Grouting pipe construction device and grouting pipe construction method
By setting up a vertical slurry outlet tube in the grouting pipe construction device, the problem of grouting pipe being blocked by soil is solved, and the normal outflow of grouting liquid and successful construction is achieved.
Patent Information
- Application Number
- CN201911100504.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2039-11-12
AI Technical Summary
The existing grouting pipes are easily blocked by soil when they are penetrated into the ground, resulting in the inability to grout normally.
A grouting pipe construction device is designed, including a grouting pipe fixing structure and a pile tip structure. A slurry outlet tube perpendicular to the surface of the grouting pipe is arranged in the upper structure of the pile tip, and the slurry direction of the slurry outlet tube and the surface of the grouting pipe. Vertical, preventing mud from entering, thus preventing clogging.
Effectively prevent the grouting pipe from being blocked by soil, ensure that the grouting liquid can flow out normally, and complete the grouting work.
Smart Images

Figure CN110847178B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a grouting pipe construction device and a grouting pipe construction method. Background Art
[0002] With the development of the economy, there are more and more large-scale buildings. When constructing larger buildings, grouting pipes are usually required during the construction process. Grouting pipes can play an important role in bearing in various buildings.
[0003] In the prior art, most grouting pipes are hollow cylindrical. When the grouting pipes are driven into the ground, soil can easily enter the grouting pipes from the lower ports thereof, thereby blocking the grouting pipes and preventing normal grouting work. Summary of the invention
[0004] Based on this, it is necessary to provide a grouting pipe construction device and a grouting pipe construction method that can prevent the grouting pipe from being blocked in order to address the problems existing in the prior art.
[0005] A grouting pipe construction device, comprising: a grouting pipe fixing structure and a pile tip structure;
[0006] The grouting pipe fixing structure is used to fix the grouting pipe;
[0007] The pile tip structure comprises a pile tip upper structure connected to the grouting pipe and a pile tip lower structure connected to the pile tip upper structure. A slurry outlet pipe connected to the grouting pipe is arranged in the pile tip upper structure, and a slurry outlet direction of the slurry outlet pipe is perpendicular to the surface of the grouting pipe.
[0008] In one of the embodiments, the grouting pipe fixing structure is a cylindrical structure, and the diameter of the grouting pipe fixing structure is larger than the diameter of the grouting pipe.
[0009] In one of the embodiments, the pile tip superstructure further includes an upper end plate disposed between the grouting pipe and the grout outlet pipe.
[0010] In one of the embodiments, the pile tip superstructure further includes a partition plate disposed between each slurry outlet pipe.
[0011] In one embodiment, the number of the slurry outlet pipes is 3 or 4.
[0012] In one embodiment, the pile tip lower structure further includes: a lower end plate connected to the slurry outlet pipe, a first pile tip plate and a second pile tip plate, wherein the first pile tip plate and the second pile tip plate are perpendicular to the lower end plate.
[0013] In one embodiment, the first pile tip plate and the second pile tip plate are disposed perpendicular to each other.
[0014] In one embodiment, the first pile tip plate and the second pile tip plate are provided with cut corners.
[0015] A grouting pipe construction method, comprising:
[0016] Fixing the grouting pipe to the grouting pipe fixing structure in the above-mentioned grouting pipe construction device;
[0017] The grouting pipe fixing structure is transported to a preset pile position, and the grouting pipe fixing structure with the grouting pipe fixed thereon is vertically driven into the preset depth of the pile position in a downward direction of the pile tip structure;
[0018] The prepared slurry is injected into the grouting pipe until the grouting is completed.
[0019] In one of the embodiments, after the slurry is injected into the grouting pipe, the slurry flows out through a slurry outlet pipe connected to the grouting pipe.
