Prefabricated I-beam composite floor installation structure
By adopting support adjustment devices and double connection reinforcement methods of embedded connecting plates and internal thread casings in prefabricated buildings, the problem of low connection strength between reinforced skeleton and concrete overlapping floor slabs in the prior art is solved, and high connection is achieved Strength and flatness adjustment are suitable for seismic design, improving construction quality and stability.
Patent Information
- Application Number
- CN201910278355.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-04-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2039-04-09
AI Technical Summary
In existing prefabricated buildings, the connection strength between the steel skeleton and concrete overlapping floor slabs is not high and is difficult to adjust, resulting in matching problems in seismic design, cumbersome operation, and difficult to meet the needs of modern buildings.
Using vertical and parallel arrangement of left steel concrete composite wall and right steel concrete composite wall, embedded connecting plate and internal threaded casing, the high connection of I-steel overlapping floor slabs is ensured through support adjustment devices and double connection reinforcement. Strength and flatness adjustment.
It realizes a prefabricated I-steel stacked floor installation structure for easy operation, high connection strength and good stability, which is suitable for seismic design and improves construction quality and stability.
Smart Images

Figure CN109972730B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of assembled building construction, and in particular relates to an assembled I-beam composite floor slab installation structure. Background Art
[0002] In recent years, due to the increasing requirements of energy-saving and emission-reduction policies, the sharp increase in labor prices, and the widespread promotion of advanced technologies in prefabricated structures, the application of prefabricated structures has begun to get rid of the trough and show a rapid upward trend. Prefabricated buildings are currently mainly suitable for non-seismic design and various types of civil buildings of Class B and below in seismic design areas with seismic fortification intensity of 6-8 degrees. In the application process of prefabricated buildings, the existing composite floor slabs are made of steel skeleton + lower concrete, which is greatly mismatched with the installation of prefabricated steel-concrete composite shear walls. Not only is the operation cumbersome, but the connection strength is not high, and the horizontality is not easy to adjust during the actual installation process. . Summary of the invention
[0003] In order to solve the deficiencies in the prior art, the present invention provides an assembled I-beam composite floor installation structure which is easy to operate, has high connection strength and is easy to adjust the horizontality.
[0004] To solve the above technical problems, the present invention adopts the following technical scheme: an assembled I-beam composite floor installation structure, comprising a left steel-concrete composite wall and a right steel-concrete composite wall arranged perpendicularly and parallel to the I-beam composite wall, at least two support and adjustment devices are arranged on the right side of the left steel-concrete composite wall and the left side of the right steel-concrete composite wall at the same height, a plurality of connecting plates and a plurality of internal threaded sleeves are pre-buried inside the left steel-concrete composite wall and the right steel-concrete composite wall, the connecting plates at the same height are evenly arranged in the front-to-back direction, the internal threaded sleeve is located between two adjacent connecting plates at the same height, the right side surface of the connecting plate in the left steel-concrete composite wall and the right end of the internal threaded sleeve are both flush with the right side surface of the left steel-concrete composite wall, the left side surface of the connecting plate in the right steel-concrete composite wall and the left end of the internal threaded sleeve are both flush with the left side surface of the right steel-concrete composite wall, and the left and right sides of the I-beam composite floor are respectively arranged at the upper ends of the left and right support and adjustment devices.
[0005] All support and adjustment devices have the same structure. A support and adjustment device on the right side of the left steel-concrete composite wall includes two connecting sleeves embedded in the left steel-concrete composite wall. The two connecting sleeves are arranged up and down. The two connecting sleeves are connected to the open support frame on the right side through a connecting bolt. A support bolt is threadedly connected to the top of the support frame. The head of the support bolt is located above the support frame. A support plate with an L-shaped cross section is arranged on the upper end of a row of support bolts at the same side and height. There is a gap between the left side of the upper part of the support frame and the right side of the left steel-concrete composite wall, and the left side of the support plate is located in the gap.
