A composite anchoring structure for explosion-proofing of foundation pit or slope
By setting up an array of inclined grouting holes in the foundation pit or slope and covering it with a polyurea elastomer layer, a three-layer explosion-proof energy-absorbing structure is formed, which solves the problem of insufficient explosion resistance of the existing anchor structure and significantly improves the performance of the foundation pit. , The anti-blast performance of the slope avoids landslide accidents caused by blasting.
Patent Information
- Application Number
- CN201911108471.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-13
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2039-11-13
AI Technical Summary
The existing anchoring structures of foundation pits or slopes are weak in blast resistance, making it difficult to ensure the safety of foundation pits and slopes. Especially during blasting construction, they are prone to collapse accidents, affecting surrounding buildings and roads.
A composite anchoring structure is adopted, which includes an array of inclined grouting holes on the foundation pit wall or slope. Each grouting hole is divided into a cavity and a grouting area by a buffer baffle, with a metal anchor rod and a cement slurry inner core inside, and an outer grouting hole. Coated with a polyurea elastomer layer, it forms a three-layer explosion-proof energy-absorbing structure.
Through the combination of cavity buffering, buffer baffles and polyurea elastomer layers, this structure significantly weakens blasting vibrations, provides superior blast resistance, protects foundation pits and slopes, and ensures construction safety.
Smart Images

Figure CN110685288B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of engineering construction, and in particular relates to a composite anchoring structure for explosion prevention of foundation pits or slopes. Background Art
[0002] The foundation pit is a pit dug at the design location of the foundation according to the base elevation and the plane size of the foundation. Before excavation, the excavation plan should be determined based on geological and hydrological data and the situation of nearby buildings on site, and waterproofing and drainage should be done. If the excavation is not deep, the slope can be used to stabilize the slope, and the slope size is determined according to relevant construction regulations. For deep excavations and nearby buildings, the foundation pit wall support method and shotcrete wall protection method can be used. Large foundation pits can even use underground continuous walls and column-type bored pile interlocking methods to prevent the outer soil layer from collapsing; if there is no impact on nearby buildings, the well point method can be used to lower the groundwater level and use slope open excavation; in cold areas, natural cold air freezing method can be used for excavation, etc.
[0003] The side slope is a slope with a certain slope made on both sides of the roadbed to ensure the stability of the roadbed.
[0004] In order to prevent the pit wall or slope from collapsing, it is necessary to construct a protective structure on the pit wall or slope. Currently, the more commonly used protective structure is an anchor structure. Specifically, inclined anchor rods are set on the pit wall or slope, cement slurry is poured around the anchor rods, the ends of the anchor rods are connected to form a mesh with fine steel bars, and concrete is sprayed on the surface.
[0005] However, the above anchoring structures are relatively weak in explosion resistance. Blasting technology is often used in engineering construction. The ground vibration caused by blasting has a great impact on the safety of foundation pits and slopes, and is prone to landslide accidents. It is difficult to ensure the safety of foundation pits and slopes using conventional protective structures, and it may even affect surrounding roads and buildings. Summary of the invention
[0006] The purpose of the present invention is to provide a composite anchoring structure for explosion-proofing of foundation pits or slopes, which has good buffering, explosion-proof and energy-absorbing properties, can effectively protect foundation pits and slopes, and avoid landslides that affect surrounding buildings.
[0007] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a composite anchoring structure for explosion-proof of foundation pits or slopes, including a grouting hole array, the grouting hole array is composed of a plurality of grouting holes obliquely drilled downward on the foundation pit wall or the slope, each grouting hole is divided into a cavity and a grouting area by a buffer baffle, the cavity is located at the bottom of the grouting hole, and a metal anchor rod is also provided in the grouting area of each grouting hole, the metal anchor rod and the buffer baffle are perpendicular, and in the grouting area, a cement slurry core formed by injected cement slurry is provided from the mouth of the grouting hole to the position of the buffer baffle, the metal anchor rod is buried in the cement slurry core, the outer end of the metal anchor rod protrudes from the grouting hole, and the outer end heads of each metal anchor rod are connected by a metal tie rod to form a metal mesh, and a polyurea elastomer layer is coated on the outside of each metal anchor rod protruding from the grouting hole and the metal mesh, and the setting range of the polyurea elastomer layer is larger than the range of the grouting hole array.
[0008] The metal anchor rod is threaded steel bar.
[0009] The length of the cavity accounts for 1 / 10 of the total length of the grouting hole.
