Assembled combined stopper for cable-stayed bridge and use method thereof

Through the design of the prefabricated combined blocks of the cable-stayed bridge, bolted connections and post-cast tape fixation are used to avoid manual cutting of the thrust blocks, solve the problems of complex construction and damage to the anti-corrosion structure, and achieve simple construction, reduced costs and shortened the construction period. shortening effect.

CN110644351BActive Publication Date: 2024-10-25GUIZHOU BRIDGE CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910919110.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-26
Publication Date
2024-10-25
Estimated Expiration
2039-09-26

AI Technical Summary

Technical Problem

The construction of the existing cable-stayed bridge is complicated during the installation and rotation process. Manual cutting of the thrust blocks will destroy the anti-corrosion structure, and the cutting process has a high risk factor, affecting the steel beam structure, and the construction period is long and the cost is high.

Method used

The prefabricated combined block of the cable-stayed bridge is used, and the notches of the prefabricated block and the fixed block are connected by bolts, and the post-casting tape is used to fix the steel beam to avoid manual cutting, realize the separability and reuse of the prefabricated block, and simplify construction process.

Benefits of technology

It achieves simple construction and easy use, avoids cutting thrust stops, shortens the construction period, reduces costs and labor intensity of workers, and protects the original anti-corrosion structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110644351B_ABST
    Figure CN110644351B_ABST
Patent Text Reader

Abstract

The invention discloses an assembled combined stopper for a cable-stayed bridge and a method for using the same. The assembly includes a steel beam, a support is provided at the lower end of the steel beam, a support pad stone is movably provided at the lower end of the support, fixed stops are respectively provided on the steel beams on both sides of the support, notches are provided at the lower ends of the fixed stops on both sides relative to the inner side, assembled stops are movably provided on the notches, and a post-casting strip is provided between the assembled stops and the support pad stone. The invention has the advantages of simple construction, convenient use, avoiding cutting of thrust stops, meeting construction requirements, shortening construction period, and reducing costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a cable-stayed bridge consolidation stopper, in particular to an assembled combined stopper for a cable-stayed bridge and a use method thereof. Background Art

[0002] A cable-stayed bridge, also known as a cable-tensioned bridge, is a type of bridge in which the main beam is directly pulled onto the bridge tower by many cables. It is a structural system composed of pressure-bearing towers, tensioned cables and bending-bearing beams.

[0003] At present, thrust blocks are respectively provided on both sides of the lower end support of the main beam of the cable-stayed bridge, and the cable-stayed bridge and the thrust blocks are a whole piece. In the steel structure factory, the thrust blocks are welded to the steel beam (main beam) into a whole. During the installation process, the lower end support of the main beam of the cable-stayed bridge is placed on the cast support pad stone, and a 40-60 cm post-cast strip is left between the support pad stone and the thrust blocks on both sides of the lower end of the steel beam. After the lower end support of the steel beam is placed on the support pad stone, the post-cast strips on both sides of the support pad stone are cast with reinforced cement to fix the thrust blocks on both sides of the steel beam to the support pad stone to prevent the cable-stayed bridge from moving during installation or rotation. When the entire bridge is closed, some thrust blocks close to both sides of the post-cast strip must be manually cut off, and the cut portion must be larger than the sliding distance of the steel beam support to complete the conversion of the bridge structure system. In the above process, the construction is complicated, and when the thrust stop is manually cut off, the original anti-corrosion structure of the thrust stop will be destroyed. At the same time, most of the existing oxygen cutting will heat the cutting part and the surrounding area, which will affect the thrust stop and the steel beam structure. At the same time, the cutting process is high in risk factor, and it is very complicated to grind and anti-corrosion the cut part after cutting. Summary of the invention

[0004] The purpose of the present invention is to provide a cable-stayed bridge assembled combined stopper and a method for using the same. The present invention has the characteristics of simple construction, convenient use, avoiding cutting of the thrust stopper, meeting construction requirements, shortening construction period and reducing costs.

[0005] The technical solution of the present invention is: an assembled combined stopper for a cable-stayed bridge, comprising a steel beam, a support is provided at the lower end of the steel beam, a support pad stone is movably provided at the lower end of the support, fixed stops are respectively provided on the steel beams on both sides of the support, grooves are provided at the lower ends of the fixed stops on the inner sides of both sides, assembled stops are movably provided on the grooves, and a post-cast strip is provided between the assembled stopper and the support pad stone.

[0006] In the aforementioned assembled combined stopper of the cable-stayed bridge, the assembled stopper is connected to the notch of the fixed stopper by bolts.

