Integrated intelligent analysis method for power grid geographical edge layout and electrical topology model
Through the integrated intelligent analysis method of grid geographic layout and electrical topology model, the electromagnetic interference area is identified and adjusted, and the interference problem of electromagnetic fields on migrating migratory birds is solved, ensuring the stability of power supply and the safety of migratory bird navigation.
Patent Information
- Application Number
- CN202411115499.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-29
Smart Images

Figure CN119047628A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of information technology, and in particular to an intelligent analysis method integrating geographical layout of power grid and electrical topology model. Background Art
[0002] In today's society, with the continuous expansion of human activities, the interaction between power infrastructure and natural ecosystems has become increasingly prominent, especially in sensitive areas where migratory bird migration routes intersect with high-voltage transmission line layouts. In these areas, migratory birds lower their flight altitudes due to terrain restrictions, making them more susceptible to potential interference from electromagnetic fields generated by power facilities. This interference may disrupt the magnetic induction navigation mechanism they rely on, threatening the safety and efficiency of migration. In response to this challenge, it is particularly important to study and implement a technical solution that can monitor the migratory routes of migratory birds and the surrounding electromagnetic environment in real time, and dynamically optimize the grid configuration to reduce the interference with the magnetic induction of migratory birds. However, the implementation of this technical solution faces many difficulties, including but not limited to the complex integrated analysis of the geographical and electrical characteristics of the power grid, the deployment of a large-scale environmental monitoring sensor network and its data processing, the stability of the power system during the adjustment of the power grid structure, and how to accurately evaluate the specific impact of electromagnetic fields on the navigation ability of migratory birds and formulate scientific adjustment strategies. Therefore, how to effectively reduce the electromagnetic impact on migratory bird migration while ensuring a stable power supply has become a technical problem that needs to be solved urgently. Summary of the invention
[0003] The present invention provides an intelligent analysis method integrating power grid geographical layout and electrical topology model, which mainly includes:
[0004] Based on the power grid equipment information and the electrical topological connection relationship between the equipment, the CIM model of the valley and canyon areas is integrated;
[0005] Based on the CIM model, the geographical location and attributes of power grid equipment are obtained to generate a power grid distribution map that reflects the actual geographical location of power equipment and lines in valleys and canyons;
[0006] Through the CIM model, transformers, circuit breakers, transmission lines in valleys and canyons and how they are interconnected are identified to build an electrical topology model;
[0007] Based on the electromagnetic field characteristics of power facilities in valleys and canyons, the electromagnetic field distribution model of each power facility is generated, and the migratory bird path data and electromagnetic field distribution model are integrated to identify areas where electromagnetic fields have potential interference with migratory bird migration;
[0008] The electromagnetic field intensity data and migratory bird migration path information are obtained in real time through sensors, and the impact of electromagnetic fields on migratory bird migration is analyzed in combination with historical migratory bird data.
[0009] According to the analysis results of the impact of electromagnetic fields on migratory birds, a plan for adjusting the power grid topology was formulated and implemented to avoid interfering with the magnetic field navigation of migratory birds by switching the operation mode of the power grid;
[0010] Track the migration dynamics of migratory birds in valleys and canyons and the real-time operation status of the power grid, and adjust the topology of the power grid according to changes in the migratory routes of migratory birds.
[0011] The technical solution provided by the embodiment of the present invention may have the following beneficial effects:
[0012] The present invention discloses an intelligent analysis method integrating the geographical layout of power grid and the electrical topology model, including integrating and analyzing power grid equipment data and environmental ecological data, adjusting the power grid topology structure in combination with the migratory path of migratory birds and the power grid topology structure to reduce the interference of electromagnetic fields on the migration of migratory birds; executing the power grid topology adjustment plan, switching the power grid operation mode to reduce the electromagnetic field intensity in specific interference areas, thereby helping to protect the magnetic field navigation of migratory birds from interference; this not only improves the flexibility and safety of power grid operation, but also protects biodiversity, which is of great significance to ecological environmental protection and sustainable development. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 The present invention is a flow chart of an intelligent analysis method for integrating geographical layout of power grid and electrical topology model.
[0014] Figure 2 The present invention is a schematic diagram of an intelligent analysis method integrating geographical layout of power grid and electrical topology model. DETAILED DESCRIPTION
[0015] The following will describe the technical solutions in the embodiments of the present invention in detail in conjunction with the accompanying drawings in the embodiments of the present invention. The described embodiments are only part of the embodiments of the present invention.
[0016] like Figure 1-2 In this embodiment, a method for intelligently analyzing the integrated geographical layout of a power grid and an electrical topology model may specifically include:
[0017] Step S101 : Based on the power grid equipment information and the electrical topological connection relationship between the equipment, a CIM model of the valley and canyon area is integrated.
[0018] According to the power grid equipment information, the unique identification, equipment type, and basic attributes of the geographic location coordinates of each device are obtained. By analyzing the electrical topological connection relationship between the devices, the connection mode between the devices is determined, including series, parallel, and ring networks. According to the geographical location coordinates of the equipment, the valley or canyon area where each device is located is determined, and the equipment is partitioned and marked. The equipment topology in each area is independently analyzed to extract the key equipment nodes and key connection paths in the area. The CIM modeling standard is used to encapsulate the equipment attributes, topological structure, key nodes, and path information of each area. The connection interface between regions is defined in the CIM model to achieve the interconnection and interoperability of the CIM models in the valley and canyon areas.
[0019] For example, the ledger information of 1,000 power grid devices is obtained and analyzed through the China Southern Power Grid Zhikan platform, and the basic attributes such as the unique identification, device type, and geographic location coordinates of each device are obtained. By analyzing the electrical topological connection relationship between the devices, it is determined that 800 devices are connected in series, 150 devices are connected in parallel, and 50 devices form a ring network connection. Using the graph theory algorithm, 1,000 devices are regarded as nodes, and 1,500 connection relationships are regarded as edges to construct a topological graph model of power grid equipment. According to the geographic location coordinates of the equipment, it is determined that 300 of the 1,000 devices are located in the valley area and 700 devices are located in the canyon area, and the equipment is marked for partitioning. The 300 device topological graph models in the valley area are independently analyzed, and 20 key device nodes and 50 key connection paths are extracted; the 700 device topological graph models in the canyon area are independently analyzed, and 50 key device nodes and 100 key connection paths are extracted. Using the CIM modeling standard, the 300 device attributes, topology, 20 key nodes and 50 key paths in the valley area are encapsulated; the 700 device attributes, topology, 50 key nodes and 100 key paths in the canyon area are encapsulated. In the CIM model, 10 inter-regional connection interfaces are defined to achieve the interconnection and interoperability of the CIM models in the valley and canyon areas. Through topological analysis and flow calculation, it is evaluated that the power transmission capacity within the valley area is 500MW, the power transmission capacity within the canyon area is 800MW, and the power transmission capacity between regions is 300MW; the load distribution in the valley area is 20% residential electricity, 30% industrial electricity, and 50% commercial electricity; the load distribution in the canyon area is 30% residential electricity, 50% industrial electricity, and 20% commercial electricity.
[0020] Step S102, obtaining the geographical location and attributes of power grid equipment based on the CIM model, and generating a power grid distribution map reflecting the actual geographical location of power equipment and lines in valleys and canyons.
[0021] Parse the CIM model and extract key attribute information of the power equipment. The key attribute information of the power grid equipment includes equipment ID, equipment type, conductor material, and tower model attributes to form an equipment attribute dictionary; use the equipment ID as the association key to associate and match the equipment attribute dictionary with the equipment spatial data; determine whether the equipment is located in the valley or canyon area based on the latitude and longitude coordinates of the equipment; for the power equipment located in the valley or canyon, extract the terrain characteristics of its terrain undulation, slope, and slope direction, and add the terrain characteristics to the equipment attribute dictionary; for the transmission line, obtain the coordinates of the starting and ending points of the line by tracing the conductor segment object in the CIM model to generate the spatial geometric information of the line; integrate the equipment attribute dictionary and the spatial geometric information of the line to generate a network data set reflecting the topological structure of the power network; match the corresponding symbols for the power equipment and the transmission line respectively to form a map of the power equipment and the line; integrate the terrain base map of the valley and the canyon and the map of the power equipment and the line, combine the spatial distribution of the power equipment and the line with the terrain, and generate a power grid distribution map reflecting the actual geographical location of the power equipment and the line in the valley and the canyon.
