Project risk identification method and device, equipment and storage medium
By obtaining and analyzing project plans and actual execution information, and calculating project popularity, the problem of inaccurate project risk identification in the existing technology is solved, and the efficiency of risk identification and the timeliness of integrity prevention and control are improved.
Patent Information
- Application Number
- CN202311146889.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-06
- Publication Date
- 2024-10-18
AI Technical Summary
Existing technology is difficult to accurately identify risks caused by resource anomalies and time logic anomalies in projects, resulting in low project risk identification efficiency. Especially in the face of emerging industries and new corruption issues, it is difficult to effectively prevent and control them.
By obtaining project plan information and actual execution information, the planned risk project participants, project information, time deviation and resource deviation are determined, the project popularity is calculated based on this information, and project risk identification results are generated.
It improves the accuracy and efficiency of project risk identification, enables timely identification and early warning of potential risks, and ensures the timely implementation of integrity prevention and control work.
Smart Images

Figure CN118798624A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of computer technology, and in particular to a project risk identification method, device, equipment and storage medium. Background Art
[0002] The relevant ways to reduce project risks generally include administrative means such as responsibility compaction and hierarchical approval of affairs. However, in the face of emerging industries and new corruption problems, the relevant project risk avoidance methods have the problems of inaccurate risk identification and unscientific prevention and control measures. It is difficult to identify potential "bleeding points" such as specific risk scenarios, hidden dangers and problems in the production and operation process of the project simply through the division of functions. Therefore, how to identify risks such as resource anomalies and time logic anomalies in the project has become a technical problem that needs to be solved urgently. Summary of the invention
[0003] The main purpose of the present invention is to provide a project risk identification method, device, equipment and storage medium, aiming to solve the technical problem that the existing technology is difficult to identify specific risk scenarios in the project production and operation process, resulting in low efficiency in project risk identification.
[0004] To achieve the above object, the present invention provides a project risk identification method, which comprises the following steps:
[0005] Obtain project plan information and project actual execution information;
[0006] Determine the planned risk project participant information, planned risk project information, time deviation project information and actual resource deviation project information according to the project plan information and the project actual execution information;
[0007] Determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information;
[0008] A project risk identification result is generated according to the project heat.
[0009] Optionally, the step of determining the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information according to the project plan information and the project actual execution information includes:
[0010] Determine the planned risk project participant information and planned risk project information according to the project plan information;
[0011] The time deviation project information and the actual resource deviation project information are determined according to the actual execution information of the project.
[0012] Optionally, the step of determining the planned risk project participant information and the planned risk project information according to the project plan information includes:
[0013] Determine project personnel information based on the project plan information;
[0014] Determine the work area information and the popularity of the project personnel according to the project personnel information;
[0015] Based on the work interval information and the project personnel enthusiasm, the planned risk project participant information is determined by a preset first algorithm;
[0016] The planned risk project information is determined according to the project personnel information by using a preset second algorithm.
[0017] Optionally, the step of determining the time deviation project information and the actual resource deviation project information according to the actual execution information of the project includes:
[0018] Determine the information of the actual executors of the project based on the actual execution information of the project;
[0019] Determine the time deviation project information based on the information of the actual executors of the project;
[0020] The actual resource deviation project information is determined according to the actual execution information of the project.
[0021] Optionally, the step of generating a project risk identification result according to the project heat includes:
[0022] Comparing the project heat with a preset project heat threshold to obtain a comparison result;
[0023] When the comparison result is that the project heat is greater than the preset project heat threshold, it is determined that the target project corresponding to the project heat has project risk.
[0024] Optionally, when the comparison result shows that the project popularity is greater than the preset project popularity threshold, after the step of determining that the target project corresponding to the project popularity has a project risk, the method further includes:
[0025] Determine the project leader information corresponding to the target project;
[0026] Determine the risk project information corresponding to the project leader according to the project leader information;
[0027] A risk identification result for the project manager is generated based on the risk project information.
[0028] Optionally, the step of obtaining project plan information and project actual execution information includes:
[0029] Collect project plan data, and store the project plan data as serialized structure data;
[0030] Determine project plan information according to the serialized structure data;
[0031] Collecting actual execution data of the project, and constructing tree structure data according to the actual execution data of the project;
[0032] The actual execution information of the project is determined according to the tree structure data.
[0033] In addition, to achieve the above-mentioned purpose, the present invention also provides a project risk identification device, the device comprising:
[0034] The acquisition module is used to obtain project plan information and project actual execution information;
[0035] A calculation module, used to determine the planned risk project participant information, planned risk project information, time deviation project information and actual resource deviation project information according to the project plan information and the project actual execution information;
[0036] A project heat determination module, used to determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information;
[0037] The project risk identification result generation module is used to generate a project risk identification result according to the project heat.
[0038] In addition, to achieve the above-mentioned purpose, the present invention also proposes a project risk identification device, which includes: a memory, a processor, and a project risk identification program stored in the memory and executable on the processor, and the project risk identification program is configured to implement the steps of the project risk identification method described above.
