Construction system and method of top slab formwork for large-section multi-compartment cast-in-place integrated pipe gallery

Through the roof formwork system, mobile steel bar tying frame and construction platform, the construction speed and stability of the roof of the large-section multi-cabin cast-in-place comprehensive pipe gallery have been improved, solving the problems of slow construction speed and low economic benefits, and achieving high efficiency , safe construction effect.

CN112376612BActive Publication Date: 2024-10-25ANHUI ROAD & BRIDGE GRP
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202011420409.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-08
Publication Date
2024-10-25
Estimated Expiration
2040-12-08

AI Technical Summary

Technical Problem

The construction speed of the roof formwork of the large-section multi-cabin cast-in-place integrated pipe gallery is slow, the stability is poor and the economic benefits are low.

Method used

A construction system including a roof formwork system, a movable roof steel bar tying frame and a movable roof construction platform is adopted, and the cantilevering of the roof of the pipe gallery is realized through components such as adjustable supporting poles, folding frames and stereotyped brackets. The formwork and steel bar binding efficiency is improved.

Benefits of technology

It effectively saves construction materials and time costs, improves operation safety and stability, and has good social and economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112376612B_ABST
    Figure CN112376612B_ABST
Patent Text Reader

Abstract

The present invention provides a large-section multi-cabin cast-in-place integrated pipe gallery roof template construction system and construction method, which mainly include a mobile roof construction platform, a mobile roof steel bar binding frame, a roof formwork system and a roof steel bar cage shaped support; an adjustable top support rod is supported on the upper part of the adjacent pipe gallery side wall, a scaffold is set up on the basis of the adjustable top support rod, and the top of the pipe gallery roof bottom formwork is installed on the top of the scaffold; a mobile top steel bar binding frame is symmetrically arranged on both sides of the integrated pipe gallery, and the mobile top steel bar binding frame is used to perform the pipe gallery roof steel bar binding construction, and the pipe gallery roof steel bar cage is supported on the top surface of the pipe gallery side wall through a shaped support; the top wall upper part of the outer wall at both ends of the outer wall of the pipe gallery is installed with a top plate side formwork through a tension screw, and the mobile top plate construction platform is used to perform top plate steel bar auxiliary operation and concrete pouring construction. The large-section multi-cabin cast-in-place integrated pipe gallery roof template system involved in the present invention is simple to install, has a large construction operation space, high efficiency and good benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of foundation engineering, and in particular to a top slab formwork construction system and a construction method for a large-section multi-compartment cast-in-place integrated pipe gallery. Background Art

[0002] Underground integrated pipeline corridors are used to centralize various pipelines in municipal infrastructure, such as electricity, communications, water supply, gas, and heating, for unified laying, management, and maintenance. It not only solves urban traffic problems, but also greatly promotes the maintenance and operation of municipal services, and also has some functions to prevent natural disasters.

[0003] At present, according to the analysis of domestic and foreign engineering examples, under non-special environments, the main structure of the integrated pipe corridor is mainly divided into two types according to the construction method: cast-in-place method and prefabrication method. The main structure of the prefabricated pipe corridor is completed in the prefabrication plant. Compared with outdoor cast-in-place operations, the component size accuracy is high and the quality of the finished product can be guaranteed to the maximum extent. However, at present, only some areas in China have built single-cabin prefabricated pipe corridors, and there are no mature construction cases for double-cabin prefabricated pipe corridors, especially large-section multi-cabin integrated pipe corridors, which are all cast-in-place. There is still a lot of room for improvement in the cast-in-place construction of large-section multi-cabin integrated pipe corridors, including the formwork support of the pipe corridor and the rapid binding of steel bars.

[0004] In view of this, there is an urgent need to invent a large-section multi-compartment cast-in-place integrated pipeline gallery top slab formwork system with fast construction speed, good stability, and outstanding economic and technical benefits. Summary of the invention

[0005] The purpose of the present invention is to provide a large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system and construction method, aiming to solve the current technical problems of slow construction speed, poor stability and low economic benefit of large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork.

