Transmission mechanism and construction method for reducing damage to concrete foundation formwork
By designing a transmission device including bottom plate, cylinder, rotating shaft, roller and positioning plate, the problem of difficult and damage to formwork transmission in concrete foundation construction is solved, the stable transmission and fixation of formwork is achieved, and construction efficiency and operation convenience are improved. .
Patent Information
- Application Number
- CN202111008247.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-08-31
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2041-08-31
AI Technical Summary
In concrete foundation construction, too large gap between the ground and the foundation makes it difficult to transfer the steel formwork and is prone to damage or contamination.
A transmission device including bottom plate, cylinder, rotating shaft, roller, positioning plate, right angle plate and spring is designed. By adjusting the height of the cylinder and screw, combined with the design of roller and slide chute, the stable transmission and fixing of the template is achieved to avoid falling. and pollution.
The transmission process of templates is simplified, labor intensity is reduced, the risk of template damage is reduced, construction efficiency is improved, and operation is simpler and more convenient.
Smart Images

Figure CN113653323B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a transmission mechanism and a construction method of the mechanism, and in particular to a transmission mechanism construction method capable of reducing damage to a concrete foundation formwork. Background Art
[0002] In the construction of concrete foundation, the use of steel formwork is indispensable. During construction, there needs to be a certain distance between the ground and the foundation frame for pouring concrete; and before pouring, the foundation frame needs to be fixed with a steel formwork. At this time, the following defects will occur: ① Due to the distance between the ground and the foundation frame, when the workers are transferring the steel formwork, two workers are required to cooperate to move the formwork to the position of the foundation frame for fixing. In addition, the steel formwork itself has a certain weight. When the distance between the ground and the foundation frame is too large, it will be more difficult for the workers to transfer the formwork; ② During the transfer process, the formwork may be collided and deformed or the side coated with the release agent may be stained with mud or gravel. Summary of the invention
[0003] The problem to be solved by the present invention is to overcome the shortcomings of the prior art and provide a formwork transmission device for concrete foundation construction, which solves the problem that the formwork is difficult to transmit due to the large gap between the ground and the foundation frame, and avoids the formwork being damaged during transmission. The device is easy to use, simple to operate, and saves time and effort.
[0004] The technical solution adopted by the present invention to solve the technical problem is:
[0005] The top surface of the bottom plate is distributed in a slope shape, a cylinder is arranged at the bottom of the left end of the bottom plate, and a base is arranged at the bottom of the cylinder; the right end of the bottom plate is rotatably connected with a rotating shaft, and a right end support member is arranged at the bottom of the rotating shaft, at least one groove is arranged on the top surface of the bottom plate, and a roller is arranged in the groove; slide grooves are respectively arranged on the bottom plates on both sides of the groove, and a positioning plate is connected with a positioning plate above the groove through a sliding block, a positioning rod is arranged on the right end surface of the positioning plate, a right-angle plate is sleeved on the positioning rod, and the right-angle plate is slidably connected with the slide groove through the sliding block; a limiting block is arranged at the right end of the positioning rod, and a spring is sleeved on the positioning rod between the right-angle plate and the limiting block; a positioning ring is arranged at the front end of the bottom plate, the rope passes through the positioning ring and is fixed to the front end of the positioning plate, and a hand ring is arranged at the other end of the rope.
[0006] At least one second positioning hole is arranged on the left side of the positioning plate, and a second screw rod is threadedly connected in the second positioning hole.
[0007] At least four rollers are respectively arranged in each groove.
[0008] A first connecting block is provided at the left end of the base plate, and the push rod of the cylinder is hinged to the first connecting block; a through hole is dug on the base, and a bolt is welded at a position of the through hole corresponding to the ground, and the base is sleeved on the bolt and fixed by a nut.
[0009] There are two right-end support members, which are respectively located at the two ends of the rotating shaft, and each right-end support member is composed of a first positioning sleeve, a first screw, a third positioning sleeve and a chassis. The first positioning sleeve is fixedly connected to the rotating shaft, the first screw and the first positioning sleeve are connected together by threads, and the third positioning sleeve is connected to the bottom of the first screw by threads. A chassis is arranged at the bottom of the third positioning sleeve, and a first positioning hole is arranged on the chassis. The chassis is fixed to the concrete foundation frame by iron wire.
