Modular fully enclosed pier integrated construction platform and construction method thereof

Through the combination of modular fully enclosed pier-column integrated construction platform and tower crane lifting equipment, the existing technology problems of high pier column construction cost, poor safety and complexity are solved, and the standardization of low, medium and high pier columns is realized. Universal and intelligent construction improves construction efficiency and safety.

CN113737657BActive Publication Date: 2024-10-01CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111087968.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-09-16
Publication Date
2024-10-01
Estimated Expiration
2041-09-16

AI Technical Summary

Technical Problem

Existing bridge pier construction methods have shortcomings in terms of cost, safety and complexity. They lack standardized, universal and intelligent construction equipment and methods, making it difficult to achieve factory-based construction of low, medium and high piers.

Method used

A modular fully enclosed pier-column integrated construction platform is used, including standard sections of the construction platform, ceiling, lifting system, formwork lifting system and vibration device. Through modular assembly, the construction of piers and columns with different cross-section sizes is realized, and the tower crane and hoisting system are combined. Heavy equipment is used for segmental assembly and climbing to realize the construction of low, medium and high piers.

Benefits of technology

It achieves standardized, universal and intelligent pier construction, reduces construction costs and safety risks, improves construction efficiency and standardization, and is suitable for factory construction of different pier cross-section sizes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113737657B_ABST
    Figure CN113737657B_ABST
Patent Text Reader

Abstract

The present invention discloses a modular fully enclosed pier column integrated construction platform and a construction method thereof, comprising: a number of construction platform standard sections, a ceiling, a lifting system, a template lifting system and a vibrating device; a number of construction platform standard sections are arranged on the outside of the pier column to form a cylindrical enclosure structure, the ceiling is installed on the top surface of the uppermost construction platform standard section, the lifting system is installed on the inner side of the construction platform standard section, and is used for lifting and supporting the construction platform standard section; the template lifting system comprises a template, a template guide rail and a lifting device; the template guide rail is installed between the ceiling and the top surface of the uppermost construction platform standard section, and the lifting device can move horizontally along the template guide rail, and drive the template to complete the opening and closing of the mold by lowering the lifting rope. In terms of universality, the present invention can continuously add sections to the standard sections as a working platform for low piers as the construction progresses; for the construction of medium and high piers, a climbing system can be installed on the platform, and after one assembly, it climbs with the pier column until it reaches the top without falling to the ground.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and more specifically, to a modular fully enclosed pier-column integrated construction platform and a construction method thereof. Background Art

[0002] In the field of highway bridge construction, for low pier construction, there are mainly assembled scaffolding and flip formwork construction methods, etc., and for medium and high pier construction, there are mainly hanging racks and hydraulic climbing formwork methods. However, the above commonly used pier construction methods have simple process operations and low costs, but many lifting operations and high safety risks, such as flip formwork and hanging racks; or high construction efficiency and good safety performance, but high maintenance costs and complex procedures, such as hydraulic climbing formwork; or taking into account both cost and safety, but single function and insufficient standardization, such as assembled scaffolding. It is necessary to explore an idea for the industrialized construction of piers, develop a standardized, universal, and intelligent pier construction equipment and construction method, and realize the factory construction of low, medium and high piers. Summary of the invention

[0003] The purpose of the present invention is to overcome the shortcomings of the above technical background and provide a modular fully enclosed pier integrated construction platform and a construction method thereof.

[0004] In order to achieve these objects and other advantages according to the present invention, a modular fully enclosed pier-column integrated construction platform is provided, comprising: a number of construction platform standard sections, a ceiling, a lifting system, a template lifting system and a vibrating device;

[0005] Several construction platform standard sections are arranged on the outside of the pier to form a cylindrical enclosure structure, the ceiling is installed on the top surface of the uppermost construction platform standard section, and the lifting system is installed on the inner side of the construction platform standard section for lifting and supporting the construction platform standard section;

[0006] The template lifting system includes a template, a template guide rail and a lifting device; the template guide rail is installed between the ceiling and the top surface of the standard section of the uppermost construction platform, and the lifting device can move horizontally along the template guide rail, and drive the template to complete the opening and closing actions by lowering the lifting rope.