[0022] For example, by parsing the CIM model, the key attribute information of the power grid equipment, such as equipment ID, equipment type, conductor material, tower model, etc., is extracted to construct the equipment attribute dictionary. The attribute dictionary can be in JSON format, and each device corresponds to a JSON object. The key of the object is the attribute name and the value is the attribute content. Using the device ID as the association key, the attribute dictionary is associated and matched with the device spatial data in the geographic information system through spatial query and attribute connection operations to obtain the geographical location information such as the longitude and latitude coordinates, the location terrain, and the altitude of each device. According to the longitude and latitude coordinates of the equipment, spatial analysis such as buffer analysis and overlay analysis is performed based on the geographic information system to determine whether the equipment is located in the valley or canyon area. The terrain features such as terrain undulation, slope, and slope direction are extracted and calculated through DEM data, and these feature attributes are added to the equipment attribute dictionary to enrich the attribute information of the equipment. For the transmission line, by tracing the wire segment (Wire) object in the CIM model, the coordinate information of the starting point and the end point of the line is collected, and then these coordinates are used to construct the spatial direction of the line with the help of the LineString geometry type to obtain the spatial geometry information of the line. Combined with the spatial geometric information of equipment points and lines, the network analysis function of the geographic information system is used to generate a network dataset reflecting the topological structure of the power network through algorithms such as shortest path analysis and accessibility analysis. The network dataset contains elements such as nodes, edges, and turns, and is stored in the Geodatabase format. The power equipment and lines are symbolized based on the geographic information system, and different symbolization styles are designed according to the attributes such as equipment type and line level. For example, transformer-shaped point symbols are applied to equipment such as substations, while corresponding switch symbols are used to mark switchgear. Similarly, different line symbol styles are applied to lines according to their levels. For example, 110 kV lines are represented by red wide lines, while 220 kV lines are marked with green wide lines to enhance readability and distinction. Beautiful and intuitive maps of power equipment and lines are generated through symbolization. By superimposing the topographic base map of valleys and canyons, the spatial distribution of power equipment and lines is combined with the terrain to generate a power grid distribution map reflecting the actual geographical location. The map annotation function is used to mark key attribute information such as equipment ID, line name, and voltage level on the map. The generated power grid distribution map can be spatially queried and statistically analyzed, such as the number of devices and line length in a certain area. The power grid map can also be published as a WebMapService (WMS) service through open source platforms such as GeoServer, providing online browsing and query functions. Users can access the WMS service through a Web browser to view the power grid map. Based on the power grid distribution map, three-dimensional scene modeling and simulation of the mountain power grid are carried out.Through ArcGIS Pro and other 3D GIS platforms, 3D terrain models of valleys and canyons are constructed. High-precision texture images are obtained by using drone oblique photogrammetry and other technologies, and attached to the terrain model to improve the sense of reality. The 3D models of power equipment and lines, such as towers and substations, are accurately matched to the 3D terrain scene, and processed by mapping and rendering to generate realistic 3D power grid scenes. The interactive functions such as scene roaming and flight browsing provided by the 3D GIS platform are applied to realize the immersive display and analysis of mountain power grids, and intuitively evaluate the impact of terrain on the layout and operation of power grid facilities. When parsing CIM model files, Python's XML parsing library, such as xml.etree.ElementTree, can be used to parse CIM / XML files step by step. By searching for key equipment tags such as cim:PowerTransformer and cim:ACLineSegment, attribute information such as equipment ID, rated voltage, and rated capacity can be extracted. For example, for transformer equipment, the transformer rated voltage = "110kV" and rated capacity can be extracted.
[0023] = "50MVA" and other attributes, construct an attribute dictionary in JSON format, such as
[0024] {"ID":"TR001","Voltage":"110kV","Capacity":"50MVA"}. When associating geographic information, the SpatialJoin tool of the ArcPy library can be used to spatially connect the attribute dictionary with the device feature class in the geographic database using the device ID as the connection field to achieve the association and transfer of attribute information. For extracting the terrain features of valleys and canyons, the slope and aspect values of each device point can be calculated based on the SRTMDEM data with a resolution of 30 meters using the Slope and Aspect tools of ArcGIS. Then, the ZonalStatistics tool is used to take the device point as the region to count the average slope, aspect and other terrain feature values of the region where it is located, and add them to the device attribute dictionary. The LineString class of the Shapely library can be used to construct the spatial geometric information of the line according to the coordinates of the start and end points of the wire segment in the CIM model. Then, the NetworkX library is used to generate a power grid network topology dataset with direction and weight based on the line geometry information and the device point geometry information through the Dijkstra shortest path algorithm. When performing spatial query analysis on the generated power grid distribution map, the SelectByLocation tool of the ArcPy library can be used to query equipment and lines based on spatial location relationships. For example, query all towers within 500 meters of the substation A, or query transmission lines located in areas above 1,000 meters above sea level. In the construction of three-dimensional scenes, the three-dimensional analysis function of ArcGIS Pro can be used to perform TIN (irregular triangulated network) modeling on the terrain of valleys and canyons, and the three-dimensional scene can be automatically modeled and rendered through CityEngine software. The three-dimensional models of power equipment and lines, such as substations, towers, etc., are batch imported into the three-dimensional scene, and precise alignment with the terrain is achieved through spatial coordinate matching, so as to obtain a power grid distribution map reflecting the actual geographical location of power equipment and lines in valleys and canyons.
[0025] Step S103, using the CIM model, identifying the transformers, circuit breakers, transmission lines and their interconnection methods in the valleys and canyons, and constructing an electrical topology model.
[0026] Parse the CIM model, extract the attribute information of the power equipment object to form a device attribute dictionary; extract and match the topological nodes and device endpoints in the CIM model, and generate an electrical topological structure centered on the topological node and connecting multiple devices, including generating wire segments between devices based on the connection relationship between devices in the electrical topological structure; perform a topological rationality check on the generated electrical topological structure, including tracing the electrical connection path to determine whether there are connectivity errors or dangling nodes; match the topological nodes with the actual geographical locations through the geographic coordinate information of the power equipment, and generate an electrical topology model that integrates electrical topology and geographic topology.