[0006] The I-beam composite floor slab includes I-beams of the same number as the connecting plates. All I-beams are arranged horizontally in the left-right direction. Both ends of each I-beam correspond to and contact a connecting plate on the right side of the left steel-concrete composite wall and a connecting plate on the left side of the right steel-concrete composite wall. A number of cast holes are arranged at intervals along the length direction on the web of the I-beam. A horizontal steel mesh at the same height as the bottom of the cast hole is laid on the lower part of the I-beam. The lower layer of concrete is cast outside the horizontal steel mesh. The left and right sides of the lower layer of concrete are 10-50cm away from the left steel-concrete composite wall and the right steel-concrete composite wall, respectively. The left and right bottoms of the lower concrete layer are supported on the left and right support plates, and a number of longitudinal steel bars are arranged in the front-to-back direction at the same height as the top of the cast through-holes. The longitudinal steel bars pass through the cast through-holes and are welded to the I-beams as a whole. Two layers of internal threaded sleeves are arranged between two adjacent connecting plates, and the internal threaded sleeves of the upper layer are all threadedly connected with upper transverse steel bars. The upper transverse steel bars are located above the longitudinal steel bars and are tied to the longitudinal steel bars as a whole, and the internal threaded sleeves of the lower layer are threadedly connected with lower transverse steel bars. The right ends of the lower transverse steel bars in a row on the left are in contact with the left side of the lower concrete layer, and the left ends of the lower transverse steel bars in a row on the right are in contact with the right side of the lower concrete layer.
[0007] With the above technical solution, each casting hole is in the shape of a runway, and two longitudinal steel bars are inserted into each casting hole. First, adjust the flatness of the composite floor slab, use a wrench to tighten the support bolts, and adjust the height of the support plate by the height of the support bolts, so as to fine-tune the flatness of the composite floor slab, and then weld the two ends of the I-beam to the adjacent connecting plates, and then lay pipelines on the surface of the lower concrete layer before pouring the upper concrete layer, and pour the longitudinal steel bars, lower transverse steel bars, upper transverse steel bars and I-beams at the height of the inner support plate. After the pouring is completed and the upper concrete is solidified, remove the support adjustment device and seal the connecting sleeve.
[0008] The invention adopts a double connection reinforcement method, in which the I-beam is welded to the connection plate embedded in the left steel-concrete composite wall and the right steel-concrete composite wall, and the upper transverse steel bars and the lower transverse steel bars are threadedly connected to the internal threaded sleeve and cast in the upper concrete, thereby ensuring the reliability and stability of the connection between the floor slab and the steel-concrete composite wall.
[0009] The connecting plate, internal threaded sleeve and connecting sleeve are embedded in the steel-concrete composite pipe according to the design drawings when the factory makes it. The I-beam composite floor slab formed by pouring and connecting the lower concrete, horizontal steel mesh and I-beam is also made in the factory.
[0010] The invention has novel design, simple structure, easy operation, and can adjust the horizontality before pouring, thereby ensuring the construction quality, and has high connection strength and good stability. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a three-dimensional structural schematic diagram of the present invention;
[0012] Figure 2 yes Figure 1 The enlarged view of point A in the middle;
[0013] Figure 3 yes Figure 1 Enlarged view of point B in the middle. DETAILED DESCRIPTION
[0014] like Figure 1 , Figure 2 and Figure 3 As shown, the assembled I-beam composite floor installation structure of the present invention includes a left steel concrete composite wall 1 and a right steel concrete composite wall 2 which are arranged perpendicularly and parallel to each other. At least two support adjustment devices 3 are arranged on the right side of the left steel concrete composite wall 1 and the left side of the right steel concrete composite wall 2 at the same height. A plurality of connecting plates 5 and a plurality of internal threaded sleeves 4 are pre-buried inside the left steel concrete composite wall 1 and the right steel concrete composite wall 2. The connecting plates 5 at the same height are evenly arranged in the front-to-back direction. The internal threaded sleeve 4 is located between two adjacent connecting plates 5 at the same height. The right side surface of the connecting plate 5 in the left steel concrete composite wall 1 and the right end of the internal threaded sleeve 4 are both flush with the right side surface of the left steel concrete composite wall 1, and the left side surface of the connecting plate 5 in the right steel concrete composite wall 2 and the left end of the internal threaded sleeve 4 are both flush with the left side surface of the right steel concrete composite wall 2. The left and right sides of the I-beam composite floor 6 are respectively arranged on the upper ends of the left and right support adjustment devices 3.