[0007] Preferably, the standard section of the construction platform is assembled from a number of frame bodies along the piers;

[0008] A certain gap should be left between the inner surface of the standard section of the construction platform and the outer surface of the pier column; the frame is a truss structure, including a number of vertical poles, horizontal poles, diagonal braces, scaffolding boards, flaps and protective nets;

[0009] The vertical poles, horizontal poles and diagonal braces form a standard section main frame; the scaffolding boards and flaps are laid at the bottom of the main frame for people to walk on; the protective net is installed on the periphery of the main frame;

[0010] Preferably, the lifting system comprises a lifting rail, a lifting device, an anti-falling device and a lifting mount;

[0011] The lifting bracket is installed on the wall attached to the pier column, the anti-falling device is fixed to the lifting bracket, and the lifting guide rail is vertically installed on the inner side of the standard section of the construction platform, so that the frame is guided by the lifting guide rail when it is lifted. After the frame is positioned, the lifting guide rail is supported on the anti-falling device to bear the deadweight of the frame;

[0012] The lifting device is connected between the frame and the pier column wall, and the lifting device drives the frame to lift.

[0013] Preferably, the template guide rail is a foldable structure.

[0014] Preferably, the vibrating device is installed between the ceiling and the top surface of the standard section of the uppermost construction platform, in the same plane as the template guide rail; the vibrating device includes a mechanical arm and a vibrating rod.

[0015] Preferably, a comb-shaped slot is detachably installed on the vertical pole on the inner side of the standard section of the construction platform to assist in the loose binding of the steel bars.

[0016] The present invention also provides a method for constructing a hollow low pier using the integrated construction platform, comprising the following steps:

[0017] A1 According to the cross-sectional dimensions of the pier, assemble the frames and then splice them into several standard sections of the construction platform. After the foundation is constructed, the standard sections of the construction platform are assembled section by section on the outside of the initial section of the pier by the lifting equipment. The initial installation height of the frame should be slightly higher than the first section of the pier. After the standard section is installed, install the ceiling;

[0018] A2 When carrying out steel bar component construction, the lifting equipment hoists the steel bar components to complete the steel bar component docking; when carrying out steel bar loose binding construction, the slots on the installed construction platform standard section are used to assist the steel bar loose binding position to complete the steel bar binding;

[0019] A3 formwork projects should be constructed by flipping the formwork. After the formwork is cleaned and coated with release agent, the formwork is hoisted by a crane.

[0020] A4 pouring pier concrete;

[0021] After A5 concrete reaches the demolding strength, the lower part of the inner and outer formwork is hoisted out by lifting equipment for cleaning and grinding, and the upper interface formwork of the inner and outer formwork is retained;

[0022] A6 installation inner bracket platform;

[0023] A7 The construction platform is added with lifting equipment, and the height of the added section should be the same as the height of each pouring of the pier column;

[0024] A8 Repeat steps 2 to 5 until the construction of this section of piers is completed;

[0025] A9 lifting equipment lifts the inner support to the next section:

[0026] A10 Repeat steps 7 to 8 until the construction of this section of piers is completed;

[0027] A11 Repeat steps 9 to 10 until all sections are completed

[0028] The A12 lifting equipment dismantles the construction platform section by section.

[0029] The present invention also provides a method for componentized construction of medium-high pier steel bars using the integrated construction platform, comprising the following steps:

[0030] B1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform is installed by the tower crane;

[0031] The B2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs the embedded parts;

[0032] B3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork. The bottom of the first section formwork is supported on the top surface of the pedestal. Pads can be set at the bottom of the formwork for leveling.

