System and method for automatically maintaining vacuum degree of heat pipe heat exchanger

By coordinating the design of the heat pipe heat exchanger unit, vacuum monitoring and pumping unit, and central control unit, the problem of heat pipe vacuum degradation was solved, online automated maintenance was achieved, and the stability and economy of equipment operation were improved.

CN122083736APending Publication Date: 2026-05-26HUADIAN POWER INTERNATIONAL CORPORATION LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202610161335.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-02-04
Publication Date
2026-05-26

AI Technical Summary

Technical Problem

In existing heat pipe heat exchangers, the accumulation of non-condensable gas during long-term operation leads to a decrease in vacuum. Traditional maintenance methods are cumbersome, require shutdown, and have low levels of intelligence, making it impossible to achieve real-time monitoring and automatic response.

Method used

The system employs a collaborative design of a heat pipe heat exchanger unit, a vacuum monitoring and pumping unit, and a central control unit to achieve real-time monitoring and automatic maintenance of the heat pipe vacuum level. This includes the use of a high-precision vacuum pressure sensor, solenoid valves, and a centralized vacuum pump. The central control unit enables automatic pumping and data recording.

Benefits of technology

It enables 24/7 uninterrupted real-time monitoring and automatic recovery of heat pipe vacuum, eliminating the need for downtime for disassembly and inspection, improving equipment availability and maintenance efficiency, reducing costs, extending service life, and supporting predictive maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122083736A_ABST
    Figure CN122083736A_ABST
Patent Text Reader

Abstract

The invention discloses a system and method for automatically maintaining the vacuum degree of a heat pipe heat exchanger, relates to the technical field of heat pipe heat exchange, and particularly relates to a heat pipe heat exchanger suitable for a thermal power generating unit boiler flue gas waste heat recovery occasion. A heat pipe heat exchanger unit, a vacuum monitoring and air exhaust unit and a central control unit are constructed, each heat pipe is independently provided with a vacuum pressure sensor and an air exhaust branch pipe with an electromagnetic valve, a centralized air exhaust header and a vacuum pump are combined, and 7 * 24-hour real-time monitoring of the vacuum degree of each heat pipe is achieved; by presetting the vacuum degree threshold value, the central control unit automatically identifies the heat pipe with the degraded vacuum degree, the corresponding air exhaust process is accurately started, non-condensable gas is eliminated, the target vacuum degree is recovered, and shutdown for inspection is not needed. According to the method, online automatic maintenance of the vacuum degree of the heat pipe is achieved, the faulted heat pipe is accurately positioned, energy is saved, efficiency is high, the service life of the heat pipe and the heat exchanger is remarkably prolonged, data support is provided for predictive maintenance of equipment, and the requirement for long-term stable operation of a large heat pipe heat exchanger is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of heat pipe heat exchange technology, specifically to a system and method for automatically maintaining the vacuum level of a heat pipe heat exchanger. It is particularly suitable for heat pipe heat exchangers in flue gas waste heat recovery applications such as boilers in thermal power units, and can realize online monitoring and automatic recovery of the vacuum level inside the heat pipe, ensuring long-term, efficient and stable operation of the heat pipe heat exchanger. Background Technology

[0002] Heat pipe heat exchangers, with their significant advantages such as high-efficiency heat transfer, compact structure, and good isothermal properties, are widely used in industrial heat exchange fields such as waste heat recovery from boiler flue gas in thermal power units. Their core working component is the heat pipe. The heat pipe is evacuated to a high vacuum and filled with an evaporation medium (usually water). During operation, the evaporation section (heat absorption end) of the heat pipe is inserted into a hot fluid such as a flue, absorbing heat from the fluid and causing the evaporation medium to vaporize. The vaporized steam flows along the heat pipe to the condensation section (heat release end), where it releases heat and condenses into a liquid state. The condensate then flows back to the evaporation section by gravity, completing the cycle of heat transfer and achieving waste heat recovery.

