Device for quickly hoisting long hoisting guide rail in narrow area
By designing a fast lifting device for long-row lifting guide rails in narrow areas, and using the lifting mechanism of wire rope and retracting wheels, the problems of transportation and installation of door crane rails in narrow corridors of sluice gates are solved, and construction efficiency and safety are improved.
Patent Information
- Application Number
- CN202420910795.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-28
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-28
AI Technical Summary
In the narrow corridor of the sluice, the installation of door crane rails is difficult to transport and install due to space limitations and concrete foundations higher than the ground. The existing technology is difficult to effectively solve, affecting construction efficiency and safety.
A fast lifting device for long-row lifting guide rails in narrow areas is designed, including a gantry, walking wheel, rectangular working platform, lifting mechanism and positioning mechanism. The lifting and installation of guide rails is achieved by using wire ropes and retracting wheels, and the construction safety is ensured in combination with guardrails.
The device can conveniently transport and install long-row lifting guide rails in narrow areas, improving the construction efficiency and benefits of sluice projects and achieving good results in safe production.
Smart Images

Figure CN222042465U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water conservancy project construction, in particular to a device for quickly hoisting a long overhead crane guide rail in a narrow area. Background Art
[0002] A sluice gate is a low-head hydraulic structure built on rivers and channels that uses gates to control flow and adjust water levels. It is widely used as a structure for retaining, discharging or taking water. The basic structure of an integral sluice gate is composed of a row of many gates connected in series, forming a very narrow and particularly long corridor inside the sluice gate. A connecting crane is installed on the upper part of the long corridor. This crane that can operate in the long corridor is the only lifting equipment in the entire sluice gate. It is responsible for the installation of gate parts during construction. During the operation of the sluice gate, the crane is responsible for the lifting, maintenance and other work of all gate equipment. The most difficult part of the indoor lifting equipment of the sluice is the installation of the track that runs through the long corridor. There are multiple concrete foundations above the ground arranged continuously in the long and narrow corridor. The door hanging track is set on the highest concrete beams on both sides of the room. The door hanging track and all the gate parts can only enter the room from one end of the long and narrow corridor. It is very difficult to transport the door hanging track in the long and narrow corridor. It is even more difficult to install the door hanging track on the highest concrete beams on both sides of the room, because no transport vehicles or cranes can enter the room. The installation of indoor door hanging track is the most critical node in the installation of the entire sluice equipment. If this work is not done well, it will affect the smooth progress of the entire sluice project. For this reason, a lot of technical research and process innovation work has been carried out in response to the harsh on-site conditions of the indoor door hanging track installation work. Chinese patent 2018116284340 discloses "A steel pipe installation structure lined in a narrow space of a water supply tunnel", with the announcement number CN109469498B. A propulsion device is provided at the entrance of the tunnel body. The propulsion system includes an in-tunnel rolling device and an in-tunnel guide rail device. The in-tunnel rolling device and the in-tunnel guide rail device are arranged at intervals in the tunnel body. The in-tunnel rolling device includes a pair of earrings symmetrically arranged at the bottom of the tunnel body, a steel shaft arranged between the earrings, and a sleeve rotatably arranged on the steel shaft. This installation structure solves the problem of low efficiency of steel pipe installation in the narrow space of a straight tunnel. However, as mentioned above, the sluice chamber is not only narrow in space but also has multiple concrete foundations above the ground, which does not have the conditions for installing the in-tunnel rolling device and the in-tunnel guide rail device. Utility Model Content
[0003] In view of the above technical problems, the utility model provides a device for quickly lifting long crane rails in narrow areas, which meets the construction requirements of transporting door crane rails in narrow and long sluice corridors and installing door crane rails on the highest concrete beams on both sides of the room, thereby improving the construction efficiency and benefits of sluice projects and achieving good results in safe production.
[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0005] The lifting of the lifting mechanism is a lifting mechanism, and the lifting of the lifting mechanism is a lifting mechanism, and the lifting of the lifting mechanism is a lifting mechanism, and the lifting of the lifting mechanism is a lifting mechanism, and a lifting mechanism is a lifting mechanism, and a lifting mechanism is a lifting mechanism, and a lifting mechanism is a lifting mechanism, and a lifting mechanism is a lifting mechanism, and a lifting mechanism is a lifting mechanism, and a lifting mechanism is a
[0006] Through this solution, the device can easily enter and exit the narrow corridor chamber of the sluice, serve as a working platform for lifting and installing long crane guide rails, facilitate the transportation of long crane guide rails in the corridor chamber and install the guide rails on the highest concrete beams on both sides of the chamber, improve the efficiency and benefits of the construction of the sluice project, and achieve good results in safe production.