[0033] Concrete is poured in the first section of B4, and the internal and external formwork is removed after reaching the same strength;

[0034] B5 The lower two layers of the frame are installed with the lifting system, platform section, formwork lifting system and vibrating device together with the top section;

[0035] B6 hoisting steel bar parts;

[0036] B7 Install the inner bracket and inner and outer formwork, and pour the second section of pier column concrete after closing the mold. Vibration device assists in vibration. After reaching the same strength, the inner formwork is removed and the outer formwork is dismantled;

[0037] After the B8 frame is lifted, the lowest frame section and the bracket are installed in bulk, and the platform is fully assembled and then lifted to the third section construction position;

[0038] B9 hoisting the third section of pier column steel bars;

[0039] The B10 tower crane lifts the inner support to the construction position of the third section;

[0040] B11 Install the outer formwork, and pour concrete after the inner and outer formworks are closed. Vibration is assisted by a vibrating device. After reaching the same strength, the inner and outer formworks are removed from the formworks.

[0041] B12 hoist the next section of steel bar components;

[0042] B13 construction platform and inner bracket are lifted to the construction position of the next pier;

[0043] B14 Pour concrete after the inner and outer formworks are closed, vibrate with the aid of a vibrating device, and remove the inner and outer formworks after reaching the same strength;

[0044] B15 Repeat steps 12 to 14 until all sections are completed;

[0045] B16 dismantles the construction platform section by section;

[0046] The present invention also provides a method for loosely binding steel bars of a medium-high pier using the integrated construction platform, comprising the following steps:

[0047] C1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform is installed by the tower crane;

[0048] The C2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs embedded parts;

[0049] C3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork. The bottom of the first section formwork is supported on the top surface of the pedestal. Pads can be set at the bottom of the formwork for leveling.

[0050] The first section of C4 is poured with concrete, and the internal and external formwork is removed after reaching the same strength;

[0051] The C5 lower two-layer frame installation lifting system, platform section addition, formwork lifting system and vibrating device are installed together with the top section;

[0052] C6 uses the installed construction platform standard section and the slots on the inner bracket to assist in the loose binding of the steel bars and complete the steel bar binding;

[0053] C7 installs the inner bracket and inner and outer formwork, and pours the second section of pier column concrete after closing the mold. The vibrating device assists in vibrating. After reaching the same strength, the inner formwork is removed and the inner and outer formwork is removed;

[0054] After the C8 frame is raised, the lowest frame section and bracket are installed in bulk to complete the overall assembly of the platform.

[0055] The C9 construction platform and inner bracket are lifted to the construction position of the next pier;

[0056] C10 uses the installed construction platform standard section and the slots on the inner bracket to assist in the loose binding of the steel bars and complete the steel bar binding of this section;

[0057] C11 Install the inner and outer formwork, pour concrete after closing the formwork, use a vibrating device to assist in vibrating, and remove the inner and outer formwork after reaching the same strength;

[0058] C15 Repeat steps 12 to 14 until all sections are completed;

[0059] C16 dismantles the construction platform section by section.

[0060] Compared with the prior art, the modular fully enclosed pier integrated construction platform and the construction method thereof described in the present invention have the following advantages:

[0061] In terms of standardization, by adopting modular standard sections, the standard sections can be assembled in a modular manner and can also integrate functions such as formwork, maintenance, and lifting, so that the construction platform can take into account the construction of bottom, middle and high piers with different cross-sectional sizes.

[0062] In terms of universality, for low piers, standard sections can be continuously added as construction progresses to serve as working platforms; for the construction of medium and high piers, a climbing system can be installed on the platform, which can climb along with the pier column to the top without touching the ground after one assembly.

[0063] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 This is the elevation drawing of the high pier construction of the pier-column integrated construction platform;

[0065] Figure 2 It is the plan view of the low pier construction of the pier-column integrated construction platform;

[0066] Figure 3 It is the elevation drawing of the pier-column integrated construction platform;

[0067] Figure 4 This is the upper elevation of the pier-column integrated construction platform;

[0068] Figure 5 This is the elevation view of the lower part of the pier-column integrated construction platform;

[0069] Figure 6 It is a schematic diagram of the frame of the pier-column integrated construction platform;

[0070] Figure 7 This is a side view of the pier-column integrated construction platform;

[0071] Figure 8 It is the plan view of the pier-column integrated construction platform;

[0072] Fig. 9 It is the elevation drawing of the inner bracket;

[0073] Fig.10 This is the elevation drawing of the low pier construction of the pier-column integrated construction platform.

