Fire alarm processing system for multi-period construction

By designing a fire alarm and treatment system built in multiple phases in the thermal power plant, the signal connection between the first phase and the later phase of fire control devices is realized, the problems of equipment waste and misoperation are solved, and the efficiency of fire emergency response is improved and security.

CN222286299UActive Publication Date: 2025-01-03CENT SOUTHERN CHINA ELECTRIC POWER DESIGN INST CHINA POWER ENG CONSULTING GROUP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421016001.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-11
Publication Date
2025-01-03
Estimated Expiration
2034-05-11

AI Technical Summary

Technical Problem

In the thermal power plants built in multiple phases, it is difficult for existing technology to achieve linkage of fire alarm and disposal facilities, resulting in the early construction of facilities that need to be re-integrated into new systems, resulting in the risk of waste of equipment and misoperation of operations.

Method used

Design a fire alarm handling system built in multiple phases, through signal connection between the first phase and the later phase fire control device, including communication facilities, operation terminals and monitoring terminals, and use optical cables and hard wiring to establish signal connections to realize two phases of equipment. centralized control and unified management.

Benefits of technology

It reduces the cost of equipment relocation and transformation, reduces the difficulty for operators to become familiar with the new system, and improves the efficiency of emergency response in emergencies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222286299U_ABST
    Figure CN222286299U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of linkage control, and particularly discloses a fire alarm processing system for multi-period construction. Through the system structure, it is guaranteed that the fire pump device, alarm information and disposal measures can be shared, tedious schemes of overall relocation, first-time existing on-site equipment wiring transformation and the like are avoided, the change amount of a first-time built area is minimum, and the functions of unified management and control in a later-period fire control room are well achieved. And the operation methods of the new system and the old system are similar, so that safety monitoring personnel can be familiar and mastered conveniently, and time is gained for emergency disposal when a fire disaster occurs. The system is suitable for being popularized in a project of realizing fire alarm centralized control in a power plant / power station which is constructed by stages.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of linkage control, and specifically discloses a multi-phase constructed fire alarm disposal system. Background Art

[0002] According to the current standard "Design Fire Protection Standard for Thermal Power Plants and Substations", the fire control room should be arranged together with the centralized control room. According to the "General Code for Building Fire Protection" (implemented on June 1, 2023), the fire control room is required to be located on the first floor or underground floor of the building, and the evacuation door should lead directly to the outdoors or the emergency exit.

[0003] Based on the above design background, the fire control room of thermal power plants that have been built or have started construction before June 1, 2023 will be combined with the centralized control room and located on the operation floor. For thermal power plants that start expansion after June 1, 2023, the fire control room will be set up separately and located on the first floor of the building.

[0004] Large thermal power plants are often built in phases. When the second phase is constructed, the flow and head of the first phase fire pump will be recalculated to see if they can meet the requirements of the second phase. If the flow and head are not enough, the fire pump needs to be replaced; if the flow and head are enough, the fire pump of the first phase can be used directly. In short, the fire pumps of the first and second phases of the thermal power plant are shared by the two phases regardless of whether they are replaced or not. However, the smoke and exhaust fans and various monitoring facilities are configured separately for the two phases.

[0005] If the linkage of fire alarm handling facilities is to be achieved in multiple phases of construction, it is often necessary to reintegrate the facilities that have been built in the early stage into the new system, which brings great waste. At the same time, the operators have to familiarize themselves with the monitoring plan of the new system again. In the process of switching between the old and new systems, it is easy to cause misoperation in emergency situations due to unfamiliarity. Utility Model Content

[0006] In order to solve the technical problems listed in the background technology, the utility model provides a multi-phase construction fire alarm handling system. The specific technical solution is as follows:

[0007] A multi-phase fire alarm handling system includes a first-phase fire control device and a later-phase fire control device. Both the first-phase fire control device and the later-phase fire control device include communication facilities, operation terminals and monitoring terminals located in the same control room; the same equipment in the communication facilities, operation terminals and monitoring terminals of the first-phase fire control device and the later-phase fire control device respectively establish signal connections; wherein the communication facilities include a host computer, a centralized fire alarm controller, a fire linkage controller, a fire alarm telephone host, and a fire alarm broadcast host, the host computer provides an interactive interface for the centralized fire alarm controller, and the centralized fire alarm controller is signal-connected with the fire linkage controller, the fire alarm telephone host, and the fire alarm broadcast host respectively; the operation terminal includes a fire pump operation terminal and a smoke and exhaust fan operation terminal; the monitoring terminal includes an emergency lighting and evacuation indication system controller, a fire door monitor, and a fire power supply monitor; the monitoring terminal of the later-phase fire control device also includes a display connected to the first-phase DCS (distributed monitoring system) cabinet, and the first-phase DCS cabinet stores fire water tank status information.