[0010] The buffer baffle is composed of a hard frame and an elastic layer coated on the surface of the hard frame, and the hard frame is fixedly connected to the metal anchor rod.
[0011] The buffer baffle is a foam board.
[0012] The inclination angle of the grouting hole is 15 to 30 degrees.
[0013] The length of the metal anchor rod extending out of the grouting hole is 10 cm.
[0014] The distance between adjacent grouting holes is 1 meter.
[0015] The beneficial effects of the present invention are as follows: the present invention is a composite structure combining a rigid structure and a three-layer explosion-proof energy-absorbing structure, which has excellent explosion-proof performance and is easy to construct. A cavity is reserved at the bottom of the grouting hole. When blasting vibration occurs, the air in the cavity can play a certain buffering role, and the buffer baffle used also has the functions of buffering and energy absorption, which can effectively weaken the energy of blasting vibration. In addition, the explosion-proof energy absorption of the polyurea elastomer layer formed by external injection forms a three-layer explosion-proof energy-absorbing structure from the outside to the inside, which greatly weakens the vibration effect of blasting on the foundation pit wall and slope. The metal anchor rods in the grouting holes and the metal mesh connecting each metal anchor rod outside the holes constitute the rigid structure of the composite anchoring structure, which cooperates with the above-mentioned three-layer explosion-proof energy-absorbing structure in a rigid and flexible manner, and together forms an effective protection for the foundation pit or slope, protecting the safety of surrounding buildings or other nearby construction sections. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the present invention;
[0017] Figure 2 It is a schematic diagram of the connection between the metal anchor rod and the metal pull rod of the present invention;
[0018] Markings in the figure: 1. Slope, 2. Grouting hole, 3. Cavity, 4. Buffer baffle, 5. Cement slurry core, 6. Metal anchor rod, 7. Polyurea elastomer layer, 8. Metal tie rod. DETAILED DESCRIPTION
[0019] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the invention in any way.
[0020] Refer to the attached Figure 1 , 2 As shown, a composite anchoring structure for explosion-proof of foundation pit or slope comprises a grouting hole array, a metal anchor rod 6 and a polyurea elastomer layer 7, wherein the grouting hole array is composed of a plurality of grouting holes 2. The construction of the grouting holes 2 is carried out according to specific construction requirements, and is generally inclined downward. A cavity 3 is reserved in the grouting hole 2. When cement slurry is poured into the grouting hole 2, it is blocked by a corresponding buffer baffle 4 so that the cement slurry cannot flow into the cavity 3. The cavity 3 is located at the bottom of the grouting hole 2. The length of the cavity 3 is preferably 1 / 10 of the total length of the grouting hole 2. The other space in the grouting hole 2 except the cavity 3 is the grouting area. The total length of the grouting hole 2 is the length of the grouting area plus the length of the cavity 3. A metal anchor rod 6 is arranged in the grouting area. The metal anchor rod 6 can be selected from threaded steel. The end of the metal anchor rod 6 located in the grouting hole 2 is the inner end of the metal anchor rod 6 The other end is the outer end of the metal anchor rod 6, and the inner end of the metal anchor rod 6 is connected to the buffer baffle 4, or is pressed against the buffer baffle 4, and the outer end of the metal anchor rod 6 extends out from the opening of the grouting hole 2. The grouting area is filled with cement slurry. After the cement slurry solidifies, a cement slurry inner core 5 is formed to fix the metal anchor rod 6 and the buffer baffle 4 in the grouting hole 2. The outer ends of the metal anchor rod 6 are connected to each other through metal tie rods 8 to form a metal mesh, and the metal anchor rods 6 in each grouting hole 2 are connected into a whole. The metal tie rod 8 is selected from steel bars with a diameter smaller than that of the metal anchor rod 6. The metal tie rod 8 and the metal anchor rod 6 can be welded or tied with wire. Polyurea is sprayed outside the formed metal mesh to form a polyurea elastomer layer 7 that wraps the metal mesh and the outer end of the metal anchor rod 6. The area of the polyurea elastomer layer 7 is larger than the area of the grouting hole array.
[0021] The buffer baffle 4 of the present invention can be made of lightweight materials or elastic materials, such as foam boards, or the buffer baffle 4 is composed of a hard frame and an elastic layer. The hard frame plays a supporting and separating role, and the elastic layer is coated on the surface of the hard frame and mainly plays a buffering and energy absorbing role. The elastic layer can be foam, rubber or sponge.
