A method and system for safe construction and safety monitoring of railway underpasses

By using safety monitoring models and three-dimensional models to mark abnormal points in underpass railway projects, the problem of monitoring relying on professional abilities is solved, construction safety and monitoring accuracy are improved, and visual display and timely display of railway construction conditions are achieved. Alert.

CN118378104BActive Publication Date: 2024-10-29CHINA RAILWAY GUIZHOU ENG CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410837788.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-10-29
Estimated Expiration
2044-06-26

AI Technical Summary

Technical Problem

The existing monitoring methods for underpass railway projects rely on the professional abilities of monitoring personnel and are prone to missed detections and false alarms, resulting in extended construction cycles and poor error reporting accuracy.

Method used

A safety construction and safety monitoring method for underpassing railways is adopted to collect data through monitoring equipment and substitute it into the safety monitoring model for pre-processing, build a three-dimensional model, mark abnormal points, and automatically send out alarm signals based on the model training results, reducing the impact on professional capabilities. dependence.

Benefits of technology

It improves the accuracy and comprehensiveness of monitoring data, enables visual display of railway construction conditions, detects and solves abnormal problems in a timely manner, prevents safety accidents, and improves construction safety and monitoring accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118378104B_ABST
    Figure CN118378104B_ABST
Patent Text Reader

Abstract

The present invention specifically provides a method and system for safe construction and safety monitoring of underpasses. To this end, the method of the present invention includes collecting monitoring data in response to a monitoring instruction corresponding to at least one monitoring device; substituting the monitoring data into a safety monitoring model so that the monitoring data is preprocessed, selectively recollecting the monitoring data of the monitoring device, and constructing a three-dimensional model of railway construction based on the preprocessed monitoring data, and selectively marking abnormal points on the three-dimensional model, wherein the abnormal points include current abnormal points and predicted abnormal points; if there are abnormal points on the three-dimensional model, then based on the abnormal points, an alarm signal corresponding to the abnormal points is issued to the management personnel corresponding to the abnormal points. The accuracy and completeness of the monitoring data are ensured, and a visual display of the railway construction situation is realized, so that the management personnel can promptly learn and solve the abnormal problem according to the location and situation of the abnormal points.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of safe construction and safety monitoring for underpass railways, and specifically provides a method and system for safe construction and safety monitoring for underpass railways. Background Art

[0002] "Underpassing railway projects" usually involve building underground passages or tunnels where roads and railways intersect, so that roads pass under railways to achieve smooth and safe traffic. The design and construction of underpass projects need to consider a variety of factors, such as geological conditions, railway operation safety, and construction difficulty.

[0003] However, in the prior art, the monitoring method for underpass railway projects is generally that monitoring personnel install collection equipment at multiple points based on their own experience, and then compare the data information collected by the collection equipment with the preset data information to determine whether there is any abnormality in the underpass railway project. This monitoring method relies heavily on the professional ability of the monitoring personnel, and is prone to partial missed detection and false alarms, which in turn leads to the extension of the construction period and poor error reporting accuracy.

[0004] Accordingly, the art needs a new solution for safe construction and safety monitoring of underpasses to solve the above problems. Summary of the invention

[0005] In order to overcome the above-mentioned defects, the present invention is proposed to provide a solution or at least partially solve the technical problem that the monitoring method in the prior art is highly dependent on the professional ability of the monitoring personnel, which is very prone to partial missed detection and false alarms, thereby leading to extended construction period and poor error reporting accuracy.

[0006] In a first aspect, the present invention provides a method for safety construction and safety monitoring of underpass railway, the method comprising the following steps:

[0007] In response to a monitoring instruction corresponding to at least one monitoring device, collecting monitoring data;

[0008] Substituting the monitoring data into the safety monitoring model so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring device, and constructing a three-dimensional model of railway construction based on the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model, wherein the abnormal points include current abnormal points and predicted abnormal points;

[0009] If there are abnormal points on the three-dimensional model, based on the abnormal points, an alarm signal corresponding to the abnormal points is sent to the management personnel corresponding to the abnormal points.

[0010] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railway, before collecting monitoring data in response to a monitoring instruction corresponding to at least one monitoring device, the method further includes:

[0011] Acquire construction data of railway construction and at least one designated installation location matching the construction data, wherein the construction data includes geologically different construction areas, setting parameters corresponding to the construction areas, and the type of construction to be performed;

[0012] Acquire equipment data of the monitoring equipment, wherein the equipment data includes monitoring type, equipment model, effective monitoring range and equipment parameters;

[0013] The equipment data of the monitoring equipment, the construction data of the railway construction and at least one designated installation location matching the construction data are substituted into the safety monitoring model to obtain a monitoring plan corresponding to the railway construction, wherein the monitoring plan includes a monitoring equipment deployment plan and a monitoring execution plan corresponding to each monitoring equipment.

[0014] In a technical solution of the above-mentioned railway underpass safety construction and safety monitoring method, before substituting the equipment data of the monitoring equipment, the construction data of the railway construction, and at least one designated installation location matching the construction data into the safety monitoring model, the method further includes performing solution training on the safety monitoring model through the following steps:

[0015] Acquire multiple sets of training solution sample sets with different marking conditions, wherein each set of training solution sample sets includes a set of equipment data, a set of construction data, and at least one designated installation location matching the construction data;

[0016] Based on each set of training solution sample sets, multiple sets of monitoring solutions are obtained;

[0017] Simulate each group of monitoring plans corresponding to each group of training plan sample sets to obtain the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan;

[0018] Based on the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan, a group of monitoring plans is selected as a group of monitoring plans corresponding to the training plan sample set;

[0019] Based on the marking conditions of each group of training solution sample sets and the monitoring solutions corresponding to each group of training solution sample sets, the training results of the solution training of the safety monitoring model are obtained.

[0020] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railway, a preset historical data solution library is stored in the safety monitoring model, and the historical data solution library stores multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data matching the construction data. Acquiring multiple sets of training solution sample sets with different marking conditions includes:

[0021] Based on a preset historical data solution library, randomly select multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data that matches the construction data;

[0022] The construction data corresponding to each selected historical monitoring scheme, at least one designated installation location matching the construction data, and equipment data are used as one set of training scheme sample sets, and the training scheme sample sets are marked;

[0023] The selected construction data, at least one designated installation location matching the construction data, and the equipment data are randomly combined to obtain multiple sets of training solution sample sets.

[0024] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railways, the simulation of each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain the execution results of the monitoring equipment deployment scheme in each group of monitoring schemes and the execution results of the monitoring execution schemes include:

[0025] Simulating each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain simulation data of each group of monitoring schemes in each group of training scheme sample sets;

[0026] Based on the simulation data of the monitoring equipment deployment scheme in the simulation data of each group of monitoring schemes, the execution result of the monitoring equipment deployment scheme in each group of monitoring schemes is obtained, wherein the execution result of the monitoring equipment deployment scheme includes execution success or execution failure, and an execution score matching the execution success;

[0027] Based on the simulation data of the monitoring execution scheme in the simulation data of each group of monitoring schemes, the execution results of the monitoring execution scheme in each group of monitoring schemes are obtained, wherein the execution results of the monitoring execution scheme include execution success or execution failure, and an execution score matching the execution success.