[0074] Explanation of the reference numerals: 1—integrated construction platform; 2—pier; 3—inner support; 4—vibrating device; 5—ceiling; 6—standard section of construction platform; 7—template lifting system; 8—external ladder cage; 9—lifting system; 10—hanging rack; 11—mechanical arm; 12—vibrating rod; 13—template guide rail; 14—lifting device; 15—external template; 16—lifting guide rail; 17—anti-fall device; 18—lifting bracket; 19—lifting device; 20—flap; 21—inner pole; 22—outer pole; 23—walkway board; 24—transition connection between standard sections of upper and lower platforms; 25—protective net; 26—inclined ladder; 27—inner template; 28—upper interface template of inner and outer templates. DETAILED DESCRIPTION

[0075] The present invention is described in detail and completely below in conjunction with the accompanying drawings. A person of ordinary skill in the art will be able to implement the present invention based on these descriptions. Before describing the present invention in conjunction with the accompanying drawings, it should be particularly pointed out that the technical solutions and technical features provided in each part of the present invention, including the following description, can be combined with each other without conflict.

[0076] In addition, the embodiments of the present invention involved in the following description are generally only a part of the embodiments of the present invention, rather than all the embodiments. Therefore, based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0077] The present invention is further described in detail below in conjunction with the accompanying drawings and implementations, and its specific implementation process is as follows:

[0078] Example 1

[0079] like Figures 1 to 5 , 7, and 8, a modular fully enclosed pier 2 integrated construction platform 1, comprising: a number of construction platform standard sections 6, a ceiling 5, a lifting system 9, a template lifting system 7, and a vibrating device 4;

[0080] A number of construction platform standard sections 6 are arranged outside the pier 2 to form a cylindrical enclosure structure. The ceiling 5 is installed on the top surface of the uppermost construction platform standard section 6. When materials need to be hoisted, the ceiling 5 is opened. The lifting system 9 is installed inside the construction platform standard section 6 to lift and support the construction platform standard section 6.

[0081] The template lifting system 7 includes a template, a template guide rail 13 and a lifting device 14; the template guide rail 13 is installed between the ceiling 5 and the top surface of the uppermost construction platform standard section 6, and the lifting device 14 can move horizontally along the template guide rail 13, and drive the template to complete the opening and closing actions by lowering the lifting rope.

[0082] In the above technical scheme, the integrated construction platform 1 integrates functions such as construction enclosure, steel bar binding, concrete pouring, maintenance, and decoration. It can be constructed by continuously adding sections to the standard sections 6 of the dry construction platform, or by installing devices such as a lifting system 9, and then climbing upward with the construction of the pier 2 until it reaches the top without touching the ground.

[0083] In the above technical solution, if Fig. 9 As shown, during the construction of the hollow pier, an inner support 3 platform is provided inside the hollow pier, including an inner support 3, an inner formwork 27 and an inclined ladder 26, which are used for inner cavity reinforcement binding, concrete pouring and decoration.

[0084] This technical solution may also include the following technical details to better achieve the technical effect: the construction platform standard section 6 is composed of a number of frame bodies assembled along the pier 2;

[0085] The height of the standard section 6 of the construction platform is preferably the height of a half section of the pier 2, but the height of the standard section of the construction platform is not limited to the heights listed in the embodiment. It is only necessary to make the height of the standard section of the construction platform and the height of the pier in a certain proportional relationship to facilitate the addition of sections. The inner surface of the standard section 6 of the construction platform should leave a certain gap with the outer surface of the pier 2; the standard sections of the construction platform 6 are connected by transitions 24 of the upper and lower platform standard sections, such as Figure 6 As shown, the frame is a truss structure, including a number of vertical poles, horizontal poles, diagonal braces, scaffolding boards, flaps and a protective net 25;

[0086] The vertical poles, horizontal poles and diagonal braces constitute a standard section main frame, and the vertical poles are divided into inner vertical poles 21 and outer vertical poles 22; the scaffolding boards and flaps are laid on the bottom of the main frame to form walkway boards 23 for people to walk on; the protective net 25 is installed on the periphery of the main frame; through the arrangement and combination of horizontal poles and diagonal braces of different lengths, the frame can adapt to piers 2 of different cross-sectional sizes.