[0003] However, in actual long-term operation, heat pipes with carbon steel shells and water as the evaporation medium have significant technical drawbacks: the iron elements in the pipe wall undergo a slow chemical reaction with water, generating non-condensable gases such as hydrogen. These non-condensable gases cannot condense with the circulating evaporation medium and gradually accumulate at the top of the heat pipe's condensation section, forming a "gas lock" phenomenon. This significantly reduces the effective condensation area of ​​the heat pipe, leading to a marked decrease in its heat transfer performance. In severe cases, it can cause heat pipe failure and affect the waste heat recovery efficiency of the entire heat exchanger.

[0004] To address the aforementioned issues, the traditional solution involves periodically removing the heat pipes from the heat exchanger system for overall leak testing and re-vacuuming. This method suffers from drawbacks such as cumbersome procedures, long downtime, and high maintenance costs, failing to meet the demands of continuous industrial production and exhibiting extremely low maintenance efficiency. Existing technologies also propose manually evacuating individual heat pipes by installing vacuum valves and instruments. However, for large heat pipe heat exchangers composed of dozens or even hundreds of heat pipes, manual operation is impractical, and real-time monitoring and automatic response of vacuum levels are impossible, resulting in low levels of automation and failing to fundamentally solve the routine maintenance problem of heat pipe vacuum deterioration.

[0005] Therefore, developing a system and method that can achieve online monitoring of heat pipe vacuum, automatic removal of non-condensable gases, and inspection without shutdown is key to solving the pain points of existing technologies and improving the operational stability and economy of heat pipe heat exchangers. Summary of the Invention

[0006] The purpose of this invention is to provide a system and method for automatically maintaining the vacuum level of a heat pipe heat exchanger, solving the technical problems of non-condensable gas accumulation forming "gas locks" and reduced heat exchange performance during long-term operation of existing heat pipe heat exchangers, as well as cumbersome maintenance methods, shutdown requirements, and low level of intelligence. This invention enables 24 / 7 uninterrupted real-time monitoring of the heat pipe vacuum level, automatically and accurately handles heat pipes with deteriorating vacuum levels without requiring shutdown for disassembly and inspection, improves equipment availability and maintenance efficiency, extends the service life of heat pipes and heat exchangers, reduces maintenance costs, and provides data support for predictive maintenance of the equipment.

[0007] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A system for automatically maintaining the vacuum level of a heat pipe heat exchanger includes a heat pipe heat exchanger unit, a vacuum monitoring and pumping unit, and a central control unit. The three work together to achieve real-time monitoring and automatic maintenance of the heat pipe vacuum level.

[0008] 1. Heat pipe heat exchanger unit This unit includes at least one circular water tank and several heat pipes. The circular water tank comprises a cylinder, an upper cover, and a lower bottom. Its circular design enhances the tank's pressure resistance and facilitates the uniform arrangement of the heat pipes, dispersing mechanical stress and optimizing fluid distribution within the tank. The heat pipes penetrate the upper cover and lower bottom of the circular water tank vertically or at an angle. A continuous sealing welding process is used between the outer wall of the heat pipes and the openings in the cover and bottom to ensure the water tank's airtightness, prevent cooling water leakage, and guarantee heat exchange efficiency and system stability. The heat pipes contain an evaporation medium (usually water). The portion of the heat pipe inside the circular water tank is the heat-exchanging end (condensation section), used for heat exchange with the cooling water inside the tank; the portion outside the circular water tank is the heat-absorbing end (evaporation section), used to insert into hot fluids such as flues to absorb heat from the hot fluid. Depending on the heat exchange scale requirements, the circular water tank can be set as an independent unit, or multiple circular water tanks can be connected in parallel or series through connecting pipes to adapt to heat pipe heat exchanger application scenarios of different specifications and heat exchange loads, especially suitable for waste heat recovery systems of flue gas at the tail end of thermal power unit boilers.