[0015] The structures of all the support and adjustment devices 3 are the same. A support and adjustment device 3 on the right side of the left steel-concrete composite wall 1 includes two connecting sleeves embedded in the left steel-concrete composite wall 1. The two connecting sleeves are arranged up and down, and the two connecting sleeves are connected to the right open support frame 8 through a connecting bolt. A support bolt 9 is threadedly connected to the top of the support frame 8, and the head of the support bolt 9 is located above the support frame 8. A support plate 10 with an L-shaped cross section is arranged on the upper end of a row of support bolts 9 at the same side and at the same height. There is a gap between the upper left side of the support frame 8 and the right side surface of the left steel-concrete composite wall 1, and the left side of the support plate 10 is located in the gap. The setting of the gap can enhance the stability of the support plate 10, and the support plate serves as a bottom template.
[0016] The I-beam composite floor 6 includes I-beams 11 of the same number as the connecting plates 5. All the I-beams 11 are arranged horizontally in the left-right direction. Both ends of each I-beam 11 correspond to and contact a connecting plate 5 on the right side of the left steel-concrete composite wall 1 and a connecting plate 5 on the left side of the right steel-concrete composite wall 2. A plurality of cast holes 12 are arranged at intervals along the length direction on the web of the I-beam 11. A horizontal steel mesh 13 of the same height as the bottom of the cast hole 12 is laid on the lower part of the I-beam 11. A lower layer of concrete 14 is cast on the outside of the horizontal steel mesh 13. The left and right sides of the lower layer of concrete 14 are 10-50 cm away from the left steel-concrete composite wall 1 and the right steel-concrete composite wall 2, respectively. The bottoms of the left and right sides of the lower concrete layer 14 are supported on the left and right support plates 10, and a plurality of longitudinal steel bars 15 are arranged at the same height as the top of the cast through hole 12 along the front-to-back direction. The longitudinal steel bars 15 pass through the cast through hole 12 and are welded to the I-beam 11 as a whole. Two layers of internal threaded sleeves 4 are arranged between two adjacent connecting plates 5, and the internal threaded sleeves 4 of the upper layer are all threadedly connected with upper transverse steel bars 16, and the upper transverse steel bars 16 are located above the longitudinal steel bars 15 and are tied to the longitudinal steel bars 15 as a whole. The internal threaded sleeves 4 of the lower layer are threadedly connected with lower transverse steel bars 17, and the right ends of a row of lower transverse steel bars 17 on the left side are in contact with the left side edge of the lower concrete layer 14, and the left ends of a row of lower transverse steel bars 17 on the right side are in contact with the right side edge of the lower concrete layer 14.
[0017] Each casting through hole 12 is in the shape of a runway, and two longitudinal steel bars 15 are inserted into each casting through hole 12. First, adjust the flatness of the composite floor slab, use a wrench to tighten the support bolts 9, and adjust the height of the support plate 10 by the height of the support bolts 9, so as to fine-tune the flatness of the composite floor slab, and then weld the two ends of the I-beam 11 to the adjacent connecting plates 5 as a whole, and then lay pipelines on the surface of the lower concrete 14 before pouring the upper concrete, and pour the longitudinal steel bars 15, the lower transverse steel bars 17, the upper transverse steel bars 16 and the I-beam 11 at the height of the inner support plate 10. After the pouring is completed and the upper concrete is solidified, the support adjustment device 3 is removed and the connecting sleeve is sealed.
[0018] The present invention adopts a double connection reinforcement mode by welding the I-beam 11 to the connection plate 5 pre-buried in the left steel-concrete composite wall 1 and the right steel-concrete composite wall 2, and pouring the upper transverse steel bar 16 and the lower transverse steel bar 17 threadedly connected to the internal threaded sleeve 4 in the upper concrete, thereby ensuring the reliability and stability of the connection between the floor slab and the steel-concrete composite wall.