[0039] In addition, to achieve the above-mentioned purpose, the present invention also proposes a storage medium, on which a project risk identification program is stored, and when the project risk identification program is executed by a processor, the steps of the project risk identification method described above are implemented.
[0040] The present invention obtains project planning information and project actual execution information; determines planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on the project planning information and the project actual execution information; determines project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information; generates project risk identification results based on the project heat. Since the present invention determines planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on project planning information and project actual execution information, and then determines project risk identification results. This solves the technical problem in the related art that it is difficult to identify specific risk scenarios in the project production and operation process, resulting in low efficiency in project risk identification. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 It is a schematic diagram of the structure of a project risk identification device in a hardware operating environment involved in an embodiment of the present invention;
[0042] Figure 2 This is a flow chart of the first embodiment of the project risk identification method of the present invention;
[0043] Figure 3 This is a flow chart of a second embodiment of the project risk identification method of the present invention;
[0044] Figure 4 It is a flowchart of the third embodiment of the project risk identification method of the present invention;
[0045] Figure 5 It is a functional module diagram of the third embodiment of the project risk identification method of the present invention;
[0046] Figure 6 This is a structural block diagram of the first embodiment of the project risk identification device of the present invention.
[0047] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0048] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.
[0049] Reference Figure 1 , Figure 1 It is a schematic diagram of the structure of a project risk identification device for a hardware operating environment involved in an embodiment of the present invention.
[0050] like Figure 1As shown, the project risk identification device may include: a processor 1001, such as a central processing unit (CPU), a communication bus 1002, a user interface 1003, a network interface 1004, and a memory 1005. Among them, the communication bus 1002 is used to realize the connection and communication between these components. The user interface 1003 may include a display screen (Display), an input unit such as a keyboard (Keyboard), and the optional user interface 1003 may also include a standard wired interface and a wireless interface. The network interface 1004 may optionally include a standard wired interface and a wireless interface (such as a wireless fidelity (Wireless-Fidelity, WI-FI) interface). The memory 1005 may be a high-speed random access memory (Random Access Memory, RAM), or a stable non-volatile memory (Non-Volatile Memory, NVM), such as a disk storage. The memory 1005 may also be a storage device independent of the aforementioned processor 1001.
[0051] Those skilled in the art will understand that Figure 1 The structure shown in the figure does not constitute a limitation on the project risk identification device, and may include more or less components than shown in the figure, or combine certain components, or arrange the components differently.
[0052] like Figure 1 As shown, the memory 1005 as a storage medium may include an operating system, a network communication module, a user interface module, and a project risk identification program.
[0053] exist Figure 1 In the project risk identification device shown, the network interface 1004 is mainly used for data communication with the network server; the user interface 1003 is mainly used for data interaction with the user; the processor 1001 and the memory 1005 in the project risk identification device of the present invention can be set in the project risk identification device, and the project risk identification device calls the project risk identification program stored in the memory 1005 through the processor 1001, and executes the project risk identification method provided by the embodiment of the present invention.
[0054] Based on the above project risk identification device, an embodiment of the present invention provides a project risk identification method, referring to Figure 2 , Figure 2 This is a flow chart of the first embodiment of the project risk identification method of the present invention.
[0055] In this embodiment, the project risk identification method includes the following steps:
[0056] Step S10: Obtain project plan information and project actual execution information.
[0057] It should be noted that the execution subject of this embodiment can be a computing service device with data processing, network communication and program running functions, such as a mobile phone, a tablet computer, a personal computer, etc., or an electronic device or a project risk identification device that can realize the above functions. The project risk identification device is taken as an example to illustrate this embodiment and the following embodiments.
[0058] It should be noted that the project planning information may be data such as project resources, plans, scale, person in charge, etc. The actual project execution information may be information such as account information, process information, and working hours of project-related personnel when executing the project.
[0059] Step S20: Determine the planned risk project participant information, planned risk project information, time deviation project information and actual resource deviation project information according to the project plan information and the project actual execution information.
[0060] It should be noted that the determining of the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information according to the project plan information and the project actual execution information may be determining the planned risk project participant information and the planned risk project information according to the project plan information;
[0061] The time deviation project information and the actual resource deviation project information are determined according to the actual execution information of the project.
[0062] Furthermore, in order to improve the efficiency of project risk identification, the step of determining the planned risk project participant information and the planned risk project information according to the project plan information includes:
[0063] Determine project personnel information based on the project plan information;
[0064] Determine the work area information and the popularity of the project personnel according to the project personnel information;
[0065] Based on the work interval information and the project personnel enthusiasm, the planned risk project participant information is determined by a preset first algorithm;
[0066] The planned risk project information is determined according to the project personnel information by using a preset second algorithm.
