High-reliability optimal scheduling method for micro-grid in industrial park in severe weather
By correcting the forecast curves of wind power, photovoltaic, and load power and building a robust optimization model, the problem of unstable operation of the microgrid in industrial parks under severe weather is solved, and a high economic and high reliability operation strategy is achieved, reducing economic losses and Running cost.
Patent Information
- Application Number
- CN202411092832.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-09
AI Technical Summary
The existing microgrid optimization scheduling methods in industrial parks fail to effectively consider the impact of bad weather on operating strategies, especially under typhoons, high temperatures, solar eclipses and other conditions, resulting in operational instability and economic losses.
By obtaining bad weather warning information, correct the wind power, photovoltaic, and load power prediction curves, and construct a robust optimization model connected to the grid or off-grid based on the operating status of the microgrid to achieve a high-reliability operation strategy in bad weather.
It realizes high economic and high reliability operation of the microgrid in bad weather, reduces operating costs and economic losses, and ensures stable power supply under harsh conditions.
Smart Images

Figure CN119010037A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power system operation optimization, and specifically relates to a high-reliability optimization dispatching method for a microgrid in an industrial park under severe weather. Background Art
[0002] The deployment of wind power, photovoltaic and other new energy and energy storage in industrial parks is an important direction for the development of distributed power sources (see the schematic diagram of industrial park microgrid for details) Figure 1 ), can improve the self-sufficiency rate of electricity for work and life in industrial parks and realize clean power supply. By optimizing the wind, light, and storage power generation plans and the power exchange plans with the external power grid, the industrial park microgrid can reduce electricity costs and even achieve profitability, and maintain an isolated island operation state for a certain period of time after a fault, reducing economic losses. Existing industrial park microgrid optimization and scheduling methods usually only consider strategy optimization under normal operating conditions, and rarely consider the impact of severe weather such as typhoons, high temperatures, and solar eclipses on operating strategies. This method considers the impact of severe weather on boundary conditions such as new energy and load power, the operating state of industrial park microgrids, and the uncertainty of the prediction of the time of severe weather, and carries out optimized scheduling under both grid-connected and off-grid conditions to achieve high-reliability operation of industrial park microgrids under severe weather. Summary of the invention
[0003] The purpose of the present invention is to provide a high-reliability optimization scheduling method for industrial park microgrids under severe weather conditions. The method is based on the wind, light and load prediction correction curves under severe weather conditions, and carries out robust optimization scheduling of microgrids under grid-connected and off-grid conditions to obtain an operation strategy that meets both economy and reliability.
[0004] To achieve the above object, the technical solution of the present invention is: a high reliability optimization scheduling method for industrial park microgrids under severe weather conditions, comprising the following steps:
[0005] Step 1: Obtain the data required for calculation, including power supply parameters, tie line parameters, new energy forecast data, and load forecast data;
[0006] Step 2: Obtain severe weather warning information, including the type, start and end time of severe weather;
[0007] Step 3: According to the severe weather warning information, correct the wind power, photovoltaic and load power forecast curves;
[0008] Step 4: Determine the operating status of the microgrid. If the microgrid is in a grid-connected state, a robust optimization model of the microgrid grid-connected operation strategy is constructed with the goal of optimal economic efficiency. If the microgrid is in an off-grid state, a robust optimization model of the microgrid off-grid operation is constructed with the goal of maximizing the power supply time of important loads.
[0009] Step 5: Solve the optimization model and obtain the operation strategy.
[0010] In one embodiment of the present invention, in step 1, the power supply parameters, tie line parameters, new energy forecast data, and load forecast data are specifically as follows:
[0011] 1) Power supply parameters: including capacity and power parameters of various power sources such as wind power, photovoltaic power, and energy storage;
[0012] 2) Tie-line parameters: the upper limit of the transmission power of the tie-line connecting the industrial park microgrid and the distribution network;
[0013] 3) New energy forecast data: forecast values of wind power and photovoltaic power generation at each moment;
[0014] 4) Load forecast data: The predicted power consumption of the industrial park microgrid at each moment.
[0015] In one embodiment of the present invention, in step 2, the types of severe weather include: typhoon, high temperature, and solar eclipse.