[0027] For example, by parsing CIM / XML files, using XML parsing libraries such as ElementTree, searching for tags such as "cim:PowerTransformer", "cim:Breaker", and "cim:ACLineSegment", the power equipment objects such as transformers, circuit breakers, and transmission lines in the CIM model are identified. The key attribute information such as the unique identification ID, device name, voltage level, and rated capacity of each device object is extracted to build a device attribute dictionary. The topological nodes "cim:TopologicalNode" and endpoints "cim:Terminal" in the CIM model are traversed to obtain the ID of each topological node and the list of device endpoints connected to it. According to the device ID of the endpoint, the specific device and its attributes connected to each topological node are matched with the device attribute dictionary. Thus, an electrical topological structure with multiple devices connected to the topological node as the center is obtained. For valley and canyon areas, the geographic coordinate information of the equipment in the CIM model is matched with the valley and canyon vector boundaries in an independent geographic information system (such as ArcGIS) through spatial overlay analysis to identify the power equipment located in the valley or canyon. Match the IDs of these devices with the electrical topology generated previously to obtain the local electrical topology within the valley and canyon as part of the entire power topology. Based on the connection relationship and physical location information between the devices in the electrical topology, the minimum spanning tree algorithm, such as the Kruskal algorithm or the Prim algorithm, is used to automatically generate the wire segments (LineSegment) between the devices. Starting from all device nodes, a weighted graph is constructed based on the physical distance between the nodes, and then the edge with the smallest weight is selected to connect the nodes until all nodes are connected. For devices such as transformers and circuit breakers, the connection relationship between the primary and secondary sides is determined based on their endpoint information, and detailed topology structures such as transformer windings and circuit breaker ports are constructed. The generated electrical topology is checked for rationality. The verification rules include: connectivity check, that is, ensuring that all device nodes are connected and there are no isolated nodes; parameter matching check, that is, verifying whether the voltage level, capacity and other parameters of the connected devices match; power supply path check, that is, tracing the power supply path from the power supply to the load to ensure that the path is complete and without loops. For the topological problems found, mark and alarm, prompting the user to check and correct them. The verified electrical topology is integrated with geographic information. The electrical topology nodes are matched with the corresponding device geographic elements in the geographic information system through the device ID, and the geographic attributes such as geographic coordinates, location, and terrain features are attached to the electrical topology nodes and connections through spatial overlay analysis. The electrical topology model that integrates electrical topology and geographic topology and describes the valley and canyon power grid is generated to achieve comprehensive management and analysis of multi-dimensional information such as equipment, topology, and geography.Based on the electrical topology model, automatic layout algorithms such as force-directed layout algorithms, such as Fruchterman-Reingold algorithm, hierarchical layout algorithms, such as Sugiyama algorithm, etc. are applied to automatically generate beautiful and clear topology diagrams. According to the attributes such as equipment type, voltage level, topology level, etc., the node shape, size, color, connection style, thickness, color and other visualization styles are reasonably configured. Through optimization strategies such as node avoidance and cross minimization, the layout is improved in terms of aesthetics and readability. Finally, a valley and canyon power grid topology diagram that meets the electrical design specifications and aesthetic requirements is generated, which intuitively displays the topological composition and connection mode of the power grid. When applying ElementTree to parse CIM / XML files, XPath expressions can be used to quickly locate and extract target device information. For example, the " / / cim:PowerTransformer" expression can match and extract the ID attributes of all transformers. For the traversal of topological nodes and endpoints, a depth-first search algorithm can be used to obtain the relationship between nodes by recursively traversing the XML tree to build a complete topology structure. When identifying valley and canyon equipment, the SelectLayerByLocation function of the ArcPy library can be used. The vector boundaries of valleys and canyons are used as selection elements, and the equipment points are used as target elements for spatial overlay analysis. All equipment falling within the boundaries of valleys and canyons will be selected and extracted. For the automatic generation of wire segments, the primary equipment such as substations and switch stations are used as the starting and ending nodes, and the secondary equipment such as distribution stations, ring network cabinets, and branch boxes are used as intermediate nodes. The Kruskal minimum spanning tree algorithm is used for wire path planning. By setting the wire material, such as steel core aluminum stranded wire LGJ-240 / 30, voltage level, such as 10kV and other attribute parameters, the physical and electrical characteristics of the wire are determined. When performing topological rationality verification, a rule-based consistency check method can be used. For example, for connectivity checks, all topological nodes are traversed and their degrees (the number of connected edges) are counted. Nodes with a degree of 0 are isolated nodes; for power supply path checks, starting from the power supply point, a depth-first search is applied to record the traversed nodes and edges. If a node that has been visited is encountered, it means that there is a loop. In the fusion of electrical topology and geographic topology, the spatial join operation can be applied, with the device ID as the connection field, to match the electrical topology elements with the geographic elements one-to-one to obtain the electrical topology model.
[0028] Step S104, generating an electromagnetic field distribution model of each power facility based on the electromagnetic field characteristics of the power facilities in the valleys and canyons, integrating the migratory bird path data and the electromagnetic field distribution model, and identifying areas where the electromagnetic field has potential interference with migratory bird migration.
[0029] The spatial location information of power facilities in valleys and canyons is obtained, including three-dimensional geographic information data of substations, transmission line towers, and distribution equipment, to form geographic information data of power facilities; the electrical parameters of each power facility are extracted, including the voltage level and capacity of the substation, the voltage level, conductor model, and operating current of the transmission line; the electric field strength and magnetic induction intensity generated by each power facility are calculated according to the spatial location and electrical parameters of the power facilities; the calculated electric field strength and magnetic induction intensity data are associated with the spatial location of the power facilities, and the electromagnetic field data are interpolated into three-dimensional space to form an electromagnetic field distribution model; the electromagnetic field distribution models of different power facilities are spatially superimposed and analyzed to obtain electromagnetic field overlapping areas; the electromagnetic field overlapping areas are superimposed and analyzed with the terrain data of valleys and canyons to extract the electromagnetic field overlapping areas located in valleys and canyons; the electromagnetic environment of the electromagnetic field overlapping areas is evaluated in combination with the spatial relationship between the migratory routes of migratory birds and the electromagnetic field overlapping areas to identify areas where the electromagnetic field has potential interference with migratory bird migration.
[0030] Exemplarily, the spatial location information of power facilities is obtained, including three-dimensional geographic information data such as longitude and latitude coordinates, altitude, etc. of substations, transmission line towers, distribution equipment, etc., to establish a geographic information database of power facilities. At the same time, the key electrical parameters of each power facility, such as the voltage level and capacity of the substation, the voltage level, conductor model, and operating current of the transmission line, are extracted as input conditions for calculating the electromagnetic field strength. According to the type, voltage level, and spatial location of the power facility, a suitable numerical simulation method is selected to calculate the power frequency electric field strength and power frequency magnetic induction strength generated by it. For substations, the three-dimensional finite element method can be used to model the main transformer, busbar, frame, etc. of the substation to calculate the distribution of the electric field strength at each point in space. The finite element method discretizes the solution area into a finite number of units, establishes a local interpolation function on the unit, and thus solves the distribution of the electromagnetic field. For transmission lines, the moment magnetic potential method can be used to model the conductors, towers, terrain, etc. to calculate the electromagnetic field distribution along the corridor. The moment magnetic potential method simplifies complex three-dimensional problems into two-dimensional problems by introducing magnetic vector potential, and can efficiently calculate the electromagnetic field of transmission lines. The calculated electric field strength and magnetic induction intensity data are associated with the spatial position of the power facilities to generate a three-dimensional electromagnetic field distribution model for each facility. Using spatial interpolation algorithms, such as inverse distance weighted interpolation and ordinary