A debugging method for passive containment heat removal system

By formulating a debugging method for the passive containment heat extraction system, including test items, methods, content and logic, the problem of lack of debugging methods in the existing technology is solved, ensuring that the system operates effectively under accident conditions and achieving system safety. and reliability.

CN110931141BActive Publication Date: 2024-10-22CHINA NUCLEAR POWER ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911106718.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-11-13
Publication Date
2024-10-22
Estimated Expiration
2039-11-13

AI Technical Summary

Technical Problem

The existing technology lacks debugging methods and technical requirements for passive containment heat extraction systems, resulting in the inability of the system to effectively verify its functions and performance when a beyond-design basis accident occurs, and unable to ensure that the system functions under accident conditions.

Method used

The debugging method of the passive containment heat extraction system was formulated, including formulating system debugging test items, test methods, test content and debugging logic. Through the analysis of system function composition and component composition, combined with nuclear power site conditions, diversified test methods and Technical indicators to ensure that the system operates effectively under accident conditions.

Benefits of technology

Through comprehensive debugging of the system, it is ensured that the passive containment heat extraction system can effectively play its inherent role in the event of an accident beyond the design basis, limit the consequences of the accident, and ensure the safety and reliability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110931141B_ABST
    Figure CN110931141B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for debugging a passive containment heat removal system. The method formulates system debugging test items according to the functional composition and component composition of the passive containment heat removal system; formulates system debugging test methods in combination with the prerequisites for test execution and the external conditions that can be created at the nuclear power site; formulates system debugging test contents according to the functions designed for the passive containment heat removal system, the methods for realizing the functions, and the important indicators and parameters that characterize the functions; formulates the logic of the system debugging test according to the solid-state physical connection of the components of the passive containment heat removal system and the envelope relationship between the functions constituted by the components. The present invention can comprehensively and efficiently verify the functions of the passive containment heat removal system and its compliance with the system design objectives, and provide a strong guarantee for ensuring that the passive containment heat removal system fully plays its inherent role when an over-design basis accident or a severe accident occurs in a nuclear power plant.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of nuclear power plant commissioning, and in particular relates to a commissioning method for a passive containment heat removal system. Background Art

[0002] The commissioning of a nuclear power plant refers to all activities that will be performed to put structures, systems and components into a certain operating mode after the installation work is basically completed, so as to fully verify the design, equipment manufacturing, construction and installation quality of the nuclear power plant and ensure that the nuclear power plant can operate continuously and stably at rated power. The whole process is mainly divided into two parts: non-nuclear test and nuclear test. Commissioning is both the last step in the construction phase of a nuclear power plant and the first step in the operation phase. The comprehensiveness, safety and effectiveness of the commissioning test are crucial to the safe and reliable operation of the nuclear power plant.

[0003] After the Fukushima nuclear accident in Japan, according to the adjustment of my country's nuclear energy policy and the development trend of international advanced nuclear energy, newly built nuclear power plants in China will adopt advanced pressurized water reactor nuclear power technology with higher safety and stronger accident resistance. Advanced pressurized water reactor nuclear power plants first improve the overall safety of nuclear power plants from a design perspective, introducing new concept designs and items with new design features, among which the more typical new items are passive containment heat removal systems. The passive containment heat removal system is used for long-term heat removal of the containment under the beyond-design basis accident conditions of the nuclear power plant, including accidents related to power outages in the entire plant and failures of the spray system. When an beyond-design basis accident (including a severe accident) occurs in the power plant, the pressure and temperature in the containment are reduced to an acceptable level to maintain the integrity of the containment.

[0004] As a process system with a new concept design in an advanced pressurized water reactor nuclear power plant, all functions of the passive containment heat removal system need to be debugged before it is officially put into operation. By analyzing and designing complete test items and test contents, reasonable test methods and execution logic, and accurate and easy-to-obtain and judge acceptance criteria, the design, manufacture and installation of the entire system are fully tested to meet the design requirements and system performance standards, thereby ensuring that the entire system plays its inherent role in effectively limiting the consequences of accidents when beyond-design basis accidents and severe accidents occur in nuclear power plants. However, in the design manual and related literature of this system, there is no specific description of the overall system debugging test plan and requirements, nor is there any description of the debugging technical requirements; and for a passive system with a completely new design like this, there is no debugging experience to adopt and learn from. Summary of the invention

[0005] The purpose of the present invention is to provide a debugging method for a passive containment heat removal system based on the design characteristics of the passive containment heat removal system, so as to comprehensively and efficiently verify the functions of the system and its compliance with the system design objectives, and provide a strong guarantee for ensuring that the passive containment heat removal system fully plays its inherent role when beyond-design basis accidents and severe accidents occur in nuclear power plants.

