Intelligent drawing review method and system for nuclear power engineering
By subdividing review rules into text, format, and editing, and utilizing a neural network module for intelligent review of nuclear power engineering documents, the problem of low efficiency in document and drawing review in the nuclear power engineering field has been solved, achieving efficient and accurate document review and ensuring the compliance and security of documents.
Patent Information
- Application Number
- CN202411006681.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-26
AI Technical Summary
In nuclear power engineering projects, existing AI-assisted review solutions are inefficient in reviewing documents and drawings, suffer from serious data omissions, and negatively impact user experience.
The review rules are broken down into three aspects: text, format, and editing. Combining artificial intelligence and OCR technology, a trained neural network module is used to intelligently review nuclear power engineering documents and output the review results.
It has significantly improved the efficiency and quality of nuclear power engineering document review, ensuring the accuracy of content, clarity of format, and error-free editing, strengthening the compliance and reliability of documents, and promoting the standardization and normalization of project management.
Smart Images

Figure CN119027968A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of intelligent review technology, and in particular to an intelligent review method and system for drawings used in nuclear power engineering. Background Art
[0002] In the process of nuclear power project construction, design work is the leading factor. Every drawing and document produced in the nuclear power project design work must give priority to quality, strictly follow the management regulations at all levels and avoid various errors.
[0003] Nuclear power design is characterized by many file types and a large number of files. The design output products mainly include engineering drawings, equipment drawings, equipment lists, material lists, cable lists, calculation books, analysis models, scheme demonstration reports, safety analysis reports and other file types, collectively referred to as IED (Index of Engineering Documents). The number of IEDs for large nuclear power projects can reach more than 100,000.
[0004] To ensure the safety and reliability of the design, construction, commissioning and operation of nuclear power plants, each IED document has gone through the stages of compilation, verification, countersignature (on demand), review, QC review, department review, project manager review, and warehousing review. Documents with high quality assurance levels also have an approval stage. Despite this, due to the large number and content of IEDs, and the fact that all of the above processes are completed manually, some low-level errors in text, format, and editing still occur in the documents, causing the documents to be rolled back for revision.
[0005] In order to solve the above problems, the existing technology has proposed solutions for using artificial intelligence to assist in review, which has improved the review efficiency and accuracy to a certain extent. However, these solutions were originally intended to achieve document review in the field of power engineering. Due to their universal design, when dealing with specific scenarios such as documents and drawings in the field of nuclear power engineering, there are still problems with low review efficiency and data omissions, which seriously affect the user experience. Summary of the invention
[0006] In order to solve the above-mentioned problems, the present invention proposes a method and system for intelligent review of drawings for nuclear power engineering. By dividing the review rules into three aspects: text, format, and editing, the efficiency and quality of nuclear power document review are improved, the compliance of the content, the clarity of the format, and the accuracy of editing are ensured, the compliance is strengthened, and the management standardization is promoted; at the same time, by utilizing artificial intelligence and OCR technology, efficient and accurate review of documents and drawings in the field of nuclear power engineering is achieved.
[0007] In order to achieve the above object, the present invention adopts the following technical solution:
[0008] In a first aspect, the present invention provides a method for intelligent review of drawings for nuclear power engineering, comprising:
[0009] Collecting original engineering files and preprocessing them; the original engineering files include IED engineering files and review rules; the review rules include review rules for text, format and editing;
[0010] Generate a download link for the preprocessed original project file and initiate a review request;
[0011] The intelligent review platform receives the download link and downloads the IED engineering files and review rules to be reviewed based on the review request;
[0012] Using the trained neural network module, the IED engineering documents to be reviewed are reviewed in terms of text, format and editing based on the review rules, and the review results are output.
[0013] Preferably, the preprocessing is to uniformly convert the IED engineering files into rasterized PDF files.
[0014] Preferably, before the intelligent review of the text, format and editing of the IED engineering file to be reviewed, the method further includes using OCR technology to recognize the pre-processed original engineering file as text.
[0015] Preferably, the text review rules include:
[0016] Verify the markings before and after modification or change to see if the words before and after the change, as well as before and after the modification, appear in pairs; if not, issue a modification reminder to-do instruction;
[0017] Verify the modification description: when upgrading drawings, files, or the entire drawing, check whether the modification description clearly states the reason; if not, issue a modification reminder to be done;
[0018] Verify the drawing modification description column. When the drawing is upgraded, check whether all design change orders are listed in the modification description column. If not, issue a modification reminder to be done.