[0067] It should be noted that the project personnel information may include the heat variable of each project participant, i.e., the heat of the project personnel, with an initial value of 0, and the participation time of each project participant in each project, i.e., the work interval information. The determination of the planned risk project participant information based on the work interval information and the project personnel heat by the preset first algorithm may be to determine whether the project personnel heat is greater than the project participation time in the work interval information. If it is greater, the planned risk project participant information indicates that the project participant is at risk, and the project corresponding to the project participant is also at risk. The determination of the planned risk project information based on the project personnel information by the preset second algorithm may be to determine the sum of the working time of the project participant in each project based on the project personnel information. When the sum of the working time is greater than or equal to the preset working time threshold, the planned risk project information indicates that the project corresponding to the project participant is at risk. When the sum of the working time is less than the preset working time threshold, the planned risk project information does not include the project corresponding to the project participant. The preset working time threshold may be a threshold set in advance according to the project information for determining whether a project is at risk.
[0068] Furthermore, the step of determining the time deviation project information and the actual resource deviation project information according to the actual execution information of the project includes:
[0069] Determine the information of the actual executors of the project based on the actual execution information of the project;
[0070] Determine the time deviation project information based on the information of the actual executors of the project;
[0071] The actual resource deviation project information is determined according to the actual execution information of the project.
[0072] It should be noted that the project actual executor information may include the project workflow node information, and the arrival and exit time points of each project node in the workflow node information. The time deviation project information determined according to the project actual executor information may be to calculate the difference between the arrival and exit time points of the project node, and determine whether the difference is greater than or equal to a preset time deviation threshold. If the difference is greater than or equal to the preset time deviation threshold, the project with a difference greater than or equal to the preset time deviation threshold is added to the time deviation project information, and the project in the time deviation project information is a risky project. The actual resource deviation project information determined according to the project actual execution information may be to calculate the difference between the arrival and exit time points of the project node, and determine whether the difference is greater than or equal to a preset actual resource deviation threshold. If the difference is greater than or equal to the preset actual resource deviation threshold, the project with a difference greater than or equal to the preset actual resource deviation threshold is added to the actual resource deviation project information, and the actual resource deviation project information stores risky projects.
[0073] Step S30: Determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information.
[0074] It should be noted that the determination of the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information can be to determine the number of occurrences of the target project in the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information, and determine the number of occurrences as the project heat. For example. Project A exists in the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information at the same time, then the project heat of Project A is 4; Project B exists in the planned risk project information, the time deviation project information and the actual resource deviation project information at the same time, then the project heat of Project B is 3.
[0075] Step S40: Generate a project risk identification result according to the project heat.
[0076] It should be noted that generating a project risk identification result according to the project heat may be that when the project heat is greater than a preset project heat threshold, it is determined that the project has a higher level of project risk.
[0077] Furthermore, in order to accurately determine the project risk identification result, the step S40 may include: comparing the project heat with a preset project heat threshold to obtain a comparison result;
[0078] When the comparison result is that the project heat is greater than the preset project heat threshold, it is determined that the target project corresponding to the project heat has project risk.
[0079] It should be noted that the preset project heat threshold may be a preset project risk determination threshold used to determine whether the project has a higher level of project risk.
[0080] This embodiment obtains project planning information and project actual execution information; determines the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on the project planning information and the project actual execution information; determines the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information; generates a project risk identification result based on the project heat. Since this embodiment determines the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on the project planning information and the project actual execution information, and then determines the project risk identification result. This solves the technical problem in the related technology that it is difficult to identify specific risk scenarios in the project production and operation process, resulting in low efficiency in project risk identification.
[0081] refer to Figure 3 , Figure 3 This is a flow chart of the second embodiment of the project risk identification method of the present invention.
[0082] Based on the above first embodiment, in this embodiment, step S10 includes:
[0083] Step S101: Collect project plan data, and store the project plan data as serialized structure data.
[0084] It should be noted that the project plan data may be data on project resources, plans, scale, responsible persons, etc. The storing of the project plan data as serialized structure data may be storing the project plan data as serialized structure data in the following format:
[0085] S i ={id i , o i , w i , R i , M i},(R i ={{r i1 , P startir1 , p endir1}, …{r in , P startirn , p endirn}},Mi
[0086] ={{m i1 , p startim1 , p endim1},…{m i1 , P startimn , p endimn}})
[0087] Among them, id i Identification information for identifiable items, o i This is the personal information that can identify the project leader. i is the overall size of the project (usually measured in terms of workload), r i The resources invested in the project (usually the personal information of the identifiable participants), m i is the workflow node of the project, p starti and p endi They are the starting interval and ending interval of the node or resource respectively.
[0088] Step S102: determining project plan information according to the serialized structure data.