[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions:

[0007] The large-section multi-compartment cast-in-place integrated pipe gallery roof formwork construction system includes the roof formwork system, the mobile roof reinforcement binding frame and the mobile roof construction platform;

[0008] The roof formwork system includes adjustable top support rods, scaffolding, gallery roof bottom formwork, standardized brackets and gallery roof side formwork; the two ends of the adjustable top support rods are respectively abutted against the inner sides of adjacent gallery side walls for limiting positions; the scaffolding is erected on the adjustable top support rods; the gallery roof bottom formwork is installed on the scaffolding; the standardized brackets are positioned on the top of the gallery side walls to support the gallery roof steel cage on the top surface of the gallery side walls; the gallery roof side formwork is positioned on the outer walls at both ends of the gallery side walls by tension bolts;

[0009] The mobile top plate steel bar binding tire frame comprises a tire frame support body, a foldable tire frame and tire frame running wheels; the foldable tire frame is arranged on the tire frame support body; the tire frame running wheels are arranged at the bottom of the tire frame support body; the mobile top plate steel bar binding tire frames are symmetrically arranged on the cushion layer outside the bottom plate of the pipe gallery;

[0010] The mobile roof construction platform includes a platform support body, a platform beam, platform running wheels and a construction connecting beam; the platform beam is positioned on the platform support body to form a gate-shaped support structure; the platform running wheels are arranged under the platform support body; the construction connecting beam is arranged under the platform beam to realize the connection of the platform beams adjacent to each other along the longitudinal direction of the pipeline corridor; the mobile roof construction platform is laterally spanned on the integrated pipeline corridor.

[0011] As a further improvement of the present invention, the adjustable top support rod includes a rod body and a telescopic end; the telescopic ends are respectively arranged at both ends of the rod body; and the outer ends of the telescopic ends are pressed against the side wall of the pipe gallery through support plates.

[0012] As a further improvement of the present invention, the tire frame support body is arranged in a longitudinal array along the integrated pipeline corridor; the tire frame support body is symmetrically arranged on both lateral sides of the integrated pipeline corridor.

[0013] As a further improvement of the present invention, the foldable tire frame structure includes a bending connecting rod, a tire frame upright rod and a transverse steel casing; the tire frame upright rods are evenly distributed on the bending connecting rod; and the transverse steel casing is fixedly provided on the tire frame upright rod.

[0014] As a further improvement of the present invention, a tire frame connecting plate is further provided; the tire frame connecting plate is arranged between the folding tire frames adjacent to each other in the longitudinal direction of the pipe gallery, and is used to connect the adjacent folding tire frames; the curved connecting rod is positioned on the tire frame connecting plate.

[0015] As a further improvement of the present invention, the standardized bracket includes a positioning plate and claws; the positioning plate is positioned on the claws; the claws are positioned at the top of the side wall of the corridor; a limiting ring is provided on the edge of the positioning plate to support the steel cage of the corridor top plate and the top surface of the corridor side wall.

[0016] As a further improvement of the present invention, the positioning plate is a plate structure with a U-shaped cross section; and the foot claw is an E-shaped plate structure.

[0017] As a further improvement of the present invention, the platform support bodies are arranged in a longitudinal array along the integrated pipe gallery; the platform support bodies are symmetrically arranged on both lateral sides of the integrated pipe gallery.

[0018] As a further improvement of the present invention, a construction panel and a construction beam shelf are further provided; the construction panel is laid on the construction connecting beam; the construction beam shelf is arranged between adjacent construction panels to achieve connection between front and rear construction panels.

[0019] The construction method of the large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork system comprises the following steps:

[0020] S1. Excavation and protection of foundation pit: carry out layered excavation of foundation pit according to the survey and layout results, carry out cushion construction after excavation to the designed elevation of the pit bottom, and take protective measures at the edge of the foundation pit;

[0021] S2. Construction of the tunnel floor and side walls: Clean the cushion layer and lay out the tunnel floor steel bars according to the design drawings. After acceptance, pour the floor concrete. After the tunnel floor is cured, tie the side wall steel bars, support the formwork with the side formwork trolley system, and pour the side wall concrete.