[0016] In one embodiment of the present invention, in step 3, the different impacts of various severe weather conditions including typhoons, high temperatures, and solar eclipses on wind power, photovoltaic power, and load curves are considered, and the uncertainty of the prediction of the start and end times of severe weather is considered.
[0017] In one embodiment of the present invention, step 3 is specifically implemented as follows:
[0018] Obtain the severe weather power correction curve, and record the wind power, photovoltaic, and load power forecast curves as P t W,pre , P t S ,pre , P t L,pre The corresponding power correction curves are ΔP t W , ΔP t S , ΔP t L ;
[0019] Typhoons will cause dramatic changes in wind speed in the area where the microgrid is located, which will in turn cause changes in wind power generation, and the amplitude of the change is highly random. It can be considered that the change value of the wind power correction curve is a series of data that satisfies the normal distribution, namely:
[0020] ΔP t W ~N(0,σ 2 )(1)
[0021]
[0022] In the formula, σ is the variance of the normal distribution, which can be set according to the typhoon warning situation, P W is the wind power installed capacity, and the wind power correction curve is generated according to formula (1). At the same time, the generated curve should meet the upper and lower limit requirements of formula (2);
[0023] At the same time, the cooling brought by the typhoon will lead to a reduction in load power consumption. It is believed that the load power consumption is reduced in proportion, that is:
[0024]
[0025] In the formula, k L is the load power scaling factor, with a value range of 0-1;
[0026] The impact of typhoons on photovoltaic power is relatively small, and the photovoltaic correction power during typhoons can be considered to be 0, that is:
[0027]
[0028] For high temperature, the load and photovoltaic power will increase, while the wind power will decrease. It can be considered that under the influence of high temperature, the wind power, photovoltaic and load forecast power will be scaled in proportion. The corresponding power correction curve is as follows:
[0029]
[0030] Among them, k W , k S are wind power and photovoltaic power scaling factors, P S is the photovoltaic installed capacity, and the photovoltaic corrected power should also meet the upper and lower limit requirements of formula (8);
[0031] For solar eclipses, the main impact is on photovoltaic output. During the solar eclipse, photovoltaic power drops to a minimum value p S , then the photovoltaic power correction curve is:
[0032]
[0033] The impact of solar eclipse on wind power and load power can be ignored, and the modified power curve during the solar eclipse is considered to be 0, that is:
[0034]
[0035] After obtaining the power correction curve, the wind power, photovoltaic and load power can be corrected according to the severe weather forecast period. Respectively represent the time periods when wind power, photovoltaic power, and load are affected by bad weather. If affected, the value is 1, and if not affected, the value is 0. The affected period should be continuous. For wind power, the affected period is The impact start time is recorded as The impact end time is recorded as The middle moment of impact is recorded as The impact duration between, The value of is 1, and the value of the rest of the time period is 0; similarly, for photovoltaic and load, the impact time periods are
[0036] Due to the uncertainty in the forecast of the period affected by severe weather, the start and end times may deviate from the predicted time; that is, the actual impact start time may not be Rather At some time near Rather At some point in the vicinity; W Under the premise of severe weather at all times, considering the uncertainty of the occurrence / end time, the affected period It is expressed as follows:
[0037]
[0038]
[0039] In the formula, The predicted starting time when photovoltaic and load power are affected by bad weather. is the predicted end time of the photovoltaic and load power being affected by bad weather, t S ,t L is the middle moment when the predicted photovoltaic and load power are affected by bad weather, Γ W,1 , Γ S,1 , Γ L,1 Respectively represent the maximum possible offset of wind power, photovoltaic power and load power at the start time of being affected, Γ W,2 , Γ S,2 , Γ L,2 They represent the maximum possible offsets of the affected end times of wind power, photovoltaic power, and load power, respectively;
[0040] Then the power curve P after wind power, photovoltaic and load correction t W,fix , P t S,fix , P t L,fix It is expressed as:
[0041]
[0042] In one embodiment of the present invention, in step 4, according to the operating status of the microgrid, a grid-connected operation robust optimization model and an off-grid operation robust optimization model are respectively constructed to achieve the lowest cost operation of the grid-connected condition and high reliability operation of the off-grid condition under the influence of uncertain factors.
