A construction method for excavation treatment structure of foundation pit retaining pile gap
By arranging retaining steel plates, steel flower tubes and anchor bars in the foundation pit, the problem of unbearable ground pressure at the openings of the retaining piles during the construction of deep foundation pits is solved, making foundation pit excavation safer and more convenient. sex.
Patent Information
- Application Number
- CN202010190941.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-18
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2040-03-18
AI Technical Summary
In the construction of urban rail transit stations, when deep foundation pit construction encounters gaps in the retaining piles caused by underground obstacles, the existing retaining structures cannot withstand the large formation pressure. Especially when the excavation depth exceeds 10m, ordinary retaining structures The earth structure and retaining piles are difficult to support safely and effectively.
The retaining steel plate, steel flower tubes and anchor bars are set up in the foundation pit for support. The anchor bars are installed by drilling holes on the pile bodies of the enclosure piles. The anchor bars are inserted and the holes are filled for anchoring. The steel plates are set up and connected with the steel flower tubes. For connection, cement slurry and double-liquid grouting are used to strengthen the soil connection to ensure that the formation pressure outside the foundation pit is supported.
It provides a convenient, safe and reliable retaining structure, which is suitable for foundation pit projects with deep depth and fast construction speed. It can effectively support the formation pressure outside the deep foundation pit and ensure the safety of foundation pit excavation.
Smart Images

Figure CN111270679B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of subway engineering, and more specifically, it is a construction method for a foundation pit retaining pile gap excavation treatment structure. The present invention also discloses a foundation pit retaining pile gap excavation treatment structure constructed by using the construction method for the foundation pit retaining pile gap excavation treatment structure. Background Art
[0002] In the process of urban rail transit station construction, in order to minimize the interference with the surrounding environment and road traffic, vertical excavation is generally used for foundation pit construction. Depending on the different strata where the project is located, various support structures such as bored piles, underground continuous walls, and construction piles are often used, which requires a comprehensive judgment based on economic, technical, construction period, and environmental conditions.
[0003] The bored cast-in-place pile support structure has the characteristics of flexible plan layout, large support rigidity and moderate investment cost. It is often used in deep foundation pit projects with low internal and external water head difference.
[0004] The construction sites of urban rail transit stations are mostly urban traffic arteries. Various underground pipelines and road traffic are complex around the projects. Before the construction process, it is necessary to relocate underground pipelines and relieve road traffic according to specific circumstances. When the external environment meets the construction conditions, the drilling and grouting of piles and earthwork operations within the enclosure can be carried out.
[0005] When the construction project is under tight schedule, it is common to relocate pipelines or relieve traffic while constructing bored piles. In the process of bored pile construction, it is necessary to adopt the skipping construction process. When encountering underground obstacles, the surrounding retaining piles will generally be constructed by skipping the location of the obstacle first, and then the retaining piles will be constructed after the obstacle is cleared.
[0006] During the construction of bored cast-in-place piles, when the retaining piles on both sides of the underground obstacle have been completed, but the underground obstacle at the planned construction site of the retaining piles cannot be removed, and the outside of the foundation pit cannot be supplemented due to surrounding restrictions, a gap will occur in the foundation pit retaining structure at the underground obstacle.
[0007] The width of the retaining pile gap is determined by the width of the proposed retaining structure occupied by the underground obstacles, such as the lack of one or two retaining piles. The depth of the retaining pile gap is consistent with the depth of the foundation pit.
[0008] When vertical excavation is carried out at the gap of retaining piles, the retaining structure at the gap needs to be considered comprehensively in combination with the geological conditions, width and depth of the gap. Generally, reinforced concrete or steel plates are used for support. This type of retaining structure is mostly suitable for foundation pits with an excavation depth of about 10m.
