A convenient operating platform for installing steel structure skylights
By using interlaced wire ropes and anchoring devices in the construction of the lighting roof, the problems of platform stability and safety in the lighting roof are solved, and convenient installation and efficient construction of the convenient operation platform are achieved, especially suitable for large lower floor heights. steel structure installation.
Patent Information
- Application Number
- CN202110793569.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-07-14
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2041-07-14
AI Technical Summary
In the construction of the lighting roof, due to the high distance from the ground, the existing steel pipe scaffolding is poor in economicality and takes up a large space, which cannot meet the construction requirements and lacks a convenient operating platform.
A convenient operating platform for installation of the lighting roof of the steel structure is designed. By installing the interlaced connection of the main and secondary stressed steel wire ropes in the concrete structure, combining the anchoring device and formwork to ensure the stability and safety of the platform.
Effectively avoid sliding and falling off between the main and secondary stressed wire ropes, ensure the fixity of the formwork, improve construction safety, simplify the installation and disassembly process, save labor, and is suitable for when the lower floor height is large. Steel structure installation.
Smart Images

Figure CN113503013B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of skylight construction, and more particularly to a convenient operating platform for installing a skylight of a steel structure. Background Art
[0002] In building construction, the operating platform is an indispensable temporary setting, which provides a safe and stable working support surface for construction workers. However, in some skylight construction, since the skylight is high from the ground, setting up a steel pipe scaffolding is not only uneconomical, but also occupies a large space and cannot meet the requirements of on-site construction.
[0003] Therefore, it is urgent to design a horizontal operating platform for skylight construction to solve the existing technical problems. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a convenient operating platform for installing a steel structure skylight roof.
[0005] The solution adopted by the present invention to solve the technical problem is:
[0006] A convenient operating platform for installing a steel structure skylight, which is installed in a cavity formed by a concrete structure; it includes a plurality of main stress-bearing steel wire ropes, a plurality of secondary stress-bearing steel wire ropes which are staggeredly connected with the main stress-bearing steel wire ropes and form a steel wire mesh, an anchoring device for connecting the free ends of two adjacent main stress-bearing steel wire ropes or the free ends of two adjacent secondary stress-bearing steel wire ropes, a template installed on the steel wire mesh, and a net installed on the side of the steel wire mesh away from the template; the anchoring device is located on the outside of the concrete structure.
[0007] In some possible implementations, a cross point fixing device is provided at the connection between the primary stress-bearing steel wire rope and the secondary stress-bearing steel wire rope.
[0008] In some possible embodiments, the intersection fixing device includes a mounting plate and a U-shaped hoop mounted on the mounting plate, wherein the end of the U-shaped hoop is screwed to the mounting plate; the U-shaped hoop and the mounting plate form a locking cavity for installing the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope.
[0009] In some possible embodiments, the free end of the main stress-bearing steel wire rope or the free ends of two adjacent secondary stress-bearing steel wire ropes penetrates the concrete structure; the anchoring device includes a connecting rope clamp respectively connected to the two main stress-bearing steel wire ropes or the secondary stress-bearing steel wire ropes, and a rope clamp B for locking each main stress-bearing steel wire rope or the secondary stress-bearing steel wire rope after it is folded in half.
[0010] In some possible embodiments, the anchoring device further comprises a plurality of rubber sleeves installed in the concrete structure and arranged one-to-one with the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope; the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope pass through the corresponding rubber sleeves and are connected to the anchoring device.
[0011] In some possible implementations, the number of the rope clamps B is at least two.
[0012] In some possible implementations, the net is a flame-retardant safety flat net with a diameter of 6 mm and a mesh size of 10 cm.
[0013] In some possible implementations, the bottom of the template is provided with locking slots corresponding to the long direction of the secondary stress-bearing steel wire ropes.
[0014] In some possible implementations, the thickness of the template is 15 mm.