[0010] There are at least two first screws, and the upper and lower adjacent first screws are connected together by a second positioning sleeve. The second positioning sleeve is distributed in a state where both ends are connected, and a partition is provided at the middle position of the second positioning sleeve to evenly divide the interior of the second positioning sleeve into upper and lower parts; the upper part of the second positioning sleeve is connected to the upper first screw by a thread, and the lower part of the second positioning sleeve is connected to the lower first screw by a thread.
[0011] Second connecting blocks are respectively arranged on both sides of the right end of the bottom plate, and both ends of the rotating shaft are respectively rotatably connected to the second connecting blocks.
[0012] The construction method of the transmission mechanism for reducing damage to the concrete foundation formwork comprises the following steps:
[0013] A. Construction preparation:
[0014] ①. Determine the number of first screws according to the height of the base frame, and set bolts on the ground accordingly according to the position of the base;
[0015] ②. Dig through holes on the base at the positions corresponding to the bolts, put the base on the bolts, and fix the base to the ground by screwing matching nuts on the bolts;
[0016] ③. When the top of the base frame is lower than the ground, the first screw is connected to the bottom of the first positioning sleeve by threading, so that the bottom surface of the bottom plate is parallel and close to the bottom surface; when the top of the base frame is higher than the bottom surface, a first screw is arranged between the first positioning sleeve and the third positioning sleeve, and at the same time, the base sleeve is arranged in the middle or upper part of the bolt and fixed by the matching nut, and then the bottom of the bottom plate is parallel to the ground by adjusting the cylinder;
[0017] B. Fixing of template:
[0018] ①. Tie the rope to the positioning ring, make the positioning plate be located at the left end of the bottom plate, connect the second screw rod through the second positioning hole, and then tighten the rear end of the template against the right angle plate, so that the second screw rod is located outside the top end of the template;
[0019] C. Template transmission:
[0020] Loosen the rope, and the positioning plate moves along the roller on the top of the bottom plate to the right end of the base. The worker on one side of the base frame removes the template, and the worker on the other end holds the ring to pull the rope back to reset the positioning plate; then go through the steps in operation B to transmit the new template.
[0021] The positive beneficial effects of the present invention are:
[0022] The top surface of the base plate of the present invention is sloped. When in use, the steel template is placed on the positioning plate. The steel template can be moved to the position of the base frame by sliding the positioning plate and the right-angle plate along the top of the base plate, thereby solving the problem of difficulty in template transportation caused by the gap between the ground and the base frame. A spring is provided on the positioning rod behind the right-angle plate in conjunction with the use of a second screw rod to fix the steel template and prevent the steel template from falling during the sliding process.
[0023] The present invention has at least one first screw rod. When in use, the height of both ends of the base plate can be adjusted according to the position of the base frame and the ground. At the same time, the use of the cylinder can make the bottom of the base plate parallel to the bottom surface. At this time, the top surface of the base plate is distributed in a landslide shape, which is convenient for the sliding of the steel formwork.
[0024] The present invention fixes the chassis and the base frame together through steel wires, so that the right end of the bottom plate is fixed; at the same time, the base is sleeved on the bolts and the base is fixed to the ground through nuts, so as to ensure the overall stability of the bottom plate during use, and the structure is simple, practical and convenient.
