A method for manufacturing and hoisting underground continuous wall steel cage

Through BIM technology and Revit software, the problems of low precision and high safety risks in the production and hoisting of underground diaphragm wall steel cages were solved, and a high-precision, visualized construction process was achieved to ensure quality and safety.

CN112487541BActive Publication Date: 2024-10-18CHINA CONSTR FIRST DIV GROUP CONSTR & DEV
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202011492931.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-17
Publication Date
2024-10-18
Estimated Expiration
2040-12-17

AI Technical Summary

Technical Problem

The traditional underground diaphragm wall steel cage manufacturing and hoisting methods have problems such as low accuracy and high safety risks. The lack of effective theoretical calculation support and intuitive explanation makes it difficult to control quality and safety.

Method used

Use BIM technology combined with Revit software to establish a three-dimensional site layout plan and steel cage model, conduct visual communication and acceptance, calculate the steel cage weight and hoisting load, select hoisting machinery and slings, and conduct dynamic simulation and construction optimization.

Benefits of technology

It improves construction accuracy and safety, provides clear and intuitive construction guidance, ensures reliable quality and safety and controllability, and reduces the disadvantages of material waste and reliance on experience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112487541B_ABST
    Figure CN112487541B_ABST
Patent Text Reader

Abstract

A method for manufacturing and hoisting a steel cage of an underground continuous wall, S1, establishing a three-dimensional site plan in Revit software to form a project BIM model; S2, creating a steel cage to make a fetal membrane frame in the project BIM model; S3, gradually establishing a three-dimensional model of the steel cage in Revit software, using the model to visualize the steel cage processing and accept the steel cage; S4, using Revit software to calculate the weight G of the steel cage; S5, performing steel cage hoisting calculation according to the size and weight of the steel cage; S6, dynamically simulating and visually explaining the steel cage hoisting process; S7, summarizing and optimizing the construction process after the construction is completed. The present invention combines BIM technology with the manufacturing and hoisting construction of the steel cage of an underground continuous wall, so that the entire construction process has a high degree of visualization, is clear and intuitive, and is easy to check and predict, which is conducive to improving the construction accuracy and quality, and uses BIM technology for three-dimensional visualization explanation and acceptance, so that workers can more easily understand and master the construction process, and the work efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a method for manufacturing and hoisting a steel cage for an underground continuous wall. Background Art

[0002] The underground continuous wall is a foundation pit retaining structure that is increasingly widely used. It is a reinforced concrete structure that requires the production and hoisting of a steel cage before pouring concrete. The steel cage of the underground continuous wall is often lowered after the ground continuous wall is grooved, and there are a large number of embedded parts, so the production accuracy of the steel cage is required to be high; in addition, the underground continuous wall steel cage is large in size and weight, which makes it difficult to hoist and has high safety risks.

[0003] Traditional underground continuous wall steel cages are often manufactured and processed based on two-dimensional construction drawings, which makes it difficult to find spatial conflicts in the drawings and ensure the accuracy of steel cage processing; in the installation of underground continuous wall steel cages, they are often based on construction experience, lack effective theoretical calculation support, lack certain guidance when explaining to workers, and are not intuitive enough. Therefore, the traditional underground continuous wall steel cage manufacturing and installation construction methods have certain hidden dangers in terms of quality and safety control. Summary of the invention

[0004] The purpose of the present invention is to provide a method for the production and hoisting construction of an underground continuous wall steel cage. The method combines BIM technology with the production and hoisting construction of an underground continuous wall steel cage, and provides a reliable theoretical calculation basis. It has the advantages of high construction accuracy, clear and intuitive, high degree of three-dimensionalization and visualization, reliable quality, and safe and controllable.

[0005] To achieve the above object, the present invention adopts the following technical solution:

[0006] A method for manufacturing and hoisting a steel cage for an underground continuous wall, characterized in that it comprises the following steps:

[0007] S1, create a three-dimensional site layout in Revit software to form a project BIM model;

[0008] S2, create a steel cage in the project BIM model to make a fetal membrane frame to guide on-site construction and acceptance;

[0009] S3, gradually build a three-dimensional model of the steel cage in Revit software, and use the model to visualize the steel cage processing and steel cage acceptance;

[0010] S4, calculate the weight G of the steel cage using Revit software;

[0011] S5, calculate the lifting of the steel cage according to its size and weight;

[0012] Specifically include:

[0013] S51, according to the weight G of the steel cage obtained in step S4, the additional load weight of the hook and the sling is G', then the total hoisting weight G 总 =G+G'; Select the lifting machinery according to the total lifting weight Gtotal. For the main crane in the steel cage lifting operation, the most unfavorable working condition is that the main crane walks alone with load after the steel cage is vertical. The main crane lifting safety factor is K 主 , then the main crane selection lifting capacity [F 主 ] Reach the calculated lifting capacity of the main crane F 主 , that is, satisfying [F 主 ]>F 主 , where F 主 =G 总 / K 主 ;

[0014] The auxiliary crane bears 70%G load under the most unfavorable working condition 总 , the auxiliary crane lifting safety factor is K 副 , then the auxiliary crane selection lifting capacity [F 副 ]To achieve the auxiliary crane calculated lifting capacity K 副 , that is, satisfying [F 副 ]>F 副 , where F 副 =70%G 总 / K 副 ;

[0015] The maximum allowable lifting height [H] of the main crane reaches the calculated lifting height H, that is, [H]>H. Among them, the calculated lifting height of the steel cage H=b+h1+h2+h3+h4+h5, where b is the distance from the center of the hook to the arm end, h1 is the height of the wire rope above the shoulder pole, h2 is the height of the shoulder pole, h3 is the height of the wire rope below the shoulder pole, h4 is the length of the steel cage, and h5 is the height of the steel cage from the ground. Then, by consulting the crawler crane manual, select the maximum allowable lifting height [H]>H to meet the requirements;

[0016] S52, determine the position of the lifting point according to the length of the steel cage. The determination of the lifting point position is a key step in the lifting process. According to the law of bending moment equilibrium, that is, -M=+M, where +M is the positive bending moment value of the steel cage; -M is the negative bending moment value of the steel cage. Since the bending moment deformation of the underground continuous wall steel cage is the smallest when the positive and negative bending moments are equal, the spacing between the lifting points is the most reasonable when the lifting point position of the steel cage is determined by the principle of equal positive and negative bending moments.

[0017] S53, calculate the force of the sling according to the weight G of the steel cage, the arrangement of the lifting points and the principle of static balance, and select the sling;

[0018] For the main crane, the most unfavorable state of the sling force is that the main crane bears the weight of the steel cage alone after the steel cage is vertical. n steel wire ropes are set under the shoulder pole for load distribution. Therefore, the force of a single steel wire rope under the shoulder pole of the main crane is F s1 =G 总 / 2n, where G 总 —Total hoisting weight; n—number of steel wire ropes under the shoulder pole;

[0019] For the auxiliary crane, the force on the lifting sling is the most unfavorable state when the two cranes are hoisting the steel cage horizontally. According to the static equilibrium condition, we get: G 总 =F 合 , G 总 —Total lifting weight; F 合 —Calculated value of vertical resultant force;

[0020] Take the moment at one end of the steel cage, and according to the moment balance, we get: the calculated value of the resultant moment Ma=0;

[0021] Through calculation, it can be concluded that the maximum force on a single wire rope of the auxiliary crane is F S3 ;

[0022] Based on the principle of static balance, the forces on all slings such as wire ropes and pulleys can be obtained;

[0023] S54, combined with the weight of the steel cage and the crane load, the foundation bearing capacity is rechecked and calculated considering the most unfavorable working conditions. If it is not satisfied, corresponding measures need to be taken;

[0024] S6, dynamic simulation and visual explanation of the steel cage hoisting process;

[0025] S7, after the construction is completed, summarize and optimize the construction process.

[0026] Furthermore, the step S1 specifically includes:

[0027] S11, before modeling, establish a project-level BIM template model, unify elevation and coordinate positioning, and unify component naming rules and management standards;

[0028] S12, when modeling, the electronic drawings in AutoCAD are imported into Revit software through the connection command to ensure that the base points coincide; through the creation of family commands, the partitions and components in the floor plan are generated into three-dimensional models, and the corresponding sizes and materials are assigned to form the project BIM model.

[0029] Furthermore, the step S2 specifically includes:

[0030] S21, in the steel cage production and stacking area in the BIM model, create a steel cage production membrane frame model according to the size and shape of the underground continuous wall steel cage, and extract the location and elevation information of the membrane frame model for on-site construction measurement and positioning;

[0031] S22, after the construction of the on-site steel cage membrane frame is completed, the membrane frame BIM model is used for inspection and acceptance.