[0022] S3, dismantling of the tunnel side wall formwork system: after the tunnel side wall concrete curing is completed, first remove the auxiliary components on the tunnel side formwork trolley system, then demould through the trolley system, and move the trolley system to the next working surface until the tunnel side wall construction is completed;

[0023] S4. Installation of the bottom formwork of the pipe gallery roof: Install adjustable top support rods on the upper part of the adjacent pipe gallery side walls, manually determine the support position and place the support plates, adjust the telescopic ends of the support rods to make them completely press against the support plates, then set up scaffolding on the top surface of the adjustable top support rods, and install the bottom formwork of the pipe gallery roof on the top of the scaffolding;

[0024] S5. Erection of the mobile top plate reinforcement tyre frame: The assembled mobile top plate reinforcement tyre frame is pushed into the site according to the construction route outside the side wall of the pipe gallery. After being moved to the construction position, the top bending connecting rod and the bottom walking wheel are adjusted to ensure the operability of the folding tyre frame, and finally the position of the entire mobile top plate reinforcement tyre frame is locked;

[0025] S6. Erection of the mobile roof construction platform: Assemble the platform crossbeam, platform support body and platform running wheels according to the width and construction height of the mobile roof reinforcement binding frame. After determining the construction route and the spacing between the platform support bodies, push the preliminarily assembled mobile roof construction platforms one by one in an orderly manner into the site. After locking the position, manually weld the construction connecting beams at the bottom of the platform crossbeam according to the designed spacing, and lay the construction panels;

[0026] S7. Tie up the steel bars on the top slab of the pipe gallery: Use the mobile steel bar tie up frame and the mobile top slab construction platform to tie up the steel bars on the top slab of the pipe gallery. Use the standardized bracket to support the steel bar cage on the top slab of the pipe gallery and the top surface of the side wall of the pipe gallery.

[0027] S8. Concrete pouring of the pipe gallery roof: After the steel bar binding of the pipe gallery roof is accepted, the foldable cradle is retracted first, and the entire mobile steel bar binding cradle is moved to the next working surface, and then the side formwork of the pipe gallery roof is installed by tension bolts. The concrete of the pipe gallery roof can be poured only after the side formwork is accepted. After pouring, it is maintained in time;

[0028] S9. The formwork system is dismantled and transferred to the next working surface: After the maintenance measures for the tunnel roof are arranged, the mobile roof construction platform can be moved to the next working surface. After the tunnel roof concrete is cured, the tunnel roof side formwork, adjustable top support rods, scaffolding and tunnel roof bottom formwork are dismantled, and the dismantled construction materials are uniformly transferred to the next working surface;

[0029] S10. Completion of construction: After completing the construction of the entire working surface in sequence, clean up the site and remove other components and equipment to complete the construction.

[0030] Compared with the prior art, the present invention has the following beneficial effects:

[0031] The present invention realizes the cantilever formwork of the tunnel roof by supporting adjustable top support rods between the side walls of the tunnel, which effectively saves construction materials and construction time costs; by arranging a movable top plate steel bar tying frame, the steel bar tying efficiency of the tunnel roof is greatly improved; by arranging a movable top plate construction platform, convenience is provided for the tunnel roof operation, thereby saving time cost, and further improving the operation safety, and at the same time, it can protect the finished steel bar cage of the tunnel roof during the construction process; the structure of the present application is simple to assemble, fast to transfer, and can be used repeatedly, and the overall construction setting is reasonable, the structure is compact, the construction operation space is large, the stability is high, and it has very good social and economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. It is obvious that the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0033] Figure 1 This is a schematic diagram of the construction of a movable top plate reinforcement binding frame in the present invention;

[0034] Figure 2 It is a top view of the movable top plate reinforcement binding frame of the present invention;

[0035] Figure 3 It is a construction schematic diagram of the movable top plate construction platform in the present invention;

[0036] Figure 4 It is a schematic diagram of the formwork system of the pipe gallery roof in the present invention;

[0037] Figure 5 It is a plan view of the movable top plate construction platform of the present invention;

[0038] Figure 6 It is a construction flow chart of the present invention.

