Container port crane energy consumption management and prediction method and medium thereof
Through the energy consumption management and prediction methods of container port cranes, combined with changes in box volume and box shape, accurate analysis and prediction of energy consumption at different stages is achieved, and the problems of energy consumption statistical deviation and high-cost hardware installation in the existing technology are solved. , reducing energy consumption and operating costs.
Patent Information
- Application Number
- CN202410949106.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-11-08
AI Technical Summary
The existing energy consumption statistical methods for cranes at container ports fail to effectively analyze the energy consumption in the standby stage, resulting in energy consumption prediction deviations. The equipment hardware installation cost is high, so differentiated energy consumption analysis cannot be achieved.
A method for energy consumption management and prediction of container port cranes is proposed. By collecting operation data and energy consumption data, fitting and amortizing energy consumption, correcting actual energy consumption, and performing differentiated analysis, combining box volume and box shape changes, predicting the future Energy consumption.
Accurate analysis and prediction of the energy consumption of container port cranes at different stages has been achieved, which reduces energy consumption, reduces operating costs, and improves the accuracy and efficiency of energy consumption management.
Smart Images

Figure CN118917527A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of energy management of port cranes, and in particular to an energy consumption management and prediction method of a container port crane and a medium thereof. Background Art
[0002] As an important logistics hub and economic node, container ports have a huge energy consumption status. Large-scale quay cranes, gantry cranes and other loading and unloading equipment, large freight vehicles and lighting facilities in the port area all require a lot of energy to support their normal operation. However, with the continuous changes in the global energy situation and the enhancement of environmental protection awareness, the problem of excessive energy consumption in container ports has become increasingly prominent.
[0003] It is of great significance for container ports to implement energy management. Energy conservation can not only reduce the operating costs of container ports and improve profitability, but also reduce dependence on traditional energy resources and enhance the stability of energy supply; by reducing environmental pollution and carbon emissions, container ports can fulfill their corporate social responsibility and promote green and sustainable development; implementing energy conservation measures can also help improve the logistics efficiency and service level of container ports and enhance their competitiveness in the global supply chain.
[0004] The energy consumption of container port cranes can be divided into the operating stage and the standby stage according to the operation stage. The operating stage mainly refers to the hoisting stage of the crane, which is the actual operating stage of the crane and also the main stage of energy consumption; the standby stage mainly refers to other operating stages except the hoisting stage, including the control off stage (i.e. the unstarted state), the static stage (i.e. the start-up but not operating stage), and the scheduling stage (i.e. the crane non-operating mechanism operation stage). The standby stage is a secondary stage of energy consumption. The existing statistical analysis methods for energy consumption of container port cranes mainly focus on the energy consumption in the operating stage, or directly use the overall energy consumption to judge the energy consumption level of the port, without detailed analysis of the actual energy consumption structure or stage of the port, which is mainly manifested in the following aspects:
[0005] 1) The existing statistical methods for energy consumption of container port cranes mainly focus on the energy consumption in the operation phase, and do not include the energy consumption in the standby phase into the actual energy consumption of container port cranes. Therefore, deviations are prone to occur when analyzing the actual energy consumption of container port cranes;
[0006] 2) Directly dividing the energy consumption data by the operating container volume data to obtain the energy consumption per unit volume of container port crane operations cannot effectively determine the operating energy consumption level of the crane;
[0007] 3) Install an energy meter or other related hardware on the equipment side. Although this method can directly count the energy consumption of each link of the equipment, the hardware cost, transformation cost, and related data transmission cost are high;
[0008] 4) The energy consumption in the standby phase is not taken into account comprehensively, and the proportion of energy consumption in the operating phase and the standby phase cannot be analyzed, so the actual energy consumption level of port cranes cannot be predicted. Summary of the invention
[0009] In view of this, it is necessary to propose an energy consumption management and prediction method and medium for container port cranes to address the above problems, so as to overcome several shortcomings of the above background technology and solve the following technical problems:
[0010] How to conduct differentiated and accurate energy consumption analysis and predict future energy consumption of container port cranes at different stages based on changes in the volume and type of port containers.
[0011] To achieve the above object, the present invention adopts the following technical solutions:
[0012] The present invention proposes a method for managing and predicting energy consumption of a container port crane, comprising the following steps S1-S5 executed in sequence:
[0013] S1, collecting operation data and energy consumption data of container port cranes; the operation data includes the number of empty containers of different types lifted by the container port cranes and the number of loaded containers of different types lifted by the container port cranes; the energy consumption data includes the energy consumption value of each container port crane corresponding to the operation data;
[0014] S2, fitting the energy consumption of the container port crane corresponding to different types of containers by using the operation data and energy consumption data obtained in S1;
[0015] S3, performing data correction by using the fitted shared energy consumption obtained in S2, thereby obtaining the corrected actual shared energy consumption corresponding to different types of containers of the container port crane;
[0016] S4, performing energy difference analysis on the fitted shared energy consumption obtained in S2 and the actual shared energy consumption obtained in S3, so as to obtain a differential analysis calibration parameter;
[0017] S5, obtaining energy consumption prediction analysis results according to the number of containers of different types obtained in S1, the actual allocated energy consumption obtained in S3, and the differential analysis calibration parameters obtained in S4.
[0018] Furthermore, after S5, the container port crane energy consumption management and prediction method also includes: S6, judging whether the deviation value between the actual energy consumption value of the container port crane and the predicted energy consumption value of the energy consumption prediction analysis result obtained in S5 is greater than a threshold value, if it is judged to be yes, executing S4, if it is judged to be no, the energy consumption prediction analysis result obtained in S5 is used as the final prediction result.
