Stiff column type steel framework splicing structure

By using deviation correction connecting components in the steel frame splicing structure, the problems of cumbersome operation and difficulty in fine adjustment in the prior art are solved, and efficient and simple construction process and precise deviation correction effect are achieved.

CN222649015UActive Publication Date: 2025-03-21CSCEC STRAIT CONSTR & DEV
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420985765.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-08
Publication Date
2025-03-21
Estimated Expiration
2034-05-08

AI Technical Summary

Technical Problem

The prior art requires the use of multiple jacks when splicing steel frames, which are cumbersome and difficult to achieve precise fine-tuning, resulting in low construction efficiency and difficulty in correcting operation.

Method used

The corrective connection assembly is adopted, including a double-headed screw and a positioning seat, and the support height and deflection are adjusted through the double-headed screw, and precise fine-tuning and positioning is achieved using the cross positioning groove and the adjustment screw.

Benefits of technology

No need to use jack equipment, the construction process is simple and efficient, and the deviation correction operation is easy and accurate, which significantly improves the splicing efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222649015U_ABST
    Figure CN222649015U_ABST
Patent Text Reader

Abstract

The utility model discloses a stiff column type steel framework splicing structure which comprises a lower section type steel framework fixed on a foundation plane and an upper section type steel framework installed above the lower section type steel framework, an installation groove is formed in the top of the lower section type steel framework, and a deviation rectifying connecting assembly is arranged in the installation groove. The upper section steel framework is fixedly connected with the lower section steel framework after being rectified and positioned by the rectifying connecting component; the deviation rectifying connecting assembly is arranged between the upper section steel framework and the lower section steel framework, the supporting height of the deviation rectifying connecting assembly is adjusted through a middle double-thread screw, deviation is adjusted through peripheral adjusting screws, and the upper section steel framework can be assembled and positioned through the embedded connection mode of a cross-shaped positioning groove and cross-shaped steel; the whole construction process does not need to be assisted by jack equipment, accurate fine adjustment can be achieved through thread screwing adjustment, construction is efficient, simple and convenient, and deviation rectifying operation is easy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a rigid column-type steel frame splicing structure. Background Art

[0002] The rigid column is a steel rigid column, which uses the internal structure of the steel as a supporting force frame, welds bolts on the outer surface, ties the steel bars and pours concrete to form a tightly integrated structure. The steel rigid concrete structure has the advantages of high strength, small cross-sectional dimensions of the components, strong bond strength with concrete, space saving, reduced cost, improved engineering quality, and significantly improved seismic performance of the structure. It is currently widely used in super-high-rise buildings and buildings with seismic requirements.

[0003] Steel rigid columns are generally set in the core tube of a single building. To meet the requirements of earthquake-resistant design, they all run through the top of the structure. Considering the hoisting conditions of the steel structure construction on site, the steel frame is processed and hoisted in sections, assembled and welded section by section to meet the mechanical lifting and step-by-step layered construction of the main structure.

[0004] The installation accuracy of the upper and lower sections of the steel skeleton directly affects the quality and safety of the upper building structure. Generally, before the upper and lower sections of the steel skeleton are welded and connected on site, it is necessary to use a measuring instrument to detect the verticality and correct the tilt state; in the prior art, such as Chinese patent CN106150105A, a method for installing a rigid column is disclosed, in which an adjustment plate is welded on the outer wall of the upper and lower sections of the steel skeleton, and a jack is placed between the upper and lower adjustment plates. By operating the jacks on each side to lift, the vertical state of the upper section of the steel skeleton is adjusted to achieve tilt correction.

[0005] This operation plan requires the use of multiple jacks for operation, which need to be dismantled after use, and the operation is cumbersome. Moreover, during the actual correction operation, due to the large dead weight of the steel frame itself, it is difficult to accurately push the jack back a small amount, making the operation difficult. Utility Model Content

[0006] In order to solve the above problems existing in the prior art, the utility model provides a rigid column type steel frame splicing structure.