[0025] The rope of the present invention passes through the positioning ring and is fixed to the front end of the positioning plate, and a hand ring is arranged at the other end of the rope. When in use, the positioning plate can be pulled back to the original point by pulling the rope, so that the steel template can be transferred again. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a structural schematic diagram of the present invention;
[0027] Figure 2 It is a structural schematic diagram of the front end of the base plate of the present invention. DETAILED DESCRIPTION
[0028] The present invention will be further explained and described below in conjunction with the accompanying drawings:
[0029] See also Figure 1-Figure 2A template transmission device for concrete foundation construction includes a bottom plate 1 and a rope 25. The top surface of the bottom plate 1 is distributed in a slope shape. A cylinder 7 is arranged at the bottom of the left end of the bottom plate 1, and a base 6 is arranged at the bottom of the cylinder 7; a rotating shaft 11 is rotatably connected to the right end of the bottom plate 1, and a right end support is arranged at the bottom of the rotating shaft 11. At least one groove 3 is arranged on the top surface of the bottom plate 1, and a roller 4 is arranged in the groove 3; slide grooves 2 are respectively arranged on the bottom plate 1 on both sides of the groove 3, and a positioning plate 19 (that is, a positioning plate 19) is connected to the top of the groove 3 through a slider. The positioning plate 19 is slidably connected to the groove 3 through a slider), a positioning rod 23 is arranged on the right end face of the positioning plate 19, a right-angle plate 22 is sleeved on the positioning rod 23, and the right-angle plate 22 is slidably connected to the slide groove 2 through the slider; a limiting block is arranged at the right end of the positioning rod 23, and a spring 24 is sleeved on the positioning rod 23 between the right-angle plate 22 and the limiting block; a positioning ring 18 is arranged at the front end of the base plate 1, a rope 25 passes through the positioning ring 18 and is fixed to the front end of the positioning plate 19, and a hand ring 26 is arranged at the other end of the rope.
[0030] At least one second positioning hole 20 is provided on the left side of the positioning plate 19 , and a second screw rod 21 is threadedly connected in the second positioning hole 20 .
[0031] At least four rollers 4 are respectively arranged in each groove 3, and the tops of the rollers 4 are respectively in contact with the bottom of the positioning plate 19 and the bottom of the right-angle plate 22; that is, the right-angle plate 22 and the positioning plate 19 can slide along the rollers on the top of the bottom plate.
[0032] A first connecting block 5 is provided at the left end of the base plate 1, and the push rod of the cylinder 7 is hinged to the first connecting block 5; a through hole is provided on the base 6, and a bolt 8 is welded at a position of the through hole corresponding to the ground, and the base 6 is sleeved on the bolt 8 and fixed by a nut 9.
[0033] There are two right-end support members, which are respectively located at the two ends of the rotating shaft 11, and each right-end support member is composed of a first positioning sleeve 12, a first screw 13, a third positioning sleeve 15 and a chassis 16. The first positioning sleeve 12 is fixedly connected to the rotating shaft 11, the first screw 13 is connected to the first positioning sleeve 12 through threads, the third positioning sleeve 15 is threadedly connected to the bottom of the first screw 13, a chassis 16 is arranged at the bottom of the third positioning sleeve 15, a first positioning hole 17 is arranged on the chassis 16, and the chassis 16 is fixed to the concrete foundation frame through wire.
[0034] There are at least two first screws 13, and the upper and lower adjacent first screws 13 are connected together by a second positioning sleeve 14. The second positioning sleeve 14 is distributed in a state where both ends are connected, and a partition 141 is provided at the middle position of the second positioning sleeve 14 to evenly divide the interior of the second positioning sleeve 14 into upper and lower parts; the upper part of the second positioning sleeve 14 is connected to the upper first screw 13 through a thread, and the lower part of the second positioning sleeve 14 is connected to the lower first screw 13 through a thread.
[0035] Second connection blocks 10 are respectively arranged on both sides of the right end of the bottom plate 1 , and both ends of the rotating shaft 11 are rotatably connected to the second connection blocks 10 .