[0019] Open item number verification: check whether the number in the open item number column on the file or drawing is consistent with the open item number output in the file or drawing in the design quality management platform; if not, issue a modification reminder to be done instruction;
[0020] Verify the version of mandatory standards and regulations to verify whether the latest valid version of mandatory standards and regulations is adopted; if not, issue a modification reminder to be done instruction;
[0021] Standardization check of English abbreviations and commonly used units: when the English abbreviations in the document body are inconsistent with the commonly used abbreviations, or the commonly used units are not written in a standardized manner, a modification reminder pending instruction will be issued;
[0022] Data result unit labeling verification. When the unit is not marked in the chart, a modification reminder will be issued.
[0023] Preferably, the format review rules include:
[0024] Open item column check: when the file status is a construction file, if there is no open item, the corresponding open item content description column is filled with None or None; when the file status is a non-construction file, if there is no open item, the corresponding open item content description column is filled with Not Applicable; if it is not filled in as required, a modification reminder pending instruction is issued;
[0025] Check the catalog of drawings and atlases. No blank lines should be set between catalog numbers. If the catalog name exceeds the specified number of characters, it needs to be crossed, and the middle lines should be hidden or deleted when crossing lines. If the operation is not carried out as required, a modification reminder pending instruction will be issued;
[0026] Check the co-signature column. If there is no co-signature, fill in the co-signature column of the drawing and DMN as "None". If it is not filled in as required, issue a modification reminder to be done.
[0027] Preferably, the editorial review rules include:
[0028] Project code verification: when the project information in the drawing or document is inconsistent with the uploaded project, a modification reminder pending instruction will be issued; the project information includes the project number, unit number, engineering number, and project name contained in the title page, text, and drawing of the document;
[0029] Chapter and figure number verification: if there are duplicate or skipped chapter numbers in the document; if the figures, tables, and chapter numbers in the text index do not exist in the text; and if there are duplicate or skipped illustration and table numbers, a modification reminder pending instruction will be issued;
[0030] Page number verification: when the page number displayed at the current page position in the file or directory is repeated or skipped, or the page number at the total page position is skipped, a modification reminder will be issued.
[0031] In a second aspect, the present invention provides a drawing intelligent review system for nuclear power engineering, comprising:
[0032] The design quality management platform is used to receive the original engineering files and transmit the original engineering files to the paperless platform; receive the original engineering files pre-processed by the paperless platform and generate download links; send review requests and download link lists to the intelligent review platform, and receive feedback from the intelligent review platform; the original engineering files include IED engineering files and review rules;
[0033] The paperless platform is used to receive the original engineering files sent by the design quality management platform for preprocessing, and return the preprocessed original engineering files to the design quality management platform;
[0034] The intelligent review platform is used to receive the review request and download link list sent by the design quality management platform, select the IED project file to be reviewed from the download link list based on the review request; conduct text, format and editing reviews based on the review rules, and feed back the review results to the design quality management platform.
[0035] Preferably, the sending of the review request and the download link list to the intelligent review platform is specifically: the design quality management platform calls the external interface of the intelligent review platform to send the review request and the download link list to the intelligent review platform.
[0036] In a third aspect, the present invention provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of a method for intelligent review of drawings for nuclear power engineering as described in the first aspect.
[0037] In a fourth aspect, the present invention provides a computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps of a method for intelligent review of drawings for nuclear power engineering described in the first aspect are implemented.
[0038] Compared with the prior art, the present invention has the following beneficial effects:
[0039] The present invention subdivides the review rules into three aspects: text, format, and editing, which significantly improves the efficiency and quality of nuclear power project document review. Text review ensures that the content is accurate and in compliance with specifications; format review ensures that the document looks neat and the information is clear; editing review focuses on details, such as coding, page numbers, etc., to avoid omissions. This division not only covers common problems and potential errors in the field of nuclear power engineering, improves the comprehensiveness and accuracy of document review, but also strengthens the compliance and reliability of documents, laying a solid foundation for the safe operation of nuclear power projects. In addition, this approach has also promoted the standardization and normalization of project management and improved the overall management level.
[0040] This application uses a neural network model to learn review rules and thus has the ability to learn autonomously. It can understand the laws and regulations in the field of nuclear power design. Based on the construction of a multi-professional and multi-disciplinary intelligent review library, it can quickly and accurately identify potential errors and flaws in design documents. At the same time, it can effectively solve the problems of high reliance on the experience of senior engineers, complex design documents, and high safety requirements in the design document review process. Compared with the traditional manual review mode, the review speed of the intelligent review system can be increased by about 100 times.
