A construction method for reinforced concrete rigid oblique column
By comprehensively improving the cast-in-place structure of the stiffening column, the problem of the high construction difficulty of ultra-high inclined stiffening columns was solved, and a safe and efficient construction process was achieved.
Patent Information
- Application Number
- CN202411146911.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-21
AI Technical Summary
In the construction of ultra-high inclined stiffened columns, the existing scaffolding support system is difficult to construct, resulting in operational difficulties and construction inconvenience.
The prefabricated rigid column frame is connected to the steel formwork to form an integral cast-in-place structure. The rigid column is lifted as a whole by using sliding rails and end support structures in conjunction with lifting equipment. During the casting process, the deformation is controlled by steel tie rods. Finally, the steel formwork and steel tie rods are disassembled to complete the construction.
This reduces construction difficulty and time, avoids the need for high-altitude construction platforms or scaffolding support systems, and improves construction safety and efficiency.
Smart Images

Figure CN118653626B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a construction method of a reinforced concrete rigid oblique column. Background Art
[0002] The rigid column is a structure composed of a steel structure with concrete wrapped around it, and is generally widely used in large and complex structures. At present, the construction of inclined rigid columns often uses wooden formwork or shaped steel formwork, and ordinary steel pipes or disc scaffolding as the support system. However, for the construction of ultra-high inclined rigid columns, the higher the height, the more difficult the operation, the higher the requirements for the support system, and the more difficult the support and reinforcement are, resulting in inconvenience in construction. Summary of the invention
[0003] In view of this, the purpose of the present invention is to provide a construction method for reinforced concrete rigid oblique columns, which is used to solve the problem of difficulty in construction of existing scaffolding support systems when constructing ultra-high inclined rigid columns in the prior art.
[0004] In order to achieve the above object, the present invention provides the following technical solutions:
[0005] The present invention provides a construction method of reinforced concrete rigid oblique columns, which is used for obliquely arranging rigid oblique columns between a tower and a steel corridor perpendicular to the tower, and comprises the following steps:
[0006] S1: The prefabricated rigid column skeleton is positioned and installed on the connecting steel plate, and a plurality of longitudinal reinforcements surrounding the rigid column skeleton are fixedly arranged on the connecting steel plate. After the plurality of longitudinal reinforcements are tied and welded through stirrups, a steel formwork is fixedly arranged on the connecting steel plate to form an integral cast structure of the rigid column; wherein a steel tie rod is arranged in the middle of the steel formwork;
[0007] S2: Installing a slide rail at the pre-connection position between the tower and the steel corridor and the integral cast structure of the rigid column, wherein the slide rail is provided with an end support structure for supporting the end of the integral cast structure of the rigid column;
[0008] S3: Slide the end support structure along the slide rail to displace the end support structure and the rigid column integral casting structure, then lift the rigid column integral casting structure to a preset position by a lifting device, slide the end support structure along the slide rail to make the two end support structures respectively abut against the two ends of the rigid column integral casting structure, then connect and fix the two ends of the rigid column integral casting structure to the tower and the steel corridor respectively, and connect and fix the steel tie rod away from the rigid column integral casting structure end to the tower or the steel corridor;
[0009] S4: pouring concrete into the rigid column integral casting structure to form a rigid oblique column. During the pouring process, the deformation of the rigid column integral casting structure is regulated by adjusting the steel tie rods.
[0010] S5: After the rigid diagonal columns are formed, the steel formwork is dismantled and the steel tie rods are separated from the tower or steel corridor, and then the steel formwork and steel tie rods are lowered as a whole through the lifting equipment.
[0011] Furthermore, the steel formwork includes: a bottom formwork arranged in a U shape and a cover formwork capable of closing the bottom formwork, the bottom formwork is provided with a plurality of first connection parts on two opposite side walls, the cover formwork is provided with a plurality of second connection parts corresponding one to one to the first connection parts, the first connection parts and the second connection parts are threadedly connected and fixed by tension screws so that the cover formwork is connected and fixed to the bottom formwork.
[0012] Further, in step S5, the process of disassembling the steel formwork includes:
[0013] A1: When the concrete strength reaches 70% of the preset strength, the cover formwork is removed by turning the tension screws and maintenance operations are carried out;
[0014] A2: When the concrete strength reaches 100% of the preset strength, the bottom formwork is demoulded, the steel tie rods are separated from the tower or steel corridor, and the steel formwork and steel tie rods are lowered as a whole through lifting equipment.