[0032] Furthermore, the step S3 specifically includes:

[0033] S31, using the Create Family command in Revit software to generate steel bars, using the Loft command to generate single steel bars with reference to the reinforcement drawing of the steel cage, and using commands such as Array to arrange the steel bars according to the steel bar spacing to form a three-dimensional model of the steel cage;

[0034] S32, importing the steel cage BIM model in the Revit software into the Navisworks software, using the collision and error checking function of the Navisworks software to check whether there is a conflict in the arrangement of the components in the steel cage, and re-optimizing if there is a conflict;

[0035] S33, use the optimized BIM model of the steel cage for visual explanation and guidance of construction. After the steel cage is processed, use the BIM model of the steel cage for on-site inspection and acceptance.

[0036] Furthermore, the step S4 specifically includes, according to the three-dimensional model of the steel cage created in the step S31, automatically counting the volume information of each component through the detailed list in the Revit software, and extracting the steel volume V of the underground continuous wall steel cage through the keyword filtering function, multiplying it by the steel density ρ to obtain the weight G of the steel cage, that is, G=ρV, and the weight G of the steel cage is used as the basis for the calculation of material delivery and steel cage hoisting.

[0037] In addition, step S6 specifically includes: exporting the BIM model in the Revit software into an NWC file, importing it into the NavisWorks software for construction simulation, forming a construction simulation animation of the crane station, lifting, walking, lowering and other processes of the steel cage hoisting construction, and conducting a visual briefing on the steel cage hoisting for the construction personnel.

[0038] More preferably, the step S7 specifically includes, after completing the production and hoisting of the first steel cage, summarizing the experience, improving the BIM model and construction method, and guiding the production and hoisting of subsequent steel cages.

[0039] Compared with the prior art, the present invention has the following characteristics and beneficial effects:

[0040] The present invention combines BIM technology with the production and hoisting construction of underground continuous wall steel cages, making the entire construction process highly visualized, clear and intuitive, and easy to check and predict, which is conducive to improving construction accuracy and quality;

[0041] The present invention uses BIM technology to conduct three-dimensional visual disclosure and acceptance, so that workers can more easily understand and grasp the construction process, and the work efficiency is high;

[0042] The present invention can accurately calculate the weight of the steel cage through the engineering quantity statistics in the BIM model. On the one hand, it can be used as a basis for purchasing steel bars to reduce material waste. On the other hand, it also provides accurate load values ​​for steel cage hoisting calculations.

[0043] The present invention provides a theoretical calculation method for steel cage hoisting, thereby avoiding the drawback of relying on construction experience in traditional construction. The steel cage hoisting construction has a basis to follow and has the advantages of safety and controllability. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 This is a flowchart of the production and hoisting construction method of underground continuous wall steel cage;

[0045] Figure 2 This is a schematic diagram for calculating the lifting height of the steel cage;

[0046] Figure 3 This is a schematic diagram for calculating the lifting points of the steel cage;

[0047] Figure 4 It is a schematic diagram of the arrangement of steel cage lifting points and lifting rigging;

[0048] Figure 5 This is a schematic diagram for calculating the main crane rigging;

[0049] Figure 6 This is a schematic diagram for calculating the auxiliary crane rigging;

[0050] Figure 7 This is a schematic diagram of the construction road structure;

[0051] Figure 8 Schematic diagram of load diffusion. DETAILED DESCRIPTION

[0052] In order to make the technical means, innovative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below.

[0053] The embodiments described herein are specific embodiments of the present invention, which are used to illustrate the concept of the present invention, are illustrative and exemplary, and should not be construed as limiting the embodiments of the present invention and the scope of the present invention. In addition to the embodiments described herein, those skilled in the art can also adopt other obvious technical solutions based on the claims and the contents disclosed in the specification of this application, including technical solutions that adopt any obvious replacement and modification of the embodiments described herein.

[0054] Figure 1The present invention is a flowchart of a preferred embodiment of a method for manufacturing and hoisting a steel cage for an underground continuous wall.

