A multifunctional high-voltage cable lifting and laying guide arm and laying method thereof
By designing a multi-functional high-voltage cable lifting and laying guide arms, using hydraulic motors and telescopic arm structures, the problems of low efficiency and safety risks of manual laying of high-voltage cables are solved, and the cable mechanized guide and high-altitude operations are realized, and construction efficiency and safety are improved. .
Patent Information
- Application Number
- CN202010305432.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-17
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2040-04-17
Smart Images

Figure CN111490493B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the lifting and laying of railway high-voltage cables, urban rail transit stray cables and professional high-voltage cables for electric power, substation and contact network in the field of national power grid construction, and is a special construction equipment for mechanized laying of high-voltage cables into cable trenches using a flatbed vehicle, specifically a high-voltage cable lifting and laying guide arm. Background Art
[0002] Railway high-voltage cables, urban rail transit stray cables, and power, substation, and contact network professionals in the field of national power grid construction manually lay high-voltage cables. After the cables are laid out on the plate, they are laid into the cable trench by means of a winch and manual traction to complete the laying of high-voltage cables. In particular, the length of a single reel of high-voltage cables for high-speed railway trunk lines is more than 3,000 meters and weighs about 5,000 kg. Due to the constraints of the construction environment and terrain, 3 safety protection personnel and 10 workers are required to rotate the cable reel. Depending on the location of the cable reel, 5-8 people are required to drag the cable into the cable trench. During the cable laying process, the cable sheath is damaged, the cable bending stress is not released, and the finished product is not properly protected and construction safety risks are accompanied.
[0003] In the past, when laying high-voltage cables in railway tunnels, tunnel ventilation and lighting, and urban rail transit stray cables, ladders and ladder cars were used, which required four people to control them. Operators fixed the high-voltage cables to the wall. In response to the above working conditions and to solve the problems of aging construction workers and low construction efficiency, a multifunctional high-voltage cable lifting and laying guide arm was developed. Summary of the invention
[0004] A multifunctional high-voltage cable lifting and laying guide arm, comprising a slewing body assembly providing a slewing action, a column assembly providing a supporting action, a folding arm assembly, a multi-stage telescopic arm assembly, an auxiliary extension arm, a hanging basket assembly for operators to work at high altitudes, and a control device; the lower part of the slewing body assembly is fixed to an external movable vehicle body, and the upper end is fixed to the lower end of the column assembly; the two ends of the folding arm assembly are respectively hinged to the fixed column assembly and the multi-stage telescopic arm assembly; a folding control oil cylinder is provided between the folding arm assembly and the slewing body assembly or the column assembly; one end of the folding arm assembly is hinged to the fixed column assembly and the multi-stage telescopic arm assembly; A folding arm cylinder for operating the folding arm amplitude change or adjusting the up and down swinging angle of the guide arm is fixedly installed on the side, the telescopic end of the folding arm cylinder is fixed on the ear seat of the multi-stage telescopic arm cylinder, the built-in cylinder of the multi-stage telescopic arm assembly drives the multi-stage telescopic arm to extend and retract, and the front end of the auxiliary extension arm is fixedly connected to the end of the multi-stage telescopic arm assembly; the folding arm assembly is provided with at least one folding arm cable limiter, the multi-stage telescopic arm assembly is provided with at least one telescopic arm cable limiter, and a safety wire rope for insurance is provided between the folding arm assembly and the multi-stage telescopic arm assembly.
[0005] Furthermore, the rotating body assembly includes a hydraulic motor, a base plate, a slewing bearing, a hydraulic motor slewing disk, and a slewing body top cover; the hydraulic motor and the inner ring of the slewing bearing are respectively connected to the base plate by bolts; the spline hole of the hydraulic motor slewing disk is connected to the spline shaft of the hydraulic motor, and the hydraulic motor slewing disk and the rotating body top cover are fixedly connected to the slewing bearing by bolts.
[0006] Furthermore, the folding control cylinder is installed in reverse, that is, the telescopic end of the folding control cylinder is connected to the rotating body assembly or the column assembly, and the folding control cylinder base is installed on the folding arm assembly to increase the lifting force of the variable amplitude cylinder top.
