Pipeline foundation template mounting and supporting device
By designing the installation support device of the pipeline foundation formwork and using the combined structure of the positioning bracket and the connecting rod, the problem of slow fixing and reinforcement speed and easy positioning in the prior art is solved, and efficient and stable installation of the formwork and the improvement of the concrete quality are achieved.
Patent Information
- Application Number
- CN202420896927.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-28
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2034-04-28
AI Technical Summary
In the prior art, after the pipeline foundation formwork is installed, the fixing and reinforcement speed is slow, which can easily lead to the formwork offset and affect the apparent quality of concrete and construction efficiency.
A pipe foundation formwork installation support device is designed, adopting a combined structure of positioning bracket and connecting rod, and positioning and adjustment is achieved by pulling bolts and long strip connecting holes, enhancing the stability and installation efficiency of the formwork.
It improves the stability and installation efficiency of the formwork, avoids the deviation of the formwork, improves the quality and construction efficiency of concrete, and reduces the secondary reinforcement of the formwork during construction.
Smart Images

Figure CN222632322U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of municipal engineering, in particular to a pipeline foundation template installation support device. Background Art
[0002] In the prior art, after the pipeline foundation template is installed, the template is usually fixed with steel bar heads, square wood, large stones, etc., and then concrete is poured.
[0003] However, the inventors found in the process of implementing the embodiments of the present application that this construction method requires a lot of man-hours for installation and fixation, the reinforcement speed is slow, and the concrete pouring process has high requirements. The formwork is easily displaced when pouring concrete, and the apparent quality of the concrete is poor after the formwork is removed, which affects the appearance. The entire construction process is prone to formwork deviation due to poor reinforcement, and the formwork needs to be continuously reinforced in the middle, which not only greatly reduces the construction efficiency but also makes it difficult to ensure the construction quality. Summary of the invention
[0004] The purpose of the utility model is to provide a pipeline foundation template installation support device, which provides an auxiliary roller at the top to assist in positioning while effectively reducing resistance, thereby improving the efficiency and safety of rolling operations.
[0005] To achieve the above purpose, the technical solution of the utility model is:
[0006] A pipeline foundation template installation support device, comprising:
[0007] Positioning bracket: The positioning bracket comprises an L-shaped plate, one end of the L-shaped plate is provided with a fixing hole, and the other end of the L-shaped plate is provided with a connecting portion;
[0008] Connecting rod: Both ends of the connecting rod are connected to positioning brackets through connecting parts.
[0009] Furthermore: reinforcing ribs are provided between the two sides of the L-shaped plate, so that the template is less likely to deform during the construction process. The reinforcing ribs are supporting steel plates, and the supporting steel plates are fixed between the two sides of the L-shaped plate by welding.
[0010] Furthermore, the present application can adjust the distance between the two positioning brackets by controlling the fixed position of the connecting rod on the positioning bracket.
[0011] Furthermore, in order to facilitate the connection of the two positioning brackets and adjust the distance between the positioning brackets, the connecting rod is a tension bolt.
[0012] The connection between the connecting rod and the positioning bracket may not only be through a threaded connection with tension bolts, but may also be fixed between the connecting rod and the positioning bracket through an adjustable connection method such as quick release and clamping.
[0013] Furthermore, the connecting portion is an elongated connecting hole, so that the connecting rod can move up and down in the elongated connecting hole to adjust the height of the connecting rod, making it easier to pour concrete for the pipeline foundation.
[0014] Further, as another option of the present application, in order to adjust the height of the connecting rod, the connecting portion is a plurality of through holes so that different height gears can be set according to actual needs.
[0015] Furthermore, the pipeline foundation template installation support device also includes a fixing member, so that the pipeline foundation template installation support device can be fixed on the ground through the fixing member and the fixing hole.
[0016] Furthermore, there are more than one fixing hole. Usually, the device can be stably fixed on the ground by only one fixing hole and a fixing piece. If it is necessary to deal with special circumstances, the stability of the device can be further enhanced by adding fixing holes and fixing pieces. Preferably, the fixing piece is a steel chisel. Beneficial Effects
[0017] 1. This application uses oblique supports for fixing, and the two sides are connected and fixed with tension bolts, which improves the stability of the formwork, avoids the deviation of the formwork during concrete pouring, makes the formwork more solid and reliable, and the poured concrete has been greatly improved in terms of quality and appearance, with significant effects. At the same time, it reduces the secondary reinforcement of the formwork during construction and improves construction efficiency.
[0018] 2. The device can adapt to a variety of template sizes through the setting of long strip connection holes, and can be repeatedly used, which greatly improves construction efficiency and saves construction costs.
[0019] 3. This method improves the stability and installation efficiency of the formwork by using the auxiliary device to fix and install the formwork, avoiding adverse effects on the next step of concrete pouring due to formwork problems. At the same time, the auxiliary device greatly improves the stability of the formwork. At the same time, the auxiliary device can be recycled and reused, avoiding waste of labor, machinery and materials during construction, and greatly saving costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a front view of a pipeline foundation template installation support device of the utility model.
[0021] Figure 2 It is a side view of a pipeline foundation template installation support device of the utility model.
