Double-layer flange plate box-type concrete structure construction hanging basket and construction method thereof

By adopting the main truss system, anchoring system and walking system in the construction of cantilever box girder bridges, the fully automated progress of the hanging basket is achieved, and the problems of slow forward movement speed and poor accuracy are solved, construction efficiency is improved and safety hazards are reduced.

CN110983985BActive Publication Date: 2024-11-05NANJING FORESTRY UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911333214.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-20
Publication Date
2024-11-05
Estimated Expiration
2039-12-20

AI Technical Summary

Technical Problem

The existing hanging baskets move forward slowly, have poor accuracy, and are prone to deviation during the construction of cantilever box girder bridges, resulting in structural safety hazards and require frequent disassembly and installation, which is a large workload.

Method used

A double-layer flange box-type concrete structure construction hanging basket is designed, using main truss system, anchoring system, suspension system and walking system. The fully automated advancement of the hanging basket is achieved through assembled tracks, jacks and pull rods to reduce friction force, improve forward speed and accuracy.

Benefits of technology

The full automation and continuous progress of hanging baskets is realized, the construction efficiency is improved, the manpower and material consumption is reduced, and the safety hazards are reduced. There is no need to frequently disassemble the jack, saving construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110983985B_ABST
    Figure CN110983985B_ABST
Patent Text Reader

Abstract

A construction hanging basket for a double-layer flange plate box-type concrete structure and a construction method thereof, wherein a main truss system is fixed to a cast box girder through an anchoring system, a running system is composed of a front sliding block, a rear sliding block, an assembled track, a first jack, a second jack, a tie rod and a movable anchor block, and a formwork system is composed of a core formwork, a side formwork, a lower flange plate formwork and a bottom formwork. The continuous forward movement of the construction hanging basket for a double-layer flange plate box-type concrete structure is completed by moving the assembled track forward, installing the movable anchor block, fixing the tie rod, starting the first jack, returning the oil to reset the first jack, starting the second jack, returning the oil to reset the second jack, and alternately tensioning and pushing. The present invention designs a special construction hanging basket for a double-layer flange plate continuous box-type concrete bridge, optimizes the formwork system and the running system of the hanging basket, the assembled track construction is quick and convenient, the movable anchor block can be reused, and the jacks are alternately tensioned, so that the continuous movement of the construction hanging basket can be achieved, thereby saving construction time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of civil engineering, and relates to a temporary facility for the construction of a double-flange plate continuous box girder bridge structure and a construction method thereof, and specifically relates to a double-flange plate box-type concrete structure construction hanging basket and a construction method thereof. Background Art

[0002] Prestressed concrete continuous box girder bridge is one of the main types of bridges with a long history and wide application. In the construction process of cantilever box girder bridge, hanging basket is an indispensable construction equipment. It does not require the erection of brackets and does not use large cranes. Compared with other methods, hanging basket construction has the advantages of light structure, simple and convenient assembly, and no pressure.

[0003] With the development of economy, most of the built bridges are becoming increasingly congested, so there is a phenomenon of building wide bridges to ease the traffic pressure. In order to overcome various problems such as the difficulty of designing and constructing wide bridges, large land area and high cost, various double-deck bridges that can realize double-deck traffic have come into being. The flange plate of the traditional box girder bridge is flush with the bridge deck, while the equal-section double-deck flange plate structure bridge adds a layer of flange plate to the bottom plate of the bridge. The upper flange plate and the box girder top plate together form the motor vehicle lane, and the lower flange plate serves as a passage for non-motor vehicles and pedestrians, realizing the separation of people and vehicles, while also reducing the climbing height of pedestrians.

[0004] When the existing hanging basket is pushed forward, it is mostly controlled symmetrically by manual chain hoists. The friction force generated during the forward movement is large. For large bridges, when the forward movement distance is large, the hand chain hoists or jacks need to be constantly disassembled and installed due to the range limitation, which is labor-intensive and slow. Once a deviation occurs, it is difficult to control, which can easily lead to asynchronous displacement of the two sides of the hanging basket, causing the hanging basket to be misaligned, causing different degrees of safety hazards to the entire structure. For example, Chinese patent CN 203049470 U discloses a hanging basket walking system, which includes left and right walking tracks arranged corresponding to the left and right main longitudinal beams of the hanging basket, and each walking track is at least equipped with a hydraulic cylinder, a sliding locking device and a sliding shoe. The sliding locking device is arranged on the walking track, can walk along the walking track, and is fixed to the walking track through a connecting piece. The sliding shoe is fixedly connected to the first component on the hanging basket for bearing the driving force, and can walk along the walking track. One end of the hydraulic cylinder is connected to the sliding locking device, and the other end is connected to the sliding shoe.