[0007] Furthermore, the multi-stage telescopic arm assembly has multiple HSG80-1700 model cylinders built in, and the cylinders are installed in the inner cavity of each stage of the telescopic arm assembly. The cylinder barrel base is fixed in the first stage, and the telescopic end of the piston rod is fixed in the inner cavity of the second stage arm. The same applies to the remaining stages of telescopic arms (operate the first section of the cylinder to extend and retract, and the second section of the telescopic arm to extend and retract).
[0008] Furthermore, one end of the auxiliary extension arm is fixedly connected to the end of the multi-stage telescopic arm assembly through a triangular plate, and a rotatable universal cable fork is installed on the top of the other end for guiding and lifting cables, and is designed for crossing poles and pillars.
[0009] Furthermore, the hanging basket assembly is an up and down telescopic structure, the lifting ring is rectangular, and a fan-shaped hole is arranged on the upper part, which is connected to the corresponding shaft on the end of the telescopic arm. The fan-shaped hole can adapt to the vertical posture of the hanging basket. The two limit columns at the bottom are blocked under the upper cross brace of the hanging basket. A hole is opened on the cross brace according to the cross-sectional size of the lifting ring. The lifting ring is inserted into the hole, and the two limit columns are installed and locked. The lifting ring is forced to rise, and the cross brace of the hanging basket is hung on the two limit columns. Conversely, the lifting ring is lowered and retracted.
[0010] Furthermore, the structure of the folding arm cable limiter or the telescopic arm cable limiter is that the flat steel is folded into a U-shape, a hole is drilled at the bottom, and it is fixed to the folding arm or telescopic arm head with bolts. Holes are drilled above the U-shape, and the buckles at both ends of the nylon belt and the rotatable hollow shaft are placed therein. The function is to limit the exported cable and prevent the cable from popping out of the guide arm due to tension.
[0011] The beneficial effects and features of the present invention are as follows: (1) the cable reel rotates smoothly and evenly, guiding the cable on the reel into the cable trough, reducing the number of construction workers by 5 to 8 or more; (2) when there are obstacles between the flatbed truck and the cable trough, such as electric poles and contact network pillars, the cable cannot be directly guided into the trough, and the auxiliary extension arm is installed on the telescopic arm, the guide arm is lengthened to 9.6 meters, and the folding arm is lifted to the highest point. The total length of the telescopic arm is 9.6 meters, the height of the flatbed truck is 0.7 meters + the total height of the rotating body column is 2.4 meters. The top of the guide arm exceeds the height of the electric poles and contact network pillars, and the cable can be easily climbed over and dropped into the cable trough, realizing barrier-free cable laying; (3) equipped with a hanging basket assembly, it can also be used for workers to work at high altitudes, achieving the effect of one machine with multiple uses. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the overall structure of a preferred embodiment of the present invention (folded state);
[0013] Figure 2 It is a schematic diagram of the overall structure of a preferred embodiment of the present invention (expanded state);
[0014] Figure 3 yes Figure 1 Schematic diagram of the exploded structure of the rotating body assembly (the black solid arrow in the figure indicates the loading direction);
[0015] Figure 4 yes Figure 1 A schematic diagram of the structure of the column assembly;
[0016] Figure 5 yes Figure 1 Schematic diagram of the structure of the folding arm assembly;
[0017] Figure 6 yes Figure 1 A schematic diagram of the structure of a multi-stage telescopic arm assembly;
[0018] Figure 7 yes Figure 1 Structural diagram of the auxiliary extension arm;
[0019] Figure 8 yes Figure 1 A schematic diagram of the structure of the hanging basket assembly;
[0020] Fig. 9 It is a schematic diagram of track side laying in bridge and tunnel sections;
[0021] Fig.10 It is a schematic diagram of track laying across bridges and tunnels;
[0022] Fig.11 This is a schematic diagram of laying high voltage cables across the roadbed section; DETAILED DESCRIPTION
[0023] The present invention will be further described below in conjunction with the accompanying drawings:
[0024] Please refer to Figure 1-Figure 2 A multifunctional high-voltage cable lifting and laying guide arm, comprising a slewing body assembly 1 for providing a slewing action, a column assembly 2 for providing a supporting action, a folding arm assembly 3, a multi-stage telescopic arm assembly 4, an auxiliary extension arm 5, a hanging basket assembly 6 for operators to work at high altitudes, and a control device; the slewing body assembly is fixed at the lower part on an external movable vehicle body, and the upper end is fixed to the lower end of the column assembly 2; the two ends of the folding arm assembly 3 are respectively hinged to the fixed column assembly 2 and the multi-stage telescopic arm assembly 4; a folding control oil cylinder 1-1 is provided between the folding arm assembly 3 and the slewing body assembly 1 or the column assembly 2; and a folding control oil cylinder 1-1 is fixedly installed on one side of the folding arm assembly 3 for operating A folding arm cylinder 3-2 is used for folding arm amplitude change or adjusting the up and down swing angle of the guide arm. The telescopic end of the folding arm cylinder 3-2 is fixed on the ear seat of the multi-stage telescopic arm cylinder. The built-in cylinder of the multi-stage telescopic arm drives the telescopic arm to extend and retract. An adjustable cable limiter is arranged on the upper part of the multi-stage telescopic arm assembly 4. The front end of the auxiliary extension arm 5 is fixedly connected to the end of the multi-stage telescopic arm assembly 4; the folding arm assembly 3 is provided with at least one folding arm cable limiter 3-2; the multi-stage telescopic arm assembly 4 is provided with at least one telescopic arm cable limiter 4-1; a safety wire rope 4-2 is arranged between the folding arm assembly 3 and the multi-stage telescopic arm assembly 4 for insurance.
[0025] Please refer to Figure 3 The slewing body assembly 1 includes a hydraulic motor 11, a base plate 12, a slewing bearing 13, a hydraulic motor slewing disk 14, and a slewing body top cover 15; the hydraulic motor 11 and the inner ring of the slewing bearing 13 are respectively connected to the base plate 12 by bolts; the spline hole of the hydraulic motor slewing disk 14 is connected to the spline shaft of the hydraulic motor 11, and the hydraulic motor slewing disk 14 and the slewing body top cover 15 are fixedly connected to the slewing bearing 13 by bolts; by operating the hydraulic slewing motor, rotation at any position within a range of 360° and locking can be achieved.
[0026] Please refer to Figure 5 The structure of the folding arm cable limiter 3-2 or the telescopic arm cable limiter 4-1 is that the flat steel is folded into a U shape, a hole is drilled at the bottom, and it is fixed to the folding arm and the telescopic arm head with bolts. Holes are drilled above the U shape, and the buckles at both ends of the nylon belt and the hollow shaft are placed in it and fixed with nails. The function is to limit the exported cable and prevent the cable from popping out of the guide arm due to tension.
[0027] The column assembly 2 is welded with Q235 steel plate with a thickness of 24mm according to the drawing, and the bottom is welded with a cylinder ear seat. The top hinge shaft hole has a diameter of 50mm, and is connected with the corresponding hole of the folding arm by the shaft. The bolt hole with a three-side spacing of 120mm has a diameter of 18mm and is installed on the top cover of the rotating body by bolts. The height from the center of the hinge shaft hole to the top cover of the rotating body is 2.0 meters.
[0028] The folding arm assembly 3 is welded with a U-shaped section using HQ70 steel plate with a thickness of 4mm according to the drawing. The hinge holes at both ends have a diameter of 50mm and are connected to the column and the three-stage telescopic arm respectively with a shaft with a diameter of 50mm. The folding arm cylinder ear seat is welded on the side, and the jacking cylinder earring connection hole with a diameter of 50mm is drilled in the middle. The hinge is designed as a four-link structure to increase the torque. The cable guide ring fixing frame and the wire rope fixing hole are welded on the top. The cable guide ring structure is a quick-install nylon belt and a roller structure with a diameter of 60mm. The wire rope has a diameter of 14mm, and the two ends are crimped with hole terminals. The total length is 485mm. The wire rope terminals are fixed to the corresponding holes of the folding arm and telescopic arm respectively, which play a safety protection role when in working state.