[0015] In some possible implementations, the diameters of the primary stress-bearing steel wire rope and the secondary stress-bearing steel wire rope are 10 mm.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] The present invention effectively realizes the connection between the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope through the intersection fixing device, thereby avoiding the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope from sliding during use, causing unstable template installation and affecting construction safety;
[0018] The present invention realizes the connection between the main force-bearing steel wire rope and the secondary force-bearing steel wire rope and the concrete structure through the anchoring device, thereby avoiding the phenomenon that the main force-bearing steel wire rope and the secondary force-bearing steel wire rope are not firmly connected to the concrete structure and fall off, thereby causing construction safety accidents;
[0019] The present invention effectively fixes the template and the wire mesh by arranging a locking groove at the bottom of the template, and effectively prevents the template from moving on the wire mesh and affecting construction safety.
[0020] The present invention has a simple structure and strong practicality. Compared with setting up a ground scaffolding at the light well location for personnel operation, the convenient operation platform has the advantages of simple and fast installation and disassembly, saving labor, and not affecting the lower decoration construction. It is particularly suitable for installing steel structures when the lower floor height is large. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the top view of the structure of the present invention;
[0022] Figure 2 It is a schematic diagram of the cross-sectional structure of the present invention;
[0023] Figure 3It is a structural schematic diagram of the connection between the intersection fixing device and the primary stress-bearing steel wire rope and the secondary stress-bearing steel wire rope in the present invention;
[0024] Figure 4 It is a schematic diagram of the connection relationship among the anchoring device, the concrete structure, the primary force-bearing steel wire rope, and the secondary force-bearing steel wire rope in the present invention;
[0025] Among them: 1. Wire mesh; 11. Main load-bearing wire rope; 12. Secondary load-bearing wire rope; 13. Mounting plate; 14. U-shaped hoop; 2. Net; 3. Formwork; 4. Anchoring device; 41. Connecting rope clamp; 42. Rope clamp B; 43. Rubber casing; 10. Concrete structure. DETAILED DESCRIPTION
[0026] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral body; it can be directly connected, or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. The "first", "second" and similar words mentioned in this application do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, "one" or "one" and other similar words do not indicate a quantity restriction, but indicate the existence of at least one. In the implementation of this application, "and / or" describes the association relationship of the associated objects, indicating that there can be three relationships, for example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In the description of the embodiments of the present application, unless otherwise specified, the meaning of "multiple" refers to two or more. For example, multiple positioning columns refer to two or more positioning columns. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] The present invention is described in detail below.
[0028] like Figure 1-Figure 4 As shown:
[0029] A convenient operating platform for installing a steel structure skylight roof is installed in a chamber formed by a concrete structure 10; it includes a plurality of main stress-bearing steel wire ropes 11, a plurality of secondary stress-bearing steel wire ropes 12 which are staggeredly connected with the plurality of the main stress-bearing steel wire ropes 11 and form a steel wire mesh 1, an anchoring device 4 for connecting the free ends of two adjacent main stress-bearing steel wire ropes 11 or the free ends of two adjacent secondary stress-bearing steel wire ropes 12, a template 3 installed on the steel wire mesh 1, and a net 2 installed on the side of the steel wire mesh 1 away from the template 3; the anchoring device 4 is located on the outside of the concrete structure 10.
[0030] Preferably, the plurality of main force-bearing steel wire ropes 11 are arranged in parallel and at equal intervals, and are vertically staggered and connected with the plurality of secondary force-bearing steel wire ropes 12, and the plurality of secondary force-bearing steel wire ropes 12 are arranged in parallel and at equal intervals; this will make the force on the wire mesh 1 more uniform; and effectively support the formwork 3 and the construction personnel on the formwork 3, avoiding shaking due to uneven force and affecting construction safety.
[0031] The net 2 is installed at the bottom of the main force-bearing steel wire rope 11 and is connected to the main force-bearing steel wire rope 11. It is mainly used as a protective measure when a high falling object hits during the construction process, and effectively catches the object or construction personnel to prevent them from falling directly.
[0032] In some possible implementations, in order to prevent the main force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12 from sliding during use, the main force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12 are effectively locked;
[0033] A cross point fixing device is provided at the connection between the primary stress-bearing steel wire rope 11 and the secondary stress-bearing steel wire rope 12 .
[0034] In some possible implementations, in order to effectively achieve the locking of the primary force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12;
[0035] like Figure 3 As shown, the intersection fixing device includes a mounting plate 13 and a U-shaped hoop 14 mounted on the mounting plate 13, and the end of the U-shaped hoop 14 is screwed to the mounting plate 13; the U-shaped hoop 14 and the mounting plate 13 form a locking cavity for installing the main force-bearing wire rope 11 and the secondary force-bearing wire rope 12.