[0028] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railways, the training results of the scheme training of the safety monitoring model obtained based on the marking conditions of each group of training scheme sample sets and the monitoring schemes corresponding to each group of training scheme sample sets include:

[0029] Obtain monitoring plans corresponding to all labeled training plan sample sets;

[0030] Based on the preset historical data solution library and all the marked training solution sample sets, obtain the historical monitoring solution corresponding to each marked training solution sample set;

[0031] If the monitoring scheme corresponding to the marked training scheme sample set is completely consistent with the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful;

[0032] Otherwise, obtaining the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set;

[0033] If the comprehensive execution score of the monitoring scheme corresponding to the marked training scheme sample set is higher than the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful; otherwise, then the result of the scheme training of the marked training scheme sample set is judged to be a failure;

[0034] Determine the training success rate of the solution training for all the labeled training solution sample sets based on the solution training results for each labeled training solution sample set;

[0035] Based on the training success rate of the solution training for all labeled training solution sample sets, the training result of the solution training of the safety monitoring model is obtained.

[0036] In a technical solution of the above-mentioned underpass railway safety construction and safety monitoring method, a preset historical database is stored in the safety monitoring model, and the historical database stores multiple groups of historical monitoring data of each monitoring device, the monitoring data range value corresponding to each monitoring device, and the monitoring data type corresponding to each monitoring device. Substituting the monitoring data into the safety monitoring model so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring device, and construct a three-dimensional model of railway construction based on the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model includes:

[0037] Preprocessing the monitoring data, and selectively recollecting the monitoring data of the monitoring device;

[0038] Construct a 3D model of railway construction based on pre-processed monitoring data;

[0039] Based on the monitoring data, abnormal points are selectively marked on the three-dimensional model.

[0040] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railway, the preprocessing of the monitoring data and the selective recollection of the monitoring data of the monitoring equipment include:

[0041] Based on the monitoring data, determining at least one monitoring device corresponding to the monitoring data;

[0042] Based on at least one monitoring device corresponding to the monitoring data and a preset historical database, determining whether it is necessary to re-collect the monitoring data of the monitoring device:

[0043] If the judgment is yes, the monitoring data of the monitoring device is collected again, and based on the recollected monitoring data and the preset historical database, the step of “determining whether it is necessary to recollect the monitoring data of the monitoring device” is re-executed;

[0044] If the judgment is no, the monitoring data is preprocessed to obtain preprocessed monitoring data.

[0045] In a technical solution of the above-mentioned method for safe construction and safety monitoring of underpass railway, selectively marking abnormal points on the three-dimensional model based on the monitoring data includes:

[0046] Based on the monitoring data, determine all current abnormal data in the monitoring data, and determine location information of each current abnormal data;

[0047] Performing an estimate based on the monitoring data to obtain estimated data;

[0048] Based on the estimated data, determining all estimated abnormal data in the estimated data, and determining location information of each estimated abnormal data;

[0049] If there is at least one current abnormal data in the monitoring data, based on all the current abnormal data in the monitoring data and the position information of each current abnormal data, marking the current abnormal point at a position matching each position information on the three-dimensional model of the railway construction;

[0050] If there is at least one estimated abnormal data in the estimated data, based on all the estimated abnormal data in the estimated data and the position information of each estimated abnormal data, marking the estimated abnormal point at the position matching each position information on the three-dimensional model of the railway construction;

[0051] If the monitoring data does not contain current abnormal data and the estimated data does not contain estimated abnormal data, marking on the three-dimensional model is not performed.

[0052] In a second aspect, the present invention provides a system for safe construction and safety monitoring of underpass railways, wherein the system exchanges information with terminal devices corresponding to management personnel corresponding to various construction data, the system comprises a plurality of monitoring devices, preset construction information, a safety monitoring model and a control device, the monitoring device being used to collect monitoring data of railway construction, the preset construction information comprising construction data of railway construction and at least one designated installation location matching the construction data, and the construction data comprising geologically different construction areas, setting parameters corresponding to the construction areas and types of construction to be executed, the safety monitoring model storing a preset historical database and a preset historical data solution library, the control device comprising a processor and a memory, the memory being suitable for storing a plurality of program codes, the program codes being suitable for being loaded and run by the processor to execute the method for safe construction and safety monitoring of underpass railways described in any one of the technical solutions of the above-mentioned technical solutions for the method for safe construction and safety monitoring of underpass railways.

[0053] The above one or more technical solutions of the present invention have at least one or more of the following beneficial effects:

[0054] By responding to the monitoring instruction, the monitoring data is collected by the monitoring equipment corresponding to the monitoring instruction, so as to realize the periodic collection of the monitoring data, and then the monitoring data is substituted into the safety monitoring model, and then the monitoring data is preprocessed, and the monitoring data is selectively recollected, so as to ensure the accuracy and completeness of the monitoring data, and then the three-dimensional model of the railway construction is constructed according to the preprocessed monitoring data, and the abnormal points are selectively marked on the three-dimensional model, so as to realize the visual display of the railway construction situation, so that the management personnel can timely know and solve the abnormal problem according to the location and situation of the abnormal point, and when there is an abnormal point on the three-dimensional model, according to the abnormal point, the alarm signal corresponding to the abnormal point is sent to the management personnel corresponding to the abnormal point, so that the management personnel can timely understand the abnormal situation and take corresponding measures, so as to prevent the occurrence of safety accidents, improve the accuracy and comprehensiveness of the safety monitoring of the railway construction, and ensure the safe operation of the railway construction, and avoid the monitoring method in the prior art that greatly relies on the professional ability of the monitoring personnel, and is prone to partial missed detection and false alarm, thereby leading to the extension of the construction period and the technical problem of poor accuracy of error reporting.

[0055] In the technical solution for implementing the present invention, in model training, multiple groups of monitoring schemes corresponding to each group of training scheme sample sets are obtained according to multiple groups of training scheme sample sets with different marking conditions, and then each group of monitoring schemes is simulated to obtain the execution results of each group of monitoring schemes, and one group of monitoring schemes is selected as the monitoring schemes corresponding to the training scheme sample set, thereby realizing the screening of monitoring schemes to ensure that the monitoring schemes match the training scheme sample set, and then combining the marking conditions of the training scheme sample set to further determine the training results of the scheme training of the security monitoring model, thereby realizing the training of the model according to multiple groups of training scheme sample sets, and selectively retraining according to the training results, thereby ensuring the intelligent capability of the security monitoring model.