[0029] The folding control cylinder 1-1 is installed in reverse, that is, the telescopic end of the folding control cylinder 1-1 is connected to the rotating body assembly 1 or the column assembly 2, and the base of the folding control cylinder 1-1 is installed on the folding arm assembly 3 to improve the lifting force of the variable amplitude cylinder top;
[0030] The multi-stage telescopic arm assembly 4 has multiple HSG80-1700 model cylinders built in, with a total extended length of 5.4 meters. The built-in cylinders are specifically installed in the inner cavity of the telescopic arm assembly, the cylinder base is fixed on the first stage, and the telescopic end of the piston rod is fixed on the inner cavity of the second-stage arm, and so on. The first section of the cylinder is operated to telescope, the second section of the telescopic arm is telescoped, and so on; the two holes on the head of the first arm are connected to the folding arm and the lifting cylinder respectively by pins, and three cable guide ring fixing frames are welded on the top of the telescopic arm; the cable guide ring structure is a quick-install nylon belt and diameter roller structure, and the telescopic arm and the folding arm make corresponding movements according to different needs.
[0031] Please refer to Figure 2 , Figure 5 , Figure 7 , Figure 8 One end of the auxiliary extension arm 5 is fixedly connected to the end of the multi-stage telescopic arm assembly 4 through a triangular plate 4-3, and a universal cable fork 5-1 is installed on the top of the other end for guiding and lifting the cable. It is designed to cross over poles and pillars. Figure 7 ;
[0032] The guide wall is equipped with a hanging basket assembly, which can also be used in situations where workers need to work at high altitudes, avoiding the need to configure additional operating equipment, and achieving a one-machine-multiple-purposes effect. The hanging basket assembly 6 is an up and down telescopic structure, the lifting ring 6-1 is rectangular, and a fan-shaped hole is arranged on the upper part, which is connected to the corresponding shaft on the end of the telescopic arm. The fan-shaped hole can adapt to the vertical posture of the hanging basket, and the two limit columns at the bottom are blocked below the upper cross brace of the hanging basket. A hole is opened on the cross brace according to the cross-sectional size of the lifting ring, and the lifting ring is inserted into this hole, and the two limit columns are installed and locked. The lifting ring is forced to rise, and the hanging basket cross brace is hung on the two limit columns. On the contrary, the lifting ring is lowered and retracted. When not in use, the bolts are loosened to drop the lifting ring; the auxiliary extension arm 5 is welded with a U-shaped section with a thickness of 4mm HQ70 steel plate, with a length of 2.2 meters. The triangular hole at one end is connected and fixed to the corresponding position shaft at the tail of the third stage of the telescopic arm, and the total length of the guide arm is extended to 9.6 meters. The hanging basket is fixed at the corresponding axis of the third-stage tail of the telescopic arm to realize high-altitude operations. The maximum load of the hanging basket is 500Kg, which meets all high-altitude operation needs of this industry.
[0033] The rotary motor of the rotary body adopts the cycloid reduction motor BM2-250, with a speed between 0-250rpm, an output torque between 0-470N.m, an output power of 0-10Kw, a maximum pressure of 14Mpa, and a maximum flow of 25L / min.