[0015] Furthermore, the end support structure includes: a support seat slidably mounted on a slide rail, a screw rod rotatably mounted on the slide rail, the screw rod being threadedly connected to the support seat, and rotating the screw rod can make the support seat slide along the slide rail, and the support seat is connected to a support plate capable of cooperating with the end of the integral cast structure of the rigid column through an adjusting screw, wherein both ends of the support seat extending outside the tower or the steel corridor are threadedly connected with two adjusting screws, and the two adjusting screws are arranged along the sliding direction of the support seat, and two sliding blocks are slidably mounted on the upper limit position of the support plate, and the two adjusting screws on the same side of the support seat are rotatably connected to the two sliding blocks respectively.
[0016] Furthermore, strip slide grooves are provided on the two opposite side walls of the bottom mold, a bidirectional screw is rotatably installed in the strip slide groove, a slider capable of sliding along the strip slide groove is threadedly connected to the opposite threads of the bidirectional screw, a steel pull rod is rotatably installed on the slider, two steel pull rods are rotatably connected to the same connecting shaft away from the slider end, a fixed block is fixedly provided in the middle of the strip slide groove, and the middle part of the bidirectional screw is rotatably installed on the fixed block.
[0017] Furthermore, arc-shaped plates for supporting the connecting shaft are provided on the two opposite side walls of the bottom mold. When the two sliding blocks abut against the side walls in the strip slide groove away from the fixed block, the connecting shaft is arranged in the arc-shaped plate, and the angle between the two steel pull rods is less than 180°.
[0018] Further, in step S3, the method for connecting and fixing the end of the steel tie rod away from the integral cast structure of the rigid column to the tower or steel corridor is: rotating the bidirectional screw to move the two sliders toward the fixed block, thereby driving the two steel tie rods to rotate around the connecting shaft, and moving the connecting shaft away from the arc plate to a position close to the tower or steel corridor, and then fixing the connecting shaft to the tower or steel corridor.
[0019] Further, in step S5, the implementation steps of lowering the steel formwork and steel tie rods as a whole by lifting equipment include: removing the connecting shaft from the tower or steel corridor, rotating the bidirectional screw to move the two sliders away from the fixed block, thereby driving the connecting shaft to move toward the arc plate until the connecting shaft falls on the arc plate, and then demolding the steel formwork and the formed rigid inclined column, and lowering the steel formwork and steel tie rods as a whole by lifting equipment.
[0020] The beneficial effects of the present invention are:
[0021] The present invention forms an integral cast structure of the rigid columns by connecting the rigid column skeleton and the steel formwork, so as to facilitate overall lifting, and does not require setting up a construction platform or a scaffolding support system under high altitude conditions, thereby reducing construction difficulty and construction period.
[0022] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration:
[0024] Figure 1 This is a schematic diagram of the construction of a rigid oblique column according to an embodiment of the present invention;
[0025] Figure 2 It is a structural schematic diagram of the integral casting structure of the rigid column according to an embodiment of the present invention;
[0026] Figure 3 It is a schematic diagram of the state of the steel tie rod extending out of the rigid column integral casting structure according to the embodiment of the present invention;
[0027] Figure 4 It is a schematic diagram of the rigid column skeleton structure of an embodiment of the present invention.
[0028] The markings in the accompanying drawings are as follows: rigid column frame 1, connecting steel plate 101, tower 2, steel corridor 201, steel formwork 3, bottom formwork 301, cover formwork 302, first connecting part 303, second connecting part 304, tension screw 305, strip slide 306, bidirectional screw 307, slider 308, connecting shaft 309, fixed block 310, arc plate 311, rigid column integral casting structure 4, steel tie rod 5, slide rail 6, end support structure 7, support seat 701, screw 702, adjusting screw 703, support plate 704, slider 705. DETAILED DESCRIPTION
[0029] like Figure 1~Figure 4 As shown, the present invention provides a construction method of reinforced concrete rigid oblique columns, wherein the rigid oblique columns are obliquely arranged between a tower 2 and a steel corridor 201 perpendicular to the tower 2, and the construction method comprises the following steps:
[0030] S1: The prefabricated rigid column skeleton 1 is positioned and installed on the connecting steel plate 101, and a plurality of longitudinal bars surrounding the rigid column skeleton 1 are fixedly arranged on the connecting steel plate 101, and the plurality of longitudinal bars are bound and welded by stirrups, and a steel formwork 3 is fixedly arranged on the connecting steel plate 101 to form a rigid column integral casting structure 4; and a steel tie rod 5 is arranged in the middle of the rigid column integral casting structure 4;
[0031] S2: Installing a slide rail 6 at the pre-connection position between the tower 2 and the steel corridor 201 and the integral cast structure 4 of the rigid column, wherein an end support structure 7 for supporting the end of the integral cast structure 4 of the rigid column is installed on the slide rail 6;
[0032] S3: Slide the end support structure 7 along the slide rail 6 to displace the end support structure 7 from the rigid column integral casting structure 4, and then lift the rigid column integral casting structure 4 to a preset position by a lifting device, and then slide the end support structure 7 along the slide rail 6 to make the two end support structures 7 respectively abut against the two ends of the rigid column integral casting structure 4 to support the rigid column integral casting structure 4, and then respectively connect and fix the two ends of the rigid column integral casting structure 4 to the tower 2 and the steel corridor 201, and connect and fix the steel tie rod 5 away from the end of the rigid column integral casting structure 4 to the tower 2 or the steel corridor 201;
[0033] S4: pouring concrete into the rigid column integral casting structure 4 to form a rigid oblique column. During the pouring process, the deformation of the rigid column integral casting structure 4 is regulated by adjusting the steel tie rod 5;
[0034] S5: After the rigid oblique column is formed, the steel formwork 3 is disassembled and the steel formwork 3 and the steel tie rod 5 are lowered as a whole by a lifting device.