[0019] The connecting plate 5, the internal threaded sleeve 4 and the connecting sleeve are embedded in the steel-concrete composite pipe according to the design drawings when the factory is manufacturing the steel-concrete composite pipe. The I-beam composite floor slab 6 formed by pouring and connecting the lower concrete 14, the horizontal steel mesh 13 and the I-beam 11 is also manufactured in the factory.
[0020] This embodiment does not impose any formal limitation on the shape, material, structure, etc. of the present invention. Any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the technical solution of the present invention.
Claims
1. The assembled I-beam composite floor installation structure is characterized by: It comprises a left steel-concrete composite wall and a right steel-concrete composite wall which are arranged perpendicularly and in parallel, at least two support adjustment devices are arranged on the right side of the left steel-concrete composite wall and the left side of the right steel-concrete composite wall at the same height, a plurality of connection plates and a plurality of internal threaded sleeves are pre-buried inside the left steel-concrete composite wall and the right steel-concrete composite wall, the connection plates at the same height are evenly arranged in the front-to-back direction, the internal threaded sleeve is located between two adjacent connection plates at the same height, the right side surface of the connection plate in the left steel-concrete composite wall and the right end of the internal threaded sleeve are both flush with the right side surface of the left steel-concrete composite wall, the left side surface of the connection plate in the right steel-concrete composite wall and the left end of the internal threaded sleeve are both flush with the left side surface of the right steel-concrete composite wall, and the left and right parts of the I-beam composite floor slab are respectively arranged at the upper ends of the left and right support adjustment devices; All the support adjustment devices have the same structure. A support adjustment device on the right side of the left steel-concrete composite wall includes two connecting sleeves embedded in the left steel-concrete composite wall. The two connecting sleeves are arranged up and down. The two connecting sleeves are connected to the right open support frame through a connecting bolt. A support bolt is threadedly connected to the top of the support frame. The head of the support bolt is located above the support frame. A support plate with an L-shaped cross section is arranged at the upper end of a row of support bolts at the same side and height. There is a gap between the left side of the upper part of the support frame and the right side of the left steel-concrete composite wall. The left side of the support plate is located in the gap. The I-beam composite floor slab includes I-beams with the same number as the connecting plates. All I-beams are arranged horizontally in the left-right direction. Both ends of each I-beam correspond to and contact a connecting plate on the right side of the left steel-concrete composite wall and a connecting plate on the left side of the right steel-concrete composite wall. A number of cast holes are arranged at intervals along the length direction on the web of the I-beam. A horizontal steel mesh at the same height as the bottom of the cast hole is laid on the lower part of the I-beam. The lower layer of concrete is cast on the outside of the horizontal steel mesh. The left and right bottoms of the lower concrete layer are supported on the left and right support plates, and a number of longitudinal steel bars are arranged in the front-to-back direction at the same height as the top of the cast through-holes. The longitudinal steel bars pass through the cast through-holes and are welded to the I-beams as a whole. Two layers of internal threaded sleeves are arranged between two adjacent connecting plates, and the internal threaded sleeves of the upper layer are all threadedly connected with upper transverse steel bars. The upper transverse steel bars are located above the longitudinal steel bars and are tied to the longitudinal steel bars as a whole, and the internal threaded sleeves of the lower layer are threadedly connected with lower transverse steel bars. The right ends of the lower transverse steel bars in a row on the left are in contact with the left side of the lower concrete layer, and the left ends of the lower transverse steel bars in a row on the right are in contact with the right side of the lower concrete layer.
2. The assembled I-beam composite floor installation structure according to claim 1 is characterized in that: Each casting through hole is in the shape of a runway, and two longitudinal steel bars are passed through each casting through hole.
Citation Information
Patent Citations
Precast composite outer insulated wall plate and manufacturing method thereof
CN101831986A
Building adopting aseismatic precasted reinforcing steel truss shear wall composite structure
CN103397696A
Reusable overhanging I-beam fixing device
CN202577939U
Assembly type I-shaped steel composite floor slab mounting structure
CN210049373U
multi-storey BUILDING OF COMBINED STRUCTURAL SYSTEM
EA201600480A1