[0089] It should be noted that the determining of the project plan information according to the serialized structure data may be to construct a data structure of the serialized structure data, which may be: upon first receiving the serialized structure data S i When creating a node o i , the value is the chain data block L oi The tree data structure of (p idn The deadline minus the start time is used to represent the project) where p oi Used to store personnel heat variables, the initial value is 0; the construction node is id i , the value is o i , w i , R i , M i The tree data structure of Construct a graph data structure with horizontal nodes as ri and vertical nodes as dates Pri is used to store personnel heat variables, with an initial value of 0. i When there are repeated nodes, P ri The value is assigned as the total number of repetitions. To improve the efficiency of risk identification, the data is stored in a high-speed storage module. If the incremental S caused by the subsequent project data change is received i Data, then according to o i ,id i 、r i As a node identifier, To 、T id , H r Expand or refresh; store the data in a high-speed storage module after updating; and store it in a database for data persistence and disaster recovery backup.
[0090] Step S103: Collecting actual execution data of the project, and constructing tree structure data according to the actual execution data of the project.
[0091] Step S104: determining the actual execution information of the project according to the tree structure data.
[0092] It should be noted that the actual project execution data may include project-related personnel ledgers, process records, project-related source code, components, various manuals, reports and other materials and deliverables. The tree structure data constructed based on the actual project execution data and determining the actual project execution information may be the operation ledger S′ of the synchronized project deliverables. i ={id′ i , r′ i , t′ i}, where id′ i is the identification information of the identifiable item, r′ i is the resource of the deliverable on the account (usually the personal information of the identifiable participant), t′ i It is the time point of the ledger flow (the time period when the participants actually participated). During the first synchronization, the receiving module establishes a node with id' i , the value is the chain data block L′ id′i The tree data structure:
[0093]
[0094] If there are changes in the project deliverables, add T′ id′ Node, or append the corresponding L′ id′i Node. And synchronize electronic circulation records at the same time:
[0095] S″ i ={id″ i , F i},(F i ={{m″ i1 , r″ i1 , t″ arri1 , t″ sndi1},...{m″ in , r″ in , t″ arrin , t″ sndin}})
[0096] Where id" iis the identification information of the identifiable item, m′′ i is the workflow node of the project, t″ arri and t″ sndi are the arrival and exit time points of the node respectively. During the first synchronization, the receiving module establishes the node as id" i , the value is chain data block L″ id″i The tree data structure:
[0097]
[0098] In order to improve the processing efficiency of the risk prevention and control processing module, the data is stored in the high-speed storage module B; and in the event of changes in the project deliverables, a new T″ id″ Node, or append the corresponding L″ id″ i-node; stored in the database at the same time for data persistence and disaster recovery backup.
[0099] This embodiment collects project plan data, stores the project plan data as serialized structure data; determines project plan information based on the serialized structure data; collects project actual execution data, constructs tree structure data based on the project actual execution data; and determines project actual execution information based on the tree structure data. This embodiment achieves effective integration of project process and integrity prevention and control mechanism by accessing data such as project data, personnel ledgers, and behavior records, and accurately identifies projects with risks.
[0100] refer to Figure 4 , Figure 4 This is a flow chart of the third embodiment of the project risk identification method of the present invention.
[0101] Based on the above embodiments, in this embodiment, the step: when the comparison result is that the project heat is greater than the preset project heat threshold, after determining that the target project corresponding to the project heat has a project risk, the method further includes:
[0102] Step S50: Determine the project manager information corresponding to the target project.
[0103] It should be noted that the project person in charge information may be the project responsible person corresponding to the target project, and may be a project manager or an actual project manager.
[0104] Step S60: Determine the risk project information corresponding to the project leader according to the project leader information.
[0105] It should be noted that determining the risk project information corresponding to the project leader according to the project leader information may be determining the risk projects corresponding to each project leader and the number of accumulated risk projects according to the project risk identification results and the project leader information corresponding to the project.
[0106] Step S70: Generate a risk identification result for the project manager based on the risk project information.
[0107] It should be noted that the risk identification result of the project leader generated according to the risk project information can be to sort the project leaders according to the number of risk projects corresponding to each project leader, and define the first preset number of project leaders in the sorting result as risk project leaders. The number of risk projects corresponding to the remaining project leaders is less than the number of risk projects corresponding to the risk project leader. The preset number can be a custom number, which is not limited in this embodiment.
[0108] This embodiment determines the project leader information corresponding to the target project; determines the risk project information corresponding to the project leader based on the project leader information; generates the risk identification result of the project leader based on the risk project information. This embodiment can determine the project leader responsible for the risk project, and then determine the person responsible for the risk project, and can accurately identify the risk of the project leader. Early warning of possible integrity prevention and control risks is carried out to ensure the timely implementation of integrity prevention and control work.