[0056] In the technical solution of the present invention, the corresponding monitoring equipment is determined through monitoring data, and then combined with the preset historical database, it is judged whether the monitoring data needs to be re-collected, so as to realize the judgment of whether the monitoring data meets the requirements and improve the accuracy and comprehensiveness of the monitoring data. When re-collection is not necessary, the monitoring data is pre-processed to realize the cleaning and data conversion of the monitoring data, so that the processed monitoring data matches the safety monitoring model, ensuring the quality and consistency of the data, thereby improving the data processing and analysis efficiency of the safety monitoring model, and constructing a three-dimensional model of railway construction based on the pre-processed monitoring data to realize the visual display of railway construction, and selectively marking abnormal points on the three-dimensional model based on the monitoring data, realizing the marking of current abnormal points and estimated abnormal points, so as to facilitate the management personnel to view and handle the abnormal situation, so that the management personnel can timely discover potential safety risks and improve the safety of railway construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] The disclosure of the present invention will become more easily understood with reference to the accompanying drawings. It is easy for those skilled in the art to understand that these drawings are only for illustrative purposes and are not intended to limit the scope of protection of the present invention. In addition, similar numbers in the figures are used to represent similar components, among which:

[0058] Figure 1 It is a schematic flow chart of the main steps of a method for safe construction and safety monitoring of underpass railway according to an embodiment of the present invention;

[0059] Figure 2 It is a schematic diagram of the main structural block diagram of a railway underpass safety construction and safety monitoring system according to an embodiment of the present invention.

[0060] List of reference numerals:

[0061] 200: Underpass railway safety construction and safety monitoring system; 201: Control device; 2011: Processor; 2012: Memory; 2013: Program code; 202: Safety monitoring model; 2021: Historical database; 2022: Historical data solution library; 203: Monitoring equipment; 204: Construction information; 205: Communication device. DETAILED DESCRIPTION

[0062] Some embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.

[0063] In the description of the present invention, "module" and "processor" may include hardware, software or a combination of the two. A module may include hardware circuits, various suitable sensors, communication ports, and memories, and may also include software parts, such as program codes, or a combination of software and hardware. The processor may be a central processing unit, a microprocessor, an image processor, a digital signal processor, or any other suitable processor. The processor has data and / or signal processing functions. The processor may be implemented in software, hardware, or a combination of the two. Non-temporary computer-readable storage media include any suitable medium that can store program codes, such as a magnetic disk, a hard disk, an optical disk, a flash memory, a read-only memory, a random access memory, and the like. The term "A and / or B" means all possible combinations of A and B, such as only A, only B, or A and B. The term "at least one A or B" or "at least one of A and B" has a similar meaning to "A and / or B", and may include only A, only B, or A and B. The singular terms "one" and "the" may also include plural forms.

[0064] See attached Figure 1 , Figure 1 1 is a schematic flow chart of the main steps of a method for safe construction and safety monitoring of a railway underpass according to an embodiment of the present invention. Figure 1 As shown, the method for safe construction and safety monitoring of underpass railway in the embodiment of the present invention is applied to the safe construction and safety monitoring system of underpass railway, and the method mainly includes the following steps S101 to S103.

[0065] Step S101: collecting monitoring data in response to a monitoring instruction corresponding to at least one monitoring device;

[0066] Furthermore, in some embodiments, before collecting monitoring data in response to a monitoring instruction corresponding to at least one monitoring device, the method further includes:

[0067] Acquire construction data of railway construction and at least one designated installation location matching the construction data, wherein the construction data includes geologically different construction areas, setting parameters corresponding to the construction areas, and the type of construction to be performed;

[0068] Acquire equipment data of the monitoring equipment, wherein the equipment data includes monitoring type, equipment model, effective monitoring range and equipment parameters;

[0069] The equipment data of the monitoring equipment, the construction data of the railway construction and at least one designated installation location matching the construction data are substituted into the safety monitoring model to obtain a monitoring plan corresponding to the railway construction, wherein the monitoring plan includes a monitoring equipment deployment plan and a monitoring execution plan corresponding to each monitoring equipment.

[0070] Specifically, in some embodiments, the monitoring equipment deployment plan includes at least a plurality of monitoring devices, a deployment position and a deployment angle corresponding to each monitoring device; the monitoring execution plan includes at least a monitoring period of the monitoring device, a monitoring data type and a duration of the monitoring data.

[0071] Specifically, in some embodiments, if a monitoring time point of a monitoring cycle in a monitoring plan of any monitoring device is reached, a monitoring instruction is issued to the monitoring device.

[0072] In the above embodiment, by acquiring construction data and at least one designated installation location matching it, as well as the equipment data of the monitoring equipment, into the safety monitoring model, a monitoring plan corresponding to the railway construction is obtained, and the monitoring equipment deployment plan matching the railway construction and the monitoring execution plan of each monitoring equipment are obtained, so as to facilitate comprehensive monitoring of the construction site, timely discover and warn of potential risk factors, thereby improving the safety of the construction process.

[0073] Step S102: Substituting the monitoring data into the safety monitoring model, so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring equipment, and constructing a three-dimensional model of railway construction according to the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model, wherein the abnormal points include current abnormal points and predicted abnormal points;

[0074] Furthermore, in some embodiments, before substituting the equipment data of the monitoring equipment, the construction data of the railway construction, and at least one designated installation location matching the construction data into the safety monitoring model, the method further includes performing solution training on the safety monitoring model by the following steps:

[0075] Acquire multiple sets of training solution sample sets with different marking conditions, wherein each set of training solution sample sets includes a set of equipment data, a set of construction data, and at least one designated installation location matching the construction data;

[0076] Based on each set of training solution sample sets, multiple sets of monitoring solutions are obtained;

[0077] Simulate each group of monitoring plans corresponding to each group of training plan sample sets to obtain the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan;

[0078] Based on the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan, a group of monitoring plans is selected as a group of monitoring plans corresponding to the training plan sample set;

[0079] Based on the marking conditions of each group of training solution sample sets and the monitoring solutions corresponding to each group of training solution sample sets, the training results of the solution training of the safety monitoring model are obtained.

[0080] Specifically, in some embodiments, the safety monitoring model stores a preset historical data solution library, wherein the historical data solution library stores multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data matching the construction data, and obtaining multiple sets of training solution sample sets with different marking conditions includes:

[0081] Based on a preset historical data solution library, randomly select multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data that matches the construction data;

[0082] The construction data corresponding to each selected historical monitoring scheme, at least one designated installation location matching the construction data, and equipment data are used as one set of training scheme sample sets, and the training scheme sample sets are marked;

[0083] The selected construction data, at least one designated installation location matching the construction data, and equipment data are randomly combined to obtain multiple sets of training solution sample sets, and the training solution sample sets are not marked.