[0008] Preferably, the monitoring terminals and smoke and exhaust fan operating terminals of the first-phase fire control unit and the later-phase fire control unit are respectively electrically connected to the corresponding equipment on site, and only the fire water pump operating terminal of the first-phase fire control unit is electrically connected to the fire water pump on site.

[0009] Preferably, the same type of equipment in the communication facility and the monitoring terminal establish signal connections respectively through optical cables; the same type of equipment in the operation terminal establish signal connections respectively through hard wiring.

[0010] Compared with the prior art, the utility model has the following advantages:

[0011] The utility model provides a multi-phase fire alarm handling system, which avoids the cumbersome schemes such as overall relocation and reconstruction of the existing on-site equipment wiring in the first phase in the later construction, minimizes the amount of changes in the first phase built area, and well realizes the function of unified management and control in the later fire control room. It saves the procurement cost of multi-phase fire pumps, and the operation methods of the new and old systems are similar, which is convenient for security monitoring personnel to be familiar with and master, and wins time for emergency handling when a fire occurs. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of a fire alarm handling system constructed in two phases in an embodiment of the utility model. DETAILED DESCRIPTION

[0013] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model is described below in conjunction with the accompanying drawings and specific embodiments. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on this embodiment, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0014] like Figure 1 As shown, a multi-phase fire alarm handling system provided by an embodiment of the utility model includes a first-phase fire control device and a second-phase fire control device. Both the first-phase fire control device and the second-phase fire control device include communication facilities, operation terminals and monitoring terminals located in the same control room; wherein, the communication facilities include a host computer, a centralized fire alarm controller, a fire linkage controller, a fire alarm telephone host, and a fire alarm broadcast host. The host computer provides an interactive interface for the centralized fire alarm controller. The operation terminal includes a fire pump control button and a fire smoke and exhaust fan control button (i.e., the fire pump operation terminal and the smoke and exhaust fan operation terminal in the invention content); the monitoring terminal includes an emergency lighting and evacuation indication system controller, a fire door monitor, and a fire power supply monitor; the monitoring terminal of the later fire control device also includes a display connected to the first-phase DCS cabinet in communication, and the first-phase DCS cabinet stores the fire water tank status information.

[0015] The existing connection lines of Phase I are as follows: the Phase I centralized fire alarm controller is connected to the Phase I fire alarm area controller through an optical cable; the Phase I fire water pump control button is connected to the Phase I fire water pump control box through hard wiring; the Phase I fire smoke and exhaust fan control button is connected to the Phase I smoke and exhaust fan control box through hard wiring; the Phase I emergency lighting and evacuation indication system controller is connected to the Phase I emergency lighting and evacuation indication lighting box through a communication bus; the Phase I fire door monitor is connected to the Phase I fire door monitoring module through a communication bus; the Phase I electrical fire monitoring system host is connected to the Phase I residual current electrical fire monitoring detector through a communication bus; the Phase I fire power supply monitor is connected to the Phase I fire power supply cabinet through a communication bus; the Phase I centralized fire alarm controller realizes operation and display functions through the Phase I host computer operation station.

[0016] The second phase connection lines are as follows: the second phase centralized fire alarm controller is connected to the second phase fire alarm area controller through an optical cable; the second phase fire smoke and exhaust fan control button is connected to the second phase smoke and exhaust fan control box through hard wiring; the second phase emergency lighting and evacuation indication system controller is connected to the second phase emergency lighting and evacuation indication lighting box through a communication bus; the second phase fire door monitor is connected to the second phase fire door monitoring module through a communication bus; the second phase electrical fire monitoring system host is connected to the second phase residual current electrical fire monitoring detector through a communication bus; the second phase fire power supply monitor is connected to the second phase fire power supply cabinet through a communication bus; the second phase centralized fire alarm controller realizes operation and display functions through the second phase host computer operation station.