[0043] In one embodiment of the present invention, the grid-connected operation robust optimization model is specifically constructed as follows:
[0044] The optimization goal of the grid-connected operation robust optimization model is to achieve the lowest operating cost in all possible bad weather start and end periods, and return the possible operating cost under the worst case. X is the set of all decision variables, including wind power generation power, photovoltaic power generation power, energy storage charging and discharging power, and interconnection line exchange power. U is the set of all uncertain variables, including Then the expression of the objective function is as follows:
[0045]
[0046] In the formula, c in 、c out are the unit electricity purchase cost and unit electricity sales revenue, P t L,in , P t L,out They are the power purchased by the tie line and the power sold by the tie line respectively;
[0047] Operational constraints include:
[0048] 1) Wind power operation constraints:
[0049]
[0050] Where P t W Indicates wind power generation power;
[0051] 2) Photovoltaic operation constraints:
[0052]
[0053] Where P t S Represents photovoltaic power generation;
[0054] 3) Energy storage operation constraints:
[0055]
[0056] Among them, P t Stor,c , P t Stor,d , Q Stor , are respectively energy storage charging power, discharging power, power upper limit, charging state, discharging state, storage capacity, storage capacity lower limit, and storage capacity upper limit; η q , η c , η d They are the self-loss coefficient, charging efficiency and discharging efficiency of energy storage, respectively, and M is a very large constant; When it is 1, it means charging. When it is 1, it indicates discharge;
[0057] If the severe weather warning is high temperature or solar eclipse, the lower limit of energy storage capacity Q P Take 5%; if the severe weather warning is a typhoon, considering the impact of factors such as faults during the typhoon, the microgrid may enter an off-grid operation state, and some power needs to be reserved for use in off-grid operation. The lower limit of energy storage capacity Q P Take 50%;
[0058] 4) Tie line transmission power constraints:
[0059]
[0060] Where P L,max is the maximum transmission power of the tie line;
[0061] 5) Power balance constraints:
[0062]
[0063] 6) Uncertainty constraints on wind, solar and load forecast power: Equations (12) to (20).
[0064] In one embodiment of the present invention, the off-grid operation robust optimization model is specifically constructed as follows:
[0065] The operation goal of the off-grid operation robust optimization model is to achieve the longest time of power supply to important loads in the off-grid state under all possible bad weather start and end periods, and give the continuous power supply time in the worst case. The expression of the objective function is:
[0066]
[0067] In the formula, Indicates the load supply situation. If the wind, solar and storage power can meet the power demand of important loads, the value is 1. If it cannot meet the power supply of important loads, the value is 0. Therefore, The following constraints must be met:
[0068]
[0069] Among them, δ Lis the important load proportion coefficient, and it is considered that the proportion of important load to the total load of the microgrid is a fixed value; for formula (38), when the power generation capacity of the microgrid can meet the power consumption of important loads, the formula in the bracket is 0. Under the action of the objective function, Take 1; if the microgrid power generation capacity cannot meet the power demand of important loads, the formula in the bracket is less than 0. Under the constraint of formula (38), Take 0;
[0070] The constraints include:
[0071] 1) Wind power operation constraints: that is, formula (22);
[0072] 2) PV operation constraints: that is, formula (23);
[0073] 3) Energy storage operation constraints: that is, equations (24) to (31);
[0074] The present invention also provides a high-reliability optimization and dispatching system for industrial park microgrids under severe weather conditions, comprising a memory, a processor, and computer program instructions stored in the memory and capable of being executed by the processor. When the processor executes the computer program instructions, the method steps described above can be implemented.
[0075] The present invention also provides a computer-readable storage medium on which computer program instructions that can be executed by a processor are stored. When the processor executes the computer program instructions, the method steps described above can be implemented.
[0076] Compared with the prior art, the present invention has the following beneficial effects: the method first obtains severe weather warning information, and corrects the wind power, photovoltaic, and load forecast curves based on the severe weather warning information, and then monitors the operating status of the microgrid in real time, and constructs and solves the grid-connected / off-grid optimization scheduling models according to the monitoring results, so as to achieve high economy and high reliability operation under the influence of various severe weather such as typhoons, high temperatures, and solar eclipses. BRIEF DESCRIPTION OF THE DRAWINGS
[0077] Figure 1 This is a schematic diagram of the microgrid structure in the industrial park;
[0078] Figure 2 Optimize dispatch flow chart for industrial park microgrid;
[0079] Figure 3 This is a schematic diagram of the time periods affected by severe weather. DETAILED DESCRIPTION
[0080] The technical solution of the present invention is described in detail below in conjunction with the accompanying drawings.