[0039] Description of the numbers in the figure:

[0040] 1. Roof formwork system; 11. Adjustable top support rod; 111. Rod body; 112. Telescopic end; 12. Scaffolding; 13. Pipe gallery roof bottom formwork; 14. Formed bracket; 141. Positioning plate; 142. Claw; 15. Roof gallery side formwork; 16. Tension bolts; 2. Mobile roof reinforcement binding frame; 21. Frame support body; 22. Folding frame; 221. Flexing connecting rod; 222. Frame upright; 223. Horizontal steel casing; 23. Frame walking wheel; 24. Frame connecting plate; 3. Mobile roof construction platform; 31. Platform support body; 32. Platform crossbeam; 33. Platform walking wheel; 34. Construction connecting beam; 35. Construction panel; 36. Construction beam shelf; 4. Pipe gallery side wall; 5. Pipe gallery roof reinforcement cage; 6. Pad layer; 7. Foundation pit slope; 8. Pipe gallery bottom plate. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] Combined with Figures 1 to 6 The present invention provides a large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system and construction method, aiming to solve the current technical problems of slow construction speed, poor stability and low economic benefit of large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork.

[0043] Specifically, the large-section multi-cabin cast-in-place integrated pipe gallery roof formwork construction system includes a roof formwork system 1, a mobile roof steel bar binding frame 2 and a mobile roof construction platform 3;

[0044] The roof formwork system 1 includes an adjustable top support rod 11, a scaffolding 12, a pipe gallery roof bottom formwork 13, a shaped support 14 and a gallery roof side formwork 15; the two ends of the adjustable top support rod 11 are respectively abutted against the inner side of the adjacent pipe gallery side wall 4 for limiting; the scaffolding 12 is erected on the adjustable top support rod 11; the pipe gallery roof bottom formwork 13 is installed on the scaffolding 12; the shaped support 14 is positioned on the top of the pipe gallery side wall 4, and is used to support the pipe gallery roof steel cage 5 on the top surface of the pipe gallery side wall 4; the gallery roof side formwork 15 is positioned on the outer wall at both ends of the pipe gallery side wall 4 through tension bolts 16;

[0045] The mobile top plate steel bar binding tire frame 2 includes a tire frame support body 21, a foldable tire frame 22 and tire frame running wheels 23; the foldable tire frame 22 is arranged on the tire frame support body 21; the tire frame running wheels 23 are arranged at the bottom of the tire frame support body 21; the mobile top plate steel bar binding tire frame 2 is symmetrically arranged on the cushion layer 6 on the outer side of the bottom plate of the pipe gallery;

[0046] The mobile roof construction platform 3 includes a platform support body 31, a platform beam 32, platform running wheels 33 and a construction connecting beam 34; the platform beam 32 is positioned on the platform support body 31 to form a gate-shaped support structure; the platform running wheels 33 are arranged under the platform support body 31; the construction connecting beam 34 is arranged under the platform beam 32 to realize the connection of the platform beams 32 adjacent to each other along the longitudinal direction of the pipeline corridor; the mobile roof construction platform 3 is laterally spanned on the integrated pipeline corridor.

[0047] Furthermore, the adjustable top support rod 11 includes a rod body 111 and a telescopic end 112; the telescopic end 112 is respectively arranged at both ends of the rod body 111; the outer end of the telescopic end 112 is pressed against the side wall 4 of the pipe gallery through a support plate.

[0048] Preferably, the cross section of the rod body 111 is rectangular; the vertical poles of the scaffolding 12 are set on the top surface of the rod body 111.

[0049] Furthermore, the tire frame support bodies 21 are arranged in a longitudinal array along the integrated pipe gallery. The tire frame support bodies 21 are symmetrically arranged on both lateral sides of the integrated pipe gallery.

[0050] Preferably, the tire frame support body 21 is a steel structure; the tire frame support body 21 is provided with a top plate and a bottom plate, the tire frame walking wheels 23 are provided under the bottom plate, and the foldable tire frame 22 is provided on the top plate.

[0051] Furthermore, the foldable tire frame 22 structure includes a curved connecting rod 221, a tire frame upright rod 222 and a transverse steel casing 223; the tire frame upright rod 222 is evenly distributed on the curved connecting rod 221; and the transverse steel casing 223 is fixedly provided on the tire frame upright rod 222.

[0052] Furthermore, a tire frame connecting plate 24 is provided; the tire frame connecting plate 24 is provided between the adjacent folding tire frames 22 in the longitudinal direction of the pipe gallery, and is used to achieve the connection of adjacent folding tire frames 22; the curved connecting rod 221 is positioned on the tire frame connecting plate 24.