[0006] The technical solution of the present invention is as follows: A method for debugging a passive containment heat removal system, comprising:

[0007] (1) Formulate system commissioning test items based on the functional composition and component composition of the passive containment heat removal system;

[0008] (2) Formulate the system commissioning test method in combination with the prerequisites for test execution and the external conditions that can be created at the nuclear power site;

[0009] (3) Formulate the system commissioning test contents according to the functions of the passive containment heat removal system design, the methods of realizing the functions and the important indicators and parameters characterizing the functions;

[0010] (4) The logic of the system debugging test is formulated according to the solid-state physical connection of the components of the passive containment heat removal system and the envelope relationship between the functions constituted by each component.

[0011] Furthermore, in the above-mentioned method for debugging the passive containment heat removal system, the debugging test items described in step (1) include: internal flushing and cleaning of the system pipeline, instrument control system debugging, valve debugging, heat exchange water tank debugging, recirculation loop debugging and system performance debugging.

[0012] Furthermore, in the above-mentioned method for debugging the passive containment heat removal system, the debugging test method formulated in step (2) includes: internal flushing and cleaning of the system pipeline, instrument control system debugging, valve debugging, heat exchange water tank debugging, and recirculation loop debugging are debugged by nuclear power field testing; system performance debugging should adopt bench testing or laboratory testing, and at the same time, multiple parallel methods of theoretical calculation and reasoning are carried out for debugging.

[0013] Further, in the above-mentioned passive containment heat removal system debugging method, the debugging test content described in step (3) includes:

[0014] Flushing and cleaning of circulation loops, water tanks and internal heat exchanger pipes;

[0015] On-site debugging of instrument, analog control channel and logic control channel performance;

[0016] On-site commissioning of valve limit switches, valve stem travel, valve operating time and other performances;

[0017] On-site commissioning of water filling and drainage performance of heat exchanger tank;

[0018] On-site debugging of the liquid level alarm performance of the water exchange tank;

[0019] On-site commissioning of the performance of the electric pump in the recirculation loop;

[0020] On-site commissioning of the recirculation loop electric heater performance;

[0021] On-site commissioning of chemical addition performance of recirculation loop;

[0022] Bench test and calculation of heat transfer performance of heat exchanger.

[0023] Furthermore, in the above-mentioned non-active containment heat removal system debugging method, the debugging test logic formulated in step (4) is as follows: first, the entire component and the inside of the system pipeline are rinsed and cleaned with desalted water; then the performance of individual instruments, control channels, and valves are debugged; then the performance of the heat exchanger tank is debugged; finally, the performance of the recirculation loop is debugged; before or during the execution of the above-mentioned debugging work, the bench test and calculation of the heat exchange performance of the heat exchanger are independently carried out.

[0024] The beneficial effects of the present invention are as follows:

[0025] The debugging method provided by the present invention requires that the functional composition and component composition of the passive containment heat removal system be analyzed in step (1). The purpose is to interpret the passive containment heat removal system from the two aspects of the safety and non-safety functions, components and equipment composition of the system, so as to set up the debugging work from the two perspectives of the system functional composition and the system component composition. On the one hand, this scheme can ensure the integrity of the system debugging project setting to ensure that all functions and components of the system can be effectively verified, and on the other hand, it can lay the foundation for setting up a reasonable test method for each test.

[0026] Step (2) of the debugging method should first sort out the prerequisites for the execution of each debugging test. These prerequisites mainly include the working conditions of the nuclear reactor required for the execution of the test (such as the temperature and pressure state of the reactor), the operating status of the upstream and downstream related systems, the availability of personnel and equipment required for the test, the accessibility of the test space and site, the effectiveness of safety protection measures, the reliability of the supply of water, power, gas, heat and cold sources required for the test, and the feasibility of the external conditions required for the test (such as ambient temperature conditions, air pressure conditions, and air flow conditions). When the analysis shows that the external conditions available at the nuclear power site can meet all the prerequisites required for the test, the test should be debugged at the nuclear power site; otherwise, it should be debugged through bench tests or laboratory tests, and multiple methods of theoretical calculation and reasoning. The purpose of adopting a variety of test methods is to ensure the absolute safety of personnel and equipment during the debugging period, that is, to effectively control the test risks and fully verify the performance of the system.