[0109] In the specific implementation, please refer to Figure 5 , Figure 5 This is a functional module diagram of the third embodiment of the project risk identification method of the present invention. The functional modules of the project risk identification method of the present invention are divided into a project information processing module, a product warehouse and behavior record processing module, a risk prevention and control processing module, a display and alarm module, etc. For details, please refer to Figure 5 , the following basis Figure 5 The specific process in this embodiment is described in detail:
[0110] The project information processing module is deployed in the background server cluster and the front-end project management server, and is used to collect relevant data on the project management server; the front-end project management server mainly monitors the changes of project data through the front-end agent, and synchronizes the relevant data to the background when changes occur; the background server cluster mainly stores the returned project information through the background receiving module, and saves it to the cache module for access by other modules. The specific steps of data interaction are as follows:
[0111] The front-end agent grabs the project's resources, plans, scale, responsible persons and other data from the front-end project management server and saves it as a serialized data structure:
[0112] S i =
[0113] {id i , o i , wi , R i , M i},(R i = {r i1 , p startir1 , p endir1}, ... {r in , p startirn , p endirn}}M i =mi1,pstartim1,pendim1,...mi1,pstartimn,pendimn,
[0114] Where id i Identification information for identifiable items, o i This is the personal information that can identify the project leader. i is the overall size of the project (usually measured in terms of workload), r i The resources invested in the project (usually the personal information of the identifiable participants), m i is the workflow node of the project, p starti and p endi They are the starting interval and ending interval of the node or resource respectively.
[0115] When the agent is started for the first time, it will start the full transfer mode and transfer the historical project information stored in the server to the receiving module of the background server in batches; then it will monitor the data changes on the server, and when the data changes, it will transfer the incremental data of the changes to the background server module.
[0116] The background receiving module receives S for the first time i After that, create node o i , the value is the chain data block L oi The tree data structure of where p oi Used to store personnel heat variables, the initial value is 0; the construction node is id i , the value is o i , w i , R i , M i The tree data structure of Construct horizontal nodes as ri and vertical nodes as dates to establish a graphical data structure Where P ri Used to store personnel heat variables, the initial value is 0. i When there are repeated nodes, P ri Assign the value to the total number of repetitions. To improve the processing efficiency of the risk prevention and control processing module, the data is stored in the high-speed storage module A; iFor incremental data caused by changes, according to o i ,id i 、r i As a node identifier, T o 、T id , H r Expand or refresh; after updating, store the data in high-speed storage module A; and store it in the database for data persistence and disaster recovery backup.
[0117] The product warehouse and behavior record processing module are deployed in the background server cluster. By integrating the product warehouse and the client of the electronic flow tool, the ledgers and process records of project-related personnel are synchronized and sent to the background receiving module. Among them, the product warehouse archives the project-related source code, components, various manuals, reports and other materials and deliverables, and the process records are based on m i , record each node in detail, responsible for r i The workflow between modules is transferred; the relevant data is stored in the background receiving module and saved to the cache module for access by other modules. The specific steps of data interaction are as follows:
[0118] The backend receiving module synchronizes the operation record S′ of the project deliverables from the integrated product warehouse client i ={id′ i , r′ i , t′ i}, where id′ i is the identification information of the identifiable item, r′ i is the resource of the deliverable on the account (usually the personal information of the identifiable participant), t′ i It is the time point of the ledger flow (the time period when the participants actually participated). During the first synchronization, the receiving module establishes a node with id' i , the value is the chain data block L′ id′i The tree data structure:
[0119]
[0120] If there are changes in the project deliverables, add T′ id′ Node, or append the corresponding L′ id′i node.
[0121] The backend receiving module synchronizes the electronic flow records from the integrated electronic flow tool client:
[0122] S″ i ={id″ i , F i},(F i ={{m″ i1 , r″ i1 , t″arri1 , t″ sndi1}, ... {m`` in , r`` i n, t`` arrin , t`` sndin}})
[0123] Where id '' i is the identification information of the identifiable item, m′′ i For the workflow node of the project, t`` arri and t″ sndi are the arrival and exit time points of the node respectively. During the first synchronization, the receiving module establishes the node as id" i , the value is chain data block L″ id″i The tree data structure:
[0124]
[0125] In order to improve the processing efficiency of the risk prevention and control processing module, the data is stored in the high-speed storage module; and in the event of changes in the project deliverables, a new T″ id″ Node, or append the corresponding L″ id″i nodes; and stored in the database for data persistence and disaster recovery backup.
[0126] The risk prevention and control processing module is deployed in the background server cluster, integrating project information data, warehouse ledger data, and electronic workflow data, evaluating the progress of projects and resources, and conducting risk prevention and control by establishing an integrity defense line and a sub-health list. The specific steps are as follows:
[0127] The risk prevention and control processing module obtains H from the project information processing module r According to H r Medium ri The height of the impact sample T pre , which is a tree data structure:
[0128]
[0129] According to the prevention and control requirements, project samples (i.e. project data) can be drawn in proportion to identify project risks, or all project samples can be identified. The defense line density coefficient α can be set according to the project situation. pre’ (α pre ∈[0,1]), sample redundancy parameter γ pre’ (γ pre ∈[0,1]), forming a sub-health control list, which is a chain data structure (i.e., information of participants in planned risk projects)
[0130]
[0131] The L pre It is used to characterize the information of participants in the planned risk projects mentioned above, which can also be called the sub-healthy project control list of resource overload. pre , the prevention and control tends to be strict, and vice versa. If resources are reused, it is necessary to adjust γ pre Make corrections.