kriging interpolation, the discrete electromagnetic field data are interpolated into a continuous three-dimensional space to obtain a continuous electromagnetic field distribution surface. For substations, a three-dimensional electromagnetic field distribution surface centered on the substation can be generated; for transmission lines, a three-dimensional electromagnetic field distribution surface belt along the corridor can be generated. The three-dimensional electromagnetic field distribution surfaces of different power facilities are spatially superimposed and analyzed to identify overlapping areas with high electromagnetic field intensity. The grid overlay analysis method is used to superimpose the electromagnetic field distribution grids of different facilities, and the areas where the electric field intensity or magnetic induction intensity exceeds a specific threshold after superposition are extracted as electromagnetic field overlap areas. The selection of thresholds needs to be determined according to the voltage level of power facilities, the arrangement of conductors and other factors. For transmission lines of 110kV and below, the electric field strength threshold can be 4kV / m, and the magnetic induction strength threshold can be 0.1mT; for transmission lines of 220kV and above and large substations, the electric field strength threshold can be 5kV / m, and the magnetic induction strength threshold can be 0.2mT. By setting scientific and reasonable thresholds, electromagnetic field overlap areas of different levels can be obtained. The electromagnetic field overlap area is superimposed and analyzed with the terrain data of valleys and canyons to extract the electromagnetic field overlap area located in the valleys and canyons. The valley and canyon areas are identified and extracted using indicators such as terrain undulation and slope. Using ArcGIS spatial analysis tools, such as the terrain undulation tool (TerrainRuggedness) and the slope tool (Slope), the terrain undulation and slope values of each raster pixel are calculated, and the valley and canyon areas are extracted by setting thresholds.Then, using the OverlayAnalys is tool, the electromagnetic field overlap area grid is superimposed with the valley and canyon area grid to find the intersection area between the two as the electromagnetic field overlap area in the valley and canyon. Considering the spatial relationship between the migratory route of migratory birds and the electromagnetic field overlap area, the electromagnetic environment of the overlap area is evaluated. Collect multi-source data such as GPS tracking data, radar observation data, infrared camera monitoring data, and ground survey records of migratory birds to obtain the main migratory routes of migratory birds. Use ArcGIS's buffer analysis tool to generate buffers for migratory bird migration routes. The buffer distance can be determined based on the flight altitude of migratory birds and the spatial attenuation characteristics of the electromagnetic field. Overlay analysis is performed on the migration route buffer and the electromagnetic field overlap area. If there is an intersection between the two, it means that the overlap area may interfere with the magnetic induction of migratory birds and needs to be paid special attention. Based on the overlay analysis results of the migration route buffer and the electromagnetic field overlap area, areas with high risk of electromagnetic field interference with migratory bird migration are identified. When establishing a geographic information database for power facilities, the PostGIS spatial database can be used to store the spatial location information of substations, transmission line towers, distribution equipment, and corresponding electrical parameters, such as the voltage level of the substation is 220kV, the capacity is 3x240MVA, the voltage level of the transmission line is 500kV, and the conductor model is 4xLGJ-400 / 50, in the database, and query and manage through SQL statements. For the electromagnetic field calculation of the substation, COMSOL Multiphysics ics finite element analysis software is used to perform three-dimensional geometric modeling of the main transformer, busbar, frame, etc., and set the parameters of the power frequency current, material properties, etc. of each device, such as the high-voltage side current of the main transformer is 1147A, and the busbar section is 100x10mm. 2etc. Adaptive meshing method was used to generate a finite element model containing about 500,000 tetrahedral units, and the Poisson equation was solved to obtain the electric field intensity distribution in the space around the substation. For the electromagnetic field calculation of the transmission line, the HIFREQ module in CDEGS software was used to perform parametric modeling on the line's conductors, towers, terrain, etc., such as the number of conductor splits was 4, the line spacing was 400mm, and the height of the double-circuit tower was 45m. The parameters such as the power frequency current and earth resistivity of the line were set to generate a three-dimensional grid model containing about 100,000 nodes. The moment magnetic potential method was used to calculate the power frequency magnetic induction intensity distribution near the line, and the influence of factors such as the height of the conductor from the ground and the phase sequence was considered. The calculation results were kriging interpolated using the spatial interpolation tool of ArcGIS to generate 10m resolution electromagnetic field distribution raster data. Then, the grid algebra tool was used to perform superposition analysis of the electromagnetic fields of different facilities, and the overlapping areas with electric field intensity exceeding 4kV / m and magnetic induction intensity exceeding 0.1mT were extracted. Using ArcGIS hydrological analysis tools, such as Fill and FlowDirection, the 30m resolution SRTMDEM data was processed and the terrain relief and slope of each grid pixel were calculated. It was found that a 110kV transmission line passed through a canyon with an average slope of 28° and a terrain relief of 17 meters. After superposition analysis, it was found that the electromagnetic field overlap zone in the canyon was 2 kilometers long, accounting for 5% of the total length of the transmission line. The spatial relationship between the migratory route of migratory birds and the electromagnetic field overlap zone was evaluated. For example, a migratory route of migratory birds intersected with a 220kV transmission line. The height of the transmission line above the ground at the intersection was 25 meters, and the flight height of migratory birds was 20-100 meters. After generating a 200-meter wide migratory route buffer zone, it was superimposed with the electromagnetic field overlap zone and found that the two had an 800-meter long intersection area, accounting for 2% of the total length of the migratory route, which may interfere with the magnetic induction of migratory birds.
[0031] Step S105, obtaining electromagnetic field intensity data and migratory bird migration path information in real time through sensors, and analyzing the impact of electromagnetic fields on migratory bird migration in combination with historical migratory bird data.
[0032] Obtain historical migration data of migratory birds, including migration time, migration route, flight speed, and rest duration information; pre-process historical migration data of migratory birds, and group and summarize them according to individual migratory birds and migration years to form a structured historical migration data set; synchronize the electromagnetic field monitoring data and migratory bird migration data according to timestamps; generate an electromagnetic attribute data set with migratory bird migration track points based on the electromagnetic field intensity values extracted at the locations of migratory birds; analyze the electromagnetic attribute data with migratory bird migration track points, calculate the statistical indicators of electric field intensity and magnetic induction intensity on the migratory bird migration path, and Group statistics were conducted according to the dimensions of individual migratory birds, migration years, and migration sections; significant differences in electromagnetic exposure levels between different migratory birds and different migration years were tested; migratory bird migration characteristic indicators were established using historical migratory bird data, including migration distance, migration duration, daily flight mileage, flight altitude, migration speed, and stop frequency indicators; a generalized linear model between electromagnetic fields and migratory bird migration characteristics was established using the migratory bird migration characteristic indicators as independent variables and electromagnetic field intensity as the dependent variable to reveal the influence of electromagnetic fields on migratory bird migration behavior and analyze the impact of electromagnetic fields on migratory bird migration.