[0053] Furthermore, the standardized bracket 14 includes a positioning plate 141 and a claw 142; the positioning plate 141 is positioned on the claw 142; the claw 142 is positioned at the top of the corridor side wall 4; a limiting ring is provided on the edge of the positioning plate 141, which is used to support the corridor top plate steel cage 5 and the top surface of the corridor side wall 4.

[0054] Preferably, the positioning plate 141 is a plate structure with a U-shaped cross section; and the claws 142 are an E-shaped plate structure.

[0055] Furthermore, the platform support bodies 31 are arranged in a longitudinal array along the integrated pipe gallery; the platform support bodies 31 are symmetrically arranged on both lateral sides of the integrated pipe gallery.

[0056] Preferably, the platform support body 31 is a steel structure, and platform walking wheels 33 are provided at the bottom.

[0057] Furthermore, a space for a movable top plate reinforcement binding frame 2 is reserved between the platform support body 31 and the side wall 4 of the pipe gallery.

[0058] Furthermore, a construction panel 35 and a construction beam shelf 36 are provided; the construction panel 35 is laid on the construction connecting beam 34 to facilitate the operation and construction of the construction personnel; the construction beam shelf 36 is provided between adjacent construction panels 35 to realize the connection between the front and rear construction panels 35 .

[0059] The construction method of the large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork system comprises the following steps:

[0060] S1. Excavation and protection of foundation pit: carry out layered excavation of foundation pit according to the survey and layout results, and carry out cushion layer 6 construction after excavation to the design elevation of the pit bottom, and take protective measures at the edge of the foundation pit;

[0061] S2. Construction of the pipe gallery floor and side walls: Clean the cushion layer 6 and lay out the pipe gallery floor steel bars according to the design drawings. After acceptance, pour the floor concrete. After the maintenance of the pipe gallery floor is completed, tie the side wall steel bars, support the formwork through the side formwork trolley system, and pour the side wall concrete.

[0062] S3, dismantling of the tunnel side wall formwork system: after the tunnel side wall 4 concrete curing is completed, the auxiliary components on the tunnel side formwork trolley system are first dismantled, and then the trolley system is used for demoulding, and the trolley system is moved to the next working surface until the tunnel side wall 4 construction is completed;

[0063] S4, installation of the bottom formwork of the pipe gallery roof: installing an adjustable top support rod 11 on the upper part of the adjacent pipe gallery side wall 4, manually determining the support position and placing the support plate, adjusting the telescopic end 112 of the support rod to make it completely close to the support plate, and then setting up a scaffolding 12 on the top surface of the adjustable top support rod 11, and installing the bottom formwork 13 of the pipe gallery roof on the top of the scaffolding 12;

[0064] S5, erection of the mobile top plate steel bar binding cradle: the assembled mobile top plate steel bar binding cradle 2 is pushed into the site according to the construction route outside the side wall 4 of the pipe gallery, and after being moved to the construction position, the top curved connecting rod 221 and the bottom running wheel are adjusted to ensure the operability of the foldable cradle 22, and finally the position of the entire mobile top plate steel bar binding cradle 2 is locked;

[0065] S6, erection of mobile roof construction platform: assemble the platform cross beam 32, platform support body 31 and platform walking wheel 33 according to the width and construction height of the mobile roof reinforcement binding frame 2, determine the construction route and the spacing of the platform support body 31, and push the preliminarily assembled mobile roof construction platform 3 one by one in an orderly manner into the site. After locking the position, manually weld the construction connecting beam 34 at the bottom of the platform cross beam 32 according to the designed spacing, and lay the construction panel 35;

[0066] S7, pipe gallery roof reinforcement binding: use the mobile roof reinforcement binding frame 2 and the mobile roof construction platform 3 to bind the pipe gallery roof reinforcement, and use the standardized bracket 14 to support the pipe gallery roof reinforcement cage 5 and the top surface of the pipe gallery side wall 4;

[0067] S8, pouring concrete for the top slab of the pipe gallery: after the steel bar binding of the top slab of the pipe gallery is accepted, the foldable tire frame 22 is retracted first, and the entire mobile top slab steel bar binding tire frame 2 is moved to the next working surface, and then the side formwork 15 of the top slab of the pipe gallery is installed by tension bolts. The concrete for the top slab of the pipe gallery can be poured only after the side formwork is accepted. After pouring, it is maintained in time;