[0019] Further, S2 includes the following sub-steps S21-S22 executed in sequence:
[0020] S21, according to the power and torque relationship of the crane T = 9550P / n, the torque formula T = ml and the energy consumption formula Q = Pt, obtain the energy consumption and weight relationship, that is, the linear function Q = km + b about energy consumption and weight, wherein k and b of the linear function are constants, Q is the energy consumption of the crane, t is the working time of the crane, and m is the weight of the container lifted by the crane; wherein T in the torque relationship is the torque of the crane, P is the motor power of the crane, and n is the motor speed of the crane;
[0021] S22, obtain the weight of each hoist of empty boxes of different types of cranes and the weight of each hoist of different types of loaded boxes, substitute the obtained weight of each hoist into the linear function Q=km+b, and use two sets of data on energy consumption and weight to jointly solve the values of constants k and constants b.
[0022] Further, S22 includes the following sub-steps S221-S223 executed in sequence:
[0023] S221, according to the container type and weight, obtain the total weight of the container port crane operation;
[0024] S222, obtaining the weight of each lifting operation of the container port crane according to the equipment type of the crane;
[0025] S223, establishing a linear function Q=km+b through the operation data and the energy consumption data, and solving for constants k and b;
[0026] In S3, the simulated allocated unit consumption of container port cranes corresponding to different container types is obtained through constants k and b.
[0027] Furthermore, in S221, the weight of each container in the operation is counted, and the total weight of the empty container in the crane operation and the total weight of the loaded container in the crane operation are accumulated to obtain the following:
[0028] The total weight of the empty container for crane operation is m 空 =∑U 空j *m 空j Formula (1);
[0029] The total weight of the crane operation box is m 重 =∑U 重j *m 重j Formula (2);
[0030] In formula (1), m 空 is the total weight of the empty containers in crane operation, i.e. the total weight of the empty containers, m 空jFor the enumeration of the weight of various empty containers, U 空j The number of empty boxes of each type corresponding to the empty box weight;
[0031] In formula (2), m 重 is the total weight of the crane operation load box, that is, the sum of the weight of the load boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes for each type of corresponding heavy box weight.
[0032] Further, in S222, for a crane that operates only one container per crane, the average weight of each crane is the total weight of the containers divided by the total number of containers, that is,
[0033] The weight of each empty container is
[0034] The weight of each heavy box is
[0035] The cranes corresponding to formula (3) and formula (4) are container port cranes corresponding to single-box operations;
[0036] In formula (3), m 空吊 The empty container weight per hang, m 空 is the total weight of the empty containers, m 空j For the enumeration of the weight of various empty containers, U 空j is the number of empty boxes of each type of corresponding empty box weight; in formula (4), m 重吊 is the weight of each heavy box, m 重 is the total weight of the heavy boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes corresponding to the heavy box weight of each type;
[0037] In S222, for a port container crane that operates two or four containers, that is, the container port crane can load and unload n containers (n = 1, 2, 3, 4) at a time, the total number of lifts is the number of single containers in each type of container plus the number of double containers divided by n. The ratio of the number of n containers in one operation to the total number of operations is set to β, that is, the mathematical expression of the weight of each lift is:
[0038]
[0039] When β is 0, formula (5) is the same as formula (3) or formula (4) per hanging weight;
[0040] In formula (5), m 吊 is the weight of each crane lift, i is defined as an empty container or a loaded container, j is defined as the container type of different sizes, ∑U ij *m ij is the total weight of all types of containers in operation, n吊 is the total number of operations, ∑U ij is the total amount of work corresponding to i and j.
[0041] Further, in S223, according to the linear relationship between the energy consumption of container port cranes and the weight per crane,
[0042] The energy consumption of the crane with empty box is Q 空 =∑U 空j *(k*m 空吊 + b) = ∑U 空j *b+k*∑U 空j *m 空j Formula (6)
[0043] The energy consumption of the crane load box is Q 重 =∑U 重j *(k*m 重吊 + b) = ∑U 重j *b+k*∑U 重j *m 重j Formula (7)
[0044] The total energy consumption Q = Q 空 +Q 重 Formula (8)
[0045] Solve the k and b values based on multiple sets of statistical period data, and substitute the k and b values into the linear function Q ij =km ij + b can be used to obtain the actual unit energy consumption of the corresponding container type related to the crane operation in the container port.
[0046] Further, in S4,
[0047] When the total energy consumption Q of the fitting allocation is less than the statistical energy consumption Q 实际 When the energy consumption of a single box is apportioned, the box weight is used to simulate the operation, and the energy consumption of each box type in the non-operation stage is obtained according to the ratio of empty boxes to full boxes and the ratio of different box types in empty boxes and full boxes.
[0048] When the total energy consumption Q of the fitting distribution is equal to the statistical energy consumption Q 实际 That is, the changes in box quantity and box type in different stages are normal.
[0049] Furthermore, the energy consumption of container port cranes includes the energy consumption of front equipment, the energy consumption of yard equipment, and the energy consumption of translational transport equipment;
[0050] In S4, the energy consumption data in the future can be obtained by multiplying the different types of container volumes of various types of container port crane operations by the operating energy consumption of each type of container in the future. The mathematical expression of the energy consumption data is:
[0051] Q 港口 =∑∑U ij Q ij Formula (9)
[0052] In formula (9), Q 港口 The sum of the energy consumption of the equipment in the loading and unloading process, ∑U ij Q ij Statistical data for energy consumption of a single type of equipment during a period of operation.