[0084] Specifically, in some embodiments, the method for generating multiple groups of monitoring schemes based on each group of training scheme sample sets can adopt a machine learning model or a trained neural network model in the prior art. The selection of the method for generating multiple groups of monitoring schemes here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs, as long as multiple groups of monitoring schemes corresponding to each training scheme sample set can be generated based on each group of training scheme sample sets, and no further details will be given here.

[0085] Specifically, in some embodiments, simulating each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain the execution results of the monitoring equipment deployment scheme in each group of monitoring schemes and the execution results of the monitoring execution schemes includes:

[0086] Simulate each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain simulation data of each group of monitoring schemes in each group of training scheme sample sets;

[0087] Based on the simulation data of the monitoring equipment deployment scheme in the simulation data of each group of monitoring schemes, the execution result of the monitoring equipment deployment scheme in each group of monitoring schemes is obtained, wherein the execution result of the monitoring equipment deployment scheme includes execution success or execution failure, and an execution score matching the execution success;

[0088] Based on the simulation data of the monitoring execution scheme in the simulation data of each group of monitoring schemes, the execution results of the monitoring execution scheme in each group of monitoring schemes are obtained, wherein the execution results of the monitoring execution scheme include execution success or execution failure, and an execution score matching the execution success.

[0089] Specifically, in some embodiments, the simulation method for simulating each group of monitoring schemes corresponding to each group of training scheme sample sets can be a simulation technology or emulation technology in the prior art. The selection of the simulation method here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs. As long as the simulation data of each group of monitoring schemes of each group of training scheme sample sets can be obtained by simulating each group of monitoring schemes corresponding to each group of training scheme sample sets, it will not be repeated here.

[0090] Specifically, in some embodiments, the simulation data of the monitoring equipment deployment plan includes at least the coverage rate of the effective monitoring range covered by the monitoring equipment to all construction areas, the proportion of each construction area, the monitoring type corresponding to each construction area, and the equipment parameters;

[0091] If the monitoring type corresponding to the construction area matches the geological conditions of the construction area, the score of the monitoring type corresponding to the construction area is determined to be "1", otherwise, the score of the monitoring type corresponding to the construction area is determined to be "0";

[0092] If the score of the monitoring type corresponding to the construction area is "1", if the equipment parameter corresponding to the construction area exceeds the preset equipment parameter threshold corresponding to the geological conditions of the construction area, the score of the equipment parameter corresponding to the construction area is determined to be "1", otherwise, the score of the equipment parameter corresponding to the construction area is determined to be "0";

[0093] The execution score of the monitoring equipment deployment plan is obtained by the following formula:

[0094] The execution score of the monitoring equipment deployment plan = the coverage rate of the effective monitoring range covered by the monitoring equipment to all construction areas The coefficient value that matches the effective monitoring coverage corresponding to the construction area + the proportion of each construction area The score of each monitoring type corresponding to each construction area The sum of the scores of the equipment parameters corresponding to the construction area;

[0095] Specifically, the coefficient value that matches the effective monitoring range coverage corresponding to the construction area is pre-set by the management personnel, and each coefficient value that matches the effective monitoring range coverage corresponding to the construction area may be different or the same. The setting of the coefficient value that matches the effective monitoring range coverage corresponding to the construction area here is only an exemplary description. In actual testing, technical personnel in this field can set it according to actual needs, which will not be repeated here.

[0096] Specifically, in some embodiments, the simulation data of the monitoring execution scheme includes at least the monitoring data type of at least one construction area corresponding to each monitoring device, the coverage rate of each construction area corresponding to each monitoring device, and the clear data ratio of each construction area corresponding to each monitoring device;

[0097] If the monitoring data type corresponding to the construction area in the monitoring device matches the geological conditions of the construction area, the score of the monitoring data type corresponding to the construction area in the monitoring device is determined to be "1"; otherwise, the score of the monitoring data type corresponding to the construction area in the monitoring device is determined to be "0";

[0098] The execution score of the monitoring execution plan is obtained by the following formula:

[0099] The execution score of the monitoring execution plan = the score of the monitoring data type in one of the construction areas corresponding to each monitoring device The coverage rate of the construction area of ​​the monitoring equipment The sum of the clear data proportions of the construction area of ​​the monitoring equipment;

[0100] Specifically, the clear data proportion of each construction area corresponding to the monitoring equipment is obtained including:

[0101] Acquire multiple characteristic areas of each construction area corresponding to the monitoring equipment;

[0102] Based on each feature region, determine whether each feature region belongs to a clear data region;

[0103] Based on the judgment results of each characteristic area, determine the clear data proportion of each construction area corresponding to the monitoring equipment;

[0104] The clear data ratio of each construction area corresponding to the monitoring equipment is obtained by the following formula:

[0105] The clear data ratio of any construction area corresponding to the monitoring device = the number of clear data areas of the construction area corresponding to the monitoring device / the number of all characteristic areas of the construction area corresponding to the monitoring device;

[0106] Among them, the method for judging whether each feature area belongs to a clear data area can adopt a machine learning model or a trained neural network model in the prior art. The selection of the method for judging whether each feature area belongs to a clear data area here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs, as long as it can be judged whether each feature area belongs to a clear data area based on each feature area, and it will not be repeated here.

[0107] Specifically, in some embodiments, based on the execution results of the monitoring equipment deployment scheme in each group of monitoring schemes and the execution results of the monitoring execution scheme, selecting a group of monitoring schemes as a group of monitoring schemes corresponding to the training scheme sample set includes:

[0108] Based on the execution results of the monitoring equipment deployment plan and the execution results of the monitoring execution plan in each group of monitoring plans, the monitoring plans having the execution scores of the monitoring equipment deployment plan and the execution scores of the monitoring execution plan are screened out;

[0109] Based on the screened monitoring plans, determine a comprehensive implementation score for each screened monitoring plan;

[0110] Based on the comprehensive execution scores of the monitoring solutions corresponding to each group of training solution sample sets, a group of monitoring solutions with the highest comprehensive execution scores are selected as the monitoring solutions corresponding to the training solution sample sets.

[0111] Specifically, in some embodiments, the comprehensive execution score of the monitoring scheme is obtained by the following formula:

[0112] The comprehensive execution score of the monitoring plan = the execution score of the monitoring equipment deployment plan in the monitoring plan The weight value corresponding to the monitoring equipment deployment plan + the execution score of the monitoring execution plan in the monitoring plan The weight value corresponding to the monitoring execution plan.