[0068] S9, the formwork system is dismantled and transferred to the next working surface: after the maintenance measures for the pipe gallery roof are arranged, the mobile top plate construction platform 3 can be moved to the next working surface first, and after the concrete maintenance of the pipe gallery roof is completed, the pipe gallery roof side formwork 15, the adjustable top support rod 11, the scaffolding 12 and the pipe gallery roof bottom formwork 13 are dismantled, and the dismantled construction materials are uniformly transferred to the next working surface;

[0069] S10. Completion of construction: After completing the construction of the entire working surface in sequence, clean up the site and remove other components and equipment to complete the construction.

[0070] The present invention realizes the cantilever formwork of the tunnel roof by supporting adjustable top support rods between the side walls of the tunnel, which effectively saves construction materials and construction time costs; by arranging a movable top plate steel bar tying frame, the steel bar tying efficiency of the tunnel roof is greatly improved; by arranging a movable top plate construction platform, convenience is provided for the tunnel roof operation, thereby saving time cost, and further improving the operation safety, and at the same time, it can protect the finished steel bar cage of the tunnel roof during the construction process; the structure of the present application is simple to assemble, fast to transfer, and can be used repeatedly, and the overall construction setting is reasonable, the structure is compact, the construction operation space is large, the stability is high, and it has very good social and economic benefits.

[0071] During the specific construction, the foundation pit is excavated in layers according to the measurement and layout results. The layer thickness should be controlled within 3m. Slope support should be carried out in time after each layer and each section is excavated. After excavation to the design elevation of the pit bottom, cushion layer 6 is constructed, and protective measures are taken at the edge of the foundation pit; then the cushion layer 6 is cleaned and the corridor bottom slab 8 steel bars are arranged according to the requirements of the design drawings. After acceptance, the bottom slab concrete is poured. After the maintenance of the corridor bottom slab 8 is completed, the side wall steel bars are tied, and the side formwork trolley system is used to support the formwork and pour the side wall concrete; after the concrete maintenance of the corridor side wall 4 is completed, the auxiliary components on the corridor side formwork trolley system are first removed, and then the formwork is demolded through the trolley system, and the trolley system is moved to the next working surface until the construction of the corridor side wall 4 is completed.

[0072] After the side wall 4 of the tunnel is completed, an adjustable top support rod 11 is installed on the upper part of the adjacent side wall 4 of the tunnel, the support position is manually determined and the support plate is placed, the telescopic end of the support rod is adjusted to make it completely tight against the support plate, and then a scaffolding 12 is erected on the top surface of the adjustable top support rod 11, and the tunnel roof bottom formwork 13 is installed on the top of the scaffolding 12, and the height difference between the two adjacent formwork surfaces is controlled within 2 mm.

[0073] Subsequently, the assembled mobile top plate reinforcement tying frame 2 is pushed into the site according to the construction route outside the side wall 4 of the tunnel. After moving to the construction position, the top curved connecting rod 221 and the bottom walking wheel are adjusted to ensure the operability of the foldable frame, and finally the position of the entire mobile top plate reinforcement tying frame 2 is locked.

[0074] Next, the platform beam 32, platform support body 31 and platform walking wheel 33 are assembled according to the width and construction height of the mobile roof reinforcement binding frame 2. After determining the construction route and the spacing between the platform support bodies 31, the preliminarily assembled mobile roof construction platforms are pushed into the site one by one in an orderly manner. After locking the position, the connecting beam 34 is manually welded at the bottom of the platform beam 32 according to the designed spacing, and the construction panel 35 is laid.

[0075] The above-mentioned mobile top slab reinforcement tying frame 2 and the mobile top slab construction platform are used to tie the top slab reinforcement of the corridor, and the top slab reinforcement cage 5 of the corridor and the top surface of the corridor side wall 4 are supported by a standardized bracket 1; after the corridor top slab reinforcement tying is accepted, the folding tyre is first retracted, and the entire mobile top slab reinforcement tying frame is pushed to the next working surface, and then the corridor top slab side formwork 15 is installed by tension bolts 16.