[0041] Advantages of additional aspects of the present invention will be given in part in the following description, and in part will become obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] The accompanying drawings constituting a part of the present disclosure are used to provide a further understanding of the present disclosure. The exemplary embodiments of the present disclosure and the description thereof are used to explain the present disclosure but do not constitute a limitation of the present disclosure.
[0043] Figure 1 A main flow chart of a method for intelligent review of drawings for nuclear power engineering provided by the present disclosure;
[0044] Figure 2 A detailed flow chart of an intelligent review method for drawings of nuclear power projects provided in the present invention. DETAILED DESCRIPTION
[0045] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0046] Embodiment 1
[0047] like Figure 1 As shown, this embodiment discloses a method for intelligent review of drawings for nuclear power engineering, comprising the following steps:
[0048] Step 1: Collect original engineering files and perform preprocessing; the original engineering files include IED engineering files and review rules; the review rules include review rules for text, format and editing;
[0049] Step 2: Generate a download link for the preprocessed original project file and initiate a review request;
[0050] Step 3: The intelligent review platform receives the download link and downloads the IED engineering files and review rules to be reviewed based on the review request;
[0051] Step 4: Use the trained neural network module to review the text, format and editing of the IED engineering documents to be reviewed based on the review rules, and output the review results.
[0052] Next, combine Figure 2 , a method for intelligent review of drawings for nuclear power engineering disclosed in this embodiment is described in detail.
[0053] In this embodiment, engineers prepare original engineering documents, namely, IED engineering documents and review rules in advance.
[0054] In order to ensure the security of IED project files during transmission and facilitate opening in any operating system such as Windows, macOS, Linux, and mobile devices, IED project files in various file formats (WORD, CAD drawings, etc.) are preprocessed and uniformly converted into rasterized PDF files.
[0055] The OCR model is used to extract text from the preprocessed PDF file. The OCR model scans the PDF file image from left to right and from top to bottom to extract text by line. If there is a gap in the text on the same line, it will be divided into multiple blocks, such as codes, English abbreviations, and cross-line text.
[0056] It should be understood that extracting text from a PDF file using OCR technology is achievable by those skilled in the art.
[0057] Review rules are the basis for ensuring the quality and compliance of nuclear power drawings and documents. Review rules include text, format and editing review rules. If they do not meet the requirements of the rules, the review results will be sent to the preparer.
[0058] The review rules provided in this embodiment specifically include:
[0059] 1. Text review rules
[0060] (1) DMN annotation verification before and after modification / change
[0061] The words "Before change" / "After change" and "Before modification" / "After modification" should appear in pairs. If they do not appear in pairs, a modification reminder pending instruction will be issued.
[0062] The DMN modification / change annotation verification provided in this embodiment is used to ensure the clarity and traceability of the modification or change, avoid confusion and misunderstanding, and improve the accuracy and reliability of nuclear power engineering documents.
[0063] (2) Modification description verification
[0064] When the drawing is upgraded, the modification description cannot just say "the whole drawing is modified", but the reason should be stated; when the file is upgraded, the modification page cannot just say "the whole text is modified", but the reason should be stated. If the above requirements are violated, a modification reminder pending instruction will be issued.
[0065] The modification description verification provided in this embodiment requires a detailed description of the modification reason, which helps subsequent engineering personnel to quickly understand the change background and evaluate the rationality and necessity of the change.
[0066] (3) Verification of the drawing modification description field
[0067] When the drawing is upgraded, all design change orders should be listed in the modification description column. If not listed, a modification reminder pending instruction should be issued.
[0068] The drawing modification description field check provided in this embodiment is used to ensure that all design change orders are clearly listed, which facilitates tracking and management of design changes and ensures the consistency and integrity of nuclear power engineering design.
[0069] (4) Open item number verification
[0070] The number in the "Open Item Number" column on the file (or drawing) should be consistent with the output open item number of the file (or drawing) in the design quality management platform. If the above requirements are violated, a modification reminder pending instruction will be issued.
[0071] The opening item number verification provided in this embodiment is used to ensure that the opening item number on the document (or drawing) is consistent with the number in the actual management platform, thereby promoting accurate transmission of information and timely resolution of problems.
[0072] (5) Verification of mandatory standards and regulations
[0073] Verify whether the latest valid version of mandatory standards and regulations is adopted; if not, issue a modification reminder pending instruction.