[0053] The present invention further proposes a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method for energy consumption management and prediction of container port cranes as described in any one of the above items are implemented.
[0054] The beneficial effects of the present invention are:
[0055] The present invention can perform differentiated and accurate energy consumption analysis and predict future energy consumption of container port cranes in different stages according to the changes in the quantity and type of port containers, thereby saving energy and reducing the operating costs of container ports; the present invention deconstructs the energy consumption of port container cranes, reasonably allocates the standby energy consumption, and calculates the practical energy consumption of different types of containers of port container cranes, which helps to analyze the reasons for energy consumption changes, and analyzes the reasons for energy consumption increases or decreases through changes in operating box types and quantities. It can also select reasonable parameter values according to the operating box quantity in a period of time in the future, and more accurately predict and analyze the energy consumption in this period of time. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] Figure 1 This is a workflow diagram of an energy consumption management and prediction method for a container port crane in Example 2 of the present invention. DETAILED DESCRIPTION
[0057] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be further clearly and completely described in combination with the embodiments of the present invention. It should be noted that the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0058] It should be understood that the directions or positional relationships indicated by terms such as "upper", "lower", "front", "back", "left", and "right" are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limitations on the present invention.
[0059] The terms "first", "second", "third", "fourth", etc. are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the definition of "first", "second", "third", "fourth" features may explicitly or implicitly include one or more of the features.
[0060] Example 1
[0061] This embodiment proposes a method for managing and predicting energy consumption of a container port crane, comprising the following steps S1-S5 executed in sequence:
[0062] S1, collecting operation data and energy consumption data of container port cranes; the operation data includes the number of empty containers of different types lifted by the container port cranes and the number of loaded containers of different types lifted by the container port cranes; the energy consumption data includes the energy consumption value of each container port crane corresponding to the operation data;
[0063] S2, fitting the energy consumption of the container port crane corresponding to different types of containers by using the operation data and energy consumption data obtained in S1;
[0064] S3, performing data correction by using the fitted shared energy consumption obtained in S2, thereby obtaining the corrected actual shared energy consumption corresponding to different types of containers of the container port crane;
[0065] S4, performing energy difference analysis on the fitted shared energy consumption obtained in S2 and the actual shared energy consumption obtained in S3, so as to obtain a differential analysis calibration parameter;
[0066] S5, obtaining energy consumption prediction analysis results according to the number of containers of different types obtained in S1, the actual allocated energy consumption obtained in S3, and the differential analysis calibration parameters obtained in S4.
[0067] Specifically, the energy consumption data includes the data in the following Table 1:
[0068]
[0069] Table 1
[0070] Example 2
[0071] like Figure 1 As shown:
[0072] This embodiment proposes a method for managing and predicting energy consumption of a container port crane, comprising the following steps S1-S6 executed in sequence:
[0073] S1, collecting operation data and energy consumption data of container port cranes; the operation data includes the number of empty containers of different types lifted by the container port cranes and the number of loaded containers of different types lifted by the container port cranes; the energy consumption data includes the energy consumption value of each container port crane corresponding to the operation data;
[0074] S2, fitting the energy consumption of the container port crane corresponding to different types of containers by using the operation data and energy consumption data obtained in S1;
[0075] S3, performing data correction by using the fitted shared energy consumption obtained in S2, thereby obtaining the corrected actual shared energy consumption corresponding to different types of containers of the container port crane;
[0076] S4, performing energy difference analysis on the fitted shared energy consumption obtained in S2 and the actual shared energy consumption obtained in S3, so as to obtain a differential analysis calibration parameter;
[0077] S5, obtaining energy consumption prediction analysis results according to the number of containers of different types obtained in S1, the actual allocated energy consumption obtained in S3, and the differential analysis calibration parameters obtained in S4;
[0078] S6, judging whether the deviation between the actual energy consumption value of the container port crane and the predicted energy consumption value of the energy consumption prediction analysis result obtained in S5 is greater than a threshold value, if it is judged to be yes, executing S4, if it is judged to be no, taking the energy consumption prediction analysis result obtained in S5 as the final prediction result.
[0079] Example 3
[0080] Embodiment 3 is a further optimization scheme of Embodiment 1 or Embodiment 2;
[0081] S2 includes the following sub-steps S21-S22 executed in sequence:
[0082] S21, according to the power and torque relationship of the crane T = 9550P / n, the torque formula T = ml and the energy consumption formula Q = Pt, obtain the energy consumption and weight relationship, that is, the linear function Q = km + b about energy consumption and weight, wherein k and b of the linear function are constants, Q is the energy consumption of the crane, t is the working time of the crane, and m is the weight of the container lifted by the crane; wherein T in the torque relationship is the torque of the crane, P is the motor power of the crane, and n is the motor speed of the crane;
[0083] S22, obtain the weight of each hoist of empty boxes of different types of cranes and the weight of each hoist of different types of loaded boxes, substitute the obtained weight of each hoist into the linear function Q=km+b, and use two sets of data on energy consumption and weight to jointly solve the values of constants k and constants b.
[0084] Further optimized, S22 includes the following sub-steps S221-S223 executed in sequence:
[0085] S221, according to the container type and weight, obtain the total weight of the container port crane operation;
[0086] S222, obtaining the weight of each lifting operation of the container port crane according to the equipment type of the crane;
[0087] S223, establishing a linear function Q=km+b through the operation data and the energy consumption data, and solving for constants k and b;
[0088] In S3, the simulated allocated unit consumption of container port cranes corresponding to different container types is obtained through constants k and b.