[0036] The above-mentioned construction method of the transmission mechanism for reducing damage to the concrete foundation formwork comprises the following steps:
[0037] A. Construction preparation:
[0038] ①, according to the height of the basic frame, determine the number of the first screw rods 13, and according to the position of the base 6, set the bolts 8 on the ground accordingly;
[0039] ②. Dig a through hole on the base 6 at the position corresponding to the bolt 8, put the base 6 on the bolt 8, and fix the base 6 to the ground by screwing the matching nut 9 on the bolt 8;
[0040] ③. When the top of the base frame is lower than the ground, the first screw 13 is threadedly connected to the bottom of the first positioning sleeve 12 to make the bottom surface of the bottom plate 1 parallel and close to the bottom surface; when the top of the base frame is higher than the bottom surface, a first screw is arranged between the first positioning sleeve 12 and the third positioning sleeve 15, and at the same time, the base sleeve is arranged on the middle or upper part of the bolt 8 and fixed by the matching nut, and then the bottom of the bottom plate 1 is parallel to the ground by adjusting the cylinder 7;
[0041] B. Fixing of template:
[0042] ①, tie the rope 25 to the positioning ring 18, make the positioning plate 19 be located at the left end of the bottom plate 1, connect the second screw 21 in the second positioning hole 20 by threading, and then press the rear end of the template against the right angle plate 22, so that the second screw 21 is located outside the top end of the template;
[0043] C. Template transmission:
[0044] Loosen the rope 25, and the positioning plate moves along the roller on the top of the bottom plate to the right end of the base. The staff on one side of the base frame removes the template, and the staff on the other end holds the ring to pull the rope 25 back to reset the positioning plate; then the new template is transmitted through the steps in operation B.
[0045] In the above description, this mechanism is suitable for construction sites where the height difference between the top of the foundation frame and the ground (not the bottom of the foundation pit) is less than 1.
[0046] In the above description, the length of the rope is sufficient, the positioning plate 19 can be moved to the right end of the base plate 1, and the length of the bolt 8 is determined according to the actual construction height. When the top of the base frame is higher than the ground, the bolt 8 can be longer. When in use, the base sleeve is placed at the top and middle of the bolt 8.
[0047] In actual operation, before use, two bolts are fixed on the ground in advance, and then the base 6 is placed on the bolts and tightened and fixed by nuts.
[0048] When in use, when fixing the steel template, the second screw is threadedly connected in the second positioning hole, the upper end of the steel template is pressed against the second screw, and then the lower end of the steel template is pushed to the inner side of the right-angle plate 22. At this time, the steel template is clamped between the second screw and the right-angle plate; in actual operation, when the spring is in an uncompressed state, the rear end face of the positioning plate and the front end face of the right-angle plate are in a closed state. During use, the width of the template is greater than the distance between the second screw and the right-angle plate (in the closed state).
[0049] In actual operation, after the steel formwork is fixed, the rope is lowered to make the positioning plate and the right-angle plate slide down along the rollers on the top of the base plate. After the staff removes the formwork, the staff at the other end can pull the rope to pull the positioning plate back again.
[0050] The present invention not only solves the problem of inconvenient transmission of the template during use, but also solves the problem of the template being damaged during transmission, reduces the labor intensity of the staff, improves the construction efficiency, is easy to use, simple to operate, and easy to promote.
Claims
1. A conveying mechanism for reducing damage to a concrete foundation formwork, comprising a base plate (1) and a rope (25), It is characterized by: The top surface of the bottom plate (1) is distributed in a slope shape. A cylinder (7) is arranged at the bottom of the left end of the bottom plate (1), and a base (6) is arranged at the bottom of the cylinder (7). The right end of the bottom plate (1) is rotatably connected to a rotating shaft (11), and a right end support member is arranged at the bottom of the rotating shaft (11). At least one groove (3) is arranged on the top surface of the bottom plate (1), and a roller (4) is arranged in the groove (3). Slide grooves (2) are respectively arranged on the bottom plate (1) on both sides of the groove (3), and a positioning plate (19) is connected to the top of the groove (3) through a slider, and a positioning rod (23) is arranged on the right end surface of the positioning plate (19). ), a right-angle plate (22) is sleeved on the positioning rod (23), and the right-angle plate (22) is slidably connected to the slide groove (2) through a slider; a limit block is provided at the right end of the positioning