[0005] Although this system solves the problem of poor manual control accuracy, the limited range of the jack cannot guarantee the continuous advancement of the basket, and fully automated forward movement has not been achieved. Summary of the invention

[0006] The present invention develops a matching formwork system for a new type of double-layer flange plate continuous box-type concrete structure bridge, which is mainly composed of a core formwork, a side formwork, a lower flange plate formwork and a bottom formwork, so that casting and forming can be realized in one time. At the same time, the problems of poor forward movement accuracy, difficult control and slow forward movement speed of the hanging basket are solved, and the traveling system of the hanging basket is improved. The assembled track is used to realize the rapid laying of the track in the forward direction of the hanging basket. The movable anchor block has strong maneuverability and is convenient to install and disassemble. The first jack and the second jack are fixed to the main truss system, and the tensioning oil pump system is used to alternately tension the pull rods anchored on the movable anchor block, so that the fully automatic advancement of the hanging basket is realized. The deviation occurring during the forward movement process can be controlled at any time by the differential speed of the jacks on both sides of the hanging basket, and the jacks do not need to be disassembled during the construction process. Each time the hanging basket moves forward, it only needs to splice the track when assembling in the forward direction of concrete pouring, and install the movable anchor block and the pull rod. The construction is quick and convenient, and a large amount of manpower and material resources are saved, and the construction period is saved.

[0007] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a double-layer flange plate box-type concrete structure construction hanging basket, including a main truss system, an anchoring system, a suspension system, a formwork system and a running system, characterized in that the main truss system is fixed to the cast box girder through the anchoring system, the running system is placed between the main truss system and the cast box girder, the running system is composed of a front sliding block, a rear sliding block, an assembled track, a first jack, a second jack, a pull rod and a movable anchor block, the front sliding block and the rear sliding block are respectively welded or anchored to the front and rear nodes on the lower side of the main truss system, and the front sliding block and the rear sliding block are respectively It is fixed to the assembled track in the vertical direction and connected by sliding or rolling in the horizontal direction. The first jack and the second jack are respectively arranged at the rear ends of the front sliding block and the rear sliding block, and are fixedly connected to the main truss system. The movable anchor block is flexibly embedded in the front end of the assembled track in the forward direction of concrete pouring. One end of the pull rod is anchored to the movable anchor block, and the other end passes through the first jack and the second jack along the longitudinal direction of the poured box girder. The formwork system is assembled by a core mold, a side mold, a lower flange plate mold and a bottom mold, all of which are suspended by a suspension system around the concrete of the box girder segment to be poured in the forward direction of box girder pouring.

[0008] The assembled track is composed of a plurality of steel sections and a plurality of transverse partitions. Each piece of assembled track is composed of two or more steel sections connected and fixed in sequence along the longitudinal front and back. A perforated steel plate is provided at the end of each section of steel section. The front and rear steel sections are connected front and back through bolts passing through the perforated steel plate to form an assembled track.

[0009] The movable anchor block is composed of an anchor block and an embedded block. The embedded block is flexibly embedded and connected to the front end of the assembled track. The anchor block is vertically connected to the embedded block. The anchor block protrudes outside the cross section of the steel section of the assembled track and anchors the pull rod.

[0010] The first jack and the second jack are located above each piece of assembled track, and are connected in series at intervals in front and back to alternately lift and tension the pull rods so that the main truss system moves continuously in the pouring direction.

[0011] The lower flange plate formwork and the bottom formwork extend outwards to the outside of the web plates on the outermost sides of the box beam.

[0012] The construction method of the double-flange plate box-type concrete structure construction hanging basket is characterized by at least comprising the following steps:

[0013] A. Move the assembled track forward: remove the assembled track at the rear and move it forward to the cast box girder in the forward moving direction of the hanging basket, and connect and fix it with the assembled track of the previous section by bolts;

[0014] B. Install the movable anchor block: embed one end of the embedded block of the movable anchor block into the end of the assembled track in the pouring forward direction;

[0015] C. Fixed tie rod: one end of the tie rod passes through the first jack, the front sliding block, the second jack and the rear sliding block in sequence, and the other end is temporarily anchored on the anchor block of the movable anchor block;

[0016] D. Start the first jack: Start the first jack in the pouring forward direction, tension the tie rod, and push the front sliding block to move the main truss system forward;

[0017] E. Oil return and reset of the first jack: When the first jack reaches the range, the oil of the first jack returns to the original position;

[0018] F. Start the second jack: Start the second jack to tension the tie rod and push the rear sliding block to make the main truss system continue to move forward;