[0089] Further optimized, in S221, the weight of each container in the operation is counted, and the total weight of the empty container in the crane operation and the total weight of the loaded container in the crane operation are accumulated to obtain as follows:
[0090] The total weight of the empty container for crane operation is m 空 =∑U 空j *m 空j Formula (1);
[0091] The total weight of the crane operation box is m 重 =∑U 重j *m 重j Formula (2);
[0092] In formula (1), m 空 is the total weight of the empty containers in crane operation, i.e. the total weight of the empty containers, m 空j For the enumeration of the weight of various empty containers, U 空j The number of empty boxes of each type corresponding to the empty box weight;
[0093] In formula (2), m 重 is the total weight of the crane operation load box, that is, the sum of the weight of the load boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes for each type of corresponding heavy box weight.
[0094] Further optimized, in S222, for a crane that only operates one container per crane, the average weight of each crane is the total weight of the containers (i.e., the total mass) divided by the total number of containers, i.e.
[0095] The weight of each empty container is
[0096] The weight of each heavy box is
[0097] The cranes corresponding to formula (3) and formula (4) are container port cranes corresponding to single-box operations;
[0098] In formula (3), m 空吊 The empty container weight per hang, m 空 is the total weight of the empty containers, m 空j For the enumeration of the weight of various empty containers, U 空j is the number of empty boxes of each type of corresponding empty box weight; in formula (4), m 重吊 is the weight of each heavy box, m 重 is the total weight of the heavy boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes corresponding to the heavy box weight of each type;
[0099] In S222, for a port container crane that operates two or four containers, that is, the container port crane can load and unload n containers (n = 1, 2, 3, 4) at a time, the total number of lifts is the number of single containers in each type of container plus the number of double containers divided by n. The ratio of the number of n containers in one operation to the total number of operations is set to β, that is, the mathematical expression of the weight of each lift is:
[0100]
[0101] When β is 0, formula (5) is the same as formula (3) or formula (4) per hanging weight;
[0102] In formula (5), m 吊 is the weight of each crane lift, i is defined as an empty container or a loaded container, j is defined as the container type of different sizes, ∑U ij *m ij is the total weight of all types of containers in operation, n 吊 is the total number of operations, ∑U ij is the total amount of work corresponding to i and j.
[0103] Further optimized, in S223, according to the linear relationship between the energy consumption of container port cranes and the weight per crane,
[0104] The energy consumption of the crane with empty box is Q 空 =∑U 空j *(k*m 空吊 + b) = ∑U 空j *b+k*∑U 空j *m空j Formula (6)
[0105] The energy consumption of the crane load box is Q 重 =∑U 重j *(k*m 重吊 + b) = ∑U 重j *b+k*∑U 重j *m 重j Formula (7)
[0106] The total energy consumption Q = Q 空 +Q 重 Formula (8)
[0107] Solve the k and b values based on multiple sets of statistical period data, and substitute the k and b values into the linear function Q ij =km ij + b can be used to obtain the actual unit energy consumption of the corresponding container type related to the crane operation in the container port.
[0108] Further optimized, in S4,
[0109] When the total energy consumption Q of the fitting allocation is less than the statistical energy consumption Q 实际 When the energy consumption of a single box is apportioned, the box weight is used to simulate the operation, and the energy consumption of each box type in the non-operation stage is obtained according to the ratio of empty boxes to full boxes and the ratio of different box types in empty boxes and full boxes.
[0110] When the total energy consumption Q of the fitting distribution is equal to the statistical energy consumption Q 实际 That is, the changes in box quantity and box type in different stages are normal.
[0111] Furthermore, the energy consumption of container port cranes includes the energy consumption of front equipment, the energy consumption of yard equipment, and the energy consumption of translational transport equipment;
[0112] In S4, the energy consumption data in the future can be obtained by multiplying the different types of container volumes of various types of container port crane operations by the operating energy consumption of each type of container in the future. The mathematical expression of the energy consumption data is:
[0113] Q 港口 =∑∑U ij Q ij Formula (9)
[0114] In formula (9), Q 港口 The sum of the energy consumption of the equipment in the loading and unloading process, ∑U ij Q ij Statistical data for energy consumption of a single type of equipment during a period of operation.
[0115] Example 4
[0116] Embodiment 4 is a further optimized technical solution of Embodiment 3;
[0117] In S1, the weight of an empty container is generally a fixed value; however, due to the different cargoes loaded in a heavy container, the weight of each container has certain differences. However, when the cargo is fixed, the weight of the heavy container is not much different. For the convenience of statistics, our port currently uses simulated container weight, that is, a 20-foot heavy container is 23 tons, and a 40-foot and 45-foot heavy container is uniformly 27 tons. The method of the present invention only needs to collect the number of different container types within a certain period of time, the corresponding total energy consumption value, and the simulated container weight of each container type. If the simulated container weight of each container type is known or specified, then only the container quantity and energy consumption need to be collected to calculate the simulated unit consumption. In terms of energy consumption prediction, it is only necessary to understand the number of various container types to predict the total energy consumption value of the equipment;
[0118] In S5, energy consumption is simulated and allocated according to the container weight. Therefore, when the business structure of the container port changes (business changes cause changes in cargo types, and cargo types determine container weights. For example, containers filled with grain and fruits have certain differences in container weights even though the containers are also full), differences in the allocated unit consumption will appear. Therefore, it is necessary to adjust the parameters in time according to the differences so that the difference between the fitted allocated energy consumption obtained by S2 and the actual allocated energy consumption obtained by S3 is as small as possible. The smaller the difference, the more accurate the energy consumption results of the prediction analysis.