[0081] The present invention provides a high reliability optimization scheduling method for an industrial park microgrid under severe weather conditions, comprising the following steps:
[0082] Step 1: Obtain the data required for calculation, including power supply parameters, tie line parameters, new energy forecast data, and load forecast data;
[0083] Step 2: Obtain severe weather warning information, including the type, start and end time of severe weather;
[0084] Step 3: According to the severe weather warning information, correct the wind power, photovoltaic and load power forecast curves;
[0085] Step 4: Determine the operating status of the microgrid. If the microgrid is in a grid-connected state, a robust optimization model of the microgrid grid-connected operation strategy is constructed with the goal of optimal economic efficiency. If the microgrid is in an off-grid state, a robust optimization model of the microgrid off-grid operation is constructed with the goal of maximizing the power supply time of important loads.
[0086] Step 5: Solve the optimization model and obtain the operation strategy.
[0087] The following is the specific implementation process of the present invention.
[0088] Aiming at the operational decision-making difficulties of microgrids in industrial parks under severe weather conditions, the present invention proposes a high-reliability optimization scheduling method for microgrids in industrial parks under severe weather conditions. The proposed method takes into account the impact of various severe weather conditions such as typhoons, high temperatures, and solar eclipses, as well as prediction uncertainties, and takes into account the needs of both grid-connected economic operation and off-grid reliable operation.
[0089] Reference Figure 2 , a high reliability optimization dispatching method for industrial park microgrid under severe weather conditions, the specific implementation steps are as follows:
[0090] Step 1: Obtain the data required for calculation, including power supply parameters, tie line parameters, new energy forecast data, load forecast data, etc., including:
[0091] 1) Power supply parameters: including capacity, power and other parameters of various power sources such as wind power, photovoltaic power and energy storage;
[0092] 2) Tie-line parameters: transmission power limit of the tie-line connecting the industrial park microgrid and the distribution network;
[0093] 3) New energy forecast data: forecast values of wind power and photovoltaic power generation at each moment;
[0094] 4) Load forecast data: The predicted power consumption of the industrial park microgrid at each moment.
[0095] Step 2: Obtain severe weather warning information, including the type, start and end time of severe weather.
[0096] Among them, the types of severe weather include: typhoon, high temperature, and solar eclipse.
[0097] Step 3: According to the severe weather warning information, correct the wind power, photovoltaic and load power forecast curves.
[0098] Specifically, we first obtain the severe weather power correction curve, and note that the wind power, photovoltaic, and load power prediction curves are P t W,pre , P t S,pre , P t L,pre , the power correction curves are ΔP t W , ΔP t S , ΔP t L .
[0099] Typhoons will cause dramatic changes in wind speed in the area where the microgrid is located, which will in turn cause changes in wind power generation, and the amplitude of the change is highly random. The change value of the wind power curve can be considered as a series of data that satisfies the normal distribution, namely:
[0100] ΔP t W ~N(0,σ 2 ) (1)
[0101]
[0102] In the formula, σ is the variance of the normal distribution, which can be set according to the typhoon warning situation, P W is the installed capacity of wind power. The wind power correction curve is generated according to formula (1), and the generated curve should meet the upper and lower limit requirements of formula (2).
[0103] At the same time, the temperature drop brought by the typhoon will lead to a reduction in load power consumption. It is assumed that the load power consumption is reduced in equal proportion, that is:
[0104]
[0105] In the formula, k L is the load power scaling factor, ranging from 0 to 1.
[0106] The impact of typhoons on photovoltaic power is relatively small, and the photovoltaic correction power during typhoons can be considered to be 0, that is:
[0107]
[0108] For high temperatures, the load and photovoltaic power will increase, while the wind power will decrease. It can be considered that under the influence of high temperature, the wind power, photovoltaic, and load forecast power are scaled proportionally, and the corrected power is as follows:
[0109]
[0110] Among them, k W , k S are wind power and photovoltaic power scaling factors, P S is the photovoltaic installed capacity. The photovoltaic correction power should also meet the upper and lower limit requirements of formula (8).