[0007] In the aforementioned assembled combined block for the cable-stayed bridge, the assembled block is 3-10 cm higher than the post-cast zone.

[0008] In the aforementioned assembled combined stopper of the cable-stayed bridge, the upper end of the assembled stopper (4) is shorter than the lower end in the longitudinal direction of the bridge, and the angle between the side of the assembled stopper (4) away from the post-cast strip (5) and the vertical direction is 2 to 4 o .

[0009] In the aforementioned assembled combined stopper of the cable-stayed bridge, the fixed stopper is connected to the lower end of the steel beam by welding.

[0010] The method for using the aforementioned assembled combined stopper for a cable-stayed bridge comprises the following steps:

[0011] A. Weld the fixed blocks to both sides of the lower support of the steel beam, connect the assembled blocks to the notches of the fixed blocks with bolts, and then transport the steel beam to the construction site;

[0012] B. Install the support at the lower end of the steel beam on the support pad stone, pour reinforced concrete in the post-casting strip between the assembled block and the support pad stone, and continue to install other components;

[0013] C. When the entire bridge is closed, remove the bolts of the fixed block and the assembled block, move the assembled block on the slot downward, separate the assembled block and take it out.

[0014] In the aforementioned method for using the assembled combined stopper of a cable-stayed bridge, in the step B, after pouring reinforced concrete in the post-casting strip between the assembled stopper and the support pad stone for 8-15 days, other components are installed.

[0015] In the aforementioned method of using the assembled combined block of the cable-stayed bridge, in step C, after the entire bridge is closed, the bolts of the fixed block and the assembled block are removed, the assembled block is knocked downward to move the assembled block on the slot downward, the assembled block is separated and taken out, and the bridge structure system conversion is completed.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] 1. The present invention comprises the following steps: A. in a steel structure factory, a fixed stopper is welded to both sides of a support at the lower end of a steel beam, and an assembled stopper is connected to a notch of the fixed stopper by bolts, and then the steel beam is transported to a construction site; B. the support at the lower end of the steel beam is installed on a support pad stone, and reinforced concrete is poured in a post-casting strip between the assembled stopper and the support pad stone. When the post-casting strip solidifies, the cable-stayed bridge is installed. During the installation of the cable-stayed bridge, the assembled stops on both sides of the steel beam and the fixed stops are fixed to the support pad stone by pouring reinforced concrete in the post-casting strip on both sides of the support pad stone, so as to prevent the cable-stayed bridge from moving during the installation or rotation process; C. when the entire After the bridge is closed, the bolts of the fixed block and the assembled block are removed, the assembled block is knocked downward to move the assembled block on the notch downward, the assembled block is separated and taken out, and the taken out assembled block can be reused. The notches on both sides of the post-cast strip are used to ensure the sliding distance of the steel beam support to complete the conversion of the bridge structure system. The present invention avoids the technical defects of the prior art that when the entire bridge is closed, the thrust blocks close to both sides of the post-cast strip are manually cut off, and the cut off portion must be larger than the sliding distance of the steel beam support to complete the conversion of the bridge structure system. The invention realizes simple construction and convenient use, avoids cutting of the thrust blocks, and can meet the construction requirements.

[0018] 2. Since the present invention does not use manual cutting to remove the thrust block, it will not damage the original anti-corrosion structure, will not affect the block and steel beam structure, and does not require grinding, anti-corrosion and other treatments on the cut part. While shortening the construction period, it also greatly reduces the cost and labor intensity of workers.

[0019] In summary, the present invention has the beneficial effects of simple construction, convenient use, avoiding cutting of the thrust block, meeting construction requirements, shortening construction period and reducing costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the structure of the present invention;

[0021] Figure 2 It is a partial schematic diagram of the present invention;

[0022] Figure 3 This is a schematic diagram of the working state of the assembled stopper (4) of the present invention after it is removed;

[0023] Figure 4 It is a schematic structural diagram of the assembled stopper (4) of the present invention.

[0024] The markings in the attached drawings are: 1-steel beam, 2-fixed block, 3-bolt, 4-assembled block, 5-post-cast strip, 6-support, 7-support pad stone, 8-slot. DETAILED DESCRIPTION

[0025] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

[0026] Embodiment. A cable-stayed bridge assembled combined stopper, comprising: Figure 1-4 As shown, it includes a steel beam 1, a support 6 is provided at the lower end of the steel beam 1, a support pad stone 7 is movably provided at the lower end of the support 6, fixed blocks 2 are respectively provided on the steel beam 1 on both sides of the support 6, and grooves 8 are provided at the lower ends of the fixed blocks 2 on both sides relative to the inner side, and assembled blocks 4 are movably provided on the grooves 8, and a post-cast strip 5 is provided between the assembled block 4 and the support pad stone 7; the post-cast strip 5 is flush with the support pad stone 7.