[0019] G. The second jack returns oil to reset: When the second jack reaches the range, the second jack returns oil to return to its original position;

[0020] H. Repeat the above steps D to G, so that the main truss system continuously moves forward on the assembled track until the forward movement of the main truss system reaches a specified value;

[0021] I. Remove the movable anchor block: remove the tie rod on the anchor block of the movable anchor block, and remove the movable anchor block from the end of the assembled track;

[0022] J. The forward movement of the hanging basket is completed: the continuous forward movement of the hanging basket for the construction of the double-layer flange plate box-type concrete structure is completed;

[0023] K. Circular movement of the hanging basket: After the hanging basket moves forward to its position, the construction and maintenance of the formwork, reinforcement and concrete of the box girder segment are completed, and steps A to J are repeated to complete the next movement of the hanging basket.

[0024] The present invention optimizes the formwork system and the travel system of the hanging basket for the new double-flange plate continuous box-type concrete structure bridge, and designs a hanging basket device for cantilever casting construction of a double-flange plate structure equal-section continuous beam bridge. The hanging basket solves the problem of slow forward movement and low efficiency of the hanging basket during cantilever construction. The first jack and the second jack alternately tension the pull rod and simultaneously push the front and rear sliding blocks, thereby realizing the fully automatic continuous forward movement of the hanging basket; the front and rear sliding blocks are connected to the assembled rails in horizontal sliding or rolling, which better assists the forward movement of the hanging basket and reduces friction; the assembled rails are connected by bolts, which realizes the rapid laying of the rails in the forward direction of the hanging basket, greatly improving the construction efficiency.

[0025] The beneficial effects of the present invention are as follows:

[0026] (1) The core formwork, side formwork, lower flange plate formwork and bottom formwork are assembled into a formwork system, which realizes the cantilever casting construction of a concrete structure bridge with a continuous beam and equal cross-section and double-layer flange plate.

[0027] (2) The two assembled rails are connected by bolts, which makes installation and disassembly quick and convenient during the forward movement of the hanging basket, achieving seamless docking without the need for welding, saving manpower and material resources and reducing safety hazards.

[0028] (3) The first jack and the second jack are welded under the main truss system, and the tensioning oil pump system controls the alternating tensioning of the tension rods, thus realizing the fully automated continuous advancement of the hanging basket. The fast advancement speed saves the time of each installation and disassembly, greatly improving the construction efficiency. The deviations that occur during the forward movement can be corrected by the differential speed correction of the jacks on both sides of the hanging basket, thus reducing the hidden dangers of twisting and dislocation of the hanging basket.

[0029] (4) The movable anchor block is easy to install and disassemble, without the need for bolts or welding. It is directly fixed to the end of the assembled track through a slot, and provides an anchoring reaction force together with the assembled track. It can be reused, thereby improving economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a side view of a double-flange plate box-type concrete structure construction hanging basket;

[0031] Figure 2 This is the main view of the double-flange plate box-type concrete structure construction hanging basket;

[0032] Figure 3 It is a schematic diagram of a single assembled track of a double-layer flange plate box-type concrete structure construction hanging basket;

[0033] Figure 4 It is a schematic diagram of the tie rod anchoring of the double-layer flange plate box-type concrete structure construction hanging basket;

[0034] Figure 5It is a schematic diagram of the movable anchor block of the double-layer flange plate box-type concrete structure construction hanging basket;

[0035] Figure 6 It is a flow chart of the construction method of the double-flange plate box-type concrete structure construction hanging basket;

[0036] In all the drawings, 1 is the main truss system; 2 is the anchoring system; 3 is the suspension system; 4 is the formwork system; 41 is the core formwork; 42 is the side formwork; 43 is the lower flange plate formwork; 44 is the bottom formwork; 5 is the running system; 511 is the front sliding block; 512 is the rear sliding block; 52 is the assembled track; 521 is the steel section; 522 is the cross partition; 523 is the perforated steel plate; 531 is the first jack; 532 is the second jack; 54 is the pull rod; 55 is the movable anchor block; 551 is the anchor block; 552 is the embedded block; 6 is the cast box girder. DETAILED DESCRIPTION