[0007] The technical solution of the utility model is as follows:

[0008] A rigid column steel frame splicing structure comprises a lower steel frame fixed on a foundation plane and an upper steel frame installed above the lower steel frame, wherein a mounting groove is provided on the top of the lower steel frame, and a deviation correction connection component is arranged in the mounting groove; the upper steel frame is fixedly connected to the lower steel frame after deviation correction positioning by the deviation correction connection component.

[0009] Preferably, the deviation-correcting connection assembly includes a double-headed screw and a pair of positioning seats, wherein the pair of positioning seats are symmetrically arranged at both ends of the double-headed screw, and the thread rotation directions of the screws at both ends of the double-headed screw are opposite.

[0010] Preferably, the positioning seat includes a cross base, on which a cross positioning groove is provided, and the cross positioning groove is used to match with the upper section steel frame and the lower section steel frame.

[0011] Preferably, threaded holes are provided on the bottom surfaces of the four directions of the cross positioning groove located at the top longitudinally, and adjusting screws are respectively screwed inside the threaded holes, with the screw ends of the adjusting screws facing the inside of the cross positioning groove.

[0012] Preferably, a nut seat is fixedly provided on the cross base for threaded connection with the double-headed screw.

[0013] Preferably, the upper section steel frame and the lower section steel frame are both cross-shaped steels, and the ends of the cross-shaped steels also have side panels, and bolts are evenly arranged on the outer walls of the side panels.

[0014] Preferably, longitudinal steel bars are distributed circumferentially around the periphery of the upper section steel frame and the lower section steel frame, and concrete is poured around the upper section steel frame, the lower section steel frame and the longitudinal steel bars to form a rigid column.

[0015] The utility model has the following beneficial effects: the utility model sets a deviation correction connection component between the upper section steel frame and the lower section steel frame; the deviation correction connection component uses a middle double-headed screw to adjust the support height, uses surrounding adjustment screws to adjust the deflection, and the interlocking connection method of the cross positioning groove and the cross steel can also assemble and position the upper section steel frame; the entire construction process does not require the assistance of jack equipment, and the threaded screw adjustment can achieve precise fine-tuning, the construction is efficient and simple, and the deviation correction operation is easy. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0017] Figure 2 It is a top view of the overall device of the utility model;

[0018] Figure 3 It is a structural schematic diagram of the deviation-correcting connection assembly of the utility model;

[0019] Figure 4 It is a top view of the deviation-correcting link assembly of the utility model;

[0020] Figure 5 It is a schematic diagram of the installation sequence flow of the utility model.

[0021] The reference numerals in the figure are as follows:

[0022] 1. Upper section of steel frame; 2. Lower section of steel frame; 3. Correction connection assembly; 310. Positioning seat; 311. Cross positioning groove; 312. Nut seat; 313. Cross base; 320. Adjusting screw; 330. Double-headed screw; 4. Bolts; 5. Longitudinal reinforcement; 6. Foundation plane. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] See also Figures 1 to 5 A rigid column steel frame splicing structure comprises a lower steel frame 2 fixed on a foundation plane 6 and an upper steel frame 1 installed above the lower steel frame 2. An installation groove is provided on the top of the lower steel frame 2, and a correction connection component 3 is arranged in the installation groove; the upper steel frame 1 is fixedly connected to the lower steel frame 2 after correction positioning by the correction connection component 3.

[0025] Furthermore, the deviation-correcting connection assembly 3 includes a double-headed screw 330 and a pair of positioning seats 310 . The pair of positioning seats 310 are symmetrically arranged at both ends of the double-headed screw 330 , and the thread rotation directions of the screws at both ends of the double-headed screw 330 are opposite.

[0026] Furthermore, the positioning seat 310 includes a cross base 313 , on which a cross positioning groove 311 is formed. The cross positioning groove 311 is used to match with the upper section steel frame 1 and the lower section steel frame 2 .

