the description, and therefore should not be construed as limiting this invention.

[0078] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.

Claims

1. A novel shallow-hole ore-keeping mining method with pillar recovery, wherein the ore-to-be-mined stope (9.1) and the pillars to be mined (8.1) in the middle section are arranged at intervals along the strike of the ore body; on both sides of the ore-to-be-mined stope (9.1), there are pillars (8.2) being mined and pillar stopes (8.3) being filled; the upper part of the top pillar (4) of the ore-to-be-mined stope (9.1) is the upper-middle section ore-to-be-mined stope (9.3); the lower part of the pillars (8.2) being mined is the pillar stope storage ore (14); the upper part of the top pillar (4) of the pillars (8.2) being mined and the pillar stopes (8.3) being filled is the upper-middle section filled pillar stope (1); the lower part of the ore-to-be-mined stope (9.1) is the ore-to-be-mined stope storage ore (20), and the two sides are the pillar stopes (8.4) that have been filled; characterized in that The following steps are to be taken: S1 preparation engineering layout ① In the footwall of the ore body (16), a mid-section transport roadway (17) is constructed along the strike direction of the ore body. The cross-sectional dimensions of the mid-section transport roadway (17) are: 2.5-4.0m wide and 2.6-3.5m high. The mid-section transport roadway (17) is 5-15m away from the ore body. ② Along the middle section transport roadway (17), at every 5-6m intervals, a ore outlet roadway (11) is excavated perpendicularly or obliquely at 45-60° toward the ore-to-be-mined block (9.1). The ore outlet roadway (11) extends through the ore-to-be-mined block (9.1) to the contact surface (18) between the ore body and the hanging wall. The net cross-sectional dimensions of the ore outlet roadway (11) are: width 2.2-3.0m and height 2.4-3.0m. ③ A column ore extraction roadway (10) is excavated perpendicularly or obliquely to the column to be mined (8.1) along the middle section transport roadway (17). The column ore extraction roadway (10) extends through the column to be mined (8.1) to the contact surface (18) between the ore body and the hanging wall. The net cross-sectional dimensions of the column ore extraction roadway (10) are: width 2.2-3.0m and height 2.4-3.0m. ④ In the footwall of the ore body within 5-8m of the footwall of the column to be mined (8.1), construct an external ventilation shaft (6) upwards from the top of the column ore extraction roadway (10). The dimensions of the external ventilation shaft (6) are: 1.8-2.0m long and 1.8-2.0m wide. The slope of the external ventilation shaft (6) is consistent with the dip angle of the ore body. The top of the external ventilation filling shaft (6) is connected to the corresponding upper and middle section column ore extraction roadway (3). The bottom of the external ventilation filling shaft (6) is connected to the top of the middle section column ore extraction roadway (10). The right end of the upper and middle section column ore extraction roadway (3) is connected to the upper and middle section transport roadway (2). ⑤ Construct a column connecting road (5) perpendicular to the column to be mined (8.1) every 3-5m in the vertical direction of the external ventilation shaft (6), and construct a ore chamber connecting road (7) on both sides of the external ventilation shaft (6) to connect the ore chambers (9.1) to be mined on both sides of the column to be mined (8.1) until the ore body is just exposed, without penetrating the ore body; the column connecting road (5) and the ore chamber connecting road (7) are arranged alternately, and the vertical distance between them is ≥1.5m; the cross-sectional dimensions of the column connecting road (5) are: width 1.8-2.0m, height 2.0-2.2m, length 5-8m; the cross-sectional dimensions of the ore chamber connecting road (7) are: width 1.8-2.0m, height 2.0-2.2m, length 5-8m; S2 Intercolumn Reclamation and Backfilling ① Using the section of the inter-column ore extraction roadway (10) that penetrates into the inter-column to be mined (8.1) as a free face, blast holes (12) parallel to the dip angle of the ore body are constructed upwards; the blast holes (12) are arranged in a fan shape, with a hole depth of 1.8 to 2.2 m and a hole spacing of 0.6 to 0.8 m. The blast holes (12) are filled with emulsion explosives, and the detonation is initiated by a non-electric detonating cord initiation network. Micro-delay blasting is adopted, and the delay error is ≤25 ms; ②After blasting, a remote-controlled electric shovel is used to transport part of the ore stored in the inter-pillar stope (14) out along the inter-pillar ore extraction roadway (10). When the upper storage elevation of the ore stored in the inter-pillar stope (14) is lowered to be level with the bottom elevation of the first inter-pillar connecting roadway (5) under the inter-pillar (8.2) being mined, the shoveling and ore extraction is stopped. At this time, an inter-pillar stope mining space (13) is formed between the ore stored in the inter-pillar stope (14) and the