A shear connector
By pre-embedding perforated steel plates and stirrups in the concrete structure, and using the connection method of pinned steel rods and mounting plates, the problem of docking accuracy and integrity of connectors in steel-concrete composite structures is solved, and efficient shear force is achieved. The connection enhances the shear resistance and integrity of the structure.
Patent Information
- Application Number
- CN201910474903.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-06-03
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2039-06-03
AI Technical Summary
In the prefabricated construction of steel-concrete composite structures, it is difficult for existing shear connectors to accurately connect the reserved holes in the concrete slab with the bolt connectors on the steel structure, and the reserved holes are too large to affect the integrity and cannot fully Make use of connectors.
A combined structure of pinned steel rods and perforated steel plates is used. By pre-embedding the pinned steel rod mounting plate and perforated steel plate in the concrete structure and welding them with the stirrups, the precision and integrity of the hole position docking can be improved. The pinned bolts are used The connection method between steel rods and mounting plates simplifies the installation process, reduces reserved holes, and enhances the shear resistance of the structure.
It achieves the precise connection between the concrete slab and the steel structure, reduces the impact of reserved holes on the integrity, improves the integrity and shear strength of the structure, and ensures the coordinated work of the steel structure and the concrete structure.
Smart Images

Figure CN110158448B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of bridge construction, and in particular to a shear connector. Background Art
[0002] Steel-concrete composite structures integrate steel and concrete structures through shear connectors, which are crucial for their mechanical performance. This structure fully utilizes the mechanical properties of both steel and concrete, offering advantages such as high bearing capacity, high rigidity, low deadweight, excellent stability, and easy construction. It is widely used in engineering fields such as bridges, building structures, and pipeline corridors.
[0003] With the advancement of engineering technology, demands for construction techniques and project quality are increasing, and the application of prefabricated construction technology is becoming increasingly widespread. Prefabricated construction allows for the complete assembly of structural components within the factory, improving component quality and reducing material consumption, which is crucial for building energy conservation. Prefabricated construction can significantly reduce on-site construction workload and time, making it crucial for projects with strict deadlines and harsh on-site environments.
[0004] The prefabricated construction of steel-concrete composite structures faces the problem of how to set up shear connectors. The most widely used bolt connectors currently require multi-point coordination. The reserved points in the precast concrete slab will change position due to the shrinkage of the concrete during the hardening process, making it impossible to complete the multi-point matching during the installation process. Since the perforated steel plate connectors continuously penetrate along the longitudinal direction of the beam, it is impossible to reserve a longitudinal penetration seam in the precast concrete slab, and it is impossible to achieve an effective connection between the perforated steel plate connector and the concrete precast slab. In the existing separate bolt group connection method, large holes are reserved in the concrete precast slab, and the longitudinal and transverse steel bars between the reserved holes are all cut off, which seriously affects the integrity of the concrete slab. In addition, the force between the bolt group and the precast concrete slab is only transmitted through the post-poured concrete. The bolt connector cannot fully play its role in connecting the steel structure and the concrete structure into a whole.
[0005] The prefabricated construction of steel-concrete composite structures requires addressing three key connector issues. First, how can the reserved holes in the precast concrete slabs precisely align with the stud connectors on the steel structure? Second, how can the reserved holes in the precast concrete slabs be minimized to minimize their impact on the integrity of the slabs? Third, how can the shear connectors be fully utilized to connect the steel and concrete structures into a single entity?
[0006] Patent CN201120487335 discloses a shear member for fastening concrete in bridge construction, including a shear member body composed of several interconnected shear member units, the shear member units including a support plate, mounting plates provided at both ends of the support plate, several groups of through holes provided on the mounting plate, and support columns provided between each group of through holes.
[0007] Although this patent uses shear member units connected to each other to form a whole, its supporting plate structure is relatively complex, resulting in a relatively complex manufacturing process; at the same time, the shear member unit setting method results in the shear members forming a whole, but has a greater impact on the integrity of the concrete.
[0008] There is a need for a shear connector that can precisely connect the reserved holes in the precast concrete slab with the bolt connectors on the steel structure; the reserved holes in the concrete slab are small; and it can connect the steel structure and the concrete structure into a whole. Summary of the Invention
[0009] In order to solve the problem in the prior art of the docking accuracy of the reserved holes in the concrete slab and the bolt connectors on the steel structure, reduce the impact on the integrity of the precast concrete slab, and give full play to the role of the shear connector, the present invention provides a shear connector with high concrete slab integrity, small reserved holes, and easy and precise docking, thereby solving the above problems.