[0009] 2. Vacuum monitoring and pumping unit This unit is configured independently for each heat pipe, yet integrated into a centralized system, balancing the accuracy and economy of monitoring and evacuation. Each heat pipe has a high-precision vacuum pressure sensor (replacing a traditional simple vacuum gauge) installed at its heat-dissipating end to monitor the absolute pressure inside the corresponding heat pipe in real time, accurately capturing changes in vacuum level. Each heat pipe also has an evacuation branch pipe at its top, equipped with a normally closed solenoid valve to control the opening and closing of the evacuation channel for that heat pipe. All heat pipe evacuation branches converge into a single evacuation manifold, which is connected to a high-vacuum pump (preferably a rotary vane vacuum pump). The high-vacuum pump's inlet pipe is equipped with a main isolation valve and a vacuum gauge. The main isolation valve controls the connection between the evacuation manifold and the vacuum pump, while the vacuum gauge monitors the vacuum state within the evacuation manifold in real time, ensuring a stable and controllable evacuation process. This centralized design requires only one vacuum pump to serve all heat pipes, significantly reducing hardware costs and operating energy consumption. Furthermore, the vacuum pump is only activated when evacuation is needed, resulting in high operational economy.

[0010] 3. Central control unit This unit, comprising a programmable logic controller (PLC) or industrial computer, is the core of the system for achieving automated control. The central control unit presets a vacuum alarm threshold P_alarm and a target vacuum level P_target for each heat pipe, ensuring that P_alarm > P_target (preferably set to P_alarm = 500 Pa and P_target = 50 Pa, with the target vacuum level significantly lower than the saturated vapor pressure of the evaporating medium at the corresponding condensation temperature to ensure effective removal of non-condensable gases). The central control unit is electrically connected to all vacuum pressure sensors, solenoid valves, and the high-vacuum pump, enabling real-time acquisition of vacuum pressure data for each heat pipe. By comparing this data with preset thresholds, the vacuum status of each heat pipe is determined. When a heat pipe's vacuum level deteriorates (pressure exceeds P_alarm), the pumping control logic is automatically triggered, precisely controlling the opening of the corresponding solenoid valve and starting the vacuum pump. After pumping is complete, the solenoid valve and vacuum pump are automatically shut off, achieving automatic vacuum recovery. Simultaneously, the central control unit records historical vacuum monitoring data and pumping operation logs, generating pressure change trend curves to provide data support for predictive maintenance and condition assessment of the equipment.

[0011] A method for automatically maintaining the vacuum level of a heat pipe heat exchanger, based on the aforementioned system for automatically maintaining the vacuum level of a heat pipe heat exchanger, specifically includes the following steps: S1: System initialization, setting the vacuum alarm threshold P_alarm and target vacuum level P_target for each heat pipe, controlling all normally closed solenoid valves to be in the closed state, and the high vacuum pump and main isolation valve to be in the closed state to ensure the initial state of the system is stable; S2: The central control unit starts the cyclic monitoring program and continuously reads the real-time pressure data Pi collected by the vacuum pressure sensor at the top of each heat pipe to achieve uninterrupted monitoring of the vacuum level of all heat pipes. S3: The central control unit compares the real-time pressure data Pi of each heat pipe with the preset alarm threshold P_alarm. If Pi ≤ P_alarm, it is determined that the vacuum state of the heat pipe is good and there is no need for evacuation. Then, return to step S2 to continue monitoring the next heat pipe. S4: If Pi>P_alarm, it is determined that the vacuum of the heat pipe has deteriorated and non-condensable gas has accumulated. The central control unit immediately generates a pumping command to control the normally closed solenoid valve corresponding to the heat pipe to open the pumping channel of the heat pipe. S5: The central control unit synchronously checks the operating status of the high vacuum pump. If the high vacuum pump is not in operation, it starts the high vacuum pump and opens the main isolation valve. Through the evacuation manifold, branch pipes and the opened evacuation branch pipe, the heat pipe with deteriorated vacuum is evacuated to remove the non-condensable gas accumulated inside. S6: During the evacuation process, the central control unit continuously monitors the pressure data Pi of the heat pipe in real time, and at the same time monitors the vacuum status in the evacuation manifold through the vacuum gauge to ensure the stability of the evacuation process; when Pi drops to the preset target vacuum level P_target, the evacuation is determined to be completed, and the central control unit controls the solenoid valve corresponding to the heat pipe to close, cutting off the evacuation channel. S7: The central control unit cyclically checks the vacuum status of all heat pipes to determine if there are other heat pipes with deteriorated vacuum levels. If the vacuum status of all heat pipes is good and there are no heat pipes that need to be evacuated, the high vacuum pump and the main isolation valve are delayed and shut down to reduce energy consumption. S8: Return to step S2. The central control unit continues to enter the cyclic monitoring state, achieving 24 / 7 uninterrupted maintenance of the heat pipe vacuum level, ensuring that the heat pipe operates in the optimal vacuum state for a long time.