[0074] The mandatory standards and regulations version verification provided in this embodiment is used to ensure that the file complies with the latest mandatory standards and regulations, thereby improving the compliance and security of the project.
[0075] (6) Standardization check of English abbreviations and commonly used units
[0076] When the English abbreviations in the document body are inconsistent with commonly used abbreviations (for example, RV or RPV, etc.) and the commonly used units are not written in a standardized manner, a modification reminder pending instruction is issued.
[0077] The standardization check of English abbreviations and commonly used units provided in this embodiment improves the professionalism and readability of the document and reduces misunderstandings and errors by unifying the use of English abbreviations and units.
[0078] (7) Data result unit labeling verification
[0079] When the units are not indicated in the results in the chart, a modification reminder pending instruction is issued.
[0080] The data result unit labeling verification provided in this embodiment is used to ensure that the units of the data results in the chart are clearly labeled, thereby improving the accuracy and usability of the data.
[0081] The text review rules described in this specific embodiment focus on the accuracy and logic of the content of nuclear power engineering documents, including the completeness of modification instructions, compliance with standards and regulations, and the standardization of unit markings. This division can quickly focus on the core content of the document and quickly identify and correct potential errors or inconsistencies.
[0082] 2. Format review rules
[0083] (1) Open item column verification
[0084] When the file status is a construction file, if there is no open item, the corresponding "Open Item Content Description" column should be filled with "None" or "None"; when the file status is not a construction file, if there is no open item, the corresponding "Open Item Content Description" column should be filled with "Not Applicable". When the above rules are violated, a modification reminder pending instruction is issued.
[0085] The opening item column check provided in this embodiment is used to check whether the opening item content description is correctly filled in according to the file status, thereby improving the standardization and clarity of the file.
[0086] (2) Drawing / atlas catalog verification
[0087] No blank lines should be set between directory numbers. When a directory name is too long, it needs to cross lines. When crossing lines, the middle lines must be hidden or deleted. If the above requirements are violated, a modification reminder pending instruction will be issued.
[0088] The drawing / atlas catalog verification provided in this embodiment is used to standardize the catalog format, ensure the accuracy and readability of the catalog, and facilitate reference and indexing.
[0089] (3) Check the signature column
[0090] If there is no countersignature, "None" should be written in the countersignature column of the drawing and DMN. If the above requirements are violated, a modification reminder pending instruction will be issued.
[0091] The countersignature column verification provided in this embodiment is used to clarify the filling requirements of the countersignature column, ensure the completeness of the approval process of nuclear power engineering documents, and improve the legality and effectiveness of nuclear power engineering documents.
[0092] The format review rules described in this specific embodiment focus on the appearance and structure of the document, such as directory arrangement, filling in the countersignature column, and the use of the open item column. The correctness of the format not only affects the overall aesthetics of the document, but is also directly related to the clarity and readability of the information. Treating format review as an independent part helps ensure that nuclear power engineering documents meet unified standards in form and improve the professionalism and standardization of the documents.
[0093] 3. Editorial Review Rules
[0094] (1) Project code verification
[0095] When the project information in the drawing or document is inconsistent with the uploaded project, including the project number, unit number, engineering number, and project name contained in the document title page, text, and drawings, a modification reminder pending instruction is issued.
[0096] The project coding verification provided in this embodiment is used to ensure that the project information in the drawing or document is consistent with the uploaded project, prevent information mismatch, and improve the accuracy and traceability of the project.
[0097] (2) Chapter and figure number verification
[0098] When chapter numbers are repeated or skipped in a file, or the numbers of figures, tables, and chapters in the text index do not exist in the text, a modification reminder pending instruction is issued.
[0099] When there are duplications or skipped numbers in illustration numbers or table numbers, a modification reminder will be issued.
[0100] The chapter and figure number verification provided in this embodiment is used to prevent errors such as number duplication and number skipping, ensure the clarity and completeness of the file structure, and facilitate readers to understand and find information.
[0101] (3) Page number verification
[0102] When the page number displayed in the "Current Page" position in a file (including the directory) is repeated or skipped, or the page number in the "Total Pages" position is skipped, a reminder to the compiler to make changes is sent.
[0103] The page number verification provided in this embodiment is used to ensure the correctness and continuity of the document page numbers, improve the overall standardization and professionalism of the document, and facilitate later review and reference.