[0119] Example 5
[0120] Embodiment 5 is a further optimized technical solution of Embodiment 3;
[0121] In S21, the relationship between power, torque and speed is derived as follows:
[0122] Power = force * speed P = F * V --- Formula [1];
[0123] Torque (T) = torque (F) * radius of action (R) -----F = T / R - formula [2];
[0124] Linear speed (V) = 2πR*rotation per second (n seconds) = 2πR*rotation per minute (n minutes) / 60 = πR*n minutes / 30 -------Formula [3];
[0125] Substituting formulas [2] and [3] into formula [1], we get:
[0126] P=F*V=T / R*πR*nmin / 30=π / 30*T*nmin-----P=power unit W, T=torque unit Nm, nmin=speed per minute unit rpm
[0127] If the unit of P is changed to KW, then the formula is as follows:
[0128] P*1000=π / 30*T*n;
[0129] 30000 / π*P=T*n;
[0130] 30000 / 3.1415926*P=T*n;
[0131] 9549.297*P=T*n;
[0132] Therefore, 9550 is generally taken as a constant in the motor torque calculation formula;
[0133] The derivation of this embodiment is only to prove that energy consumption and weight are generally in a linear relationship. It does not specify which motor is used. All mechanisms of the port crane are powered by motors. For a single mechanism, there is a k i and b i (i is a single motor), then k = ∑k i , b=∑b i .
[0134] Example 6
[0135] Embodiment 6 is a further optimized technical solution of Embodiment 3;
[0136] In S221, the total weight of the empty boxes in operation is equal to the number of empty boxes of each type multiplied by the total weight of the empty boxes of that type, where j = 20 feet, 40 feet, 45 feet, which can be expanded to be:
[0137] m 空 =U 空20尺 *m 空20尺 +U 空40尺 *m 空40尺 +U 空45尺 *m 空45尺
[0138] That is, the total weight of the empty container is equal to the sum of the number of empty 20-foot containers multiplied by the single weight of an empty 20-foot container, the number of empty 40-foot containers multiplied by the single weight of an empty 40-foot container, and the number of empty 45-foot containers multiplied by the single weight of an empty 45-foot container. Formula (2) is the same as above for the heavy container.
[0139] In S222, each lifting weight is equal to the total weight divided by the number of operating lifts. For a crane that can only lift one container at a time, each lifting weight can be directly described as the total weight divided by the number of operating containers; however, some equipment types can operate 2 or 4 or even more (even number) containers at a time. However, due to the location restrictions of the ship, the entire ship will not always operate by lifting multiple containers at a time. There may also be a situation where one container is lifted at a time. Taking equipment that can lift 2 containers at a time as an example, the number of operating lifts is the number of lifts for lifting 2 containers plus the number of lifts for operating 1 container. Assuming that the total number of operating containers is n, where n1 is the amount of lifting of 1 container at a time, and n2 is the amount of lifting of 2 containers at a time, the number of lifts for lifting 1 container at a time is n1, and the number of lifts for lifting 2 containers at a time is n2 / 2, and the total number of lifts is n1+n2 / 2. The total weight of n containers is m, and the weight per lift is m / (n1+n2 / 2);
[0140]
[0141] Substituting into the above formula, the numerator is the total weight m, the amount of lifting 2 containers at a time accounts for β in the total workload, and n in the formula refers to the 2 containers lifted at a time.
[0142] In S223, k and b can be used to calculate the simulated shared unit consumption of different container types. For example, the empty 20-foot container is 2 tons, and the empty 40-foot / 45-foot container is 4 tons. The simulated shared unit consumption of the empty 20-foot container is 2k+b, and the simulated shared unit consumption of the empty 40-foot / 45-foot container is 4k+b. In general, the simulated shared unit consumption of lifting the container can be calculated by substituting any weight. Multiple groups of data refer to multiple statistical period data, such as various types of containers and operation energy consumption within the statistical period of day, week, month, and year. Solve the k and b values by simultaneous equations for any two groups of data.
[0143] Example 7
[0144] Embodiment 7 is a further optimized technical solution of Embodiment 3;
[0145] In S4, Q is the total value of the energy consumption of the fitting, the symbol of formula (8); Q 实际To count energy consumption, the energy consumption of meter reading within the statistical period is counted; this embodiment simulates the energy consumption of a single box operation by box weight. The actual operation process is different in different statistical periods. Taking the total number of operating boxes as an example, the energy consumption of port equipment within the statistical period includes the energy consumption of the operating stage and the energy consumption of the non-operating stage. The energy consumption of the operating stage refers to the energy consumption of the hoisting (lifting, trolley mechanism) operation, and the energy consumption of the non-operating stage refers to the energy consumption of the non-hoisting mechanism (trolley mechanism, pitch mechanism, auxiliary mechanism such as elevator, air conditioner, fan, etc.). When the workload is relatively large, The energy consumption in the operation phase accounts for a higher proportion, while the energy consumption in the non-operation phase accounts for a lower proportion. Therefore, the calculated simulated apportioned energy consumption is lower. In the extreme case, all the equipment is in hoisting operation during the statistical period, and there is no non-operation phase. Then the calculated apportioned energy consumption is the pure hoisting operation energy consumption. In non-extreme cases, the calculated simulated apportioned energy consumption is greater than the pure hoisting operation energy consumption. On the contrary, when the workload is small during the statistical period, the calculated apportioned energy consumption will be much greater than the pure hoisting operation energy consumption. If the k and b calculated when the workload is small are used to simulate Q, it will be greater than Q 实际 , that is, we can get Q ij Basic and operating box volume ∑U ij Inversely correlated;
[0146] The analysis method of “the ratio of empty boxes to full boxes, and the ratio of different box types in empty boxes and full boxes” is similar. The Q calculated by simulation is ij The energy consumption during the non-operation phase is allocated to each type of box, meaning Q ij =Equal to pure lifting energy consumption + allocated non-operation phase energy consumption. The allocation of empty and loaded containers is also different when the ratios in the quotation marks are different. Therefore, when the above ratio changes, Q ij It will also change accordingly. According to actual statistics, when the proportion of heavy boxes is high, its Q ij It will also increase, basically showing a positive correlation;
[0147] Due to the complexity of the actual on-site operation conditions, such as the different weights of each container, the different operating habits of equipment drivers, and the different attendance operation methods, it is impossible to make a general comparison between Q and Q 实际 It is impossible to conduct quantitative analysis on the differences, and only qualitative analysis can be performed to describe their correlation.