[0037] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation methods of the present invention are now described with reference to the accompanying drawings. The present invention provides a double-layer flange plate box-type concrete structure construction hanging basket, including a main truss system 1, an anchoring system 2, a suspension system 3, a formwork system 4 and a running system 5, characterized in that the main truss system 1 is fixed to the cast box girder 6 by the anchoring system 2, the running system 5 is placed between the main truss system 1 and the cast box girder 6, the running system 5 is composed of a front sliding block 511, a rear sliding block 512, an assembled track 52, a first jack 531, a second jack 532, a pull rod 54 and a movable anchor block 55, the front sliding block 511 and the rear sliding block 512 are respectively welded or anchored to the front and rear nodes on the lower side of the main truss system 1, and the front sliding block 511 and the rear sliding block 512 are respectively connected to the assembled track 52 are fixed to each other in the vertical direction and connected by sliding or rolling in the horizontal direction. The first jack 531 and the second jack 532 are respectively arranged at the rear ends of the front sliding block 511 and the rear sliding block 512, and are fixedly connected to the main truss system 1. The movable anchor block 55 is flexibly embedded in the front end of the assembled track 52 in the forward direction of concrete pouring. One end of the pull rod 54 is anchored to the movable anchor block 55, and the other end is passed through the first jack 531 and the second jack 532 along the longitudinal direction of the cast box girder 6. The formwork system 4 is assembled by a core mold 41, a side mold 42, a lower flange plate mold 43 and a bottom mold 44, all of which are suspended by the suspension system 3 around the concrete of the box girder segment to be poured in the forward direction of box girder pouring.

[0038] The assembled track 52 is composed of a plurality of steel sections 521 and a plurality of cross partitions 522. Each piece of assembled track 52 is composed of two or more steel sections 521 connected and fixed in sequence along the longitudinal front and back. A perforated steel plate 523 is provided at the end of each section of steel section 521. The front and rear steel sections 521 are connected front and back by bolts passing through the perforated steel plate 523 to form the assembled track 52.

[0039] The movable anchor block 55 is composed of an anchor block 551 and an embedded block 552. The embedded block 552 is flexibly embedded and connected to the front end of the assembled track 52. The anchor block 551 is vertically connected to the embedded block 552. The anchor block 551 protrudes from the outside of the cross-section of the steel section 521 of the assembled track 52 and anchors the pull rod 54.

[0040] The first jack 531 and the second jack 532 are located above each piece of assembled track 52 , and are connected in series at intervals in front and back to alternately lift and pull the tension rods 54 to make the main truss system 1 move continuously in the pouring direction.

[0041] The lower flange plate formwork 43 and the bottom formwork 44 extend outwards to the outside of the web plates on the outermost sides of the box beam.

[0042] The construction method of the double-flange plate box-type concrete structure construction hanging basket is characterized by at least comprising the following steps:

[0043] A. Move the assembled track forward: remove the assembled track 52 at the rear and move it forward to the cast box beam 6 in the forward moving direction of the hanging basket, and connect and fix it with the assembled track 52 of the previous section by bolts;

[0044] B. Install the movable anchor block: embed one end of the embedding block 552 of the movable anchor block 55 into the end of the assembled track 52 in the pouring forward direction;

[0045] C. Fixed rod: one end of the rod 54 passes through the first jack 531, the front sliding block 511, the second jack 532 and the rear sliding block 512 in sequence, and the other end is temporarily anchored on the anchor block 551 of the movable anchor block 55;

[0046] D. Start the first jack: Start the first jack 531 in the pouring forward direction sequence, tension the tie rod 54, and push the front sliding block 511 to move the main truss system 1 forward;

[0047] E. Return oil to the first jack and reset: When the first jack 531 reaches the measuring range, the first jack 531 returns oil and returns to its original position;

[0048] F. Start the second jack: Start the second jack 532 to tension the pull rod 54 and push the rear sliding block 512 to make the main truss system 1 continue to move forward;

[0049] G. The second jack returns oil to reset: When the second jack 532 reaches the measuring range, the second jack 532 returns oil to return to the original position;

[0050] H. Repeat the above steps D to G, so that the main truss system 1 continuously moves forward on the assembled track 52, until the forward movement of the main truss system 1 reaches a specified value;

[0051] I. Remove the movable anchor block: remove the pull rod 54 on the anchor block 551 of the movable anchor block 55, and remove the movable anchor block 55 from the end of the assembled track 52;

[0052] J. The forward movement of the hanging basket is completed: the continuous forward movement of the hanging basket for the construction of the double-layer flange plate box-type concrete structure is completed;

[0053] K. Circular movement of the hanging basket: After the hanging basket moves forward to its position, the construction and maintenance of the formwork, reinforcement and concrete of the box girder segment are completed, and steps A to J are repeated to complete the next movement of the hanging basket.