[0035] In this scheme, steps S1 and S2 may not be performed separately in the above order. During the pouring process, the lifting equipment is connected to the integral pouring structure 4 of the rigid column to increase the supporting force and ensure the construction safety. In step S3, before the integral pouring structure 4 of the rigid column is lifted, the integral pouring structure 4 of the rigid column is misaligned with the end support structure 7 to prevent the integral pouring structure 4 of the rigid column from interfering with the end support structure 7 during the lifting process. After the integral pouring structure 4 of the rigid column is lifted into place, the end support structure 7 is slid to support the rigid column. The column integral casting structure 4 plays a pre-supporting role to ensure the stability during the process of connecting and fixing the rigid column integral casting structure 4 with the tower 2 or the steel corridor 201; and by arranging a steel tie rod 5 in the middle of the rigid column integral casting structure 4, it is convenient to control the deformation of the rigid column integral casting structure 4 during the casting process; by connecting the rigid column skeleton 1 and the steel formwork 3 to form the rigid column integral casting structure 4, it is convenient to lift the whole, and there is no need to set up a construction platform or scaffolding support system under high altitude conditions, which reduces the construction difficulty and construction period.
[0036] In one embodiment of the present invention, the steel formwork 3 includes: a bottom mold 301 arranged in a U shape and a cover mold 302 capable of closing the bottom mold 301, a plurality of first connection parts 303 are arranged on the opposite side walls of the bottom mold 301, and a plurality of second connection parts 304 corresponding to the first connection parts 303 are arranged on the cover mold 302, and the first connection parts 303 and the second connection parts 304 are threadedly connected and fixed by tension screws 305 to connect and fix the cover mold 302 to the bottom mold 301.
[0037] In this solution, after pouring is completed, when the concrete strength reaches 70% of the preset strength, the cover formwork 302 is removed by rotating the tension screw 305, and maintenance operations are performed until the concrete strength reaches 100% of the preset strength. After that, the bottom formwork 301 is demolded, and the steel formwork 3 is lowered as a whole by lifting equipment.
[0038] In one embodiment of the present invention, the end support structure 7 includes: a support seat 701 slidably mounted on a slide rail 6, a screw 702 rotatably mounted on the slide rail 6, the screw 702 being threadedly connected to the support seat 701, rotating the screw 702 can make the support seat 701 slide along the slide rail 6, the support seat 701 is connected to a support plate 704 capable of cooperating with the end of the rigid column integral casting structure 4 through an adjusting screw 703, wherein both ends of the support seat 701 extending outside the tower 2 or the steel corridor 201 are threadedly connected with two adjusting screws 703, the two adjusting screws 703 are arranged along the sliding direction of the support seat 701, and two sliders 705 are slidably mounted on the support plate 704 for upper limit movement, and the two adjusting screws 703 on the same side of the support seat 701 are rotatably connected to the two sliders 705 respectively.
[0039] In the present solution, by arranging two adjusting screws 703 at both ends of the support seat 701, the supporting force of the support seat 701 on the support plate 704 can be guaranteed, and by synchronously rotating the two adjusting screws 703 on the same side of the support seat 701, the height of the support plate 704 can be adjusted, and by rotating the two adjusting screws 703 on the same side of the support seat 701 separately, the inclination of the support plate 704 can be adjusted, so that the support plate 704 cooperates with the inclined surface of the integral casting structure 4 of the rigid column.