[0111] For solar eclipses, the main impact is on photovoltaic output. During a solar eclipse, photovoltaic power drops to a minimum value p S , then the photovoltaic power correction curve is:
[0112]
[0113] The impact of solar eclipse on wind power and load power can be ignored, and the modified power curve during the solar eclipse is considered to be 0, that is:
[0114]
[0115] After obtaining the correction curve, the wind power, photovoltaic power and load power can be corrected according to the severe weather forecast period. They represent the time periods when wind power, photovoltaic power and load are affected by bad weather. If affected, the value is 1, and if not affected, the value is 0. The affected time period should be continuous. Taking wind power as an example, the affected time period The curve is as Figure 3 As shown in the figure, the impact start time is recorded as The impact end time is recorded as The middle moment of impact is recorded as The impact duration between, The value of is 1, and the value of other time periods is 0.
[0116] Furthermore, due to the uncertainty in the prediction of the period of severe weather impact, the start and end time may deviate from the predicted time. Rather At some time near Rather At some point in the vicinity. W Under the premise of severe weather at all times, considering the uncertainty of the occurrence / end time, the affected period It can be expressed as follows:
[0117]
[0118] In the formula, The predicted starting time when photovoltaic and load power are affected by bad weather. is the predicted end time of the photovoltaic and load power being affected by bad weather, t S ,t L is the middle moment when the predicted photovoltaic and load power are affected by bad weather, Γ W,1 , Γ S,1 , Γ L,1 Respectively represent the maximum possible offset of wind power, photovoltaic power and load power at the start time of being affected, Γ W,2 , Γ S,2 , Γ L,2 They respectively represent the maximum possible offset of the affected end time of wind power, photovoltaic power and load power.
[0119] Then the power curve P after wind power, photovoltaic and load correction t W,fix , P t S,fix , P t L,fix It can be expressed as:
[0120]
[0121] Step 4: Determine the operating status of the microgrid. If the microgrid is in a grid-connected state, a robust optimization model of the microgrid grid-connected operation strategy is constructed with the goal of optimal economic efficiency. If the microgrid is in an off-grid state, a robust optimization model of the microgrid off-grid operation is constructed with the goal of maximizing the power supply time of important loads.
[0122] Specifically, the grid-connected operation optimization model is as follows:
[0123] The optimization goal is to achieve the lowest operating cost in all possible bad weather start and end periods. At the same time, the possible operating cost in the worst case is returned. X is the set of all decision variables (including wind power generation, photovoltaic power generation, energy storage charging and discharging power, interconnection line switching power, etc.), and U is the set of all uncertain variables, including Then the expression of the objective function is as follows:
[0124]
[0125] In the formula, c in 、c out are the unit electricity purchase cost and unit electricity sales revenue, P t L,in , P t L,outThey are the interconnection line power purchase and interconnection line power sale respectively.
[0126] Operational constraints include:
[0127] 1) Wind power operation constraints:
[0128]
[0129] Where P t W Indicates wind power generation power.
[0130] 2) Photovoltaic operation constraints:
[0131]
[0132] Where P t S Represents photovoltaic power generation power.
[0133] 3) Energy storage operation constraints:
[0134]
[0135]
[0136] Among them, P t Stor,c , P t Stor,d , Q Stor , are respectively energy storage charging power, discharging power, power upper limit, charging state, discharging state, storage capacity, storage capacity lower limit, and storage capacity upper limit; η q , η c , η d They are the self-loss coefficient, charging efficiency and discharging efficiency of energy storage respectively, and M is a huge constant. When it is 1, it means charging. When it is 1, it indicates discharge.
[0137] If the severe weather warning is high temperature or solar eclipse, the lower limit of energy storage capacity Q P A smaller value, such as 5%, can be taken; if the severe weather warning is a typhoon, considering the impact of factors such as faults during the typhoon, the microgrid may enter an off-grid operation state, and some power needs to be reserved for use in off-grid operation. The lower limit of energy storage capacity Q P A larger value, such as 50%, can be taken.