[0010] The present invention provides a shear connector, including a pin steel rod, a pin steel rod mounting plate and a perforated steel plate, the pin steel rod mounting plate is provided with a mounting through hole, the pin steel rod is arranged in the mounting through hole, the pin steel rod mounting plate is vertically arranged on the upper surface of the steel structure, the perforated steel plate is provided with at least one through hole, the pin steel rod mounting plate vertically passes through the through hole, and the perforated steel plate is arranged above the steel structure.
[0011] By embedding a pin-bolt steel bar mounting plate within the concrete structure, the docking accuracy of the shear connector holes is improved; a simple, quick, and reliable connection is achieved through the pin-bolt steel bar and the pin-bolt steel bar mounting plate. Pre-set holes are set in the perforated steel plate at the designed location. The perforated steel plate is installed with its ends flush with the formwork to ensure that its position does not change during the concrete pouring process, achieving precise docking of the shear connector holes. After the perforated steel plate is installed in the concrete structure, ordinary stirrups and disconnected stirrups are laid and welded to the embedded perforated steel plate. The perforated steel plate can replace the longitudinal reinforcement at that location, avoiding the longitudinal reinforcement at that location being disconnected due to the reserved holes, thereby improving the integrity of the structure.
[0012] The connection method of the connector is that after the concrete slab and the steel structure are prefabricated, the through-hole positions of the perforated steel plate are connected, and then the pin steel rod is inserted into the pin steel rod installation plate to complete the reliable fixed connection of the shear connector.
[0013] Both reserved holes on the pin steel rod mounting plate and the perforated steel plate are considered to be appropriately enlarged to take into account the shrinkage of concrete and various errors.
[0014] The shear connector described in the present invention is, as a preferred embodiment, a pin steel rod including a first frustum, a second frustum, and a cylindrical connecting portion, the first frustum, the second frustum and the cylindrical connecting portion are coaxial, the lower surfaces of the first frustum and the second frustum are arranged on the two bottom surfaces of the cylindrical connecting portion, and the area of the lower surfaces of the first frustum and the second frustum is ≤ the area of the bottom surface of the cylindrical connecting portion.
[0015] In the shear connector described in the present invention, as a preferred embodiment, the first frustum and the second frustum are of the same shape and size, and the bottom areas of the first frustum and the second frustum are equal to the bottom area of the cylindrical connecting portion.
[0016] The use of shuttle-shaped pin steel rods facilitates positioning during splicing and improves splicing efficiency.
[0017] In the shear connector described in the present invention, as a preferred embodiment, the through hole of the perforated steel plate and the pin steel rod mounting plate are interference fit.
[0018] In the shear connector described in the present invention, as a preferred embodiment, the connection between the pin steel rod mounting plate and the steel structure is welding.
[0019] In the shear connector described in the present invention, as a preferred embodiment, the through hole of the pin steel rod mounting plate is a circular through hole, and the diameter of the through hole is the maximum width of the pin steel rod.
[0020] In the shear connector described in the present invention, as a preferred embodiment, the pin steel rod mounting plate is arranged transversely along the beam and on the top of the steel structure.
[0021] The pin-bolt steel column connection plate can also be arranged along the transverse direction of the beam to improve the transverse shear resistance.
[0022] In the shear connector described in the present invention, as a preferred embodiment, the pin steel rod connecting plate is arranged on the top of the steel structure along the longitudinal direction of the beam.
[0023] The pin-bolt steel column connection plate can be arranged along the longitudinal direction of the beam to improve the longitudinal shear performance.
[0024] The shear connector described in the present invention, as a preferred embodiment, further includes stirrups, the stirrups forming a plane perpendicular to the horizontal plane, and the stirrups present a three-dimensional grid structure.
[0025] You can add a description of how to use it
[0026] The stirrups include disconnected stirrups connected to the shear connectors and ordinary stirrups not connected to the shear connectors. Disconnected stirrups are set at positions where perforated steel plates are provided on the orthographic projection surface, and ordinary stirrups are set at positions where no perforated steel plates are provided on the orthographic projection surface.
