Automatic feeding mechanism for central material pipe of yellow phosphorus electric furnace

The automatic feeding of the central material pipe of the yellow phosphorus electric furnace is achieved through the hydraulic remote control gate valve mechanism, which solves the problems of frequent inspections and flue gas/open flame overflow, improves operational safety and economic benefits, and extends the service life of the high-voltage switch .

CN222069292UActive Publication Date: 2024-11-26HUBEI XINGFA CHEM GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323290765.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-04
Publication Date
2024-11-26
Estimated Expiration
2033-12-04

AI Technical Summary

Technical Problem

The existing yellow phosphorus electric furnace central material pipe needs to be inspected every half hour and requires power outage, resulting in frequent use of SF6 high-voltage switches and flue/open flame overflow, endangering the operator and the environment.

Method used

A automatic feeding mechanism for the central material pipe of yellow phosphorus electric furnace is designed, and a hydraulic remote control gate valve mechanism is used to achieve remote operation and sealing improvement. The valve plate is driven to discharge material through the hydraulic cylinder to avoid manual operation and power outage.

Benefits of technology

It can operate without power outage, reduce the frequency of SF6 high-voltage switches, extend the service life, and prevent smoke and flame from overflowing, improving safety and environmental protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222069292U_ABST
    Figure CN222069292U_ABST
Patent Text Reader

Abstract

The utility model provides a yellow phosphorus electric furnace center material pipe automatic feeding mechanism which comprises a center material pipe communicated with an electric furnace body, the center material pipe is provided with a hydraulic remote control gate valve mechanism, the hydraulic remote control gate valve mechanism comprises a vertically-through installation box body, and installation plates are arranged in the middles of the upper side and the lower side of the installation box body. The mounting plate divides the mounting box into a feeding area and a valve plate temporary retention area, an upper opening and a lower opening of the valve plate temporary retention area are sealed through sealing plates, a connecting flange of the center material pipe is connected with an opening of the feeding area, a valve plate is arranged in the mounting box and connected with a telescopic rod of a hydraulic cylinder, and the hydraulic cylinder is arranged at the end, away from the feeding area, of the mounting box. A through hole for a telescopic rod of the hydraulic cylinder to penetrate through is formed in one end of the installation box body. The mechanism can achieve remote operation blanking, power failure is not needed, and meanwhile the sealing performance is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of yellow phosphorus production equipment, in particular to an automatic feeding mechanism for a central material pipe of a yellow phosphorus electric furnace. Background Art

[0002] The existing yellow phosphorus electric furnace needs to inspect the central material pipe every half an hour, and to prevent electric shock, the central material pipe can only be operated when the furnace is powered off. During operation, smoke and even open flames often overflow from the gap between the central material pipe and the central material pipe discharge gate valve, which will cause serious harm to the operator's health and the environment in the long run.

[0003] The disadvantages of this technique are:

[0004] 1. The center material pipe of the yellow phosphorus electric furnace needs to be inspected every half an hour, and to prevent electric shock, the center material pipe can only be operated when the furnace is powered off. This requires the SF6 high-voltage switch to be operated every time there is a power outage, and the number of operations per day can even be as high as 50 times, while the maximum number of operations of the SF6 high-voltage switch is 10,000 times. Based on 50 operations per day, the SF6 high-voltage switch can only be used for 6 months before it needs to be replaced.

[0005] 2. During the operation of the center pipe discharge valve, smoke and even open flames often overflow from the gap between the center pipe and the center pipe discharge gate valve. Over time, the smoke will cause harm to the operator's health.

[0006] 3. In addition, since smoke and even open flames overflow from the gap between the central material pipe and the central material pipe discharge gate valve, it also causes harm to safety and environmental protection, pollutes the on-site environment, and is not conducive to the construction of a green factory. Summary of the invention

[0007] The technical problem to be solved by the utility model is to provide an automatic feeding mechanism for the central material pipe of a yellow phosphorus electric furnace, which can be remotely operated without power outage and improves the sealing performance.

[0008] In order to solve the above technical problems, the technical solution adopted by the utility model is: an automatic feeding mechanism for the central material pipe of a yellow phosphorus electric furnace, comprising a central material pipe connected to the electric furnace body, the central material pipe is provided with a hydraulic remote-controlled gate valve mechanism, the hydraulic remote-controlled gate valve mechanism comprises an installation box which passes through from top to bottom, and installation plates are provided in the middle of the upper and lower sides of the installation box, the installation plate divides the installation box into a feeding area and a valve plate temporary retention area, the upper and lower openings of the valve plate temporary retention area are sealed by a sealing plate, the connecting flange of the central material pipe is connected to the opening of the feeding area, a valve plate is provided in the installation box, the valve plate is connected to the telescopic rod of the hydraulic cylinder, the hydraulic cylinder is arranged at one end of the installation box away from the feeding area, and a through hole for the telescopic rod of the hydraulic cylinder to pass through is provided at one end of the installation box.