[0027] The assembled stopper 4 is connected to the notch 8 of the fixed stopper 2 by means of bolts 3, so as to facilitate the installation and separation of the assembled stopper 4.

[0028] The assembled stopper 4 is 3-10 cm higher than the post-cast strip 5. When the entire bridge is closed, the assembled stopper 4 is separated and taken out to avoid contact between the assembled stopper 4 and the post-cast strip 5. The sliding distance of the steel beam support is ensured by the notches 8 on both sides of the post-cast strip 5.

[0029] The upper end of the assembled stopper (4) is shorter in the longitudinal direction than the lower end, and the angle between the side of the assembled stopper (4) away from the post-cast strip (5) and the vertical direction is 2 to 4. o Under the effect that the upper end of the assembled stopper 4 is shorter than the lower end, it is easy for the assembled stopper 4 on the notch 8 to move downward, so that the assembled stopper 4 can be separated and removed simply and conveniently.

[0030] The fixed stopper 2 is connected to the lower end of the steel beam 1 by welding.

[0031] The method for using the assembled combined stopper of a cable-stayed bridge comprises the following steps:

[0032] A. In the steel structure factory, the fixed stopper 2 is welded to both sides of the lower end support 6 of the steel beam 1, and the assembled stopper 4 is connected to the notch 8 of the fixed stopper 2 by bolts 3, and then the steel beam 1 is transported to the construction site;

[0033] B. Install the support 6 at the lower end of the steel beam 1 on the support pad stone 7, pour reinforced concrete in the post-casting strip 5 between the assembled stopper 4 and the support pad stone 7 for 8-15 days, and then continue to install other components;

[0034] C. After the entire bridge is closed, remove the bolts 3 of the fixed stopper 2 and the assembled stopper 4, knock the assembled stopper 4 downward to move the assembled stopper 4 on the notch 8 downward, separate and take out the assembled stopper 4, ensure the sliding distance of the steel beam support through the notch 8 on both sides of the post-cast strip 5, and complete the conversion of the bridge structure system.

Claims

1. An assembled combined stopper for a cable-stayed bridge, characterized in that: The invention comprises a steel beam (1), a support (6) is provided at the lower end of the steel beam (1), a support cushion stone (7) is movably provided at the lower end of the support (6), fixed blocks (2) are respectively provided on the steel beam (1) on both sides of the support (6), the lower ends of the fixed blocks (2) on both sides relative to the inner side are provided with notches (8), an assembled block (4) is movably provided on the notches (8), and a post-cast strip (5) is provided between the assembled block (4) and the support cushion stone (7); the assembled block (4) is connected to the notch (8) of the fixed block (2) by bolts (3); the assembled block (4) is 3-10 cm higher than the post-cast strip (5); the upper end of the assembled block (4) is shorter than the lower end in the longitudinal direction of the bridge, and the angle between the side of the assembled block (4) away from the post-cast strip (5) and the vertical direction is 2-4 o The fixed stopper (2) is connected to the lower end of the steel beam (1) by welding.

2. A method for using the assembled combined stopper of a cable-stayed bridge according to claim 1, characterized in that: The following steps are involved: A. Weld the fixed block (2) to both sides of the lower end support (6) of the steel beam (1), connect the assembled block (4) to the notch (8) of the fixed block (2) by bolts (3), and then transport the steel beam (1) to the construction site; B. Install the support (6) at the lower end of the steel beam (1) on the support pad stone (7), pour reinforced concrete in the post-casting strip (5) between the assembled stopper (4) and the support pad stone (7), and continue to install other components; C. After the entire bridge is closed, remove the bolts (3) of the fixed stopper (2) and the assembled stopper (4), move the assembled stopper (4) on the notch (8) downward, separate the assembled stopper (4), and remove it.

3. The method for using the assembled combined stopper of a cable-stayed bridge according to claim 2 is characterized in that: In the step B, after pouring reinforced concrete in the post-casting strip (5) between the assembled stopper (4) and the support pad stone (7) for 8-15 days, other components are installed.

4. The method for using the assembled combined stopper of a cable-stayed bridge according to claim 3 is characterized in that: In step C, after the entire bridge is closed, the bolts (3) between the fixed stopper (2) and the assembled stopper (4) are removed, and the assembled stopper (4) is knocked downward to move the assembled stopper (4) on the notch (8) downward, and the assembled stopper (4) is separated and removed.