[0027] The beneficial effects of the present invention are as follows:
[0028] (1) The embedded perforated steel plates in the reinforced concrete structure are welded to the ordinary stirrups and stirrups at the section openings, thus avoiding the impact of stirrup disconnection at the reserved holes and improving the integrity of the structure;
[0029] (2) Pre-embedded perforated steel plates in reinforced concrete structures can replace the longitudinal reinforcement at that location, thus avoiding the disconnection of the longitudinal reinforcement at that location due to the reserved holes and improving the integrity of the structure;
[0030] (3) After the steel structure and the concrete structure are installed according to the reserved holes, the two are integrated by installing pin steel rods in the perforated steel plates, which not only takes into account the convenience of construction but also ensures the effective connection of the connectors. The pin steel rods have a large rigidity and can effectively transmit the shear force between the steel structure and the concrete structure, while effectively resisting the lifting between the concrete structure and the steel structure.
[0031] (4) The perforated steel plates can be flexibly arranged in the longitudinal and transverse directions of the beam and have high applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 is a schematic diagram of the shear connector;
[0033] Figure 2 Schematic diagram of the shear connector pin steel rod.
[0034] Reference numerals:
[0035] 1. Pin steel rod; 11. First frustum; 12. Second frustum; 13. Cylindrical connection; 2. Pin steel rod mounting plate; 3. Perforated steel plate; 4. Steel structure. DETAILED DESCRIPTION
[0036] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0037] Example 1
[0038] like Figure 1 As shown, a shear connector includes a pin steel rod 1, a pin steel rod mounting plate 2 and a perforated steel plate 3. The pin steel rod mounting plate 2 is provided with a mounting through hole, the pin steel rod 1 is arranged in the mounting through hole, the pin steel rod mounting plate 2 is vertically arranged on the upper surface of the steel structure 4, the perforated steel plate 3 is provided with at least one through hole, the pin steel rod mounting plate 2 vertically passes through the through hole, and the perforated steel plate 3 is arranged above the steel structure 4.
[0039] The pin steel bar mounting plate 2 is made of steel plate, the diameter of its circular hole matches the base circle diameter of the cylindrical connecting part of the pin steel bar, and its root is welded to the top of the steel structure.
[0040] like Figure 2 As shown, the pin steel bar 1 includes a first frustum 11, a second frustum 12, and a cylindrical connecting portion 13. The first frustum 11, second frustum 12, and cylindrical connecting portion 13 are coaxial. The lower surfaces of the first frustum 11 and second frustum 12 are disposed on both bottom surfaces of the cylindrical connecting portion 13. The first frustum 11 and second frustum 12 are identical in shape and size, and the lower bottom areas of the first frustum 11 and second frustum 12 are equal to the bottom area of the cylindrical connecting portion 13. The pin steel bar 1 is made of steel, and the pin steel bar mounting plates 2 can be arranged either longitudinally or transversely. The spacing, length, and arrangement of the pin steel bar mounting plates 2 can be designed and determined according to actual project requirements.
[0041] The construction method of the shear connector of the prefabricated composite structure includes the following steps:
[0042] S1, making a pin steel rod 1;
[0043] S2, making a steel beam and a pin steel rod mounting plate 2, and welding the pin steel rod mounting plate 2 to the top surface of the steel beam;
[0044] S3, make a concrete perforated steel plate 3; perform prefabricated reinforced concrete structure formwork support, lay the pin steel bar mounting plate 2, lay ordinary stirrups and disconnected stirrups at the reserved holes, weld the ordinary stirrups and disconnected stirrups to the perforated steel plate 3; lay longitudinal ordinary steel bars; set reserved holes at the positions of the concrete slab connectors; pour concrete, and remove the formwork after the concrete curing is completed;
[0045] S4. Perform on-site assembly by docking the steel structure pin steel bar mounting plate 2 with the reserved hole of the concrete slab; insert the pin steel bar 1 into the steel beam pin steel bar mounting plate 2 through the reserved hole of the concrete slab and the opposite end of the embedded perforated steel plate;
[0046] S5. Pour self-compacting, steam-free, slightly expanding ultra-high performance fiber concrete into the reserved holes.
[0047] During the prefabrication of the concrete structure, a pre-set hole is reserved to match the mounting plate 2 for the pin rod on the steel structure. A pre-set hole is also reserved to allow the pin rod 1 to be installed into the pre-set steel plate. Both pre-set holes are appropriately enlarged to account for concrete shrinkage and various errors.
[0048] Pre-set holes are set at the designed locations for the perforated steel plates 3. The pre-embedded perforated steel plates 3 are installed, with their ends flush with the formwork to ensure they remain in place during the concrete pouring process and precisely align the holes for the shear connectors. After the pre-embedded perforated steel plates 3 are installed within the concrete structure, conventional stirrups and disconnected stirrups are laid and welded to the pre-embedded perforated steel plates 3.