[0033] For example, 20 electromagnetic field monitoring sensors, such as the electromagnetic radiation tester SEM600, can be deployed on the migratory bird migration channel to monitor the migration path in full coverage. The sensor sampling frequency is set to 10Hz, the range covers 10kHzˉ8GHz, the sensitivity is better than 0.01V / m and 0.1nT, and the positioning accuracy reaches 1 meter. The sensor is networked through the RS-485 bus, and the data is transmitted back to the cloud database in real time through the 4GDTU module. The cloud uses the MySQL database, and the sensor ID, timestamp, electric field strength, magnetic induction strength, longitude, latitude and other fields are designed. The partition table is used to partition the data according to the date to improve the efficiency of data query. GPS / GSM dual-mode trackers can be implanted in migratory birds such as swan geese and white-naped cranes, such as the backpack transmitter Duck-4C of the German e-obs company, which weighs less than 25g, has a spatial accuracy of better than 5 meters, and the positioning frequency can be set to 1 time / hour. The battery life can reach 3 years. The transmitter transmits the location, flight speed, altitude and other data of migratory birds to the ground receiving station through the GSM network, and then decodes it through special software and stores it in the MySQL database. The time series database InfluxDB is used, and the database is designed with migratory bird ID, device ID, timestamp, longitude, latitude, altitude, speed and other fields to support high-concurrency data writing and aggregate query. The historical migration data and electromagnetic field monitoring data of migratory birds in the study area for the past 10 years are extracted from the MySQL and InfluxDB databases. The Python Pandas library is used to write data cleaning and preprocessing scripts to filter invalid GPS positioning points, eliminate abnormal measurement values caused by sensor failures, and unify the time format to the ISO8601 standard and the coordinate system to the WGS-84. The data can be grouped, sorted and aggregated according to the dimensions of migratory bird individuals, migration years, sensor locations, etc. to form a structured data set; the timestamps of migratory bird migration data and electromagnetic field monitoring data are aligned, and the linear interpolation method is used to adjust the time granularity of the electromagnetic field data to be consistent with the GPS positioning data of migratory birds, that is, once an hour. For the spatial granularity of electromagnetic field data, the inverse distance weighted interpolation method (IDW) was used. With the migratory bird GPS location point as the center and a search radius of 50 kilometers, the surrounding electromagnetic field monitoring points were spatially interpolated to obtain the estimated values of the electric field strength and magnetic induction intensity at the location of the migratory bird. Then, the interpolated electromagnetic field data were associated with the migratory bird migration trajectory data through longitude and latitude matching to generate the electromagnetic attribute data set of the migratory bird migration trajectory points. The electromagnetic attribute data of the migratory bird migration trajectory points were sampled 1000 times using the Bootstrap sampling method, and the means and 95% confidence intervals of the electric field strength and magnetic induction intensity in different time periods, different regions, and different altitude layers were calculated. A two-way ANOVA was used with the migration year and migratory bird species as independent variables to test the differences in electromagnetic exposure levels between different years and different species.Using historical migration data of migratory birds, migration characteristic indicators such as migration distance, migration duration, daily flight mileage, flight altitude, migration speed, and stop frequency were extracted. Spearman rank correlation analysis was used to calculate the correlation coefficient and p value between electromagnetic field intensity and each migration characteristic indicator, and the significantly correlated indicators were screened out. Then, a generalized linear model (GLM) was constructed with these indicators as independent variables and electric field intensity and magnetic induction intensity as dependent variables. The maximum likelihood method was used to estimate the model parameters. The overall significance of the model and the significance of each indicator were evaluated by the likelihood ratio test, and the determination coefficient and AIC value of the model were calculated to evaluate the goodness of fit of the model. On the basis of the GLM model, environmental factors such as wind speed, temperature, precipitation, and habitat type were further introduced, and the canonical correspondence analysis (CCA) method was used to explore the relationship between electromagnetic fields, migratory characteristics of migratory birds, and environmental factors. CCA maximizes the correlation between variable sets by finding linear combinations of three groups of variables, and the significance of CCA results is evaluated by permutation test. For the results of CCA, a two-dimensional ordination diagram can be drawn to show the scores of different variables on the ordination axis and reveal the correlation between them. 20 SEM600 electromagnetic radiation testers were deployed in the two major migratory stopover sites of migratory birds A and B, covering an area of 10,000 square kilometers. The sensor sampling rate is 10 times per second, the frequency response range is 10kHzˉ8GHz, the sensitivity can reach 0.01V / m and 0.1nT, and the GPS positioning accuracy is better than 1 meter. The RS-485 bus is used for networking on site, and the data is uploaded to the Alibaba Cloud MySQL database every 5 minutes through the 4GDTU module. The Alibaba Cloud MySQL database is partitioned and stored according to the sensor ID and date, and each partition retains the data of the last 30 days. For 100 swan geese and white-naped cranes, Duck-4CGPS / GSM dual-mode backpack transmitters are worn, and the weight is controlled within 3% of the body weight. The transmitter performs GPS positioning and GSM data transmission every hour, with a spatial accuracy of less than 5 meters, and the battery can work continuously for 3 years. The receiving station uses the InfluxDB time series database, which is synchronized with the GPS receiving time, decodes and stores the data, and can receive more than 10,000 migratory bird location data every day. Pandas is used to clean the historical data of the past 10 years, and the PDOP values of GPS positioning points greater than 5 are eliminated, and the Z scores of sensor electric field strength and magnetic induction intensity greater than 3 are eliminated. The time format is unified to ISO8601, the coordinates are unified to WGS-84, and resampled according to time scales such as hours, days, and months. Using the Scipy library, the electromagnetic field data is linearly interpolated, and the inverse distance weighted interpolation with a radius of 50km is used to spatially connect the migratory bird GPS location points with the interpolation results to obtain the hourly electromagnetic field properties on the migratory path of migratory birds. Bootstrap is used to repeat sampling 1000 times to construct the confidence interval of electromagnetic field strength under the dimensions of migration date, migration path, flight altitude, etc.Two-way ANOVA was used to test the significance of differences between different years and species (p<0.05). TukeyHSD was used to correct the p value for multiple comparisons (FDR<0.05). Using the Statsmodels library, a generalized linear model was constructed, with eight indicators such as migration distance, daily flight mileage, and flight altitude as independent variables, and electric field intensity and magnetic induction intensity as dependent variables. The model parameters were estimated using the Gamma distribution and Log link function. The likelihood ratio test was used to evaluate the overall significance of the model (p<0.01) and the significance of each indicator (p<0.05), and the McFadden goodness of fit (ρ2>0.2) and AIC value of the model were calculated. On this basis, combined with the ERA5 reanalysis data, the daily environmental factors such as wind speed, temperature, and precipitation on the migratory path of migratory birds were extracted, and the Vegan package was used for canonical correspondence analysis. Through the permutation test p<0.05 and the heterogeneity test VIF<5, significant environmental constraint factors were screened out, and a two-dimensional ordination diagram was drawn to explain the impact of each factor on the relationship between electromagnetic fields and migratory bird migration.
[0034] Step S106, based on the analysis results of the impact of electromagnetic fields on migratory birds, a power grid topology adjustment plan is formulated and implemented to avoid interference with the magnetic field navigation of migratory birds by switching the operation mode of the power grid.
[0035] Based on the areas where electromagnetic fields have potential interference with migratory bird migration, a set of candidate objects for power grid adjustment is formed by extracting key transmission lines and / or substations overlapping with the buffer zone of migratory bird migration routes; wherein, the areas where electromagnetic fields have potential interference with migratory bird migration include power facilities and line corridors; for the candidate object set, the power grid operation conditions under different adjustment schemes are simulated with the power load curve as the boundary condition; the electromagnetic environmental impact of different adjustment schemes is evaluated, including calculating the distribution of power frequency electric field strength and power frequency magnetic induction intensity in the space around the line; and the preferred adjustment scheme that meets safety requirements is screened by comparing with the flight altitude of migratory birds and the electromagnetic field safety threshold.
[0036] For example, the areas where electromagnetic fields have potential interference with migratory bird migration can also be obtained in the following ways: Use NetworkX library GIS data for topological analysis, take substations and towers as nodes, and lines as edges to construct a directed weighted graph. The attribute fields of nodes include name, voltage level, transformer capacity, etc., and the attribute fields of edges include line number, conductor model, length, resistance, reactance, etc. Use NetworkX's shortest path and connectivity algorithms to analyze the topological characteristics of the power grid. Perform spatiotemporal correlation analysis on the power grid topology diagram, migratory bird GPS tracking data, and electromagnetic field monitoring data. Use ArcGIS's "Near" tool to calculate the shortest distance from the migratory bird track point to the transmission line, and connect the line attributes to the migratory bird track point. Perform Kriging interpolation on the electromagnetic field monitoring point data to generate the electromagnetic field distribution grid layer of the area, and extract the electric field strength and magnetic induction intensity attributes of the migratory bird track point. Combine the line distance and electromagnetic field strength to identify the key line corridors that have a greater impact on the navigation of migratory birds' magnetic field. The key line corridor is the area where the electromagnetic field has potential interference with migratory bird migration. Specifically, we can collect load monitoring data from substations and large users along the line, use load forecasting methods such as multivariate linear regression, and generate a 24-hour load curve for a typical day with a time granularity of 15 minutes. With substations as nodes and lines as branches, we build a power flow model for the local power grid and embed it into the power flow model of the entire network. Set typical fault conditions such as N-1 and N-2 to simulate the power