[0027] The debugging method step (3) mainly adopts effective technical solutions to perform tests for different functions performed by the system, and can judge whether the test results meet the design requirements through easy-to-read technical indicator parameters. Effective methods mainly refer to: pipeline air purging and cleaning, deoxygenated and demineralized water flushing and cleaning, verification of the control ability and response of the system through simulated or real signal input, water replenishment and drainage capacity of the heat exchanger tank, liquid level alarm logic of the heat exchanger tank, main performance parameters of the recirculation electric pump, performance parameters of the electric heater, chemical addition capacity, and heat exchange efficiency of the heat exchanger. Easy-to-read indicator parameters mainly refer to: foreign matter and impurity content of the product of air purging or deoxygenated and demineralized water flushing, correctness and response time of simulated or real signal control logic, valve travel distance and running time, water replenishment, drainage rate and water storage capacity of the heat exchanger tank, accuracy of liquid level alarm setting value and timeliness of alarm triggering, electrical parameters, vibration value, temperature value and flow value of the electric pump, electrical parameters and heating efficiency of the electric heater, chemical addition rate and pipeline flowability, and heat exchange factor of the heat exchanger.

[0028] The debugging method step (4) simultaneously considers the solid physical connection of the components in the system and the envelope relationship between the functions. First, the entire system is cleaned to ensure that there are no foreign objects or impurities in the system; then the solid physical connection of the independent components in each function is debugged (according to the direction of water flow, air flow and process flow); then each independent sub-function is isolated for targeted debugging; finally, the independent sub-functions are connected to perform overall performance debugging. During or before the above debugging work, bench tests and calculations of the heat exchanger performance can be performed in parallel, thereby optimizing the debugging period of the entire system. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1A flow chart of a method for debugging a passive containment heat removal system provided by the present invention. DETAILED DESCRIPTION

[0030] The present invention is described in detail below with reference to the accompanying drawings and embodiments.

[0031] During the construction of a nuclear power plant, the purpose of commissioning is to operate the structures, components and systems of the nuclear power plant and verify that their performance meets the design requirements and performance standards. All systems and functions of the nuclear power plant must complete the commissioning test and the test results must meet the design criteria before they can be put into operation. The passive containment heat removal system is a passive system with a new concept design in an advanced pressurized water reactor nuclear power plant. There is no description of the commissioning method in its system design manual, and there is no relevant commissioning experience to learn from and refer to.

[0032] The present invention provides a method for debugging a passive containment heat removal system. The method is based on the design characteristics of the passive containment heat removal system and considers different factors to formulate an overall debugging method of the system in sequence. That is, the system debugging test items are formulated through the system function composition and component composition; the system debugging test mode is formulated through the prerequisites for test execution and the external conditions that can be created at the nuclear power site; the debugging test content is formulated through the functions of the system design, the way to realize the functions and the important indicators and parameters that characterize them; the logic of the debugging test is formulated through the solid-state physical connection of the system components and the envelope relationship of various functions.

[0033] The specific implementation steps are as follows:

[0034] (1) Development of commissioning test items

[0035] The passive containment heat removal system adopts a passive design concept, using a heat exchanger group built into the containment to cool the containment through condensation of water vapor on the heat exchanger, convection and radiation heat exchange between the mixed gas and the heat exchanger, and continuously brings the heat inside the containment to the outside of the containment through the flow of water in the heat exchanger tube. At the same time, a heat exchange water tank is set outside the containment to realize the passive removal of heat from the containment by using the density difference caused by the temperature difference of the water. According to the functional composition and component composition of the system, the debugging test items are formulated as follows: internal cleaning of the system pipeline, control system debugging, valve debugging, heat exchange water tank debugging, recirculation loop debugging and system performance debugging.

[0036] (2) Development of debugging test methods

[0037] First, sort out the prerequisites for the execution of various commissioning tests, then analyze whether the external conditions that can be created at the nuclear power site can meet these prerequisites, and then formulate a practical implementation method. System pipeline internal cleaning, control system commissioning, valve commissioning, heat exchanger tank commissioning, and recirculation loop commissioning can be debugged by nuclear power site tests; system performance verification should be carried out by bench tests or laboratory tests, and multiple parallel methods of theoretical calculations and reasoning should be carried out at the same time.