[0148] The first summation symbol in formula (8) refers to the operating energy consumption of a single type of equipment within the statistical period, and the second summation symbol refers to the sum of the equipment energy consumption within the loading and unloading process; the general process of loading and unloading ships at the terminal is as follows: for example, a ship comes to load and unload several containers. After the ship berths, taking unloading as an example, several front-end equipment needs to be allocated to operate the ship, and correspondingly, several horizontal transportation equipment is also required to transport the containers hoisted by the front-end equipment to the yard, and then the yard equipment hoists them to the designated position of the yard. The loading order is the opposite of the above description. Therefore, when predicting the energy consumption of the port, it is necessary to comprehensively consider the operation of various types of equipment and the volume of various types of containers. The sum of the energy consumption of various types of equipment is the total equipment energy consumption of the port.
[0149] Example 8
[0150] Embodiment 8 is a further optimized technical solution of Embodiment 1;
[0151] In S1, the operation data and energy consumption data of the crane are collected. Specifically, the operation box type data U of the crane that needs to be analyzed is counted. ij , where i is an empty container or a full container, and j is 20 feet, 40 feet, 45 feet, etc., and the energy consumption Q of the crane during the analysis phase is calculated.
[0152] In S2, the container types of container ports are generally divided into 20 feet, 40 feet, and 45 feet. According to whether there are goods in the container, there are simple empty containers and full containers. Therefore, the operation types of container ports are divided into empty 20 feet, empty 40 feet, empty 45 feet, full 20 feet, full 40 feet, and full 45 feet. For the convenience of calculation, the container operation volume of each type of container crane operation in a period of time is counted as U ij (i is empty container, full container, j is 20 feet, 40 feet, 45 feet), the total energy consumption of container cranes during the statistical period is Q, and the above data can be directly collected at the container terminal;
[0153] The total energy consumption Q of a container crane within a certain period of time is divided into energy consumption in the operating stage and energy consumption in the non-operating stage. Since port cranes generally have a constant power output, the energy consumption in the operating stage is only related to the weight of the container. Based on the power-torque relationship, torque formula, energy consumption formula and other physical concepts, the relationship between energy consumption and weight can be obtained as follows:
[0154] T=9550P / n T is torque, P is motor power, n is motor speed
[0155] T = ml T is the torque, m is the weight of the object, and 1 is the length of the lever arm
[0156] Q=Pt Q is energy consumption, P is motor power, t is time
[0157] The above formula can be transformed into
[0158]
[0159] It can be seen from the above formula that when the arm length 1, time t, and motor speed n are constant, the energy consumption of the container port crane in the operation stage is basically proportional to the weight of the container. Considering energy loss, statistical errors and other issues, the energy consumption in the non-operation stage needs to be calculated uniformly. Therefore, the constant b can be added to ensure the accuracy of the data. Therefore, the energy consumption and weight can be simplified to a linear function
[0160] Q = km + b, where k and b are constants;
[0161] According to the characteristics of container port operations, the above formula can be expressed as a linear relationship between the energy consumption of container port crane operations and the weight of the container. According to the fitting algorithm, the main idea is to calculate the weight of each crane lift (each operation cycle). Since the weight difference between empty containers and full containers is large, they need to be divided into empty containers and full containers for separate calculations. The calculated weight of each lift is substituted into a linear function, and the values of k and b can be obtained by solving the two sets of data together. The calculation method mainly includes the following steps 1), step 2), and step 3):
[0162] Step 1) Calculate the total weight of the crane operation based on the box type and box weight
[0163] In order to facilitate throughput statistics, general container ports stipulate the box weight m for each type of container based on the characteristics of the operating routes and experience. ij It can be a fixed value (for example, a port stipulates that the weight of an empty 20-foot container is 2 tons, the weight of an empty 40-foot and 45-foot container is 4 tons, the weight of a loaded 20-foot container is 23 tons, and the weight of a loaded 40-foot and 45-foot container is 27 tons. At the same time, this method is also commonly used in the statistical calculation of port carbon emissions in related industries), or the weight of each container in the operation can be counted, and the weight of the empty and loaded containers of the crane operation can be accumulated:
[0164] The total weight of the empty container for crane operation is m 空 =∑U 空j *m 空j
[0165] The total weight of the crane operation box is m 重 =∑U 重j *m 重j
[0166] Step 2), calculating the weight of each lifting operation of the crane according to the equipment type;
[0167] For a crane that only operates one container per lift, the average weight of each lift is the total mass divided by the total number of containers, that is,
[0168] The weight of each empty container is
[0169] The weight of each heavy box is
[0170] The above m 空吊 and m 重吊 The calculation formula is for a container crane operating a single container; for a port container crane operating double containers or 4 containers, that is, a port container loading and unloading container port crane that can load and unload n containers (n = 1, 2, 3, 4) at a time, the total number of lifts in operation should be the number of single containers in each type of container plus the number of double containers in operation divided by n. Suppose the ratio of the number of n containers in one operation to the total number of operations is β, that is, the mathematical expression of the weight of each lift is
[0171]
[0172] When the proportion of n boxes in one operation, that is, β is 0, the above formula is the same as the formula for each lifting weight;
[0173] Step 3), using the weight and energy consumption data to establish a two-variable linear equation model with two constants, and solve the two constants;
[0174] According to the linear relationship between crane energy consumption and each hoist weight,
[0175] The energy consumption of empty box is Q 空 =∑U 空j *(k*m 空吊 + b) = ∑U 空j *b+k*vU 空j *m 空j
[0176] The energy consumption of a heavy box is Q 重 =vU 重j *(k*m 重吊 + b) = ∑U 重j *b+k*∑U 重j *m 重j
[0177] Q=Q 空 +Q 重
[0178] Using multiple sets of data, we can solve the k and b values and substitute them into Q ij =km ij + b can be used to obtain the actual unit energy consumption of the relevant box type of the crane operation.