[0087] The external ladder cage 8 is connected to the frame column to provide a passage for personnel to go up and down.

[0088] This technical solution may also include the following technical details to better achieve the technical effect: the lifting system 9 includes a lifting rail 16, a lifting device 19, an anti-falling device 17 and a lifting bracket 18;

[0089] The lifting bracket 18 is installed on the wall attached to the pier 2, the anti-falling device 17 is fixed to the lifting bracket 18, and the lifting guide rail 16 is vertically installed on the inner side of the standard section 6 of the construction platform, so that the frame is guided by the lifting guide rail 16 when it is lifted. After the frame is positioned, the lifting guide rail 16 is supported on the anti-falling device 17 to bear the dead weight of the frame;

[0090] The lifting device 19 is connected between the frame and the wall attached to the pier 2. The lifting device 19 drives the frame to lift through a pulley set or a walking structure. After the lifting is completed, the frame load is transferred to the lifting guide rail 16. The lifting guide rail 16 is supported by the anti-fall device 17 to bear the weight of the frame.

[0091] The lifting system 9 is a commonly used device in the construction field, and its specific structure is not described in detail.

[0092] The technical solution may also include the following technical details to better achieve the technical effect: the template guide rail 13 is a foldable structure and does not interfere with the construction of steel bars and concrete.

[0093] The present technical solution may also include the following technical details to better achieve the technical effect: the vibrating device 4 is installed between the ceiling 5 and the top surface of the standard section 6 of the uppermost construction platform, in the same plane as the formwork guide rail 13; the vibrating device 4 includes a mechanical arm 11 and a vibrating rod 12, and after the mechanical arm 11 is positioned in a plane, the vibrator is lowered for automatic vibration.

[0094] The technical solution may also include the following technical details to better achieve the technical effect: a comb-shaped slot is detachably installed on the vertical pole on the inner side of the standard section 6 of the construction platform to assist in the loose binding of the steel bars.

[0095] Example 2

[0096] like Fig.10 As shown, a method for constructing a hollow low pier using the integrated construction platform 1 includes the following steps:

[0097] A1 Assemble the frames according to the cross-sectional dimensions of the pier 2, and then splice them into several standard sections 6 of the construction platform. After the foundation is constructed, the standard sections 6 of the construction platform are assembled section by section on the outside of the initial section of the pier 2 by the lifting equipment. The initial installation height of the frame should be slightly higher than the first section of the pier 2. After the standard section is installed, the ceiling 5 is installed;

[0098] A2 When carrying out steel bar component construction, the lifting equipment hoists the steel bar components to complete the steel bar component docking; when carrying out steel bar loose binding construction, the slots on the installed construction platform standard section 6 are used to assist the steel bar loose binding position to complete the steel bar binding;

[0099] A3 formwork projects should be constructed by flipping the formwork. After the formwork is cleaned and coated with release agent, the formwork is hoisted by a crane.

[0100] A4 pouring pier concrete;

[0101] After A5 concrete reaches the demoulding strength, the inner formwork 27 and the lower part of the outer formwork 15 are hoisted out by the lifting equipment for cleaning and grinding, and the upper interface formwork 28 of the inner and outer formworks is retained;

[0102] A6 installation inner bracket 3 platform;

[0103] A7 lifting equipment is used to add sections to the construction platform. The height of the added section should be the same as the height of each pouring of pier 2;

[0104] A8 Repeat steps 2 to 5 until the construction of pier 2 in this section is completed;

[0105] A9 lifting equipment lifts inner support 3 to the next section:

[0106] A10 Repeat steps 7 to 8 until the construction of pier 2 in this section is completed;

[0107] A11 Repeat steps 9 to 10 until all sections are completed

[0108] The A12 lifting equipment dismantles the construction platform section by section.