[0009] When the excavation depth reaches 20m, the maximum ground pressure on the retaining structure increases sharply, and the ordinary retaining structure and adjacent retaining piles at the retaining pile gaps are difficult to withstand. If reinforced concrete retaining walls are used for support, the construction period will be long. Therefore, it is necessary to develop a new retaining structure that is easy to construct. Summary of the invention
[0010] The first purpose of the present invention is to provide a construction method for the foundation pit retaining pile gap excavation treatment structure, which is convenient for construction.
[0011] The second purpose of the present invention is to provide a foundation pit retaining pile gap excavation treatment structure constructed by adopting the construction method of the foundation pit retaining pile gap excavation treatment structure; by arranging retaining steel plates, steel flower pipes and anchor bars in the foundation pit to support the stratum pressure outside the foundation pit, thereby ensuring the safety of foundation pit excavation.
[0012] In order to achieve the first object of the present invention, the technical solution of the present invention is: the construction method of the foundation pit retaining pile gap excavation treatment structure is characterized by comprising the following steps:
[0013] Step 1: Earth excavation;
[0014] Step 2: Spray anchors between piles; before installing the anchor rods, drill a hole with a depth of 410 mm and a diameter of Insert anchor bars between the retaining piles, fill the holes with anchor glue, and anchor the anchor bars firmly;
[0015] Step 3: Plant steel bars and anchor them and set up steel plates; the steel plates can be pre-processed in the ground processing plant in advance, and holes can be reserved according to the layout of steel flower pipes and anchor bars; the retaining steel plates can be assembled and welded in blocks to facilitate construction;
[0016] Before installing the anchor rod, drill a hole with a depth of 410 mm and a diameter of Insert anchor bars into the second reserved hole, fill the hole with anchor glue, and install the retaining steel plate after the anchor bars are firmly anchored;
[0017] At the gap of the retaining piles of the foundation pit, three retaining piles are extended on both sides of the gap in the plane direction, and the height direction of the gap is the same as the depth of the foundation pit. Retaining steel plates are used for retaining soil, and the retaining steel plates are reinforced and connected with the retaining piles on both sides of the gap with anchor bars;
[0018] Step 4: Drilling and grouting of steel pipes. During the construction of steel pipes, the steel pipes are driven into the soil between piles at the designed inclination angle. Grouting is first performed with cement slurry and then with double liquid slurry.
[0019] The double liquid grouting parameters are as follows:
[0020] a) Water-cement ratio of cement paste: 1:1;
[0021] b) Water glass concentration: 35 degrees Baume; modulus: 2.4;
[0022] c) Grouting pressure: 0.5-1.0MPa;
[0023] d) Grouting parameters should be determined according to actual conditions through on-site tests, and the grouting volume should be adjusted accordingly according to actual construction conditions;
[0024] Steel pipes are used between the retaining piles to strengthen the connection between the soil outside the foundation pit and the retaining steel plate;
[0025] Steel pipes and retaining steel plates are connected by steel pads, and adjacent retaining steel plates and retaining piles are connected by anchor bars.
[0026] Step 5: Fill the back of the retaining steel plate with grout and make it dense; fill the space between the retaining steel plate and the sprayed anchors between the piles with cement slurry to make the retaining structure evenly stressed.
[0027] In the above technical solution, in step 2, welding is performed using E43 type welding rods.
[0028] In order to achieve the second object of the present invention, the technical solution of the present invention is: a foundation pit retaining pile gap excavation treatment structure, characterized in that: it includes a retaining steel plate, a steel flower pipe and anchor bars;
[0029] The retaining steel plate is located in the foundation pit and above the notch;
[0030] The retaining steel plate is closely attached to the retaining piles on both sides of the notch through anchor bars;
[0031] The steel flower pipe is located between the retaining piles; the steel flower pipe is connected to the retaining steel plate;
[0032] The retaining steel plate and the inter-pile spray anchors are densely filled with cement slurry.
[0033] In the above technical solution, the retaining steel plate is made of Q235b steel;
[0034] The height of the retaining steel plate is equal to the depth of the foundation pit; the thickness is 10 mm.