[0049] After the concrete structure and the steel structure are prefabricated and connected according to the reserved holes, the pin steel rod 1 is inserted into the pin steel rod mounting plate 2 to complete the reliable fixed connection of the shear connector.
[0050] After the concrete structure and steel structure are assembled, self-compacting, steam-free, micro-expanding ultra-high performance fiber concrete is poured into the reserved holes, taking into account the construction convenience and connection reliability.
[0051] The shear connector and construction method for prefabricated steel-concrete composite structures proposed in this invention involves pre-embedding a perforated steel plate (3) within the concrete structure and welding it to stirrups. A pinned steel bar mounting plate (2) is welded to the top surface of the steel beam. After factory prefabrication, the connector is installed through pre-reserved holes and secured with a pinned steel bar (1). After installation, self-compacting, steam-free, and micro-expanding ultra-high-performance fiber concrete is poured into the pre-reserved holes. This connection method significantly improves the integrity of the prefabricated steel-concrete composite structure, effectively enhancing its shear strength and rigidity, and ensuring the coordinated operation of the steel and concrete structures.
[0052] Example 2
[0053] like Figure 1 As shown, a shear connector includes a pin steel rod 1, a pin steel rod mounting plate 2 and a perforated steel plate 3. The pin steel rod mounting plate 2 is provided with a mounting through hole, the pin steel rod 1 is arranged in the mounting through hole, the pin steel rod mounting plate 2 is vertically arranged on the upper surface of the steel structure 4, the perforated steel plate 3 is provided with at least one through hole, the pin steel rod mounting plate 2 vertically passes through the through hole, and the perforated steel plate 3 is arranged above the steel structure 4.
[0054] The holes in the concrete perforated steel plate 3 should be drilled according to the pre-designed connector positions. A 1-2mm margin should be considered when drilling to account for various errors. Both ends of the steel plate should be flush with the formwork to prevent the embedded steel plate from changing position during the concrete pouring process and becoming incompatible with the pre-designed connectors.
[0055] The pin steel bar mounting plate 2 is made of steel plate, the diameter of its circular hole matches the base circle diameter of the cylindrical connecting part of the pin steel bar, and its root is welded to the top of the steel structure.
[0056] like Figure 2As shown, the pin steel bar 1 includes a first frustum 11, a second frustum 12, and a cylindrical connecting portion 13. The first frustum 11, second frustum 12, and cylindrical connecting portion 13 are coaxial. The lower surfaces of the first frustum 11 and second frustum 12 are disposed on both bottom surfaces of the cylindrical connecting portion 13. The first frustum 11 and second frustum 12 are identical in shape and size, and the lower bottom areas of the first frustum 11 and second frustum 12 are equal to the bottom area of the cylindrical connecting portion 13. The pin steel bar 1 is made of steel, and the pin steel bar mounting plates 2 can be arranged either longitudinally or transversely. The spacing, length, and arrangement of the pin steel bar mounting plates 2 can be designed and determined according to actual project requirements.
[0057] The construction method of the shear connector of the prefabricated composite structure includes the following steps:
[0058] S1, making a pin steel rod 1;
[0059] S2, making a steel beam and a pin steel rod mounting plate 2, and welding the pin steel rod mounting plate 2 to the top surface of the steel beam;
[0060] S3, make a concrete perforated steel plate 3; perform prefabricated reinforced concrete structure formwork support, lay the pin steel bar mounting plate 2, lay ordinary stirrups and disconnected stirrups at the reserved holes, weld the ordinary stirrups and disconnected stirrups to the perforated steel plate 3; lay longitudinal ordinary steel bars; set reserved holes at the positions of the concrete slab connectors; pour concrete, and remove the formwork after the concrete curing is completed;
[0061] S4. Perform on-site assembly by docking the steel structure pin steel bar mounting plate 2 with the reserved hole of the concrete slab; insert the pin steel bar 1 into the steel beam pin steel bar mounting plate 2 through the reserved hole of the concrete slab and the opposite end of the embedded perforated steel plate;
[0062] S5. Pour self-compacting, steam-free, slightly expanding ultra-high performance fiber concrete into the reserved holes.
[0063] During the prefabrication of the concrete structure, a pre-set hole is reserved to match the mounting plate 2 for the pin rod on the steel structure. A pre-set hole is also reserved to allow the pin rod 1 to be installed into the pre-set steel plate. Both pre-set holes are appropriately enlarged to account for concrete shrinkage and various errors.