[0022] Figure 3 It is a top view of the pipeline foundation template installation support device of the utility model.
[0023] Figure 4 It is a construction schematic diagram of a pipeline foundation template installation support device of the utility model.
[0024] In the figure: 1. L-shaped plate, 2. fixing hole, 3. connecting part, 4. reinforcing rib, 5. connecting rod, 6. fixing part, A. template.
[0025] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the utility model.
[0027] Embodiment 1: A pipeline foundation template installation support device, comprising:
[0028] A pipeline foundation template installation support device, comprising:
[0029] Positioning bracket: The positioning bracket includes an L-shaped plate 1, one end of the L-shaped plate 1 is provided with a fixing hole 2, the other end of the L-shaped plate 1 is provided with a connecting portion 3, and reinforcing ribs 4 are provided between the two sides of the L-shaped plate 1, so that its template is less likely to deform during the construction process, and the connecting portion 3 is a long strip connecting hole, so that the connecting rod 5 can move up and down in the long strip connecting hole to adjust the height of the connecting rod 5, making it more convenient to pour concrete for the pipeline foundation;
[0030] Connecting rod 5: Both ends of the connecting rod 5 are connected to positioning brackets through connecting parts 3, so that the distance between the two positioning brackets can be adjusted by controlling the fixed position of the connecting rod 5 on the positioning bracket. The connecting rod 5 is a tension bolt. It is more convenient to connect the two positioning brackets, and the distance between the positioning brackets can be adjusted by adjusting the nut;
[0031] The fixing member 6 is a steel chisel, and the fixing member 6 fixes the positioning device on the ground through the fixing hole 2.
[0032] In addition, as other options, the utility model also discloses the following technical solutions based on the above embodiments;
[0033] 1. The connection between the connecting rod 5 and the positioning bracket can be not only through the threaded connection of the tension bolts, but also through adjustable connection methods such as quick release and clamping to achieve the fixation between the connecting rod 5 and the positioning bracket.
[0034] 2. As another option of the present application, in order to adjust the height of the connecting rod 5, the connecting portion 3 is provided with a plurality of through holes so that different height positions can be set according to actual needs.
[0035] 3. There are more than one fixing holes 2. Normally, the device can be stably fixed on the ground by only one fixing hole 2 and the fixing piece 6. If special circumstances are to be dealt with, the stability of the device fixation can be further enhanced by increasing the fixing holes 2 and the fixing piece 6.
[0036] The preparation method is as follows;
[0037] 1. Required materials: A steel chisel with a diameter of 0.02m and a height of 0.3m, a set of tension bolts with a diameter of 0.016m, and a steel plate of 0.005m*0.5m*1m.
[0038] 2. Cut the 5mm steel plate into a 0.3m long steel backrest, a 0.25m long base, and a 0.2m long inclined support steel plate.
[0039] 3. Cut the steel drill holes on the base steel plate, with the center distance of 0.04m and the diameter of 0.022m. At the same time, cut the long strip connection holes at the bolt placement position of the backrest steel plate, with a width of 0.02m.
[0040] 4. Finally, weld the base and backrest steel plates to form the L-shaped plate 1, and then weld the 0.2m inclined support steel plate to both sides of the L-shaped plate 1. Use J422 welding rod to ensure the welding quality, and then insert the tension bolts into the slide groove of the backrest steel plate.
[0041] Here’s how to use it:
[0042] After releasing the template edge line, place the positioning bracket on the edge line and fix the positioning bracket with a steel chisel.
[0043] Place the two side templates A against one side of the positioning bracket with a long strip connection hole and tighten the tension bolts accordingly.
[0044] Formwork A reinforcement is completed and concrete is poured.
[0045] The above description is only a specific implementation method of the present utility model, but the protection scope of the present utility model is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present utility model, which should be included in the protection scope of the present utility model. Therefore, the protection scope of the present utility model should be based on the protection scope of the claims.
Claims
1. A pipeline foundation template installation support device, characterized in that: include; Positioning bracket: The positioning bracket comprises an L-shaped plate, one end of the L-shaped plate is provided with a fixing hole, and the other end of the L-shaped plate is provided with a connecting portion; Connecting rod: Both ends of the connecting rod are connected to positioning brackets through connecting parts.
2. A pipeline foundation template installation support device according to claim 1, characterized in that: Reinforcing ribs are arranged between the two sides of the L-shaped plate.
3. A pipeline foundation template installation support device according to claim 1, characterized in that: The connecting rod is a tension bolt.
4. A pipeline foundation template installation support device according to claim 1, characterized in that: The connecting portion is a long strip-shaped connecting hole.
5. A pipeline foundation template installation support device according to claim 1, characterized in that: The connecting parts are a plurality of through holes.
6. A pipeline foundation template installation support device according to claim 5, characterized in that: There are more than one fixing hole.
7. A pipeline foundation template installation support device according to any one of claims 1 to 6, characterized in that: The pipeline foundation template installation support device also includes a fixing member, so that the pipeline foundation template installation support device can be fixed on the ground through the fixing member and the fixing hole.
8. A pipeline foundation template installation support device according to claim 7, characterized in that: The fixing piece is a steel chisel.