[0035] In the above technical solution, the retaining steel plates are symmetrically arranged on both sides of the foundation pit with the retaining piles at the notch as the center.
[0036] In the above technical solution, the retaining steel plate is provided with reserved holes;
[0037] The reserved holes include a first reserved hole and a second reserved hole;
[0038] The steel flower pipe is installed in the first reserved hole; the anchor bar is installed in the second reserved hole.
[0039] In the above technical solution, the steel flower tube is a hot-rolled seamless steel tube with an outer diameter of 42 mm and a wall thickness of 3.5 mm;
[0040] The steel flower tube has a length of 6m, an inclination angle of 30°, a vertical spacing of 1m, and a plane spacing of 0.5D;
[0041] The front end of the steel flower pipe is in a pointed cone shape, a stiffening hoop is welded at the tail, and grouting holes are arranged on the pipe wall; the grouting holes are arranged in a plum blossom shape, with a hole diameter of 10mm and a hole spacing of 20-30cm; the length of the steel flower pipe without drilling holes at the upper and lower ends is 0.5-1.5m.
[0042] In the above technical solution, the steel flower pipe and the retaining steel plate are connected by a steel pad.
[0043] In the above technical solution, the thickness of the steel plate is greater than or equal to 10 mm;
[0044] The center of the steel plate and the center of the steel flower tube are on the same straight line;
[0045] There are multiple steel pads.
[0046] In the above technical solution, the anchor bar is HPB400 precision rolled threaded steel bars with a diameter of 2.
[0047] The present invention has the following advantages:
[0048] (1) The present invention is applicable to retaining soil at the gap of foundation pit retaining piles. When the gap of retaining piles encounters underground obstacles and cannot be constructed, and the adjacent retaining piles have been completed, a safe and reliable retaining structure is required before the foundation pit can be excavated. The present invention is particularly applicable to foundation pit projects with deep excavation depth and fast construction speed requirements.
[0049] (2) The present invention can be applied to soil between piles with certain self-stability or strata with small water seepage. When the strata outside the foundation pit have poor self-stability or large water seepage, high-pressure jet grouting piles or mixing piles should be added outside the foundation pit to form reinforced soil and water-stopping curtain. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] Figure 1 It is a plan view of the connection between the steel plate and the steel flower pipe at the gap of the foundation pit retaining pile of the present invention.
[0051] Figure 2 This is a vertical view of the connection between the steel plate and the steel pipe at the gap of the foundation pit retaining pile of the present invention
[0052] Figure 3 for Figure 1 A-A section view.
[0053] Figure 4 for Figure 1 BB section view.
[0054] In the figure, 1- bored pile, 2- anchor bar, 3- retaining steel plate, 4- steel flower pipe, 4.1- grouting hole, 5- reserved hole, 5.1- first reserved hole, 5.2- second reserved hole, 6- underground obstacle, 7- anchor glue, 8- nut, 9- steel pad, 10- foundation pit. DETAILED DESCRIPTION
[0055] The following is a detailed description of the implementation of the present invention in conjunction with the accompanying drawings, but they do not constitute a limitation of the present invention and are only given as examples. At the same time, the advantages of the present invention are made clearer and easier to understand through the description.