[0017] The connection lines between Phase I and Phase II are as follows: Phase I centralized fire alarm controller is connected to Phase II centralized fire alarm controller through optical cable; Phase I fire linkage controller is connected to Phase II fire linkage controller through optical cable; Phase I fire alarm telephone host is connected to Phase II fire alarm telephone host through optical cable; Phase I fire alarm broadcast host is connected to Phase II fire alarm broadcast host through optical cable; Phase I emergency lighting and evacuation indication system controller is connected to Phase II emergency lighting and evacuation indication system controller through optical cable; Phase I fire door monitor is connected to Phase II fire door monitor through optical cable; Phase I electrical fire monitoring system host is connected to Phase II The mainframe of the electrical fire monitoring system is connected via an optical cable; the first-phase fire power supply monitor is connected to the second-phase fire power supply monitor via an optical cable; a first-phase fire pump control button is set in the cabinet of the second-phase host computer operation station, and is hard-wired and connected to the first-phase fire pump control button contact in the cabinet of the first-phase host computer operation station; a first-phase fire smoke and exhaust fan control button is set in the cabinet of the second-phase host computer operation station, and is hard-wired and connected to the first-phase fire smoke and exhaust fan control button contact in the cabinet of the first-phase host computer operation station; the second-phase fire water tank status display is hard-wired to the first-phase DCS cabinet.

[0018] After the first phase centralized fire alarm controller and the first phase fire linkage controller are interconnected with the second phase centralized fire alarm controller and the second phase fire linkage controller respectively, the operation and display functions of the first and second phases can be realized in the second phase host computer operation station, realizing the functions of centralized control and fire linkage between the two phases.

[0019] After the first phase fire alarm broadcast host and the second phase fire alarm broadcast host are interconnected, they can receive the linkage control signal from the second phase fire linkage controller to realize the functions of two-phase centralized control and fire linkage.

[0020] After the first phase fire alarm telephone host and the second phase fire alarm telephone host are interconnected, the second phase fire alarm telephone host can be set as a fire-dedicated telephone switchboard, so that each telephone extension in the two phases can be connected to the switchboard individually.

[0021] After the first-phase emergency lighting and evacuation indication system controller and the second-phase emergency lighting and evacuation indication system controller are interconnected, they can receive the linkage start signal from the second-phase fire linkage controller to realize the functions of two-phase centralized control and fire linkage.

[0022] After the first phase fire door monitor, the first phase electrical fire monitoring system host, and the first phase fire power supply monitor are interconnected with the second phase fire door monitor, the second phase electrical fire monitoring system host, and the second phase fire power supply monitor respectively, the status of related equipment in the two phases can be monitored simultaneously in the second phase fire control room.

[0023] Because the fire pump is shared by the two phases, a control button for the fire pump of the first phase is set on the cabinet of the host computer operation station of the second phase, so that the one-key start function of the fire pump can be realized in the fire control room of the second phase.

[0024] The control buttons of the fire smoke prevention and exhaust fans of the first phase are set in the cabinet of the second phase host computer operation station, so that the manual direct control of the fire smoke prevention and exhaust fans of the whole plant can be realized in the second phase fire control room.

[0025] The fire water tank status display of the second phase needs to display the fire water tank liquid level status and alarm signal from the first phase DCS cabinet, avoiding the tedious installation and wiring work of reinstalling the liquid level meter from the fire water tank.

[0026] Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions described in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A multi-phase fire alarm handling system, comprising a first-phase fire centralized control device and a later-phase fire centralized control device, wherein the first-phase fire centralized control device and the later-phase fire centralized control device both comprise communication facilities, operation terminals and monitoring terminals located in the same control room; characterized in that: Signal connections are established for the same equipment in the communication facilities, operation terminals and monitoring terminals of the first phase fire control device and the later phase fire control device respectively; wherein, the communication facilities include a host computer, a centralized fire alarm controller, a fire linkage controller, a fire alarm telephone host, and a fire alarm broadcast host; the host computer provides an interactive interface for the centralized fire alarm controller, and the centralized fire alarm controller is signal-connected with the fire linkage controller, the fire alarm telephone host, and the fire alarm broadcast host respectively; the operation terminal includes a fire pump operation terminal and a smoke and exhaust fan operation terminal; the monitoring terminal includes an emergency lighting and evacuation indication system controller, a fire door monitor, and a fire power supply monitor; the monitoring terminal of the later phase fire control device also includes a display connected to the first phase DCS cabinet in communication, and the first phase DCS cabinet stores the fire water tank status information.

2. A multi-phase fire alarm handling system according to claim 1, characterized in that: The monitoring terminals and smoke and exhaust fan operating terminals of the first phase fire control unit and the later phase fire control unit are electrically connected to the corresponding equipment on site, and only the fire water pump operating terminal of the first phase fire control unit is electrically connected to the fire water pump on site.

3. A multi-phase fire alarm handling system according to claim 2, characterized in that: The same type of equipment in the communication facility and the monitoring terminal respectively establishes signal connection through optical cables; the same type of equipment in the operation terminal respectively establishes signal connection through hard wiring.