[0012] Compared with the prior art, the advantages and positive effects of the present invention are as follows: 1. Achieve online automated maintenance without downtime for disassembly and inspection: Through the coordinated operation of vacuum monitoring, the pumping unit, and the central control unit, this invention achieves 24 / 7 uninterrupted real-time monitoring of the heat pipe vacuum and automatic pumping recovery. It eliminates the need to remove the heat pipe from the system, avoiding downtime and production stoppages caused by traditional maintenance methods. This significantly improves the equipment availability and maintenance efficiency of heat pipe heat exchangers, making it suitable for continuous industrial production needs.

[0013] 2. Precise fault location and avoidance of resource waste: Each heat pipe is independently equipped with a vacuum pressure sensor and solenoid valve, which can accurately locate which heat pipe has a vacuum deterioration problem. Only the faulty heat pipe is evacuated individually, avoiding the resource waste caused by "one-size-fits-all" evacuation. At the same time, it avoids interference with heat pipes with good vacuum conditions, thus improving the accuracy of maintenance.

[0014] 3. High efficiency and energy saving, excellent economic performance: The centralized air extraction system can serve all heat pipes with one vacuum pump, which greatly reduces the hardware purchase cost and equipment operating energy consumption; moreover, the vacuum pump only starts when there is an air extraction demand and does not need to run continuously, further reducing operating costs and improving the economic performance of the system.

[0015] 4. Reliable structure and stable operation: The heat pipe and the circular water tank adopt a through-type continuous sealed welding structure, which has good sealing performance and high mechanical strength, and can effectively withstand system pressure and avoid cooling water leakage; the circular water tank structure is conducive to fluid distribution and mechanical stress dispersion, further improving the system's operational stability and service life.

[0016] 5. High level of intelligence and support for predictive maintenance: The central control unit can collect and record vacuum monitoring data and pumping operation logs in real time, generate pressure change trend curves, accurately determine the operating status of the heat pipe, provide reliable data support for predictive maintenance, fault warning and condition assessment of the equipment, further extend the service life of the heat pipe and the entire heat exchanger, and improve long-term economic benefits. Attached Figure Description

[0017] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the following description of the embodiments will be briefly introduced. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0018] Figure 1 This is a schematic diagram of the system structure for automatically maintaining the vacuum level of the heat pipe heat exchanger according to the present invention; In the diagram: 1-Circular water tank; 11-Cylinder body; 12-Upper cylinder cover; 13-Lower cylinder bottom; 2-Heat pipe; 21-Heat release end (condensation section); 22-Heat absorption end (evaporation section); 23-Evaporation medium; 24-Pipe shell; 3-Vacuum monitoring and pumping unit; 31-Vacuum pressure sensor; 32-Pumping branch pipe; 33-Solenoid valve; 34-Pumping manifold; 35-High vacuum pump; 36-Main isolation valve; 37-Vacuum gauge; 4-Central control unit; 5-Hot flue gas (hot fluid). Detailed Implementation

[0019] To better understand the above-mentioned objectives, features, and advantages of the present invention, the present invention will be further described below in conjunction with the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments can be combined with each other.