[0056] Referring to the attached drawings, it can be seen that the construction method of the foundation pit retaining pile gap excavation treatment structure comprises the following steps:
[0057] Step 1: Earth excavation;
[0058] Step 2: Spray anchors between piles; before installing the anchor rods, drill a hole with a depth of 410 mm and a diameter of Insert anchor bars between the retaining piles, fill the holes with anchor glue 7, and anchor the anchor bars firmly;
[0059] Step 3: Plant steel bars and anchor them and set up steel plates; the steel plates can be pre-processed in the ground processing plant in advance, and holes can be reserved according to the layout of steel flower pipes and anchor bars; the retaining steel plates can be assembled and welded in blocks to facilitate construction;
[0060] Before installing the anchor rod, drill a hole with a depth of 410 mm and a diameter of Insert the anchor bar 2 into the second reserved hole 5.2, fill the hole with the anchor glue 7, and install the retaining steel plate 3 after the anchor bar 2 is firmly anchored;
[0061] At the gap of the foundation pit retaining piles, three retaining piles are extended on both sides of the gap in the plane direction, and the height direction of the gap is the same as the depth of the foundation pit. The retaining steel plate 3 is used for retaining soil, and the retaining steel plate 3 is reinforced and connected with the retaining piles on both sides of the gap by anchor bars 2;
[0062] Step 4: Drilling and grouting of steel pipes; During the construction of steel pipes 4, the steel pipes 4 are driven into the soil between piles at the designed inclination angle; grouting is first performed using cement slurry, and then using double liquid slurry;
[0063] The double-liquid grouting parameters are as follows:
[0064] a) Water-cement ratio of cement paste: 1:1;
[0065] b) Water glass concentration: 35 degrees Baume; modulus: 2.4;
[0066] c) Grouting pressure: 0.5-1.0MPa;
[0067] d) Grouting parameters should be determined according to actual conditions through on-site tests, and the grouting volume should be adjusted accordingly according to actual construction conditions;
[0068] Steel pipes 4 are used between the retaining piles to strengthen the connection between the soil outside the foundation pit and the retaining steel plate 3;
[0069] The steel flower tube 4 and the retaining steel plate 3 are connected by a steel pad 9, and the adjacent retaining steel plates 3 and the retaining piles are connected by anchor bars 2;
[0070] Step 5: Grout the back of the retaining steel plate 3 to make it dense; use cement slurry to fill the space between the retaining steel plate 3 and the spray anchor between the piles to make the retaining structure evenly stressed (such as Figure 1 , Figure 2 , Figure 3 , Figure 4 shown).
[0071] Furthermore, in step 2, E43 type welding rods are used for welding, all welds are fully welded, and the weld thickness is greater than or equal to 12 mm.
[0072] The following technical requirements should be noted during excavation construction at the gaps in the retaining piles of the foundation pit: a) In order to improve the stability of the soil at the gaps in the retaining piles, it is necessary to construct steel pipes in advance and fill them densely with grouting; b) Steel plates should be constructed in a timely manner, and the construction height should not exceed 1m in each step. If sudden water or mud is found, the construction height should be adjusted in time; when excavating the backfill in the pit, the two sides should be excavated first, and then the middle part. If there is any abnormality, backfill should be done in time; c) To facilitate on-site construction operations, drainage holes should be set within the soil range between the piles to drain the pressurized water in the soil outside the foundation pit to the water collection well.
[0073] Referring to the attached drawings, it can be seen that the foundation pit retaining pile gap excavation treatment structure constructed by the construction method of the foundation pit retaining pile gap excavation treatment structure comprises a retaining steel plate 3, a steel flower pipe 4 and an anchor bar 2;
[0074] The retaining steel plate 3 is located in the foundation pit 10 and above the notch 11; the retaining steel plate 3 is used for retaining soil;
[0075] The retaining steel plate 3 is closely attached to the retaining piles on both sides of the notch through the anchor bars 2; the retaining steel plate 3 is reinforced and connected to the retaining piles on both sides of the notch by the anchor bars 2;
[0076] The steel flower pipe 4 is located between the retaining piles; the steel flower pipe 4 is connected to the retaining steel plate 3; the steel flower pipe is used between the retaining piles to strengthen the connection between the soil outside the foundation pit and the steel plate;
[0077] The retaining steel plate 3 and the sprayed anchors between the piles are filled with cement slurry to make the retaining structure evenly stressed (such as Figure 1 , Figure 2 The sprayed anchor between piles is a combination of sprayed concrete and a single-layer steel mesh.