[0104] The editorial review rules described in this specific embodiment cover details such as project coding, chapter and figure numbers, page numbers, etc. These seemingly minor errors may have an adverse impact on the management and execution of the entire project if they are not corrected in a timely manner. Treating editorial review as a separate aspect helps to check the document in detail to ensure that every detail is accurate.
[0105] The review rules described in this embodiment are formulated based on the complexity, high risk and strict compliance requirements of nuclear power projects, and include all aspects of nuclear power project design, from material selection, equipment configuration, safety protection measures to construction process, construction period management, etc., with detailed regulations and standards. By subdividing the review rules into three aspects: text, format, and editing, and conducting strict reviews one by one, it can be ensured that the nuclear power project documents meet compliance requirements in terms of content, form, details, etc. These regulations and standards cover common problems in the field of nuclear power engineering that are prone to errors or have safety hazards. They are targeted at nuclear power engineering scenarios and can ensure the accuracy and compliance of drawings.
[0106] Based on such review rules, the neural network module is trained to provide a unified review framework and operating process for the neural network module. By learning the review rules, the neural network module can check and inspect the drawings item by item to ensure that every detail complies with regulations, which helps to quickly discover potential problems and risks and reduce the possibility of omissions and misjudgments, thereby improving the accuracy of the review.
[0107] It should be understood that the neural network module may adopt various large-scale language models, which are not specifically limited in this embodiment, and those skilled in the art may select a suitable model and complete the training as needed.
[0108] This embodiment subdivides the review rules into three aspects: text, format, and editing, which significantly improves the efficiency and quality of nuclear power project document review. Text review ensures that the content is accurate and in compliance with specifications; format review ensures that the document looks neat and the information is clear; editing review focuses on details, such as coding, page numbers, etc., to avoid omissions. This division not only covers common problems and potential errors in the field of nuclear power engineering, improves the comprehensiveness and accuracy of document review, but also strengthens the compliance and reliability of documents, laying a solid foundation for the safe operation of nuclear power projects. In addition, this practice has also promoted the standardization and regularization of project management and improved the overall management level.
[0109] Embodiment 2
[0110] like Figure 2 As shown, this embodiment provides a drawing intelligent review system for nuclear power engineering, including:
[0111] The design quality management platform is used to receive the original engineering files and transmit the original engineering files to the paperless platform; receive the original engineering files pre-processed by the paperless platform and generate download links; send review requests and download link lists to the intelligent review platform, and receive feedback from the intelligent review platform; the original engineering files include IED engineering files and review rules;
[0112] The paperless platform is used to receive the original engineering files sent by the design quality management platform for preprocessing, and return the preprocessed original engineering files to the design quality management platform;
[0113] The intelligent review platform is used to receive the review request and download link list sent by the design quality management platform, select the IED project file to be reviewed from the download link list based on the review request; conduct text, format and editing reviews based on the review rules, and feed back the review results to the design quality management platform.
[0114] In this embodiment, the design quality management platform (DMS platform) stores the review results in the database after receiving them. The IED compiler can enter the DMS platform to view them, and continue to modify them if they do not pass.
[0115] As an implementation mode, the sending of the review request and the download link list to the intelligent review platform is specifically: the design quality management platform calls the external interface of the intelligent review platform to send the review request and the download link list to the intelligent review platform.
[0116] Embodiment 3
[0117] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps of the intelligent review method for drawings of nuclear power engineering as described in the above-mentioned embodiment 1 are implemented.
[0118] Embodiment 4
[0119] This embodiment provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the steps of a method for intelligent review of drawings for nuclear power engineering as described in the first embodiment above are implemented.
[0120] The steps or modules involved in the above embodiments 2 to 4 correspond to those in embodiment 1. For the specific implementation, please refer to the relevant description of embodiment 1. The term "computer-readable storage medium" should be understood as a single medium or multiple media including one or more instruction sets; it should also be understood to include any medium that can store, encode or carry an instruction set for execution by a processor and enable the processor to execute any method in the present invention.
[0121] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for intelligent review of drawings for nuclear power engineering, characterized in that: include: Collect original engineering files and perform preprocessing; The original engineering documents include IED engineering documents and review rules; the review rules include review rules for text, format and editing; Generate a download link for the preprocessed original project file and initiate a review request; The intelligent review platform receives the download link and downloads the IED engineering files and review rules to be reviewed based on the review request; Using the trained neural network module, the IED engineering documents to be reviewed are reviewed in terms of text, format and editing based on the review rules, and the review results are output.
2. The method for intelligent review of drawings for nuclear power engineering according to claim 1, characterized in that: The preprocessing is to uniformly convert the IED engineering files into rasterized PDF files.