[0132] According to T id Medium R i , forming the impact sample T′ pre , which is a tree structure:
[0133]
[0134] According to the prevention and control requirements, samples can be drawn in proportion. In this embodiment, the full amount of samples can be taken; combined with the project situation, the defense line density coefficient α′ is set pre’ (α′ pre ∈[0,1]), sample cost elasticity parameter γ′ pre’ (γ′ pre ∈[0,1]), forming a sub-health control list, that is, the planned risk project information, the list is a chain data structure (planned risk project information)
[0135]
[0136] It can be seen that reducing α′ pre , the prevention and control tends to be strict, and vice versa. If the project resources are not in place and there is scalability, it is necessary to adjust γ′ pre Correction, L′ pre It is a control list of sub-health projects with abnormal planning time logic, that is, the planning risk project information mentioned above.
[0137] The risk prevention and control processing module obtains T′ from the product warehouse and behavior record processing module id′ and T″ id″ Equivalent data structures, according to T′ id′ Medium r′ i and t′ in , extract r′ i The corresponding L′ id′i The maximum value forms an impact sample with a tree structure:
[0138]
[0139] Samples can be drawn in proportion according to the prevention and control requirements, but in order to ensure the temporal logic coherence of the sample selection data, id i For dimensions, you cannot use r iIn this embodiment, the full sample is used; according to the project situation, the defense line density coefficient α is set opt’ (α opt ∈[0,1]), sample delivery density coefficient δ opt’ (γ opt ∈0,1, forming a sub-health control list, which is a chain data structure (i.e., time deviation item information):
[0140]
[0141] It can be seen that reducing α opt , the control tends to be strict, and vice versa. If the delivered items do not change frequently, it is necessary to adjust δ opt Make corrections, L opt A control list of sub-health projects with abnormal resource investment, namely the time deviation project information mentioned above.
[0142] According to T`` id`` Chinese in , r″ in , t″ arrin , t″ sndin , forming an impact sample with a tree structure:
[0143]
[0144] Samples can be drawn in proportion according to the prevention and control requirements, but in order to ensure the temporal logic coherence of the sample selection data, id i or m i For dimensions, you cannot use r i In this embodiment, the full sample is used; according to the project situation, the defense line density coefficient α′ is set opt’ (α′ opt ∈[0,1]), sample plan elasticity parameter θ′ opt’ (θ′ opt ∈[0,1]), forming a sub-health control list, which is a chain data structure: (actual resource deviation item information)
[0145]
[0146] It can be seen that reducing α′ opt , the control tends to be strict, and vice versa. If the delivery cycle is flexible, it is necessary to adjust δ′ opt Correction, L′ opt It is a control list of sub-healthy projects with abnormal execution time logic, namely the actual resource deviation project information mentioned above.
[0147] The risk prevention and control processing module obtains T from the project information processing module oData structure, according to L pre , L′ pre , L opt , L′ opt If there is a situation in the project, the project heat is calculated as follows:
[0148]
[0149] where q pren ,q′ pren ,q optn ,q′ optn is the weight coefficient of each data structure, which can be adjusted according to the weight of each defense line model in the whole. In this embodiment, the weight of each defense line model in prevention and control can be calculated as a percentage. Combined with the project situation, when the weight coefficient is a percentage, set the defense line density coefficient α post’ (α post ∈[0,1]), set the service tolerance coefficient μ post’ (μ post ∈[0, 1]), forming a sub-health control list, which is a chain data structure:
[0150]
[0151] It can be seen that reducing a′ opt , the prevention and control tends to be strict, and vice versa. When there are special circumstances in the business areas involved in each project, it is necessary to adjust μ post To make corrections, you can set μ for the project. post , you can also create multiple control lists, L post A control list that aggregates sub-health project indicators, which contains information on projects with higher risks.
[0152] Can be T o p o Update as follows:
[0153]
[0154] Form a control list, which is a chain data structure L o :
[0155]
[0156] L o Gather relevant personnel control lists for sub-health project indicators.
[0157] The display and alarm module is deployed in the background server cluster and the front-end project management server. It is used to display various prevention and control lists, red and black lists and other risk prevention and control results. For projects with possible integrity risks, relevant supervisors and responsible persons are informed in a timely manner through SMS, email and other means. Among them, in the background server cluster, various control lists are loaded mainly through data synchronization components, and then the lists are aggregated and implemented; in the front-end project management server, human-computer interaction with relevant personnel is mainly carried out through web pages, SMS and email services. The specific steps are as follows:
[0158] The display and warning module combines risk prevention and control requirements to form black, white and gray lists and red and black lists for multiple protections, such as id All items in the white control list are included in the white control list w After the project is launched, it appears in L pre , L′ pre , L opt , L′ opt If the g , while from L w After the project is delivered, there are still post In the black control list b , while from L w , L g The same is true for L o According to p oi Sort in descending order and take the top n names to form the blacklist L b , for T o and L o The difference is listed in the red list r , store all lists and lists in the database for data persistence and disaster recovery backup.