[0007] Preferably, a plurality of inner tube axial holes are axially arranged on the tube wall of the inner tube, a short rod is inserted through one of the inner tube axial holes, both ends of the short rod are supported on the upper end surface of the outer sleeve, and a handle is fixedly installed on one end of the short rod.
[0008] Through this solution, the height of the lifting mechanism can be adjusted and the boom can be rotated horizontally, which facilitates the lifting and installation of the overhead crane guide rail.
[0009] Preferably, the upper end of the hanging plate is connected to the steel wire rope, and the lower end of the hanging plate is provided with a T-shaped groove for clamping the wing plate of the overhead crane guide rail.
[0010] Through this solution, the wire rope can quickly grab the crane rail to improve construction efficiency.
[0011] Preferably, an annular flat washer is fixedly welded to the upper end surface of the outer sleeve, and both ends of the short rod are supported on the flat washer.
[0012] Through this solution, the friction force of the inner tube during rotation can be reduced, and the inner tube rotates more smoothly.
[0013] Preferably, a guardrail is provided at the edge of the working platform.
[0014] Through this solution, the guardrail can prevent construction workers or equipment on the working platform from accidentally falling, thereby achieving safe production.
[0015] The utility model can meet the construction requirements of transporting door hanging rails in narrow and long sluice corridors and installing door hanging rails on the highest concrete beams on both sides of the room, improve the construction efficiency and benefits of the sluice project, and achieve good results of safe production. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:
[0017] Figure 1 This is a front structural schematic diagram of an embodiment of the utility model;
[0018] Figure 2 for Figure 1 A side structural schematic diagram of an embodiment; DETAILED DESCRIPTION
[0019] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0020] See also Figure 1-Figure 2 As shown, the utility model discloses a device for fast lifting of a long-travel hanging guide rail in a narrow area, comprising a gantry 16 and a running wheel 17 installed at the lower end of the gantry 16, and a rectangular-structured working platform 19 is fixedly provided at the upper end of the gantry 16. The gantry 16 adopts an elevated structure, and directly below the working platform 19 is a space that is large enough to pass through the front and rear through-going concrete foundation columns continuously arranged in the sluice corridor. The supporting legs of the gantry 16 are respectively arranged on the left and right sides of the lower surface of the working platform 19, and the spacing between the supporting legs on the left and right sides is greater than the width of the concrete foundation columns. The running wheel 17 is installed at the lower end of the supporting legs of the gantry 16, and the gantry 16 can be moved from one end of the sluice corridor to the inside of the sluice corridor by pushing or towing it with a winch.
[0021] The working platform 19 can be welded with steel plates, or it can be a frame structure welded with square steel or angle steel. The four corners of the working platform 19 are fixedly installed with lifting mechanisms and positioning mechanisms. The positioning mechanism is used to stabilize the position of the working platform 19, prevent shaking, and provide a stable working environment for the lifting mechanism; the lifting mechanism is used to grab and lift one end of the traveling lifting rail. The two lifting mechanisms on the same side act together on the same traveling lifting rail to complete the lifting and installation of the traveling lifting rail. In addition, in order to ensure the safety of the construction workers, a guardrail 15 is provided at the edge of the working platform 19. The guardrail 15 is composed of horizontal bars and vertical bars arranged around the edge of the working platform 19. There is a certain distance between each horizontal bar or each vertical bar, so that the construction workers can pass through the gaps between these horizontal and vertical bars to carry out construction work.