[0055] In this preferred embodiment, a method for manufacturing and hoisting a steel cage for an underground continuous wall comprises the following steps:

[0056] S1, create a three-dimensional site layout in Revit software to form a project BIM model;

[0057] S2, create a steel cage to make a fetal membrane frame in the project BIM model, and guide on-site construction and acceptance;

[0058] S3, gradually build a three-dimensional model of the steel cage in Revit software, and use the model to visualize the steel cage processing and steel cage acceptance;

[0059] S4, calculate the weight G of the steel cage using Revit software;

[0060] S5, calculate the lifting of the steel cage according to its size and weight;

[0061] S6, dynamic simulation and visual explanation of the steel cage hoisting process;

[0062] S7, after the construction is completed, summarize and optimize the construction process.

[0063] Step S1 specifically includes:

[0064] S11, before modeling, establish a project-level BIM template model, unify elevations, coordinate positioning, etc., unify component naming rules and management standards;

[0065] S12, when modeling, the electronic drawings in AutoCAD are imported into Revit software through the connection command to ensure that the base points coincide; through the creation of family commands, the partitions and components in the floor plan are generated into three-dimensional models, and the corresponding sizes and materials are assigned to form the project BIM model.

[0066] Step S2 specifically includes:

[0067] S21, in the steel cage production and stacking area in the BIM model, create a steel cage production membrane frame model according to the size and shape of the underground continuous wall steel cage, and extract the location and elevation information of the membrane frame model for on-site construction measurement and positioning;

[0068] S22, after the construction of the on-site steel cage membrane frame is completed, the membrane frame BIM model is used for inspection and acceptance.

[0069] Step S3 specifically includes:

[0070] S31, using the Create Family command in Revit software to generate steel bars, using the Loft command to generate single steel bars with reference to the reinforcement drawing of the steel cage, and using commands such as Array to arrange the steel bars according to the steel bar spacing to form a three-dimensional model of the steel cage;

[0071] S32, importing the steel cage BIM model in the Revit software into the Navisworks software, using the collision and error checking function of the Navisworks software to check whether there is a conflict in the arrangement of the components in the steel cage, and re-optimizing if there is a conflict;

[0072] S33, use the optimized BIM model of the steel cage for visual explanation and construction guidance. After the steel cage is processed, use the model for on-site inspection and acceptance.

[0073] Step S4 specifically includes: using the Revit software's list, the volume of the underground continuous wall steel cage can be extracted by filtering keywords, and then multiplied by the steel density to obtain the weight of the steel cage, which is used as the basis for material delivery and the basis for calculation of steel cage hoisting. After the model is created, it comes with volume and other information. Through the list in the Revit software, the volume information of each component can be automatically counted. By filtering keywords, the volume of the steel cage steel bars is obtained to be V=13.2 cubic meters.

[0074] In this example, the weight of the steel cage is: G = ρV = 13.2 * 7.85 = 103.6t

[0075] Step S5 specifically includes but is not limited to the following contents: crane lifting capacity verification, lifting point location determination, sling selection, foundation bearing capacity verification, etc., specifically:

[0076] S51, select the lifting machinery according to the weight of the steel cage and the additional load weight obtained in the Revit software. In addition to the lifting capacity of the crane, the lifting height should also be checked;

[0077] The deadweight of the steel cage obtained from step S41 is: G = 103.6t. Considering the additional load weight of the hook, slings, etc. is G' = 15t, the total hoisting weight is: G 总 =G+G'=103.62+15=118.62t.

[0078] For the main crane in the steel cage lifting operation, the most unfavorable working condition is that the main crane walks alone with load after the steel cage is vertical. The lifting safety factor is 0.7, so the lifting capacity of the main crane is required to be at least: F 主 =G 总 / K 主 =118.62 / 0.7=169.5t.

[0079] In this example, the main crane is a ZCC5200S crawler crane, and the selected working conditions are: arm length 84m, rotation radius 16m, and equipped with 80t super-lift counterweight. By consulting the technical performance manual of this model of crawler crane, the allowable lifting capacity under this working condition is 176t, that is, [F 主 ]=176t>F 主 =169.5t, the lifting capacity of the main crane meets the requirements.

[0080] For the auxiliary crane in the steel cage lifting operation, it only bears the load during the horizontal lifting and turning process of the steel cage. The load borne by the auxiliary crane generally does not exceed 70% of the total lifting weight. Therefore, the load borne by the auxiliary crane under the most unfavorable working condition is: 70%G 总 =0.7*118.62=83.03t, the auxiliary crane lifting safety factor is 0.8, then the auxiliary crane lifting capacity is required to be at least: F 副 =70%G 总 / K 副 =83.03 / 0.8=103.8t.