rod (23), and a spring (24) is sleeved on the positioning rod (23) between the right-angle plate (22) and the limit block; a positioning ring (18) is provided at the front end of the bottom plate (1), the rope (25) passes through the positioning ring (18) and is fixed to the front end of the positioning plate (19), and a hand ring (26) is provided at the other end of the rope; at least one second positioning hole (20) is provided on the left side of the positioning plate (19), and at least one second positioning hole (20) is provided on the second positioning hole (20) A second screw rod (21) is connected to the hole (20) by a thread; at least four rollers (4) are arranged in each groove (3), and the tops of the rollers (4) are respectively in contact with the bottom of the positioning plate (19) and the bottom of the right-angle plate (22); a first connecting block (5) is arranged at the left end of the bottom plate (1), and the push rod of the cylinder (7) is hinged to the first connecting block (5); a through hole is dug on the base (6), and a bolt (8) is welded at a position of the through hole corresponding to the ground, and the base (6) is sleeved on the bolt (8) and fixed by a nut (9); the right end support members are two, which are respectively located at the rotating shaft (1 1), and each right end support member is respectively composed of a first positioning sleeve (12), a first screw rod (13), a third positioning sleeve (15) and a chassis (16); the first positioning sleeve (12) is fixedly connected to the rotating shaft (11); the first screw rod (13) and the first positioning sleeve (12) are connected together by threads; the third positioning sleeve (15) is connected to the bottom of the first screw rod (13) by threads; the chassis (16) is arranged at the bottom of the third positioning sleeve (15); a first positioning hole (17) is arranged on the chassis (16); and the chassis (16) is fixed to the concrete foundation frame by iron wire.
2. The conveying mechanism for reducing damage to the concrete foundation formwork according to claim 1, Features: There are at least two first screw rods (13), and the upper and lower adjacent first screw rods (13) are connected together via a second positioning sleeve (14); the second positioning sleeve (14) is arranged with both ends communicating with each other, and a partition plate (141) is provided at the middle position of the second positioning sleeve (14) to evenly divide the interior of the second positioning sleeve (14) into upper and lower parts; the upper part of the second positioning sleeve (14) is connected to the upper first screw rod (13) via a thread, and the lower part of the second positioning sleeve (14) is connected to the lower first screw rod (13) via a thread.
3. The conveying mechanism for reducing damage to the concrete foundation formwork according to claim 1, Features: Second connection blocks (10) are respectively arranged on both sides of the right end of the bottom plate (1), and both ends of the rotating shaft (11) are respectively rotatably connected to the second connection blocks (10).
4. A construction method for a conveying mechanism for reducing damage to a concrete foundation formwork according to any one of claims 1 to 3, It is characterized in that The steps include: A. Construction preparation: ①, according to the height of the base frame, determine the number of first screw rods (13), and according to the position of the base (6), set bolts (8) on the ground accordingly; ②, digging through holes at positions corresponding to the bolts (8) on the base (6), sleeve the base (6) on the bolts (8), and fix the base (6) to the ground by screwing matching nuts (9) on the bolts (8); ③. When the top of the base frame is lower than the ground, the first screw rod (13) is threadedly connected to the bottom of the first positioning sleeve (12) so that the bottom surface of the base plate (1) is parallel to and in close contact with the bottom surface; when the top of the base frame is higher than the bottom surface, a first screw rod is arranged between the first positioning sleeve (12) and the third positioning sleeve (15), and at the same time, the base (6) is sleeved on the middle or upper part of the bolt (8) and fixed by a matching nut, and then the bottom of the base plate (1) is parallel to the ground by adjusting the cylinder (7); B. Fixing of template: ①, tie the rope (25) to the positioning ring (18), make the positioning plate (19) be located at the left end of the bottom plate (1), connect the second screw rod (21) in the second positioning hole (20) by threading, and then press the rear end of the template against the right angle plate (22), so that the second screw rod (21) is located outside the top end of the template; C. Template transmission: The rope (25) is loosened, and the positioning plate is moved along the roller on the top of the bottom plate to the right end of the base. The staff on one side of the base frame removes the template, and the staff on the other end holds the ring and pulls the rope (25) back to achieve the reset operation of the positioning plate; and then the steps in operation B are followed to transfer the new template.
Citation Information
Patent Citations
Geothermal well pipe hoisting and transporting device
CN213445286U