[0113] Specifically, in some embodiments, the training result of the solution training of the security monitoring model based on the labeling of each group of training solution sample sets and the monitoring solution corresponding to each group of training solution sample sets includes:

[0114] Obtain monitoring plans corresponding to all labeled training plan sample sets;

[0115] Based on the preset historical data solution library and all the marked training solution sample sets, obtain the historical monitoring solution corresponding to each marked training solution sample set;

[0116] If the monitoring scheme corresponding to the marked training scheme sample set is completely consistent with the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful;

[0117] Otherwise, obtaining the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set;

[0118] If the comprehensive execution score of the monitoring scheme corresponding to the marked training scheme sample set is higher than the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful; otherwise, then the result of the scheme training of the marked training scheme sample set is judged to be a failure;

[0119] Determine the training success rate of the solution training for all the labeled training solution sample sets based on the solution training results for each labeled training solution sample set;

[0120] Based on the training success rate of the solution training for all labeled training solution sample sets, the training result of the solution training of the safety monitoring model is obtained.

[0121] Specifically, in some embodiments, obtaining the training result of the solution training of the safety monitoring model based on the training success rate of the solution training of all labeled training solution sample sets includes:

[0122] If the training success rate of the scheme training for all marked training scheme sample sets is higher than the preset scheme training threshold, the training result of the scheme training of the safety monitoring model is judged to be successful training; otherwise, the training result of the scheme training of the safety monitoring model is judged to be a training failure, and the scheme training of the safety monitoring model is re-executed.

[0123] In the above embodiment, in model training, multiple groups of monitoring schemes corresponding to each group of training scheme sample sets are obtained according to multiple groups of training scheme sample sets with different marking conditions, and then each group of monitoring schemes is simulated to obtain the execution results of each group of monitoring schemes, and one group of monitoring schemes is selected as the monitoring schemes corresponding to the training scheme sample set, thereby realizing the screening of monitoring schemes to ensure that the monitoring schemes match the training scheme sample set, and then combining the marking conditions of the training scheme sample set to further determine the training results of the scheme training of the security monitoring model, thereby realizing the training of the model according to multiple groups of training scheme sample sets, and selectively retraining according to the training results, thereby ensuring the intelligent capability of the security monitoring model.

[0124] Specifically, in some embodiments, a preset historical database is stored in the safety monitoring model, and the historical database stores multiple groups of historical monitoring data of each monitoring device, a monitoring data range value corresponding to each monitoring device, and a monitoring data type corresponding to each monitoring device. Substituting the monitoring data into the safety monitoring model so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring device, and constructing a three-dimensional model of railway construction based on the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model includes:

[0125] Preprocessing the monitoring data, and selectively recollecting the monitoring data of the monitoring device;

[0126] Construct a 3D model of railway construction based on pre-processed monitoring data;

[0127] Based on the monitoring data, abnormal points are selectively marked on the three-dimensional model.

[0128] Specifically, in some embodiments, the preprocessing of the monitoring data and selectively recollecting the monitoring data of the monitoring device includes:

[0129] Based on the monitoring data, determining at least one monitoring device corresponding to the monitoring data;

[0130] Based on at least one monitoring device corresponding to the monitoring data and a preset historical database, determining whether it is necessary to re-collect the monitoring data of the monitoring device:

[0131] If the judgment is yes, the monitoring data of the monitoring device is collected again, and based on the recollected monitoring data and the preset historical database, the step of “determining whether it is necessary to recollect the monitoring data of the monitoring device” is re-executed;

[0132] If the judgment is no, the monitoring data is preprocessed to obtain preprocessed monitoring data.

[0133] Specifically, in some embodiments, based on at least one monitoring device corresponding to the monitoring data and a preset historical database, determining whether it is necessary to re-collect the monitoring data of the monitoring device includes:

[0134] Determine the type of monitoring data corresponding to each monitoring device based on at least one monitoring device corresponding to the monitoring data and a preset historical database;

[0135] If the monitoring data matches the monitoring data range value corresponding to each monitoring device corresponding to the monitoring data and the monitoring data type corresponding to each monitoring device, it is determined that there is no need to re-collect the monitoring data of the monitoring device;

[0136] Otherwise, it is determined that the monitoring data of the monitoring device needs to be collected again.

[0137] Specifically, in some embodiments, preprocessing the monitoring data to obtain the preprocessed monitoring data includes:

[0138] Performing data cleaning on the monitoring data to obtain cleaned monitoring data;

[0139] Perform data conversion on the cleaned monitoring data to obtain monitoring data whose data format matches the safety monitoring model;

[0140] The monitoring data whose data format matches the safety monitoring model is used as the preprocessed monitoring data.

[0141] Specifically, in some embodiments, the monitoring data includes data values ​​corresponding to multiple different data types. Specifically, the monitoring data includes various key indicators collected by the monitoring equipment. The data type can be an image or a video. The selection of the data type here is only an exemplary description. In actual testing, those skilled in the art can make a selection according to actual needs, which will not be repeated here.

[0142] Specifically, in some embodiments, the three-dimensional model construction technology for constructing a three-dimensional model of railway construction based on the preprocessed monitoring data can adopt the three-dimensional model construction technology in the prior art. The choice of construction method for constructing the three-dimensional model of railway construction here is only an exemplary description. In actual testing, technical personnel in this field can make a choice according to actual needs, as long as it is possible to construct a three-dimensional model of railway construction based on the preprocessed monitoring data, and it will not be repeated here.

[0143] Specifically, in some embodiments, selectively marking abnormal points on the three-dimensional model based on the monitoring data includes:

[0144] Based on the monitoring data, determine all current abnormal data in the monitoring data, and determine location information of each current abnormal data;

[0145] Performing an estimate based on the monitoring data to obtain estimated data;

[0146] Based on the estimated data, determining all estimated abnormal data in the estimated data, and determining location information of each estimated abnormal data;

[0147] If there is at least one current abnormal data in the monitoring data, based on all the current abnormal data in the monitoring data and the position information of each current abnormal data, the current abnormal point is marked at a position matching each position information on the three-dimensional model of the railway construction, and each mark of the current abnormal point is associated with a selectively displayed text box, and the text box records the current abnormal data corresponding to the current abnormal point;

[0148] If there is at least one estimated abnormal data in the estimated data, based on all the estimated abnormal data in the estimated data and the position information of each estimated abnormal data, the estimated abnormal point is marked at a position matching each position information on the three-dimensional model of the railway construction, and each mark of the estimated abnormal point is associated with a selectively displayed text box, and the text box records the estimated abnormal data corresponding to the estimated abnormal point;

[0149] If the monitoring data does not contain current abnormal data and the estimated data does not contain estimated abnormal data, marking on the three-dimensional model is not performed.

[0150] Specifically, in some embodiments, the estimated data corresponds to the data type of the monitoring data one by one.

[0151] Specifically, in some embodiments, the estimation method used for estimating the monitoring data may be an estimation technology in the prior art, or a neural network model in the prior art. The selection of the estimation method here is only an exemplary description. In actual testing, those skilled in the art may make a selection based on actual needs, as long as the estimation can be made based on the monitoring data to obtain the estimated data, which will not be elaborated here.