[0040] In one embodiment of the present invention, a strip slide groove 306 is provided on both side walls opposite to each other of the bottom mold 301, a bidirectional screw 307 is rotatably installed in the strip slide groove 306, and a slider 308 capable of sliding along the strip slide groove 306 is threadedly connected on the opposite threads of the bidirectional screw 307, and a steel tie rod 5 is rotatably installed on the slider 308, and the two steel tie rods 5 are rotatably connected to the same connecting shaft 309 at the ends away from the slider 308, wherein a fixed block 310 is fixedly provided in the middle of the strip slide groove 306, and the middle part of the bidirectional screw 307 is rotatably installed on the fixed block 310, and the fixed block 310 is provided to ensure the support stability of the bidirectional screw 307.
[0041] In this solution, before lifting the steel formwork 3, the two sliders 308 are respectively located on the side of the strip slide 306 away from the fixed block 310, so that the two steel tie rods 5 do not extend out of the steel formwork 3, so as to facilitate the overall lifting of the steel formwork 3; after the steel formwork 3 is lifted into place, the two-way screw 307 is rotated to move the two sliders 308 toward the fixed block 310, so that the two steel tie rods 5 rotate around the connecting shaft 309, and the connecting shaft 309 moves to the outside of the steel formwork 3 until the connecting shaft 309 moves to the tower 2 or the steel corridor 201, and the connecting shaft 309 is fixed to the tower 2 or the steel corridor 201 to complete the installation of the steel tie rod 5, avoiding the need to set up a separate lifting mechanism to lift the steel tie rod 5 to a preset position and then connect and fix it to the tower 2 or the steel corridor 201.
[0042] In one embodiment of the present invention, arc-shaped plates 311 for supporting the connecting shaft 309 are provided on the opposite side walls of the bottom mold 301. When the two sliding blocks 308 abut against the side walls of the strip slide groove 306 away from the fixed block 310, the connecting shaft 309 is located in the arc-shaped plate 311, and the angle between the two steel tie rods 5 is less than 180°.
[0043] In the present solution, an arc plate 311 is provided to provide support for the connecting shaft 309 during the lifting process, and the arc design of the arc plate 311 can limit the connecting shaft 309 to ensure the stability of the steel tie rod 5 during lifting, and at this time the angle between the two steel tie rods 5 is less than 180°, so that when the bidirectional screw 307 is rotated, the two steel tie rods 5 can rotate around the connecting shaft 309, and the connecting shaft 309 can move away from the arc plate 311.
[0044] In one embodiment of the present invention, in step S3, the method for connecting and fixing the end of the steel tie rod 5 away from the integral cast structure of the rigid column to the tower or the steel corridor is as follows: rotating the bidirectional screw 307 to move the two sliders 308 toward the fixed block 310, thereby driving the two steel tie rods 5 to rotate around the connecting shaft 309, and when the connecting shaft 309 moves away from the arc plate 311 to a position close to the tower 2 or the steel corridor 201, the connecting shaft 309 is fixedly connected to the tower 2 or the steel corridor 201;
[0045] In step S5, the implementation steps of lowering the steel formwork 3 and the steel tie rod 5 as a whole by lifting equipment include: removing the connecting shaft 309 from the tower 2 or the steel corridor 201, rotating the bidirectional screw 307 to move the two sliders 308 away from the fixed block 310, thereby driving the connecting shaft 309 to move toward the arc plate 311 until the connecting shaft 309 falls on the arc plate 311, and then demolding the steel formwork 3 and the formed rigid inclined column, and lowering the steel formwork 3 and the steel tie rod 5 as a whole by lifting equipment.
[0046] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.
Claims
1. A method for constructing reinforced concrete rigid oblique columns, which is used to obliquely set rigid oblique columns between a tower and a steel corridor perpendicular to the tower, characterized in that: The following steps are involved: S1: The prefabricated rigid column skeleton is positioned and installed on the connecting steel plate, and a plurality of longitudinal reinforcements surrounding the rigid column skeleton are fixedly arranged on the connecting steel plate. After the plurality of longitudinal reinforcements are tied and welded through stirrups, a steel formwork is fixedly arranged on the connecting steel plate to form an integral cast structure of the rigid column; wherein a steel tie rod is arranged in the middle of the steel formwork; S2: Installing a slide rail at the pre-connection position between the tower and the steel corridor and the integral cast structure of the rigid column, wherein the slide rail is provided with an end support structure for supporting the end of the integral cast structure of the rigid column; S3: Slide the end support structure along the slide rail to displace the end support structure and the rigid column integral casting structure, then lift the rigid column integral casting structure to a preset position by a lifting device, slide the end support structure along the slide rail to make the two end support structures respectively abut against the two ends of the rigid column integral casting structure, then connect and fix the two ends of the rigid column integral casting structure to the tower and the steel corridor respectively, and connect and fix the steel tie rod away from the rigid column integral casting structure end to the tower or the steel corridor; S4: pouring concrete into the rigid column integral casting structure to form a rigid oblique column. During the pouring process, the deformation of the rigid column integral casting structure is regulated by adjusting the steel tie rods. S5: After the rigid diagonal columns are formed, the steel formwork is dismantled and the steel tie rods are separated from the tower or steel corridor, and then the steel formwork and steel tie rods are lowered as a whole through the lifting equipment.