[0034] Please refer to Figure 9-11 The method for laying the multifunctional high-voltage cable lifting and laying guide arm comprises:
[0035] (1) Laying on the track side of bridges and tunnels; adjust the angle of the column assembly 2 and rotate it to 30-60° with the line, adjust the swing angle of the folding arm assembly 3 and the length of the multi-stage telescopic arm assembly 4, so that the head of the multi-stage telescopic arm assembly 4 is about 1-1.3 meters away from the cable trough, and the high-voltage cable is clamped in the folding arm cable limiter 3-2 or the telescopic arm cable limiter 4-1. The cable drum rotates synchronously with the external loading vehicle (the guide arm is loaded on the external loading vehicle as a whole), and the cable 7 is released. The guide arm guides the cable into the direction of the cable trough. The cable falling into the cable trough forms tension on the folding arm assembly 3 and the multi-stage telescopic arm assembly 4. The guide arm guides the cable to the cable trough to complete the high-voltage cable laying;
[0036] (2) Laying across tracks in bridges and tunnels; adjust the angle of the column assembly 2 and rotate it to 20-40° with the line, adjust the swing angle of the folding arm assembly 3, install the auxiliary extension arm 5 at the corresponding position of the head of the multi-stage telescopic arm assembly 4, adjust the length of the multi-stage telescopic arm assembly 4, so that the total length of the folding arm assembly 3, the multi-stage telescopic arm assembly 4, and the auxiliary extension arm 5 is greater than 7.3 meters, adjust the rotation angle of the rotating body, so that the cable fork 5-1 at the head of the auxiliary extension arm 5 is 1-1.3 meters above the cable trough, and install the high-voltage cable in the folding arm cable limiter 3-2, the telescopic arm cable limiter 4-1 and the auxiliary arm cable fork 5-1. The cable drum rotates synchronously with the vehicle to release the cable 7. The auxiliary arm cable fork 5-1 guides the cable into the direction of the cable trough. The cable falling into the cable trough forms tension on the guide arm. As the external loading vehicle moves forward, the cable guide is sequentially guided to the cable trough to complete the laying of the high-voltage cable;
[0037] (3) Laying high-voltage cables over the roadbed section; according to the railway design specifications, the cable trough of the roadbed section is designed on the outside of the contact network pillar 9 foundation, and the implementation method is consistent with the laying on the track side of the bridge and tunnel sections; the cross-construction and mutual interference of the four majors of the railway have not been overcome. After the contact network pillars are assembled, the high-voltage cables are completely laid manually. The implementation method is as follows;
[0038] (a) Install the auxiliary extension arm 5 at the corresponding position of the telescopic arm head, adjust the column rotation angle to 30-60° with the line, adjust the angle of the folding arm assembly 3, adjust the multi-stage telescopic arm assembly 4, adjust the swing angle of the rotating body assembly 1 and the folding arm, so that the cable fork 5-1 at the head of the auxiliary arm crosses the top of the contact network pillar, and the high-voltage cable crosses the contact network pillar 9 in the cable fork, and the folding arm assembly 3 is dropped, and the cable falls into the cable trough, and the cable crosses the pillar. At this time, the external loading vehicle stops, and the cable drum rotates to release the cable length to meet the crossing height of the guide arm. After the crossing, the rotating column is completed to make the swing angle of the folding arm assembly 3 and the multi-stage telescopic arm assembly 4 follow the line direction. When it reaches the next pillar, the column is rotated, and the swing angle of the folding arm assembly 3 is adjusted to cross the next time. Repeat this process to complete the laying of the cable across the pillar;
[0039] (b) It is implemented as laid on the track side of bridges and tunnels: first advance and lay all the cables to a safe position on the roadbed between the track plate and the contact network pillar 9. After all the cables are laid, when the empty car returns, adjust the total length of the guide arm to meet the crossing requirements, manually put the cable near the pillar into the cable fork 5-1, operate the swing angle of the folding arm assembly 3 and the angle of the rotating body assembly 1, and climb over the top of the contact network pillar 9. Drop the guide arm, and the cable will fall into the cable trough. Rotate the column to make the guide arm and the line in the same direction, and repeat this process to complete the cable crossing.
[0040] The use of folding arm and telescopic arm structure is conducive to the compact structure of the guide arm and free extension. The guide arm is used to lift the cable, which saves the number of truck cranes. It is used for high-altitude operations to improve work efficiency, reduce labor costs, and has a better lifting curve.
[0041] Economic benefit comparison: Manual line laying: 8 people x 200 yuan / person = 1,600 yuan, management fee
[0042] 1600x25%=400 yuan, totaling 2000 yuan, based on 70 days of operation, the manual line laying cost is 210000 yuan. If there are obstacles, more than 30 people or even more are needed, and the efficiency is as low as less than 1km per hour.