[0020] The above-mentioned grouting pipe construction device and grouting pipe construction method, the grouting pipe construction device includes: a grouting pipe fixing structure and a pile tip structure; the grouting pipe fixing structure is used to fix the grouting pipe; the pile tip structure includes a pile tip upper structure connected to the grouting pipe and a pile tip lower structure connected to the pile tip upper structure, and a slurry outlet pipe connected to the grouting pipe is arranged in the pile tip upper structure, and the slurry outlet direction of the slurry outlet pipe is perpendicular to the surface of the grouting pipe. In the grouting pipe construction device, the grouting work is completed with the help of the slurry outlet pipe connected to the grouting pipe, and because the slurry outlet direction of the slurry outlet pipe is perpendicular to the surface of the grouting pipe, during the grouting pipe construction process, the slurry outlet pipe is usually driven in perpendicular to the ground, and the slurry outlet direction of the slurry outlet pipe can be considered as a horizontal direction parallel to the ground, and the soil cannot enter the slurry outlet pipe, thereby preventing the grouting pipe from being blocked. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A schematic diagram of the structure of a grouting pipe construction device in one embodiment;
[0022] Figure 2 Schematic diagram of the pile tip superstructure 210 when the number of the slurry discharge pipes 211 is 4 in one embodiment;
[0023] Figure 3 Schematic diagram of the pile tip superstructure 210 when the number of the slurry discharge pipes 211 is 3 in one embodiment;
[0024] Figure 4 is a schematic structural diagram of a pile tip lower structure 220 in one embodiment;
[0025] Figure 5It is a schematic flow chart of a grouting pipe construction method in one embodiment. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0027] In one embodiment, Figure 1 As shown, a grouting pipe construction device is provided, and the grouting pipe construction device comprises: a grouting pipe fixing structure 100 and a pile tip structure 200;
[0028] The grouting pipe fixing structure 100 is used to fix the grouting pipe, and the grouting pipe is fixed inside the grouting pipe fixing structure 100;
[0029] The pile tip structure 200 includes a pile tip upper structure 210 connected to the grouting pipe and a pile tip lower structure 220 connected to the pile tip upper structure 210. A slurry outlet pipe 211 connected to the grouting pipe is provided in the pile tip upper structure 210, and the slurry outlet direction of the slurry outlet pipe 211 is perpendicular to the surface of the grouting pipe.
[0030] The present embodiment provides a grouting pipe construction device, in which the grouting work is completed with the help of a slurry outlet pipe 211 connected to the grouting pipe, and since the slurry outlet direction of the slurry outlet pipe 211 is perpendicular to the surface of the grouting pipe, during the grouting pipe construction process, the slurry outlet pipe 211 is usually driven into the ground perpendicularly, and the slurry outlet direction of the slurry outlet pipe 211 can be considered as a horizontal direction parallel to the ground, and mud cannot enter the slurry outlet pipe 211, thereby preventing the grouting pipe from being blocked.
[0031] In one embodiment, the grouting pipe fixing structure 100 is a cylindrical structure, and the diameter of the grouting pipe fixing structure 100 is greater than the diameter of the grouting pipe. Specifically, the grouting pipe can be a PHC pile (pre-stressed high-strength concrete), which is a hollow cylindrical concrete prefabricated component. Correspondingly, the diameter of the grouting pipe fixing structure 100 can be determined according to the diameter and wall thickness of the PHC pile. For ease of operation, the material of the grouting pipe fixing structure 100 can be galvanized iron with a thickness of 1.2 mm. In addition, the number of openings of the grouting pipe fixing structure 100 is determined according to the number and diameter of the grouting pipes, and the diameter of the opening is generally 2 to 3 cm larger than the diameter of the grouting pipe.
[0032] In one embodiment, reference Figure 1The pile tip superstructure 210 also includes an upper end plate 212 disposed between the grouting pipe and the grouting pipe 211, so as to play the role of connecting, fixing, supporting and isolating.
[0033] In one embodiment, Figure 2 , which is a schematic diagram of the structure of the pile tip superstructure 210, the pile tip superstructure 210 also includes a partition plate 213 arranged between each grouting pipe 211, and the partition plate 213 is used to separate the grouting space corresponding to each grouting pipe, so as to prevent slurry blockage during the grouting process.
[0034] In one embodiment, the number of the slurry outlet pipes 211 is 3 or 4. Figure 2 , is a schematic diagram of the pile tip superstructure 210 when the number of the slurry outlet pipes 211 is 4, wherein the angle between adjacent slurry outlet pipes 211 is 90°, that is, the 4 slurry outlet pipes 211 are evenly distributed.
[0035] In one embodiment, Figure 3 , which is a schematic diagram of the pile tip superstructure 210 when the number of the slurry outlet pipes 211 is 3, wherein the angle between adjacent slurry outlet pipes 211 is 120°, that is, the three slurry outlet pipes 211 are evenly distributed.