[0078] Furthermore, the retaining steel plate 3 is made of Q235b steel;
[0079] In order to ensure the stability of the soil at the notch after the foundation pit is excavated to the designed elevation, the height of the retaining steel plate 3 is equal to the depth of the foundation pit 10; the thickness is 10 mm.
[0080] In order to evenly load the retaining piles and the retaining steel plates 3 at the notch, the retaining steel plates 3 are further symmetrically arranged on both sides of the foundation pit 10 with the retaining piles at the notch as the center.
[0081] Furthermore, the retaining steel plate 3 is provided with reserved holes 5 to facilitate the rapid installation of steel pipes and anchor bars;
[0082] The reserved holes 5 include a first reserved hole 5.1 and a second reserved hole 5.2;
[0083] The steel tube 4 is installed in the first reserved hole 5.1; the anchor bar 2 is installed in the second reserved hole 5.2 (such as Figure 3 , Figure 4 As shown), in order to quickly install the steel pipe and anchor bars.
[0084] Furthermore, the steel flower tube 4 is a hot-rolled seamless steel tube with an outer diameter of 42 mm and a wall thickness of 3.5 mm;
[0085] The steel flower tube 4 is 6m long, with an inclination of 30°, a vertical spacing of 1m, and a plane spacing of 0.5D;
[0086] The front end of the steel flower pipe 4 is in a pointed cone shape, and a (φ8) stiffening hoop is welded at the tail. Grouting holes 4.1 are arranged on the pipe wall; the grouting holes 4.1 are arranged in a plum blossom shape, with a hole diameter of 10mm and a hole spacing of 20-30cm; the length of the undrilled holes at the upper and lower ends of the steel flower pipe 4 is 0.5m, which serves as a grouting stop section.
[0087] Furthermore, the steel flower pipe 4 and the retaining steel plate 3 are connected by a steel pad 9 to increase the connection strength.
[0088] Furthermore, the thickness of the steel backing plate 9 is greater than or equal to 10 mm;
[0089] The center of the steel plate 9 is aligned with the center of the steel flower tube 4 (eg Figure 1 , Figure 2 shown).
[0090] When dealing with vertical excavation at the gap of retaining piles in the existing technology, it is necessary to comprehensively consider the retaining structure at the gap in combination with the stratum conditions, the width and depth of the gap. Generally, reinforced concrete or steel plates are used for support. This type of retaining structure is mostly suitable for foundation pits with an excavation depth of about 10m.
[0091] In order to more clearly illustrate the advantages of the construction method of the foundation pit retaining pile gap excavation treatment structure and its structure compared with the prior art, the staff compared the two technical solutions, and the comparison results are shown in the following table:
[0092]
[0093] It can be seen from the above table that the construction method and structure of the foundation pit retaining pile gap excavation treatment structure described in the present invention are convenient in construction and safe and reliable in foundation pit excavation compared with the prior art. It can be applied to strata where the soil between piles has a certain self-stability or a small amount of water seepage; it is particularly suitable for foundation pit projects with deep excavation depth and fast construction speed requirements.
[0094] Example
[0095] The present invention is now described in detail by taking its application to a station of a rail transit line project in a certain city as an example, which also has a guiding role in the application of the present invention to other subway projects.
[0096] In this embodiment, the retaining pile gap treatment structure includes retaining steel plates, steel flower pipes, anchor bars and other structures.
[0097] At the gap of the retaining piles of the foundation pit, three retaining piles are extended on both sides of the plane direction of the gap. At the gap, the height direction is the same as the depth of the foundation pit. Retaining steel plates are used for retaining soil. The retaining steel plates are reinforced with anchor bars and connected to the retaining piles on both sides of the gap. Steel flower pipes are used between the retaining piles to strengthen the connection between the soil outside the foundation pit and the steel plates. Steel pads are used to connect the steel flower pipes and retaining steel plates. Anchor bars are used to connect the adjacent steel plates and retaining piles. Cement slurry is used to fill the space between the retaining steel plates and the sprayed anchors between the piles so that the retaining structure is evenly stressed. In addition, the retaining steel plates, steel flower pipes, anchor bars and other structures are only used for retaining soil at the gap. The internal support system of the gap of the retaining piles of the foundation pit is consistent with the surrounding area.