[0179] In S3, the above k value and b value are solved by two sets of data (for example, the box type data and energy consumption data of January and February), so the error of k value and b value in these two sets of data is small, but the equipment operation conditions in each stage (or each month) are slightly different, so Q (calculated energy consumption) and Q may differ in different stages.实际 (Q 实际 The practical energy consumption in the analysis stage) will have different degrees of error. Since the k value is relatively fixed, it is generally only necessary to modify the b value to make Q and Q 实际 The error between them is reasonable and controllable. The corrected k value and b value are the constant indicators of crane energy consumption at the current stage. Substitute them into Q ij =km ij +b is the actual unit energy consumption of the relevant box type of the crane operation at the current stage.
[0180] In S4, due to the different stages of Q and Q 实际 There are different degrees of errors between them, which mainly include the following aspects according to the relationship between the two:
[0181] (Aspect 1) When Q is greater than Q 实际 Since k and b are constants, we know from Q = km + b that there exists a value m (m is the theoretical calculated box weight) greater than m 实际 (m 实际 is the actual box weight). According to the expression m, the total number of boxes in the two sets of data, the ratio of empty boxes to full boxes, the ratio of different box types in empty boxes and full boxes, etc. can be compared to analyze the reasons for the change in energy consumption.
[0182] (Aspect 2) When Q is less than Q 实际 When the energy consumption change analysis is similar to the above analysis method, it is also analyzed by the change of box quantity and box type;
[0183] (Aspect 3) When Q equals Q 实际 That is, the changes in box quantity and box type in different stages are small or reasonably controllable.
[0184] In S5, the energy consumption of container port cranes includes the energy consumption of frontier equipment (quay cranes, gantry cranes, etc.) and yard equipment (tyre cranes, rail cranes, forklifts, reach stackers, etc.) and translational transport equipment (tractors, etc.). The above-mentioned algorithms and analysis methods can be used to analyze the energy consumption of the above-mentioned equipment. The energy consumption data in the future can be obtained by multiplying the different types of boxes operated by various types of equipment in the future by the operating energy consumption of each type of box. The mathematical expression is:
[0185] Q 港口 =∑∑U ij Q ij
[0186] In the above formula Q 港口 =ΣΣU ij Q ij In the calculation process, in order to ensure that the error of the budget result is small, when selecting the k value and b value, data with similar box quantity and box type should be used for calculation, which can effectively ensure the accuracy of the calculation results.
[0187] Example 9
[0188] This embodiment further proposes a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, the steps of the method for energy consumption management and prediction of container port cranes as described in any of the above embodiments are implemented.
[0189] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for managing and predicting energy consumption of container port cranes, characterized in that: The method comprises the following steps S1-S5 performed in the following order: S1, collecting operation data and energy consumption data of container port cranes; the operation data includes the number of empty containers of different types lifted by the container port cranes and the number of loaded containers of different types lifted by the container port cranes; the energy consumption data includes the energy consumption value of each container port crane corresponding to the operation data; S2, fitting the energy consumption of the container port crane corresponding to different types of containers by using the operation data and energy consumption data obtained in S1; S3, performing data correction by using the fitted shared energy consumption obtained in S2, thereby obtaining the corrected actual shared energy consumption corresponding to different types of containers of the container port crane; S4, performing energy difference analysis on the fitted shared energy consumption obtained in S2 and the actual shared energy consumption obtained in S3, so as to obtain a differential analysis calibration parameter; S5, obtaining energy consumption prediction analysis results according to the number of containers of different types obtained in S1, the actual allocated energy consumption obtained in S3, and the differential analysis calibration parameters obtained in S4.
2. The method for energy consumption management and prediction of container port cranes according to claim 1, characterized in that: After S5, the container port crane energy consumption management and prediction method also includes: S6, judging whether the deviation between the actual energy consumption value of the container port crane and the predicted energy consumption value of the energy consumption prediction analysis result obtained in S5 is greater than a threshold value, if it is judged to be yes, S4 is executed, if it is judged to be no, the energy consumption prediction analysis result obtained in S5 is used as the final prediction result.