[0009] In a preferred solution, a pressure plate is provided around one side of the sealing plate away from the mounting box, and the pressure plate is connected to the sealing plate and the mounting box by bolts.

[0010] In a preferred solution, a slide groove cooperating with the valve plate is provided inside the installation box.

[0011] In a preferred solution, sealing fillers are provided around the upper and lower sides of the valve plate.

[0012] In a preferred solution, the hydraulic cylinder is installed at the end of the mounting box through a gland, and the gland covers and seals the through hole through which the telescopic rod of the hydraulic cylinder passes.

[0013] The utility model provides an automatic feeding mechanism for the central material pipe of a yellow phosphorus electric furnace, which has the following beneficial effects:

[0014] 1. The hydraulic cylinder drives the valve plate to move, realizing remote operation of material discharge. No manual operation is required on site, thus saving human resources and realizing intelligent requirements.

[0015] 2. It can be operated without power outage, which increases the start-up rate of the electric furnace and improves economic benefits.

[0016] 3. Good sealing, no smoke and flame overflow during material discharge, meeting the safety and environmental protection requirements of the device.

[0017] 4. When discharging materials, there is no need for manual operation and the electric furnace does not need to be powered off, so there is no need to frequently operate the switch, which greatly reduces the frequency of switch operation and greatly extends the service life of the high-voltage switch. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The utility model is further described below in conjunction with the accompanying drawings and embodiments:

[0019] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0020] Figure 2 It is a structural schematic diagram of the hydraulic remote-controlled gate valve mechanism when the sealing plate is not installed;

[0021] Figure 3 This is a schematic diagram of the structure of the hydraulic remote-controlled gate valve mechanism after the sealing plate is installed;

[0022] Figure 4 It is a schematic diagram of the distribution of sealing packing;

[0023] In the figure: electric furnace body 1, central material pipe 2, mounting box 3, mounting plate 4, sealing plate 5, valve plate 6, hydraulic cylinder 7, pressure plate 8, pressure cover 9, feeding area 301, valve plate temporary retention area 302, slide groove 303, sealing packing 601. DETAILED DESCRIPTION

[0024] like Figures 1 to 3 As shown, an automatic feeding mechanism for the central material pipe of a yellow phosphorus electric furnace includes a central material pipe 2 connected to the electric furnace body 1, and the central material pipe 2 is provided with a hydraulic remote-controlled gate valve mechanism, and the hydraulic remote-controlled gate valve mechanism includes an installation box 3 that is connected from top to bottom. The installation box 3 is a rectangular box that is connected from top to bottom, so as to form a through passage after being connected with the central material pipe 2, so as to facilitate feeding. A mounting plate 4 is provided in the middle of both upper and lower sides of the installation box 3, and the mounting plate 4 divides the installation box 3 into a feeding area 301 and a valve plate temporary retention area 302. A valve plate 6 is provided in the installation box 3, and the valve plate 6 can move along the length direction of the installation box 3, move to the position of the feeding area 301, realize material blocking, and move to the position of the valve plate temporary retention area 302, so that the central material pipe 2 can be fed.

[0025] The upper and lower openings of the valve plate temporary retention area 302 are sealed by the sealing plate 5, and the connecting flange of the central material pipe 2 is connected to the opening of the feeding area 301, that is, the central material pipe 2 and the feeding area 301 form a connecting material channel, and the material is added to the electric furnace body 1 through the channel. The valve plate temporary retention area 302 is sealed by the sealing plate 5 to prevent smoke or open flames from escaping from the matching gap between the valve plate 6 and the mounting box 3 and leaking from the opening of the valve plate temporary retention area 302.

[0026] The valve plate 6 is connected to the telescopic rod of the hydraulic cylinder 7. The hydraulic cylinder 7 is arranged at one end of the installation box 3 away from the feeding area 301. The end of the installation box 3 is provided with a through hole for the telescopic rod of the hydraulic cylinder 7 to pass through.

[0027] Preferably, a pressure plate 8 is provided around the side of the sealing plate 5 away from the installation box 3, and the pressure plate 8 is connected to the sealing plate 5 and the side wall of the installation box 3 by bolts. The installation strength of the sealing plate 5 is improved by providing the pressure plate 8, and in specific use, a sealing gasket can also be provided at the bottom of the sealing plate 5 to improve the sealing performance.