[0109] The modular fully enclosed pier column 2 integrated construction platform 1 of the present invention reduces the internal support 3 and internal formwork 27 related processes when constructing a solid low pier compared to the hollow pier construction.

[0110] Example 3

[0111] The modular fully enclosed pier column 2 integrated construction platform 1 of the present invention is preferably provided with a transition connection between the upper and lower frames when used for the componentized construction of medium-high pier steel bars. The upper and lower frames are arranged in staggered layers, and a demoulding space is reserved for the upper frame. A method for the componentized construction of medium-high pier steel bars using the integrated construction platform 1 includes the following steps:

[0112] B1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform is installed by the tower crane (section 2 / 3 / 4 from bottom to top);

[0113] The B2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs the embedded parts;

[0114] B3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork. The bottom of the first section formwork is supported on the top surface of the pedestal. Pads can be set at the bottom of the formwork for leveling.

[0115] Concrete is poured in the first section of B4, and after reaching the same strength, the internal and external formwork is removed 15;

[0116] The lower two layers of B5 frame are installed with the lifting system 9, platform section (section 5 / 6), formwork lifting system 7 and vibrating device 4 together with the top section;

[0117] B6 hoisting steel bar parts;

[0118] B7 installs the inner support 3 and the inner and outer formwork 15, and after closing the mold, pours the concrete of the second section pier 2, and the vibrating device 4 assists in vibrating. After reaching the same strength, the inner mold is removed and the outer mold is dismantled;

[0119] After the B8 frame is lifted, the lower frame section and the bracket 10 are installed in bulk, and after the platform is assembled as a whole, it is lifted to the third section construction position;

[0120] B9 hoisting the third section pier 2 steel bar components;

[0121] B10 tower crane lifts inner support 3 to the third section construction position;

[0122] B11 installs the outer formwork 15, and after the inner and outer formworks 15 are closed, concrete is poured, and the vibrating device 4 assists in vibrating, and after the inner and outer formworks have reached the same strength, the concrete is removed;

[0123] B12 hoist the next section of steel bar components;

[0124] B13 construction platform and inner support 3 are lifted to the construction position of the next section of pier 2;

[0125] B14 After the inner and outer formwork 15 are closed, concrete is poured, and the vibrating device 4 assists in vibrating. After the inner and outer formworks have reached the same strength, they are demolded;

[0126] B15 Repeat steps 12 to 14 until all sections are completed;

[0127] B16 dismantles the construction platform section by section.

[0128] Example 4 The modular fully enclosed pier column 2 integrated construction platform 1 described in the present invention is used for the loose binding construction of medium-high pier steel bars. The construction platform is built with standard sections. Its process flow is similar to the process steps of the componentized construction of medium-high pier steel bars. The main difference is that the frame is lifted first, and then the steel bars are loosely bound. The steel bar binding and the template share a work station, and the template is repeatedly installed and disassembled to leave enough space for the steel bar loose binding. A method for the loose binding construction of medium-high pier steel bars using the integrated construction platform 1 includes the following steps:

[0129] C1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform (section 2 / 3 / 4 from bottom to top) is installed by the tower crane;

[0130] The C2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs embedded parts;

[0131] C3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork. The bottom of the first section formwork is supported on the top surface of the pedestal. Pads can be set at the bottom of the formwork for leveling.

[0132] The first section of C4 is poured with concrete, and after reaching the same strength, the internal and external formwork is removed 15;

[0133] The lower two layers of C5 frame are installed with the lifting system 9, platform section (section 5 / 6), formwork lifting system 7 and vibrating device 4 together with the top section;

[0134] C6 uses the installed construction platform standard section 6 and the slots on the inner bracket 3 to assist the steel bar loose binding position and complete the steel bar binding;

[0135] C7 installs the inner support 3 and the inner and outer formwork 15, and after closing the mold, pours the concrete of the second section pier 2, and the vibrating device 4 assists in vibrating. After the strength reaches the same level, the inner mold is removed, and the inner and outer formwork 15 is removed;

[0136] After the C8 frame is lifted, the lowermost frame section and the bracket 10 are assembled in bulk to complete the overall assembly of the platform.