[0020] Numerous specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be practiced in other ways than those described herein, and therefore the invention is not limited to the specific embodiments disclosed in the following specification.

[0021] In this embodiment, the system and method for automatically maintaining the vacuum level of a heat pipe heat exchanger are applied to the waste heat recovery system of flue gas at the tail end of a thermal power unit boiler, which is adapted to the routine maintenance needs of large heat pipe heat exchangers.

[0022] like Figure 1 As shown, the system for automatically maintaining the vacuum level of the heat pipe heat exchanger includes a heat pipe heat exchanger unit, a vacuum monitoring and evacuation unit 3, and a central control unit 4. The heat pipe heat exchanger unit includes a circular stainless steel water tank 1 and 96 carbon steel-water heat pipes 2. The circular water tank 1 includes a cylinder 11, an upper cover 12, and a lower bottom 13. The 96 heat pipes 2 vertically penetrate the upper cover 12 and the lower bottom 13 in a matrix configuration. The outer wall of the heat pipes 2 is continuously and sealed at the openings of the upper cover 12 and the lower bottom 13 to ensure the airtightness of the circular water tank 1 and prevent internal cooling water leakage. Water is encapsulated inside the heat pipes 2 as an evaporation medium 23. The portion of the heat pipe 2 inside the circular water tank 1 is the heat-exchanging end 21, which exchanges heat with the cooling water inside the tank. The portion outside the circular water tank 1 is the heat-absorbing end 22, which is inserted into the boiler tail flue to contact the hot flue gas 5 and absorb heat.

[0023] The vacuum monitoring and pumping unit 3 is independently configured for each heat pipe 2, specifically including: a resistance vacuum gauge tube (as a vacuum pressure sensor 31) is installed on the top of the heat dissipation end 21 of each heat pipe 2 to monitor the absolute pressure inside the corresponding heat pipe 2 in real time; a DN8 stainless steel pumping branch pipe 32 is provided on the top of each heat pipe 2, and a two-position two normally closed solenoid valve 33 is installed on the pumping branch pipe 32; the pumping branch pipes 32 of all 96 heat pipes 2 are connected to a DN40 pumping manifold 34 through branch pipelines, and the pumping manifold 34 is connected to a rotary vane high vacuum pump 35 with a pumping speed of 8L / s. The inlet pipe of the high vacuum pump 35 is equipped with a main isolation valve 36 and a vacuum gauge 37 to control the opening and closing of the pumping channel and monitor the pumping status.

[0024] The central control unit 4 uses a programmable logic controller (PLC), which is electrically connected to all vacuum pressure sensors 31, solenoid valves 33 and high vacuum pumps 35. The central control unit 4 has a preset vacuum alarm threshold P_alarm = 500Pa and a target vacuum P_target = 50Pa. This target vacuum is much lower than the saturated vapor pressure of water at the corresponding condensation temperature, ensuring that non-condensable gases such as hydrogen accumulated in the heat pipe 2 can be effectively removed.