[0076] The tunnel roof slab concrete can only be poured after the side formwork has been accepted. When pouring, first evenly pour 5 cm thick cement mortar, the same as the wall concrete, on the bottom. After the concrete is put into the mold, it is vibrated layer by layer. The layer thickness should not exceed 500 mm, and the vibrator should be inserted into the next layer of concrete by not less than 100 mm. After the concrete is poured, it should be covered and watered within 12 hours, and a curing period of not less than 7 days and nights should be ensured.

[0077] After the maintenance measures for the tunnel roof are arranged, the mobile roof construction platform can be pushed to the next working surface. After the tunnel roof concrete maintenance is completed, the tunnel roof side formwork 15, adjustable top support rods 11, scaffolding 12 and tunnel roof bottom formwork 13 are dismantled, and the dismantled construction materials are uniformly transferred to the next working surface.

[0078] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0079] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0080] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0081] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0082] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0083] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. The large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system is characterized by: It includes the roof formwork system, the mobile roof reinforcement binding frame and the mobile roof construction platform; The roof formwork system includes adjustable top support rods, scaffolding, gallery roof bottom formwork, standardized brackets and gallery roof side formwork; the two ends of the adjustable top support rods are respectively abutted against the inner sides of adjacent gallery side walls for limiting positions; the scaffolding is erected on the adjustable top support rods; the gallery roof bottom formwork is installed on the scaffolding; the standardized brackets are positioned on the top of the gallery side walls to support the gallery roof steel cage on the top surface of the gallery side walls; the gallery roof side formwork is positioned on the outer walls at both ends of the gallery side walls by tension bolts; The mobile top plate steel bar binding tire frame comprises a tire frame support body, a foldable tire frame and tire frame running wheels; the foldable tire frame is arranged on the tire frame support body; the tire frame running wheels are arranged at the bottom of the tire frame support body; the mobile top plate steel bar binding tire frames are symmetrically arranged on the cushion layer outside the bottom plate of the pipe gallery; The mobile roof construction platform includes a platform support body, a platform beam, platform running wheels and a construction connecting beam; the platform beam is positioned on the platform support body to form a gate-shaped bracket structure; the platform running wheels are arranged under the platform support body; the construction connecting beam is arranged under the platform beam to realize the connection of the platform beams adjacent to each other in the longitudinal direction of the pipe gallery; the mobile roof construction platform is laterally arranged across the integrated pipe gallery; The foldable tire frame structure comprises a bending connecting rod, a tire frame upright rod and a transverse steel casing; the tire frame upright rods are evenly distributed on the bending connecting rod; and the transverse steel casing is fixedly provided on the tire frame upright rod.

2. The large-section multi-compartment cast-in-place integrated pipe gallery top slab formwork construction system according to claim 1 is characterized by: The adjustable top support rod comprises a rod body and a telescopic end; the telescopic ends are respectively arranged at two ends of the rod body; and the outer ends of the telescopic ends are pressed against the side wall of the pipe gallery through support plates.

3. The large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system according to claim 1 is characterized by: The tire frame support body is arranged in a longitudinal array along the integrated pipeline corridor; the tire frame support body is symmetrically arranged on both lateral sides of the integrated pipeline corridor.

4. The large-section multi-compartment cast-in-place integrated pipe gallery top slab formwork construction system according to claim 3 is characterized by: A tire frame connecting plate is also provided; the tire frame connecting plate is arranged between the folding tire frames adjacent to each other in the longitudinal direction of the pipe gallery, and is used to connect the adjacent folding tire frames; the bending connecting rod is positioned on the tire frame connecting plate.

5. The large-section multi-compartment cast-in-place integrated pipe gallery top slab formwork construction system according to claim 1 is characterized by: The standardized bracket includes a positioning plate and claws; the positioning plate is positioned on the claws; the claws are positioned at the top of the side wall of the corridor; a limiting ring is provided on the edge of the positioning plate to support the steel cage of the corridor top plate and the top surface of the corridor side wall.

6. The large-section multi-compartment cast-in-place integrated pipe gallery top slab formwork construction system according to claim 5 is characterized by: The positioning plate is a plate structure with a U-shaped cross section; the foot claw is an E-shaped plate structure.