[0098] (1) Specifications of retaining steel plates
[0099] The material specification of the retaining steel plate is Q235b, and the length in the plane direction is 0.3m+6d+0.3m (d is the diameter of the bored pile, and 0.3m is the extension length of both ends of the steel plate in the plane direction). The plane layout is symmetrically arranged on both sides with the retaining pile at the notch as the center; the height direction is the depth of the entire foundation pit; the thickness is 10mm; the retaining steel plate can be pre-processed in the ground processing plant in advance, and holes are reserved according to the layout of the steel flower pipe and anchor bar. The retaining steel plate can be assembled and welded in blocks for the convenience of construction during the construction process.
[0100] (2) Specifications of steel pipes
[0101] The steel flower pipe is a hot-rolled seamless steel pipe with an outer diameter of 42mm and a wall thickness of 3.5mm. The length is 6m, the inclination is 30°, the vertical spacing is 1m, and the plane spacing is 0.5D (D is the center spacing of the retaining piles) and D, that is, the density is 0.5D at the notch of the retaining piles. The front end of the steel pipe is in a pointed cone shape, and a φ8 stiffening hoop is welded on the tail. There are 6mm grouting holes around the pipe wall, but there is no grouting hole for 1m at the tail. When the steel flower pipe is constructed, it is driven into the soil between the piles at the designed inclination angle. Grouting first uses cement slurry, and then uses double liquid slurry (adding 5% of the weight of cement with water glass). The grouting parameters are as follows: a. Cement slurry water-cement ratio: 1:1; b. Water glass concentration: 35 degrees Baume; modulus: 2.4; c. Grouting pressure: 0.5-1.0MPa; d. Grouting parameters should be determined according to actual conditions through on-site tests, and the grouting amount should be adjusted accordingly according to the actual construction conditions.
[0102] The steel flower pipe and the steel plate are connected by steel pads. The thickness of the steel pads is not less than 10mm. The center of the steel pads is aligned with the center of the steel flower pipe. The number of supporting steel pads in the plane direction is 6, which is the same as the number of anchor bars.
[0103] (3) Anchor bar specifications
[0104] In order to improve the connection strength between the steel plate and the retaining pile, the two are reinforced with anchor bars anchored in the retaining pile. The diameter of HPB400 finely rolled threaded steel bars is 410mm. Before installing the anchor rods, drill holes with a diameter of 410mm on the pile body. Insert the anchor bars into the circular holes and fill the holes with anchor glue. After the anchor bars are firmly anchored, install the steel plates. Use E43 type welding rods for welding, all welds are fully welded, and the weld thickness is not less than 12mm.
[0105] Conclusion: The foundation pit excavation in this embodiment is safe and reliable, and the construction is convenient.
[0106] Other parts not described belong to the prior art.