[0025] Based on the above system, the method for automatically maintaining the vacuum level of a heat pipe heat exchanger in this embodiment includes the following steps: S1: System initialization, the central control unit 4 sets P_alarm = 500Pa and P_target = 50Pa, controls all solenoid valves 33 to be in the closed state, the high vacuum pump 35 and the main isolation valve 36 to be in the closed state, and the system enters the standby monitoring state; S2: The central control unit 4 starts the cyclic monitoring program, and reads the real-time pressure data Pi collected by the vacuum pressure sensor 31 on the top of the 96 heat pipes 2 every 10 seconds. S3: The central control unit 4 compares Pi with P_alarm (500Pa) for each heat pipe 2. If Pi ≤ 500Pa, it is determined that the vacuum state of the heat pipe 2 is good, and the process returns to step S2 to continue monitoring the next heat pipe 2. S4: After the system has been running for half a year, the central control unit 4 detects that the Pi of heat pipes 23 and 45 has risen to more than 600Pa, which is greater than P_alarm. It determines that the vacuum of the two heat pipes 2 has deteriorated and immediately generates a pumping command to open the solenoid valves 33 corresponding to heat pipes 23 and 45 respectively. S5: The central control unit 4 checks the status of the high vacuum pump 35 and finds that the high vacuum pump 35 is not running. It then starts the high vacuum pump 35 and opens the main isolation valve 36. It then pumps air from heat pipes 23 and 45 through the pumping manifold 34, branch pipes and the opened pumping branch pipe 32. S6: During the evacuation process, the central control unit 4 continuously monitors the Pi of the two heat pipes 2 in real time, and at the same time monitors the vacuum status in the evacuation manifold 34 through the vacuum gauge 37; after about 3 minutes, the Pi of the two heat pipes 2 drops to 45Pa (below P_target = 50Pa), the central control unit 4 determines that the evacuation is complete, and closes the solenoid valves 33 corresponding to heat pipes 23 and 45 respectively. S7: The central control unit 4 cyclically checks the vacuum status of the remaining 94 heat pipes 2, confirms that the Pi of all heat pipes 2 is ≤ 500Pa, and there are no other heat pipes 2 with deteriorated vacuum. After a delay of 5 minutes, the high vacuum pump 35 and the main isolation valve 36 are turned off. S8: Return to step S2, and the central control unit 4 continues to enter the cycle monitoring state to continuously maintain the vacuum level of all heat pipes 2.

[0026] In this embodiment, the entire evacuation maintenance process does not require shutdown, and the circular water tank 1 continues to operate normally without affecting the boiler's normal production and flue gas waste heat recovery efficiency. After maintenance, the heat exchange performance of heat pipes 23 and 45 is restored to their initial level, effectively solving the problem of non-condensable gas accumulation forming "gas locks". At the same time, the central control unit 4 records the evacuation time and pressure change data of the two heat pipes 2, generating historical monitoring logs to provide data support for subsequent predictive maintenance of the equipment.

[0027] This invention achieves online, automatic, and precise maintenance of heat pipe vacuum by optimizing system structure design and control logic, effectively solving many pain points of existing technologies and significantly improving the operational stability and economy of heat pipe heat exchangers. It can be widely used in heat pipe heat exchangers in fields such as waste heat recovery from boiler flue gas in thermal power units and industrial waste heat utilization, and is especially suitable for large heat pipe heat exchangers, space-constrained applications, and applications with high continuous operation requirements.

[0028] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any other way. Any person skilled in the art may make changes or modifications to the above-disclosed technical content to create equivalent embodiments for application in other fields. However, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the protection scope of the present invention.

Claims

1. A system for automatically maintaining the vacuum level of a heat pipe heat exchanger, characterized in that, The system includes a heat pipe heat exchanger unit, a vacuum monitoring and pumping unit, and a central control unit. The heat pipe heat exchanger unit comprises at least one circular water tank and several heat pipes. The circular water tank includes a cylinder, an upper cover, and a lower bottom. The heat pipes penetrate the upper cover and lower bottom vertically or obliquely, and the outer walls of the heat pipes are continuously and sealed to the openings in the cover and bottom. The portion of the heat pipe inside the circular water tank is the heat-releasing end, and the portion outside the circular water tank is the heat-absorbing end, which is used to insert into the hot fluid. The vacuum monitoring and pumping unit is independently configured for each heat pipe but integrated into a centralized system. The central control unit is electrically connected to the vacuum monitoring and pumping unit to achieve vacuum monitoring and automatic pumping control.

2. The system for automatically maintaining the vacuum level of a heat pipe heat exchanger according to claim 1, characterized in that, The vacuum monitoring and pumping unit includes a vacuum pressure sensor, a pumping branch pipe, a solenoid valve, a pumping manifold, a high vacuum pump, and a main isolation valve. A vacuum pressure sensor is installed at the top of the heat-dissipating end of each heat pipe to monitor the absolute pressure inside the corresponding heat pipe in real time. Each heat pipe has a pumping branch pipe at its top, and a normally closed solenoid valve is installed on the pumping branch pipe. All pumping branch pipes converge into the pumping manifold through branch pipes. The pumping manifold is connected to the high vacuum pump, and a main isolation valve and a vacuum gauge are installed on the inlet pipe of the high vacuum pump.