[0081] In this example, the auxiliary crane adopts XGC260 crawler crane, and the selected working condition is: the arm length is 51m, the main arm working condition of the swing radius is 12m. By consulting the technical performance manual of this model crawler crane, the allowable lifting capacity under this working condition is 109t, that is, [F 副 ]=109t>F 副 =103.8t, the lifting capacity of the auxiliary crane meets the requirements.

[0082] Figure 2 The following is a schematic diagram for calculating the hoisting height of the steel cage. Among them, the distance between the center of the hook and the arm end is b = 6.5m, the height of the wire rope above the shoulder pole is h1 = 2.8m, the height of the shoulder pole is h2 = 0.8m, the height of the wire rope below the shoulder pole is h3 = 5m, the length of the steel cage is h4 = 59.5m, and the height of the steel cage from the ground is h5 = 0.5m. The hoisting height of the steel cage needs to be at least: H = b + h1 + h2 + h3 + h4 + h5 = 6.5 + 2.8 + 0.8 + 5 + 59.5 + 0.5 = 75.1m. By consulting the crawler crane manual, when the arm length is 84m and the slewing radius is 16m, the maximum allowable lifting height [H] = 84m>H = 75.1m, which meets the requirements.

[0083] S52, according to the length of the steel cage, determine the lifting point position of the steel cage by the principle of equal positive and negative bending moments;

[0084] Figure 3 The figure is a schematic diagram of the calculation of the steel cage lifting point. The determination of the lifting point position is a key step in the lifting process. According to the law of moment equilibrium, the bending moment deformation of the underground continuous wall steel cage is the smallest when the positive and negative moments are equal, so the spacing between the lifting points is the most reasonable at this time. In this example, the total length of the steel cage is L=59.5m.

[0085] Let -M=+M (+M—positive bending moment of steel cage; -M—negative bending moment of steel cage); where +M=1 / 2ql1 2 , -M=1 / 8ql2 2 -1 / 2ql1 2

[0086] but,

[0087] Again: 2l1+5l2=L=59.5m

[0088] Calculated: l1=3.75m, l2=10.4m

[0089] Combined with the arrangement of steel bars in the steel cage, the first row of lifting points is 1m away from the cage head, and the spacing between the remaining rows of lifting points is 11m, which can meet the actual construction needs and is close to the theoretical calculation results. It is the optimal solution. The arrangement of lifting points and corresponding slings is referenced Figure 4 shown.

[0090] S53, calculate the force of the sling according to the weight of the steel cage, the arrangement of the lifting points and the principle of static balance, and select the sling;

[0091] For the main crane, the most unfavorable state of the sling force is that the main crane bears the weight of the steel cage alone after the steel cage is vertical. Figure 5 As shown. Four steel wire ropes are set at each row of lifting points for load distribution, so the force on a single steel wire rope under the shoulder pole of the main crane is: F s1 =G 总 / 8=118.62 / 8=14.83t

[0092] For the auxiliary crane, the sling force is in the most unfavorable state when the double cranes are hoisting the steel cage horizontally. Figure 6 As shown. According to the static equilibrium condition:

[0093] Vertical force of steel cage: G 总 =F 合 =2×Sin48°×F1+2×Sin48°×F3=118.62t

[0094] in,

[0095] Sin48°×F1=2×Sin48°×F2,

[0096] Sin48°×F3=2×Sin48°×F4

[0097] Take the moment from the bridle, according to the moment balance Ma=0, that is:

[0098] 1×Sin48°×F1+12×Sin48°×F2+23×Sin48°×F2+34×Sin48°×F3+45×Sin48°×F4+56×Sin48°×F4=G 总 ×L / 2=118.62×59.5 / 2

[0099] Combining the above formulas, we get: F1=30.2t; F2=15.1t; F3=49.6t; F4=24.8t

[0100] Then, the maximum force on a single wire rope of the auxiliary crane is: FS3=F3 / 4=12.4t; FS4=F4 / 4=6.2t

[0101] Similarly, according to the principle of static balance, the forces on all slings such as wire ropes and pulleys can be obtained. Figure 4 According to the stress of the sling, the sling selection in this example is as shown in Table 1:

[0102] Table 1 Sling selection table in this embodiment

[0103]

[0104] S54, considering the weight of the steel cage and the crane load, the foundation bearing capacity is re-checked and verified considering the most unfavorable working condition. If it is not satisfied, corresponding measures need to be taken.