grid operation status under different maintenance and scheduling schemes. Output the active and reactive power of key lines, line current and other parameters, and calculate indicators such as line loss and node voltage qualification rate. The HIFREQ module in the CDEGS software is used to evaluate the electromagnetic environmental impact of transmission lines under different operation schemes. Based on the power flow calculation results, the current intensity, phase and other parameters of the line are extracted. Considering factors such as conductor splitting, arrangement, height, tower structure, and earth resistivity, a three-dimensional geometric model of the space around the line is established. The charge simulation method is used to calculate the power frequency electric field intensity distribution of the line, and the vector magnetic potential method is used to calculate the power frequency magnetic induction intensity distribution. The calculation results are spatially superimposed with the flight altitude and migration route of migratory birds to evaluate the electromagnetic compatibility of the line operation plan. For lines with prominent electromagnetic interference, on the premise of ensuring N-1 reliability, planning measures such as ring network reconnection and multi-terminal distribution are taken to reduce the line load rate. New types of conductors such as low-magnetic conductors and fully insulated internal suspension conductors are selected to increase the conductor diameter and split spacing, optimize the conductor arrangement, and reduce the electromagnetic field level. An electromagnetic environment online monitoring device is installed with a measurement frequency range of 30Hzˉ1kHz and a sensitivity better than 0.1V / m and 0.1nT. The monitoring data is transmitted back in real time through a wireless sensor network and integrated into the data bus of the dispatching automation system. Establish dispatching procedures and emergency plans for the electromagnetic environment management of the power grid. According to the migration season and activity patterns of migratory birds, the maintenance plan of the transmission line is reasonably arranged. During the peak migration period, the maintenance frequency and duration of key lines are strictly controlled.When the electromagnetic radiation monitoring value exceeds the threshold value of 0.2kV / m or 2μT, the emergency response mechanism is activated in time, the line operation mode is adjusted, and power outage or maintenance measures are taken when necessary. Through closed-loop control, the electromagnetic radiation of the line is controlled within the safe range of migratory birds. The analytic hierarchy process can also be used to determine the weights of each evaluation index, including average field strength, exceedance rate, failure rate, voltage qualification rate, network loss rate, environmental benefits, investment cost, etc. Collect the quantitative values of the indicators of each scheme and construct a fuzzy evaluation matrix. Through the principle of maximum membership, the comprehensive evaluation level of each scheme is determined to form a set of preferred schemes. On this basis, the full life cycle cost of each preferred scheme is further calculated, including grid transformation investment, operation and maintenance costs, environmental benefit discount, etc. Calculate financial indicators such as investment payback period and financial internal rate of return, and select the most economical governance scheme. From the resource and environmental information system of the State Grid Corporation of China, the GIS data of 500 kV and above transmission and transformation facilities in area A are obtained, including the spatial coordinates, equipment parameters, electrical parameters, etc. of 192 substations, 571 lines, and 3528 towers. The DiGraph class of NetworkX is used to construct a directed weighted graph model. The node data structure is (lon, lat, volt, capacity), and the edge data structure is (line_id, tower_num, r, x, c, length). The Dijkstra shortest path algorithm is used to analyze the topological characteristics of the network, such as connectivity and centrality. Combined with the GPS tracking data of 1,000 white cranes in area A, the GPS accuracy is 10 meters, the data collection frequency is 1 hour, and the 35 electromagnetic field monitoring points arranged near the migratory bird habitats, the frequency of the electromagnetic field monitoring points is 20 Hz, and the sensitivity is 0.01 microtesla radiation data, based on the three-dimensional geometric model of the space around the line, the spatiotemporal coupling relationship between the migratory bird corridor and the power grid facilities is analyzed. The RandomForest algorithm is used to train the association model of migration trajectory and radiation intensity, and 8 high-risk lines with greater interference to migratory birds are extracted by sorting the feature importance. For high-risk lines, load monitoring data from 6 500 kV substations and 23 110 kV large users along the line were collected, and a load forecasting model was established using the LSTM long short-term memory network, with an average relative error of less than 5%. In the PSASP power flow calculation program, a refined power flow model of the regional power grid was built, with a scale of 436 nodes and 935 branches. Five typical fault scenarios and 18 operation modes were set to simulate and optimize line maintenance and scheduling strategies. Using the line parameterization modeling tool in CDEGS, three-dimensional space discrete points were established within a 50-meter span of the high-risk line with a step length of 5 meters. The number of conductor splits (36) was divided according to the interquartile range, the average sag was 5.2 meters, and the ground resistivity was 57Ω·m. The line current amplitude was introduced by the power flow calculation results, and the phase angle was randomly generated.The magnetic vector potential method is used to calculate the power frequency magnetic field, with an iteration error of 10-8, and compared with the 100μT limit of the standard GB8702-2014 to evaluate the electromagnetic exceeding standard area. Non-contact electric and magnetic field sensors and self-powered environmental monitors are set up in hot spots, with a sampling rate of 100Hz and a measurement range of 30Hz10MHz. The monitoring data is aggregated by the TD-LTE / 230MHz concentrator and connected to the dispatching data network in full-duplex mode. The monitoring device can cover a radiation radius of 5 kilometers and a positioning accuracy of 10 meters. Combined with the activity rhythm and migration schedule of birds, during the peak migration period in spring and autumn, load reduction measures such as alternate day rotation maintenance and peak-cutting scheduling are adopted. Under the conditions of electromagnetic field alarm thresholds of 0.3kV / m and 2.4μT, the control target of 90% quantile of field strength better than the standard limit can be achieved. A comprehensive evaluation model for local power grid optimization and adjustment is established, and a fuzzy membership function is constructed from five dimensions: field strength qualified rate weight 0.35, power supply reliability weight 0.25, network loss level weight 0.2, ecological benefit weight 0.15, and investment cost weight 0.05. The membership degree is obtained by linear normalization of the index value, the fuzzy matrix is determined by the AHP hierarchical analysis method, and the interval number VIKOR method is used to solve the comprehensive evaluation value of each scheme. For the top three candidate schemes, the ecological compensation cost corresponding to the environmental benefit is further calculated, and the investment payback period and the whole life cycle cost are calculated according to the benchmark rate of return of 3.87%. The transmission line electromagnetic environment governance scheme with the best comprehensive benefit and an investment payback period of no more than 5 years is selected.
[0037] Step S107, tracking the migration dynamics of migratory birds in the valley and canyon areas and the real-time operation status of the power grid, and adjusting the topology of the power grid according to the changes in the migratory paths of the migratory birds.
[0038] The migratory bird monitoring equipment on the migratory bird corridors in valleys and canyons is used to obtain migratory bird migration parameters. The power grid monitoring equipment is used to obtain power grid operation parameters. The migratory bird migration parameters and power grid operation parameters are matched in time and space, that is, correlation analysis is performed, including analysis of the correlation between the migratory bird migration location and the power grid load distribution. Based on the dynamic changes in the migratory bird migration path, the power grid topology is optimized in real time, including generating a real-time power grid reconstruction plan with minimizing migratory bird interference as the optimization goal. The power grid reconstruction plan includes adjusting the topological connection method of key nodes and lines of the power grid.
[0039] For example, in the migratory bird channels of valleys and canyons, multi-source heterogeneous migratory bird monitoring equipment such as infrared thermal imaging, radar bird detection, and acoustic recording are deployed to continuously collect migratory bird species, quantity, height, speed and other migration parameters. Among them, infrared thermal imaging uses the temperature difference between migratory birds and the environment to monitor at night and in bad weather; radar bird detection can obtain the spatial position and movement trajectory of migratory birds through electromagnetic echo signals; acoustic recording can achieve qualitative and quantitative analysis of bird populations by capturing bird calls. The spatial resolution of the monitoring equipment is better than 50 meters, and the time resolution is better than 10 seconds. The data transmission adopts 5G wireless private network, with a transmission rate of 10Gbps and a delay of less than 1 millisecond, which can meet the real-time return of migratory bird migration data. On the power grid side, online monitoring facilities such as smart substations and distribution automation systems are used to obtain power grid flow, voltage, load and other operating parameters. By deploying micro-synchronous phasor measurement units (μPMUs), full observation coverage of mountain power grids is achieved, with a measurement accuracy of 0.01% and a sampling frequency of 12.8kHz.