[0138] 4) Tie line transmission power constraints:
[0139]
[0140] Where PL,max is the maximum transmission power of the interconnection line.
[0141] 5) Power balance constraints:
[0142]
[0143] 6) Uncertainty constraints on wind, solar and load forecast power: Equations (12) to (20).
[0144] The off-grid operation optimization model is as follows:
[0145] The operation goal is to achieve the longest time of power supply to important loads in the off-grid state in all possible bad weather start and end periods. At the same time, the continuous power supply time in the worst case is given. The expression of the objective function is:
[0146]
[0147] In the formula, Indicates the load supply situation. If the wind, solar and storage power can meet the power demand of important loads, the value is 1. If it cannot meet the power supply of important loads, the value is 0. Therefore, The following constraints must be met:
[0148]
[0149] Among them, δ L is the important load proportion coefficient, and it is considered that the proportion of important load to the total load of the microgrid is a fixed value. For formula (38), when the microgrid power generation capacity can meet the power demand of important loads, the formula in the bracket is 0. Under the action of the objective function, Take 1; if the microgrid power generation capacity cannot meet the power demand of important loads, the formula in the bracket is less than 0. Under the constraint of formula (38), Take 0.
[0150] The constraints include:
[0151] 1) Wind power operation constraints: that is, formula (22).
[0152] 2) PV operation constraints: that is, formula (23).
[0153] 3) Energy storage operation constraints: namely, equations (24) to (31).
[0154] Step 5: Solve the optimization model and obtain the operation strategy. The decision results include the moment-by-moment wind power generation plan, photovoltaic power generation plan, energy storage charging and discharging plan, and interconnection line power purchase and sales plan (only under grid-connected conditions).
[0155] The present invention also provides a high-reliability optimization and dispatching system for industrial park microgrids under severe weather conditions, comprising a memory, a processor, and computer program instructions stored in the memory and capable of being executed by the processor. When the processor executes the computer program instructions, the method steps described above can be implemented.
[0156] The present invention also provides a computer-readable storage medium on which computer program instructions that can be executed by a processor are stored. When the processor executes the computer program instructions, the method steps described above can be implemented.
[0157] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0158] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0159] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0160] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1The steps for the functions specified in one or more boxes.
[0161] The above is only a preferred embodiment of the present invention, and does not limit the present invention in other forms. Any technician familiar with the profession may use the above disclosed technical content to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the technical solution of the present invention still belongs to the protection scope of the technical solution of the present invention.
Claims
1. A high reliability optimization dispatching method for industrial park microgrids under severe weather conditions. It is characterized in that The steps include: Step 1: Obtain the data required for calculation, including power supply parameters, tie line parameters, new energy forecast data, and load forecast data; Step 2: Obtain severe weather warning information, including the type, start and end time of severe weather; Step 3: According to the severe weather warning information, correct the wind power, photovoltaic and load power forecast curves; Step 4: Determine the operating status of the microgrid. If the microgrid is in a grid-connected state, a robust optimization model of the microgrid grid-connected operation strategy is constructed with the goal of optimal economic efficiency. If the microgrid is in an off-grid state, a robust optimization model of the microgrid off-grid operation is constructed with the goal of maximizing the power supply time of important loads. Step 5: Solve the optimization model and obtain the operation strategy.
2. According to the method for optimizing the high reliability of industrial park microgrids under severe weather conditions described in claim 1, It is characterized in that In step 1, the power supply parameters, tie line parameters, new energy forecast data, and load forecast data are as follows: 1) Power supply parameters: including capacity and power parameters of various power sources such as wind power, photovoltaic power, and energy storage; 2) Tie-line parameters: the upper limit of the transmission power of the tie-line connecting the industrial park microgrid and the distribution network; 3) New energy forecast data: forecast values of wind power and photovoltaic power generation at each moment; 4) Load forecast data: The predicted power consumption of the industrial park microgrid at each moment.
3. According to the method for optimizing the high reliability of industrial park microgrids under severe weather conditions described in claim 1, It is characterized in that In step 2, the types of severe weather include: typhoon, high temperature, and solar eclipse.