[0022] The lifting mechanism includes an outer sleeve 14 vertically mounted on a working platform 19, an inner tube 13 whose lower end is rotatably inserted into the outer sleeve 14, and an inclined rod 6 fixedly connected to the upper end of the inner tube 13. The outer sleeve 14 and the inner tube 13 are both round tubes, so that the inner tube 13 can be inserted into the outer sleeve 14 and can rotate. The inclined rod 6 is welded to the inner tube 13 at an obtuse angle, one end of the inclined rod 6 is welded to the upper end of the inner tube 13, and the other end extends obliquely upward. A fixed pulley 4 is installed at the upper end of the inclined rod 6, and a take-up wheel 61 is installed at the rear end of the inclined rod 6. The take-up wheel 61 is connected to the inclined rod 6 through a mounting seat with a bearing, so that the take-up wheel 61 can rotate to wind the wire rope 5 around the take-up wheel 61. The wire rope 5 is wound around the take-up wheel 61, and the other end of the wire rope 5 is passed around the fixed pulley 4 and fixedly connected to the hanging plate 8. When the take-up wheel 61 rotates to retract the wire rope 5, the hanging plate 8 at the end of the wire rope 5 is lifted, and vice versa, when the take-up wheel 61 rotates to release the wire rope 5, the hanging plate 8 at the end of the wire rope 5 is lowered; the hanging plate 8 is a flat plate structure cut from a steel plate, and the upper end of the hanging plate 8 has a connecting hole for connecting the wire rope 5, and is connected to the wire rope 5 through the connecting hole, and the lower end of the hanging plate 8 has a T-shaped groove for clamping the wing plate of the overhead crane guide rail, and the cross-sectional shape of the T-shaped groove is a T-shape that adapts to the shape of the wing plate of the overhead crane guide rail. Figure 1 As shown, the cross-section of the existing crane guide rail 9 is an I-shape. When in use, the hanging plate 8 can be firmly clamped on the crane guide rail 9 by simply inserting the T-shaped groove at the lower end of the hanging plate 8 from one end of the crane guide rail 9 into the upper wing plate of the hanging guide rail 9. It will not fall off when lifting upwards. After the lifting is completed, the hanging plate 8 can be removed by simply moving it along the length direction of the crane guide rail 9.
[0023] The take-up wheel 61 can be rotated manually or by a motor. In the present embodiment, manual drive is adopted. As long as a crank is fixedly connected to the extended end of the axle of the take-up wheel 61, the take-up wheel 61 can be rotated by turning the crank to retract or release the wire rope 5.
[0024] In addition, as a further improvement of the utility model, a plurality of inner tube axial holes are axially arranged on the tube wall of the inner tube 13, and a short rod 101 is inserted through one of the inner tube axial holes, and both ends of the short rod 101 are supported on the upper end surface of the outer tube 14, and a handle 10 is fixedly installed on one end of the short rod 101. The handle 10 can push the inner tube 13 to rotate, and the height of the lifting mechanism can be adjusted by inserting the short rod 101 into different outer tube axial holes. In addition, to avoid excessive wear between the short rod 101 and the upper end surface of the outer tube 14, an annular flat washer 141 is fixedly welded on the upper end surface of the outer tube 14, and both ends of the short rod 101 are supported on the flat washer 141. The surface of the flat washer 141 is flat and has a large contact area with the short rod 101, which can protect the short rod 101 from rapid wear.
[0025] The positioning mechanism includes a clamping plate seat 1 fixedly mounted on the working platform 19, a support rod 11 hinged at the upper end of the clamping plate seat 1, the clamping plate seat 1 includes two clamping plates arranged on both sides of the support rod 11 and a fastening bolt 12 inserted through the upper end of the clamping plate, and a long hole 111 is arranged on the support rod 11, and the fastening bolt 12 is inserted into the long hole 111. The two clamping plates clamp the support rod 11 in the middle and enable it to rotate around the fastening bolt 12, and the axis of the fastening bolt 12 is parallel to the length direction of the sluice corridor and perpendicular to the walls on both sides of the sluice corridor. When the fastening bolt 12 is loosened, the direction and position of the support rod 11 can be adjusted, such as Figure 1 As shown on the left side, when the door frame 16 moves, the support rod 11 is in a vertical state and will not hinder the movement of the door frame 16; after the door frame 16 moves to the working position, as shown in FIG. Figure 1 As shown on the right side, the support rod 11 is adjusted to a horizontal state, the outer end of the support rod 11 is against the wall of the sluice corridor, the fastening bolts 12 are tightened, and the support rod 11 is fixed by the clamping force of the two splints. The four support rods 11 on the working platform 19 are respectively against the walls on both sides of the sluice corridor at four positions in front, back, left and right, so as to stabilize the working platform 19.