3. The method for intelligent review of drawings for nuclear power engineering according to claim 1, characterized in that: Before conducting intelligent review of the text, format and editing of the IED engineering documents to be reviewed, it also includes using OCR technology to recognize the pre-processed original engineering documents as text.
4. The method for intelligent review of drawings for nuclear power engineering according to claim 1, characterized in that: The text review rules include: Verify the markings before and after modification or change to see if the words before and after the change, as well as before and after the modification, appear in pairs; if not, issue a modification reminder to-do instruction; Verify the modification description: when upgrading drawings, files, or modifying the entire drawing, check whether the modification description clearly states the reason; if not, issue a modification reminder to be done; Verify the drawing modification description column. When the drawing is upgraded, check whether all design change orders are listed in the modification description column. If not, issue a modification reminder to be done. Open item number verification: check whether the number in the open item number column on the file or drawing is consistent with the open item number output in the file or drawing in the design quality management platform; if not, issue a modification reminder to be done instruction; Verify the version of mandatory standards and regulations to verify whether the latest valid version of mandatory standards and regulations is adopted; if not, issue a modification reminder to be done instruction; Standardization check of English abbreviations and commonly used units: when the English abbreviations in the document body are inconsistent with the commonly used abbreviations, or the commonly used units are not written in a standardized manner, a modification reminder pending instruction will be issued; Data result unit labeling verification. When the unit is not marked in the chart, a modification reminder will be issued.
5. The method for intelligent review of drawings for nuclear power engineering according to claim 1, characterized in that: The format review rules include: Open item column check: when the file status is a construction file, if there is no open item, the corresponding open item content description column is filled with None or None; when the file status is a non-construction file, if there is no open item, the corresponding open item content description column is filled with Not Applicable; if it is not filled in as required, a modification reminder pending instruction is issued; Check the catalog of drawings and atlases. No blank lines should be set between catalog numbers. If the catalog name exceeds the specified number of characters, it needs to be crossed, and the middle lines should be hidden or deleted when crossing lines. If the operation is not carried out as required, a modification reminder pending instruction will be issued; Check the co-signature column. If there is no co-signature, fill in the co-signature column of the drawing and DMN as "None". If it is not filled in as required, issue a modification reminder to be done.
6. The method for intelligent review of drawings for nuclear power engineering according to claim 1, characterized in that: The editorial review rules include: Project code verification: when the project information in the drawing or document is inconsistent with the uploaded project, a modification reminder pending instruction will be issued; the project information includes the project number, unit number, engineering number, and project name contained in the title page, text, and drawing of the document; Chapter and figure number verification: if there are duplicate or skipped chapter numbers in the document; if the figures, tables, and chapter numbers in the text index do not exist in the text; and if there are duplicate or skipped illustration and table numbers, a modification reminder pending instruction will be issued; Page number verification: when the page number displayed at the current page position in the file or directory is repeated or skipped, or the page number at the total page position is skipped, a modification reminder will be issued.
7. An intelligent drawing review system for nuclear power engineering, characterized in that: include: Design quality management platform, used to receive original engineering files and transfer them to paperless platform; Receive the original engineering files pre-processed by the paperless platform and generate download links; Sending a review request and a download link list to the intelligent review platform, and receiving feedback from the intelligent review platform; the original engineering files include IED engineering files and review rules; The paperless platform is used to receive the original engineering files sent by the design quality management platform for preprocessing, and return the preprocessed original engineering files to the design quality management platform; The intelligent review platform is used to receive the review request and download link list sent by the design quality management platform, and select the IED engineering file to be reviewed from the download link list based on the review request; Conduct text, format and editing reviews based on review rules, and provide feedback on the review results to the design quality management platform.
8. The intelligent drawing review system for nuclear power engineering as claimed in claim 7, characterized in that: The sending of the review request and the download link list to the intelligent review platform specifically includes: the design quality management platform calling the external interface of the intelligent review platform to send the review request and the download link list to the intelligent review platform.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of a method for intelligent review of drawings for nuclear power engineering as described in any one of claims 1-6 are implemented.
10. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps in the method for intelligent review of drawings for nuclear power engineering as described in any one of claims 1-6 are implemented.
Citation Information
Cited By
Nuclear power design file intelligent review method and system
CN120726662A
Nuclear power safety report examination method and system, electronic equipment and storage medium
CN121327159A
Automatic drawing auditing method and system for nuclear power instrument control display picture
CN121478799A