[0038] (3) Debugging test content formulation

[0039] According to the functions designed by the system, the methods of realizing the functions and the important indicators and parameters characterized by the realization of the functions, the debugging test contents are formulated. Mainly including:

[0040] Flushing and cleaning of circulation loops, water tanks and internal heat exchanger pipes;

[0041] On-site debugging of instrument, analog control channel and logic control channel performance;

[0042] On-site commissioning of valve limit switches, valve stem travel, valve operating time and other performances;

[0043] On-site commissioning of water filling and drainage performance of heat exchanger tank;

[0044] On-site debugging of the liquid level alarm performance of the water exchange tank;

[0045] On-site commissioning of the performance of the electric pump in the recirculation loop;

[0046] On-site commissioning of the recirculation loop electric heater performance;

[0047] On-site commissioning of chemical addition performance of recirculation loop;

[0048] Bench test and calculation of heat transfer performance of heat exchanger.

[0049] (4) Debugging test logic formulation

[0050] According to the solid physical connection of each component in the system and the envelope relationship between the functions constituted by the components, the logical relationship of each debugging test is formulated. The execution logic is as follows:

[0051] First, flush and clean the entire component and the inside of the system pipeline with desalted water; then debug the performance of individual instruments, control channels, and valves; then debug the performance of the heat exchanger tank; and finally debug the performance of the recirculation loop. Before or during the above debugging work, the bench test and calculation of the heat exchanger performance can be carried out independently.

[0052] All the above tests must be completed before the nuclear reactor core is loaded with nuclear fuel and the test results must meet the design criteria.

[0053] Example

[0054] like Figure 1 As shown in the figure, the specific design process of the debugging method of the passive containment heat removal system includes the following steps:

[0055] (1) Development of commissioning test items

[0056] The passive containment heat removal system (PCS) is used for long-term heat removal of the containment under beyond-design basis accident conditions, including accidents related to power outages and sprinkler system failures. When an beyond-design basis accident (including severe accidents) occurs in the power plant, the containment pressure and temperature are reduced to acceptable levels to maintain the integrity of the containment. The PCS is equipped with a liquid seal measure for the external containment cooling water tank to prevent the water quality of the containment heat exchanger tank from being contaminated by the external environment. During normal operation and maintenance of the power plant, the system is equipped with a circulating water pump and dosing measures to prevent the growth of microorganisms and the degradation of water quality in the heat exchanger tank outside the containment. The heat exchanger in the system containment, the isolation valve outside the containment, and the pipeline between the two are components of the third safety barrier of the power plant. When a breach occurs in the system equipment or pipeline, the isolation valve is closed in time to prevent the leakage of radioactive materials and ensure the integrity of the third safety barrier of the power plant. The heat exchanger tank provides cooling water for the passive residual heat removal system (PRS) on the secondary side of the evaporator. When the secondary side loses power and cooling water source, it provides natural circulation cooling power and cooling water source for the secondary side of the evaporator. The condensed water on the outer surface of the heat exchanger after the accident is collected and fed into the core injection and cooling system (CIS) for use in reactor cavity water injection and cooling after the accident.

[0057] Therefore, according to the functional composition and component composition of the system, the debugging test items are formulated as follows:

[0058] Flushing and cleaning of the inside of the system pipeline;

[0059] Instrument and analog control channel test;

[0060] ·Logic control channel test;

[0061] Electric valve test;

[0062] ·Hot water tank test;

[0063] Recirculation loop start-up test (electric pump performance test, heater performance test and chemical addition performance test);

[0064] System performance debugging.

[0065] (2) Development of debugging test methods

[0066] Combined with the prerequisites for test execution and the external conditions that can be created at the nuclear power site, the system commissioning test method is formulated. The following commissioning test items are commissioned using the nuclear power site test method:

[0067] - Flushing and cleaning of the system pipeline (on-site commissioning);

[0068] -Instrument and analog control channel test (on-site debugging);

[0069] -Logic control channel test (on-site debugging);

[0070] -Electric valve test (on-site debugging);

[0071] -Hot water exchange tank test (on-site commissioning);

[0072] - Recirculation loop start-up test: electric pump performance test, heater performance test and chemical addition performance test (on-site commissioning).

[0073] System performance debugging should be carried out using bench tests or laboratory tests, while also conducting multiple parallel methods of theoretical calculations and reasoning.