[0036] It is installed at the bottom of the main force-bearing steel wire rope 11 and is used to support the main force-bearing steel wire rope 11; the U-shaped steel passes through the mounting plate 13 from top to bottom and is fixedly connected to the mounting plate 13, forming a locking cavity between the two, and the long direction of the secondary force-bearing steel wire rope 12 will pass through the locking cavity;
[0037] Preferably, the free end of the U-shaped hoop 14 is provided with a thread, and the mounting plate 13 is provided with a mounting hole that matches the free end of the U-shaped hoop 14. During installation, the opening of the U-shaped hoop 14 is downward from the top of the secondary stress-bearing wire rope 12 and passes through the mounting hole. When the secondary stress-bearing wire rope 12 abuts against the U-shaped hoop 14, the nut is connected to the thread of the free end of the U-shaped hoop 14, and then the nut is tightened by twisting it;
[0038] Since the secondary stress-bearing steel wire rope 12 is located above the primary stress-bearing steel wire rope 11, and the mounting plate 13 is located below the primary stress-bearing steel wire rope 11, the U-shaped hoop 14 moves downward and applies force to the secondary stress-bearing steel wire rope 12. The primary stress-bearing steel wire rope 11 is located at the bottom of the secondary stress-bearing steel wire rope 12, and will be subjected to the force transmitted by the secondary stress-bearing steel wire rope 12 and abut against the mounting plate 13, thereby achieving locking and effectively preventing sliding;
[0039] In some possible implementations, in order to effectively realize the effective connection between the main force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12 and the concrete structure 10; and effectively avoid the situation that the main force-bearing steel wire rope and the secondary force-bearing steel wire rope 12 are not firmly connected to the concrete structure 10 and fall off;
[0040] like Figure 4 As shown, the free end of the main stress-bearing steel wire rope 11 or the free ends of two adjacent secondary stress-bearing steel wire ropes 12 penetrate the concrete structure 10; the anchoring device 4 includes a connecting rope clamp 41 respectively connected to the two main stress-bearing steel wire ropes 11 or the secondary stress-bearing steel wire ropes 12, and a rope clamp B42 used to lock each main stress-bearing steel wire rope 11 or the secondary stress-bearing steel wire rope 12 after it is folded in half.
[0041] The anchoring device 4 also includes a plurality of rubber sleeves 43 installed on the concrete structure 10 and arranged one-to-one corresponding to the main load-bearing steel wire rope 11 and the secondary load-bearing steel wire rope 12 ; the main load-bearing steel wire rope 11 and the secondary load-bearing steel wire rope 12 pass through the corresponding rubber sleeves 43 and are connected to the anchoring device 4 .
[0042] In order to make the locking of a primary stress-bearing steel wire rope 11 or a secondary stress-bearing steel wire rope 12 more secure, the number of the rope clamps B42 is at least two.
[0043] The connecting rope clamp 41 is an annular component. When in use, after the free ends of the two main force-bearing steel wire ropes 11 or the two secondary force-bearing steel wire ropes 12 pass through the corresponding rubber sleeves 43, the free ends will pass through a common connecting rope clamp 41, and then be folded in half respectively, and the connection between the through-portion and the folded portion of the free end is achieved through the rope clamp B42.
[0044] Preferably, during on-site construction, the main force-bearing steel wire ropes 11 and the secondary force-bearing steel wire ropes 12 can be respectively set to an even number according to the size of the chamber; through holes corresponding to the main force-bearing steel wire ropes 11 and the secondary force-bearing steel wire ropes 12 are provided on the concrete structure 10, and the rubber sleeves 43 are installed in the through holes; one main force-bearing steel wire rope 11 passes through one rubber sleeve 43; one secondary force-bearing steel wire rope 12 also passes through one rubber sleeve 43; two adjacent main force-bearing steel wire ropes 11 pass through the corresponding rubber sleeves 43 and are connected by the anchoring device 4; preferably, as Figure 1As shown, there are 10 main force-bearing steel wire ropes 11, so there will be 10 anchoring devices 4 used to connect the free ends of the main force-bearing steel wire ropes 11; the connection method of the secondary force-bearing steel wire ropes 12 is the same and will not be described in detail here.