4. According to the method for optimizing the high reliability of industrial park microgrids under severe weather conditions as described in claim 1, It is characterized in that In step 3, the different impacts of various severe weather conditions including typhoons, high temperatures, and solar eclipses on wind power, photovoltaic power, and load curves are considered, and the uncertainty of the prediction of the start and end times of severe weather is considered.
5. According to the method of high reliability optimization and dispatching of industrial park microgrid under bad weather conditions as described in claim 4, It is characterized in that Step 3 is implemented as follows: Obtain the severe weather power correction curve, and record the wind power, photovoltaic, and load power forecast curves as P t W,pre , P t S,pre , P t L,pre The corresponding power correction curves are ΔP t W , ΔP t S , ΔP t L ; Typhoons will cause dramatic changes in wind speed in the area where the microgrid is located, which will in turn cause changes in wind power generation, and the amplitude of the change is highly random. It can be considered that the change value of the wind power correction curve is a series of data that satisfies the normal distribution, namely: ΔP t W ~N(0,σ 2 (1) Where, σ is the variance of the normal distribution, which can be set according to the typhoon warning situation, P W is the wind power installed capacity, and the wind power correction curve is generated according to formula (1). At the same time, the generated curve should meet the upper and lower limit requirements of formula (2); At the same time, the cooling brought by the typhoon will lead to a reduction in load power consumption. It is believed that the load power consumption is reduced in proportion, that is: In the formula, k L is the load power scaling factor, with a value range of 0-1; The impact of typhoons on photovoltaic power is relatively small, and the photovoltaic correction power during typhoons can be considered to be 0, that is: For high temperature, the load and photovoltaic power will increase, while the wind power will decrease. It can be considered that under the influence of high temperature, the wind power, photovoltaic and load forecast power will be scaled in proportion. The corresponding power correction curve is as follows: Among them, k W , k S are wind power and photovoltaic power scaling factors, P S is the photovoltaic installed capacity, and the photovoltaic corrected power should also meet the upper and lower limit requirements of formula (8); For solar eclipses, the main impact is on photovoltaic output. During the solar eclipse, photovoltaic power drops to a minimum value p S , then the photovoltaic power correction curve is: The impact of solar eclipse on wind power and load power can be ignored, and the modified power curve during the solar eclipse is considered to be 0, that is: After obtaining the power correction curve, the wind power, photovoltaic and load power can be corrected according to the severe weather forecast period. Respectively represent the time periods when wind power, photovoltaic power, and load are affected by bad weather. If affected, the value is 1, and if not affected, the value is 0. The affected period should be continuous. For wind power, the affected period is The impact start time is recorded as The impact end time is recorded as The middle moment of impact is recorded as The impact duration between, The value of is 1, and the value of the rest of the time period is 0; similarly, for photovoltaic and load, the impact time periods are Due to the uncertainty in the forecast of the period affected by severe weather, the start and end times may deviate from the predicted time; that is, the actual impact start time may not be Rather At some time near Rather At some point in the vicinity; W Under the premise of severe weather at all times, considering the uncertainty of the occurrence / end time, the affected period It is expressed as follows: In the formula, The predicted starting time when photovoltaic and load power are affected by bad weather. is the predicted end time of the photovoltaic and load power being affected by bad weather, t S ,t L is the middle moment when the predicted photovoltaic and load power are affected by bad weather, Γ W,1 , Γ S,1 , Γ L,1 Respectively represent the maximum possible offset of wind power, photovoltaic power and load power at the start time of being affected, Γ W,2 , Γ S,2 , Γ L,2 They represent the maximum possible offsets of the affected end times of wind power, photovoltaic power, and load power, respectively; Then the power curve P after wind power, photovoltaic and load correction t W,fix , P t S,fix , P t L,fix It is expressed as:
6. A high reliability optimization dispatching method for industrial park microgrids under severe weather conditions according to claim 5, It is characterized in that In step 4, according to the operating status of the microgrid, a grid-connected operation robust optimization model and an off-grid operation robust optimization model are constructed respectively to achieve the lowest cost operation of the grid-connected condition and high reliability operation of the off-grid condition under the influence of uncertain factors.