[0105] In this example, the total hoisting weight is 118.62t, the deadweight load of the main crane is about 410t, and the maximum ground load Ftotal = 528.62t. To ensure uniform distribution of the load, a 12*2.5m thick steel plate or roadbed plate is set under the crane crawler. In the most unfavorable case, all the loads are transferred to the construction road surface through the steel plate or roadbed plate under a single crawler.

[0106] Road structure reference Figure 7 As shown, from top to bottom there are 35 cm thick reinforced concrete, 25 cm thick water-stabilizing layer, and 50 cm thick gravel cushion layer.

[0107] The maximum load that the road surface can bear is Pmax=F 总 / S=528.62 / (12*2.5)=176kPa, which is much smaller than the compressive strength of concrete. It is only necessary to calculate whether the bearing capacity of the roadbed meets the requirements after the load is diffused to the roadbed.

[0108] The load diffusion angle in concrete is 45°, and the diffusion angle in the water-stable layer and crushed stone layer is 25°. Figure 8As shown. The width of load diffusion is: a=35*tan45°+(25+50)*tan25°=70cm=0.7m, and the stress area of ​​the roadbed is: S'=(12+2a)*(2.5+2a)=(12+0.7*2)*(2.5+0.7*2)=52.26m 2

[0109] Therefore, the load borne by the roadbed is: P=Pmax*S / S'=176*(12*2.5) / 52.26=101kPa. According to the geological survey report, the bearing capacity of the foundation is fa=120kPa>P=101kPa, which meets the requirements.

[0110] In step S5, all calculations for the lifting of the steel cage can meet the requirements and can be used for actual construction; if the verification in other examples fails, the lifting selection calculation should be performed again until all verifications meet the requirements.

[0111] Step S6 specifically includes:

[0112] S61, export the BIM model in Revit software into NWC file, import it into NavisWorks software for construction simulation, form a construction simulation animation of the crane position, lifting, walking, lowering and other processes of the steel cage hoisting construction, and conduct visual explanation of the steel cage hoisting to the construction personnel.

[0113] Step S7 specifically includes:

[0114] S71, after completing the production and hoisting of the first steel cage, summarize the experience, improve the BIM model and construction methods, and guide the subsequent production and hoisting of steel cages.