[0137] C9 construction platform and inner support 3 are lifted to the construction position of the next section of pier 2;

[0138] C10 uses the installed construction platform standard section 6 and the slots on the inner bracket 3 to assist in the loose binding of the steel bars, completing the steel bar binding of this section;

[0139] C11 installs the inner and outer formwork 15, and pours concrete after closing the mold, and the vibrating device 4 assists in vibrating, and removes the inner and outer formwork 15 after reaching the same strength;

[0140] C15 Repeat steps 12 to 14 until all sections are completed;

[0141] C16 dismantles the construction platform section by section.

[0142] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the embodiments shown and described herein.

Claims

1. A modular fully enclosed pier integrated construction platform, characterized in that: include: Several construction platform standard sections, ceilings, lifting systems, formwork lifting systems and vibrating devices; Several construction platform standard sections are arranged on the outside of the pier to form a cylindrical enclosure structure, the ceiling is installed on the top surface of the uppermost construction platform standard section, and the lifting system is installed on the inner side of the construction platform standard section for lifting and supporting the construction platform standard section; The template lifting system includes a template, a template guide rail and a lifting device; the template guide rail is installed between the ceiling and the top surface of the standard section of the uppermost construction platform, and the lifting device can move horizontally along the template guide rail, and drive the template to complete the opening and closing of the mold by lowering the lifting rope; The vibrating device is installed between the ceiling and the top surface of the standard section of the uppermost construction platform, in the same plane as the template guide rail; the vibrating device includes a mechanical arm and a vibrating rod; The lifting system includes a lifting guide rail, a lifting device, an anti-falling device and a lifting bracket; The lifting bracket is installed on the wall attached to the pier column, the anti-falling device is fixed to the lifting bracket, and the lifting guide rail is vertically installed on the inner side of the standard section of the construction platform so that the frame is guided by the lifting guide rail when it is lifted; The lifting device is connected between the frame and the pier column wall, and the lifting device drives the frame to lift; The standard section of the construction platform is composed of several frame bodies assembled along the piers; A certain gap is left between the inner surface of the standard section of the construction platform and the outer surface of the pier column; the frame is a truss structure, including a number of vertical poles, horizontal poles, diagonal braces, scaffolding boards, flaps and protective nets; The vertical poles, horizontal poles and diagonal braces form a standard section main frame; the scaffolding boards and flaps are laid on the bottom of the main frame for people to walk on; the protective net is installed on the periphery of the main frame.

2. The modular fully enclosed pier integrated construction platform according to claim 1, characterized in that: The template guide rail is a foldable structure.

3. The modular fully enclosed pier integrated construction platform according to claim 1, characterized in that: The vertical poles on the inner side of the standard section of the construction platform are detachably provided with comb-shaped slots to assist in the loose binding of the steel bars.

4. A method for constructing a hollow low pier using the integrated construction platform according to claim 3, characterized in that: The following steps are involved: A1 According to the cross-sectional dimensions of the pier, assemble the frames and then splice them into several standard sections of the construction platform. After the foundation is constructed, the standard sections of the construction platform are assembled section by section on the outside of the initial section of the pier by the lifting equipment. The initial installation height of the frame is slightly higher than the first section of the pier. After the standard section is installed, the ceiling is installed; A2 When carrying out steel bar component construction, the lifting equipment hoists the steel bar components to complete the steel bar component docking; when carrying out steel bar loose binding construction, the comb-shaped clamping grooves on the installed standard section of the construction platform are used to assist the steel bar loose binding position to complete the steel bar binding; A3 formwork engineering adopts the method of flipping the formwork. After the formwork is cleaned and coated with release agent, the formwork is hoisted by crane. A4 pouring concrete for the pier body; After A5 concrete reaches the demolding strength, the lower part of the inner and outer formwork is hoisted out by lifting equipment for cleaning and grinding, and the upper interface formwork of the inner and outer formwork is retained; A 6 Install the inner bracket platform; A7 lifting equipment is used to add sections to the construction platform, and the height of the added section is the same as the height of each pouring of the pier column; A8 Repeat steps 2 to 5 until the construction of this section of piers is completed; A9 lifting equipment lifts the inner support to the next section: A10 Repeat steps 7 and 8 until the construction of this section of piers is completed; A11 Repeat steps 9 to 10 until all sections are completed; The A12 lifting equipment dismantles the construction platform section by section.