Claims

1. A double-layer flange plate box-type concrete structure construction hanging basket, comprising a main truss system (1), an anchoring system (2), a suspension system (3), a formwork system (4) and a travel system (5), characterized in that: The main truss system (1) is fixed to the cast box girder (6) through the anchor system (2). The running system (5) is placed between the main truss system (1) and the cast box girder (6). The running system (5) is composed of a front sliding block (511), a rear sliding block (512), an assembled track (52), a first jack (531), a second jack (532), a pull rod (54) and a movable anchor block (55). The front sliding block (511) and the rear sliding block (512) are respectively welded or anchored to the front and rear nodes on the lower side of the main truss system (1). 1), the rear sliding block (512) is fixed to the assembled track (52) in the vertical direction and connected by sliding or rolling in the horizontal direction, the first jack (531) and the second jack (532) are respectively arranged at the rear ends of the front sliding block (511) and the rear sliding block (512), and are fixedly connected to the main truss system (1), the movable anchor block (55) is flexibly embedded in the front end of the assembled track (52) in the forward direction of concrete pouring, one end of the pull rod (54) is anchored to the movable anchor block (55), and the other end is passed through the first jack along the longitudinal direction of the poured box beam (6) The template system (4) is composed of a core template (41), a side template (42), a lower flange template (43) and a bottom template (44) assembled in the jack (531) and the second jack (532), and is suspended by a suspension system (3) around the concrete of the box girder segment to be poured in the forward direction of the box girder pouring; the assembled track (52) is composed of a plurality of steel sections (521) and a plurality of transverse partitions (522), and each piece of the assembled track (52) is connected and fixed in sequence along the longitudinal direction by more than two steel sections (521), and each section of steel section (521) is connected and fixed in sequence along the longitudinal direction. The end of the assembled track (52) is provided with a perforated steel plate (523), and the front and rear steel sections (521) are connected front and back by bolts passing through the perforated steel plate (523) to form an assembled track (52); the movable anchor block (55) is composed of an anchor block (551) and an embedded block (552), the embedded block (552) is flexibly embedded and connected to the front end of the assembled track (52), the anchor block (551) is vertically connected to the embedded block (552), the anchor block (551) protrudes from the outside of the cross section of the steel section (521) of the assembled track (52), and forms an anchor for the pull rod (54).

2. The double-flange plate box-type concrete structure construction hanging basket as claimed in claim 1, characterized in that The first jack (531) and the second jack (532) are located above each piece of assembled track (52), and are connected in series at intervals in front and back to alternately lift and pull the tension rod (54) so ​​that the main truss system (1) moves continuously in the pouring direction.

3. The double-layer flange plate box-type concrete structure construction hanging basket as claimed in claim 1, characterized in that The lower flange plate formwork (43) and the bottom formwork (44) extend outwards to the outside of the web plates on the outermost sides of the box beam.

4. The construction method of the double-flange plate box-type concrete structure construction hanging basket according to claim 1, characterized in that: At least the following steps are included: A. Moving the assembled track forward: remove the assembled track (52) at the rear and move it forward to the cast box girder (6) in the forward moving direction of the hanging basket, and connect and fix it with the assembled track (52) of the previous section by bolts; B. Installing the movable anchor block: embedding one end of the embedding block (552) of the movable anchor block (55) into the end of the assembled track (52) in the pouring forward direction; C. Fixed pull rod: one end of the pull rod (54) passes through the first jack (531), the front sliding block (511), the second jack (532) and the rear sliding block (512) in sequence, and the other end is temporarily anchored on the anchor block (551) of the movable anchor block (55); D. Start the first jack: Start the first jack (531) in the pouring forward direction sequence, tension the tie rod (54), and push the front sliding block (511) to move the main truss system (1) forward; E. Return oil to the first jack and reset: When the first jack (531) reaches the measuring range, the first jack (531) returns oil and returns to its original position; F. Start the second jack: Start the second jack (532), tension the pull rod (54), and push the rear sliding block (512) to make the main truss system (1) continue to move forward; G. Return oil to the second jack and reset: When the second jack (532) reaches the measuring range, the second jack (532) returns oil and returns to its original position; H. Repeating the above steps D to G, so that the main truss system (1) continuously moves forward on the assembled track (52), until the forward movement of the main truss system (1) reaches a specified value; I. Removing the movable anchor block: removing the pull rod (54) on the anchor block (551) of the movable anchor block (55), and removing the movable anchor block (55) from the end of the assembled track (52); J. The forward movement of the hanging basket is completed: the continuous forward movement of the hanging basket for the construction of the double-layer flange plate box-type concrete structure is completed; K. Circular movement of the hanging basket: After the hanging basket moves forward to its position, the construction and maintenance of the formwork, reinforcement and concrete of the box girder segment are completed, and steps A to J are repeated to complete the next movement of the hanging basket.