2. The construction method of reinforced concrete rigid oblique column according to claim 1, characterized in that: The steel formwork includes: a bottom formwork arranged in a U shape and a cover formwork capable of closing the bottom formwork, a plurality of first connection parts are arranged on opposite side walls of the bottom formwork, a plurality of second connection parts corresponding one to one to the first connection parts are arranged on the cover formwork, and the first connection parts and the second connection parts are threadedly connected and fixed by tension screws so that the cover formwork is connected and fixed to the bottom formwork.
3. The construction method of reinforced concrete rigid oblique column according to claim 2, characterized in that: In step S5, the process of disassembling the steel formwork includes: A1: When the concrete strength reaches 70% of the preset strength, the cover formwork is removed by turning the tension screws and maintenance operations are carried out; A2: When the concrete strength reaches 100% of the preset strength, the bottom formwork is demoulded, the steel tie rods are separated from the tower or steel corridor, and the steel formwork and steel tie rods are lowered as a whole through lifting equipment.
4. The construction method of reinforced concrete rigid oblique column according to claim 2, characterized in that: The end support structure includes: a support seat slidably mounted on a slide rail, a screw rod rotatably mounted on the slide rail, the screw rod being threadedly connected to the support seat, and rotating the screw rod can make the support seat slide along the slide rail, and the support seat is connected to a support plate capable of cooperating with the end of the integral casting structure of the rigid column through an adjusting screw, wherein both ends of the support seat extending outside the tower or the steel corridor are threadedly connected with two adjusting screws, and the two adjusting screws are arranged along the sliding direction of the support seat, and two sliding blocks are slidably mounted on the support plate for upper limit positioning, and the two adjusting screws on the same side of the support seat are rotatably connected to the two sliding blocks respectively.
5. The construction method of reinforced concrete rigid oblique column according to claim 4, characterized in that: The two opposite side walls of the bottom mold are provided with strip slide grooves, a bidirectional screw is rotatably installed in the strip slide groove, a slider that can slide along the strip slide groove is threadedly connected to the opposite threads of the bidirectional screw, a steel pull rod is rotatably installed on the slider, two steel pull rods are rotatably connected to the same connecting shaft away from the slider end, a fixed block is fixedly arranged in the middle of the strip slide groove, and the middle part of the bidirectional screw is rotatably installed on the fixed block.
6. The construction method of reinforced concrete rigid oblique column according to claim 5, characterized in that: The two opposite side walls of the bottom mold are each provided with an arc-shaped plate for supporting the connecting shaft. When the two sliding blocks abut against the side walls in the strip slide groove away from the fixed block, the connecting shaft is arranged in the arc-shaped plate, and the angle between the two steel pull rods is less than 180°.
7. The construction method of reinforced concrete rigid oblique column according to claim 6, characterized in that: In step S3, the method for connecting and fixing the end of the steel tie rod away from the integral cast structure of the rigid column to the tower or steel corridor is: rotating the bidirectional screw to move the two sliders toward the fixed block, thereby driving the two steel tie rods to rotate around the connecting shaft, and moving the connecting shaft away from the curved plate to a position close to the tower or steel corridor, and then fixing the connecting shaft to the tower or steel corridor.
8. The construction method of reinforced concrete rigid oblique column according to claim 6, characterized in that: In step S5, the implementation steps of lowering the steel formwork and steel tie rods as a whole by lifting equipment include: removing the connecting shaft from the tower or steel corridor, rotating the two-way screw to move the two sliders away from the fixed block, thereby driving the connecting shaft to move toward the arc plate until the connecting shaft falls on the arc plate, and then demolding the steel formwork and the formed rigid inclined column, and lowering the steel formwork and steel tie rods as a whole by lifting equipment.