Claims
1. A construction method for excavation treatment structure of foundation pit retaining piles, characterized by: It comprises a foundation pit retaining pile gap excavation treatment structure, wherein the foundation pit retaining pile gap excavation treatment structure comprises a retaining steel plate (3), a steel flower pipe (4) and anchor bars (2); The retaining steel plate (3) is located in the foundation pit (10) and above the notch (6); The retaining steel plate (3) is closely attached to the retaining piles on both sides of the notch through the anchor bars (2); The steel flower pipe (4) is located between the retaining piles; the steel flower pipe (4) is connected to the retaining steel plate (3); The retaining steel plate (3) and the inter-pile spray anchor are densely filled with cement slurry; The retaining steel plate (3) is provided with a reserved hole (5); The reserved hole (5) comprises a first reserved hole (5.1) and a second reserved hole (5.2); The steel flower tube (4) is installed in the first reserved hole (5.1); the anchor bar (2) is installed in the second reserved hole (5.2); The steel flower pipe (4) and the retaining steel plate (3) are connected by a steel pad (9); the excavation depth of the foundation pit reaches 20m; The construction method comprises the following steps: Step 1: Earth excavation; Step 2: Spray anchors between piles; before installing the anchor rods, drill a hole with a depth of 410 mm and a diameter of Insert anchor bars between the retaining piles and fill the holes with anchor glue (7) so that the anchor bars are firmly anchored; Step 3: Anchor the steel bars and install the steel plates; The steel plates can be pre-processed in advance in the ground processing plant, and holes can be reserved according to the layout of the steel pipes and anchor bars; the retaining steel plates can be assembled and welded in blocks to facilitate construction; Before installing the anchor rod, drill a hole with a depth of 410 mm and a diameter of Insert the anchor bar (2) into the second reserved hole (5.2), fill the hole with the anchor bar glue (7), and install the retaining steel plate (3) after the anchor bar (2) is firmly anchored; At the opening of the foundation pit retaining piles, three retaining piles are extended on both sides of the opening in the plane direction, and the height direction of the opening is the same as the depth of the foundation pit. A retaining steel plate (3) is used for retaining soil, and the retaining steel plate (3) is reinforced and connected with the retaining piles on both sides of the opening by anchor bars (2); Step 4: Drilling and grouting of steel pipes; During the construction of the steel pipe (4), the steel pipe is driven into the soil between the piles at a designed inclination angle; grouting is first performed using cement slurry, and then using double liquid slurry; The double-liquid grouting parameters are as follows: a) Water-cement ratio of cement paste: 1:1; b) Water glass concentration: 35 degrees Baume; Modulus: 2.4; c) Grouting pressure: 0.5-1.0MPa; d) Grouting parameters should be determined according to actual conditions through on-site tests, and the grouting volume should be adjusted accordingly according to actual construction conditions; A steel pipe (4) is used between the retaining piles to strengthen the connection between the soil outside the foundation pit and the retaining steel plate (3); The steel flower tube (4) and the retaining steel plate (3) are connected by a steel pad (9), and the adjacent retaining steel plates (3) and the retaining piles are connected by anchor bars (2); Step 5: Grouting the back of the retaining steel plate (3) to make it dense; Cement slurry is used to fill the space between the retaining steel plate (3) and the sprayed anchors between the piles to make it dense.
2. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 1 is characterized by: In step three, welding is performed using E43 type welding rod.
3. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 1 is characterized by: The retaining steel plate (3) is made of Q235b steel; The height of the retaining steel plate (3) is equal to the depth of the foundation pit (10); and the thickness is 10 mm.
4. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 3 is characterized by: The retaining steel plates (3) are symmetrically arranged on both sides of the foundation pit (10) with the retaining piles at the notch as the center.
5. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 1 is characterized by: The steel flower tube (4) is a hot-rolled seamless steel tube with an outer diameter of 42 mm and a wall thickness of 3.5 mm; The steel flower tube (4) is 6m long, with an inclination angle of 30°, a vertical spacing of 1m, and a plane spacing of 0.5D; The front end of the steel flower pipe (4) is in a pointed cone shape, a stiffening hoop is welded at the rear end, and grouting holes (4.1) are arranged on the pipe wall; the grouting holes (4.1) are arranged in a plum blossom shape, with a hole diameter of 10 mm and a hole spacing of 20-30 cm; the length of the steel flower pipe (4) without drilling holes at the upper and lower ends is 0.5 m.
6. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 1 is characterized by: The thickness of the steel backing plate (9) is greater than or equal to 10 mm; The center of the steel plate (9) and the center of the steel flower tube (4) are on the same straight line; There are multiple steel pads (9).
7. The construction method of the foundation pit retaining pile gap excavation treatment structure according to claim 6 is characterized by: The anchor bar (2) is HPB400 precision rolled threaded steel bars with a diameter of 2.