[0043] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "lateral", "parallel", "vertical", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0044] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the structural relationship and principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A multifunctional high-voltage cable lifting and laying guide arm, characterized in that: The invention comprises a slewing assembly (1) for providing a slewing action, a column assembly (2) for providing a supporting action, a folding arm assembly (3), a multi-stage telescopic arm assembly (4), an auxiliary extension arm (5), a hanging basket assembly (6) for an operator to perform aerial operations, and a control device; the lower part of the slewing assembly is fixed to an external movable vehicle body, and the upper end is fixed to the lower end of the column assembly (2); the two ends of the folding arm assembly (3) are respectively hinged to the fixed column assembly (2) and the multi-stage telescopic arm assembly (4); a folding control oil cylinder (1-1) is provided between the folding arm assembly (3) and the slewing assembly (1) or the column assembly (2); and a folding control oil cylinder (1-1) is fixedly installed on one side of the folding arm assembly (3) for operating the folding arm assembly. A folding arm oil cylinder (3-1) is used for changing the arm amplitude or adjusting the up and down swing angle of the guide arm. The telescopic end of the folding arm oil cylinder (3-1) is fixed to the ear seat (3-3) of the multi-stage telescopic arm oil cylinder. The multi-stage telescopic arm assembly (4) has a built-in oil cylinder to drive the multi-stage telescopic arm to extend and retract. The front end of the auxiliary extension arm (5) is fixedly connected to the end of the multi-stage telescopic arm assembly (4). The folding arm assembly (3) is provided with at least one folding arm cable stopper (3-2). The multi-stage telescopic arm assembly (4) is provided with at least one telescopic arm cable stopper (4-1). A safety wire rope (4-2) is provided between the folding arm assembly (3) and the multi-stage telescopic arm assembly (4) to serve as an insurance. One end of the auxiliary extension arm (5) is fixedly connected to the end of the multi-stage telescopic arm assembly (4) through a triangular plate (4-3), and a rotatable universal cable fork (5-1) is installed on the top of the other end for guiding and lifting the cable, and is designed for crossing over electric poles and pillars; The hanging basket assembly (6) is a vertical telescopic structure. The hanging ring (6-1) is rectangular and has a fan-shaped hole on the upper part, which is connected to the corresponding shaft on the end of the telescopic arm. The fan-shaped hole can adapt to the vertical posture of the hanging basket. The two limit columns at the bottom are blocked below the upper cross brace of the hanging basket. The cross brace is opened according to the cross-sectional size of the hanging ring. The hanging ring is inserted into the hole, and the two limit columns are installed and locked. The hanging ring is forced to rise, and the hanging basket cross brace is hung on the two limit columns. On the contrary, the hanging ring is lowered and retracted. The structure of the folding arm cable limiter (3-2) or the telescopic arm cable limiter (4-1) is that a flat steel is folded into a U-shape, a hole is drilled at the bottom, and it is fixed to the head of the folding arm or the telescopic arm by bolts. A hole is drilled above the U-shape, and buckles at both ends of the nylon belt and a rotatable hollow shaft (3-21) are placed therein, so as to limit the guided cable and prevent the cable from popping out of the guide arm due to tension.
2. The multifunctional high-voltage cable lifting and laying guide arm according to claim 1 is characterized in that: The rotary body assembly (1) comprises a hydraulic motor (11), a base plate (12), a slewing bearing (13), a hydraulic motor slewing disc (14), and a slewing body top cover (15); the hydraulic motor (11) and the inner ring of the slewing bearing (13) are respectively connected to the base plate (12) by bolts; the spline hole of the hydraulic motor slewing disc (14) is connected to the spline shaft of the hydraulic motor (11), and the hydraulic motor slewing disc (14) and the slewing body top cover (15) are fixedly connected to the slewing bearing (13) by bolts.
3. The multifunctional high-voltage cable lifting and laying guide arm according to claim 1 is characterized in that: The folding control oil cylinder (1-1) is installed in reverse, that is, the telescopic end of the folding control oil cylinder (1-1) is connected to the rotating body assembly (1) or the column assembly (2), and the base of the folding control oil cylinder (1-1) is installed on the folding arm assembly (3) to improve the lifting force of the variable amplitude oil cylinder top.
4. The multifunctional high-voltage cable lifting and laying guide arm according to claim 1 is characterized in that: The multi-stage telescopic arm assembly (4) has multiple HSG80-1700 oil cylinders installed inside. The oil cylinders are installed in the inner cavity of each stage of the telescopic arm assembly. The base of the oil cylinder barrel is fixed to the first stage, and the telescopic end of the piston rod is fixed to the inner cavity of the second stage arm. The same applies to the remaining stages of telescopic arms.