7. The large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system according to claim 1 is characterized by: The platform support bodies are arranged in a longitudinal array along the integrated pipe gallery; the platform support bodies are symmetrically arranged on both lateral sides of the integrated pipe gallery.

8. The large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system according to claim 1 is characterized by: A construction panel and a construction beam shelf are also provided; the construction panel is laid on the construction connecting beam; the construction beam shelf is arranged between adjacent construction panels to realize the connection between the front and rear construction panels.

9. A construction method for a large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork system, based on the large-section multi-cabin cast-in-place integrated pipe gallery top slab formwork construction system according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1. Excavation and protection of foundation pit: carry out layered excavation of foundation pit according to the survey and layout results, carry out cushion construction after excavation to the designed elevation of the pit bottom, and take protective measures at the edge of the foundation pit; S2. Construction of the tunnel floor and side walls: Clean the cushion layer and lay out the tunnel floor steel bars according to the design drawings. After acceptance, pour the floor concrete. After the tunnel floor is cured, tie the side wall steel bars, support the formwork with the side formwork trolley system, and pour the side wall concrete. S3, dismantling of the tunnel side wall formwork system: after the tunnel side wall concrete curing is completed, first remove the auxiliary components on the tunnel side formwork trolley system, then demould through the trolley system, and move the trolley system to the next working surface until the tunnel side wall construction is completed; S4. Installation of the bottom formwork of the pipe gallery roof: Install adjustable top support rods on the upper part of the adjacent pipe gallery side walls, manually determine the support position and place the support plates, adjust the telescopic ends of the support rods to make them completely press against the support plates, then set up scaffolding on the top surface of the adjustable top support rods, and install the bottom formwork of the pipe gallery roof on the top of the scaffolding; S5. Erection of the mobile top plate reinforcement tyre frame: The assembled mobile top plate reinforcement tyre frame is pushed into the site according to the construction route outside the side wall of the pipe gallery. After being moved to the construction position, the top bending connecting rod and the bottom walking wheel are adjusted to ensure the operability of the folding tyre frame, and finally the position of the entire mobile top plate reinforcement tyre frame is locked; S6. Erection of the mobile roof construction platform: Assemble the platform crossbeam, platform support body and platform running wheels according to the width and construction height of the mobile roof reinforcement binding frame. After determining the construction route and the spacing between the platform support bodies, push the preliminarily assembled mobile roof construction platforms one by one in an orderly manner into the site. After locking the position, manually weld the construction connecting beams at the bottom of the platform crossbeam according to the designed spacing, and lay the construction panels; S7. Tie up the steel bars on the top slab of the pipe gallery: Use the mobile steel bar tie up frame and the mobile top slab construction platform to tie up the steel bars on the top slab of the pipe gallery. Use the standardized bracket to support the steel bar cage on the top slab of the pipe gallery and the top surface of the side wall of the pipe gallery. S8. Concrete pouring of the pipe gallery roof: After the steel bar binding of the pipe gallery roof is accepted, the foldable cradle is retracted first, and the entire mobile steel bar binding cradle is moved to the next working surface, and then the side formwork of the pipe gallery roof is installed by tension bolts. The concrete of the pipe gallery roof can be poured only after the side formwork is accepted. After pouring, it is maintained in time; S9. The formwork system is dismantled and transferred to the next working surface: After the maintenance measures for the tunnel roof are arranged, the mobile roof construction platform can be moved to the next working surface. After the tunnel roof concrete is cured, the tunnel roof side formwork, adjustable top support rods, scaffolding and tunnel roof bottom formwork are dismantled, and the dismantled construction materials are uniformly transferred to the next working surface; S10. Completion of construction: After completing the construction of the entire working surface in sequence, clean up the site and remove other components and equipment to complete the construction.

Citation Information

Patent Citations

  • Construction system of subway station

    CN103967050A

  • Construction method for underground comprehensive pipe rack

    CN106013234A

  • Large-section multi-chamber cast-in-place integrated utility tunnel and construction method thereof

    CN109930626A

  • Pipe gallery roof construction trolley, trolley group and construction method

    CN110714785A

  • Supporting and disassembling walking system and construction method thereof for pipe gallery wall plate flow construction

    CN111364516A