5. A method for componentizing steel bars of medium-high piers using the integrated construction platform described in any one of claims 1 to 3, characterized in that: The following steps are involved: B1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform is installed by the tower crane; The B2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs the embedded parts; B3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork, the bottom of the first section formwork is supported on the top surface of the pedestal, and a pad is set at the bottom of the formwork for leveling; Concrete is poured in the first section of B4, and the internal and external formwork is removed after reaching the same strength; B5 The lower two layers of the frame are installed with the lifting system, platform section, formwork lifting system and vibrating device together with the top section; B6 hoisting steel bar parts; B7 Install the inner bracket and inner and outer formwork, and pour the second section of pier column concrete after closing the mold. Vibration device assists in vibration. After reaching the same strength, the inner formwork is removed and the outer formwork is dismantled; After the B8 frame is lifted, the lowest frame section and the bracket are installed in bulk, and the platform is fully assembled and then lifted to the third section construction position; B9 hoisting the third section of pier column steel bars; The B10 tower crane lifts the inner support to the construction position of the third section; B11 Install the outer formwork, and pour concrete after the inner and outer formworks are closed. Vibration is assisted by a vibrating device. After reaching the same strength, the inner and outer formworks are removed from the formworks. B12 hoist the next section of steel bar components; B13 construction platform and inner bracket are lifted to the construction position of the next pier; B14 Pour concrete after the inner and outer formworks are closed, vibrate with the aid of a vibrating device, and remove the inner and outer formworks after reaching the same strength; B15 Repeat steps 12 to 14 until all sections are completed; B16 dismantles the construction platform section by section.

6. A method for loosely binding steel bars of medium-high piers using the integrated construction platform of claim 3, characterized in that: The following steps are involved: C1 After the platform frame is assembled in units on the open ground, the initial operation section of the platform is installed by the tower crane; The C2 tower crane hoists the first section of steel bars, manually ties the solid section steel bars, and installs embedded parts; C3 After cleaning the formwork and applying the release agent, the tower crane hoists the formwork, the bottom of the first section formwork is supported on the top surface of the pedestal, and a pad is set at the bottom of the formwork for leveling; The first section of C4 is poured with concrete, and the internal and external formwork is removed after reaching the same strength; The C5 lower two-layer frame installation lifting system, platform section addition, formwork lifting system and vibrating device are installed together with the top section; C6 uses the installed construction platform standard section and the comb-shaped slots on the inner bracket to assist in the loose binding of the steel bars and complete the steel bar binding; C7 installs the inner bracket and inner and outer formwork, and pours the second section of pier column concrete after closing the mold. The vibrating device assists in vibrating. After reaching the same strength, the inner formwork is removed and the inner and outer formwork is removed; After the C8 frame is lifted, the lowest frame and the bracket are assembled in bulk to complete the overall assembly of the platform; The C9 construction platform and inner bracket are lifted to the construction position of the next pier; C10 uses the installed construction platform standard section and the comb-shaped slots on the inner bracket to assist in the loose binding of the steel bars and complete the steel bar binding of this section; C11 Install the inner and outer formwork, pour concrete after closing the formwork, use a vibrating device to assist in vibrating, and remove the inner and outer formwork after reaching the same strength; C15 Repeat steps 12 to 14 until all sections are completed; C16 dismantles the construction platform section by section.