[0064] The concrete slab includes a concrete slab body and high-performance fiber concrete. The concrete body is a plate type and is provided with a reserved hole. The reserved hole is a countersunk hole. The reserved hole is set at the opposite end of the embedded perforated steel plate. A through hole of the same size as the vertical position of the installation hole is set at the bottom of the reserved hole. A shear member is assembled through the through hole in the reserved hole, and the reserved hole is filled with high-performance fiber concrete.
[0065] Pre-set holes are set at the designed locations for the perforated steel plates 3. The pre-embedded perforated steel plates 3 are installed, with their ends flush with the formwork to ensure they remain in place during the concrete pouring process and precisely align the holes for the shear connectors. After the pre-embedded perforated steel plates 3 are installed within the concrete structure, conventional stirrups and disconnected stirrups are laid and welded to the pre-embedded perforated steel plates 3.
[0066] After the concrete structure and the steel structure are prefabricated and connected according to the reserved holes, the pin steel rod 1 is inserted into the pin steel rod mounting plate 2 to complete the reliable fixed connection of the shear connector.
[0067] After the concrete structure and steel structure are assembled, self-compacting, steam-free, micro-expanding ultra-high performance fiber concrete is poured into the reserved holes, taking into account the construction convenience and connection reliability.
[0068] The shear connector and construction method for prefabricated steel-concrete composite structures proposed in this invention involves pre-embedding a perforated steel plate (3) within the concrete structure and welding it to stirrups. A pinned steel bar mounting plate (2) is welded to the top surface of the steel beam. After factory prefabrication, the connector is installed through pre-reserved holes and secured with a pinned steel bar (1). After installation, self-compacting, steam-free, and micro-expanding ultra-high-performance fiber concrete is poured into the pre-reserved holes. This connection method significantly improves the integrity of the prefabricated steel-concrete composite structure, effectively enhancing its shear strength and rigidity, and ensuring the coordinated operation of the steel and concrete structures.
[0069] The above description is only a preferred specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any technician familiar with the technical field, within the technical scope disclosed by the present invention, who makes equivalent replacements or changes based on the technical solution and inventive concept of the present invention, should be covered by the scope of protection of the present invention.
Claims
1. A shear connector, Features: The invention comprises a pin steel bar (1), a pin steel bar mounting plate (2) and a perforated steel plate (3), wherein the pin steel bar mounting plate (2) is provided with a mounting through hole, the pin steel bar (1) is arranged in the mounting through hole, the pin steel bar mounting plate (2) is vertically arranged on the upper surface of the steel structure (4), the perforated steel plate (3) is provided with at least one through hole, the pin steel bar mounting plate (2) vertically passes through the through hole, and the perforated steel plate (3) is arranged above the steel structure (4).
2. A shear connector according to claim 1, Features: The pin steel rod (1) comprises a first frustum (11), a second frustum (12), and a cylindrical connecting portion (13); the first frustum (11), the second frustum (12) and the cylindrical connecting portion (13) are coaxial; the lower bottom surface of the first frustum (11) and the lower bottom surface of the second frustum (12) are respectively connected to the two bottom surfaces of the cylindrical connecting portion (13); the lower bottom surface area of the first frustum (11) and the lower bottom surface area of the second frustum (12) are ≤ the bottom surface area of the cylindrical connecting portion (13).
3. A shear connector according to claim 2, Features: The first truncated cone (11) and the second truncated cone (12) have the same shape and size, and the bottom surface areas of the first truncated cone (11) and the second truncated cone (12) are equal to the bottom surface area of the cylindrical connecting portion (13).
4. A shear connector according to any one of claims 1 to 3, Features: The through hole of the perforated steel plate (3) and the pin steel rod mounting plate (2) are in interference fit.
5. A shear connector according to claim 4, Features: The connection between the pin steel rod mounting plate (2) and the steel structure (4) is by welding.
6. A shear connector according to claim 5, Features: The through hole of the pin steel rod mounting plate (2) is a circular through hole, and the diameter of the through hole is the maximum width of the pin steel rod (1).
7. A shear connector according to claim 6, Features: The pin steel rod mounting plate (2) is arranged on the top of the steel structure (4) along the transverse direction of the beam.
8. A shear connector according to claim 6, Features: The pin steel rod mounting plate (2) is arranged on the top of the steel structure (4) along the longitudinal direction of the beam.
Citation Information
Patent Citations
Shearing force part for fastening concrete in bridge construction
CN202323763U
Shear connecting piece
CN210975497U