[0026] When in use, the device is moved to the road of the outdoor extension section of the sluice corridor, the two traveling crane guide rails 9 with the beam seat 3 installed are placed on both sides of the door frame 16, the lifting mechanism hanging plate 8 is lowered, and the hanging plate 8 is clamped on the end of the traveling crane guide rail 9, and the two lifting mechanisms on the same side grab the two ends of the traveling crane guide rail 9 respectively, and then the take-up wheel 61 is rotated to raise the height of the traveling crane guide rail 9 and lift it above the working platform 19; after the two traveling crane guide rails 9 are lifted into place, the winch is used to pull the door frame 16, and the door frame 16 is dragged To the working position; then support the support rod 11 of the positioning mechanism to the wall on the side of the sluice corridor, fix the position of the working platform 19, and then adjust the height by rotating the take-up wheel 61, rotate the inner tube 13 to adjust the direction of the diagonal rod 6 to align the beam seat 3 on the traveling crane guide rail 9 with the beam 2 of the sluice corridor, and insert the mounting bolts into the bolt holes of both, tighten the mounting bolts to fix the beam seat 3 on the beam 2, then remove the hanging plate 8, disassemble the positioning mechanism and the lifting mechanism, and drag the door frame 16 out of the sluice corridor.
[0027] The above shows and describes the basic principles and main features of the utility model and the advantages of the utility model. For those skilled in the art, it is obvious that the utility model is not limited to the details of the above exemplary embodiments, and can be implemented in other specific forms without departing from the spirit or basic features of the utility model. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the utility model is limited by the attached claims rather than the above description, and it is intended to include all changes within the meaning and scope of the equivalent elements of the claims. Any figure mark in the claims should not be regarded as limiting the claims involved.
[0028] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A device for quickly lifting a long crane guide rail in a narrow area, comprising a door frame (16) and a running wheel (17) installed at the lower end of the door frame (16), characterized in that: A rectangular working platform (19) is fixedly provided at the upper end of the gantry (16), and a lifting mechanism and a positioning mechanism are fixedly installed at the four corners of the working platform (19). The lifting mechanism comprises an outer sleeve (14) vertically installed on the working platform (19), an inner tube (13) whose lower end is rotatably inserted into the outer sleeve (14), and an inclined rod (6) fixedly connected to the upper end of the inner tube (13). A fixed pulley (4) is installed at the upper end of the inclined rod (6), and a wire take-up wheel (61) is installed at the rear end of the inclined rod (6). The wire take-up wheel (61) A steel wire rope (5) is wound around the work platform (19), and the other end of the steel wire rope (5) passes over the fixed pulley (4) and is fixedly connected to the hanging plate (8); the positioning mechanism comprises a clamping plate seat (1) fixedly mounted on the working platform (19), a support rod (11) hinged to the upper end of the clamping plate seat (1), the clamping plate seat (1) comprises two clamping plates arranged on both sides of the support rod (11) and a fastening bolt (12) inserted through the upper end of the clamping plates, and a long hole (111) is arranged on the support rod (11), and the fastening bolt (12) is inserted into the long hole (111).
2. According to claim 1, a device for fast lifting of long crane guide rails in narrow areas, characterized in that: A plurality of inner tube axial holes are axially arranged on the tube wall of the inner tube (13), a short rod (101) is inserted through one of the inner tube axial holes, both ends of the short rod (101) are supported on the upper end surface of the outer tube (14), and a handle (10) is fixedly mounted on one end of the short rod (101).
3. A device for fast lifting of long crane guide rails in narrow areas according to claim 1 or 2, characterized in that: The upper end of the hanging plate (8) is connected to the steel wire rope (5), and the lower end of the hanging plate (8) is provided with a T-shaped groove for clamping the wing plate of the crane guide rail.
4. According to claim 2, a device for fast lifting of long crane guide rails in narrow areas, characterized in that: An annular flat washer (141) is fixedly welded to the upper end surface of the outer sleeve (14), and both ends of the short rod (101) are supported on the flat washer (141).
5. The device for fast lifting of long crane guide rails in narrow areas according to claim 1 or 2, characterized in that: A guardrail (15) is provided at the edge of the working platform (19).