[0115] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for manufacturing and hoisting a steel cage for an underground continuous wall, characterized in that: The following steps are involved: S1, create a three-dimensional site layout in Revit software to form a project BIM model; Step S1 specifically includes: S11, before modeling, establish a project-level BIM template model, unify elevation and coordinate positioning, and unify component naming rules and management standards; S12, when modeling, the electronic drawings in AutoCAD are imported into Revit software through the connection command to ensure that the base points coincide; through the creation family command, the partitions and components in the floor plan are generated into three-dimensional models, and the corresponding sizes and materials are assigned to form the project BIM model; S2, creating a steel cage in the project BIM model to make a fetal membrane frame, which is used to guide on-site construction and acceptance; step S2 specifically includes: S21, in the steel cage production and stacking area in the BIM model, create a steel cage production membrane frame model according to the size and shape of the underground continuous wall steel cage, and extract the location and elevation information of the membrane frame model for on-site construction measurement and positioning; S22, after the construction of the on-site steel cage membrane frame is completed, the membrane frame BIM model is used for inspection and acceptance; S3, gradually building a three-dimensional model of the steel cage in Revit software, and using the model to visualize the steel cage processing and steel cage acceptance; step S3 specifically includes: S31, using the Create Family command in Revit software to generate steel bars, using the Loft command to generate single steel bars with reference to the reinforcement drawing of the steel cage, using the Array command to arrange the steel bars according to the steel bar spacing, and forming a three-dimensional model of the steel cage; S32, importing the steel cage BIM model in the Revit software into the Navisworks software, using the collision and error checking function of the Navisworks software to check whether there is a conflict in the arrangement of the components in the steel cage, and re-optimizing if there is a conflict; S33, use the optimized steel cage BIM model to conduct visual disclosure and guide construction. After the steel cage is processed, use the steel cage BIM model to conduct on-site inspection and acceptance; S4, calculate the weight G of the steel cage using Revit software; Step S4 specifically includes, according to the three-dimensional model of the steel cage created in step S31, automatically counting the volume information of each component through the detailed list in the Revit software, and extracting the steel volume V of the underground continuous wall steel cage through the keyword filtering function, multiplying it by the steel density ρ to obtain the weight G of the steel cage, that is, G=ρV, and the weight G of the steel cage is used as the basis for calculating the material delivery and the steel cage hoisting; S5, calculate the lifting of the steel cage according to its size and weight; Specifically include: S51, according to the weight G of the steel cage obtained in step S4, the additional load weight of the hook and the sling is G', then the total hoisting weight G 总 =G+G'; Select the lifting machinery according to the total lifting weight Gtotal. For the main crane in the steel cage lifting operation, the most unfavorable working condition is that the main crane walks alone with load after the steel cage is vertical. The main crane lifting safety factor is K 主 , then the main crane selection lifting capacity [F 主 ] Reach the calculated lifting capacity of the main crane F 主 , that is, satisfying [F 主 ]>F 主 , where F 主 =G 总 / K 主 ; The auxiliary crane bears 70%G load under the most unfavorable working condition 总 , the auxiliary crane lifting safety factor is K 副 , then the auxiliary crane selection lifting capacity [F 副 ]To achieve the auxiliary crane calculated lifting capacity K 副 , that is, satisfying [F 副 ]>F 副 , where F 副 =70%G 总 / K 副 ; The maximum allowable lifting height [H] of the main crane reaches the calculated lifting height H, that is, [H]>H; Among them, the lifting height of the steel cage is calculated as H=b+h1+h2+h3+h4+h5, where b is the distance between the center of the hook and the arm end, h1 is the height of the wire rope above the shoulder pole, h2 is the height of the shoulder pole, h3 is the height of the wire rope below the shoulder pole, h4 is the length of the steel cage, and h5 is the height of the steel cage from the ground. Then, by consulting the crawler crane manual, select the maximum allowable lifting height [H]>H to meet the requirements; S52, determine the position of the lifting point according to the length of the steel cage. The determination of the lifting point position is a key step in the lifting process. According to the law of bending moment equilibrium, that is, -M=+M, where +M is the positive bending moment value of the steel cage; -M is the negative bending moment value of the steel cage. Since the bending moment deformation of the underground continuous wall steel cage is the smallest when the positive and negative bending moments are equal, the spacing between the lifting points is the most reasonable when the lifting point position of the steel cage is determined by the principle of equal positive and negative bending moments. S53, calculate the force of the sling according to the weight G of the steel cage, the arrangement of the lifting points and the principle of static balance, and select the sling; For the main crane, the most unfavorable state of the sling force is that the main crane bears the weight of the steel cage alone after the steel cage is vertical. n steel wire ropes are set under the shoulder pole for load distribution. Therefore, the force of a single steel wire rope under the shoulder pole of the main crane is F s1 =G 总 / 2n, where G 总 —Total hoisting weight; n—number of steel wire ropes under the shoulder pole; For the auxiliary crane, the force on the lifting sling is the most unfavorable state when the two cranes are hoisting the steel cage horizontally. According to the static equilibrium condition, we get: G 总 =F 合 , G 总 —Total lifting weight; F 合 —Calculated value of vertical resultant force; Take the moment at one end of the steel cage, and according to the moment balance, we get: the calculated value of the resultant moment Ma=0; Through calculation, it can be concluded that the maximum force on a single wire rope of the auxiliary crane is F S3 ; Based on the principle of static balance, the forces on wire ropes, pulleys and all slings can be obtained; S54, combined with the weight of the steel cage and the crane load, the foundation bearing capacity is rechecked and calculated considering the most unfavorable working conditions. If it is not satisfied, corresponding measures need to be taken; S6, dynamically simulate and visualize the steel cage hoisting process; step S6 specifically includes: exporting the BIM model in the Revit software to an NWC file, importing it into the NavisWorks software for construction simulation, forming a construction simulation animation of the crane station, hoisting, walking, and lowering process of the steel cage hoisting construction, and visually explaining the steel cage hoisting to the construction personnel; S7, after the construction is completed, summarize and optimize the construction process.

2. The method for manufacturing and hoisting a steel cage for an underground continuous wall according to claim 1, characterized in that: The step S7 specifically includes, after completing the production and hoisting of the first steel cage, summarizing the experience, improving the BIM model and construction method, and guiding the production and hoisting of subsequent steel cages.

Citation Information

Patent Citations

  • Prefabricated reinforcement cage modular decomposition system and method

    CN106649989A

  • Underground diaphragm wall construction method based on BIM technology

    CN111062081A