5. The method for laying a multifunctional high-voltage cable lifting and laying guide arm according to claim 1, characterized in that: There are three situations: (1) Laying on the track side of bridges and tunnels; adjusting the angle of the column assembly (2) and rotating it to 30-60 degrees with the line, adjusting the swing angle of the folding arm assembly (3) and the length of the multi-stage telescopic arm assembly (4) so that the head of the multi-stage telescopic arm assembly (4) is about 1-1.3 meters away from the cable trough, and the high-voltage cable is clamped in the folding arm cable limiter (3-2) or the telescopic arm cable limiter (4-1). The cable drum rotates synchronously with the external loading vehicle, and the cable (7) is released. The guide arm guides the cable into the direction of the cable trough. The cable falling into the cable trough forms tension on the folding arm assembly (3) and the multi-stage telescopic arm assembly (4). The guide arm guides the cable to the cable trough, and the high-voltage cable laying is completed; (2) Laying across tracks in bridges and tunnels; adjusting the angle of the column assembly (2) to rotate it to 20-40 degrees with the track, adjusting the swing angle of the folding arm assembly (3), installing the auxiliary extension arm (5) at the corresponding position of the head of the multi-stage telescopic arm assembly (4), adjusting the length of the multi-stage telescopic arm assembly (4) to make the total length of the folding arm assembly (3), the multi-stage telescopic arm assembly (4) and the auxiliary extension arm (5) greater than 7.3 meters, adjusting the rotation angle of the rotating body to make the head of the auxiliary extension arm (5) The cable fork (5-1) of the upper part is 1-1.3 meters above the cable trough, and the high-voltage cable is clamped in the folding arm cable limiter (3-2), the telescopic arm cable limiter (4-1) and the auxiliary arm cable fork (5-1). The cable drum rotates synchronously with the vehicle to release the cable. The auxiliary arm cable fork (5-1) guides the cable into the direction of the cable trough. The cable falling into the cable trough forms tension on the guide arm. As the external loading vehicle moves forward, the cable is guided to the cable trough in sequence, and the high-voltage cable laying is completed. (3) Laying high-voltage cables over the roadbed section; according to railway design specifications, the cable trough of the roadbed section is designed on the outside of the contact network support (9) foundation, and the implementation method is the same as laying on the track side of the bridge and tunnel section; the implementation method is as follows; (a) Install the auxiliary extension arm (5) at the corresponding position of the telescopic arm head, adjust the column rotation angle to 30-60 degrees with the line, adjust the angle of the folding arm assembly (3), adjust the multi-stage telescopic arm assembly (4), adjust the rotating body assembly (1) and the folding arm swing angle, so that the cable fork (5-1) at the head of the auxiliary arm crosses the top of the contact network pillar, the high-voltage cable crosses the contact network pillar (9) in the cable fork, drop the folding arm assembly (3), the cable falls into the cable trough, and the cable crosses the pillar. At this time, the external loading vehicle stops, the cable drum rotates to release the cable length to meet the crossing height of the guide arm, and the crossing is completed by rotating the column to make the swing angle of the folding arm assembly (3) and the multi-stage telescopic arm assembly (4) follow the line direction. When reaching the next pillar, rotate the column, adjust the swing angle of the folding arm assembly (3) to cross the next time, and repeat this process to complete the cable crossing and laying; (b) The cable is laid on the track side of the bridge and tunnel section: first advance and lay all the cables to a safe position on the roadbed between the track plate and the overhead contact network pillar (9). After all the cables are laid, when the empty car returns, adjust the total length of the guide arm to meet the span requirement, manually put the cable near the pillar into the cable fork (5-1), operate the swing angle of the folding arm assembly (3) and the angle of the rotating body assembly (1), and let the cable go over the top of the overhead contact network pillar (9). Then lower the guide arm and the cable falls into the cable trough. Rotate the column so that the guide arm is in the same direction as the line. Repeat this process to complete the cable spanning.