[0040] μPMU data is uploaded to the regional control center in real time through the wireless communication network, and data is integrated with the energy management system (EMS) and the distribution management system (DMS) to build a real-time simulation model of the operation status of the mountain power grid. The migratory bird migration parameters and the power grid operation data are matched and correlated in time and space. The stream data processing framework Flink is used to clean, parse and convert the migratory bird migration parameters in real time, and extract key features such as the location and density of migratory birds. The GIS spatiotemporal indexing technology is used to achieve fast matching of migratory bird migration information and the geographical topology of the power grid, and the time complexity is better than O(n*log(n)). Based on the heterogeneous graph neural network model, the migratory bird migration characteristics and the power grid topology characteristics are fused and represented to learn, and a cross-domain correlation map is constructed. On this basis, machine learning algorithms such as support vector machine (SVM) and random forest are used to establish a correlation model between the migratory bird migration location and the power grid load distribution, and the correlation coefficient reaches more than 0.8. In view of the dynamic changes in the migratory bird migration path, the real-time optimization of the power grid topology is carried out. Based on the full topology model of the power grid, graph embedding technologies such as DeepWalk and node2vec are used to learn the low-dimensional vector representation of the power grid topology, and the bird migration features are integrated through heterogeneous graph neural networks to achieve the correlation embedding of cross-domain features. Then, deep reinforcement learning (DRL) algorithms such as DQN and DDPG are used to minimize the interference of migratory birds, dynamically adjust the topological connection mode of key nodes and lines, and generate real-time power grid reconstruction plans. The generation of power grid reconstruction plans needs to comprehensively consider the constraints such as power system security and economy. Using high-performance computing clusters, the AC Optimal Power Flow (ACOPF) model is solved in parallel to calculate the network loss, voltage qualification rate and other indicators of the reconstruction plan. Among them, the ACOPF model uses node injection power, line power flow and other optimization variables, power flow equations, power balance and other equality constraints, bus voltage, line capacity and other inequality constraints, and the objective function is to minimize network loss. For plans that exceed the N-1 reliability standard, multi-objective particle swarm optimization (MOPSO) is started for secondary screening. The MOPSO algorithm uses the weighted network loss and reliability index as the fitness function and satisfies the grid security constraint as the constraint condition to search for the Pareto optimal solution set. At the same time, combined with the power market mechanism, the economic cost of the reconstruction plan is evaluated, including grid investment, electricity procurement, maintenance costs, etc., and the plan with too high cost is pruned. Real-time simulation verification and risk assessment of the grid reconstruction plan are carried out. Using the RTDS real-time digital simulation system, a hardware-in-the-loop (HIL) simulation environment of the mountain power grid is built to simulate the transient characteristics and fault response during the grid topology reconstruction process. Monte Carlo simulation is introduced to randomly generate external disturbance factors such as migratory bird activities and weather changes.Based on migratory bird monitoring data and meteorological data, we extract characteristic quantities such as the number of migratory bird populations, wind speed, and temperature. We fit the probability distribution of the characteristic quantities through nonparametric kernel density estimation, Gaussian mixture model, and other methods. We also use Latin hypercube sampling and other methods to generate a sufficient number of random samples in the distribution space to evaluate the robustness of the reconstruction scheme to disturbances. For schemes with higher risk levels, we use active distribution network technology to improve the flexible regulation capability of the power grid through measures such as flexible alternating current transmission (FACTS) and distributed generation. We formulate power grid dispatching strategies and emergency plans based on migratory bird migration. We use deep learning algorithms, such as long short-term memory networks (LSTM) and gated recurrent units (GRU), to explore the spatiotemporal laws of migratory bird migration and predict the migration trajectory for the next 24 hours with a prediction accuracy better than 90%. Combined with the power grid load forecast results, we form a rolling optimized day-ahead and intraday power grid dispatching plan, and start power grid reconstruction 1-3 days in advance. When the migratory path of migratory birds is monitored to change dramatically and deviate from the predicted trajectory by more than 30%, the emergency dispatch mode is activated. According to the migratory bird activity area, the topological reconstruction plan of the local power grid is quickly generated and sent to the distribution automation terminal to realize the autonomous switching of the power grid operation mode. At the same time, coordinate conventional dispatch and emergency dispatch to reduce the impact on the normal operation of the power grid. On the migratory bird migration channel of the A National Nature Reserve, 20 sets of infrared thermal imagers, 10 millimeter-wave radars and 50 acoustic recorders are deployed to continuously monitor the types, numbers, heights, speeds and other parameters of migratory birds such as white cranes and little swans. The infrared thermal imager uses an uncooled focal plane array with a thermal sensitivity better than 0.05℃ and a maximum detection distance of 5 kilometers; the millimeter-wave radar works at a frequency of 77GHz, with a distance resolution of 0.5 meters and a maximum detection distance of 8 kilometers; the acoustic recorder has a pickup range of 20Hzˉ20kHz and a directional pickup distance of 1 kilometer. Various detectors are connected to the edge computing gateway through point-to-multipoint networking and Ethernet transmission, and the migratory bird feature extraction algorithm is run to realize real-time identification and tracking of migratory bird targets. At the same time, the online monitoring system of 500 kV and above power transmission and transformation facilities in area A was used to obtain 86 operating parameters such as voltage, current, and power of 5 substations and 12 transmission lines, with a data sampling frequency of 5000 frames / second. The μPMU monitoring device uploaded the data to the C power control center in real time through a wireless private network, connected to the WAMS wide-area measurement system, and realized data sharing with the Tianrun SCADA system. A spatiotemporal correlation model of migratory bird migration data and power grid parameters was established. The two types of data streams were split into sliding windows with a time granularity of 5 minutes, and 18 key features such as migratory bird positions, power grid loads, and topological states in the same time window were extracted. The heterogeneous graph convolutional network HAN was used for cross-domain correlation analysis, and the correlation calculation of migratory birds and power grid nodes was realized through meta-path search. The average AUC value reached 0.92. When the number of migratory birds migrating southward in area A was monitored to increase sharply, and the gathering area was highly overlapped with the 500 kV substation and high-speed rail line, the emergency dispatch plan was activated.Taking the migratory bird gathering area as the center, 134 grid nodes and 289 branches in the surrounding area were extracted to form a local optimization area. The multi-agent reinforcement learning algorithm MADDPG was used to dynamically reconstruct the grid topology. Among them, the agent is divided with the substation as the core, the action space is the combination of the on and off of the line and the switch, the state space includes bus voltage, line power, etc., and the reward function comprehensively considers the network loss index, overload index and power supply reliability index. Through parallel training and adaptive adjustment of the learning rate, after 5000 iterations, the grid loss decreased by 8%, the number of overloaded lines decreased by 15%, and the reliability index increased by 6%. The optimized topological structure obtained by reinforcement learning is converted into the parameter setting of the power flow calculation, and the international PSASP platform is used for static safety verification. A refined transient simulation model of the regional power grid can also be constructed, and the optimization scheme is calculated for 48 hours. The results show that all indicators of the optimized power grid meet the N-1 verification standard. At the same time, in response to the frequent dispatching during the migration season, two sets of operation plans are formulated: one is to make a rolling forecast of the grid load three days in advance based on weather forecasts, migratory bird AI identification and other results, and formulate a seasonal optimization plan based on the transmission line maintenance plan; the other is to activate the emergency dispatch mode when the number of white cranes monitored exceeds 10,000 and is concentrated in Area A, and the control center directly issues topology reconstruction and load control instructions to ensure the safe and stable operation of the regional power grid.
[0041] It should be noted that the above examples are only some specific embodiments of the present invention. Obviously, the present invention is not limited to the above embodiments, and there are many variations. All variations that can be directly derived or associated with the content disclosed by a person skilled in the art should be considered as the protection scope of the present invention.
Claims
1. An intelligent analysis method integrating geographical layout of power grid and electrical topology model, characterized in that: The method comprises: Based on the power grid equipment information and the electrical topological connection relationship between the equipment, the CIM model of the valley and canyon areas is integrated; Based on the CIM model, the geographical location and attributes of power grid equipment are obtained to generate a power grid distribution map that reflects the actual geographical location of power equipment and lines in valleys and canyons; Through the CIM model, transformers, circuit breakers, transmission lines in valleys and canyons and how they are interconnected are identified to build an electrical topology model; Based on the electromagnetic field characteristics of power facilities in valleys and canyons, the electromagnetic field distribution model of each power facility is generated, and the migratory bird path data and electromagnetic field distribution model are integrated to identify areas where electromagnetic fields have potential interference with migratory bird migration; The electromagnetic field intensity data and migratory bird migration path information are obtained in real time through sensors, and the impact of electromagnetic fields on migratory bird migration is analyzed in combination with historical migratory bird data. According to the analysis results of the impact of electromagnetic fields on migratory birds, a plan for adjusting the power grid topology was formulated and implemented to avoid interfering with the magnetic field navigation of migratory birds by switching the operation mode of the power grid; Track the migration dynamics of migratory birds in valleys and canyons and the real-time operation status of the power grid, and adjust the topology of the power grid according to changes in the migratory routes of migratory birds.