[0152] Specifically, in some embodiments, the different data types in the monitoring data also include location data of each construction area corresponding to each monitoring device, and the determining of all current abnormal data in the monitoring data based on the monitoring data and determining the location information of each current abnormal data includes:

[0153] Based on the monitoring data and a preset historical database, determining a monitoring data range value corresponding to each monitoring device in the monitoring data and an abnormal data range value in the historical monitoring data corresponding to each monitoring device;

[0154] If any data value in the monitoring data does not match the monitoring data range value corresponding to the monitoring device corresponding to the data value, or if any data value in the monitoring data matches the abnormal data range value in the historical monitoring data corresponding to the monitoring device corresponding to the data value, it is determined that the data value in the monitoring data is the current abnormal data, and based on the location data of the construction area corresponding to the monitoring device corresponding to the data value in the monitoring data, the location information of the current abnormal data is determined;

[0155] Otherwise, it is determined that there is no current abnormal data in the monitoring data.

[0156] Specifically, in some embodiments, the method of determining all current abnormal data in the monitoring data based on the monitoring data and determining the location information of each current abnormal data is the same as the method of determining all estimated abnormal data in the estimated data based on the estimated data and determining the location information of each estimated abnormal data.

[0157] In the above embodiment, the corresponding monitoring equipment is determined through monitoring data, and then combined with the preset historical database, it is judged whether the monitoring data needs to be re-collected, thereby realizing the judgment of whether the monitoring data meets the requirements and improving the accuracy and comprehensiveness of the monitoring data. When re-collection is not necessary, the monitoring data is pre-processed to realize the cleaning and data conversion of the monitoring data, so that the processed monitoring data matches the safety monitoring model, ensuring the quality and consistency of the data, thereby improving the data processing and analysis efficiency of the safety monitoring model. According to the pre-processed monitoring data, a three-dimensional model of railway construction is constructed to realize a visual display of railway construction, and according to the monitoring data, abnormal points are selectively marked on the three-dimensional model to realize the marking of current abnormal points and estimated abnormal points, so that management personnel can view and handle the abnormal situation, thereby enabling management personnel to timely discover potential safety risks and improve the safety of railway construction.

[0158] Step S103: If there are abnormal points on the three-dimensional model, based on the abnormal points, an alarm signal corresponding to the abnormal points is sent to the management personnel corresponding to the abnormal points.

[0159] Furthermore, in some embodiments, the method further comprises:

[0160] If there are no abnormal points on the three-dimensional model, the three-dimensional model is displayed to the management personnel corresponding to the monitoring data.

[0161] Specifically, in some embodiments, the alarm signal corresponding to the abnormal point can be one or more of sound, light, voice, SMS notification, and telephone notification. The setting of the alarm signal here is only an exemplary description. In actual testing, technical personnel in this field can set it according to actual needs, which will not be repeated here.

[0162] Based on the above steps S101 to S103, by responding to the monitoring instruction, the monitoring data is collected by the monitoring device corresponding to the monitoring instruction, so as to realize the periodic collection of the monitoring data, and then the monitoring data is substituted into the safety monitoring model, and then the monitoring data is preprocessed, and the monitoring data is selectively recollected, so as to ensure the accuracy and completeness of the monitoring data, and then the three-dimensional model of the railway construction is constructed according to the preprocessed monitoring data, and the abnormal points are selectively marked on the three-dimensional model, so as to realize the visual display of the railway construction situation, so that the management personnel can timely know and solve the abnormal problem according to the location and situation of the abnormal point, and when there is an abnormal point on the three-dimensional model, according to the abnormal point, the alarm signal corresponding to the abnormal point is sent to the management personnel corresponding to the abnormal point, so that the management personnel can timely understand the abnormal situation and take corresponding measures, so as to prevent the occurrence of safety accidents, improve the accuracy and comprehensiveness of the safety monitoring of the railway construction, and ensure the safe operation of the railway construction, and avoid the monitoring method in the prior art that greatly relies on the professional ability of the monitoring personnel, and is prone to partial missed detection and false alarm, thereby leading to the extension of the construction period and the technical problem of poor accuracy of error reporting.

[0163] It should be pointed out that although the various steps in the above embodiments are described in a specific order, those skilled in the art can understand that in order to achieve the effects of the present invention, different steps do not have to be performed in such an order, and they can be performed simultaneously (in parallel) or in other orders. These changes are within the scope of protection of the present invention.

[0164] Furthermore, the present invention also provides a safety construction and safety monitoring system for underpass railway.

[0165] See attached Figure 2 , Figure 2 FIG. 1 is a main structural block diagram of a railway underpass safety construction and safety monitoring system according to an embodiment of the present invention. Figure 2As shown, the underpass railway safety construction and safety monitoring system 200 in the embodiment of the present invention interacts with the terminal devices corresponding to the management personnel corresponding to each construction data. The system mainly includes multiple monitoring devices 203, preset construction information 204, a safety monitoring model 202 and a control device 201. The monitoring device 203 is used to collect monitoring data of railway construction. The preset construction information 204 includes construction data of railway construction and at least one designated installation location matching the construction data. In addition, the construction data includes construction areas with different geology, setting parameters corresponding to the construction areas, and Execution construction type, the safety monitoring model 202 stores a preset historical database 2021 and a preset historical data solution library 2022, the control device 201 includes a processor 2011 and a memory 2012, the memory 2012 can be configured to store a program code 2013 for executing the underpass railway safety construction and safety monitoring method of the above method embodiment, the processor 211 can be configured to execute the program code 213 in the memory 2012, the program code 2013 includes but is not limited to the program code 2013 for executing the underpass railway safety construction and safety monitoring method of the above method embodiment. For ease of explanation, only the parts related to the embodiment of the present invention are shown. For specific technical details not disclosed, please refer to the method part of the embodiment of the present invention. The control device 201 can be a control device 201 device formed by various electronic devices.

[0166] Specifically, in some embodiments, the historical data solution library 2022 stores a plurality of historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data that matches the construction data;

[0167] The historical database 2021 stores multiple groups of historical monitoring data of each monitoring device 203, the monitoring data range value corresponding to each monitoring device 203, and the monitoring data type corresponding to each monitoring device 203;

[0168] The system further comprises a communication device 205, and the communication device 205 is used to realize information interaction with terminal devices corresponding to management personnel corresponding to each construction data.

[0169] Specifically, in some embodiments, the terminal device of the administrator can be a mobile phone, a tablet computer, a laptop computer, etc. The selection of the terminal device of the administrator here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs, as long as the administrator can realize information interaction with the system through the terminal device, and it will not be repeated here.