[0074] (3) Debugging test content formulation

[0075] According to the functions of the passive containment heat removal system design, the way to achieve the functions and the important indicators and parameters that characterize the functions, the system commissioning test contents are formulated as follows:

[0076] Internal flushing and cleaning of circulation loops, water tanks and heat exchanger pipes (foreign matter and impurity content);

[0077] On-site debugging of instrument, analog control channel and logic control channel performance (control logic and signal response time);

[0078] On-site commissioning of valve limit switches, valve stem travel and valve operating time (valve travel distance and operating time);

[0079] On-site commissioning of water filling and drainage performance of heat exchanger tanks (rate and water storage capacity);

[0080] On-site commissioning of the liquid level alarm performance of the hot water tank (accuracy of the set value and timeliness of the alarm triggering);

[0081] On-site commissioning of the recirculation loop electric pump performance (electrical parameters, vibration values, temperature values ​​and flow values);

[0082] On-site commissioning of the recirculation loop electric heater performance (electrical parameters and heating efficiency);

[0083] On-site commissioning of chemical addition performance of recirculation loop (addition rate and pipeline flowability);

[0084] Heat exchange performance bench test of heat exchanger (heat exchange factor).

[0085] (4) Debugging test logic formulation

[0086] According to the solid physical connection of each component in the system and the envelope relationship between the functions constituted by the components, the logical relationship of each debugging test is formulated. The execution logic is as follows:

[0087] 1) Rinse and clean the entire components and system pipes with deionized water;

[0088] 2) Debug the performance of individual instruments, control channels, and valves;

[0089] 3) Debug the performance of the water exchange tank;

[0090] 4) Perform recirculation loop performance debugging.

[0091] Before or during the above commissioning work, the bench test and calculation of the heat exchanger performance can be carried out independently.

[0092] All the above tests must be completed before the nuclear reactor core is loaded with nuclear fuel and the test results must meet the design criteria.

[0093] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A method for debugging a passive containment heat removal system, wherein the passive containment heat removal system utilizes a heat exchanger group built into the containment to cool the containment through condensation of water vapor on the heat exchanger, convection and radiation heat exchange between the mixed gas and the heat exchanger, and continuously brings the heat in the containment to the outside of the containment through the flow of water in the heat exchanger tubes, and a heat exchange water tank is arranged outside the containment to utilize the density difference caused by the temperature difference of the water to realize the passive removal of the heat from the containment; The system debugging methods include: (1) According to the functional composition and component composition of the passive containment heat removal system, formulate system commissioning test items, including: internal flushing and cleaning of system pipelines, instrument control system commissioning, valve commissioning, heat exchange water tank commissioning, recirculation loop commissioning and system performance commissioning; (2) In combination with the prerequisites for test execution and the external conditions that can be created at the nuclear power site, formulate the system commissioning test method, including: internal flushing and cleaning of system pipelines, instrument control system commissioning, valve commissioning, heat exchanger tank commissioning, and recirculation loop commissioning shall be conducted by nuclear power site test; system performance commissioning shall be conducted by bench test or laboratory test, and multiple parallel methods of theoretical calculation and reasoning shall be carried out at the same time; (3) Based on the functions of the passive containment heat removal system design, the way to achieve the functions and the important indicators and parameters that characterize the system, the system commissioning test content is formulated. The important indicators and parameters include: the foreign matter and impurity content of the products of air purging or deoxygenated and demineralized water flushing, the correctness and response time of the simulation or real signal control logic, the valve travel distance and running time, the water replenishment, drainage rate and water storage capacity of the heat exchanger tank, the accuracy of the liquid level alarm setting value and the timeliness of the alarm triggering, the electrical parameters, vibration value, temperature value and flow value of the electric pump, the electrical parameters and heating efficiency of the electric heater, the chemical addition rate and pipeline flowability, and the heat exchange factor of the heat exchanger; the system commissioning test content includes: Flushing and cleaning of circulation loops, water tanks and internal heat exchanger pipes; On-site debugging of instrument, analog control channel and logic control channel performance; On-site commissioning of valve limit switches, valve stem travel and valve operating time performance; On-site commissioning of water filling and drainage performance of heat exchanger tank; On-site debugging of the liquid level alarm performance of the water exchange tank; On-site commissioning of the performance of the electric pump in the recirculation loop; On-site commissioning of the recirculation loop electric heater performance; On-site commissioning of chemical addition performance of recirculation loop; Bench test and calculation of heat transfer performance of heat exchanger; (4) According to the solid-state physical connection of the components of the passive containment heat removal system and combined with the envelope relationship between the functions of each component, the logic of the system commissioning test is formulated as follows: first, the entire component and the inside of the system pipeline are rinsed and cleaned with desalted water; then the performance of individual instruments, control channels, and valves are debugged; then the performance of the heat exchanger tank is debugged; finally, the performance of the recirculation loop is debugged; before or during the execution of the above-mentioned commissioning work, the bench test and calculation of the heat transfer performance of the heat exchanger are independently carried out.