3. The method for energy consumption management and prediction of container port cranes according to claim 1 or 2, characterized in that: S2 includes the following sub-steps S21-S22 executed in sequence: S21, according to the power and torque relationship of the crane T = 9550P / n, the torque formula T = ml and the energy consumption formula Q = Pt, obtain the energy consumption and weight relationship, that is, the linear function Q = km + b about energy consumption and weight, wherein k and b of the linear function are constants, Q is the energy consumption of the crane, t is the working time of the crane, and m is the weight of the container lifted by the crane; wherein T in the torque relationship is the torque of the crane, P is the motor power of the crane, and n is the motor speed of the crane; S22, obtain the weight of each hoist of empty boxes of different types of cranes and the weight of each hoist of different types of loaded boxes, substitute the obtained weight of each hoist into the linear function Q=km+b, and use two sets of data on energy consumption and weight to jointly solve the values of constants k and constants b.
4. The method for energy consumption management and prediction of container port cranes according to claim 3, characterized in that: S22 includes the following sub-steps S221-S223 executed in sequence: S221, according to the container type and weight, obtain the total weight of the container port crane operation; S222, obtaining the weight of each lifting operation of the container port crane according to the equipment type of the crane; S223, establishing a linear function Q=km+b through the operation data and the energy consumption data, and solving for constants k and b; In S3, the simulated allocated unit consumption of container port cranes corresponding to different container types is obtained through constants k and b.
5. The method for energy consumption management and prediction of container port cranes according to claim 4, characterized in that: In S221, the weight of each container in the operation is counted, and the total weight of the empty container in the crane operation and the total weight of the loaded container in the crane operation are accumulated to obtain the following: The total weight of the empty container for crane operation is m 空 =ΣU 空j *m 空j Formula (1); The total weight of the crane operation box is m 重 =ΣU 重j *m 重j Formula (2); In formula (1), m 空 is the total weight of empty containers in crane operation, i.e. the total weight of empty containers, m 空j For the enumeration of the weight of various empty containers, U 空j The number of empty boxes of each type corresponding to the empty box weight; In formula (2), m 重 is the total weight of the crane operation load box, that is, the sum of the weight of the load boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes for each type of corresponding heavy box weight.
6. The method for energy consumption management and prediction of container port cranes according to claim 5, characterized in that: In S222, for a crane that only operates one container per lift, the average weight of each lift is the total weight of the containers divided by the total number of containers, that is, The weight of each empty container is The weight of each heavy box is The cranes corresponding to formula (3) and formula (4) are container port cranes corresponding to single-box operations; In formula (3), m 空吊 The empty container weight per hang, m 空 is the total weight of the empty containers, m 空j For the enumeration of the weight of various empty containers, U 空j is the number of empty boxes of each type of corresponding empty box weight; in formula (4), m 重吊 is the weight of each heavy box, m 重 is the total weight of the heavy boxes, m 重j For the enumeration of the weight of various heavy boxes, U 重j The number of heavy boxes corresponding to the heavy box weight of each type; In S222, for a port container crane that operates two or four containers, that is, the container port crane can load and unload n containers (n = 1, 2, 3, 4) at a time, the total number of lifts is the number of single containers in each type of container plus the number of double containers divided by n. The ratio of the number of n containers in one operation to the total number of operations is set to β, that is, the mathematical expression of the weight of each lift is: When β is 0, formula (5) is the same as formula (3) or formula (4) per hanging weight; In formula (5), m 吊 is the weight of each crane lift, i is defined as an empty container or a loaded container, j is defined as the container type of different sizes, ∑U ij *m ij is the total weight of all types of containers in operation, n 吊 is the total number of operations, ΣU ij is the total amount of work corresponding to i and j.
7. The method for energy consumption management and prediction of container port cranes according to claim 6, characterized in that: In S223, according to the linear relationship between the energy consumption of container port cranes and the weight per crane, The energy consumption of the crane with empty box is Q 空 =ΣU 空j *(k*m 空吊 + b)=ΣU 空j *b+k*ΣU 空j *m 空j Formula (6) The energy consumption of the crane load box is Q 重 =ΣU 重j *(k*m 重吊 + b)=ΣU 重j *b+k*∑U 重j *m 重j Formula (7) The total energy consumption Q = Q 空 +Q 重 Formula (8) Solve the k and b values based on multiple sets of statistical period data, and substitute the k and b values into the linear function Q ij =km ij + b can be used to obtain the actual unit energy consumption of the corresponding container type related to the crane operation in the container port.
8. The method for energy consumption management and prediction of container port cranes according to claim 7, characterized in that: In S4, When the total energy consumption Q of the fitting allocation is less than the statistical energy consumption Q 实际 When the energy consumption of a single box is apportioned, the box weight is used to simulate the operation, and the energy consumption of each box type in the non-operation stage is obtained according to the ratio of empty boxes to full boxes and the ratio of different box types in empty boxes and full boxes. When the total energy consumption Q of the fitting distribution is equal to the statistical energy consumption Q 实际 That is, the changes in box quantity and box type in different stages are normal.
9. The method for energy consumption management and prediction of container port cranes according to claim 8, characterized in that: The energy consumption of container port cranes includes the energy consumption of front equipment, yard equipment and translational transport equipment; In S4, the energy consumption data in the future can be obtained by multiplying the different types of container volumes of various types of container port crane operations by the operating energy consumption of each type of container in the future. The mathematical expression of the energy consumption data is: Q 港口 = ∑ ∑ U ij Q ij Formula(9) In formula (9), Q 港口 The sum of the energy consumption of the equipment in the loading and unloading process, ∑U ij Q ij Statistical data for energy consumption of a single type of equipment during a period of operation.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method for managing and predicting energy consumption of a container port crane according to any one of claims 1 to 9 are implemented.
Citation Information
Cited By
Container crane control system and method based on situation awareness
CN121085139A
Container crane control system and method based on situation awareness
CN121085139B