[0028] Preferably, a slide groove 303 cooperating with the valve plate 6 is provided inside the installation box 3. By providing the slide groove 303, on the one hand, the movement of the valve plate 6 is limited, and on the other hand, the sealing performance of the valve plate 6 is improved.

[0029] Preferably, Figure 4 As shown, the valve plate 6 is provided with sealing packing 601 around the upper and lower sides. The sealing packing 601 is a circle of graphite packing pressed on the upper and lower sides of the valve plate 6 to seal the valve plate 6 in and out of the feed area 301.

[0030] Preferably, the hydraulic cylinder 7 is installed at the end of the mounting box 3 via a gland 9, which covers and seals the through hole through which the telescopic rod of the hydraulic cylinder 7 passes, thereby preventing smoke from overflowing from the gap of the through hole through which the telescopic rod of the hydraulic cylinder 7 passes.

[0031] When in use, the hydraulic cylinder 7 is connected to the hydraulic station through a hydraulic oil pipe, and a solenoid valve is provided on the hydraulic oil pipe, and the oil inlet and oil return are controlled by the solenoid valve, and the solenoid valve is controlled by the DCS system. Each time the central material pipe 2 is unloaded, the central control personnel give instructions to the DCS system. After the DCS instructions are given, the solenoid valve of the hydraulic station controls the oil inlet and oil return system of the hydraulic oil pipe, and the hydraulic cylinder 7 is controlled to move through the hydraulic oil pipe, driving the valve plate 6 to enter the feeding area 301 connected to the central material pipe 2, realizing the unloading closure, and the hydraulic cylinder 7 retracts, driving the valve plate 6 to move to the valve plate temporary retention area 302, and starting the unloading.

[0032] The mechanism can remotely unload materials through the DCS system and operate without power outage, which improves the furnace start-up rate and improves economic benefits.

[0033] Remote operation is realized, and no manual operation is required on site, thereby saving human resources and meeting intelligent requirements.

[0034] Since no manual operation is required during unloading, the electric furnace does not need to be powered off, and thus there is no need to frequently operate the SF6 switch, which greatly reduces the operation frequency of the SF6 switch and greatly extends the service life of the SF6 high-voltage switch.

[0035] The sealing between the valve plate 6 and the mounting box 3 is achieved by the sealing filler 601, which is the first seal. The sealing plate 5 can be used to provide a second seal against overflowing smoke or open flames. The third seal is achieved by providing a pressure cover 9, which has good sealing performance and does not cause smoke or flame overflow during material discharge, thus meeting the safety and environmental protection requirements of the device.

Claims

1. An automatic feeding mechanism for a central material pipe of a yellow phosphorus electric furnace, comprising a central material pipe (2) connected to an electric furnace body (1), characterized in that: The central material pipe (2) is provided with a hydraulic remote-controlled gate valve mechanism, which comprises a mounting box (3) which is connected from top to bottom, and mounting plates (4) are provided in the middle of the upper and lower sides of the mounting box (3), and the mounting plates (4) divide the mounting box (3) into a feed area (301) and a valve plate temporary retention area (302), and the upper and lower openings of the valve plate temporary retention area (302) are sealed by a sealing plate (5), and the connecting flange of the central material pipe (2) is connected to the opening of the feed area (301), and a valve plate (6) is provided in the mounting box (3), and the valve plate (6) is connected to the telescopic rod of the hydraulic cylinder (7), and the hydraulic cylinder (7) is arranged at one end of the mounting box (3) away from the feed area (301), and one end of the mounting box (3) is provided with a through hole for the telescopic rod of the hydraulic cylinder (7) to pass through.

2. The automatic feeding mechanism for the central material tube of a yellow phosphorus electric furnace according to claim 1, characterized in that: A pressure plate (8) is provided around the side of the sealing plate (5) away from the installation box (3), and the pressure plate (8) is connected to the sealing plate (5) and the installation box (3) by bolts.

3. The automatic feeding mechanism for the central material tube of a yellow phosphorus electric furnace according to claim 1, characterized in that: The inner side of the installation box (3) is provided with a sliding groove (303) that cooperates with the valve plate (6).

4. The automatic feeding mechanism for the central material tube of a yellow phosphorus electric furnace according to claim 1, characterized in that: Sealing fillers (601) are provided around the upper and lower sides of the valve plate (6).

5. The automatic feeding mechanism for the central material tube of a yellow phosphorus electric furnace according to claim 1, characterized in that: The hydraulic cylinder (7) is mounted on the end of the mounting box (3) via a gland (9), and the gland (9) covers and seals a through hole through which the telescopic rod of the hydraulic cylinder (7) passes.