inter-pillar (8.2) being mined. The inter-pillar stope mining space (13) serves as the working free face for the next layer mining blast, and the ore stored in the inter-pillar stope (14) serves as the working platform for the next layer. ③ From the inter-pillar ore extraction roadway (10) → external ventilation shaft (6) → inter-pillar connecting roadway (5) → inter-pillar stope mining space (13), the inter-pillar (8.2) being mined is mined layer by layer upwards; after each layer of blasting, the forced-in local ventilation fan is used for extraction ventilation and discharge to the surface; ④ Repeat steps ② to ③ above until the inter-column (8.2) being mined reaches the level of the top column (4); after the mining is completed, use a remote-controlled shovel to carry out centralized shoveling and ore removal in the inter-column ore removal roadway (10) at the bottom of the inter-column (8.2) being mined. ⑤ After the ore is extracted from the inter-pillar (8.2) which is being mined, high-density polyethylene pipes are laid from the upper and middle section transport roadway (2) → upper and middle section inter-pillar ore extraction roadway (3) → external ventilation shaft (6) → inter-pillar connecting roadway (5). When filling the inter-pillar stope (8.3) which is being filled, layered filling is carried out from bottom to top. Before each filling height reaches the inter-pillar connecting roadway (5), a filling retaining wall (15) is constructed. When filling to the top, pressure grouting is applied to ensure that the roof contact rate is ≥95%, forming the inter-pillar stope (8.4) that has been filled. S3 stope recovery ① After the backfilling of all the inter-pillars (8.1) to be mined and the inter-pillars (8.2) currently being mined in the middle section is completed, or when the inter-pillar stope (8.4) that has been filled is mined before two or more inter-holes to be mined (9.1), then the inter-holes to be mined (9.1) shall be mined; when mining the inter-holes to be mined (9.1), the part of the space from the ore outlet roadway (11) into the inter-holes to be mined (9.1) shall be used as the free surface, and the cutting shall be carried out along the length of the inter-holes to be mined (9.1). Cut the roadway (22). The blasting of the roadway (22) adopts wedge-shaped slotting. The slotting hole inclination angle is 55°~65°, the auxiliary hole spacing is ≤0.8m, the peripheral hole spacing is ≤0.5m, the peripheral hole charge coefficient is ≤0.6, and the reserved light blasting layer thickness is ≥200mm. The cut roadway (22) formed is used as the blasting and mining space for blasting and mining. The blasting adopts emulsion explosives and non-electric detonating tubes for initiation. One blasting is carried out after each step working face is completed. ② After the blasting is completed, the ore stored in the stope (20) is partially extracted; a remote-controlled electric shovel is used to load and transport the ore stored in the stope (20) along the stope extraction roadway (11). When the upper storage elevation of the ore stored in the stope (20) is lowered to a distance of 1.8 to 2.0m from the stope (9.2) being mined in the corresponding vertical direction, the shoveling and extraction of ore is stopped; at this time, a stope mining space (19) with a height of 1.8 to 2.0m is formed between the ore stored in the stope (20) and the stope being mined (9.2). The stope mining space (19) serves as the working free face for the next layer mining blast of the stope (9.2) being mined; the remaining ore stored in the stope (20) serves as the next drilling platform; ③ Before workers enter the mining space (19) for construction, mechanical ventilation is required for the mining room (9.2) that is being mined. A local exhaust fan is installed in the mining room connecting tunnel (7) on the other side of the mining room (9.2) to bring fresh air from the external ventilation shaft (6) through the mining room connecting tunnel (7) into the mining space (19). After washing the working face, the polluted air is discharged to the surface from the mining room connecting tunnel (7) on the other side of the ore body and the external ventilation shaft (6) into the upper and middle section transport roadway (2). ④ In order to facilitate workers to carry out rock drilling and blasting operations on the ore (20) in the mine, the surface of the remaining ore (20) in the mine should be leveled after partial ore discharge; when leveling the site, the loosened but not fallen ore and rock on the roof and sides should be pried off to ensure the safety of subsequent operations; large pieces that fall during blasting and roof prying should be broken up during leveling to facilitate ore extraction; ⑤ Repeat steps ② to ③ until the mined stope (9.2) is mined to the top pillar (4), at which point all the remaining ore in the stope (20) is released at once; the ore is transported from the stope exit roadway (11) to the middle transport roadway (17) for loading and transport to the surface; after the final mining is completed, the stope should be completely closed in a timely manner.

2. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: The ore outlet roadway (11) is located below the ore storage hole (20) in the ore storage hole, and the right end of the ore outlet roadway (11) is connected to the middle section transport roadway (17).

3. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: The inter-pillar (8.2) being mined is connected to the external ventilation and filling well (6) located in the footwall (16) of the ore body via the inter-pillar connecting passage (5).

4. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: In step ③ of S2, the fresh airflow is generated by a forced local ventilation fan and is routed through the middle section transport roadway (17) → inter-pillar ore extraction roadway (10) → external ventilation shaft (6) → inter-pillar connecting roadway (5) → inter-pillar stope recovery space (13). The polluted air is forced out and then flows from the inter-pillar connecting roadway (5) → external ventilation shaft (6) → upper middle section inter-pillar ore extraction roadway (3) → upper middle section transport roadway (2) → surface.

5. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: The filled inter-pillar stop (8.4), the inter-pillar ore extraction roadway (10), and the inter-pillar connecting roadway (5) are sealed by a filling retaining wall (15).

6. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: In step S3, when the width of the ore chamber (9.1) is less than 3m, the width of the cutting tunnel (22) is the same as the width of the ore chamber (9.1); when the width of the ore chamber (9.1) exceeds 3m, the width of the cutting tunnel (22) is 2 to 3m; the height of the cutting tunnel (22) is 2 to 4m, and the length is the same as the length of the ore chamber (9.1).

7. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: In step S3, when the ore in the storage chamber (20) is partially extracted, the amount extracted each time is 30% to 35% of the blasting amount, and the remaining ore in the storage chamber (20) is used as the next drilling platform.

8. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 1, characterized in that: In step ③ of S3, workers may enter the mining space (19) for construction only after the concentration of harmful substances in the mining stope (9.2) reaches the permissible value.

9. A novel short-hole shrinkage mining method with inter-rib recovery as claimed in claim 1, 2, 3, 4, 5, 6 or 7, characterised by: The upper and middle section transport roadways (2) are spaced 5 to 6 meters apart. Construction is carried out in a vertical or oblique direction of 45 to 60 degrees. Construction stops when the upper and middle section of the mined stope (9.3) is penetrated to the newly exposed ore body at the contact surface (18) of the hanging wall.

10. A novel bench shrinkage method with inter-pillar recovery as claimed in claim 8, characterized in that: The ore body is mined from top to bottom and divided into several intermediate sections. The height of each intermediate section is 30-60m. In each intermediate section, the mining chamber (9.1) and the inter-mining pillar (8.1) are arranged along the strike of the ore body. The width of the mining chamber (9.1) is consistent with the thickness of the ore body, the length of the ore block is 40-60m, and the height is 30-60m. The length of the top pillar (4) is 40-60m, the height is 4-8m, and its width is consistent with the thickness of the ore body. The width of the inter-mining pillar (8.1) is 6-10m, the height is 30-60m, and its width is consistent with the thickness of the ore body.

11. A new type of sublevel shrinkage mining method with inter- pillar recovery as claimed in claim 2, characterized in that: The ore body is mined from top to bottom, divided into several intermediate sections, each 30-60m high. Within each section, the ore-to-be-mined stopes (9.1) and the ore-to-be-mined pillars (8.1) are arranged along the strike of the ore body. The width of the ore-to-be-mined stopes (9.1) is the same as the thickness of the ore body, the length of the ore block is 40-60m, and the height is 30-60m. The length of the top pillar (4) is 40-60m, the height is 4-8m, and its width is the same as the thickness of the ore body. The width of the ore-to-be-mined pillars (8.1) is 6-10m, the height is 30-60m, and its width is the same as the thickness of the ore body. The ore-to-be-mined pillars (8.1) are 6-10m wide and 30-60m high, and their width is the same as the thickness of the ore body. The ore-to-be-mined pillars (8.1) are... The pillar (8.2) is connected to the external ventilation and filling shaft (6) arranged in the footwall (16) of the ore body via the pillar connecting passage (5). The filled pillar stope (8.4) is sealed with the pillar ore extraction roadway (10) and the pillar connecting passage (5) via the filling retaining wall (15). In step ③ of S2, the fresh air flow is generated by a forced-in local ventilation fan through a pipeline route from the middle transport roadway (17) → pillar ore extraction roadway (10) → external ventilation shaft (6) → pillar connecting passage (5) → pillar stope recovery space (13). The polluted air is forced out and then flows from the inter-column connecting roadway (5) → external ventilation shaft (6) → upper and middle section inter-column ore extraction roadway (3) → upper and middle section transport roadway (2) → surface; In step 3.1), when the width of the ore-to-be-mined chamber (9.1) is less than 3m, the width of the cutting roadway (22) is the width of the ore-to-be-mined chamber (9.1); when the width of the ore-to-be-mined chamber (9.1) exceeds 3m, the width of the cutting roadway (22) is 2 to 3m; the height of the cutting roadway (22) is 2 to 4m, and the length is the length of the ore-to-be-mined chamber (9.1); In step S3, step ②, the ore stored in the ore-to-be-mined chamber (2 0) When mining locally, the amount of ore mined each time is 30% to 35% of the blasting amount. The remaining ore in the stope (20) is used as the next drilling platform. In step ③ of S3, workers can enter the stope mining space (19) for construction only after the concentration of harmful substances in the stope (9.2) being mined reaches the allowable value. The upper and middle section transport roadways (2) are spaced 5 to 6 meters apart and are constructed in a vertical or oblique 45 to 60° direction. Construction stops when the upper and middle section stope (9.3) is mined through to the newly exposed ore body at the contact surface (18) of the hanging wall.