[0027] Furthermore, threaded holes are provided on the bottom surfaces of the four directions of the cross positioning groove 311 located at the top longitudinally, and the adjusting screws 320 are respectively screwed inside the threaded holes, and the screw ends of the adjusting screws 320 face the inside of the cross positioning groove 311 .

[0028] Furthermore, a nut seat 312 is fixedly provided on the cross base 313 for threadedly connecting the double-headed screw 330 .

[0029] Furthermore, the upper section steel frame 1 and the lower section steel frame 2 are both cross-shaped steels, and the ends of the cross-shaped steels are also provided with side panels, and bolts 4 are evenly provided on the outer walls of the side panels.

[0030] Furthermore, longitudinal steel bars 5 are distributed circumferentially around the outer periphery of the upper section steel frame 1 and the lower section steel frame 2, and concrete is poured around the upper section steel frame 1, the lower section steel frame 2 and the longitudinal steel bars 5 to form a rigid column.

[0031] The working principle of this utility model:

[0032] In the utility model, the rigid steel column is formed by adding a steel frame in the middle of the vertical steel bars of the conventional reinforced concrete column, and welding nails on the periphery of the steel frame to increase the bond strength between the steel column and concrete to form a vertical member that bears the force together. The steel column with a rigid column steel core is called a rigid steel column, i.e., a steel frame. The first section of the steel column that is first hoisted and fixed on the foundation plane is the first section of the rigid steel column, i.e., the lower section of the steel frame 2. The structure comprises a lower section of the steel frame 2 fixed on the foundation plane 6 and an upper section of the steel frame 1 installed above the lower section of the steel frame 2. A mounting groove is provided on the top of the lower section of the steel frame 2, in which a deviation correction connection component 3 is arranged. The upper section of the steel frame 1 is fixedly connected to the lower section of the steel frame 2 after being corrected and positioned by the deviation correction connection component 3. At the same time, longitudinal steel bars 5 are circumferentially distributed around the outer periphery of the upper section of the steel frame 1 and the lower section of the steel frame 2. Concrete is poured around the upper section of the steel frame 1, the lower section of the steel frame 2 and the longitudinal steel bars 5 to form a rigid column. The upper section of the steel frame 1 and the lower section of the steel frame 2 are both cross-shaped steels, and the ends of the cross-shaped steels also have side panels, and bolts 4 are evenly arranged on the outer walls of the side panels for fastening.

[0033] In this structure, in order to refine the verticality of the first frame, the height of the first frame is generally not set too high. Therefore, longitudinal steel bars 5 are distributed circumferentially around the outer periphery of the upper steel frame 1 and the lower steel frame 2, and concrete is poured around the upper steel frame 1, the lower steel frame 2 and the longitudinal steel bars 5 to form a rigid column.

[0034] According to the construction method of connecting the rigid columns section by section, the upper section of the steel frame 1 and the lower section of the steel frame 2 can be fixedly connected by welding; since the accuracy of the end face of the steel frame cannot be very accurately controlled during processing, and there are operational errors in the hoisting construction process, after the upper section of the steel frame is hoisted and connected with the lower section of the steel frame by a crane, it is necessary to consider the interference and adjust the inclination state of the upper section of the steel frame, so the upper section of the steel frame 1 and the lower section of the steel frame 2 are fixedly connected after the correction positioning of the correction connection component 3; therefore, an installation groove is opened on the top of the lower section of the steel frame 2, and the correction connection component 3 is arranged in the installation groove.

[0035] The deviation-correcting connection assembly 3 includes a double-headed screw 330 and a pair of positioning seats 310. The pair of positioning seats 310 are symmetrically arranged at the two ends of the double-headed screw 330, and the screw threads at the two ends of the double-headed screw 330 have opposite rotation directions. At the same time, an external hexagonal column is installed in the middle of the double-headed screw 330 for cooperating with a wrench to screw the double-headed screw 330. Since the screw threads at the two ends of the double-headed screw 330 have opposite rotation directions, when the external hexagonal column in the middle is rotated to control the rotation of the double-headed screw 330, the spacing between the upper and lower positioning seats 310 can be adjusted, and the entire upper section of the steel frame 1 can be lifted or lowered.