[0036] In one embodiment, Figure 4 , which is a schematic diagram of the structure of the pile tip lower structure 220, the pile tip lower structure 220 comprises: a lower end plate 221 connected to the grouting pipe 211, a first pile tip plate 222 and a second pile tip plate 223, wherein the first pile tip plate 222 and the second pile tip plate 223 are perpendicular to the lower end plate 221. The first pile tip plate 222 and the second pile tip plate 223 are perpendicular to the horizontal plane, thereby facilitating better driving of the grouting pipe into the ground.
[0037] In one embodiment, the first pile tip plate 222 and the second pile tip plate 223 are disposed perpendicular to each other.
[0038] In one embodiment, reference Figure 1 The first pile tip plate 222 and the second pile tip plate 223 are provided with cut corners. The cut corners may be in the shape of cutting off a triangle from the top of the pile tip plate, or trimming the top into a circle, so as to help better drive the grouting pipe into the ground.
[0039] In one embodiment, Figure 5 As shown, a grouting pipe construction method is provided, the method comprising the following steps:
[0040] Step S100, fixing the grouting pipe to the grouting pipe fixing structure 100 in the grouting pipe construction device of the present application;
[0041] Step S200, transporting the grouting pipe fixing structure 100 to a preset pile position, and vertically driving the grouting pipe fixing structure 100 with the grouting pipe fixed thereon into the preset depth of the pile position according to the downward direction of the pile tip structure 200;
[0042] Step S300, injecting the prepared slurry into the grouting pipe until the grouting is completed.
[0043] The present embodiment provides a grouting pipe construction method. During the grouting pipe construction process, the grouting work is completed with the help of a slurry outlet pipe 211 connected to the grouting pipe. Moreover, since the slurry outlet direction of the slurry outlet pipe 211 is perpendicular to the surface of the grouting pipe, during the grouting pipe construction process, the slurry outlet pipe 211 is usually driven into the ground perpendicularly. The slurry outlet direction of the slurry outlet pipe 211 can be considered as a horizontal direction parallel to the ground, and mud cannot enter the slurry outlet pipe 211, thereby preventing the grouting pipe from being blocked.
[0044] In addition, after the slurry is injected into the grouting pipe, the slurry flows out through the slurry outlet pipe 211 connected to the grouting pipe. Since the grouting pipe will not be blocked by soil, the grouting work can be better completed.
[0045] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0046] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A grouting pipe construction device, It is characterized in that include: Grouting pipe fixing structure and pile tip structure; The grouting pipe fixing structure is used to fix the grouting pipe; The pile tip structure comprises a pile tip upper structure connected to the grouting pipe and a pile tip lower structure connected to the pile tip upper structure, a slurry outlet pipe connected to the grouting pipe is arranged in the pile tip upper structure, and a slurry outlet direction of the slurry outlet pipe is perpendicular to the surface of the grouting pipe; The pile tip upper structure also includes a partition plate arranged between each grouting pipe, the partition plate is used to separate the grouting space corresponding to each grouting pipe to prevent slurry blockage during the grouting process, and a reserved space is set between the center of the partition plate and the inlet of the grouting pipe; The pile tip superstructure also includes an upper end plate disposed between the grouting pipe and the grout outlet pipe; The pile tip lower structure further includes: a lower end plate connected to the slurry outlet pipe, a first pile tip plate and a second pile tip plate, wherein the first pile tip plate and the second pile tip plate are perpendicular to the lower end plate.
2. The grouting pipe construction device according to claim 1, It is characterized in that The grouting pipe fixing structure is a cylindrical structure, and the diameter of the grouting pipe fixing structure is larger than the diameter of the grouting pipe.
3. The grouting pipe construction device according to claim 1, It is characterized in that The number of the slurry outlet pipes is 3 or 4.
4. The grouting pipe construction device according to claim 1, It is characterized in that The first pile tip plate and the second pile tip plate are arranged perpendicular to each other.
5. The grouting pipe construction device according to claim 1, It is characterized in that The first pile tip plate and the second pile tip plate are provided with cut corners.
6. A grouting pipe construction method, It is characterized in that include: Fixing the grouting pipe to the grouting pipe fixing structure in the grouting pipe construction device according to any one of claims 1 to 5; The grouting pipe fixing structure is transported to a preset pile position, and the grouting pipe fixing structure with the grouting pipe fixed thereon is vertically driven into the preset depth of the pile position in a downward direction of the pile tip structure; The prepared slurry is injected into the grouting pipe until the grouting is completed.
7. The grouting pipe construction method according to claim 6, It is characterized in that After the slurry is injected into the grouting pipe, the slurry flows out through a slurry outlet pipe connected to the grouting pipe.