[0170] Specifically, in some embodiments, the specific communication connection mode for information interaction between the communication device 205 and the terminal device corresponding to the manager corresponding to each construction data is not restrictive, and the technician can set it according to the actual use requirements, as long as the communication connection can be achieved, for example, it can be connected through wifi or Bluetooth, etc. In addition, as a preferred setting method, when the manager's terminal device is a mobile phone or a tablet computer, the manager can set up an app to facilitate user operation. Of course, it can also be operated directly through the web page. This is not restrictive, and the technician can set it according to the actual use requirements.

[0171] Specifically, in some embodiments, the communication device 205 can be a wireless communication device in the prior art, or it can be a wired communication device. The selection of the communication device 205 here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs. As long as the communication device 205 can be used to realize information interaction with the terminal devices corresponding to the managers corresponding to each construction data, it will not be repeated here.

[0172] Specifically, in some embodiments, the monitoring device 203 can be an image acquisition device, a video acquisition device, or a sensor acquisition device, wherein the sensor acquisition device can be one or more of a pressure sensor, a temperature sensor, and a humidity sensor. The selection of the monitoring device 203 here is only an exemplary description. In actual testing, technical personnel in this field can make a selection according to actual needs, as long as the monitoring data of the railway construction can be collected through the monitoring device 203, and no further details will be given here.

[0173] In one implementation, the description of the specific implementation functions may refer to steps S101 to S103.

[0174] The above-mentioned railway underpass safety construction and safety monitoring system 200 is used to perform Figure 1 The embodiment of the method for safe construction and safety monitoring of underpass railway shown in the figure has similar technical principles, technical problems solved and technical effects produced. Technicians in this technical field can clearly understand that for the convenience and conciseness of description, the specific working process and relevant instructions of the system 200 for safe construction and safety monitoring of underpass railway can refer to the contents described in the embodiment of the method for safe construction and safety monitoring of underpass railway, which will not be repeated here.

[0175] It is understood by those skilled in the art that the present invention implements all or part of the processes in the method of the above embodiment, and can also be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium, and when the computer program is executed by the processor 2011, the steps of each of the above method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable storage medium may include: any entity or device, medium, U disk, mobile hard disk, disk, optical disk, computer memory 2012, read-only memory 2012, random access memory 2012, electric carrier signal, telecommunication signal and software distribution medium that can carry the computer program code. It should be noted that the content contained in the computer-readable storage medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable storage medium does not include electric carrier signal and telecommunication signal.

[0176] Further, the system of the present invention also includes a computer-readable storage medium. In a computer-readable storage medium embodiment according to the present invention, the computer-readable storage medium can be configured to store a program code 2013 for executing the method for safe construction and safety monitoring of underpass railways of the above-mentioned method embodiment, and the program code 2013 can be loaded and run by the processor 211 to implement the above-mentioned method for safe construction and safety monitoring of underpass railways. For ease of explanation, only the parts related to the embodiment of the present invention are shown. For specific technical details not disclosed, please refer to the method part of the embodiment of the present invention. The computer-readable storage medium can be a memory 2012 device formed by various electronic devices. Optionally, the computer-readable storage medium in the embodiment of the present invention is a non-temporary computer-readable storage medium.

[0177] Further, it should be understood that since the setting of each module is only for illustrating the functional units of the device of the present invention, the physical devices corresponding to these modules may be the processor 2011 itself, or a part of the software, a part of the hardware, or a part of the combination of software and hardware in the processor 2011. Therefore, the number of each module in the figure is only schematic.

[0178] Those skilled in the art will appreciate that the modules in the device can be adaptively split or merged. Such splitting or merging of specific modules will not cause the technical solution to deviate from the principle of the present invention, and therefore, the technical solutions after splitting or merging will fall within the protection scope of the present invention.

[0179] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.

Claims

1. A method for safe construction and safety monitoring of underpass railway, It is characterized in that The method comprises the following steps: In response to a monitoring instruction corresponding to at least one monitoring device, collecting monitoring data; Substituting the monitoring data into the safety monitoring model so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring device, and constructing a three-dimensional model of railway construction based on the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model, wherein the abnormal points include current abnormal points and predicted abnormal points; If there are abnormal points on the three-dimensional model, based on the abnormal points, an alarm signal corresponding to the abnormal points is sent to the management personnel corresponding to the abnormal points; The safety monitoring model stores a preset historical database, wherein the historical database stores multiple groups of historical monitoring data of each monitoring device, a monitoring data range value corresponding to each monitoring device, and a monitoring data type corresponding to each monitoring device. Substituting the monitoring data into the safety monitoring model so as to pre-process the monitoring data, selectively re-collect the monitoring data of the monitoring device, and constructing a three-dimensional model of railway construction based on the pre-processed monitoring data, and selectively marking abnormal points on the three-dimensional model includes: Preprocessing the monitoring data, and selectively recollecting the monitoring data of the monitoring device; Construct a 3D model of railway construction based on pre-processed monitoring data; and selectively marking abnormal points on the three-dimensional model based on the monitoring data; The preprocessing of the monitoring data and selectively recollecting the monitoring data of the monitoring device comprises: Based on the monitoring data, determining at least one monitoring device corresponding to the monitoring data; Based on at least one monitoring device corresponding to the monitoring data and a preset historical database, determining whether it is necessary to re-collect the monitoring data of the monitoring device: If the judgment is yes, the monitoring data of the monitoring device is collected again, and based on the recollected monitoring data and the preset historical database, "determining whether it is necessary to recollect the monitoring data of the monitoring device" is re-executed; If the judgment is no, preprocessing the monitoring data to obtain preprocessed monitoring data; Based on at least one monitoring device corresponding to the monitoring data and a preset historical database, determining whether it is necessary to re-collect the monitoring data of the monitoring device includes: Determine the type of monitoring data corresponding to each monitoring device based on at least one monitoring device corresponding to the monitoring data and a preset historical database; If the monitoring data matches the monitoring data range value corresponding to each monitoring device corresponding to the monitoring data and the monitoring data type corresponding to each monitoring device, it is determined that there is no need to re-collect the monitoring data of the monitoring device; Otherwise, it is determined that the monitoring data of the monitoring device needs to be collected again; The selectively marking abnormal points on the three-dimensional model based on the monitoring data includes: Based on the monitoring data, determine all current abnormal data in the monitoring data, and determine location information of each current abnormal data; Performing an estimate based on the monitoring data to obtain estimated data; Based on the estimated data, determining all estimated abnormal data in the estimated data, and determining location information of each estimated abnormal data; If there is at least one current abnormal data in the monitoring data, based on all the current abnormal data in the monitoring data and the position information of each current abnormal data, marking the current abnormal point at a position matching each position information on the three-dimensional model of the railway construction; If there is at least one estimated abnormal data in the estimated data, based on all the estimated abnormal data in the estimated data and the position information of each estimated abnormal data, marking the estimated abnormal point at the position matching each position information on the three-dimensional model of the railway construction; If the monitoring data does not contain current abnormal data and the estimated data does not contain estimated abnormal data, marking on the three-dimensional model is not performed; The different data types in the monitoring data also include the location data of each construction area corresponding to each monitoring device. Based on the monitoring data, determining all current abnormal data in the monitoring data and determining the location information of each current abnormal data includes: Based on the monitoring data and a preset historical database, determining a monitoring data range value corresponding to each monitoring device in the monitoring data and an abnormal data range value in the historical monitoring data corresponding to each monitoring device; If any data value in the monitoring data does not match the monitoring data range value corresponding to the monitoring device corresponding to the data value, or if any data value in the monitoring data matches the abnormal data range value in the historical monitoring data corresponding to the monitoring device corresponding to the data value, it is determined that the data value in the monitoring data is the current abnormal data, and based on the location data of the construction area corresponding to the monitoring device corresponding to the data value in the monitoring data, the location information of the current abnormal data is determined; Otherwise, it is judged that there is no current abnormal data in the monitoring data; Among them, the method of determining all current abnormal data in the monitoring data based on the monitoring data and determining the location information of each current abnormal data is the same as the method of determining all estimated abnormal data in the estimated data based on the estimated data and determining the location information of each estimated abnormal data.