[0045] In some possible implementations, the net 2 is a flame-retardant safety flat net with a diameter of 6 mm and a mesh size of 10 cm.
[0046] In some possible implementations, in order to reduce the shaking of the template 3 on the wire mesh 1 and reduce the probability of construction safety accidents;
[0047] The bottom of the template 3 is provided with locking slots corresponding to the length direction of the secondary force-bearing steel wire ropes 12 .
[0048] In some possible implementations, the thickness of the template 3 is 15 mm.
[0049] 15mm formwork is a common material on construction sites, which can rationally utilize resources to meet construction requirements and provide a flat working surface for operators.
[0050] In some possible implementations, the diameters of the primary stress-bearing steel wire rope 11 and the secondary stress-bearing steel wire rope 12 are 10 mm.
[0051] In summary, the present invention realizes the connection between the main force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12 and the concrete structure 10 through the anchor device 4, thereby avoiding the phenomenon that the main force-bearing steel wire rope 11 and the secondary force-bearing steel wire rope 12 are not firmly connected to the concrete structure 10 and fall off, thereby causing a construction safety accident.
[0052] The present invention effectively fixes the template 3 and the wire mesh 1 by setting a locking groove at the bottom of the template 3, and effectively prevents the template 3 from moving on the wire mesh 1 and affecting construction safety.
[0053] The present invention has a simple structure and strong practicality. Compared with setting up a ground scaffolding at the light well location for personnel operation, the convenient operation platform has the advantages of simple and fast installation and disassembly, saving labor, and not affecting the lower decoration construction. It is particularly suitable for installing steel structures when the lower floor height is large.
[0054] The present invention is not limited to the above-mentioned specific embodiments.
[0055] The present invention extends to any new features or any new combination disclosed in this specification, and any new method or process steps or any new combination disclosed.
Claims
1. A convenient operating platform for installing a steel structure skylight, installed in a cavity formed by a concrete structure; characterized in that: The invention comprises a plurality of main stress-bearing steel wire ropes, a plurality of secondary stress-bearing steel wire ropes staggeredly connected with the main stress-bearing steel wire ropes and forming a steel wire mesh, an anchoring device for connecting the free ends of two adjacent main stress-bearing steel wire ropes or the free ends of two adjacent secondary stress-bearing steel wire ropes, a template installed on the steel wire mesh, and a net installed on the side of the steel wire mesh away from the template; the anchoring device is located on the outside of the concrete structure; an intersection fixing device is provided at the connection between the main stress-bearing steel wire ropes and the secondary stress-bearing steel wire ropes; the intersection fixing device comprises a mounting plate, a U-shaped hoop installed on the mounting plate, and the end of the U-shaped hoop is screwed to the mounting plate; ... The mounting plate forms a locking cavity for mounting the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope; the free end of the main stress-bearing steel wire rope or the free ends of two adjacent secondary stress-bearing steel wire ropes penetrates the concrete structure; the anchoring device comprises a connecting rope clamp connected to two main stress-bearing steel wire ropes or secondary stress-bearing steel wire ropes respectively, a rope clamp B for locking each main stress-bearing steel wire rope or secondary stress-bearing steel wire rope after being folded in half and the number of the rope clamps B is at least two, and a plurality of rubber sleeves installed in the concrete structure and arranged one by one corresponding to the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope; the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope penetrate the corresponding rubber sleeves and are connected to the anchoring device; The net is a flame-retardant safety flat net with a diameter of 6 mm and a mesh size of 10 cm; The bottom of the template is provided with locking slots corresponding to the long direction of the secondary stress-bearing steel wire rope; the thickness of the template is 15mm; the diameters of the main stress-bearing steel wire rope and the secondary stress-bearing steel wire rope are 10mm.
Citation Information
Patent Citations
Operating platform for daylighting roof and construction method
CN108316633A
A horizontal operation platform for daylighting top application worker
CN208518306U
Steel wire rope soft platform for arched lighting roof construction
CN209468984U
Convenient operation platform for mounting steel structure daylighting roof
CN216109641U
Cage winding-up device for coverless car
JP2001233569A