2. The method according to claim 1, wherein: The CIM model of valley and canyon areas is integrated based on the power grid equipment information and the electrical topological connection relationship between the equipment, including: According to the power grid equipment information, obtain the unique identification, equipment type and basic attributes of geographical location coordinates of each device; By analyzing the electrical topology connection relationship between devices, determine the connection mode between devices, including series connection, parallel connection and ring network; According to the geographical coordinates of the equipment, the valley or canyon area where each equipment is located is determined, and the equipment is marked as a partition; Independently analyze the device topology in each area and extract the key device nodes and key connection paths in the area; Adopt CIM modeling standards to encapsulate the device attributes, topology, key nodes and path information of each area; In the CIM model, the connection interface between regions is defined to realize the interconnection and interoperability of the CIM models of valley and canyon regions.
3. The method according to claim 1, wherein: The method of obtaining the geographical location and attributes of power grid equipment based on the CIM model and generating a power grid distribution map reflecting the actual geographical location of power equipment and lines in valleys and canyons includes: Parse the CIM model and extract the key attribute information of power equipment. The key attribute information of power grid equipment includes equipment ID, equipment type, conductor material and tower model attributes to form an equipment attribute dictionary; Use the device ID as the association key to associate and match the device attribute dictionary with the device space data; According to the longitude and latitude coordinates of the device, determine whether the device is located in a valley or canyon area; For power equipment located in a valley or canyon, extracting terrain features such as terrain relief, slope and slope direction, and adding the terrain features to the equipment attribute dictionary; For transmission lines, the line's starting and ending point coordinates are obtained by tracing the conductor segment objects in the CIM model, and the spatial geometric information of the line is generated; Integrate the device attribute dictionary and the spatial geometric information of the line to generate a network dataset that reflects the topological structure of the power network; Match corresponding symbols to power equipment and transmission lines respectively to form a map of power equipment and lines; Integrate the topographic base map of valleys and canyons and the map of power equipment and lines, combine the spatial distribution of power equipment and lines with the topography, and generate a power grid distribution map that reflects the actual geographical location of power equipment and lines in valleys and canyons.
4. The method according to claim 1, wherein: The CIM model is used to identify transformers, circuit breakers, transmission lines and their interconnections in valleys and canyons, and to construct an electrical topology model, including: Parse the CIM model, extract the attribute information of the power equipment object and form the equipment attribute dictionary; Extract and match the topological nodes and device endpoints in the CIM model to generate an electrical topological structure centered on the topological node and connecting multiple devices, including generating wire segments between devices based on the connection relationship between the devices in the electrical topological structure; Performing a topological rationality check on the generated electrical topology structure, including tracing the electrical connection path to determine whether there are connectivity errors or dangling nodes; Through the geographic coordinate information of the power equipment, the topological nodes are matched with the actual geographical locations to generate an electrical topology model that integrates electrical topology and geographic topology.
5. The method according to claim 1, wherein: The electromagnetic field distribution model of each power facility is generated based on the electromagnetic field characteristics of the power facilities in the valleys and canyons, and the migratory bird path data and the electromagnetic field distribution model are integrated to identify areas where the electromagnetic field has potential interference with migratory bird migration, including: Obtain spatial location information of power facilities in valleys and canyons, including three-dimensional geographic information data of substations, transmission line towers and distribution equipment, to form geographic information data of power facilities; Extract electrical parameters of each power facility, including voltage level and capacity of substations, voltage level, conductor model and operating current of transmission lines; Calculate the electric field strength and magnetic induction strength generated by each power facility based on the spatial location and electrical parameters of the power facility; The calculated electric field strength and magnetic induction intensity data are associated with the spatial location of the power facilities, and the electromagnetic field data are interpolated into three-dimensional space to form an electromagnetic field distribution model; Perform spatial superposition analysis on the electromagnetic field distribution models of different power facilities to obtain the electromagnetic field overlap area; Superimposing and analyzing the electromagnetic field overlap area with the terrain data of valleys and canyons to extract the electromagnetic field overlap area located in the valleys and canyons; Based on the spatial relationship between the migratory routes of migratory birds and the electromagnetic field overlapping areas, the electromagnetic environment of the electromagnetic field overlapping areas is evaluated to identify areas where the electromagnetic field has potential interference with the migration of migratory birds.
6. The method according to claim 1, wherein: The method of obtaining electromagnetic field intensity data and migratory bird migration path information in real time through sensors, and analyzing the impact of electromagnetic fields on migratory bird migration in combination with historical migratory bird migration data, includes: Obtain historical migration data of migratory birds, including migration time, migration route, flight speed and resting time; Preprocess the historical migration data of migratory birds and group and summarize them according to individual migratory birds and migration years to form a structured historical migration data set; Synchronize and align electromagnetic field monitoring data and migratory bird migration data according to timestamps; Based on the electromagnetic field intensity values extracted from the locations of migratory birds, an electromagnetic attribute dataset with migratory bird trajectory points is generated; Analyze the electromagnetic attribute data of migratory bird migration trajectory points, calculate the statistical indicators of electric field strength and magnetic induction intensity on the migratory bird migration path, and group and count them according to the dimensions of individual migratory birds, migration years and migration sections; To test the significant differences in electromagnetic exposure levels between different migratory bird individuals and different migration years; Using historical migration data of migratory birds, establish migratory characteristic indicators of migratory birds, including migration distance, migration duration, daily flight mileage, flight altitude, migration speed and stop frequency; Taking the migratory characteristic indicators of migratory birds as independent variables and the electromagnetic field intensity as the dependent variable, a generalized linear model between the electromagnetic field and the migratory characteristics of migratory birds was established to reveal the influence of the electromagnetic field on the migratory behavior of migratory birds and analyze the impact of the electromagnetic field on the migration of migratory birds.
7. The method according to claim 1, wherein: According to the analysis results of the impact of electromagnetic fields on migratory birds, a plan for adjusting the power grid topology is formulated and implemented to avoid interfering with the magnetic field navigation of migratory birds by switching the operation mode of the power grid, including: Based on the areas where electromagnetic fields have potential interference with migratory birds, a set of candidate objects for grid adjustment is formed by extracting key transmission lines and / or substations overlapping with the buffer zone of migratory bird routes; Among them, the areas where the electromagnetic field has potential interference with migratory birds include power facilities and line corridors; For the candidate object set, using the power load curve as a boundary condition, simulating the power grid operation conditions under different adjustment schemes; Evaluate the impact of different adjustment schemes on the electromagnetic environment, including calculating the power frequency electric field strength and power frequency magnetic induction intensity distribution in the space around the line; By comparing with the flight altitude of migratory birds and the safety threshold of electromagnetic fields, the optimal adjustment plan that meets safety requirements is screened.
8. The method according to claim 1, wherein: The method of tracking the migratory dynamics of migratory birds in valleys and canyons and the real-time operation status of the power grid, and adjusting the topology of the power grid according to the changes in the migratory paths of migratory birds, includes: Obtain migratory bird migration parameters through migratory bird monitoring equipment on migratory bird routes in valleys and canyons; Use power grid monitoring equipment to obtain power grid operation parameters; Conducting temporal and spatial matching of migratory bird parameters and power grid operation parameters, i.e. correlation analysis, including analyzing the correlation between migratory bird locations and power grid load distribution; Based on the dynamic changes of migratory bird migration paths, the grid topology is optimized in real time, including generating real-time grid reconstruction plans with the goal of minimizing migratory bird interference; The grid reconstruction plan includes adjusting the topological connection mode of key nodes and lines of the grid.
Citation Information
Cited By
Power grid dispatching anti-error method and system based on topology analysis
CN120110019A
Communication equipment resource dynamic allocation method and system based on cloud computing
CN120152049A
Rail transit underground station environment control room design method based on equipment layout
CN120180780A