2. The method for safe construction and safety monitoring of underpass railway according to claim 1, It is characterized in that Before collecting monitoring data in response to a monitoring instruction corresponding to at least one monitoring device, the method further includes: Acquire construction data of railway construction and at least one designated installation location matching the construction data, wherein the construction data includes geologically different construction areas, setting parameters corresponding to the construction areas, and the type of construction to be performed; Acquire equipment data of the monitoring equipment, wherein the equipment data includes monitoring type, equipment model, effective monitoring range and equipment parameters; The equipment data of the monitoring equipment, the construction data of the railway construction and at least one designated installation location matching the construction data are substituted into the safety monitoring model to obtain a monitoring plan corresponding to the railway construction, wherein the monitoring plan includes a monitoring equipment deployment plan and a monitoring execution plan corresponding to each monitoring equipment.

3. The method for safe construction and safety monitoring of underpass railway according to claim 2, It is characterized in that Before substituting the equipment data of the monitoring equipment, the construction data of the railway construction, and at least one designated installation location matching the construction data into the safety monitoring model, the method further includes performing solution training on the safety monitoring model by the following steps: Acquire multiple sets of training solution sample sets with different marking conditions, wherein each set of training solution sample sets includes a set of equipment data, a set of construction data, and at least one designated installation location matching the construction data; Based on each set of training solution sample sets, multiple sets of monitoring solutions are obtained; Simulate each group of monitoring plans corresponding to each group of training plan sample sets to obtain the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan; Based on the execution results of the monitoring equipment deployment plan in each group of monitoring plans and the execution results of the monitoring execution plan, a group of monitoring plans is selected as a group of monitoring plans corresponding to the training plan sample set; Based on the marking conditions of each group of training solution sample sets and the monitoring solutions corresponding to each group of training solution sample sets, the training results of the solution training of the safety monitoring model are obtained.

4. The method for safe construction and safety monitoring of underpass railway according to claim 3, It is characterized in that The safety monitoring model stores a preset historical data solution library, wherein the historical data solution library stores multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data matching the construction data. Acquiring multiple sets of training solution sample sets with different marking conditions includes: Based on a preset historical data solution library, randomly select multiple historical monitoring solutions, construction data corresponding to each historical monitoring solution, and at least one designated installation location and equipment data that matches the construction data; The construction data corresponding to each selected historical monitoring scheme, at least one designated installation location matching the construction data, and equipment data are used as one set of training scheme sample sets, and the training scheme sample sets are marked; The selected construction data, at least one designated installation location matching the construction data, and the equipment data are randomly combined to obtain multiple sets of training solution sample sets.

5. The method for safe construction and safety monitoring of underpass railway according to claim 4, It is characterized in that The simulation of each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain the execution results of the monitoring equipment deployment scheme in each group of monitoring schemes and the execution results of the monitoring execution schemes include: Simulate each group of monitoring schemes corresponding to each group of training scheme sample sets to obtain simulation data of each group of monitoring schemes in each group of training scheme sample sets; Based on the simulation data of the monitoring equipment deployment scheme in the simulation data of each group of monitoring schemes, the execution result of the monitoring equipment deployment scheme in each group of monitoring schemes is obtained, wherein the execution result of the monitoring equipment deployment scheme includes execution success or execution failure, and an execution score matching the execution success; Based on the simulation data of the monitoring execution scheme in the simulation data of each group of monitoring schemes, the execution results of the monitoring execution scheme in each group of monitoring schemes are obtained, wherein the execution results of the monitoring execution scheme include execution success or execution failure, and an execution score matching the execution success.

6. The method for safe construction and safety monitoring of underpass railway according to claim 5, It is characterized in that The training result of the scheme training of the security monitoring model obtained based on the marking of each group of training scheme sample sets and the monitoring scheme corresponding to each group of training scheme sample sets includes: Obtain the monitoring solutions corresponding to all labeled training solution sample sets; Based on the preset historical data solution library and all the labeled training solution sample sets, obtain the historical monitoring solution corresponding to each labeled training solution sample set; If the monitoring scheme corresponding to the marked training scheme sample set is completely consistent with the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful; Otherwise, obtaining the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set; If the comprehensive execution score of the monitoring scheme corresponding to the marked training scheme sample set is higher than the comprehensive execution score of the historical monitoring scheme corresponding to the marked training scheme sample set, then the result of the scheme training of the marked training scheme sample set is judged to be successful; otherwise, then the result of the scheme training of the marked training scheme sample set is judged to be a failure; Determine the training success rate of the solution training for all the labeled training solution sample sets based on the solution training results for each labeled training solution sample set; Based on the training success rate of the solution training for all labeled training solution sample sets, the training result of the solution training of the safety monitoring model is obtained.

7. A safety construction and safety monitoring system for underpass railway, It is characterized in that The system exchanges information with terminal devices corresponding to management personnel corresponding to each construction data. The system includes multiple monitoring devices, preset construction information, a safety monitoring model and a control device. The monitoring device is used to collect monitoring data of railway construction. The preset construction information includes construction data of railway construction and at least one designated installation location matching the construction data. In addition, the construction data includes geologically different construction areas, setting parameters corresponding to the construction areas, and execution types of construction. The safety monitoring model stores a preset historical database and a preset historical data solution library. The control device includes a processor and a memory. The memory is suitable for storing multiple program codes, and is characterized in that the program code is suitable for being loaded and run by the processor to execute the underpass railway safety construction and safety monitoring method described in any one of claims 1 to 6.

Citation Information

Patent Citations

  • Method and system for utility infrastructure condition monitoring, detection and response

    CA3131764A1

  • Digital twin hydraulic engineering operation and maintenance monitoring system and method

    CN116757097A