[0022] Polyurea is an elastomeric substance generated by the reaction of isocyanate components and amino compound components. The most basic properties of polyurea are corrosion resistance, water resistance and wear resistance. The present invention utilizes the anti-explosion and impact resistance of polyurea, and combines the cavity structure and the buffer baffle structure to form a three-layer explosion-proof energy absorption structure from the outside to the inside, so as to avoid landslide accidents caused by the impact vibration caused by the explosion.
[0023] The construction method of the present invention is as follows:
[0024] The first step is to drill a plurality of grouting holes 2 on the foundation pit wall or slope 1 according to the engineering requirements, the axial inclination angle of the grouting holes 2 is 15 to 30 degrees, and the spacing between adjacent grouting holes 2 is 1 meter, forming a grouting hole array;
[0025] In the second step, the threaded steel bar as the metal anchor rod 6 is inserted into the center of the cylindrical foam board, and the threaded steel bar and the foam board are inserted into the grouting hole 2 together, so that a cavity 3 is formed between the foam board and the bottom of the grouting hole 2. The length of the cavity 3 is controlled by controlling the length of the outer end of the threaded steel bar exposed from the grouting hole 2. Generally, the length of the cavity 3 is 1 / 10 of the total length of the grouting hole 2. Therefore, the length of the threaded steel bar can be selected to be the same as the length of the grouting hole 2. It is only necessary to ensure that 1 / 10 of the length of the threaded steel bar is exposed from the grouting hole 2. In this example, the length of the threaded steel bar extending out of the grouting hole is 10 cm.
[0026] The third step is to pour cement slurry into the grouting hole 2 to form a cement slurry core 5 for fixing the threaded steel bar and the surrounding soil layer;
[0027] Step 4: After the cement slurry solidifies, the threaded steel bars exposed in the grouting holes 2 are sequentially connected using steel bars to form a metal mesh, so that the threaded steel bars in the grouting hole array are connected into a whole;
[0028] The fifth step is to spray polyurea onto the formed metal mesh to form a polyurea elastomer layer 7. The spraying area should be larger than the area of the grouting hole array, and the spraying thickness should be able to wrap the metal mesh and the outer end of the threaded steel bar. After the polyurea solidifies, a composite anchoring structure with a three-layer explosion-proof energy absorption structure is formed.
Claims
1. A composite anchoring structure for explosion-proofing of foundation pits or slopes, Features: The invention comprises a grouting hole array, the grouting hole array comprises a plurality of grouting holes (2) drilled obliquely downward on a foundation pit wall or a slope (1), each grouting hole (2) is divided into a cavity (3) and a grouting area by a buffer baffle (4), the cavity (3) is located at the bottom of the grouting hole (2), and a metal anchor rod (6) is further provided in the grouting area of each grouting hole (2), the metal anchor rod (6) and the buffer baffle (4) are perpendicular to each other, and in the grouting area, from the mouth of the grouting hole (2) to the buffer baffle (4) 4) is provided with a cement slurry core (5) formed by injected cement slurry, and a metal anchor rod (6) is buried in the cement slurry core. The outer ends of the metal anchor rods (6) extend out of the grouting holes (2), and the outer ends of the metal anchor rods (6) are connected by metal tie rods (8) to form a metal mesh. A polyurea elastomer layer (7) is coated on the outside of each metal anchor rod (6) extending out of the grouting hole (2) and the metal mesh, and the setting range of the polyurea elastomer layer (7) is larger than the range of the grouting hole array.
2. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The metal anchor rod (6) is threaded steel bar.
3. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The length of the cavity (3) accounts for 1 / 10 of the total length of the grouting hole (2).
4. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The buffer baffle (4) is composed of a hard frame and an elastic layer coated on the surface of the hard frame, and the hard frame and the metal anchor rod (6) are fixedly connected.
5. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The buffer baffle (4) is a foam board.
6. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The grouting hole (2) has an inclination angle of 15 to 30 degrees.
7. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The length of the metal anchor rod (6) extending out of the grouting hole (2) is 10 cm.
8. A composite anchoring structure for explosion-proofing of foundation pit or slope according to claim 1, Features: The distance between adjacent grouting holes (2) is 1 meter.
Citation Information
Patent Citations
Panel-type framework prestressed anchor rod flexible support structure and construction method thereof
CN102330432A
Large-deformation energy-absorption anchor rod
CN105736023A
Anchor cable structure with prefabricated inner anchor head for controlling grouting for many times
CN108755677A
Compound muscle material stock lattice girder retaining structure of basalt
CN206503150U
Composite anchoring structure for foundation pit or side slope explosion prevention
CN211006703U