[0159] Display and alarm module front-end web service, load blacklist from database b And the red list L r etc. data for display; SMS and email services load L from the database g , associated with T o The person in charge logo in i , issue early warnings for possible prevention and control risks, assist relevant personnel in initiating avoidance and rectification work for related risks and problems, and ensure the timely implementation of integrity prevention and control work.
[0160] This embodiment may include a project information processing module, a product warehouse and behavior record processing module, a risk prevention and control processing module, and a display and alarm module. The project information processing module can monitor project data changes through a front-end agent, and return the project's resources, plans, links and other data in full or incrementally through the tree structure and graph structure of the nested data chain; the product warehouse and behavior record processing module can synchronize the ledgers and process records of project-related personnel, source code components and other products and deliverables through the client that integrates the product warehouse and electronic flow tools; the risk prevention and control processing module establishes a defense line system by building a sample model, analyzing resource usage, time logic and other diagnostic methods, and realizing integrity risk prevention and control; the display and alarm module establishes a human-machine port through web pages, SMS and email services, realizes the transformation of various prevention and control lists, red and black lists and other integrity risk prevention and control results, warns of possible integrity prevention and control risks, assists relevant personnel in initiating avoidance and rectification work for related risks and problems, and ensures the timely implementation of integrity prevention and control work.
[0161] This embodiment is also based on the tree structure, graph structure, weight coefficient, density coefficient, tolerance coefficient, elasticity parameter, project, personnel popularity, etc., by aggregating data on the resources and time logic of the project, establishing an impact sample, and optimizing the statistical project feature data through variables such as weight coefficients in the sample; in accordance with the integrity prevention and control mechanism, a three-layer, two-dimensional, six-line defense system is established, and density coefficients, tolerance coefficients, elasticity parameters, etc. are set to be compatible with the impact of objective factors such as resource reuse, overload, delay, and plan deviation, so as to achieve accurate identification of sub-health data and form an objective, sufficient, accurate and complete prevention and control list.
[0162] This embodiment achieves the effective integration of project process and integrity prevention and control mechanism by accessing project data, personnel ledgers, behavior records and other data. It combines impact samples, integrity defense lines, and balance parameters to effectively ensure the objectivity of the final prevention and control list. In addition to the data types mentioned in this embodiment, other data type information can also be integrated, such as personnel sign-in records, number of lines of code, number of words in deliverables, product storage space, etc., to improve data accuracy and purity.
[0163] Reference Figure 6 , Figure 6 This is a structural block diagram of the first embodiment of the project risk identification device of the present invention.
[0164] like Figure 6 As shown, the project risk identification device proposed in the embodiment of the present invention includes:
[0165] The acquisition module 10 is used to acquire project plan information and project actual execution information;
[0166] A calculation module 20, for determining the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information according to the project plan information and the project actual execution information;
[0167] A project heat determination module 30, configured to determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information;
[0168] The project risk identification result generating module 40 is used to generate a project risk identification result according to the project heat.
[0169] This embodiment obtains project planning information and project actual execution information; determines the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on the project planning information and the project actual execution information; determines the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information; generates a project risk identification result based on the project heat. Since this embodiment determines the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information based on the project planning information and the project actual execution information, and then determines the project risk identification result. This solves the technical problem in the related technology that it is difficult to identify specific risk scenarios in the project production and operation process, resulting in low efficiency in project risk identification.
[0170] It should be noted that the workflow described above is merely illustrative and does not limit the scope of protection of the present invention. In practical applications, technicians in this field can select part or all of them according to actual needs to achieve the purpose of the present embodiment, and no limitation is made here.
[0171] In addition, for technical details that are not described in detail in this embodiment, reference can be made to the project risk identification method provided in any embodiment of the present invention, and will not be repeated here.
[0172] Based on the above-mentioned first embodiment of the project risk identification device of the present invention, a second embodiment of the project risk identification device of the present invention is proposed.
[0173] In this embodiment, the calculation module 20 is further used to determine the planned risk project participant information and the planned risk project information according to the project plan information;
[0174] The time deviation project information and the actual resource deviation project information are determined according to the actual execution information of the project.
[0175] Furthermore, the calculation module 20 is also used to determine project personnel information according to the project plan information;
[0176] Determine the work area information and the popularity of the project personnel according to the project personnel information;
[0177] Based on the work interval information and the project personnel enthusiasm, the planned risk project participant information is determined by a preset first algorithm;
[0178] The planned risk project information is determined according to the project personnel information by using a preset second algorithm.
[0179] Furthermore, the calculation module 20 is also used to determine the information of the actual executor of the project according to the actual execution information of the project;
[0180] Determine the time deviation project information based on the information of the actual executors of the project;
[0181] The actual resource deviation project information is determined according to the actual execution information of the project.