[0036] Among them, the positioning seat 310 includes a cross base 313, on which a cross positioning groove 311 is opened, and the cross positioning groove 311 is used to adapt to the upper section steel frame 1 and the lower section steel frame 2; the bottom surfaces of the four directions of the cross positioning groove 311 located at the top longitudinally are provided with threaded holes, and the insides of the threaded holes are respectively screwed with adjusting screws 320, and the screw ends of the adjusting screws 320 face the inside of the cross positioning groove 311. By rotating the adjusting screw 320, the length of its screw section extending into the cross positioning groove 311 can be adjusted, that is, the support height of the cross steel end face in the cross positioning groove 311 can be adjusted.

[0037] In actual work, when the upper section of the steel frame 1 is observed by external measuring instruments or deflected to one side, the adjusting screw 320 corresponding to this side is adjusted to lift upward, so as to fine-tune the upper section of the steel frame 1 to a perpendicular state with the foundation plane 6, and then the connection can be welded; in addition, since the cross-shaped steel end face used in the upper section of the steel frame 1 is embedded in the cross positioning groove 311 of the positioning seat 310 during installation, the correction connection assembly 3 has a correction effect on the upper section of the steel frame 1 and a positioning effect. When the upper section of the steel frame 1 is hoisted and slowly falls, it falls into the cross positioning groove 311, which can save the manual adjustment of the end face alignment, and the operation is more convenient.

[0038] It should be noted that during alignment and correction operations, the correction connection assembly 3 cannot be used as a complete load-bearing structure and requires lifting equipment to assist in lifting. After the correction positioning is completed, welding construction can be carried out at the connection, and the lifting equipment can be withdrawn after welding is completed.

[0039] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A rigid column steel frame splicing structure, comprising a lower steel frame (2) fixed on a foundation plane (6) and an upper steel frame (1) installed above the lower steel frame (2), characterized in that: The top of the lower section steel frame (2) is provided with an installation groove, and a deviation correction connection component (3) is arranged in the installation groove; the upper section steel frame (1) is fixedly connected to the lower section steel frame (2) after being corrected and positioned by the deviation correction connection component (3); the deviation correction connection component (3) comprises a double-headed screw (330) and a pair of positioning seats (310), and the pair of positioning seats (310) are symmetrically arranged at the two ends of the double-headed screw (330), and the screw threads at the two ends of the double-headed screw (330) have opposite rotation directions; the positioning seat (310) comprises a cross base (313), and the cross base (313) is provided with a cross positioning groove (311), and the cross positioning groove (311) is used to adapt to the upper section steel frame (1) and the lower section steel frame (2).

2. The rigid column steel skeleton splicing structure according to claim 1 is characterized in that: The bottom surfaces of the cross positioning groove (311) located at the top in the longitudinal direction in four directions are provided with threaded holes, and the insides of the threaded holes are respectively threaded with adjusting screws (320), and the screw ends of the adjusting screws (320) face the inside of the cross positioning groove (311).

3. The rigid column steel skeleton splicing structure according to claim 1 is characterized in that: The cross base (313) is fixedly provided with a nut seat (312) for threadedly connecting the double-headed screw (330).

4. The rigid column steel skeleton splicing structure according to claim 1 is characterized in that: The upper section steel frame (1) and the lower section steel frame (2) are both cross-shaped steels, and the ends of the cross-shaped steels also have side panels, and bolts (4) are evenly arranged on the outer walls of the side panels.

5. The rigid column steel skeleton splicing structure according to claim 1 is characterized in that: Longitudinal steel bars (5) are distributed circumferentially around the outer periphery of the upper section steel frame (1) and the lower section steel frame (2), and concrete is poured around the upper section steel frame (1), the lower section steel frame (2) and the longitudinal steel bars (5) to form a rigid column.

Citation Information

Patent Citations

  • Stiff column installing method

    CN106150105A