3. The system for automatically maintaining the vacuum level of a heat pipe heat exchanger according to claim 1, characterized in that, The central control unit includes a programmable logic controller or an industrial computer. The central control unit presets a vacuum alarm threshold P_alarm and a target vacuum level P_target for each heat pipe, and P_alarm > P_target. The central control unit is electrically connected to all vacuum pressure sensors, solenoid valves and high vacuum pumps, and is used to collect vacuum pressure data, determine the vacuum status of the heat pipes and execute automatic evacuation control logic.

4. The system for automatically maintaining the vacuum level of a heat pipe heat exchanger according to claim 1, characterized in that, The circular water tank can be set as an independent unit, or multiple circular water tanks can be connected in parallel or in series through connecting pipes to adapt to heat exchange needs of different scales; the heat pipe is encapsulated with an evaporation medium, and the heat fluid is flue gas, which is suitable for the waste heat recovery scenario of flue gas at the tail end of thermal power unit boilers.

5. A method for automatically maintaining the vacuum level of a heat pipe heat exchanger, characterized in that, The system for automatically maintaining the vacuum level of a heat pipe heat exchanger as described in any one of claims 1-4, the method comprising the following steps: S1: System initialization, setting the vacuum alarm threshold P_alarm and target vacuum level P_target for each heat pipe, controlling all solenoid valves to be in the closed state, and the high vacuum pump and main isolation valve to be in the closed state; S2: The central control unit continuously reads the real-time pressure data Pi collected by the vacuum pressure sensor at the top of each heat pipe; S3: The central control unit compares the real-time pressure data Pi with the preset alarm threshold P_alarm. If Pi ≤ P_alarm, it is determined that the vacuum state of the heat pipe is good, and the process returns to step S2 to continue monitoring the next heat pipe. S4: If Pi > P_alarm, it is determined that the vacuum level of the heat pipe has deteriorated. The central control unit generates a pumping command and opens the normally closed solenoid valve corresponding to the heat pipe. S5: The central control unit checks the operating status of the high vacuum pump. If the high vacuum pump is not running, it starts the high vacuum pump and pumps air through the pump manifold, branch pipes and open pump branch pipes to pump air from the heat pipe with deteriorated vacuum. S6: During the evacuation process, the central control unit continuously monitors the real-time pressure data Pi of the heat pipe. When Pi drops to the preset target vacuum level P_target, the evacuation is determined to be complete, and the solenoid valve corresponding to the heat pipe is closed. S7: The central control unit cyclically checks the vacuum status of all heat pipes to determine if there are other heat pipes with deteriorated vacuum levels. If not, it delays and shuts down the high vacuum pump and the main isolation valve. S8: Return to step S2 and enter the continuous cycle monitoring state to achieve uninterrupted maintenance of the heat pipe vacuum.

6. The method for automatically maintaining the vacuum level of a heat pipe heat exchanger according to claim 5, characterized in that, In step S5, a rotary vane vacuum pump is used for the high vacuum pump. During the evacuation process, the vacuum state in the evacuation manifold is monitored in real time by a vacuum gauge to ensure the stability of the evacuation process. In step S6, after the evacuation is completed, the central control unit records the evacuation time and pressure change data of the heat pipe to form a historical monitoring log.

7. The method for automatically maintaining the vacuum level of a heat pipe heat exchanger according to claim 5, characterized in that, The preset alarm threshold P_alarm is set to 500 Pa, the target vacuum degree P_target is set to 50 Pa, and the target vacuum degree P_target is lower than the saturated vapor pressure of the evaporating medium in the heat pipe at the corresponding condensation temperature, to ensure effective removal of non-condensable gases.