7. A high reliability optimization dispatching method for industrial park microgrids under severe weather conditions according to claim 6, It is characterized in that The specific construction of the grid-connected operation robust optimization model is as follows: The optimization goal of the grid-connected operation robust optimization model is to achieve the lowest operating cost in all possible bad weather start and end periods, and return the possible operating cost under the worst case. X is the set of all decision variables, including wind power generation power, photovoltaic power generation power, energy storage charging and discharging power, and interconnection line exchange power. U is the set of all uncertain variables, including Then the expression of the objective function is as follows: In the formula, c in 、c out are the unit electricity purchase cost and unit electricity sales revenue, P t L,in , P t L,out They are the power purchased by the tie line and the power sold by the tie line respectively; Operational constraints include: 1) Wind power operation constraints: Where P t W Indicates wind power generation power; 2) Photovoltaic operation constraints: Where P t S Represents photovoltaic power generation; 3) Energy storage operation constraints: Among them, P t Stor,c , P t Stor,d , Q Stor , are respectively energy storage charging power, discharging power, power upper limit, charging state, discharging state, storage capacity, storage capacity lower limit, and storage capacity upper limit; η q , η c , η d They are the self-loss coefficient, charging efficiency and discharging efficiency of energy storage, respectively, and M is a very large constant; When it is 1, it means charging. When it is 1, it indicates discharge; If the severe weather warning is high temperature or solar eclipse, the lower limit of energy storage capacity Q P Take 5%; if the severe weather warning is a typhoon, considering the impact of factors such as faults during the typhoon, the microgrid may enter an off-grid operation state, and some power needs to be reserved for use in off-grid operation. The lower limit of energy storage capacity Q P Take 50%; 4) Tie line transmission power constraints: Where P L,max is the maximum transmission power of the tie line; 5) Power balance constraints: 6) Uncertainty constraints on wind, solar and load power forecasts: Equations (12) to (20).
8. A high reliability optimization dispatching method for industrial park microgrids under severe weather conditions according to claim 7, It is characterized in that The off-grid operation robust optimization model is specifically constructed as follows: The operation goal of the off-grid operation robust optimization model is to achieve the longest time of power supply to important loads in the off-grid state under all possible bad weather start and end periods, and give the continuous power supply time in the worst case. The expression of the objective function is: In the formula, Indicates the load supply situation. If the wind, solar and storage power can meet the power demand of important loads, the value is 1. If it cannot meet the power supply of important loads, the value is 0. Therefore, The following constraints must be met: Among them, δ L is the important load proportion coefficient, and it is considered that the proportion of important load to the total load of the microgrid is a fixed value; for formula (38), when the power generation capacity of the microgrid can meet the power consumption of important loads, the formula in the bracket is 0. Under the action of the objective function, Take 1; if the microgrid power generation capacity cannot meet the power demand of important loads, the formula in the bracket is less than 0. Under the constraint of formula (38), Take 0; The constraints include: 1) Wind power operation constraints: that is, formula (22); 2) PV operation constraints: that is, formula (23); 3) Energy storage operation constraints: namely, equations (24) to (31).
9. A high reliability optimization dispatching system for industrial park microgrids under severe weather conditions. It is characterized in that The method comprises a memory, a processor and computer program instructions stored in the memory and executable by the processor. When the processor executes the computer program instructions, the method steps as claimed in any one of claims 1 to 8 can be implemented.
10. A computer-readable storage medium storing computer program instructions that can be executed by a processor, wherein when the processor executes the computer program instructions, the method steps according to any one of claims 1 to 8 can be implemented.
Citation Information
Patent Citations
Solar micro-grid energy storage capacity configuration optimization processing system and processing method
CN113300403A
Method and system for optimizing operation of weak connection type wind and light storage micro-grid
CN115774935A
Hydrogen energy micro-grid rolling optimization scheduling method considering unplanned off-grid risk
CN116247745A
Novel rural power distribution network energy storage optimization configuration method
CN116961048A
Data-driven three-stage scheduling method for electricity, heat and gas networks based on wind electricity indeterminacy
US20200313433A1
Cited By
Multi-dimensional data-based collaborative and integrated optimization analysis method for water-light-storage micro-grid
CN119784042A
Pure electrochemical unit net cage typhoon resistance reliability power supply system
CN120879614A