[0182] Furthermore, the calculation module 20 is further used to compare the project heat with a preset project heat threshold to obtain a comparison result;
[0183] When the comparison result is that the project heat is greater than the preset project heat threshold, it is determined that the target project corresponding to the project heat has project risk.
[0184] Furthermore, the project risk identification result generating module 40 is also used to determine the project leader information corresponding to the target project;
[0185] Determine the risk project information corresponding to the project leader according to the project leader information;
[0186] A risk identification result for the project manager is generated based on the risk project information.
[0187] Furthermore, the acquisition module 10 is also used to collect project plan data and store the project plan data as serialized structure data;
[0188] Determine project plan information according to the serialized structure data;
[0189] Collecting actual execution data of the project, and constructing tree structure data according to the actual execution data of the project;
[0190] The actual execution information of the project is determined according to the tree structure data.
[0191] Other embodiments or specific implementations of the project risk identification device of the present invention can refer to the above-mentioned method embodiments and will not be described in detail here.
[0192] In addition, an embodiment of the present invention further proposes a storage medium, on which a project risk identification program is stored. When the project risk identification program is executed by a processor, the steps of the project risk identification method described above are implemented.
[0193] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or system including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or system. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or system including the element.
[0194] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0195] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course can also be implemented by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present invention, or the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium (such as a read-only memory / random access memory, a magnetic disk, or an optical disk), and includes a number of instructions for a terminal device (which can be a mobile phone, a computer, a server, an air conditioner, or a network device, etc.) to execute the methods described in each embodiment of the present invention.
[0196] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A project risk identification method, characterized in that: The project risk identification method comprises the following steps: Obtain project plan information and project actual execution information; Determine the planned risk project participant information, planned risk project information, time deviation project information and actual resource deviation project information according to the project plan information and the project actual execution information; Determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information, and the actual resource deviation project information; A project risk identification result is generated according to the project heat.
2. The project risk identification method according to claim 1, characterized in that: The step of determining the planned risk project participant information, planned risk project information, time deviation project information, and actual resource deviation project information according to the project plan information and the project actual execution information includes: Determine the planned risk project participant information and planned risk project information according to the project plan information; The time deviation project information and the actual resource deviation project information are determined according to the actual execution information of the project.
3. The project risk identification method according to claim 2, characterized in that: The step of determining the planned risk project participant information and the planned risk project information according to the project plan information includes: Determine project personnel information based on the project plan information; Determine the work area information and the popularity of the project personnel according to the project personnel information; Based on the work interval information and the project personnel enthusiasm, the planned risk project participant information is determined by a preset first algorithm; The planned risk project information is determined according to the project personnel information by using a preset second algorithm.
4. The project risk identification method according to claim 2, characterized in that: The step of determining the time deviation project information and the actual resource deviation project information according to the actual execution information of the project includes: Determine the information of the actual executors of the project based on the actual execution information of the project; Determine the time deviation project information based on the information of the actual executors of the project; The actual resource deviation project information is determined according to the actual execution information of the project.
5. The project risk identification method according to any one of claims 1 to 4, characterized in that: The step of generating a project risk identification result according to the project heat includes: Comparing the project heat with a preset project heat threshold to obtain a comparison result; When the comparison result is that the project heat is greater than the preset project heat threshold, it is determined that the target project corresponding to the project heat has project risk.
6. The project risk identification method according to claim 5, characterized in that: After the step of determining that the target project corresponding to the project heat has a project risk when the comparison result shows that the project heat is greater than the preset project heat threshold, the method further includes: Determine the project leader information corresponding to the target project; Determine the risk project information corresponding to the project leader according to the project leader information; A risk identification result for the project manager is generated based on the risk project information.
7. The project risk identification method according to any one of claims 1 to 4, characterized in that: The step of obtaining project plan information and project actual execution information includes: Collect project plan data, and store the project plan data as serialized structure data; Determine project plan information according to the serialized structure data; Collecting actual execution data of the project, and constructing tree structure data according to the actual execution data of the project; The actual execution information of the project is determined according to the tree structure data.
8. A project risk identification device, characterized in that: The project risk identification device comprises: The acquisition module is used to obtain project plan information and project actual execution information; A calculation module, used to determine the planned risk project participant information, planned risk project information, time deviation project information and actual resource deviation project information according to the project plan information and the project actual execution information; A project heat determination module, used to determine the project heat based on the planned risk project participant information, the planned risk project information, the time deviation project information and the actual resource deviation project information; The project risk identification result generation module is used to generate a project risk identification result according to the project heat.
9. A project risk identification device, characterized in that: The device comprises: a memory, a processor, and a project risk identification program stored in the memory and executable on the processor, wherein the project risk identification program is configured to implement the steps of the project risk identification method according to any one of claims 1 to 7.
10. A storage medium, characterized in that: The storage medium stores a project risk identification program, and when the project risk identification program is executed by the processor, the steps of the project risk identification method according to any one of claims 1 to 7 are implemented.